CN118246888A CN202410666767.1A CN202410666767A CN118246888A CN 118246888 A CN118246888 A CN 118246888A CN 202410666767 A CN202410666767 A CN 202410666767A CN 118246888 A CN118246888 A CN 118246888A
Authority
CN
China
Prior art keywords
construction
management
information
prefabricated component
area
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202410666767.1A
Other languages
Chinese (zh)
Other versions
CN118246888B (en
Inventor
高少攀
陈三彬
叶贵宏
张洪伟
李其平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Road & Bridge Shengtong Building Engineering Co ltd
Sichuan Road and Bridge Group Co Ltd
Original Assignee
Sichuan Road & Bridge Shengtong Building Engineering Co ltd
Sichuan Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Road & Bridge Shengtong Building Engineering Co ltd, Sichuan Road and Bridge Group Co Ltd filed Critical Sichuan Road & Bridge Shengtong Building Engineering Co ltd
Priority to CN202410666767.1A priority Critical patent/CN118246888B/en
Publication of CN118246888A publication Critical patent/CN118246888A/en
Application granted granted Critical
Publication of CN118246888B publication Critical patent/CN118246888B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Theoretical Computer Science (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Economics (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Primary Health Care (AREA)
  • Health & Medical Sciences (AREA)
  • Data Mining & Analysis (AREA)
  • General Health & Medical Sciences (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to the field of construction management and discloses a construction management method and system based on prefabricated components, wherein the construction management method and system comprises the steps of obtaining construction area information, partitioning the construction area to obtain a construction sub-area and a relative position relationship between the construction sub-areas, and generating a management container of the construction sub-area by a cloud data server; the cloud data server obtains a prefabricated component combination mode of a construction area according to construction information of each construction subarea of the construction area, a prefabricated component management container is generated, a construction management module confirms a construction scheme, a confirmed construction scheme is generated, the confirmed construction scheme is sent to the cloud data server, the construction management container acquires construction data of the connected prefabricated component management container, construction is carried out, and construction management is completed. By the technical scheme provided by the invention, the real-time sharing and collaborative management of the construction information can be realized, and the efficiency of construction management is improved.

Description

Construction management method and system based on prefabricated part
Technical Field
The invention relates to the field of construction management, in particular to a construction management method and system based on prefabricated components.
Background
With the continuous progress of modern building technology, prefabricated components have become an important component in the field of building construction. The prefabricated components are building elements which are prefabricated in factories and assembled on construction sites, and the efficiency and quality of building construction are greatly improved due to the mode. However, in the actual construction management process, the management and coordination of the prefabricated components become a complex and tedious task.
Traditional prefabricated part construction management methods often rely on manual recording and tracking, which is not only inefficient, but also prone to error. Because prefabricated components are various in variety, different in specification and size and complex in construction site environment, how to realize efficient and accurate management of the prefabricated components, ensure construction quality and progress and become a problem to be solved urgently in the current building construction field.
In addition, with the development of informatization technology, building construction management is gradually transformed into digitalization. However, most of construction management systems in the current market are designed aiming at the traditional cast-in-situ construction mode, and the construction management support for prefabricated components is insufficient, so that the requirements of high efficiency and accuracy of modern building construction cannot be met.
Disclosure of Invention
The invention aims to overcome the defects of the prior art and provides a construction management method based on prefabricated components, which comprises the following steps:
Step one, acquiring construction area information, partitioning a construction area to obtain a construction sub-area and a relative position relation between the construction sub-areas, and generating a management container of the construction sub-area by a cloud data server;
step two, the cloud data server obtains a prefabricated component combination mode of a construction area according to construction information of each construction subarea of the construction area, and generates a prefabricated component management container, if the prefabricated component combination mode is a single component combination mode, the cloud data server enters a step three, and if the prefabricated component combination mode is a mixed component combination mode, the cloud data server enters a step four;
Step three, the prefabricated component data are obtained from the prefabricated component database and are sent to a management container of a construction subarea included in the construction information, a cloud data server generates a management container list of the construction subarea, and a construction scheme is generated by the cloud data server according to the management container list of the construction subarea and the prefabricated component data and is sent to a construction management module to enter step six;
Step four, the cloud data server respectively acquires the data of each prefabricated component in the prefabricated component database according to the prefabricated component information in the construction information and sends the data to a management container corresponding to the construction subarea, the cloud data server obtains a management container list corresponding to the construction subarea, and generates second construction information according to the management container list corresponding to the construction subarea and the data of each prefabricated component, and sends the second construction information to the construction path planning module to enter step five;
Step five, the construction path planning module generates a construction path according to a management container list of a corresponding construction subarea in the second construction information and the relative position relation among the construction subareas, generates a construction scheme by the second construction information and the construction path, sends the construction scheme to the construction management module, and enters step six;
Step six, the construction management module confirms the construction scheme, generates a confirmed construction scheme, sends the confirmed construction scheme to the cloud data server, and the cloud data server sequentially connects management containers of construction subareas included in the confirmed construction scheme to the prefabricated component management containers according to the construction path, and the construction management containers acquire construction data of the connected prefabricated component management containers to carry out construction and finish construction management.
Further, the obtaining construction area information, partitioning the construction area to obtain a construction sub-area and a relative position relationship between the construction sub-areas, includes: dividing the construction area according to an area division strategy to obtain a plurality of divided sub-construction areas and the relative position relation of each divided construction sub-area.
Further, the cloud data server obtains a prefabricated component combination mode of the construction area according to the construction information of each construction subarea of the construction area, and the cloud data server comprises:
according to the obtained construction subareas and the construction information, respectively obtaining the information of the prefabricated components included in the construction subareas, and if the prefabricated components of the construction subareas are consistent, obtaining a single component combination mode; otherwise, a hybrid component combination mode is provided.
Further, the cloud data server generates a construction scheme according to the management container list and the prefabricated component data of the construction subarea, and the method comprises the following steps:
According to the received construction path, rearranging the management containers of the construction subareas in the management container list of the construction subareas to obtain a management container sequence of the construction subareas corresponding to the construction path, and packaging the management container sequence of the construction subareas corresponding to the construction path and the prefabricated component data to generate a construction scheme.
Further, the cloud data server generates second construction information according to the management container list corresponding to the construction subarea and each prefabricated component data, including:
According to the management container list of the corresponding construction subarea, generating a first management list by using the management containers of the construction subarea containing the same prefabricated part information; generating a second management list by using a management container containing construction subareas of different prefabricated part information; and packaging the first management list, the second management list and the data of each prefabricated part to generate second construction information.
Further, the construction path planning module generates a construction path according to the management container list of the corresponding construction subareas in the second construction information and the relative position relationship between the construction subareas, and the construction path planning module includes:
According to the relative position relation between the construction sub-areas, the construction sub-areas are construction nodes, according to the construction sub-areas containing different prefabricated component information and the relative position relation between the construction sub-areas, the construction sub-areas containing different prefabricated component information and adjacent construction sub-areas are packed into a combined construction node, and the construction nodes and the combined construction node are combined to obtain a construction path according to the construction sequence.
The construction management system based on the prefabricated part applies the construction management method based on the prefabricated part, and comprises a cloud data server, a construction path planning module, a construction management module, a data processing module and a communication module;
The construction path planning module, the construction management module and the communication module are respectively connected with the data processing module; the cloud data server is connected with the communication module.
The beneficial effects of the invention are as follows: by the technical scheme provided by the invention, the real-time sharing and collaborative management of the construction information can be realized, the efficiency of construction management is improved, the labor cost is reduced, and the construction quality and progress are ensured.
Drawings
FIG. 1 is a flow diagram of a construction management method based on prefabricated components;
fig. 2 is a schematic diagram of a construction management system based on prefabricated components.
Detailed Description
The technical solution of the present invention will be described in further detail with reference to the accompanying drawings, but the scope of the present invention is not limited to the following description.
The features and capabilities of the present invention are described in further detail below in connection with the examples.
As shown in fig. 1, a construction management method based on prefabricated components includes the following steps:
Step one, acquiring construction area information, partitioning a construction area to obtain a construction sub-area and a relative position relation between the construction sub-areas, and generating a management container of the construction sub-area by a cloud data server;
step two, the cloud data server obtains a prefabricated component combination mode of a construction area according to construction information of each construction subarea of the construction area, and generates a prefabricated component management container, if the prefabricated component combination mode is a single component combination mode, the cloud data server enters a step three, and if the prefabricated component combination mode is a mixed component combination mode, the cloud data server enters a step four;
Step three, the prefabricated component data are obtained from the prefabricated component database and are sent to a management container of a construction subarea included in the construction information, a cloud data server generates a management container list of the construction subarea, and a construction scheme is generated by the cloud data server according to the management container list of the construction subarea and the prefabricated component data and is sent to a construction management module to enter step six;
Step four, the cloud data server respectively acquires the data of each prefabricated component in the prefabricated component database according to the prefabricated component information in the construction information and sends the data to a management container corresponding to the construction subarea, the cloud data server obtains a management container list corresponding to the construction subarea, and generates second construction information according to the management container list corresponding to the construction subarea and the data of each prefabricated component, and sends the second construction information to the construction path planning module to enter step five;
Step five, the construction path planning module generates a construction path according to a management container list of a corresponding construction subarea in the second construction information and the relative position relation among the construction subareas, generates a construction scheme by the second construction information and the construction path, sends the construction scheme to the construction management module, and enters step six;
Step six, the construction management module confirms the construction scheme, generates a confirmed construction scheme, sends the confirmed construction scheme to the cloud data server, and the cloud data server sequentially connects management containers of construction subareas included in the confirmed construction scheme to the prefabricated component management containers according to the construction path, and the construction management containers acquire construction data of the connected prefabricated component management containers to carry out construction and finish construction management.
The method for obtaining the construction area information, partitioning the construction area to obtain the construction sub-area and the relative position relation between the construction sub-areas comprises the following steps: dividing the construction area according to an area division strategy to obtain a plurality of divided sub-construction areas and the relative position relation of each divided construction sub-area.
The cloud data server obtains a prefabricated component combination mode of the construction area according to the construction information of each construction subarea of the construction area, and the cloud data server comprises the following components:
according to the obtained construction subareas and the construction information, respectively obtaining the information of the prefabricated components included in the construction subareas, and if the prefabricated components of the construction subareas are consistent, obtaining a single component combination mode; otherwise, a hybrid component combination mode is provided.
The cloud data server generates a construction scheme according to a management container list of a construction subarea and prefabricated component data, and the cloud data server comprises:
According to the received construction path, rearranging the management containers of the construction subareas in the management container list of the construction subareas to obtain a management container sequence of the construction subareas corresponding to the construction path, and packaging the management container sequence of the construction subareas corresponding to the construction path and the prefabricated component data to generate a construction scheme.
The cloud data server generates second construction information according to the management container list corresponding to the construction subarea and the data of each prefabricated component, and the second construction information comprises:
According to the management container list of the corresponding construction subarea, generating a first management list by using the management containers of the construction subarea containing the same prefabricated part information; generating a second management list by using a management container containing construction subareas of different prefabricated part information; and packaging the first management list, the second management list and the data of each prefabricated part to generate second construction information.
The construction path planning module generates a construction path according to a management container list of a corresponding construction subarea in the second construction information and the relative position relation between the construction subareas, and the construction path planning module comprises:
According to the relative position relation between the construction sub-areas, the construction sub-areas are construction nodes, according to the construction sub-areas containing different prefabricated component information and the relative position relation between the construction sub-areas, the construction sub-areas containing different prefabricated component information and adjacent construction sub-areas are packed into a combined construction node, and the construction nodes and the combined construction node are combined to obtain a construction path according to the construction sequence.
As shown in fig. 2, a construction management system based on prefabricated components applies the construction management method based on prefabricated components, and the construction management system comprises a cloud data server, a construction path planning module, a construction management module, a data processing module and a communication module;
The construction path planning module, the construction management module and the communication module are respectively connected with the data processing module; the cloud data server is connected with the communication module.
The foregoing is merely a preferred embodiment of the invention, and it is to be understood that the invention is not limited to the form disclosed herein but is not to be construed as excluding other embodiments, but is capable of numerous other combinations, modifications and environments and is capable of modifications within the scope of the inventive concept, either as taught or as a matter of routine skill or knowledge in the relevant art. And that modifications and variations which do not depart from the spirit and scope of the invention are intended to be within the scope of the appended claims.

Claims (7)

1. The construction management method based on the prefabricated component is characterized by comprising the following steps of:
Step one, acquiring construction area information, partitioning a construction area to obtain a construction sub-area and a relative position relation between the construction sub-areas, and generating a management container of the construction sub-area by a cloud data server;
step two, the cloud data server obtains a prefabricated component combination mode of a construction area according to construction information of each construction subarea of the construction area, and generates a prefabricated component management container, if the prefabricated component combination mode is a single component combination mode, the cloud data server enters a step three, and if the prefabricated component combination mode is a mixed component combination mode, the cloud data server enters a step four;
Step three, the prefabricated component data are obtained from the prefabricated component database and are sent to a management container of a construction subarea included in the construction information, a cloud data server generates a management container list of the construction subarea, and a construction scheme is generated by the cloud data server according to the management container list of the construction subarea and the prefabricated component data and is sent to a construction management module to enter step six;
Step four, the cloud data server respectively acquires the data of each prefabricated component in the prefabricated component database according to the prefabricated component information in the construction information and sends the data to a management container corresponding to the construction subarea, the cloud data server obtains a management container list corresponding to the construction subarea, and generates second construction information according to the management container list corresponding to the construction subarea and the data of each prefabricated component, and sends the second construction information to the construction path planning module to enter step five;
Step five, the construction path planning module generates a construction path according to a management container list of a corresponding construction subarea in the second construction information and the relative position relation among the construction subareas, generates a construction scheme by the second construction information and the construction path, sends the construction scheme to the construction management module, and enters step six;
Step six, the construction management module confirms the construction scheme, generates a confirmed construction scheme, sends the confirmed construction scheme to the cloud data server, and the cloud data server sequentially connects management containers of construction subareas included in the confirmed construction scheme to the prefabricated component management containers according to the construction path, and the construction management containers acquire construction data of the connected prefabricated component management containers to carry out construction and finish construction management.
2. The method for managing construction based on prefabricated parts according to claim 1, wherein the steps of obtaining construction area information, partitioning the construction area, and obtaining the construction sub-area and the relative positional relationship between the construction sub-areas include: dividing the construction area according to an area division strategy to obtain a plurality of divided sub-construction areas and the relative position relation of each divided construction sub-area.
3. The construction management method based on the prefabricated component according to claim 2, wherein the cloud data server obtains a construction area prefabricated component combination mode according to construction information of each construction subarea of the construction area, and the method comprises the following steps:
according to the obtained construction subareas and the construction information, respectively obtaining the information of the prefabricated components included in the construction subareas, and if the prefabricated components of the construction subareas are consistent, obtaining a single component combination mode; otherwise, a hybrid component combination mode is provided.
4. The construction management method based on the prefabricated component according to claim 3, wherein the cloud data server generates a construction scheme according to the management container list of the construction subarea and the prefabricated component data, and the method comprises the following steps:
According to the received construction path, rearranging the management containers of the construction subareas in the management container list of the construction subareas to obtain a management container sequence of the construction subareas corresponding to the construction path, and packaging the management container sequence of the construction subareas corresponding to the construction path and the prefabricated component data to generate a construction scheme.
5. The construction management method based on prefabricated components according to claim 3, wherein the cloud data server generates second construction information according to the management container list corresponding to the construction subarea and each prefabricated component data, and the method comprises the following steps:
According to the management container list of the corresponding construction subarea, generating a first management list by using the management containers of the construction subarea containing the same prefabricated part information; generating a second management list by using a management container containing construction subareas of different prefabricated part information; and packaging the first management list, the second management list and the data of each prefabricated part to generate second construction information.
6. The method of claim 5, wherein the construction path planning module generates the construction path according to the management container list of the corresponding construction sub-area in the second construction information and the relative positional relationship between the construction sub-areas, and includes:
According to the relative position relation between the construction sub-areas, the construction sub-areas are construction nodes, according to the construction sub-areas containing different prefabricated component information and the relative position relation between the construction sub-areas, the construction sub-areas containing different prefabricated component information and adjacent construction sub-areas are packed into a combined construction node, and the construction nodes and the combined construction node are combined to obtain a construction path according to the construction sequence.
7. A construction management system based on prefabricated components, which is characterized by applying the construction management method based on the prefabricated components according to any one of claims 1-6, wherein the construction management system comprises a cloud data server, a construction path planning module, a construction management module, a data processing module and a communication module;
The construction path planning module, the construction management module and the communication module are respectively connected with the data processing module; the cloud data server is connected with the communication module.
CN202410666767.1A 2024-05-28 2024-05-28 Construction management method and system based on prefabricated part Active CN118246888B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202410666767.1A CN118246888B (en) 2024-05-28 2024-05-28 Construction management method and system based on prefabricated part

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202410666767.1A CN118246888B (en) 2024-05-28 2024-05-28 Construction management method and system based on prefabricated part

Publications (2)

Publication Number Publication Date
CN118246888A true CN118246888A (en) 2024-06-25
CN118246888B CN118246888B (en) 2024-08-06

Family

ID=91552836

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202410666767.1A Active CN118246888B (en) 2024-05-28 2024-05-28 Construction management method and system based on prefabricated part

Country Status (1)

Country Link
CN (1) CN118246888B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007277907A (en) * 2006-04-06 2007-10-25 Toda Constr Co Ltd Method of managing construction of structure using precast members
CN108876658A (en) * 2018-04-17 2018-11-23 中交武汉港湾工程设计研究院有限公司 Prefabricated part hanging procedural information management method
CN109544051A (en) * 2019-01-25 2019-03-29 中铁三局集团广东建设工程有限公司 A kind of construction management application platform based on BIM technology application
US10260232B1 (en) * 2017-12-02 2019-04-16 M-Fire Supression, Inc. Methods of designing and constructing Class-A fire-protected multi-story wood-framed buildings
CN115689464A (en) * 2022-04-14 2023-02-03 闽南理工学院 Assembly type building EPC general contract project management method and system based on BIM
CN117744224A (en) * 2023-12-23 2024-03-22 中建三局第一建设工程有限责任公司 BIM model creation method, device, equipment and medium based on construction information management
CN117808376A (en) * 2024-02-29 2024-04-02 杭州钱塘产城开发集团有限公司 Construction engineering quality detection supervision method and system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007277907A (en) * 2006-04-06 2007-10-25 Toda Constr Co Ltd Method of managing construction of structure using precast members
US10260232B1 (en) * 2017-12-02 2019-04-16 M-Fire Supression, Inc. Methods of designing and constructing Class-A fire-protected multi-story wood-framed buildings
CN108876658A (en) * 2018-04-17 2018-11-23 中交武汉港湾工程设计研究院有限公司 Prefabricated part hanging procedural information management method
CN109544051A (en) * 2019-01-25 2019-03-29 中铁三局集团广东建设工程有限公司 A kind of construction management application platform based on BIM technology application
CN115689464A (en) * 2022-04-14 2023-02-03 闽南理工学院 Assembly type building EPC general contract project management method and system based on BIM
CN117744224A (en) * 2023-12-23 2024-03-22 中建三局第一建设工程有限责任公司 BIM model creation method, device, equipment and medium based on construction information management
CN117808376A (en) * 2024-02-29 2024-04-02 杭州钱塘产城开发集团有限公司 Construction engineering quality detection supervision method and system

Also Published As

Publication number Publication date
CN118246888B (en) 2024-08-06

Similar Documents

Publication Publication Date Title
US20210314276A1 (en) System and method to control a cross domain workflow based on a hierachical engine framework
Cui et al. Offloading autonomous driving services via edge computing
Ford Jr et al. A suggested computation for maximal multi-commodity network flows
CN101794409A (en) Real-time data exchange model of cross-platform application system
KR20150118975A (en) System and methods for multi-user cax editing conflict management
CA3068185A1 (en) Systems and methods for sustainability and social interaction analysis in building information modeling
CN114077764A (en) Method for establishing temporary model based on three-dimensional GIS and BIM integration and application
US20230169805A1 (en) Fleet data collection using a unified model to collect data from heterogenous vehicles
Rauch et al. Axiomatic design based guidelines for the design of a lean product development process
CN105243237A (en) Assembly technology structure tree and building method thereof
Melzner BIM-based takt-time planning and takt control: Requirements for digital construction process management
CN111104074A (en) 3D printing service system supporting online processing
CN118246888B (en) Construction management method and system based on prefabricated part
CN107911294B (en) Cooperative plotting message routing forwarding and processing method based on earth surface block
CN114071657B (en) Processing method, device and storage medium of network slice
CN116560721B (en) Vehicle diagnosis system, method and electronic equipment
CN111006652B (en) Robot side-by-side operation method
CN111881376A (en) House resource searching system
CN115187694A (en) Map sheet edge connecting method, device, equipment and storage medium
CN114089919A (en) Heterogeneous MEC data collaboration method, collaboration service center and system
Zhou et al. Development of an agent based VCIM resource scheduling process for small and medium enterprises
CN113886921A (en) Conversion and integration method of GIS (geographic information System) model and BIM (building information modeling) model of highway engineering
CN114125597A (en) Optical fiber scheduling method and device
CN113743820A (en) Descriptive bus route data-based networked processing method
CN113127229A (en) Ground unmanned platform control system architecture based on communication middleware

Legal Events

Date Code Title Description