CN104361419B - Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification - Google Patents
Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification Download PDFInfo
- Publication number
- CN104361419B CN104361419B CN201410458815.4A CN201410458815A CN104361419B CN 104361419 B CN104361419 B CN 104361419B CN 201410458815 A CN201410458815 A CN 201410458815A CN 104361419 B CN104361419 B CN 104361419B
- Authority
- CN
- China
- Prior art keywords
- information
- defect
- management
- equipment
- equipment state
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000012544 monitoring process Methods 0.000 title claims abstract description 52
- 238000000034 method Methods 0.000 title claims abstract description 43
- 230000005540 biological transmission Effects 0.000 title claims abstract description 21
- 230000009466 transformation Effects 0.000 title claims abstract description 18
- 230000007547 defect Effects 0.000 claims abstract description 184
- 238000007726 management method Methods 0.000 claims abstract description 161
- 238000004458 analytical method Methods 0.000 claims abstract description 43
- 238000012545 processing Methods 0.000 claims abstract description 37
- 238000004519 manufacturing process Methods 0.000 claims abstract description 8
- 238000007619 statistical method Methods 0.000 claims abstract description 5
- 230000003862 health status Effects 0.000 claims abstract description 4
- 230000002159 abnormal effect Effects 0.000 claims description 77
- 230000008030 elimination Effects 0.000 claims description 47
- 238000003379 elimination reaction Methods 0.000 claims description 47
- 238000007689 inspection Methods 0.000 claims description 37
- 230000008569 process Effects 0.000 claims description 18
- 230000003993 interaction Effects 0.000 claims description 16
- 238000012423 maintenance Methods 0.000 claims description 16
- 230000010354 integration Effects 0.000 claims description 7
- 238000010835 comparative analysis Methods 0.000 claims description 6
- 238000012790 confirmation Methods 0.000 claims description 6
- 230000008439 repair process Effects 0.000 claims description 6
- PEDCQBHIVMGVHV-UHFFFAOYSA-N Glycerine Chemical compound OCC(O)CO PEDCQBHIVMGVHV-UHFFFAOYSA-N 0.000 claims description 4
- 238000012512 characterization method Methods 0.000 claims description 4
- 230000002950 deficient Effects 0.000 claims description 4
- 238000009826 distribution Methods 0.000 claims description 4
- 238000007639 printing Methods 0.000 claims description 4
- 230000005856 abnormality Effects 0.000 claims description 3
- 238000013523 data management Methods 0.000 claims description 3
- 238000012552 review Methods 0.000 claims description 3
- 230000000007 visual effect Effects 0.000 claims description 3
- 230000007812 deficiency Effects 0.000 abstract description 16
- 238000010276 construction Methods 0.000 abstract description 3
- 230000001131 transforming effect Effects 0.000 abstract description 3
- 230000004927 fusion Effects 0.000 abstract 1
- 230000000149 penetrating effect Effects 0.000 abstract 1
- 230000001737 promoting effect Effects 0.000 abstract 1
- 238000012216 screening Methods 0.000 abstract 1
- 230000032258 transport Effects 0.000 description 8
- 238000011160 research Methods 0.000 description 6
- 230000006870 function Effects 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 3
- 230000010365 information processing Effects 0.000 description 3
- 238000011835 investigation Methods 0.000 description 3
- 238000012795 verification Methods 0.000 description 3
- 230000008859 change Effects 0.000 description 2
- 238000011156 evaluation Methods 0.000 description 2
- 238000005111 flow chemistry technique Methods 0.000 description 2
- 238000003780 insertion Methods 0.000 description 2
- 230000037431 insertion Effects 0.000 description 2
- 238000005259 measurement Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000004321 preservation Methods 0.000 description 2
- 230000004044 response Effects 0.000 description 2
- 239000013589 supplement Substances 0.000 description 2
- 230000007474 system interaction Effects 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 230000002547 anomalous effect Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008901 benefit Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 239000012141 concentrate Substances 0.000 description 1
- 238000012937 correction Methods 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 238000001727 in vivo Methods 0.000 description 1
- 230000000977 initiatory effect Effects 0.000 description 1
- 230000035800 maturation Effects 0.000 description 1
- 238000005065 mining Methods 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000001105 regulatory effect Effects 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
- G06Q10/06315—Needs-based resource requirements planning or analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Economics (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification, this method is mainly for power regulation center to increasing transformer operation Centralized Monitoring, power transmission and transformation equipment state on-line monitoring and the construction of analysis business newly, realize statistical analysis to equipment deficiency situation, supervision over the processing, Closed loop track, the rule summarized the variation tendency of defect and occurred, the comprehensive extension for promoting power grid security guarantee to be run from management and running to equipment.The resource of fusion operation duty system, production management system and other equipment management systems, Erecting and improving, good working interface, typing power transmission and transforming equipment monitors defect various dimensions information, pass through lateral direction penetrating, internal control is supervised, and the management module of Closed loop track, realizes the control to the real-time running state of power transmission and transforming equipment, the query statistic of all kinds of key messages, the screening tracking of the same clan of family defect, supervise analytical equipment health status.
Description
Technical field
The present invention relates to a kind of power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification.
Background technology
Currently, transformer operation Centralized Monitoring business is included the unified pipe of dispatching control center by " big operation " System Construction
Reason, realize that regulation and control business operates integratively on the basis of safety is ensured.As " big operation " System Construction deepens continuously, nothing
The iterative method of people's work of transformer substation on duty, the business cooperation between monitoring operation and O&M unit become particularly important, monitored
Operations staff grasps the Real-time Alarm information of equipment, and O&M unit is responsible for the live operation maintenance of equipment, the circulation of monitoring information,
Disposal, analysis turn into " big operation " key of horizontal coordination between " general overhaul " system.
Monitoring abnormal information in real time, defect record is filled in the abnormal information for acting non-involution, various dimensions equipment deficiency is stepped on
Remember and initiate equipment deficiency handling process, the typing of equipment deficiency includes following information:
1) device name, affiliated transformer station, type, date of putting into operation, manufacturer, voltage class etc..
2) defect technical reason, defect type (being divided into critical, serious, general), defect numbering (system automatically generates), tool
Hold in vivo, find date, finder etc..
At present, there is blank in domestic related technical research, be worth going deep into Research on Mining.
The content of the invention
The present invention is in order to solve the above problems, it is proposed that a kind of power transmission and transformation equipment state based on regulation and control unification monitors defect
Management system and method, the system standardize registration form by formulating equipment deficiency, and the defects of existing to equipment plans as a whole
Arrange, accomplish to have looked into record, stockpile, be easy to post analysis and summing up experience.
To achieve these goals, the present invention adopts the following technical scheme that:
A kind of power transmission and transformation equipment state based on regulation and control unification monitors fault management system, including dispatching management information system
(OMS), data acquisition module, report generation module, integrated data platform and equipment state operation management system (PMS),
Wherein:
The dispatching management information system, for realizing the unified maintenance and management of dispatching of power netwoks Back ground Information;Realize production industry
Specialization, standardization and the orderly management of business;And for power grid security, operation, plan, secondary device information total score
Analysis is assessed and various visual angles displaying and issue;
The data acquisition module, for gather reflection equipment health status index various kinds of equipment basic data, in real time
Data, inspection travel data, weather information data;
The integrated data platform, on the basis of power network unified model, to the model from each system,
Figure and real-time and non-real-time data carry out integration processing, there is provided each application system near-realtime data is exchanged and shared logical
Road, implementation model, graphics management and data management, show;
The report generation module, the equipment state defect report of device category, defective item, degree is included for generating
Table, equipment state, defect abnormal conditions are shown by graph direct, are easy to regulation and control personnel to grasp the progress feelings of defect
Condition, processing procedure, understand whole grid equipment running status, supervise operation maintenance personnel accordingly to be disposed, improve electric network reliability;
The equipment state operation management system, for establish uniformly, efficient, intensive O&M overhaul management it is information-based flat
Platform, all standing to operation layer, management level, decision-making level's professional ability is realized, the integration of support O&M and maintenance are specialized.
The dispatching management information system, including ftp server, data switching exchane, OMS databases and abnormal information analysis and pipe
Module is managed, ftp server connection integrated data platform, receives the E language files that its timing is sent, and it is solved
Analysis, ftp server are communicated with data switching exchane, and data switching exchane is classified and preserved such as OMS numbers to the E language files of parsing
According to storehouse, the information in OMS databases is read in abnormal information analysis with management module, and the abnormal information of monitoring of tools state is carried out
Analysis and management, user pass through the information analysis of client access exception and management module.
The report generation module, supports multidimensional inquiry, and its keyword statistical content includes defect distribution, defect elimination rate,
Year, season, the moon or specified time section, device type, manufacturer, title, voltage class, list belonging to defect technical reason, equipment
Position, time of putting into operation, defect type or combination condition.
The exhibition method of the report generation module includes three-dimensional dynamic graphical, curve, form or list, and possesses printing
Function.
Data sharing is carried out between the dispatching management information system and equipment state operation management system, shared information includes setting
Standby information, grid graph information, operation of power networks information, appraisal of equipment information, tour information, defect information and service information side
Face.
Business cooperation demand, cooperation service bag are carried out between the dispatching management information system and equipment state operation management system
Include repair schedule workflow management, the management of power failure application process, protect definite value workflow management, scheduling to make workflow management and monitoring find
Defect workflow management;Operation flow cooperation interaction only provides interaction node content, adjusted simultaneously by the way of interaction node is defined
Degree management system is required to provide flow current-status query service with equipment state operation management system.
Based on the method for work of drawbacks described above management system, comprise the following steps:
(1) defect and initial characterization are registered, data collecting module collected equipment state, passes it to dispatching management information system
With equipment state operation management system, into integrated data platform, defect registration is carried out by input system and tentatively determined
Property;
(2) defect is audited, is qualitative, and equipment state operation management system is audited to defect, be qualitative, if that reports and submits lacks
Fall into and find input system mistake or fill in problem be present, then sending defect information to dispatching management information system reminds;If no problem
Defect elimination will be carried out;
(3) defect elimination is handled:After dispatching management information system arranges personnel to carry out defect elimination processing, maintainer is logged in by client
Input system fills in defect elimination information, including defect property, defect elimination time, defect elimination people, and submits to abnormal information analysis and management
Module;
(4) defect elimination is checked and accepted:Abnormal information is analyzed sends information to operations staff with management module, and operations staff is to fault location
Reason situation is carried out an acceptance inspection, and defect elimination is checked and accepted into archive information typing, feeds back to equipment state operation management system;
(5) equipment state operation management system is checked and accepted and audited to defect elimination processing, defect elimination, and integrated data platform will
The defects of preservation data, be transferred to report generation module, report generation module generation defect form.
In the step (1), abnormal information analysis is analyzed monitoring system abnormality alarming signal with management module, really
After the defects of thinking plant stand end production equipment or supervising device information, registered in time on scheduling OMS, and defect information is submitted
To equipment state operation management system.
In the step (2), concretely comprise the following steps:
2-1) abnormal information analysis carries out fundamental analysis with management module to abnormal information, judges whether the abnormal information deposits
In the flow for the processing that circulates, if it is present by this circulate in abnormal information frequency add up, otherwise, by abnormal letter
Breath is included in the range of statistical analysis, is transferred to step 2-2);
2-2) judge whether exception level has reached multiple or taken place frequently, if the determination result is YES, then start handling process, it is no
Then, prompt to increase accidental shortcoming information newly.
In the step (2), Flaw discrimination adjustment needs both sides to confirm, if equipment state operation management system is in defect
In review process, Flaw discrimination is adjusted, then carries out defect both sides' confirmation, each subsystem jointly with dispatching management information system
According to each self-adjusting Flaw discrimination information of qualitative information after confirmation.
In the step (2), defect information, which is reminded, includes graphical prompting, system Pop-up message frame is reminded and short message is informed
Remind;Equipment state operation management system is same to different plant stands, different manufacturers in the form of 3-D graphic in setting time
One type equipment, same manufacturer's distinct device, same producer's same type equipment are analyzed, and are contrasted according to contrast
Analysis result forms abnormal information and defect information comparative analysis report.
In the step (5), abnormal information analysis and management mould are returned to if defect elimination processing, defect elimination examination are unqualified
Block;Otherwise, equipment state operation management system confirms that monitoring alarm information stores after having resetted to defect.
Beneficial effects of the present invention are:
(1) stability, reliability and security:The technology of maturation, ripe research theory and investigation instrument are made full use of,
To ensure that achievement in research on time, with guaranteeing both quality and quantity is completed, mature and stable property follow through is in whole investigation, design, investigation process
Among.
(2) practicality and advance:Adhere to that practicality and advance are combined, ensureing the premise of achievement in research practicality
Under, it disclosure satisfy that the continuous extension of achievement in research scale and application function and perfect, effort reduction investment and operating cost, guarantee
The raising of technical merit and application level.
(3) it is compatible:Strictly in accordance with relevant regulations, for the Development System software of introducing, rational communication party will be used
The means such as formula, data exchange ways realize the interaction between related system, other extendible stipulations;
(4) by report generation module, equipment state, defect abnormal conditions are shown by graph direct, just
Progress, the processing procedure of defect are grasped in regulation and control personnel, whole grid equipment running status is understood, supervises operation maintenance personnel to enter
The corresponding disposal of row, improves electric network reliability;
(5) abnormal defect intelligent set reminder time on demand, setting one before terminating is lacked at different type defect regulation
Reminder time, regulation and control personnel are reminded to supervise the timely defect elimination in scene;The defects of for influenceing equipment operation, the bullet before the equipment is operated
Go out dialog box, the feasibility of the conscientious evaluation operation of prompt, adjusting and control personnel;Abnormal defect prediction scheme storehouse is established simultaneously, it is a kind of when inputting certain
During type exception defect, it may search for and position to corresponding equipment prediction scheme, shorten fault handling time, realize abnormal defect prediction scheme
Intelligent management and have access to.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the schematic flow sheet of the present invention;
Fig. 3 is the OMS of present invention structural representation;
Fig. 4 is the abnormal information statistical analysis schematic flow sheet of the present invention;
Fig. 5 is OMS of the present invention and PMS information interchange figures.
Embodiment:
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
As Figure 1-Figure 5, a kind of power transmission and transformation equipment state based on regulation and control unification monitors fault management system, including adjusts
Spend management system (OMS), data acquisition module, report generation module, integrated data platform and equipment state operation management
System (PMS), wherein:
The dispatching management information system, for realizing the unified maintenance and management of dispatching of power netwoks Back ground Information;Realize main raw
Specialization, standardization and the orderly management of industry business;Power grid security, operation, plan, the comprehensive analysis of secondary device information are commented
Estimate and various visual angles displaying is with issuing;
The data acquisition module, for gather reflection equipment health status index various kinds of equipment basic data, in real time
Data, inspection travel data, weather information data;
The integrated data platform, on the basis of power network unified model, to the model from each system,
Figure and real-time and non-real-time data carry out integration processing, there is provided each application system near-realtime data is exchanged and shared logical
Road, implementation model, graphics management and data management, show;
The report generation module, the equipment state defect report of device category, defective item, degree is included for generating
Table, equipment state, defect abnormal conditions are shown by graph direct, are easy to regulation and control personnel to grasp the progress feelings of defect
Condition, processing procedure, understand whole grid equipment running status, supervise operation maintenance personnel accordingly to be disposed, improve electric network reliability;
The equipment state operation management system, for establish uniformly, efficient, intensive O&M overhaul management it is information-based flat
Platform, all standing to operation layer, management level, decision-making level's professional ability is realized, the integration of support O&M and maintenance are specialized.
The dispatching management information system, including ftp server, data switching exchane, OMS databases and abnormal information analysis and pipe
Module is managed, ftp server connection integrated data platform, receives the E language files that its timing is sent, and it is solved
Analysis, ftp server are communicated with data switching exchane, and data switching exchane is classified and preserved such as OMS numbers to the E language files of parsing
According to storehouse, the information in OMS databases is read in abnormal information analysis with management module, and the abnormal information of monitoring of tools state is carried out
Analysis and management, user pass through the information analysis of client access exception and management module.
Data are sent
Integrated data platform is sent extremely per a monitoring abnormal information E language data files of day interval generation in 1 hour
Ftp server in OMS frameworks, it is daily to amount to 24 abnormal information files of transmission;
Data receiver
The monitoring of tools abnormal information E language files of the daily timing acquisition ftp server of data exchange server, it is daily common
Meter obtains 24 times, every time parses abnormal information data and is put in storage, and carries out statistics deciding grade and level to abnormal information.
The report generation module, supports multidimensional inquiry, and its keyword statistical content includes defect distribution, defect elimination rate,
Year, season, the moon or specified time section, device type, manufacturer, title, voltage class, list belonging to defect technical reason, equipment
Position, time of putting into operation, defect type or combination condition.
The exhibition method of the report generation module includes three-dimensional dynamic graphical, curve, form or list, and possesses printing
Function.
Data sharing is carried out between the dispatching management information system and equipment state operation management system, shared information includes setting
Standby information, grid graph information, operation of power networks information, appraisal of equipment information, tour information, defect information and service information side
Face.
Business cooperation demand, cooperation service bag are carried out between the dispatching management information system and equipment state operation management system
Include repair schedule workflow management, the management of power failure application process, protect definite value workflow management, scheduling to make workflow management and monitoring find
Defect workflow management;Operation flow cooperation interaction only provides interaction node content, adjusted simultaneously by the way of interaction node is defined
Degree management system is required to provide flow current-status query service with equipment state operation management system.
The defects of dispatching and monitoring personnel will have found information is registered, and the start flow on scheduling OMS.Flow is passed through
OMS and PMS information insertion, it is that dispatching and monitoring personnel are had found on PMS, be related to fortune inspection unit be responsible for the defects of information, carry
Give fortune inspection personnel to carry out auditing qualitative, arrangement defect elimination, defect elimination processing and check and accept, and whole defect processing procedure information is transmitted to
Dispatching and monitoring personnel, and audited by dispatching and monitoring personnel, filed.Equipment deficiency workflow can be traced in dispatching and monitoring personnel
And real time inspection equipment deficiency processing procedure, and fortune inspection personnel can be given to provide guiding opinion.
Based on the method for work of drawbacks described above management system, comprise the following steps:
(1) defect and initial characterization are registered, data collecting module collected equipment state, passes it to dispatching management information system
With equipment state operation management system, into integrated data platform, defect registration is carried out by input system and tentatively determined
Property;
(2) defect is audited, is qualitative, and equipment state operation management system is audited to defect, be qualitative, if that reports and submits lacks
Fall into and find input system mistake or fill in problem be present, then sending defect information to dispatching management information system reminds;If no problem
Defect elimination will be carried out;
(3) defect elimination is handled:After dispatching management information system arranges personnel to carry out defect elimination processing, maintainer is logged in by client
Input system fills in defect elimination information, including defect property, defect elimination time, defect elimination people, and submits to abnormal information analysis and management
Module;
(4) defect elimination is checked and accepted:Abnormal information is analyzed sends information to operations staff with management module, and operations staff is to fault location
Reason situation is carried out an acceptance inspection, and defect elimination is checked and accepted into archive information typing, feeds back to equipment state operation management system;
(5) equipment state operation management system is checked and accepted and audited to defect elimination processing, defect elimination, and integrated data platform will
The defects of preservation data, be transferred to report generation module, report generation module generation defect form.
In the step (1), abnormal information analysis is analyzed monitoring system abnormality alarming signal with management module, really
After the defects of thinking plant stand end production equipment or supervising device information, registered in time on scheduling OMS, and defect information is submitted
To equipment state operation management system.
In the step (2), concretely comprise the following steps:
2-1) abnormal information analysis carries out fundamental analysis with management module to abnormal information, judges whether the abnormal information deposits
In the flow for the processing that circulates, if it is present by this circulate in abnormal information frequency add up, otherwise, by abnormal letter
Breath is included in the range of statistical analysis, is transferred to step 2-2);
2-2) judge whether exception level has reached multiple or taken place frequently, if the determination result is YES, then start handling process, it is no
Then, prompt to increase accidental shortcoming information newly.
In the step (2), Flaw discrimination adjustment needs both sides to confirm, if equipment state operation management system is in defect
In review process, Flaw discrimination is adjusted, then carries out defect both sides' confirmation, each subsystem jointly with dispatching management information system
According to each self-adjusting Flaw discrimination information of qualitative information after confirmation.
In the step (2), defect information, which is reminded, includes graphical prompting, system Pop-up message frame is reminded and short message is informed
Remind;Equipment state operation management system is same to different plant stands, different manufacturers in the form of 3-D graphic in setting time
One type equipment, same manufacturer's distinct device, same producer's same type equipment are analyzed, and are contrasted according to contrast
Analysis result forms abnormal information and defect information comparative analysis report.
In the step (5), abnormal information analysis and management mould are returned to if defect elimination processing, defect elimination examination are unqualified
Block;Otherwise, equipment state operation management system confirms that monitoring alarm information stores after having resetted to defect.
By establishing the management tool of similar Gantt chart, equipment state, defect abnormal conditions are passed through into the aobvious of graph direct
Show to come, be easy to regulation and control personnel to grasp progress, the processing procedure of defect, understand whole grid equipment running status, supervise
Operation maintenance personnel is accordingly disposed, and improves electric network reliability.
The defects of having found, information registered, and the start flow on scheduling OMS.Flow passes through OMS and PMS letter
Breath insertion, it is that dispatching and monitoring personnel are had found on PMS, be related to fortune inspection unit be responsible for the defects of information, submit to fortune inspection personnel
Carry out auditing qualitative, arrangement defect elimination, defect elimination processing and check and accept, and whole defect processing procedure information is transmitted to dispatching and monitoring people
Member, and audited by dispatching and monitoring personnel, filed.Equipment deficiency workflow and real time inspection can be traced in dispatching and monitoring personnel
Equipment deficiency processing procedure, and fortune inspection personnel can be given to provide guiding opinion.
To different plant stands, different manufacturers same type equipment, with all one's life in the form of 3-D graphic in setting time
Production producer distinct device, same producer's same type equipment etc. are analyzed.Formed according to contrast comparative analysis result different
Normal information and defect information comparative analysis report.
Abnormal defect storehouse is established, mabage report is formed to the abnormal defect processing process of historical Device, and is stored in abnormal scarce
Fall into storehouse.Abnormal, defect processing report retrieval, when inputting a certain type exception defect, it may search for and position to setting accordingly
Standby mabage report, shorten single equipment fault handling time, realize abnormal scarce intelligent management and have access to.
According to the exception of equipment appearance, defect and feed through to associate device setting monitoring Response project, occurred according to equipment
Exception, defective effect to power grid security Response project setting.The similarity quick-searching of prediction scheme is monitored, allows regulation and control personnel to exist
Execution plan is done in short time, and is disposed guarantee electric power netting safe running.
Defect information specialty statistics
1) statistics and analyzing defect distribution, defect elimination rate are carried out by following keyword:Year, season, the moon or specified time section, equipment
Type, manufacturer, title, voltage class, defect technical reason, equipment affiliated unit, put into operation the time, defect type, combination
Condition etc..
2) realize and the same period of defect incidence, defect elimination rate is compared.
3) statistical result realizes that the diversified forms such as three-dimensional dynamic graphical, curve, form, list export and possess printing work(
Energy.
Abnormal defect storehouse is established, mabage report is formed to the abnormal defect processing process of historical Device, and is stored in abnormal scarce
Fall into storehouse.Abnormal, defect processing report retrieval, when inputting a certain type exception defect, it may search for and position to setting accordingly
Standby mabage report, shorten single equipment fault handling time, realize abnormal scarce intelligent management and have access to.
1) PMS and OMS are docked in provincial optimized integration data and flow.In order to ensure the atomicity of two systems,
And the agility and stability of data sharing and business cooperation, according to the deployment scenario of two systems, two systems should concentrate on province
Company realizes the data sharing and business cooperation between two systems.The maintenance that can effectively reduce between PMS and OMS is complicated
Degree, ensure that the path of data sharing and business cooperation is clear.
2) the power transmission and transformation equipment state monitoring fault management system based on regulation and control unification relies on OMS and PMS basic datas to be total to
Enjoy, realize the interaction of power transmission and transformation equipment state monitoring defect management flow processing, service data interaction can use incremental data to hand over
Mutually and complete two kinds of interface shapes of data interaction, data sharing use E formatted files.
Using WEB browsing modes
Overhauling company transports inspection personnel and monitors fault management system by logging in OMS or power transmission and transformation equipment state and lacked
Fall into business flow processing.
1) data providing encapsulates data into the WF files for meeting workflow Description standard, is sent to local message mail
Catalogue, data receiver scan local message mail directory, parse WF files, start or activate the system workflow;
2) WF files are sent to by the message mail service of both sides' system deployment according to the addresses of items of mail in flow header file
Other side's Mail assigned catalogue.
Equipment deficiency all standing
Registration form is standardized by formulating equipment deficiency, covers device name, affiliated plant stand, type, date of putting into operation, life
Produce producer, voltage class and defect technical reason, defect type (being divided into critical, serious, general), (system is automatic for defect numbering
Generation), particular content, the defects of finding date, the details such as finder, existing to equipment make overall arrangements, accomplish to look into
There are record, stockpile, be easy to post analysis and summing up experience.
Multidimensional inquiry mode
System uses leading (browser/server) mode of operation, by a variety of controls of authority and Row control to electricity
Power equipment deficiency implements closed loop management.By the advantage of network information processing, realize to existing defect, the correlation of OMS
Suresh Kumar statistics and the comprehensive inquiry function of facility information.System can be by individual event condition, including unit or device type, defect class
Type property, manufacturer, device name, defect numbering, equipment voltage class, equipment deficiency technical reason, discovery time, defect elimination
Time and combination condition carry out fast positioning to defect, make the inquiry work of complexity become convenient, fast, obtain equipment deficiency
Quick defect elimination, enables administrative staff to be exercised supervision at any time to equipment deficiency, greatly improves operating efficiency, ensure that the peace of equipment
Row for the national games.
Real-time tracking feeds back
By establishing the management tool of similar Gantt chart, equipment state, defect abnormal conditions are passed through into the aobvious of graph direct
Show to come, be easy to regulation and control personnel to grasp progress, the processing procedure of defect, understand whole grid equipment running status, supervise
Operation maintenance personnel is accordingly disposed, and improves electric network reliability.
Abnormal defect intelligent Service
Abnormal defect intelligent set reminder time on demand, one prompting of setting before terminating is lacked at different type defect regulation
Time, regulation and control personnel are reminded to supervise the timely defect elimination in scene.The defects of for influenceing equipment operation, the ejection pair before the equipment is operated
Talk about frame, the feasibility of the conscientious evaluation operation of prompt, adjusting and control personnel.Abnormal defect prediction scheme storehouse is established simultaneously, a certain type is different when inputting
During normal defect, it may search for and position to corresponding equipment prediction scheme, shorten fault handling time, realize the intelligence of abnormal defect prediction scheme
Energyization is managed and had access to.
System starts day processing
After each timing acquisition abnormal information, monitoring information secondary classification is audited and school by monitoring operations staff
Just, examination & verification correction after the completion of by system according to the same day abnormal information data according to respective rule automatic distinguishing it is accidental, it is multiple, frequency
The exception level of hair, grade reach multiple and the abnormal information are prompted with abnormal information system that is taking place frequently, it is desirable to monitoring fortune
Administrative staff starts monitoring abnormal information examination & approval management process and circulated.
System starts week processing
After the completion of daily monitoring information processing, system is to the week interior accidental grade occurred is believed extremely naturally belonging to current date
Breath is collected, and such as same abnormal information transmission times has reached the multiple of all exception levels or taken place frequently, and system is to the exception
Information is prompted, it is desirable to is regulated and controled operations staff's startup monitoring abnormal information examination & approval management process and is circulated.
Manual analysis startup is handled
Monitoring operations staff, managerial personnel can be carried out manually to all untreated accidental abnormal informations in system
Start handling process.
OMS internal module interacts
Need the contents such as power failure plan, Centralized Monitoring defect to be supported as aid decision during monitoring information consultation, need
Grid power blackout plan arrangement in the specific period regularly is obtained from power failure schedule module, be obtained from Centralized Monitoring defect module
Complete processing monitoring defect, untreated circulation defect, the contents such as untreated defect of exceeding the time limit.
With PMS system interactions
A secondary device account is needed to refer to during monitoring information processing and consultation, power transformation operation is found in defect etc.
Hold, it is necessary to obtain the account of associate device from PMS equipment accounts module, including unit type, manufacturer, the time limit that puts into operation etc. believe
Breath is, it is necessary to which slave unit defect management module obtains related power transformation operation equipment deficiency situation, with reference to OMS and PMS systems
Interconnect, correlation inquiry is done step-by-step.
With IOSS system interactions
Monitoring information defect or the management and control of anomalous variance dynamic are realized, it is necessary to adjust monitoring in time according to power network risk
The contents such as information deciding grade and level, processing time, processing requirement, it is necessary to obtain the power grid risk in special time period from IOSS systems in time
Situation, in order to be adjusted in time to monitoring information disposal arrangement.
Monthly interruption maintenance planning business coordination requirement:
Operation flow describes
Power transmission and transforming equipment repair schedule is responsible for establishment by transport inspection department door, and scheduling examination & approval are submitted after internal balance.Pass through tune
The repair schedule of approval is spent, scheduling carries out filing processing as power off notifying information, and feeds back to transport inspection department door, transport inspection department door hair
Cloth plan simultaneously arranges to perform.
Prefecture-level company's fortune inspection unit is adjusted with submitting to, and overhauling company of province saves according to corresponding to equipment adjusts scope tube to submit to and adjusted
Or net is adjusted, province according to corresponding to equipment adjusts scope tube to submit to of operation branch company is adjusted, net is adjusted or state adjusts.
(1) the monthly plan that has a power failure is submitted:Transport inspection department door submits the monthly plan that has a power failure to give traffic department's (collaboration point 1).
(2) operation plan balance, examination & verification:Traffic department is balanced to power failure plan, audited, to plan of problems
It can retract (collaboration point 2).
(3) operation plan is given an written reply and filed:Traffic department gives an written reply power failure plan and filed, and reply result is transmitted into transport inspection department
Door (collaboration point 3).
As shown in figure 5, OMS2.0 and PMS2.0 is in repair schedule workflow management, the management of power failure application process, protection definite value
Workflow management, scheduling make workflow management and monitoring find that defect workflow management etc. has business cooperation demand.
Operation flow cooperation interaction only provides interaction node content, while OMS2.0 by the way of interaction node is defined
It is required to provide flow current-status query service with PMS2.0.
PMS2.0 realizes in Provincial Power Grid Corporation presses voltage class and scheduling to the flat management of transformer station's possessionization, OMS2.0
Authority is to transformer station's classification point duty management.OMS2.0 and PMS2.0 realizes the business cooperation based on flow in Provincial Power Grid Corporation,
And the longitudinally through of respective business cooperation flow is realized respectively.
Primary equipment is newly thrown and change business cooperation
Operation flow describes
When primary equipment is newly thrown or changed, named by dispatcher's offer transformer station, circuit and equipment scheduling and examined people to fortune
Member, the foundation created as primary equipment in the power station, circuit and the station that possess equipment scheduling name.Dispatcher is completed one in station
Secondary main wiring diagram draw and it is confirmed it is consistent with actual electric network structure after, be transmitted to fortune inspection personnel, drawn as fortune inspection personnel in standing
The foundation of primary connection circuit figure.
After fortune inspection personnel's completion interval, Unit account of plant nameplate parameter, technical parameter and technical data are safeguarded, scheduling is transmitted to;
After dispatcher supplements regulation and control operational factor and actual measurement parameter, fortune inspection personnel are transmitted to.
Primary equipment is newly thrown or the equipment scope of change business cooperation includes:Primary equipment and line facility in standing.
(1) when equipment is newly thrown or changed, inspection personnel's initiating equipment modification application is transported;
(2) name of transformer station, circuit and equipment scheduling is distributed to fortune inspection personnel (collaboration point 1) by dispatcher;
(3) dispatcher names according to equipment scheduling and draws primary connection circuit figure in station, and is transmitted to fortune inspection personnel (collaboration point
2);
(4) the primary connection circuit figure that inspection personnel name according to equipment scheduling, dispatcher draws is transported, carries out primary connection circuit
Figure is drawn, equipment creates and equipment key parameter is safeguarded;
(5) inspection personnel are transported and carry out figure and the examination & verification of equipment key parameter, dispatcher's (collaboration point 3) is transmitted to after
(6) after equipment formally puts into operation, equipment is issued by O&M class monitor and group leader, while supplements Improving Equipment other parameters
With equipment and technology document information, and dispatcher's (collaboration point 4) is transmitted to.
(7) the management and running parameter of dispatcher's ancillary equipment and actual measurement parameter, and it is transmitted to fortune inspection personnel (collaboration point 5).
Need to check operation of power networks state when transporting inspection personnel, or during use power network topology analysis function (such as:Having a power failure influences model
Enclose analysis, fault impact customer analysis, failure reason analysis etc.), it is necessary to using switch changed position information, it can be slapped to transport inspection personnel
Hold accurate operation of power networks state and carry out correct power network topology analysis.In addition, fortune inspection personnel open in progress operation order figure
When ticket or work ticket graphics aided, it is also desirable to carry out operation of making out an invoice based on correct power system operating mode.
For staffed station, after fortune inspection personnel carry out transformer gear adjustment, registration gear adjustment records and is transmitted to tune
Degree personnel;Dispatcher is registered in monitoring daily record after being remotely controlled the sub-connecting switch of transformer of adjustment unattended station, and is transmitted to fortune
Inspection personnel, transformer gear adjustment number, the maintenance of auxiliary prompting shunting switch are grasped to transport inspection personnel.
Although above-mentioned the embodiment of the present invention is described with reference to accompanying drawing, model not is protected to the present invention
The limitation enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not
Need to pay various modifications or deformation that creative work can make still within protection scope of the present invention.
Claims (9)
1. a kind of power transmission and transformation equipment state based on regulation and control unification monitors fault management system, it is characterized in that:Including management and running
System, data acquisition module, report generation module, integrated data platform and equipment state operation management system, wherein:Institute
Dispatching management information system is stated, for realizing the unified maintenance and management of dispatching of power netwoks Back ground Information;Realize production business specialization,
Standardization and orderly management;And for power grid security, operation, plan, secondary device information comprehensive analysis assess and it is more
Visual angle is shown and issue;
The data acquisition module, for gather the reflection various kinds of equipment basic data of equipment health status index, real time data,
Inspection travel data, weather information data;
The integrated data platform, on the basis of power network unified model, to the model from each system, figure
And real-time and non-real-time data carries out integration processing, there is provided each application system near-realtime data exchanges and shared passage, real
Existing model, graphics management and data management, show;
The report generation module, the equipment state defect form of device category, defective item, degree is included for generating, will
Equipment state, defect abnormal conditions are shown by graph direct, are easy to regulation and control personnel to grasp the progress of defect, place
Reason process, understand whole grid equipment running status, supervise operation maintenance personnel accordingly to be disposed, improve electric network reliability;
The equipment state operation management system, for establishing O&M overhaul management informatization platform uniformly, efficient, intensive,
Realize specialized to operation layer, all standing of management level, decision-making level's professional ability, the integration of support O&M and maintenance;
The dispatching management information system, including ftp server, data switching exchane, OMS databases and abnormal information analysis and management mould
Block, ftp server connection integrated data platform, receives the E language files that its timing is sent, and it is parsed,
Ftp server is communicated with data switching exchane, and data switching exchane is classified to the E language files of parsing and preserved to OMS data
Storehouse, abnormal information analysis read the information in OMS databases with management module, the abnormal information of monitoring of tools state are divided
Analysis and management, user pass through the information analysis of client access exception and management module.
2. a kind of power transmission and transformation equipment state based on regulation and control unification as claimed in claim 1 monitors fault management system, it is special
Sign is:The report generation module, supports multidimensional inquiry, its keyword statistical content include defect distribution, defect elimination rate, year,
Season, the moon or specified time section, device type, manufacturer, title, voltage class, defect technical reason, equipment affiliated unit,
Put into operation time, defect type or combination condition.
3. a kind of power transmission and transformation equipment state based on regulation and control unification as claimed in claim 1 monitors fault management system, it is special
Sign is:The exhibition method of the report generation module includes three-dimensional dynamic graphical, curve, form or list, and possesses printing work(
Energy.
4. a kind of power transmission and transformation equipment state based on regulation and control unification as claimed in claim 1 monitors fault management system, it is special
Sign is:Data sharing is carried out between the dispatching management information system and equipment state operation management system, shared information includes equipment
In terms of information, grid graph information, operation of power networks information, appraisal of equipment information, tour information, defect information and service information.
5. a kind of power transmission and transformation equipment state based on regulation and control unification as claimed in claim 1 monitors fault management system, it is special
Sign is:Business cooperation demand is carried out between the dispatching management information system and equipment state operation management system, cooperation service includes
Repair schedule workflow management, the management of power failure application process, the workflow management of protection definite value, scheduling make workflow management and monitoring find to lack
Fall into workflow management;Operation flow cooperation interaction only provides interaction node content, dispatched simultaneously by the way of interaction node is defined
Management system is required to provide flow current-status query service with equipment state operation management system.
6. the method for work of the management system of the defects of based on as any one of claim 1-5, it is characterized in that:Including following
Step:
(1) defect and initial characterization, data collecting module collected equipment state are registered, dispatching management information system is passed it to and sets
Standby state operation management system, into integrated data platform, defect registration and initial characterization are carried out by input system;
(2) defect is audited, is qualitative, and equipment state operation management system is audited to defect, be qualitative, if the defects of reporting and submitting is sent out
Show input system mistake or fill in and problem be present, then give dispatching management information system to send defect information and remind;It will enter if no problem
Row defect elimination;
(3) defect elimination is handled:After dispatching management information system arranges personnel to carry out defect elimination processing, maintainer logs in typing by client
System fills in defect elimination information, including defect property, defect elimination time, defect elimination people, and submits to abnormal information analysis and management module;
(4) defect elimination is checked and accepted:Abnormal information is analyzed sends information to operations staff with management module, and operations staff is to defect processing feelings
Condition is carried out an acceptance inspection, and defect elimination is checked and accepted into archive information typing, feeds back to equipment state operation management system;
(5) equipment state operation management system is checked and accepted and audited to defect elimination processing, defect elimination, and integrated data platform will preserve
The defects of data, be transferred to report generation module, report generation module generation defect form.
7. method of work as claimed in claim 6, it is characterized in that:In the step (1), abnormal information analysis and management module
Monitoring system abnormality alarming signal is analyzed, after the defects of confirming as plant stand end production equipment or supervising device information,
Dispatch registration, and defect information is committed to equipment state operation management system in time on OMS.
8. method of work as claimed in claim 6, it is characterized in that:In the step (2), concretely comprise the following steps:
2-1) abnormal information analysis carries out fundamental analysis with management module to abnormal information, judges the abnormal information with the presence or absence of just
Circulation processing flow, if it is present by this circulate in abnormal information frequency add up, otherwise, abnormal information is received
Enter in the range of statistical analysis, be transferred to step 2-2);
2-2) judge whether exception level has reached multiple or taken place frequently, if the determination result is YES, then start handling process, otherwise,
Prompting increases accidental shortcoming information newly.
9. method of work as claimed in claim 6, it is characterized in that:In the step (2), Flaw discrimination adjustment needs both sides true
Recognize, if equipment state operation management system is adjusted in defect review process to Flaw discrimination, then with management and running
System carries out defect both sides' confirmation jointly, and each subsystem is according to each self-adjusting Flaw discrimination information of qualitative information after confirmation;
Defect information, which is reminded, includes graphical prompting, system Pop-up message frame is reminded and short message informs prompting;Equipment state O&M
Management system is in setting time to different plant stands, different manufacturers same type equipment, with all one's life in the form of 3-D graphic
Production producer distinct device, same producer's same type equipment are analyzed, and abnormal information is formed according to comparative analysis result
Reported with defect information comparative analysis.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410458815.4A CN104361419B (en) | 2014-09-10 | 2014-09-10 | Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410458815.4A CN104361419B (en) | 2014-09-10 | 2014-09-10 | Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104361419A CN104361419A (en) | 2015-02-18 |
CN104361419B true CN104361419B (en) | 2018-01-23 |
Family
ID=52528677
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410458815.4A Expired - Fee Related CN104361419B (en) | 2014-09-10 | 2014-09-10 | Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104361419B (en) |
Families Citing this family (37)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105590170A (en) * | 2015-12-23 | 2016-05-18 | 国家电网公司 | Electric power regulation and control data management system and method based on customized service |
CN105701546A (en) * | 2016-01-12 | 2016-06-22 | 国家电网公司 | Electric power system defect processing method, apparatus and system thereof |
CN105608561A (en) * | 2016-01-12 | 2016-05-25 | 浪潮通用软件有限公司 | Method and apparatus for processing mail |
CN105787089B (en) * | 2016-03-15 | 2019-02-26 | 国家电网公司 | A kind of distribution network planning basic data integrated approach |
CN107844873A (en) * | 2016-08-26 | 2018-03-27 | 国家电网公司 | One introduces a collection net coordinates performance whole-life cycle fee system and its management method |
CN106651087A (en) * | 2016-09-18 | 2017-05-10 | 国网山东省电力公司聊城供电公司 | Mysql database technology-based method for managing and optimizing operation and maintenance of power transformation |
CN106485598A (en) * | 2016-09-28 | 2017-03-08 | 国家电网公司 | A kind of three-dimensional digital electrical network prediction type examination and repair system |
CN106845760A (en) * | 2016-12-12 | 2017-06-13 | 国网北京市电力公司 | Management system for safety instruments and management method |
CN107680194A (en) * | 2017-09-22 | 2018-02-09 | 国网天津市电力公司 | A kind of information system for power enterprise automates cruising inspection system |
CN107977714A (en) * | 2017-11-08 | 2018-05-01 | 天津市普迅电力信息技术有限公司 | A kind of intelligent control platform of power transformation fortune inspection |
CN107657399A (en) * | 2017-11-16 | 2018-02-02 | 国网江苏省电力有限公司 | A kind of online management-control method of transformer station's electric energy balance for cooperateing with defect elimination |
CN108197771A (en) * | 2017-12-06 | 2018-06-22 | 国网江苏省电力公司泰兴市供电公司 | It is a kind of using problem as be oriented to the safe operation management method of grid equipment |
CN108039774B (en) * | 2017-12-29 | 2023-08-29 | 成都素寺图科技有限公司 | Photovoltaic power supply low-power consumption contact net and power supply equipment monitoring system and method |
CN107784485A (en) * | 2018-01-22 | 2018-03-09 | 柴建霖 | A kind of grid equipment state evaluation system |
CN108808853B (en) * | 2018-05-18 | 2022-02-22 | 广东电网有限责任公司 | Power grid alarm signal circulation system based on internet |
CN109102255B (en) * | 2018-08-16 | 2020-12-08 | 国网福建省电力有限公司龙岩供电公司 | Full-process cooperative management method for electric energy transaction and defect |
CN109165753B (en) * | 2018-08-22 | 2022-03-04 | 国网冀北电力有限公司唐山供电公司 | Transformer substation defect management method based on mobile platform |
CN109583846B (en) * | 2018-12-14 | 2023-07-11 | 国网湖南省电力有限公司 | Data checking method and system for power supply communication management system |
CN109800227B (en) * | 2018-12-26 | 2022-04-22 | 贵州电网有限责任公司 | Power grid dispatching operation recording system based on structural design |
CN110489721A (en) * | 2019-08-09 | 2019-11-22 | 国网山西省电力公司 | Power equipment typical defect prediction technique, terminal device and storage medium |
CN110502751B (en) * | 2019-08-09 | 2023-02-24 | 国网山西省电力公司 | Large power grid operation situation sensing method, terminal equipment and storage medium |
CN110688389B (en) * | 2019-08-30 | 2023-04-18 | 国网重庆市电力公司璧山供电分公司 | Cloud management system for defects of secondary equipment of transformer substation |
CN110516828B (en) * | 2019-09-20 | 2023-08-22 | 国网山东省电力公司泰安供电公司 | Monitoring information processing system and method |
CN110689260A (en) * | 2019-09-25 | 2020-01-14 | 云南电网有限责任公司大理供电局 | Intelligent assistant system applied to integration of district and county regulation and control |
CN112785006A (en) * | 2019-10-22 | 2021-05-11 | 捷普电子(广州)有限公司 | Machine equipment state monitoring system and method, computer readable storage medium |
CN110866617A (en) * | 2019-11-15 | 2020-03-06 | 国网天津市电力公司 | Maintenance aid decision-making method associated with equipment life cycle |
CN110866695A (en) * | 2019-11-15 | 2020-03-06 | 国网天津市电力公司 | Auxiliary maintenance decision method based on association of equipment running state and maintenance work |
CN111080128A (en) * | 2019-12-17 | 2020-04-28 | 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 | Big data analysis and reliability evaluation management system for thermal power station metal equipment |
CN111460772A (en) * | 2020-02-28 | 2020-07-28 | 上海维信荟智金融科技有限公司 | Automatic report processing method and system |
CN112184483A (en) * | 2020-09-29 | 2021-01-05 | 国网北京市电力公司 | Scheduling work display system based on OMS and computer equipment |
CN113052715A (en) * | 2021-04-12 | 2021-06-29 | 中煤北京煤矿机械有限责任公司 | Be used for hydraulic support technology supervision information-based management system |
CN113177647A (en) * | 2021-04-28 | 2021-07-27 | 四川嘉能佳网创新能源科技有限责任公司 | Operation and maintenance big data analysis system and method based on power transformation equipment |
CN113255940A (en) * | 2021-05-18 | 2021-08-13 | 国网山东省电力公司东平县供电公司 | Transformer substation operation inspection management and control system and method |
CN113610250B (en) * | 2021-08-13 | 2024-06-14 | 西安热工研究院有限公司 | Method for online calculation of number of wind field fault stops exceeding 24 hours based on defect list |
CN114237098B (en) * | 2021-12-02 | 2022-08-16 | 深圳市环球众一科技有限公司 | Intelligent digital management system of electrical product |
CN114462956A (en) * | 2021-12-22 | 2022-05-10 | 国网湖南省电力有限公司 | Transformer substation equipment defect/hidden danger management and control system combining maintenance plan |
CN115314360B (en) * | 2022-07-27 | 2024-04-12 | 浪潮软件股份有限公司 | Message queue service performance monitoring system and method |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101770612A (en) * | 2009-09-17 | 2010-07-07 | 宁波北电源兴电力工程有限公司 | Device defect management module of EAM (Enterprise Asset Management) system in power plant |
CN102004955A (en) * | 2010-11-16 | 2011-04-06 | 福建省电力有限公司 | Power dispatching, operation and management application system |
CN102682355A (en) * | 2011-03-17 | 2012-09-19 | 快威科技集团有限公司 | Reconfigurable production management information system based on SOA (Service-Oriented Architecture) composite application for power grid enterprises |
-
2014
- 2014-09-10 CN CN201410458815.4A patent/CN104361419B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101770612A (en) * | 2009-09-17 | 2010-07-07 | 宁波北电源兴电力工程有限公司 | Device defect management module of EAM (Enterprise Asset Management) system in power plant |
CN102004955A (en) * | 2010-11-16 | 2011-04-06 | 福建省电力有限公司 | Power dispatching, operation and management application system |
CN102682355A (en) * | 2011-03-17 | 2012-09-19 | 快威科技集团有限公司 | Reconfigurable production management information system based on SOA (Service-Oriented Architecture) composite application for power grid enterprises |
Non-Patent Citations (1)
Title |
---|
湖南省电力公司生产管理信息系统建设研究;颜碧炎;《中国优秀硕士学位论文全文数据库经济与管理科学辑》;20130715(第7期);正文第1-80页 * |
Also Published As
Publication number | Publication date |
---|---|
CN104361419A (en) | 2015-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104361419B (en) | Power transmission and transformation equipment state monitoring fault management system and method based on regulation and control unification | |
CN113450065B (en) | Production operation management system and method for wind power plant | |
CN106570784B (en) | Voltage monitoring integrated model | |
CN110570101A (en) | Intelligent OMS system for power grid distribution network | |
CN106815709A (en) | One kind service quick response center support system and method | |
CN108320069A (en) | A kind of manufacturing execution system | |
CN103578039B (en) | A kind of power networks risk prewarning analysis system | |
CN110879327B (en) | 10KV line monitoring method by multi-data fusion | |
CN111598411A (en) | Intelligent safety control system for operation site of transformer substation | |
CN109784613A (en) | Electric power field work managing and control system anti-violating the regulations | |
CN106815373A (en) | Big data methods of exhibiting and system are rushed to repair in distribution based on BI analyses | |
CN113807602B (en) | Safety risk management and control and hidden danger supervision and early warning system for pumped storage power station | |
CN114372594B (en) | Distributed power comprehensive analysis and safety control system | |
CN114462642A (en) | Intelligent electric power safety tool cabinet, management system and management method | |
CN116522746A (en) | Power distribution hosting method for high-energy-consumption enterprises | |
CN113610253A (en) | Operation and maintenance management type photovoltaic station control system based on CS version | |
CN115545560A (en) | Wisdom energy visual management platform | |
CN112862242A (en) | A production overall process acceptance tool for transformer substation capital construction engineering | |
CN110942161B (en) | Method for improving power supply reliability based on business middle station | |
CN103218758A (en) | Electric power communication device maintaining method and system | |
CN112330489A (en) | Power supply station digital architecture design method based on TOGAF | |
CN114926964A (en) | Remote research method for abnormal metering points based on AMI data | |
CN112700127B (en) | Method for implementing enterprise safety production operation management and control system | |
CN113723787B (en) | Multidimensional data checking method for power customer electricity safety management | |
CN106530119A (en) | Whole grid resource information display method and system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20180123 |