CN106875159A - The city integrated piping lane construction total management system of cast-in-place structural - Google Patents
The city integrated piping lane construction total management system of cast-in-place structural Download PDFInfo
- Publication number
- CN106875159A CN106875159A CN201710085131.8A CN201710085131A CN106875159A CN 106875159 A CN106875159 A CN 106875159A CN 201710085131 A CN201710085131 A CN 201710085131A CN 106875159 A CN106875159 A CN 106875159A
- Authority
- CN
- China
- Prior art keywords
- construction
- typing
- resource
- duration
- plan
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 60
- 238000007726 management method Methods 0.000 claims abstract description 33
- 238000013439 planning Methods 0.000 claims abstract description 11
- 238000004458 analytical method Methods 0.000 claims abstract description 8
- 238000012986 modification Methods 0.000 claims abstract description 8
- 230000004048 modification Effects 0.000 claims abstract description 8
- 238000000034 method Methods 0.000 claims description 8
- 239000000463 material Substances 0.000 claims description 7
- 230000015556 catabolic process Effects 0.000 claims description 3
- 238000009472 formulation Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 230000011218 segmentation Effects 0.000 claims description 3
- 230000008901 benefit Effects 0.000 abstract description 4
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 230000018109 developmental process Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000011017 operating method Methods 0.000 description 1
- 238000012384 transportation and delivery Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Engineering & Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Marketing (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Physics & Mathematics (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Operations Research (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses the city integrated piping lane construction total management system of cast-in-place structural, decomposed including comprehensive pipe gallery structure, Planning of construction periods typing, required resource quantity analysis, typing, issue construction plan, daily condition of construction tracking, typing, duration early warning, resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:1), comprehensive pipe gallery structure is decomposed;2), Planning of construction periods typing;3), required resource quantity analysis, typing;4) construction plan, is issued;5), daily condition of construction tracking, typing;6), duration early warning;7), resource adjustment, node time limit modification;8), closed loop, summary.It is an advantage of the invention that effectively improving live progress, quality, safety management efficiency, construction cost is reduced.
Description
Technical field
Applied the present invention relates to Urban Underground pipe gallery technical field of construction, more particularly to the city integrated piping lane of cast-in-place structural
Work total management system, it is adaptable to the work progress management of the cast-in-place pipe gallery in city and similar long range underground engineering.
Background technology
Urban Underground pipe gallery project has been studied mainly for piping lane at present in the existing certain hour of China's development
Planning, design, operation, delivery phase, for the work progress of city integrated piping lane, at present still in the incipient stage.Existing
During some pipe galleries are built, administrative staff are mainly original and are engaged in municipal administration, the administrative staff of architectural engineering, for pipe gallery
Construction, still continue to use municipal administration, the management method of architectural engineering, be not particularly suited for the construction of underground pipe gallery, particularly the duration compared with
Tightly, in the case that operating personnel, construction machinery, material input amount are huge, conventional progress, quality, safety, store keeping method without
Method meets the demand of field management.In this case it is desirable to propose a kind of new management process, a set of new management body is set up
System, to adapt to the construction of Urban Underground pipe gallery, reduces management cost, improves management quality.
The content of the invention
The problem that the purpose of the present invention exists aiming at prior art, there is provided the city integrated piping lane construction of cast-in-place structural is comprehensive
Management system is closed, by clear and definite procedure, the management method of standardization, progress, matter in pipe gallery work progress is overcome
The extensive shortcoming of amount, management of safe operation, efficiently succinct completion piping lane work progress management work.
The object of the present invention is achieved like this:The city integrated piping lane construction total management system of cast-in-place structural, including it is comprehensive
Close Pipe rack to decompose, Planning of construction periods typing, the analysis of required resource quantity, typing, issue construction plan, daily condition of construction with
Track, typing, duration early warning, resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;Second
The structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,
Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not complete
Into the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation people
Member, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progress
Management, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing system
System;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustment
In the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Compared with prior art, it is an advantage of the invention that:Live progress, quality, safety management efficiency are effectively improved, is reduced
Construction cost.
Brief description of the drawings
Fig. 1:The city integrated piping lane construction total management system flow chart of cast-in-place structural
Flow is made according to Task-decomposing, schedule requirement, operating procedure in figure.
Specific embodiment
To further describe the present invention, with reference to embodiment and accompanying drawing, the invention will be further described.
As described in Figure, the city integrated piping lane construction total management system of cast-in-place structural, including comprehensive pipe gallery structure is decomposed, work
Phase plans typing, and construction plan is issued in required resource quantity analysis, typing, and daily condition of construction is tracked, typing, duration early warning,
Resource adjustment, node time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;Second
The structure that step carries out construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step,
Refined by every section of working procedure;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, set not complete
Into the time of giving warning in advance;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operation people
Member, required construction equipment, and typing are retrodicted the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly including progress
Management, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline typing system
System;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, the required resource situation of adjustment in time, in resource adjustment
In the case of invalid, the operation duration is adjusted;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Lanzhou new district underground pipe gallery project, using management process of the invention, is assisted using computer software, is realized
Less administrative staff manage large-scale piping lane engineering.Using the present invention, live progress, quality, safety management effect can be effectively improved
Rate, advantageously reduces construction cost, with good economic benefit and social benefit.
Claims (1)
1. the city integrated piping lane construction total management system of cast-in-place structural, including comprehensive pipe gallery structure is decomposed, Planning of construction periods typing,
Required resource quantity analysis, typing, issue construction plan, daily condition of construction tracking, typing, duration early warning, resource adjustment, section
Point time limit modification and closed loop, summary, it is characterised in that carry out according to the following steps:
1), comprehensive pipe gallery structure is decomposed
Three-level division is carried out to pipe gallery main structure construction, piping lane engineering unit Engineering Division is carried out first;Second stepping
The structure of row construction unit is divided, and by piping lane plan coordinate, standard paragraphs is divided with node section;3rd step, by every
The working procedure of section is refined;
2), Planning of construction periods typing
After project structure breakdown, the duration node of each operation is formulated, specified time started and end time, unfinished carrying is set
Preceding pre-warning time;
3), required resource quantity analysis, typing
After formulating the duration node of each operation, the resource quantity needed for calculating each operation, including each work post operating personnel, institute
Construction equipment, and typing is needed to retrodict the materials arrival time, typing materials arrival period planning;
4) construction plan, is issued
According to the project structure for decomposing and node requirements, the resource requirement of formulation, work plan is issued, mainly include progress pipe
Reason, quality management, safety management, the functional department of management, while including each cooperation troop;
5), daily condition of construction tracking, typing
After construction starts, contrast construction plan is tracked daily by administrative staff, and by real resource, deadline input system;
6), duration early warning
There is error in practice of construction resource, the delay of duration progress with plan resource error, per diem issue early warning information;
7), resource adjustment, node time limit modification
For required resource and the larger error of live physical presence, resource situation needed for adjustment, adjusts invalid in resource in time
In the case of, adjust the operation duration;
8), closed loop, summary
After the completion of each section construction, required resource summary is carried out in time, the follow-up segmentation duration is adjusted in time.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085131.8A CN106875159A (en) | 2017-02-17 | 2017-02-17 | The city integrated piping lane construction total management system of cast-in-place structural |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710085131.8A CN106875159A (en) | 2017-02-17 | 2017-02-17 | The city integrated piping lane construction total management system of cast-in-place structural |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106875159A true CN106875159A (en) | 2017-06-20 |
Family
ID=59166117
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710085131.8A Pending CN106875159A (en) | 2017-02-17 | 2017-02-17 | The city integrated piping lane construction total management system of cast-in-place structural |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106875159A (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755757A (en) * | 2018-06-29 | 2018-11-06 | 上海二十冶建设有限公司 | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery |
CN109299924A (en) * | 2018-10-19 | 2019-02-01 | 杭州数建科技有限公司 | Fining and intelligent project management method based on multistage control |
CN109636675A (en) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | A kind of management method and system of the construction site based on artificial intelligence |
CN109741090A (en) * | 2018-12-18 | 2019-05-10 | 刘雨昆 | It is a kind of based on multifactor distribution engineering material needing forecasting method |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110766292A (en) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | Ship block resource scheduling method, device, equipment and storage medium |
CN110930044A (en) * | 2019-11-29 | 2020-03-27 | 伍知行 | Construction organization resource rapid configuration method and system |
CN111027803A (en) * | 2019-11-01 | 2020-04-17 | 国艺天成建设工程技术有限公司 | Construction management method and construction management system |
CN112541742A (en) * | 2020-12-21 | 2021-03-23 | 宁良武 | Building construction progress management method |
CN113935853A (en) * | 2021-10-29 | 2022-01-14 | 广东三扬网络科技有限公司 | Production progress tracking management method, module, system and storage medium |
CN116128273A (en) * | 2023-04-17 | 2023-05-16 | 清云小筑(北京)创新技术有限公司 | Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint |
CN117196161A (en) * | 2022-01-05 | 2023-12-08 | 陕西克林维尔信息科技有限公司 | Municipal engineering management method, municipal engineering management device, computer readable storage medium and server |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104484524A (en) * | 2014-12-09 | 2015-04-01 | 张家驰 | Method and system based on BIM (building information modeling) simulation model and in-site construction interaction |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106339490A (en) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
-
2017
- 2017-02-17 CN CN201710085131.8A patent/CN106875159A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104484524A (en) * | 2014-12-09 | 2015-04-01 | 张家驰 | Method and system based on BIM (building information modeling) simulation model and in-site construction interaction |
CN104766182A (en) * | 2015-04-30 | 2015-07-08 | 北京宁晖兴业科技有限公司 | Intelligent monitoring system for building design construction based on BIM |
CN105512822A (en) * | 2015-12-14 | 2016-04-20 | 国家电网公司 | Construction progress management method based on visualization technology |
CN106339490A (en) * | 2016-08-31 | 2017-01-18 | 铁道第三勘察设计院集团有限公司 | System and method for managing railway bridge construction progress based on 3DGIS (Three-dimensional Geographic Information System) and engineering three-dimensional model |
Non-Patent Citations (1)
Title |
---|
杨峰: "城市地下市政综合管廊施工方法初步探讨与分析", 《安徽建筑》 * |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108755757A (en) * | 2018-06-29 | 2018-11-06 | 上海二十冶建设有限公司 | Quick mixed construction method based on prefabrication and assembly construction superposed type underground pipe gallery |
CN109299924A (en) * | 2018-10-19 | 2019-02-01 | 杭州数建科技有限公司 | Fining and intelligent project management method based on multistage control |
CN109636675A (en) * | 2018-12-12 | 2019-04-16 | 上海荷福人工智能科技(集团)有限公司 | A kind of management method and system of the construction site based on artificial intelligence |
CN109741090A (en) * | 2018-12-18 | 2019-05-10 | 刘雨昆 | It is a kind of based on multifactor distribution engineering material needing forecasting method |
CN110443480B (en) * | 2019-07-26 | 2023-10-27 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110443480A (en) * | 2019-07-26 | 2019-11-12 | 中铁四局集团第一工程有限公司 | Construction progress monitoring and early warning method and system |
CN110766292A (en) * | 2019-09-29 | 2020-02-07 | 广船国际有限公司 | Ship block resource scheduling method, device, equipment and storage medium |
CN111027803A (en) * | 2019-11-01 | 2020-04-17 | 国艺天成建设工程技术有限公司 | Construction management method and construction management system |
CN110930044A (en) * | 2019-11-29 | 2020-03-27 | 伍知行 | Construction organization resource rapid configuration method and system |
CN112541742A (en) * | 2020-12-21 | 2021-03-23 | 宁良武 | Building construction progress management method |
CN113935853A (en) * | 2021-10-29 | 2022-01-14 | 广东三扬网络科技有限公司 | Production progress tracking management method, module, system and storage medium |
CN117196161A (en) * | 2022-01-05 | 2023-12-08 | 陕西克林维尔信息科技有限公司 | Municipal engineering management method, municipal engineering management device, computer readable storage medium and server |
CN116128273A (en) * | 2023-04-17 | 2023-05-16 | 清云小筑(北京)创新技术有限公司 | Automatic scheduling method and device for working procedure considering variable construction period and dynamic resource constraint |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106875159A (en) | The city integrated piping lane construction total management system of cast-in-place structural | |
CN109710990B (en) | BIM technology-based roller compacted concrete dam construction progress-cost cooperative control method | |
CN103136612A (en) | Development method of zero-coding component-based flow business | |
CN100561542C (en) | A kind of chain type flight delay prealarming device and disposal route thereof of Petri net | |
CN114580752A (en) | Intelligent engineering construction progress management system based on BIM technology | |
Belyakova et al. | Management strategy for regional labor market (case of the Krasnoyarsk krai) | |
CN104331779A (en) | Development area construction project management system and method | |
CN116562802A (en) | Intelligent construction application platform of track traffic based on BIM | |
CN110083989B (en) | Safety data monitoring method in pipe gallery underground excavation engineering based on BIM technology | |
Kenley et al. | Location Breakdown Structure (LBS): a solution for construction project management data redundancy | |
Qiaolan et al. | Civil engineering construction management based on BIM technology | |
CN109162459A (en) | Hyperbolic bonded prestressed large-section ring beam construction method | |
Jia et al. | Setting scheduled trip time based on AVL data | |
CN110232466A (en) | A kind of all kinds of project organization plan resources balance optimization methods of critical path method | |
Shivasami et al. | Early implementation of BIM in large infrastructure projects to manage complex interfaces in a dense urban environment | |
Trépanier et al. | Democratized smartcard data for transit operator | |
Gu | The application of BIM technology in construction project management | |
Novikova et al. | New technologies for utilization of associated petroleum gas in mature fields with no transport infrastructure | |
Cameron et al. | An environmental impact assessment for hydropower development in China | |
Liu et al. | Application practice of code mapping technology in hydropower project construction management system | |
Dara et al. | Complexities in Metrorail Project-A Case Study of Hyderabad Metro Rail | |
CN110866690A (en) | Application of BIM model data in intelligent construction site | |
He et al. | Reflection on Intelligent Construction Based on BIM: Take a Residential Building as an Example | |
Shevchenko et al. | Challenges and threats for Ukraine airports caused by the global pandemic | |
CN104217303A (en) | Workflow management system based on golden three-general integration mode |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170620 |
|
RJ01 | Rejection of invention patent application after publication |