[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JPS61102908A - Steel cell dam - Google Patents

Steel cell dam

Info

Publication number
JPS61102908A
JPS61102908A JP10545185A JP10545185A JPS61102908A JP S61102908 A JPS61102908 A JP S61102908A JP 10545185 A JP10545185 A JP 10545185A JP 10545185 A JP10545185 A JP 10545185A JP S61102908 A JPS61102908 A JP S61102908A
Authority
JP
Japan
Prior art keywords
steel
steel sheet
dam
sheet piles
cells
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP10545185A
Other languages
Japanese (ja)
Other versions
JPH041810B2 (en
Inventor
Yoshinori Motohara
元原 好則
Tatsuyuki Hatomoto
達之 波戸元
Shoji Shibuya
渋谷 正二
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumikin Kozai Kogyo KK
Original Assignee
Sumikin Kozai Kogyo KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumikin Kozai Kogyo KK filed Critical Sumikin Kozai Kogyo KK
Priority to JP10545185A priority Critical patent/JPS61102908A/en
Publication of JPS61102908A publication Critical patent/JPS61102908A/en
Publication of JPH041810B2 publication Critical patent/JPH041810B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To reduce the cost of construction by a method in which hooped reinforcing bars are plurally set in parallel at given intervals into a columnar form, and steel cells formed by connecting steel sheet piles along the inner surface of the hooped reinforcing bars are connected soft-structurally with plural connecting bars. CONSTITUTION:Hooped reinforcing bars 7 are supported on the hook portion of right-angled clamps attached to struts 18 and set into a columnar form. Steel sheet piles 6 are temporarily positioned on the struts 18 of the bars 7, and the couplers 6a' of other steel sheet piles 6' are connected to the couplers 6a of the piles 6 along the inner surface of the hooped reinforcing bars 7 in a repeating manner. All the steel sheet piles 6 are fixed to the bars 7 by connecting wires to form a steel plate cell 3. Plural cells 3 are temporarily connected with connecting bolts 5 and a filler 22, e.g., soil and stone, is packed into the cells 3.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、山岳地帯などに構築する防砂ダムまたは土
留擁壁等として使用される堰堤に関するものである。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to a dam used as a sand control dam or retaining wall built in mountainous areas.

〔絶来技術およびその問題点〕[Indigenous technology and its problems]

従来から砂防ダム等の堰堤を構築する場合、鉄筋カゴ等
に玉石などを詰め込んで、これを主構造物として敷並べ
るなどしていた。しかし近年玉石が高価になってきたこ
と等から、製作が簡単で費用も安くできると共に、製作
用部材の搬送も容易に行える堰堤が望まれていた。
Traditionally, when constructing a dam such as an erosion control dam, cobblestones and the like are packed into reinforcing cages and laid out as the main structure. However, as cobblestones have become more expensive in recent years, there has been a desire for a dam that is easy to manufacture and inexpensive, and also allows for easy transportation of materials used for manufacturing.

まだ施工現場での地盤の起伏に対応させることが面倒で
あると共に、水流等により堰堤下部の川床が洗掘された
場合などのように施工後の地盤起伏変化に対応すること
が不可能である等の問題点ので、その目的は製作が簡単
で費用も安くでき、また搬送も容易に行えると共に、施
工地盤の起伏および施工後の地盤起伏変化に容易に対応
できる堰堤を提供することにある。
It is still troublesome to deal with the undulations of the ground at the construction site, and it is also impossible to deal with changes in the undulation of the ground after construction, such as when the riverbed at the bottom of the dam is scoured by water flow, etc. Therefore, the purpose is to provide a dam that is easy to manufacture and inexpensive, is easy to transport, and can easily cope with the undulations of the construction ground and changes in the undulation of the ground after construction.

し、この鋼製セルを複数連結して堰堤を構成するものと
する。
However, a dam is constructed by connecting a plurality of these steel cells.

そして鋼製セルは、フープ筋を所定間隔で複数並設して
円柱状となるように支持した後、各フープ筋の内周面に
沿って連結しなから鋼矢板を複数並設固定して製作する
The steel cell is made by arranging a plurality of hoop reinforcements in parallel at predetermined intervals and supporting them in a cylindrical shape, then connecting them along the inner peripheral surface of each hoop reinforcement, and then fixing a plurality of steel sheet piles in parallel. To manufacture.

またこの各鋼矢板の連結は、連結バー2でよって柔構造
的:こ行うものである。
Moreover, the connection of each steel sheet pile is performed by a connection bar 2 in a flexible structure.

示すような砂防ダム2に使用する場合(第1実施例)で
説明する。
The case where it is used in the erosion control dam 2 as shown (first embodiment) will be explained.

堰堤1け、複数の鋼製セル3と、各鋼製セル3内の連結
端側に遊設されている両ボルト固定部4と、各鋼製セル
3内への充填材充填時に各鋼製セル3を連結することに
なる複数の連結ボルト5とからなっている。
One dam, a plurality of steel cells 3, both bolt fixing parts 4 loosely installed on the connection end side in each steel cell 3, and each steel cell 3 when filling the filler into each steel cell 3. It consists of a plurality of connecting bolts 5 that connect the cells 3.

この鋼製セル3は、複数の鋼矢板6と、複数の鋼矢板6
をパイプ状に固定するネジ鉄筋等の複数のフープ筋7と
から成っている。そして連結端側て相当する鋼矢板6の
長手方向には、透孔8が所定間隔で複数穿設されている
。(第3図参照)またボルト固定部4は、断面り字状の
長尺材であり、長手方向に鋼矢板6の透孔8と同間隔の
透孔9が複数穿設されている。そして第4図に示すよう
に連結ボルト5は、ネジ鉄筋で形成されており、画調製
セル3の透孔8と、ボルト固定部4の透孔9とを貫通し
た後に、ナンド10でボルト固定部4へ固着されている
。なお連結ボルト5は、両端にネジ部が設けられている
ものでもよい。(第4図参照) この堰堤1で砂防ダム2を構成するときは、第1図に示
すように渓流等の河川断面形状に合わせて、両端部に径
・高さが小さいものおよび中央位置に径・高さが大きい
もの等適宜設置する。
This steel cell 3 includes a plurality of steel sheet piles 6 and a plurality of steel sheet piles 6.
It consists of a plurality of hoop reinforcements 7, such as screw reinforcing bars, which fix the pipe into a pipe shape. A plurality of through holes 8 are bored at predetermined intervals in the longitudinal direction of the steel sheet pile 6 corresponding to the connecting end. (See FIG. 3) The bolt fixing portion 4 is a long member with a cross-section shaped like an ellipse, and a plurality of through holes 9 are bored in the longitudinal direction at the same intervals as the through holes 8 of the steel sheet pile 6. As shown in FIG. 4, the connecting bolt 5 is made of threaded reinforcing bar, and after passing through the through hole 8 of the image preparation cell 3 and the through hole 9 of the bolt fixing part 4, the connecting bolt 5 is fixed with a bolt 10. It is fixed to part 4. Note that the connecting bolt 5 may be provided with threaded portions at both ends. (See Figure 4) When constructing the erosion control dam 2 using this dam 1, as shown in Figure 1, it is necessary to have one with a small diameter and height at both ends, and one with a small diameter and height in the center according to the cross-sectional shape of a river such as a mountain stream, as shown in Figure 1. Install items with large diameters and heights as appropriate.

また下流側11直下に、玉石12およびH形鋼13かも
なる床掘れ防止用の沈床14が設置されると共に、この
沈床14のさらに下流側11に鉄筋カゴ15が敷詰めら
れる。
Further, a sunken bed 14 made up of boulders 12 and H-beams 13 to prevent floor digging is installed directly below the downstream side 11, and reinforcing bar cages 15 are laid further downstream of the sunken bed 14.

このような構成からなる砂防ダムの施工に際しては、ま
ず河川断面形状に合わせて川底16を掘削して平坦部1
7を設ける。(第1図参照)次にこの平坦部17へ各鋼
製セル3を組立てて設置すると共に、連結ボルト5で各
鋼製セル3を連結して砂防ダム2とする。
When constructing an erosion control dam with such a configuration, first, the river bed 16 is excavated according to the cross-sectional shape of the river, and the flat part 1 is
7 will be provided. (See FIG. 1) Next, each steel cell 3 is assembled and installed on this flat portion 17, and the steel cells 3 are connected with connecting bolts 5 to form the sabo dam 2.

ここで鋼製セル3の組立ては、まず支柱18長手方向で
7−プ筋7の支持位置に所定間隔をあけて直角クランプ
19を竣数設ける。そしてこの支柱18を、直角クラン
プ19のフック部19aでフープ筋7の支持が行えるよ
うに、フープ筋7の直交する直径線上位置へ4本セット
する。(第5図参照) その後直角クランプ19のフック部19aにフープ筋7
を支持させて、フープ筋7を円柱状に並設する。(第6
図参照) 次にフープ筋7の各支柱18位置へ鋼矢板6を仮設して
位置決めする。そしてこの鋼矢板6の係止部6aへ新た
な鋼矢板6′ の係止部6a′  を係止させるように
差込んで連結する作業を、フープ筋19の内周面に沿っ
て順次繰り返した後、全ての鋼矢板6を第7図に示すよ
うに鉄線20でフープ筋7へ固定して鋼製セル3を形成
する。(第7図参照) なおフープ筋7は、長尺のネジ鉄筋を円形状に曲げ加工
し、当接端部をカプラー継手21で連結したものである
Here, in assembling the steel cell 3, first, a number of right angle clamps 19 are installed at predetermined intervals in the longitudinal direction of the column 18 at the supporting position of the 7-pipe reinforcement 7. Then, four of these struts 18 are set at positions on the diameter line orthogonal to the hoop muscle 7 so that the hoop muscle 7 can be supported by the hook portion 19a of the right angle clamp 19. (See Figure 5) After that, the hoop line 7 is attached to the hook part 19a of the right angle clamp 19.
The hoop muscles 7 are arranged side by side in a cylindrical shape. (6th
(See figure) Next, the steel sheet piles 6 are temporarily installed and positioned at the positions of the respective pillars 18 of the hoop reinforcements 7. Then, the process of inserting and connecting the new steel sheet pile 6' to the locking part 6a of the steel sheet pile 6 so as to lock the locking part 6a' of the steel sheet pile 6 was repeated sequentially along the inner circumferential surface of the hoop reinforcement 19. After that, as shown in FIG. 7, all the steel sheet piles 6 are fixed to the hoop reinforcements 7 with iron wires 20 to form the steel cells 3. (See FIG. 7) The hoop reinforcement 7 is made by bending a long threaded reinforcing steel into a circular shape, and connecting the abutting ends with a coupler joint 21.

そしてこのようにして組立てた各鋼製セル3の連結は、
前述した第4図で示したように連結ボルト5で各鋼製セ
ル3を仮連結する。
The connection of each steel cell 3 assembled in this way is as follows:
As shown in FIG. 4 described above, the steel cells 3 are temporarily connected with the connecting bolts 5.

この後に、一般土石の充填材22を鋼製セル3内へ充填
することにより、ボルト固定部4が埋設固定される。こ
のことで各鋼製セル3は、連結棒材5により充填材22
を介して連結されることとなる。(第2図参照) なお各鋼製セル3の連結は、この実施例のものに限らず
、連結棒材によって柔構造的に行うものならばどのよう
なものでもよい。
Thereafter, the bolt fixing portion 4 is buried and fixed by filling the steel cell 3 with a filler material 22 of ordinary earth and stone. With this, each steel cell 3 is connected to the filler 22 by the connecting rod 5.
will be connected via. (See FIG. 2) The connection of each steel cell 3 is not limited to that of this embodiment, but may be of any type as long as it is made in a flexible structure using connecting rods.

またこの考案の堰堤は、前述した実施例のような砂防ダ
ムに限らず、土留擁壁やスクリーンダム述べる効果を有
する。
Furthermore, the dam of this invention is not limited to erosion control dams as in the above-described embodiments, but has the effect of retaining walls and screen dams.

■ 所定間隔で円柱状に複数並設されているフープ筋の
内周面に沿って巾方向へ連結しながら複数並設固定した
鋼矢板で鋼製セルを形成したことにより、鋼製セルを容
易かつ短時間で組立てることができる。
■ By forming steel cells with steel sheet piles that are fixed in parallel and connected in the width direction along the inner circumferential surface of hoop reinforcements that are arranged side by side in a cylindrical shape at predetermined intervals, steel cells can be easily assembled. And it can be assembled in a short time.

そのためフープ筋および鋼矢板とに分割したまま搬送し
、施工現場での組立てを行なうことが可能となると共に
、一般に使用されている鋼矢板を利用できて鋼製セルの
製作を安価に行える。このことから山岳地帯等での鋼製
セルを主構造物とする堰堤の築造を、容易かつ安価に行
なうことが可能となる。
Therefore, it is possible to transport the hoop bars and steel sheet piles while being separated and assemble them at the construction site, and also to use commonly used steel sheet piles, making it possible to manufacture steel cells at low cost. This makes it possible to easily and inexpensively construct a dam whose main structure is a steel cell in a mountainous region or the like.

■ 各鋼製セルの連結は、複数の連結棒材を使用すると
共に、柔構造的に行うことにより、連結後の各鋼製セル
の位置変化を吸収できる。
■ By connecting each steel cell using a plurality of connecting rods and using a flexible structure, changes in the position of each steel cell after connection can be absorbed.

また施工に際しては、堰堤の施工地盤の起伏に容易に対
処できて、堰〜堤の築造を短時間で行うことができる。
Furthermore, during construction, it is possible to easily deal with the undulations of the ground on which the dam is being constructed, and the construction of the dam can be completed in a short time.

フ      さらに水流により下部の川床が洗掘され
たりして起る施工後の地盤起伏変化や、各鋼製セルへの
土砂等の衝突および堆積とを吸収でき、連続壁の破壊を
少なくすることができる。
In addition, it can absorb changes in ground relief after construction, such as when the lower riverbed is scoured by water flow, as well as the impact and accumulation of earth and sand on each steel cell, reducing the possibility of damage to continuous walls. can.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図はこの考案の堰堤を使用した砂防ダ
ムを示す正面図および平面図、第3図は堰堤の主構造物
である鋼製セルを示す斜7兄図、第4図は各鋼製セルの
連結状態を示す部分拡大斜視図、第5図〜第7図は鋼製
セルの組立て状態を示す斜視図、第8図は鋼矢板のフー
プ筋への連結状態を示す斜視図である。 1・・堰堤、2・・砂防ダム、3・・鋼製セル4・・ボ
ルト固定部、5・・連結棒材 6・・鋼矢板、7・・フープ筋、8・・透孔9・・透孔
、10・・ナツト、11・・下流世1112・・玉石、
13・・H形鋼、14・・沈床15・・鉄筋カゴ、16
・・川底 17・・平坦部、18・・支柱 19・・直角クランプ、20・・鉄線 21・・カプラー継手、22・・充填材。 第5図 第6図 第7図 第8図
Figures 1 and 2 are a front view and a plan view of an erosion control dam using the dam of this invention, Figure 3 is a diagonal 7-dimensional diagram showing the steel cells that are the main structure of the dam, and Figure 4 is A partially enlarged perspective view showing the connected state of each steel cell, Figures 5 to 7 are perspective views showing the assembled state of the steel cells, and Figure 8 is a perspective view showing the connected state of the steel sheet pile to the hoop reinforcement. It is. 1. Weir, 2. Sabo dam, 3. Steel cell 4. Bolt fixing part, 5. Connecting bar 6. Steel sheet pile, 7. Hoop reinforcement, 8. Through hole 9. Hole, 10...Natsuto, 11...Downstream 1112...Boulder,
13...H-shaped steel, 14...Sunk bed 15...Rebar cage, 16
・・River bed 17・・Flat area, 18・・Strut 19・・Right angle clamp, 20・・Iron wire 21・・Coupler joint, 22・・・Filling material. Figure 5 Figure 6 Figure 7 Figure 8

Claims (1)

【特許請求の範囲】[Claims] 円柱状となるように所定間隔で複数並設したフープ筋と
、この各フープ筋の内周面に沿つて巾方向へ連結しなが
ら複数並設固定した鋼矢板とからなる鋼製セルが、複数
の連結棒材によつて柔構造的に相互に複数連結されて構
成されていることを特徴とする鋼製セルの堰堤。
A plurality of steel cells are made up of a plurality of hoop bars arranged in parallel at predetermined intervals so as to form a cylindrical shape, and a plurality of steel sheet piles arranged and fixed in parallel while being connected in the width direction along the inner peripheral surface of each hoop bar. A dam of steel cells characterized in that a plurality of steel cells are connected to each other in a flexible structure by connecting rods.
JP10545185A 1985-05-17 1985-05-17 Steel cell dam Granted JPS61102908A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP10545185A JPS61102908A (en) 1985-05-17 1985-05-17 Steel cell dam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP10545185A JPS61102908A (en) 1985-05-17 1985-05-17 Steel cell dam

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
JP22238584A Division JPS61102911A (en) 1984-10-23 1984-10-23 Steel cell

Publications (2)

Publication Number Publication Date
JPS61102908A true JPS61102908A (en) 1986-05-21
JPH041810B2 JPH041810B2 (en) 1992-01-14

Family

ID=14407949

Family Applications (1)

Application Number Title Priority Date Filing Date
JP10545185A Granted JPS61102908A (en) 1985-05-17 1985-05-17 Steel cell dam

Country Status (1)

Country Link
JP (1) JPS61102908A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004003250A (en) * 2002-03-22 2004-01-08 Fujita Corp Structure and construction method of structure
JP2007003376A (en) * 2005-06-24 2007-01-11 Toppan Printing Co Ltd Irregularity inspection device of cyclic pattern and cyclic pattern imaging method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004003250A (en) * 2002-03-22 2004-01-08 Fujita Corp Structure and construction method of structure
JP2007003376A (en) * 2005-06-24 2007-01-11 Toppan Printing Co Ltd Irregularity inspection device of cyclic pattern and cyclic pattern imaging method

Also Published As

Publication number Publication date
JPH041810B2 (en) 1992-01-14

Similar Documents

Publication Publication Date Title
KR101385028B1 (en) Earth retaining structure having beam
JPH07113234A (en) Reinforced earth construction
JP3564669B2 (en) Reinforcement spacer and foundation pile method
JP2000080646A (en) Interlocking cast-in-place pile
JPH10152998A (en) Earthquake-resistant reinforcing structure of existing building
JP4358792B2 (en) Earth retaining wall with water permeability
JPS61102908A (en) Steel cell dam
JP3275738B2 (en) How to assemble underground wall steel reinforced cage
JP3265092B2 (en) Construction method of tunnel with precast concrete slab
JPS5829922A (en) Constructing method for underground outer wall
JPS61102911A (en) Steel cell
JP5280150B2 (en) Yamadome retaining wall and method of forming Yamadome retaining wall
KR100662524B1 (en) Double pipe girder struts as permanent system
CN207862947U (en) A kind of enclosure structure of foundation pit of subway station support
JPS642727B2 (en)
JPH05263421A (en) Column type earth retaining wall
JPS638249B2 (en)
CN114108648B (en) Soft soil foundation pit stirring pile wall cantilever retaining structure
JP7138146B2 (en) Foundation structure, annular body, connecting mechanism of steel segments, and construction method of foundation structure
JPS6172126A (en) Method of building protection wall body
JP2558414B2 (en) Construction method of the main retaining wall and the retaining wall
JPH07894B2 (en) Construction method for underground wall
KR100513816B1 (en) Assembly steel frame with fixing element
JP2603427B2 (en) Foundation structure of reinforced concrete building
JPH06180006A (en) Water area structure and construction thereof