CN106997511A - Railway beam yard management system and railway beam yard management method based on BIM technology - Google Patents
Railway beam yard management system and railway beam yard management method based on BIM technology Download PDFInfo
- Publication number
- CN106997511A CN106997511A CN201710218010.6A CN201710218010A CN106997511A CN 106997511 A CN106997511 A CN 106997511A CN 201710218010 A CN201710218010 A CN 201710218010A CN 106997511 A CN106997511 A CN 106997511A
- Authority
- CN
- China
- Prior art keywords
- model
- information
- threedimensional model
- railway beam
- module
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 82
- 238000005516 engineering process Methods 0.000 title claims abstract description 24
- 238000004891 communication Methods 0.000 claims abstract description 25
- 238000000034 method Methods 0.000 claims description 42
- 238000010276 construction Methods 0.000 claims description 33
- 230000008569 process Effects 0.000 claims description 29
- 230000003111 delayed effect Effects 0.000 claims description 20
- 238000012407 engineering method Methods 0.000 claims description 9
- 238000004458 analytical method Methods 0.000 claims description 5
- 238000009430 construction management Methods 0.000 claims description 5
- 238000003908 quality control method Methods 0.000 claims description 4
- 230000005540 biological transmission Effects 0.000 abstract description 21
- 238000004519 manufacturing process Methods 0.000 description 12
- 238000012360 testing method Methods 0.000 description 6
- 238000013461 design Methods 0.000 description 5
- 241000196324 Embryophyta Species 0.000 description 3
- 238000007689 inspection Methods 0.000 description 3
- 239000000463 material Substances 0.000 description 3
- 238000012800 visualization Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 238000004364 calculation method Methods 0.000 description 2
- 230000008859 change Effects 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 2
- 238000001514 detection method Methods 0.000 description 2
- 230000003993 interaction Effects 0.000 description 2
- 238000010295 mobile communication Methods 0.000 description 2
- 238000004088 simulation Methods 0.000 description 2
- 230000003068 static effect Effects 0.000 description 2
- 230000000007 visual effect Effects 0.000 description 2
- 241000208340 Araliaceae Species 0.000 description 1
- 241001269238 Data Species 0.000 description 1
- PEDCQBHIVMGVHV-UHFFFAOYSA-N Glycerine Chemical compound OCC(O)CO PEDCQBHIVMGVHV-UHFFFAOYSA-N 0.000 description 1
- 235000005035 Panax pseudoginseng ssp. pseudoginseng Nutrition 0.000 description 1
- 235000003140 Panax quinquefolius Nutrition 0.000 description 1
- 230000004888 barrier function Effects 0.000 description 1
- 238000010835 comparative analysis Methods 0.000 description 1
- 238000013480 data collection Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 238000009472 formulation Methods 0.000 description 1
- 235000008434 ginseng Nutrition 0.000 description 1
- 230000008676 import Effects 0.000 description 1
- 230000002452 interceptive effect Effects 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000003032 molecular docking Methods 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000008520 organization Effects 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
- 238000002360 preparation method Methods 0.000 description 1
- 238000004886 process control Methods 0.000 description 1
- 230000000750 progressive effect Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 241000894007 species Species 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 230000002195 synergetic effect Effects 0.000 description 1
- 238000012876 topography Methods 0.000 description 1
- 238000012549 training Methods 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 238000002834 transmittance Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/067—Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06311—Scheduling, planning or task assignment for a person or group
- G06Q10/063116—Schedule adjustment for a person or group
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Strategic Management (AREA)
- General Physics & Mathematics (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Geometry (AREA)
- General Business, Economics & Management (AREA)
- Computer Hardware Design (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- General Health & Medical Sciences (AREA)
- Computational Mathematics (AREA)
- Architecture (AREA)
- Pure & Applied Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The application discloses a railway beam yard management system and a railway beam yard management method based on a BIM technology, wherein the railway beam yard management system establishes a three-dimensional model through a model establishment module, the three-dimensional model is updated in real time according to real-time information transmitted by a data communication module, and the data communication module can display the three-dimensional model in a mode of sending a request instruction to the model establishment module, so that the information transmission speed of the whole railway beam yard management system is greatly increased; in addition, the real-time information sent by the data communication module of the three-dimensional model of the railway beam yard management system can be directly transmitted to the model establishing module, so that transmission errors possibly caused by excessive transmission links of the real-time information are avoided, and the robustness of the railway beam yard management system is enhanced.
Description
Technical field
The application is related to beam administrative skill field, is managed more specifically to a kind of railway beam based on BIM technology
Reason system and railway beam management method.
Background technology
Precast beam, is to use prefabrication, then is transported to the beam that job site by design requirement position install fixation, is
Staple product during bridge construction.
Liang Chang is as the Workplace of precast beam, and the supervision and oversight of its production process is the weight of precast beam quality and duration
Ensure.The management for Liang Chang is also limited to the stage of " people's pipe people ", the transmission assigned with information of order in the prior art
By being carried out taking human as the management system of " node ", assigning for order is slower with the transmission speed of information;And entirely management is
The robustness of system is poor, it is easy to cause the biography of order or information due to the transmission mistake of some " node " in transmittance process
Mistake is passed, causes the information of whole management system inconsistent, quality and the duration of precast beam is influenceed.
Therefore, information transmission speed, and the more preferable management system of robustness can be lifted by needing one kind badly.
The content of the invention
In order to solve the above technical problems, the invention provides a kind of railway beam course management system and iron based on BIM technology
Road beam management method, provides that a kind of information transmission speed is very fast and the preferable railway beam course management system of robustness to realize
Purpose.
To realize above-mentioned technical purpose, the embodiments of the invention provide following technical scheme:
A kind of railway beam course management system based on BIM technology, including:Model building module and data communication module, its
In,
The model building module, for setting up threedimensional model according to arrangement of girder field information, and updates according to real time information
The threedimensional model, and for sending the threedimensional model to the data communication module after request instruction is received;
The data communication module, for sending the real time information to the model building module, and for described
Model building module sends request instruction, and receives the threedimensional model and shown.
Optionally, in addition to:
Database sharing module, for setting up standard element storehouse and technique according to beam component information and technique engineering method information
Engineering method storehouse, is called for the model building module;
The model building module is additionally operable to set up construction speed model simultaneously according to construction information and the technique engineering method storehouse
Shown in the threedimensional model, and Liang Chang is generated for recording beam field device use information, and according to the standard element storehouse
Device using information.
Optionally, the standard element storehouse includes product library and mechanical frock storehouse.
Optionally, the product library is used to store product model.
Optionally, the mechanical frock storehouse is used to store mechanical frock model.
Optionally, the model building module is additionally operable to analyze actual progress according to the threedimensional model, and judges described
Whether actual progress is consistent with target advance, if it is not, then judging process occur delayed, sends delayed warning information.
Optionally, the model building module analyzes actual progress according to the threedimensional model, and judges described actually to enter
Whether degree consistent with target advance, if it is not, then process occur delayed for judgement, send delayed warning information specifically for, according to
The threedimensional model analyzes actual progress, and judges whether the actual progress is consistent with program of standards development progress, if it is not, then sentencing
Make existing process delayed, send delayed warning information, and it is delayed according to the actual progress and the target advance analysis procedure
Reason.
A kind of railway beam management method, based on the railway beam course management system described in any of the above-described, the railway beam
Field management method includes:
Threedimensional model is set up using the railway beam course management system;
Progress control is carried out based on the three-dimension modeling construction plan, and based on the threedimensional model;
Work progress quality management is carried out based on the threedimensional model;
Quality control on construction management is carried out based on the threedimensional model.
It can be seen from the above technical proposal that the embodiments of the invention provide a kind of railway beam based on BIM technology pipe
Reason system and railway beam management method, wherein, the railway beam course management system sets up three by the model building module
Dimension module, the real time information real-time update that the threedimensional model is transmitted according to the data communication module, and the data are led to
Letter module can show the threedimensional model by way of sending request instruction to the model building module, considerably increase
The information transmission speed of whole railway beam course management system;In addition, the data of the threedimensional model of the railway beam course management system
The real time information that communication module is sent can be transferred directly to the model building module, it is to avoid the excessive transmission of real time information
Link and the transmission mistake being likely to result in, enhance the robustness of the railway beam course management system.
Brief description of the drawings
In order to illustrate more clearly about the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing
There is the accompanying drawing used required in technology description to be briefly described, it should be apparent that, drawings in the following description are only this
The embodiment of invention, for those of ordinary skill in the art, on the premise of not paying creative work, can also basis
The accompanying drawing of offer obtains other accompanying drawings.
A kind of structural representation for railway beam course management system that Fig. 1 provides for one embodiment of the application;
A kind of schematic flow sheet for railway beam management method that Fig. 2 provides for one embodiment of the application.
Embodiment
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete
Site preparation is described, it is clear that described embodiment is only a part of embodiment of the invention, rather than whole embodiments.It is based on
Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under the premise of creative work is not made
Embodiment, belongs to the scope of protection of the invention.
The embodiment of the present application provides a kind of railway beam course management system, as shown in figure 1, including:Model building module 200
With data communication module 100, wherein,
The model building module 200, for setting up threedimensional model according to arrangement of girder field information, and according to real time information more
The new threedimensional model, and for sending the threedimensional model to the data communication module 100 after request instruction is received;
The data communication module 100, for sending the real time information to the model building module 200 and request refers to
Make, and receive the threedimensional model and shown.
It should be noted that BIM (Building Information Modeling, BIM) technology or
Architecture information management (Building Information Management, BIM) technology is every phase with construction-engineering project
Based on the information data of pass, it is established that the technology of three-dimensional building model, had by digital information analogue simulation building
Real information.It has information completeness, information relevance, consistency on messaging, visualization, harmony, simulation, optimization property
With can go out the big feature of figure eight.
In this application, it can be set up by the model building module 200 according to arrangement of girder field information based on BIM technology
Threedimensional model, can be shown Liang Chang every terms of information based on the threedimensional model, the phase that for example precast beam construction is produced
Model data, qualitative data and work progress data etc. are closed, are easy to the unified management of box girder construction, promote the standard of box girder construction
Change and standardize, improve work progress management and quality management level.
The railway beam course management system sets up threedimensional model, the threedimensional model by the model building module 200
The real time information real-time update transmitted according to the data communication module 100, and the data communication module 100 can pass through
The mode for sending request instruction to the model building module 200 shows the threedimensional model, considerably increases whole railway beam
The information transmission speed of course management system;In addition, the data communication module 100 of the threedimensional model of the railway beam course management system
The real time information of transmission can be transferred directly to the model building module 200, it is to avoid the excessive transmission link of real time information
And the transmission mistake being likely to result in, enhance the robustness of the railway beam course management system.
It should also be noted that, in general the data communication module 100 includes multiple mobile communication equipments, the shifting
Dynamic communication equipment includes but is not limited to mobile phone, tablet personal computer and intelligent watch.Species of the application to the mobile communication equipment
Do not limit, specifically depending on actual conditions.
On the basis of above-described embodiment, in another embodiment of the application, the railway beam course management system is also
Including:
Database sharing module, for setting up standard element storehouse and technique according to beam component information and technique engineering method information
Engineering method storehouse, is called for the model building module 200;
The model building module 200 is additionally operable to set up construction speed model according to construction information and the technique engineering method storehouse
And shown in the threedimensional model, and generate beam for recording beam field device use information, and according to the standard element storehouse
Field device use information.
Specifically, the standard element storehouse includes product library and mechanical frock storehouse.
The product library is used to store product model.
The mechanical frock storehouse is used to store mechanical frock model.
The foundation of the product model needs to carry out in strict accordance with design drawing, commonly use property parameters include name of product,
Type, weight, volume, area and length etc.;Mechanical frock mode shape size is set up according to design drawing, and interior details are not made
Depth Study, thin portion modeling is carried out only for conventional consumable accessory, is managed in order to the updating maintenance of later stage plant equipment, is commonly used category
Property parameter include device name, type, power and numbering etc..
On the basis of above-described embodiment, in another embodiment of the application, the model building module 200 is also used
In analyzing actual progress according to the threedimensional model, and judge whether the actual progress is consistent with target advance, if it is not, then
It is delayed that process occurs in judgement, sends delayed warning information.
Specifically, in the preferred embodiment of the application, the model building module 200 is according to the threedimensional model
Actual progress is analyzed, and judges whether the actual progress is consistent with target advance, if it is not, then process occur delayed for judgement,
Send delayed warning information specifically for,
Actual progress is analyzed according to the threedimensional model, and judges whether the actual progress is consistent with target advance, such as
It is really no, then judge process occur delayed, send delayed warning information, and analyze according to the actual progress and the target advance
Process hysteresis reason.
It should be noted that in this application, realize that threedimensional model is practical, technological guidance based on the threedimensional model
Visualization, process management procedure and quality management are information-based, are specifically described below:
Threedimensional model is practical:
A. construction calculation volume
Construction calculation volume is as one of most basic application of BIM technology, while technical staff's workload is greatly reduced,
Improve the accuracy and efficiency of data statistics.For example in box beam concrete side's amount of this project is calculated, model export engineering
Amount differs only by 0.2% with layout design amount.
B. race storehouse is standardized
The related plant equipment storehouse of beam, frock storehouse, product library are established, with the constantly improve that race storehouse is built, by pole
The earth facilitates the BIM technology application of subsequent project.
C. field construction meter and place roaming
On the basis of standardization race storehouse, with reference to the ginseng such as beam task processed, duration arrangement, topography and geomorphology, Ground arrangement form
Number, quickly generates field and builds three-dimensional visualization model, and problem present in Ground arrangement is found in advance, reaches that reduction is done over again, saved
The purpose of cost.By the three-dimensional display interface of system, we can be with roaming on the spot in person, it is seen that Liang Chang really produces feelings
Condition, additionally it is possible to view personnel, the accurate physical location of machinery and relevant information.The model in interface is clicked on, can call and be
Data in system, view the real time information such as construction speed situation, engineering quantity.
D. resource management
In resources of production management aspect, the research that wireless location technology and BIM technology are combined, the personnel of realizing examine
Diligent, the programming count and record of machine operation;By the mounting of the production schedule and resource consumption, the automatic of handling of goods and materials is realized
Reduce and early warning, facilitate tissue and the allotment of produced on-site resource.
Technological guidance visualizes, and specifically includes:
A. collision detection
Collision detection is carried out using the threedimensional model, the component interference problem faced and built in work progress is accurately found that,
By local directed complete set, Deepen Design, can preferably guiding construction, the cost payout caused by doing over again is reduced to greatest extent.
B. job instruction
The 3D job instructions that BIM technology makes are used based on the threedimensional model, can freely be broadcast on an electronic device
Put, and can be fine displaying per pass technological process, because 3-D view image is understandable, greatly reduces the difficulty of receiving, carry
The high efficiency of training.
Process management procedure, is specifically included:
A. progress is pushed
In progress control, mobile phone mobile terminal of this Project-developing with system support realizes field data data
Push and receive in time, facilitate the upload of task to assign, improve process circulation efficiency.
B. schedule
In process of production, the overall manufacturing plan of year, season, the moon can be generated, monolithic can also be shown according to process
The schedule of beam, simultaneity factor can generate the planning of monolithic beam, actual contrast difference's figure, image and it is directly perceived.
C. progress analysis
When occur process it is delayed when, being capable of remarks the reason for go out delayed in system.By to a collection of beam plan and reality
Comparative analysis, system can also provide influence box beam manufacturing schedule master operation and influence the process progress main original
Cause, foundation is provided to improve organization of production.
D. progress display
Field Force scans Quick Response Code or manual import information by mobile terminal, remotely sends and instructs to system, realizes work
The quick transmission of sequence information, greatlys save process conversion time.
For example when a shifting beam process starts, beam information can be moved with remote visiting system by cell-phone customer terminal and box beam rises, eventually
Dot position information is to system, after system refreshes automatically, you can the virtual condition and position letter of box beam are seen in displaying interface
Breath, realizes and is virtually interconnected with real.
Quality management is information-based, specifically includes:
A. process management
The quality management of traditional construction mostly rely on paper document data, on the one hand, it cannot be guaranteed that the accuracy of data and
Promptness, on the other hand can not realize and share between system.In the present system, the tracking mode of BIM technology Life cycle is utilized
Management mode, from marching into the arena to inspection for former material, then to the links such as production whole process record, mounts with correlation model, realizes from source
Head arrives the whole process control of terminal.And the component relevant with the material, quality guarantee data can visual queries.Have simultaneously to part
There is the work equipment of access times and cycle on probation limitation, carry out shifting to an earlier date automatic early-warning, it is convenient to remind related personnel to wake up with a start operation, with
Traditional account mode compares, and production delay of being constructed caused by artificial information updating not in time greatly reduces.
B. data interaction
In order to timely and accurately reach data sharing, for the situation of not intercommunication between multiple systems, the system is preliminary
Realize and load automatically with beam body automatic Tensioning system, mixing station information system, static test in railway work management platform and be
System, the real-time, interactive of laboratory's information system, can capture the box beam that data assign reference numeral, click model can be direct
Check related data information, it is ensured that qualitative data it is authentic and valid.
C. synergetic office work
Traditional completion information is all to print storage by substantial amounts of document form, it has not been convenient to management and access, is
This, the system has also done the trial of BIM completion models, the quality guarantee data of original papery version is imparted into threedimensional model, and transfer to
System is managed as a whole.
By the three-dimensional display interface of system, we can be with roaming on the spot in person, it is seen that the real conditions of production of Liang Chang,
Personnel, the accurate physical location of machinery and relevant information can also be viewed.The model in interface is clicked on, can be with calling system
Data, view the real time information such as construction speed situation, engineering quantity.
In summary, the embodiment of the present application provides a kind of railway beam course management system, the railway beam course management system
Threedimensional model is set up by the model building module 200, the threedimensional model is transmitted according to the data communication module 100
Real time information real-time update, and the data communication module 100 can be by sending request to the model building module 200
The mode of instruction shows the threedimensional model, considerably increases the information transmission speed of whole railway beam course management system;In addition,
The real time information that the data communication module 100 of the threedimensional model of the railway beam course management system is sent can be transferred directly to institute
State model building module 200, it is to avoid the excessive transmission link of real time information and the transmission mistake that is likely to result in, enhance described
The robustness of railway beam course management system.
Accordingly, the embodiment of the present application additionally provides a kind of railway beam management method, as shown in Fig. 2 based on above-mentioned
Railway beam course management system described in one embodiment, the railway beam management method includes:
S101:Threedimensional model is set up using the railway beam course management system;
S102:Progress control is carried out based on the three-dimension modeling construction plan, and based on the threedimensional model;
Specifically, it is described to be based on the three-dimension modeling construction plan, and progress pipe is carried out based on the threedimensional model
Reason includes:According to construction characteristic and construction technology, the critical process to construction carries out detailed Task-decomposing and defined to construction
In progress template, by precast beam feature (title, figure number, model, curve element, sound barrier, secondary dead load, track plates type,
Earthquake motion peak value, classification) with the intelligent Matching of the aspect of model, realize that the online layout of construction plan, resource distribution and task are assigned;
By the pre- granting of construction plan in systems, the interaction collaboration work(between each operation, work post in construction plan formulation process is realized
Energy;Cooperateed with by the online updating of construction speed, warning function realization management with produced on-site, progress data direct drive three
Tie up the dynamic change of virtual scene, it is ensured that the promptness and validity of progress control, visual virtual scene displaying is significantly
The efficiency and quality linked up are improved, information is delivered important technology and production status is managed and feeds back to pipes at different levels in time
Reason department, and being adjusted to construction stage, task, time, resource etc., improve the accuracy of construction plan, operability and
Completion rate.All construction speed technology establishments and real-time statistics and early warning analysis, are grasped on threedimensional model
Make, it is ensured that the uniqueness and accuracy of data.
S103:Work progress quality management is carried out based on the threedimensional model;
Specifically, it is described to be included based on threedimensional model progress work progress quality management:Constructed with reference to precast beam
Critical process and task, the test data in each stage, inspection data, critical process data and task are associated, and defines
Key deliverable, determines the completion condition of task.The typing of qualitative data is completed by the multiple means such as mobile terminal and PC ends, and
The related quality document of automatic output, realizes the Classification Managements such as threedimensional model, test data, survey report;Implementation model, document
Online browse function;Threedimensional model, the quick-searching function of document are provided;Realize each operation threedimensional model, test data, inspection
Test reviewing for the qualitative datas such as data, critical process data;Associate the management of electronics builder's diary.
S104:Quality control on construction management is carried out based on the threedimensional model.
Specifically, it is described to be included based on threedimensional model progress quality control on construction management:For current railway engineering
In carry out extensively prestressing force intelligent tensioning system, Intelligent mud jacking system, Liang Chang is from dynamic and static load tests system and mixing plant, experiment
Room information system, by the exploitation and the docking of exchange data of interface, realizes that the automatic data collection of data and quality are automatic
Evaluate, and incidence relation is set up with corresponding model.
On the basis of above-described embodiment, in another embodiment of the application, the railway beam management method is also
Including:
Management platform and construction management control centre are set up, the communication exchange channel of administrative staff and operation team is set up,
Job instruction (including 3D job instruction) of the technical study achievements conversion for ease of operation, preferably guiding construction is given birth to
Production, and in implementation process checking, it is perfect.
In summary, the embodiment of the present application provides a kind of railway beam course management system and railway beam based on BIM technology
Field management method, wherein, the railway beam course management system sets up threedimensional model, the three-dimensional by the model building module
The real time information real-time update that model is transmitted according to the data communication module, and the data communication module can by
The mode that the model building module sends request instruction shows the threedimensional model, considerably increases whole railway beam management
The information transmission speed of system;In addition, the reality that the data communication module of the threedimensional model of the railway beam course management system is sent
When information can be transferred directly to the model building module, it is to avoid the excessive transmission link of real time information and be likely to result in
Mistake is transmitted, the robustness of the railway beam course management system is enhanced.
The embodiment of each in this specification is described by the way of progressive, and what each embodiment was stressed is and other
Between the difference of embodiment, each embodiment identical similar portion mutually referring to.
The foregoing description of the disclosed embodiments, enables professional and technical personnel in the field to realize or using the present invention.
A variety of modifications to these embodiments will be apparent for those skilled in the art, as defined herein
General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, it is of the invention
The embodiments shown herein is not intended to be limited to, and is to fit to and principles disclosed herein and features of novelty phase one
The most wide scope caused.
Claims (8)
1. a kind of railway beam course management system based on BIM technology, it is characterised in that including:Model building module and data are logical
Believe module, wherein,
The model building module, for setting up threedimensional model according to arrangement of girder field information, and according to updating real time information
Threedimensional model, and for sending the threedimensional model to the data communication module after request instruction is received;
The data communication module, for sending the real time information to the model building module, and for the model
Set up module and send request instruction, and receive the threedimensional model and shown.
2. system according to claim 1, it is characterised in that also include:
Database sharing module, for setting up standard element storehouse and technique engineering method according to beam component information and technique engineering method information
Storehouse, is called for the model building module;
The model building module is additionally operable to set up construction speed model and in institute according to construction information and the technique engineering method storehouse
State in threedimensional model and show, and beam field device is generated for recording beam field device use information, and according to the standard element storehouse
Use information.
3. system according to claim 2, it is characterised in that the standard element storehouse includes product library and mechanical frock
Storehouse.
4. system according to claim 3, it is characterised in that the product library is used to store product model.
5. system according to claim 3, it is characterised in that the mechanical frock storehouse is used to store mechanical frock model.
6. system according to claim 1, it is characterised in that the model building module is additionally operable to according to the three-dimensional mould
Type analysis actual progress, and judge whether the actual progress is consistent with target advance, if it is not, then judging process occur stagnant
Afterwards, delayed warning information is sent.
7. system according to claim 6, it is characterised in that the model building module is analyzed according to the threedimensional model
Actual progress, and judge whether the actual progress is consistent with target advance, if it is not, then judging process occur delayed, sends
Delayed warning information according to the threedimensional model specifically for analyzing actual progress, and judge the actual progress and standard meter
Whether the progress of drawing is consistent, if it is not, then judging process occur delayed, sends delayed warning information, and according to the actual progress
With the target advance analysis procedure hysteresis reason.
8. a kind of railway beam management method, it is characterised in that based on the railway beam management described in claim any one of 1-7
System, the railway beam management method includes:
Threedimensional model is set up using the railway beam course management system;
Progress control is carried out based on the three-dimension modeling construction plan, and based on the threedimensional model;
Work progress quality management is carried out based on the threedimensional model;
Quality control on construction management is carried out based on the threedimensional model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710218010.6A CN106997511A (en) | 2017-04-05 | 2017-04-05 | Railway beam yard management system and railway beam yard management method based on BIM technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710218010.6A CN106997511A (en) | 2017-04-05 | 2017-04-05 | Railway beam yard management system and railway beam yard management method based on BIM technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106997511A true CN106997511A (en) | 2017-08-01 |
Family
ID=59434776
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710218010.6A Pending CN106997511A (en) | 2017-04-05 | 2017-04-05 | Railway beam yard management system and railway beam yard management method based on BIM technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106997511A (en) |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107506907A (en) * | 2017-08-02 | 2017-12-22 | 中国十七冶集团有限公司 | Application of the mobile terminal based on BIM cloud platforms in construction quality inspection |
CN108898660A (en) * | 2018-05-31 | 2018-11-27 | 四川隧唐科技股份有限公司 | monitoring method and device |
CN109523182A (en) * | 2018-11-27 | 2019-03-26 | 华规软件(上海)有限公司 | A kind of beam field production management method, platform, computer equipment and storage medium |
CN109784693A (en) * | 2018-12-29 | 2019-05-21 | 陕西铁路工程职业技术学院 | A kind of Three-Dimensional Dynamic production management system for prefabricated components field |
CN110106800A (en) * | 2019-05-16 | 2019-08-09 | 北京鼎兴达信息科技股份有限公司 | High speed railway sound barrier health indicator administrative evaluation system and monitoring device |
CN110188997A (en) * | 2019-05-13 | 2019-08-30 | 赣州和永软件开发有限责任公司 | A kind of construction quality cruising resource content evaluation method and its system |
CN110197007A (en) * | 2019-05-09 | 2019-09-03 | 北新集团建材股份有限公司 | A method of automatically generating light steel keel gypsum board Wall model |
CN110363852A (en) * | 2019-07-15 | 2019-10-22 | 中铁四局集团有限公司 | Three-dimensional digital beam field, construction method, computer equipment and storage medium |
CN110414922A (en) * | 2019-06-28 | 2019-11-05 | 万翼科技有限公司 | A kind of construction data management method and device based on Building Information Model |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110658790A (en) * | 2019-09-17 | 2020-01-07 | 广州市微柏软件股份有限公司 | Precast beam production management system based on three-dimensional visual process management |
CN111210199A (en) * | 2020-01-03 | 2020-05-29 | 广西路桥工程集团有限公司 | Bridge prefab BIM information management system |
CN117371907A (en) * | 2023-09-26 | 2024-01-09 | 杭州市交通工程集团有限公司 | Precast beam field material supervision method and system based on Internet of things |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104567985A (en) * | 2015-01-28 | 2015-04-29 | 桥软科技(北京)有限公司 | Bridge information processing method and device |
CN104680320A (en) * | 2014-12-03 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM-based project management system and method |
CN105652830A (en) * | 2015-12-25 | 2016-06-08 | 中国铁道科学研究院铁道建筑研究所 | Bridge monitoring system based on BIM |
CN106339490A (en) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
-
2017
- 2017-04-05 CN CN201710218010.6A patent/CN106997511A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104680320A (en) * | 2014-12-03 | 2015-06-03 | 上海同筑信息科技有限公司 | BIM-based project management system and method |
CN104567985A (en) * | 2015-01-28 | 2015-04-29 | 桥软科技(北京)有限公司 | Bridge information processing method and device |
CN105652830A (en) * | 2015-12-25 | 2016-06-08 | 中国铁道科学研究院铁道建筑研究所 | Bridge monitoring system based on BIM |
CN106339490A (en) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
Cited By (18)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107506907A (en) * | 2017-08-02 | 2017-12-22 | 中国十七冶集团有限公司 | Application of the mobile terminal based on BIM cloud platforms in construction quality inspection |
CN108898660A (en) * | 2018-05-31 | 2018-11-27 | 四川隧唐科技股份有限公司 | monitoring method and device |
CN109523182A (en) * | 2018-11-27 | 2019-03-26 | 华规软件(上海)有限公司 | A kind of beam field production management method, platform, computer equipment and storage medium |
CN109784693B (en) * | 2018-12-29 | 2023-09-19 | 陕西铁路工程职业技术学院 | Three-dimensional dynamic production management system for prefabricated part field |
CN109784693A (en) * | 2018-12-29 | 2019-05-21 | 陕西铁路工程职业技术学院 | A kind of Three-Dimensional Dynamic production management system for prefabricated components field |
CN110197007A (en) * | 2019-05-09 | 2019-09-03 | 北新集团建材股份有限公司 | A method of automatically generating light steel keel gypsum board Wall model |
CN110188997A (en) * | 2019-05-13 | 2019-08-30 | 赣州和永软件开发有限责任公司 | A kind of construction quality cruising resource content evaluation method and its system |
CN110106800A (en) * | 2019-05-16 | 2019-08-09 | 北京鼎兴达信息科技股份有限公司 | High speed railway sound barrier health indicator administrative evaluation system and monitoring device |
CN110106800B (en) * | 2019-05-16 | 2023-09-19 | 北京鼎兴达信息科技股份有限公司 | High-speed railway sound barrier health index management evaluation system and monitoring device |
CN110414922A (en) * | 2019-06-28 | 2019-11-05 | 万翼科技有限公司 | A kind of construction data management method and device based on Building Information Model |
CN110363852B (en) * | 2019-07-15 | 2023-08-29 | 中铁四局集团有限公司 | Three-dimensional digital beam field, construction method, computer equipment and storage medium |
CN110363852A (en) * | 2019-07-15 | 2019-10-22 | 中铁四局集团有限公司 | Three-dimensional digital beam field, construction method, computer equipment and storage medium |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110443480B (en) * | 2019-07-26 | 2023-10-27 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110658790A (en) * | 2019-09-17 | 2020-01-07 | 广州市微柏软件股份有限公司 | Precast beam production management system based on three-dimensional visual process management |
CN111210199A (en) * | 2020-01-03 | 2020-05-29 | 广西路桥工程集团有限公司 | Bridge prefab BIM information management system |
CN117371907A (en) * | 2023-09-26 | 2024-01-09 | 杭州市交通工程集团有限公司 | Precast beam field material supervision method and system based on Internet of things |
CN117371907B (en) * | 2023-09-26 | 2024-06-11 | 杭州市交通工程集团有限公司 | Precast beam field material supervision method and system based on Internet of things |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106997511A (en) | Railway beam yard management system and railway beam yard management method based on BIM technology | |
CN106988221B (en) | Unit construction bridge beam construction method based on BIM | |
CN111369158A (en) | BIM-based informatization quality management method and system | |
CN109165394B (en) | Standardized BIM model lightweight realization method | |
CN111143915A (en) | Steel structure modular installation method based on Tekla software platform | |
CN107958101A (en) | A kind of assembled architecture Information Management System and method based on BIM | |
CN104866952B (en) | Three-dimensional digital management implementation method for hydropower station engineering project | |
CN105825335A (en) | BIM (Building Information Modeling) based construction onsite vehicle and device management system and method | |
CN109801038A (en) | A kind of versatility engineering construction method based on BIM technology application | |
CN107622355A (en) | Project cluster work progress digital management system and method | |
CN105549557A (en) | Real-time dynamic 3D water balance monitoring system of power plant and working method of system | |
Xu et al. | Integration of BIM and energy consumption modelling for manufacturing prefabricated components: a case study in China | |
CN107038259A (en) | A kind of operational method and its system for constructing traffic network data | |
CN109558412A (en) | The data growing method and device of assembled architecture construct platform | |
Wen | Research on the intelligent construction of prefabricated building and personnel training based on BIM5D | |
CN110263451A (en) | Arch rib processing construction method based on BIM | |
Barbosa et al. | Implementing lean construction effectively in a year in a construction project | |
CN109191577A (en) | A kind of distribution BIM collaborative platform | |
Bonenberg et al. | BIM in prefabrication and modular building | |
CN118071059A (en) | Intelligent beam field management platform based on BIM and GIS | |
CN107368972A (en) | It is a kind of that work platform and its application method are sent based on BIM technology | |
Cao et al. | A digital twin (DT) framework at design and construction phases | |
CN116561871A (en) | Deep construction method for mounting embedded part of bridge bearing platform | |
Barbosa et al. | Heijunka system to level telescopic forklift activities using tablets in construction site | |
CN112396296A (en) | Resource scheduling system based on BIM |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170801 |
|
RJ01 | Rejection of invention patent application after publication |