A case study on the success of introducing general non-construction activities for project management and planning improvement

Published: 12 June 2006 Publication History

Abstract

The creation of a proper work breakdown structure (WBS) is essential in performing successful project effort estimation and project management. The use of WBS is required on the level 1 of CMMI. There is, however, no standard WBS available. In this paper, the results of a pilot project in which new activities were introduced into the TietoEnator's WBS are reported. The activities were non-construction activities which are necessary but not directly related to the actual software construction. The study shows that the success of the introduction of such activities very much depends on the naming of the activities and how they are introduced to the employees. Additionally, it turned out that the pre-thought set of non-construction activities included activities that should not have been in the set at all as individual activities.

References

[1]
Wilson, D.N., Sifer, M.J.: Structured planning--project views. Software Engineering Journal 3 (1988) 134-140.
[2]
Wolverton, R.W.: The cost of developing large-scale software. IEEE Transactions on Computers 23 (1974) 615-636.
[3]
Boehm, B.: Software Engineering Economics. Prentice Hall (1981).
[4]
SEI: Capability maturity model integration (CMMI), version 1.1, staged representation. Technical Report CMU/SEI-2002-TE-029, ESC-TR-2002-029, CMU/SEI (2002).
[5]
Haapio, T.: The effects of non-construction activities on effort estimation. In: Proceedings of the 27th Information Systems Research in Scandinavia (IRIS'27). (2004) Available at http://w3.msi.vxu.se/users/per/IRIS27/iris27-1021.pdf.
[6]
MacDonell, S.G., Shepperd, M.J.: Using Prior-Phase Effort Records for Re-estimation During Software Projects, In: Proceedings of the Ninth International Software Metrics Symposium (METRICS'03), IEEE Computer Society (2003) 1-13.
[7]
Boehm, B., Horowitz, E., Madachy, R., Reifer, D., Clark, B., Steece, B., Brown, A., Chulani, S., Abts, C.: Software Cost Estimation with COCOMO II. Prentice Hall (2000).
[8]
Hale, J., Parrish, A., Dixon, B., Smith, R.K.: Enhancing the cocomo estimation models. IEEE Software 17 (2000) 45-49.
[9]
Blackburn, J.D., Scudder, G.D., Van Wassenhove, L.N.: Improving speed and productivity of software development: A global survey of software developers. IEEE Transactions on Software Engineering 22 (1996) 875-885.
[10]
Collier, B., DeMarco, T., Fearey, P.A.: Defined process for project post-mortem review. IEEE Software 13 (1996) 65-72.
[11]
Brady, S., DeMarco, T.: Management-aided software engineering. IEEE Software 11 (1994) 25-32.
[12]
Jalote, P.: CMM In Practice: Processes for Executing Software Projects at Infosys. Addison-Wesley, Reading, MA (2000).
[13]
Sommerville, I.: Software Engineering. 6th edn. Pearson Education, Harlow, UK (2001).
[14]
Zahran, S.: Software Process Improvement. Addison-Wesley, London (1998).
[15]
Lee, H.Y., Jung, H.W., Chung, C.S., Lee, J., Lee, K., Jeong, H.: Analysis of interrater agreement in iso/iec 15504-based software process assessment. In: APAQS '01: Proceedings of the Second Asia-Pacific Conference on Quality Software, Washington, DC, USA, IEEE Computer Society (2001) 341.
[16]
Damian, D., Zowghi, D., Vaidyanathasamy, L., Pal, Y.: An industrial experience in process improvement: An early assessment at the australian center for unisys software. In: Proceedings of the 2002 International Symposium on Empirical Software Engineering, ISESE'02, Washington, DC, USA, IEEE Computer Society (2002) 111-126.
[17]
Rautianen, K., Lassenius, C., Vähäniitty, J., Pyhäjärvi, M., Vanhanen, J.: A tentative framework for managing software product development in small companies. In: HICSS'02: Proceedings of the 35th Annual Hawaii International Conference on System Sciences (HICSS'02)-Volume 8, Washington, DC, USA, IEEE Computer Society (2002) 251.
[18]
McBride, T., Henderson-Sellers, B., Zowghi, D.: Project management capability levels: An empirical study. In: APSEC '04: Proceedings of the 11th Asia-Pacific Software Engineering Conference (APSEC'04), Washington, DC, USA, IEEE Computer Society (2004) 56-63.
[19]
Yoo, C., Yoon, J., Lee, B., Lee, C., Lee, J., Hyun, S., Wu, C.: An integrated model of ISO 9001: 2000 and CMMI for ISO registered organizations. In: APSEC '04: Proceedings of the 11th Asia-Pacific Software Engineering Conference (APSEC'04), Washington, DC, USA, IEEE Computer Society (2004) 150-157.
[20]
SEI: Capability maturity model integration (CMMI), version 1.1, continuous representation. Technical Report CMU/SEI-2002-TR-028, ESC-TR-2002-028, CMU/SEI (2002).
[21]
Järvinen, P.: On Research Methods. Opinpajan Kirja, Tampere, Finland (2001).
[22]
Iivari, J.: A paradigmatic analysis of contemporary schools of is development. European Journal of Information Systems 1 (1991) 249-272.
[23]
March, S.T., Smith, G.F.: Design and natural science research on information technology. Decision Support Systems 15 (1995) 251-266.
[24]
Hevner, A.R., March, S.T., Park, J., Ram, S.: Design science in information systems research. MIS Quarterly 28 (2004) 75-105.
[25]
Kitchenham, B., Pickard, L., Pfleeger, S.L.: Case studies for method and tool evaluation. IEEE Software 12 (1995) 52-62.
[26]
Fenton, N.E., Pfleeger, S.L.: Software Metrics: A Rigorous and Practical Approach. 2nd edn. PWS Publishing Company, Boston (1997).

Cited By

View all
  • (2010)Software engineering projects may fail before they are startedJournal of Systems and Software10.1016/j.jss.2010.06.02383:11(2175-2187)Online publication date: 1-Nov-2010
  • (2010)Vague project start makes project success of outsourced software development projects uncertainProceedings of the 11th international conference on Product-Focused Software Process Improvement10.1007/978-3-642-13792-1_27(351-365)Online publication date: 21-Jun-2010
  1. A case study on the success of introducing general non-construction activities for project management and planning improvement

      Recommendations

      Comments

      Please enable JavaScript to view thecomments powered by Disqus.

      Information & Contributors

      Information

      Published In

      cover image Guide Proceedings
      PROFES'06: Proceedings of the 7th international conference on Product-Focused Software Process Improvement
      June 2006
      473 pages
      ISBN:3540346821
      • Editors:
      • Jürgen Münch,
      • Matias Vierimaa

      Publisher

      Springer-Verlag

      Berlin, Heidelberg

      Publication History

      Published: 12 June 2006

      Qualifiers

      • Article

      Contributors

      Other Metrics

      Bibliometrics & Citations

      Bibliometrics

      Article Metrics

      • Downloads (Last 12 months)0
      • Downloads (Last 6 weeks)0
      Reflects downloads up to 20 Dec 2024

      Other Metrics

      Citations

      Cited By

      View all
      • (2010)Software engineering projects may fail before they are startedJournal of Systems and Software10.1016/j.jss.2010.06.02383:11(2175-2187)Online publication date: 1-Nov-2010
      • (2010)Vague project start makes project success of outsourced software development projects uncertainProceedings of the 11th international conference on Product-Focused Software Process Improvement10.1007/978-3-642-13792-1_27(351-365)Online publication date: 21-Jun-2010

      View Options

      View options

      Media

      Figures

      Other

      Tables

      Share

      Share

      Share this Publication link

      Share on social media