CN110443480A - Construction progress monitoring and early warning method and system - Google Patents

Construction progress monitoring and early warning method and system Download PDF

Info

Publication number
CN110443480A
CN110443480A CN201910682905.4A CN201910682905A CN110443480A CN 110443480 A CN110443480 A CN 110443480A CN 201910682905 A CN201910682905 A CN 201910682905A CN 110443480 A CN110443480 A CN 110443480A
Authority
CN
China
Prior art keywords
construction
time
spatial position
real
progress
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910682905.4A
Other languages
Chinese (zh)
Other versions
CN110443480B (en
Inventor
鲁旭东
沈凯程
胡柱奎
郑律君
伍德华
肖鹰
张明辉
梁彪
张波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
First Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
First Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, First Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201910682905.4A priority Critical patent/CN110443480B/en
Publication of CN110443480A publication Critical patent/CN110443480A/en
Application granted granted Critical
Publication of CN110443480B publication Critical patent/CN110443480B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • G06Q10/063116Schedule adjustment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a construction progress monitoring and early warning method and a system, comprising the following steps: acquiring the spatial position of a current construction section in a construction scene; determining the real-time construction progress corresponding to the current construction section according to the corresponding relation between the real-time space position and the construction progress; comparing the real-time spatial position with a preset planned spatial position, adjusting the construction progress when the real-time construction progress lags behind the target construction progress, sending the adjusted target construction plan to constructors, and sending advance early warning prompt information; by monitoring the real-time construction progress and timely notifying related personnel when the construction progress is delayed, the related personnel can reasonably adjust the construction plan and reasonably allocate construction resources; the defect that construction progress is not controlled due to the fact that construction adjustment cannot be accurately and effectively carried out in traditional construction is overcome.

Description

A kind of construction speed monitoring and early warning method and system
Technical field
The present invention relates to construction speed technical field more particularly to a kind of construction speed monitoring and early warning method and system.
Background technique
With the fast development of urban transportation, bridge engineering construction project in each stage there is a large amount of X factors and The attribute of dynamic change, which increase the complexity of bridge construction safety management and difficulty.Meanwhile science of bridge building in recent years is built If project is all towards the trend development of " higher, bigger, more complicated ", there are large-engineerings in construction process for this intermediate item The characteristics such as amount, complicated technology, information efficiency difference, this brings many potential danger factors to engineering construction, easily causes Safety accident.
Cradle structure, using extensively, during bridge construction, need to work out construction in bridge construction first Organization design, to be designed to entire construction period, speed, quality etc., construction schedule is the pass of Design of Construction Organization Key content is the foundation for controlling every construction activities such as engineering construction progress and engineering construction time limit, and whether schedule is reasonable, Directly affect speed of application, cost and quality.Therefore all work of Design of Construction Organization will be come centered on construction speed It arranges, if realtime construction progress lags target construction speed, in existing work progress, needs manually to be enucleated no at last Influence total construction period, and it also requires manually go adjustment Design of Construction Organization in personnel, the process duration, construction time kept in reserve Deng on the one hand increasing construction cost, on the other hand cannot be effectively adjusted in real time to current construction speed, thus in real time It is likely to influence total construction period without learning.
Summary of the invention
Technical problems based on background technology the invention proposes a kind of construction speed monitoring and early warning method and are System reasonably adjusts construction plan in order to related personnel and reasonably deploys working sources, in fact by monitoring realtime construction progress Now the control of construction speed is adjusted.
A kind of construction speed monitoring and early warning method proposed by the present invention, comprising:
Obtain the real-time spatial position for segment of currently constructing in construction scene;
According to the corresponding relationship of real-time spatial position and construction speed, determine the corresponding realtime construction in current construction segment into Degree;
Real-time spatial position is compared with pre-set plan spatial position;
When real-time spatial position lags plan spatial position, then realtime construction progress lags target construction speed, sends Progress early warning information.
It is further, described to be compared realtime construction progress with pre-set target construction speed, comprising:
Construction segment is divided into multiple planned times and multiple plan spatial positions, planned time and plan space bit in advance Set one-to-one correspondence;
Be intended to the time it is corresponding with real-time time be overlapped, compare real-time spatial position whether lag plan spatial position, institute Stating real-time time is real-time time corresponding when obtaining real-time spatial position;
It is obtained when real-time spatial position lags plan spatial position according to the corresponding relationship of spatial position and construction speed Realtime construction progress lags target construction speed.
Further, when the realtime construction progress lag target construction speed, comprising:
Judge other construction segments after currently construction segment with the presence or absence of the first free time;
If so, send the first progress early warning information, and according to first free time, the realtime construction into Degree and target construction speed adjust target construction plan;
If it is not, then sending the second progress early warning information, and other construction segments after the current construction segment of compression The working procedure time, obtain it is other construction segments the second free time, and according to the second free time, realtime construction progress with And target construction speed adjusts target construction plan.
Further, described according to first free time, institute after sending the first progress early warning information State realtime construction progress and target construction speed adjustment target construction plan before, comprising:
The duration of the first free time is obtained, and judges whether realtime construction progress lag duration is less than or equal to first freely The duration of time;
If so, adjusting target according to first free time, the realtime construction progress and target construction speed Construction plan;
If it is not, then sending the second progress early warning information, and other construction segments after the current construction segment of compression The working procedure time, obtain it is other construction segments the second free time, according to first free time, second it is free when Between, realtime construction progress and target construction speed adjust target construction plan, first free time and second it is free when Between the sum of be more than or equal to realtime construction progress lag duration.
Further, target construction is being adjusted according to the second free time, realtime construction progress and target construction speed Before plan, comprising:
Judge whether the second free time was greater than or equal to realtime construction progress lag duration;
If so, adjusting target construction plan according to the second free time, realtime construction progress and target construction speed;
If it is not, then sending third progress early warning information.
A kind of construction speed monitoring early-warning system, including obtain module, respective modules, comparison module and warning module;
Module is obtained for obtaining the real-time spatial position for segment of currently constructing in construction scene;
Respective modules are used for the corresponding relationship according to real-time spatial position and construction speed, determine that current construction segment is corresponding Realtime construction progress;
Comparison module is for real-time spatial position to be compared with pre-set plan spatial position, when real-time space When position lag plan spatial position, into warning module;
Warning module is for sending progress early warning information.
Further, comparison module includes division module, is overlapped respective modules and lag judgment module;
Division module divides multiple planned times and multiple plan spatial positions, planned time for the segment that will construct in advance It is corresponded with plan spatial position, into coincidence respective modules;
Respective modules are overlapped for being intended to time coincidence corresponding with real-time time, compare whether real-time spatial position lags Plan spatial position, the real-time time is real-time time corresponding when obtaining real-time spatial position, judges mould into lag Block;
Judgment module is lagged to be used for when real-time spatial position lag plan spatial position, according to spatial position and construction speed Corresponding relationship, obtain realtime construction progress lag target construction speed, and enter warning module.
A kind of computer-readable storage media is stored with several acquisitions classification journeys on the computer readable storage medium Sequence, several acquisition sort programs by processor for being called and executing following steps:
Obtain the real-time spatial position for segment of currently constructing in construction scene;
According to the corresponding relationship of real-time spatial position and construction speed, determine the corresponding realtime construction in current construction segment into Degree;
Real-time spatial position is compared with pre-set plan spatial position;
When real-time spatial position lags plan spatial position, then realtime construction progress lags target construction speed, sends Progress early warning information.
A kind of the advantages of construction speed monitoring and early warning method and system provided by the invention, is: providing in structure of the invention A kind of construction speed monitoring and early warning method and system, by monitor realtime construction progress, and construction speed lag when it is timely It notifies related personnel, reasonably adjust construction plan in order to related personnel and reasonably deploys working sources;Additionally it is possible to logical When the construction time obtained second of working procedure in other subsequent construction segments of the first free time or compression is free Between, the realtime construction progress currently lagged is adjusted, so that entire construction speed is in the range of target construction speed, Construction plan adjusted is sent to related personnel simultaneously, in order to which related personnel understands newest construction plan in time;And And when not still being able to satisfy actual construction demand by the first free time and the second free time mode, phase is notified in time Pass personnel reasonably adjust construction plan in order to related personnel and reasonably deploy working sources, realize the conjunction of working sources Reason allotment, can either guarantee the construction period, and can control construction cost;Additionally it is possible to for authorization query construction content Personnel inquire required construction content anywhere or anytime, in order to understand in real time all projects in construction construction safety situation and Construction speed situation;In addition, current construction speed can be immediately arrived at by the first, second, third progress early warning information Adjustment situation, related personnel can be according to the early warning information, the preparation being adjusted in advance, to avoid because adjustment Preparation and the defect for influencing total construction period.
Detailed description of the invention
Fig. 1 is a kind of step flow chart of construction speed monitoring and early warning method of the present invention;
Fig. 2 is a kind of flow chart of construction speed monitoring early-warning system of the present invention;
Wherein, 1- obtains module, 2- respective modules, 3- comparison module, 4- warning module, 31- division module, 32- coincidence Respective modules, 33- lag judgment module.
Specific embodiment
In the following, technical solution of the present invention is described in detail by specific embodiment, illustrate in the following description Many details are to fully understand the present invention.But the present invention can be to be much different from its other party described herein Formula is implemented, and those skilled in the art can make similar improvements without departing from the spirit of the invention, therefore the present invention is not It is limited by following public specific implementation.
It should be noted that be referred to as " being fixed on " another element when element, it can directly on another element or There may also be elements placed in the middle.When an element is considered as " connection " another element, it can be directly to another Element or there may be centering elements.Term as used herein "vertical", "horizontal", "left" and "right" and similar Statement be merely for purposes of illustration, be not meant to be the only embodiment.Herein in the used in the description of invention Term be only for the purpose of describing specific embodiments and be not intended to limit the present invention.
Referring to Fig.1, a kind of construction speed monitoring and early warning method proposed by the present invention, comprising:
S1: the spatial position for segment of currently constructing in construction scene is obtained;
Can by Beidou/GPS positioning sensor differential position or the construction segment image of acquisition, in real time or The periodically spatial position of the current construction segment of positioning can also position current construction segment according to the operational requirements of operator Spatial position.
The target factor after current construction segment in construction period can be obtained in advance while obtaining spatial position Corresponding parameter;
Influence specific gravity according to the corresponding parameter of target factor to construction speed analyzes the group of different factors in target factor The influence degree to the construction speed of bridge engineering construction project is closed, it is every in later to adjust current construction segment according to influence degree The construction time of road working procedure.
S2: according to the corresponding relationship of real-time spatial position and construction speed, determination is currently constructed, and segment is corresponding to apply in real time Work progress;
Spatial position is preset with construction speed, is to be carried out in construction project to meet certain construction speed Construction arranges.
S3: real-time spatial position is compared with pre-set plan spatial position, when realtime construction progress lags Target construction speed, enters step S4, when the advanced target construction speed of realtime construction progress, enters step S5;
S4: being adjusted construction speed, sends target construction plan adjusted to construction personnel, concurrently feeding degree is pre- Alert prompt information;
S5: to construction speed without adjustment, the advanced prompt information of progress is sent;
Can to and the corresponding construction project time management personnel of construction project and/or it is corresponding with current construction segment construct into It spends administrative staff and sends construction lag/advanced prompt information, so that the above related personnel can know current construction segment in real time Construction speed information.
It can show whether the construction speed of current cradle structure deviates mesh in real time by the real-time status data got Construction speed is marked, is on the one hand conducive to choose suitable cradle structure in other bridge engineering construction project construction processes, reach Optimize the purpose of cradle structure design, on the other hand, other construction segments after current construction segment can be adjusted in real time Progress, so that integral construction progress is within the limits prescribed, that is to say, that the practice of construction period constructs less than or equal to target Period.
It is described to be compared real-time spatial position with pre-set plan spatial position in step S3, comprising:
S31: construction segment is divided into multiple planned times and multiple plan spatial positions in advance, planned time and plan are empty Between position correspond;
By temporally divided accordingly with space to construction segment, so that any section in construction segment Point, it is consistent in the corresponding construction location of planned time construction location corresponding with plan spatial position, therefore pass through planned time Corresponding node node corresponding with by accordingly planning spatial position is consistent.
S32: be intended to the time it is corresponding with real-time time be overlapped, compare real-time spatial position whether lag plan space bit It sets, the real-time time is real-time time corresponding when obtaining real-time spatial position;
When obtaining real-time spatial position, corresponding system time, will as the corresponding real-time time of real-time spatial position After real-time time is corresponding with planned time numerical value, the relationship of real-time spatial position and lag plan spatial position can be directly obtained, Realtime construction progress is corresponded to according to real-time spatial position, plan spatial position corresponds to target construction speed, thus obtains and apply in real time The relationship of work progress and target construction speed.
As an embodiment, as shown in table 1:
Table 1
Real-time spatial position (the X that 2018/5/15 is obtained1, Y1, Z1) and preset plan spatial position (X0, Y0, Z0) It compares, offset relation of the available real-time spatial position relative to plan spatial position is said when deviation is more than or equal to zero Bright real space position is after planning spatial position, that is to say, that the project amount actually accomplished is greater than the engineering that plan is completed Amount, shows the advanced target construction speed of realtime construction progress;When deviation is less than zero, illustrate that real space position is empty in plan Between before position, that is to say, that the project amount actually accomplished is less than the project amount that plan is completed, and shows that realtime construction progress lags Target construction speed needs to adjust accordingly construction speed, so that high speed continuous beam engineering can complete on schedule.
S33: when real-time spatial position lags plan spatial position, according to the corresponding relationship of spatial position and construction speed, Obtain realtime construction progress lag target construction speed.
By step S31 to S33, obtain whether current construction speed lags target construction speed, to applying in real time for lag Work progress carries out early warning, realizes in real time to the monitoring of construction speed.
In step S4, when the realtime construction progress lags target construction speed, if not adjusting other construction segments Progress, then will affect integral construction progress, it is therefore desirable to the progresses of other construction segments after current construction segment into Row adjustment, comprising:
S41: judging that other construction segments after currently construction segment whether there is for the first free time, if so, S42 is entered step, if it is not, then entering step S43;
Using segment of currently constructing as start node, the terminal of construction speed is end node, judges start node to terminating In the time of node, if there are total time difference, and total time difference is time kept in reserve under the premise of not influencing total construction period, by the machine The time is moved as the first free time.
S42: the first progress early warning information is sent, and according to first free time, the realtime construction progress And target construction speed adjusts target construction plan;
The first progress early warning information is sent, is to prompt the realtime construction progress of currently construction segment to lag behind and work as The target construction speed of preceding construction segment, with the preparation for reminding related personnel to be adjusted construction speed.Wherein, the first progress Early warning may include real-time spatial position and/or realtime construction progress.
S43: sending the second progress early warning information, and compresses the construction of other construction segments after current construction segment Activity time obtains the second free time of other construction segments, and according to the second free time, realtime construction progress and mesh It marks construction speed and adjusts target construction plan.
Exist centainly between the earliest finish time of a upper working procedure and the late start time of next working procedure Free float, compresses the corresponding free float of multiple processes available second free time, the construction of adjustable lag into Degree, to realize monitoring and adjustment to construction speed.Above first free time and the second free time are in current construction section The redundancy time or free time of other construction segments after section, be in the case where not having to influence total construction period, can be with The time of compression.
Construction speed is adjusted by first free time of the step S41 into S43 and/or the second free time, Construction plan is reasonably adjusted in order to construction project time management personnel and reasonably deploys working sources, and then is reduced because of segment of constructing The case where working sources waste or construction speed are delayed caused by appearance construction speed is too fast or too slow is realized practical Construction speed is less than or equal to target construction speed.
In step S42, after sending the first progress early warning information, according to first free time, described Before realtime construction progress and target construction speed adjustment target construction plan, comprising:
S421: obtaining the duration of the first free time, and judges whether realtime construction progress lag duration is less than or equal to the The duration of one free time, if so, S422 is entered step, if it is not, then entering step S423;
S422: target is adjusted according to first free time, the realtime construction progress and target construction speed and is applied Work plan;
Duration is selected to be more than or equal to the period of the lag duration in the duration of the first free time, and by the period It increases in the working procedure time of current construction segment, to realize the adjustment to realtime construction progress, so that realtime construction Progress is equal to target construction speed.
S423: the second progress early warning information, and other construction segments after the current construction segment of compression are then sent The working procedure time, obtain it is other construction segments the second free time, according to first free time, second it is free when Between, realtime construction progress and target construction speed adjust target construction plan, first free time and second it is free when Between the sum of be more than or equal to realtime construction progress lag duration.
The duration of first free time is first increased in the working procedure time of current construction segment, is obtained remaining stagnant Duration afterwards, target construction segment (the construction segment of compressible working procedure time) for then successively including to other construction segments The working procedure time compressed, be more than or equal to remaining lag duration until compressing the obtained duration of the second free time When, the second free time was increased in the working procedure time of current construction segment, to realize the tune to realtime construction progress It is whole, so that realtime construction progress is equal to target construction speed.But when first free time and the second free time it When with being less than realtime construction progress lag duration, then third progress early warning information is sent, at this time the first free time and the The sum of two free times are not able to satisfy the adjustment requirement of realtime construction progress lag duration, therefore send third progress early warning Information;It notifies related personnel to be unable to complete target construction speed in current Design of Construction Organization in time, needs relevant people Member reasonably adjusts construction plan and deploys working sources reasonably to complete target construction speed, for example, can be applied by increasing The measures such as worker person, construction time, construction equipment, with rational allocation working sources.
It is applied for target is adjusted according to the second free time, realtime construction progress and target construction speed in step S43 Before work plan, comprising:
S431: judge whether the second free time was greater than or equal to realtime construction progress lag duration;
If so, entering step S432;
If it is not, then entering step S433;
S432: target construction plan is adjusted according to the second free time, realtime construction progress and target construction speed;
It can be by successively compressing working procedure time of other construction segments after current construction segment, until compressing The duration of the second free time arrived is equal to realtime construction progress and lags duration;Or successively after the current construction segment of compression its The working procedure time of its construction segment, until second certainly when the working procedure time of all other construction segment is compressed Realtime construction progress is greater than or equal to by the duration of time and lags duration.It should be understood that compressing applying for other construction segments above When work activity time, successively by construction segment compression by way of compressed, and obtain in real time the second free time when It is long, when the adjustable current lag time of the duration of the second free time, stop compression, passed through for the second free time to realize To adjust the requirement of construction speed.
S433: third progress early warning information is sent.
Since the second free time was no longer satisfied normal adjustment realtime construction progress lag duration, third is sent Progress early warning information;In time notify related personnel be unable to complete in current Design of Construction Organization target construct into Degree needs related personnel to reasonably adjust construction plan and reasonably deploys working sources to complete target construction speed, for example, can Increase the measures such as construction personnel, construction time, construction equipment to pass through, with rational allocation working sources.
Specifically, can obtain the inquiry request of terminal transmission at any time, inquiry request include the identity information of inquiry with And the construction content checked needed for inquiry, Authority Verification is carried out to the identity information of inquiry, whether is had with revene lookup person There is the search access right of construction content, when verifying inquiry has the search access right of construction content, is sent in construction to terminal Hold, the construction content includes construction speed, Design of Construction Organization, construction period and construction personnel adjusted.
More specifically, the construction content can include but is not limited to total construction speed, difference is building continuous beam suspended bracket construction Progress, certain time period issue early warning and/or pre-warning signal, certain time period or a certain moment construction plan, The construction speed of a certain moment or certain time period, the real-time status data at a certain moment or certain time period, construction plan tune At least one in whole number, the Suitable content of construction plan, the adjustment personnel of construction plan and the relevant information of construction personnel Kind.
The construction personnel that the subsequent construction period includes per pass working procedure in construction segment is adjusted in the present embodiment, and subsequent The construction plan of construction period further includes the construction personnel in the subsequent construction period adjusted.
A kind of construction speed monitoring early-warning system, including obtain module 1, respective modules 2, comparison module 3 and warning module 4;
Module 1 is obtained for obtaining the real-time spatial position for segment of currently constructing in construction scene;
Respective modules 2 are used for the corresponding relationship according to real-time spatial position and construction speed, determine current construction segment pair The realtime construction progress answered;
Comparison module 3 works as real-time empty for real-time spatial position to be compared with pre-set plan spatial position Between position lag plan spatial position when, into warning module 4;
Warning module 4 is for sending progress early warning information.
Further, comparison module 3 includes division module 31, is overlapped respective modules 32 and lag judgment module 33;
Division module 31 divides multiple planned times and multiple plan spatial positions for the segment that will construct in advance, when plan Between with plan spatial position correspond, into be overlapped respective modules 32;
Respective modules 32 are overlapped for being intended to time coincidence corresponding with real-time time, whether stagnant compare real-time spatial position After plan spatial position, the real-time time is real-time time corresponding when obtaining real-time spatial position, is judged into lag Module 33;
Lag judgment module 33 be used for when real-time spatial position lag plan spatial position, according to spatial position and construct into The corresponding relationship of degree obtains realtime construction progress lag target construction speed, and enters warning module 4.
A kind of computer-readable storage media is stored with several acquisitions classification journeys on the computer readable storage medium Sequence, several acquisition sort programs by processor for being called and executing following steps:
Obtain the real-time spatial position for segment of currently constructing in construction scene;
According to the corresponding relationship of real-time spatial position and construction speed, determine the corresponding realtime construction in current construction segment into Degree;
Real-time spatial position is compared with pre-set plan spatial position;
When real-time spatial position lags plan spatial position, then realtime construction progress lags target construction speed, sends Progress early warning information.
Those of ordinary skill in the art will appreciate that: realize that all or part of the steps of above method embodiment can pass through The relevant hardware of program instruction is completed, and program above-mentioned can be stored in a computer readable storage medium, the program When being executed, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes: ROM, RAM, magnetic disk or light The various media that can store program code such as disk.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (9)

1. a kind of construction speed monitoring and early warning method characterized by comprising
Obtain the real-time spatial position for segment of currently constructing in construction scene;
According to the corresponding relationship of real-time spatial position and construction speed, the corresponding realtime construction progress in current construction segment is determined;
Real-time spatial position is compared with pre-set plan spatial position;
When real-time spatial position lags plan spatial position, then realtime construction progress lags target construction speed, sends progress Early warning information.
2. construction speed monitoring and early warning method according to claim 1, which is characterized in that it is described by realtime construction progress with Pre-set target construction speed is compared, comprising:
Construction segment is divided into multiple planned times and multiple plan spatial positions, planned time and plan spatial position one in advance One is corresponding;
Be intended to the time it is corresponding with real-time time be overlapped, compare real-time spatial position whether lag plan spatial position, the reality When the time be corresponding real-time time when obtaining real-time spatial position;
Plan spatial position when real-time spatial position lags, according to the corresponding relationship of spatial position and construction speed, obtains in real time Construction speed lags target construction speed.
3. construction speed monitoring and early warning method according to claim 1, which is characterized in that the realtime construction progress lag When target construction speed, comprising:
Judge other construction segments after currently construction segment with the presence or absence of the first free time;
If so, send the first progress early warning information, and according to first free time, the realtime construction progress with And target construction speed adjusts target construction plan;
If it is not, then sending the second progress early warning information, and compress the construction of other construction segments after current construction segment Activity time obtains the second free time of other construction segments, and according to the second free time, realtime construction progress and mesh It marks construction speed and adjusts target construction plan.
4. a kind of construction speed monitoring and early warning method according to claim 3, which is characterized in that pre- in first progress that sends After alert prompt information, mesh is being adjusted according to first free time, the realtime construction progress and target construction speed Before mark construction plan, comprising:
The duration of the first free time is obtained, and judges whether realtime construction progress lag duration was less than or equal to for the first free time Duration;
If so, adjusting target construction according to first free time, the realtime construction progress and target construction speed Plan;
If it is not, then sending the second progress early warning information, and compress the construction of other construction segments after current construction segment Activity time obtains the second free time of other construction segments, according to first free time, the second free time, reality When construction speed and target construction speed adjust target construction plan, the sum of first free time and the second free time Duration is lagged more than or equal to realtime construction progress.
5. a kind of construction speed monitoring and early warning method according to claim 3, which is characterized in that when free according to second Between, realtime construction progress and target construction speed adjustment target construction plan before, comprising:
Judge whether the second free time was greater than or equal to realtime construction progress lag duration;
If so, adjusting target construction plan according to the second free time, realtime construction progress and target construction speed;
If it is not, then sending third progress early warning information.
6. -5 any construction speed monitoring and early warning method according to claim 1, which is characterized in that further include obtaining terminal The inquiry request of transmission after carrying out Authority Verification to the identity information of inquiry, sends construction content to terminal, in the construction Hold includes construction speed adjusted, Design of Construction Organization, construction period and construction personnel.
7. a kind of construction speed monitoring early-warning system, which is characterized in that including obtaining module (1), respective modules (2), comparing mould Block (3) and warning module (4);
Module (1) is obtained for obtaining the real-time spatial position for segment of currently constructing in construction scene;
Respective modules (2) are used for the corresponding relationship according to real-time spatial position and construction speed, determine that current construction segment is corresponding Realtime construction progress;
Comparison module (3) is for real-time spatial position to be compared with pre-set plan spatial position, when real-time space When position lag plan spatial position, into warning module (4);
Warning module (4) is for sending progress early warning information.
8. construction speed monitoring early-warning system according to claim 7, which is characterized in that comparison module (3) includes dividing Module (31) is overlapped respective modules (32) and lag judgment module (33);
Division module (31) divides multiple planned times and multiple plan spatial positions, planned time for the segment that will construct in advance It is corresponded with plan spatial position, into coincidence respective modules (32);
Respective modules (32) are overlapped for being intended to time coincidence corresponding with real-time time, compare whether real-time spatial position lags Plan spatial position, the real-time time is real-time time corresponding when obtaining real-time spatial position, judges mould into lag Block (33);
Judgment module (33) are lagged to be used for when real-time spatial position lag plan spatial position, according to spatial position and construction speed Corresponding relationship, obtain realtime construction progress lag target construction speed, and enter warning module (4).
9. a kind of computer-readable storage media, which is characterized in that be stored with several obtain on the computer readable storage medium Sort program is taken, several acquisition sort programs by processor for being called and executing following steps:
Obtain the real-time spatial position for segment of currently constructing in construction scene;
According to the corresponding relationship of real-time spatial position and construction speed, the corresponding realtime construction progress in current construction segment is determined;
Real-time spatial position is compared with pre-set plan spatial position;
When real-time spatial position lags plan spatial position, then realtime construction progress lags target construction speed, sends progress Early warning information.
CN201910682905.4A 2019-07-26 2019-07-26 Construction progress monitoring and early warning method and system Active CN110443480B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910682905.4A CN110443480B (en) 2019-07-26 2019-07-26 Construction progress monitoring and early warning method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910682905.4A CN110443480B (en) 2019-07-26 2019-07-26 Construction progress monitoring and early warning method and system

Publications (2)

Publication Number Publication Date
CN110443480A true CN110443480A (en) 2019-11-12
CN110443480B CN110443480B (en) 2023-10-27

Family

ID=68431740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910682905.4A Active CN110443480B (en) 2019-07-26 2019-07-26 Construction progress monitoring and early warning method and system

Country Status (1)

Country Link
CN (1) CN110443480B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN112176866A (en) * 2020-08-28 2021-01-05 中铁九局集团第七工程有限公司 Rectangular steel cable tower construction system and method for large-span asymmetric swivel cable-stayed bridge
CN112365160A (en) * 2020-11-11 2021-02-12 深圳市欧瑞博科技股份有限公司 Auxiliary method and device for intelligent construction, intelligent auxiliary equipment and storage medium
CN113191676A (en) * 2021-05-21 2021-07-30 湖南万达项目管理有限公司 Method and system for managing engineering consultation quality in whole process
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113362028A (en) * 2021-06-05 2021-09-07 浙江宏诚工程咨询管理有限公司 Engineering on-line management method and system
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam yard management system and railway beam yard management method based on BIM technology
CN107273587A (en) * 2017-05-26 2017-10-20 北京戴纳实验科技有限公司 A kind of Schedule monitoring method for laboratory engineering construction
WO2018120891A1 (en) * 2016-12-28 2018-07-05 平安科技(深圳)有限公司 Software development progress early warning method, device, server, and storage medium
CN109359125A (en) * 2018-08-27 2019-02-19 中铁建工集团有限公司 A kind of progress fine-grained management method and its system for construction project
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106339490A (en) * 2016-08-31 2017-01-18 铁道第三勘察设计院集团有限公司 System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model
WO2018120891A1 (en) * 2016-12-28 2018-07-05 平安科技(深圳)有限公司 Software development progress early warning method, device, server, and storage medium
CN106875159A (en) * 2017-02-17 2017-06-20 中国十七冶集团有限公司 The city integrated piping lane construction total management system of cast-in-place structural
CN106997511A (en) * 2017-04-05 2017-08-01 中铁四局集团有限公司 Railway beam yard management system and railway beam yard management method based on BIM technology
CN107273587A (en) * 2017-05-26 2017-10-20 北京戴纳实验科技有限公司 A kind of Schedule monitoring method for laboratory engineering construction
CN109359125A (en) * 2018-08-27 2019-02-19 中铁建工集团有限公司 A kind of progress fine-grained management method and its system for construction project
CN109492875A (en) * 2018-10-15 2019-03-19 筑梦高科建筑有限公司 Construction site role's management-control method based on BIM

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111222786A (en) * 2020-01-04 2020-06-02 河南惠德工程咨询有限公司 Engineering cost control system based on BIM technology
CN112176866A (en) * 2020-08-28 2021-01-05 中铁九局集团第七工程有限公司 Rectangular steel cable tower construction system and method for large-span asymmetric swivel cable-stayed bridge
CN112365160A (en) * 2020-11-11 2021-02-12 深圳市欧瑞博科技股份有限公司 Auxiliary method and device for intelligent construction, intelligent auxiliary equipment and storage medium
CN113191676A (en) * 2021-05-21 2021-07-30 湖南万达项目管理有限公司 Method and system for managing engineering consultation quality in whole process
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
CN113362028A (en) * 2021-06-05 2021-09-07 浙江宏诚工程咨询管理有限公司 Engineering on-line management method and system
CN115526739A (en) * 2022-09-16 2022-12-27 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN115526739B (en) * 2022-09-16 2023-06-30 杭州天界数字科技有限公司 Building engineering progress monitoring method based on BIM and machine vision
CN117408643A (en) * 2023-12-12 2024-01-16 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform
CN117408643B (en) * 2023-12-12 2024-03-22 长春建业集团股份有限公司 Progress monitoring management method and system applied to engineering number intelligent management platform

Also Published As

Publication number Publication date
CN110443480B (en) 2023-10-27

Similar Documents

Publication Publication Date Title
CN110443480A (en) Construction progress monitoring and early warning method and system
CN110751373B (en) Communication vehicle scheduling method and system for emergency rescue and communication vehicle
CN107240166A (en) Point inspection terminal and its data processing method
CN107239868A (en) End message processing method and processing device for security cruising inspection system
CN107240164A (en) The data processing of security cruising inspection system and device
CN105657660A (en) Access method of base station routing inspection terminal, routing inspection terminal, server and base station
CN110598872A (en) Maintenance method, device and equipment of traffic system
CN109636183A (en) A kind of multiplexing kind recruitment coordinated management method and system based on big data
CN103391422A (en) Method and device for video monitoring
CN112348457A (en) Method and system for planning patrol route of building and storage medium
CN104346839B (en) A kind of employee's electronic attendance system based on LAN
CN114548906A (en) Engineering supervision and supervision method, system and device and storage medium
CN115494802A (en) Flow operation multi-level safety digital intelligent monitoring system
CN118071059A (en) Intelligent beam field management platform based on BIM and GIS
CN114971320B (en) Substation work auxiliary processing system and self-service processing method
CN116167582A (en) Intelligent construction progress monitoring system based on BIM technology
CN107730141A (en) Workforce Management system based on indoor positioning technologies
CN114205562A (en) Distributed video command center, distributed video command platform, intelligent terminal, distributed video command system and working method of distributed video command system
CN111612088B (en) Method and device for detecting images of superimposed characters
CN107783750A (en) A kind of bridge method for information display, apparatus and system
CN107705053A (en) A kind of estate management operation automatic monitoring method and system
CN107292987A (en) A kind of line inspection system
CN117728573A (en) Distribution network fusion data quality evaluation management system
CN114254929A (en) Steel structure engineering construction management method, controller and system
CN110110465B (en) Management system for city design

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant