JP3275738B2 - How to assemble underground wall steel reinforced cage - Google Patents
How to assemble underground wall steel reinforced cageInfo
- Publication number
- JP3275738B2 JP3275738B2 JP30218996A JP30218996A JP3275738B2 JP 3275738 B2 JP3275738 B2 JP 3275738B2 JP 30218996 A JP30218996 A JP 30218996A JP 30218996 A JP30218996 A JP 30218996A JP 3275738 B2 JP3275738 B2 JP 3275738B2
- Authority
- JP
- Japan
- Prior art keywords
- steel
- frame
- horizontal
- underground
- assemble
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Landscapes
- Bulkheads Adapted To Foundation Construction (AREA)
Description
【0001】[0001]
【発明が属する技術分野】本発明は、例えば地中壁体に
用いる鉄骨鉄筋籠の組立方法の改良に関するものであ
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to an improvement in a method for assembling a steel rebar basket used for an underground wall, for example.
【0002】[0002]
【従来の技術】土留め壁の工法として、種々の工法が知
られているが、殊に大型工事では環境、強度及び構造の
点から地中連続壁工法が実施されることが多い。この工
法は、地盤を泥水などの安定液を用いて掘削し、掘削完
了後、予め掘削溝の縦横および幅寸法に合わせて組立て
られた鉄筋籠を掘削溝内に建て込み、次いでコンクリー
トを打設して安定液と置換えることにより地中壁体が構
築される。そして、前記作業を繰り返すことにより、所
定間隔をおいて先行する地中壁体を構築した後、該先行
壁体間に同様な作業を施すことによって連続した壁体を
地中に構築している。2. Description of the Related Art Various construction methods are known as construction methods for earth retaining walls. Particularly in large-scale construction, an underground continuous wall construction method is often used in view of the environment, strength and structure. In this method, the ground is excavated using a stable liquid such as muddy water, and after completion of the excavation, a reinforcing cage assembled in advance in accordance with the length, width, and width dimensions of the excavation groove is built into the excavation groove, and then concrete is poured. Then, the underground wall is constructed by replacing with the stabilizing solution. Then, by repeating the above-mentioned operation, a preceding underground wall is constructed at a predetermined interval, and then a similar operation is performed between the preceding walls to construct a continuous wall under the ground. .
【0003】以上のコンクリート地中連続壁体には鉄筋
籠が用いられている。鉄筋籠は、鉄筋を縦横に籠状に組
立てたものである。なお、鉄筋籠はコンクリートと一体
化した状態では強度を発現するが、建起しや、建て込み
時には変形しやすいので、この変形が生じないように、
補強枠などによって一部を補強した鉄筋籠もある。[0003] Reinforced baskets are used for the above concrete underground continuous wall. The reinforcing bar cage is formed by assembling reinforcing bars vertically and horizontally in a basket shape. Reinforced baskets exhibit strength when integrated with concrete, but are easily deformed when erected and built, so that this deformation does not occur.
There is also a reinforced cage partially reinforced with a reinforcing frame.
【0004】[0004]
【発明が解決しようとする課題】しかしながら、近年で
は地中構造物は大型化および大深度化の傾向にあり、こ
の種のコンクリート地中壁体に、従前通り鉄筋籠を採用
しようとすると、以下に述べる技術課題が生ずる。However, underground structures have been increasing in size and depth in recent years. In order to adopt a steel cage for a concrete underground wall of this type, as described above, The technical problem described in (1) occurs.
【0005】例えば、地下発電所、地下エネルギー備蓄
施設、および地下廃棄物処分場のような大深度で大規模
地下空間を構築する場合、その掘削深度および地中壁の
構築深度は地下数十メートルにもおよぶものとなる。こ
のような条件下では、壁面に及す土圧、水圧などによる
水平力が極めて大きく、これに対抗させるために、その
設計壁厚は通常の地中壁の三倍にもなる。For example, when a large-scale underground space is constructed at a large depth such as an underground power plant, an underground energy storage facility, and an underground waste disposal site, the excavation depth and the construction depth of the underground wall are several tens of meters underground. It also extends to. Under such conditions, the horizontal force due to earth pressure, water pressure, etc. exerted on the wall surface is extremely large, and in order to counter this, the design wall thickness is three times that of a normal underground wall.
【0006】したがって、この壁厚の増加に伴い、掘削
土量の増加による工期が増し、また建設用重機の大型化
や、産業廃棄物扱いの処分量が増すなどの一般的課題に
加え、壁厚の増加により、鉄筋籠も大型化し、従来の補
強枠による補強構造では、変形を防止することが難しい
ものとなる。Accordingly, with the increase in the wall thickness, the construction period due to the increase in the amount of excavated soil increases, the size of heavy construction equipment increases, and the amount of disposal of industrial waste increases. Due to the increase in thickness, the reinforcing bar cage also becomes large, and it is difficult to prevent deformation with a conventional reinforcing structure using a reinforcing frame.
【0007】また、地中壁体の強度を高めるためには、
鉄筋径を太くしたり、過密配筋としなければならないた
め、打設コンクリートが鉄筋間の隙間に充填しきれない
場合も生ずる懸念もあった。In order to increase the strength of the underground wall,
Since it is necessary to increase the diameter of the reinforcing bars or to arrange the reinforcing bars densely, there is a concern that cast concrete may not be able to completely fill the gaps between the reinforcing bars.
【0008】このような鉄筋籠の弱点を克服し、これに
代替する従来の構造として、例えば特開平6−1930
49号公報には、鉄骨鉄筋コンクリート造地中連続壁が
提案されている。同公報に開示された技術は、縦方向に
建て込まれるH形鋼の前後フランジを複数の横つなぎ材
で一体に接合するとともに、この横つなぎ材の外面側に
縦横に配筋した鉄骨鉄筋構造を、コンクリートに一体化
して地中連続壁を構築するものである。[0008] As a conventional structure which overcomes such weak points of the reinforcing rod cage and replaces it, for example, Japanese Patent Laid-Open No. 6-1930
No. 49 proposes a steel-walled reinforced concrete underground continuous wall. The technology disclosed in this publication is a steel rebar structure in which front and rear flanges of an H-shaped steel erected in the vertical direction are integrally joined by a plurality of horizontal connecting members, and reinforcing bars are arranged vertically and horizontally on the outer surface side of the horizontal connecting members. Is integrated with concrete to form an underground continuous wall.
【0009】したがって、この構造では、鉄骨強度に応
じた水平耐力が得られ、これにより、従来の鉄筋コンク
リート造の地中連続壁に比べてその壁厚も薄くできる。
但し、この構造においては、掘削された溝幅がその鉄骨
の幅、すなわちH形鋼であれば、両フランジ間の長さ寸
法に適合する幅であれば問題はない。Therefore, in this structure, a horizontal strength corresponding to the strength of the steel frame can be obtained, so that the wall thickness can be made smaller than that of a conventional reinforced concrete underground continuous wall.
However, in this structure, there is no problem as long as the width of the excavated groove is the width of the steel frame, that is, the H-shaped steel, if the width matches the length between the two flanges.
【0010】これに対し、前述のごとき大深度に適合す
るために、壁厚を大きく取った設計とした場合には、現
在市場に流通している定尺の鋼材では適合できない場合
も多い。このため、規格寸法外の鋼材が必要の場合に
は、その溝幅(壁厚)に適合した形状、寸法を指定し
て、鋼材メーカに特注しなければならないため、鋼材費
用が極めて高価となり、工費原価の高騰を招来するとい
う課題があった。On the other hand, if the wall thickness is designed to be large in order to conform to the large depth as described above, there are many cases where it is not possible to use a standard-sized steel material currently on the market. For this reason, if a steel material outside the specified dimensions is required, it is necessary to specify a shape and dimensions suitable for the groove width (wall thickness) and special order to the steel material manufacturer, so the cost of the steel material becomes extremely expensive, There was a problem that the cost of construction cost would rise.
【0011】本発明は、以上の課題を解決するものであ
って、その目的は、通常の鋼材を用いて地中壁の設計壁
厚に自在に適合できるようにした地中壁体の鉄骨鉄筋籠
を組立てる方法を提供するものである。SUMMARY OF THE INVENTION The present invention has been made to solve the above problems, and an object of the present invention is to provide a steel reinforcing bar for an underground wall body which can be freely adapted to a designed wall thickness of the underground wall by using ordinary steel material. basket
Is provided.
【0012】[0012]
【課題解決するための手段】前記目的を達成するため、
本発明のうち請求項1に記載の発明は、地上部に水平出
しされた加工台を配置し、その上部に細帯状鋼板からな
る複数の横枠を所定間隔をおいて並列配置し、前記横枠
の上面に直交して縦筋を配列して前記横枠に接合し、さ
らに、前記縦筋上に横筋を直交配列して該横筋を該縦筋
に接合することにより一体化した外枠部を組立てた後、
該外枠部の鉄骨交差位置にかぶり調整用の複数の鉄骨取
付台を固定し、次いで、その上部に鉄骨を設置して前記
鉄骨取付台に接合するとともに、他の加工台により別途
組立てた前記外枠部をその縦筋及び横筋を内側に配置す
べく裏返して前記鉄骨上に接合する工程を順に行うこと
を特徴とする。 In order to achieve the above object,
The invention described in claim 1 of the present invention has a horizontal projection on the ground.
Machined worktable, and a strip of steel
A plurality of horizontal frames arranged side by side at predetermined intervals,
Vertical streaks are arranged perpendicular to the upper surface of and joined to the horizontal frame,
Further, the horizontal streaks are arranged orthogonally on the vertical streaks and the horizontal streaks are aligned with the vertical streaks.
After assembling the outer frame part integrated by joining to
A plurality of steel frames for fogging adjustment at the steel frame intersections of the outer frame portion.
Fix the mounting, and then install a steel frame on top of the
Attached to the steel mounting table and separately by other processing tables
Place the assembled outer frame with its vertical and horizontal streaks inside.
Turn over and join steps on the steel frame in order
It is characterized by.
【0013】本発明のうち請求項2に記載の発明は、前
記鉄骨柱列はH形鋼であり、このH形鋼の前後側フラン
ジ部を前記鉄骨取付台に接合したことを特徴とする。 [0013] The invention according to claim 2 of the present invention, prior to
The steel column row is an H-section steel, and the front and rear flank of this H-section steel
The joint portion is joined to the steel frame mounting base.
【0014】[0014]
【0015】[0015]
【0016】[0016]
【0017】[0017]
【発明の実施の形態】以下、本発明に好適な実施の形態
を添付図面を参照して詳細に説明する。図1〜図3は本
発明の第一の実施の形態により組立てられる鉄骨鉄筋籠
を示している。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Preferred embodiments of the present invention will be described below in detail with reference to the accompanying drawings. 1 to 3 show a first embodiment of by Ri assembled that steel reinforcing bar cage in the embodiment of the present invention.
【0018】図における鉄骨鉄筋籠1は、所定間隔をお
いて縦列された複数のH形鋼2と、該H形鋼2の両側フ
ランジ部2aに接合された一対の外枠部3、および端面
を囲う補強板4とから概略構成されている。A steel rebar basket 1 shown in the figure includes a plurality of H-shaped steel members 2 arranged in a row at predetermined intervals, a pair of outer frame portions 3 joined to both side flange portions 2a of the H-shaped steel members 2, and an end face. And a reinforcing plate 4 surrounding the.
【0019】外枠部3は、高さ方向に所定間隔をおいて
横列された細帯状鋼板からなる複数の横枠5と、各横枠
5の前記各H形鋼2との交差位置にそれぞれ対をなして
接合された鉄骨取付台を構成するL字形のアングル材6
と、各横枠5の内面側に格子状に配筋された縦横の鉄筋
7,8とからなるものである。The outer frame portion 3 is provided at a crossing position between a plurality of horizontal frames 5 made of strip-shaped steel plates arranged at predetermined intervals in the height direction and the respective H-shaped steel members 2 of each horizontal frame 5. L-shaped angle members 6 forming a pair of joined steel frame mounting bases
And vertical and horizontal reinforcing bars 7 and 8 arranged in a lattice pattern on the inner surface side of each horizontal frame 5.
【0020】そして、このアングル材6の高さに応じて
各H形鋼2のフランジ面と外枠部3とのかぶりが調整さ
れ、横枠5の内面側に鉄筋7,8の配筋が行えるととも
に、コンクリートの打設時における十分な流動スペース
が確保できるようにしている。The cover between the flange surface of each H-section steel 2 and the outer frame portion 3 is adjusted according to the height of the angle member 6, and the reinforcing bars 7, 8 are arranged on the inner surface side of the horizontal frame 5. In addition to being able to do so, a sufficient flow space can be ensured when placing concrete.
【0021】なお、アングル材6に替えて、例えば丸鋼
(短尺)、I形鋼、コ形鋼、あるいはL形鋼の組合わせ
などの各種異形押出鋼材を用いることができる。In place of the angle material 6, various extruded steel materials such as a combination of round steel (short), I-shaped steel, U-shaped steel, or L-shaped steel can be used.
【0022】いずれにおいても、この高さ寸法を掘削溝
幅、あるいは設計壁厚に合わせて作ることによって、前
記H形鋼2が規格寸法のものであっても、その壁厚に自
在に対応できることになる。In any case, by making the height dimension according to the width of the excavation groove or the design wall thickness, even if the H-section steel 2 has a standard dimension, it can freely cope with the wall thickness. become.
【0023】図4は、以上の鉄骨鉄筋籠1を地盤E内に
掘削された溝9内に建込んだ状態を示している。図の一
部に拡大して示すように、溝9の壁面に対し、外枠部3
の鉄筋7、8が接近配置され、その奥に所定の離間距離
Dだけ離れてH形鋼2のフランジ部2aが対向配置され
ており、前記アングル材6の高さに応じた離間量が確保
されている。FIG. 4 shows a state where the above-mentioned steel frame cage 1 is set in a groove 9 excavated in the ground E. As shown in an enlarged part of the figure, the outer frame 3
Rebars 7 and 8 are arranged close to each other, and a flange portion 2a of the H-section steel 2 is disposed opposite to the inner portion thereof at a predetermined separation distance D, and a separation amount corresponding to the height of the angle member 6 is secured. Have been.
【0024】建て込み状態では溝9内は泥水などの安定
液で満たされており、この状態から地表部よりトレミー
管などを通じてコンクリートが打設されて安定液に置換
えられる。In the built-in state, the inside of the groove 9 is filled with a stabilizing liquid such as muddy water. From this state, concrete is poured from the surface of the ground through a tremy tube or the like and replaced with the stabilizing liquid.
【0025】このとき、一カ所ないし複数箇所から打設
されたコンクリートは、アングル材6によって確保され
た隙間を流動して、全体に回り込み、溝9の形状に応じ
た断面の地中壁体が構築される。At this time, the concrete poured from one or a plurality of places flows through the gap secured by the angle members 6 and wraps around the whole, and the underground wall having a cross section corresponding to the shape of the groove 9 is formed. Be built.
【0026】そして、鉄筋7,8はその壁体の表面部に
おけるかぶり鉄筋として機能し、各H形鋼2は主要強度
部材として機能するため、水平耐力に優れた地中壁体と
なる。The reinforcing bars 7 and 8 function as cover reinforcing bars on the surface of the wall, and each H-section steel 2 functions as a main strength member, thereby forming an underground wall having excellent horizontal strength.
【0027】図5は、鉄骨鉄筋籠1の組立手順を示して
いる。先ず(a)に示すように、施工現場近傍に確保さ
れた広場の地上部に水平出しされた組立治具となる加工
台10を配置し、その上部に横枠5となる帯状鋼板を所
定間隔で横列する。FIG. 5 shows an assembling procedure of the steel rebar basket 1. First, as shown in (a), a processing table 10 as an assembling jig horizontally set out on a ground portion of a square secured near a construction site is arranged, and a strip-shaped steel plate serving as a horizontal frame 5 is placed at a predetermined interval above the processing table. In rows.
【0028】次いで、(b)に示すように、横枠5の上
面に直交して縦筋7を配列し、溶接などにより横枠5に
接合する。さらに、横筋8を縦筋7上に直交配列し、溶
接、あるいは結束線などによって縦筋7に接合すれば、
各部が一体化した外枠部3が組立てられる。Next, as shown in (b), the vertical streaks 7 are arranged perpendicular to the upper surface of the horizontal frame 5 and joined to the horizontal frame 5 by welding or the like. Furthermore, if the horizontal streaks 8 are arranged orthogonally on the vertical streaks 7 and joined to the vertical streaks 7 by welding or binding wires,
The outer frame 3 in which the respective parts are integrated is assembled.
【0029】その後、(c)に示すように、H形鋼2と
の交差接合位置に前記アングル材6を接合し、次いで、
その上部にH形鋼2を設置し、そのフランジ部2aをア
ングル材6に接合する。Thereafter, as shown in (c), the angle member 6 is joined to the cross joint position with the H-section steel 2, and then,
The H-section steel 2 is installed on the upper part, and the flange portion 2 a is joined to the angle member 6.
【0030】次に、(d)に示すように他の加工台10
により別途組立てられたもう一方の外枠部3をその鉄筋
7、8を内側に配置すべく裏返して上面側フランジ部2
a上に設置し、そのアングル材6を接合し、その他補強
枠4を端部に配置、接合することで、図1〜図3に示す
鉄骨鉄筋籠1が完成する。Next, as shown in FIG.
The other outer frame part 3 separately assembled by the above is turned over so that the rebars 7 and 8 are arranged inside, and the upper side flange part 2
The steel frame 1 shown in FIG. 1 to FIG. 3 is completed by installing the angle member 6 and joining the angle members 6 and arranging and joining other reinforcing frames 4 at the ends.
【0031】なお、この場合には裏返すことなく設置す
ることもでき、組上がってない状態における変形しやす
く面倒な裏返し作業を解消でき、またこの場合には順次
上部側に向けて組立できるので、別途並列作業による加
工台10およびこれに要する敷地面積は不要となる。さ
らに、仕上り形状は、鉄筋7,8が横枠5の外面側とな
るが、これによる構造的な不具合はない。In this case, it can be installed without turning over, and it can be easily deformed in a state where it is not assembled and troublesome turning over work can be eliminated. In this case, it is possible to sequentially assemble it toward the upper side. Separately, the processing table 10 and the site area required for the parallel operation are not required. Further, in the finished shape, the reinforcing bars 7 and 8 are on the outer surface side of the horizontal frame 5, but there is no structural problem due to this.
【0032】図7は、鉄骨鉄筋籠1の他の組立手順を示
している。なお、同図では、アングル材6に代えて丸鋼
6Aが用いられている。この例によれば、図5(a)〜
(c)までの手順は同じであるが、図5(c)の状態
で、丸鋼6A上に縦筋7を配列して溶接等により接合
し、その後、縦筋7上に横筋8を配列して溶接等により
接合している。この例によれば、一つの加工台10上で
鉄骨鉄筋籠1を完成することができるので、作業ヤード
が狭い場合などに適する。FIG. 7 shows another assembly procedure of the steel frame cage 1. In the same figure, a round bar 6A is used in place of the angle member 6. According to this example, FIGS.
The procedure up to (c) is the same, but in the state of FIG. 5 (c), the vertical bars 7 are arranged on the round bar 6A and joined by welding or the like, and then the horizontal bars 8 are arranged on the vertical bars 7. And joined by welding or the like. According to this example, since the steel frame cage 1 can be completed on one processing table 10, it is suitable when the work yard is narrow.
【0033】図6は、本発明の鉄骨鉄筋籠を杭体に適用
した第二の実施の形態を示している。図は平断面を示す
ものであり、鉄筋コンクリート地中連続壁体または前述
の如き鉄骨鉄筋籠を組込んだ鉄骨鉄筋コンクリート地中
連続壁体20からT字形に突出して鉄骨鉄筋造の杭体2
1が一体に設けられている。FIG. 6 shows a second embodiment in which the steel frame cage of the present invention is applied to a pile. The figure shows a flat section, and a steel reinforced pile 2 projecting in a T-shape from a reinforced concrete underground continuous wall or a steel reinforced concrete underground continuous wall 20 incorporating a steel reinforced cage as described above.
1 are provided integrally.
【0034】この杭体21の内部に組合わされる鉄骨鉄
筋籠22は、前記と直交する方向に両側フランジ部23
aを配向させた一対のH形鋼23と、各H形鋼23の両
側に配置された一対の外枠24と、外枠24間を接合す
るとともに、一対のアングル材26を介して各H形鋼2
3のフランジ部23aに接合することによって各H形鋼
23を外枠24に一体化させた、細帯状鋼板からなる取
付板25とからなっている。The steel rebar basket 22 combined with the inside of the pile body 21 has flange portions 23 on both sides in a direction orthogonal to the above.
A pair of H-shaped steels 23 having a oriented therein, a pair of outer frames 24 arranged on both sides of each H-shaped steel 23, and a joint between the outer frames 24, and a pair of H-shaped steels 23 via a pair of angle members 26 Shaped steel 2
3 and a mounting plate 25 made of a strip-shaped steel plate in which each H-shaped steel 23 is integrated with the outer frame 24 by being joined to the flange portion 23a.
【0035】外枠24は、前記と同様、縦方向に所定間
隔をおいて横設された多数の横枠27と、横枠27の内
面に縦横に配筋された鉄筋28からなるものである。ま
た、取付板25の両端と各横枠27との接合部にはアン
グル材29が介在され、接合強度を向上させている。As described above, the outer frame 24 is composed of a number of horizontal frames 27 horizontally provided at predetermined intervals in the vertical direction, and reinforcing bars 28 arranged vertically and horizontally on the inner surface of the horizontal frame 27. . Further, an angle member 29 is interposed at a joint portion between both ends of the mounting plate 25 and each of the horizontal frames 27 to improve the joint strength.
【0036】以上の杭体21は、主として図の矢印に示
すように、壁体20に加わる水平力を支える機能が付加
されるものであり、それ故に各H形鋼23の両フランジ
部23aを壁体20側に配向させることにより、十分な
水平耐力をもたらすことができる。The above-mentioned pile body 21 is mainly provided with a function to support the horizontal force applied to the wall body 20, as indicated by the arrow in the figure. Therefore, both flange portions 23a of each H-shaped steel 23 are provided. By orienting it toward the wall 20, a sufficient horizontal proof stress can be provided.
【0037】なお、この鉄骨鉄筋籠の組立は、前記第一
の実施の形態と同様にして作られた外枠に対し、予め両
フランジ部23aにアングル材26を接合したH形鋼2
3を横に寝かせた状態で、取付板25の突き合せ端部を
アングル材29を介して固定するなどにより簡単に組立
できる。The steel rebar basket is assembled by assembling an H-shaped steel 2 having an angle member 26 previously joined to both flange portions 23a to an outer frame made in the same manner as in the first embodiment.
With the 3 laid down on its side, the butted end of the mounting plate 25 can be easily assembled by fixing it via an angle member 29, or the like.
【0038】また、本実施形態では、鉄骨鉄筋籠体22
を鉄筋コンクリート地中連続壁体または鉄骨鉄筋コンク
リート地中連続壁体と一体化した場合について述べた
が、鉄骨鉄筋籠体を単独に設置して基礎杭として用いる
ことができることはいうまでもない。In the present embodiment, the steel rebar cage 22
Has been described with reference to the case where the steel frame is integrated with the reinforced concrete underground continuous wall or the steel reinforced concrete underground continuous wall. However, it is needless to say that the steel reinforced cage can be independently installed and used as a foundation pile.
【0039】[0039]
【発明の効果】以上説明したように、本発明にかかる鉄
骨鉄筋籠を組立てる方法にあっては、通常の鋼材を用い
て地中壁の設計壁厚に自在に適合できるので、安価に構
築でき、大深度であって、大規模な地中構造物における
地中連続壁の壁体または地中壁に連続した杭体などに用
いて好適である。As described above, in the method of assembling the steel reinforced cage according to the present invention, the steel wall can be freely adapted to the design wall thickness of the underground wall by using ordinary steel, so that it can be constructed at low cost. It is suitable for use as a wall of an underground continuous wall or a pile connected to an underground wall in a large-scale underground structure at a large depth.
【図1】本発明の第一の実施の形態により組立てられる
鉄骨鉄筋籠の側面図である。1 is a side view of a more assembled that steel reinforcing bar cage in the first embodiment of the present invention.
【図2】同平面図である。FIG. 2 is a plan view of the same.
【図3】同斜視図である。FIG. 3 is a perspective view of the same.
【図4】同鉄骨鉄筋籠を溝内に建て込んだ状態を示す縦
断面図である。FIG. 4 is a vertical cross-sectional view showing a state where the steel rebar basket is erected in a groove.
【図5】同鉄骨鉄筋籠の組立手順を示す説明図である。FIG. 5 is an explanatory view showing a procedure for assembling the steel rebar basket.
【図6】他の組立手順を示す説明図である。FIG. 6 is an explanatory view showing another assembling procedure.
【図7】本発明の第二の実施の形態における鉄骨鉄筋籠
の平断面図である。FIG. 7 is a plan sectional view of a steel frame reinforcing bar according to a second embodiment of the present invention.
1,22 鉄骨鉄筋籠 2,23 H形鋼 3,24 外枠 5,27 横枠 6,26 鉄骨取付台(アングル材) 7,8,29 鉄筋 9 溝 25 取付板 1,22 steel frame reinforced cage 2,23 H-section steel 3,24 outer frame 5,27 horizontal frame 6,26 steel frame mount (angle material) 7,8,29 steel bar 9 groove 25 mounting plate
───────────────────────────────────────────────────── フロントページの続き (58)調査した分野(Int.Cl.7,DB名) E02D 5/20 101 - 102 E04B 2/86 E04G 21/12 ──────────────────────────────────────────────────続 き Continued on the front page (58) Fields surveyed (Int. Cl. 7 , DB name) E02D 5/20 101-102 E04B 2/86 E04G 21/12
Claims (2)
し、その上部に細帯状鋼板からなる複数の横枠を所定間
隔をおいて並列配置し、前記横枠の上面に直交して縦筋
を配列して前記横枠に接合し、さらに、前記縦筋上に横
筋を直交配列して該横筋を該縦筋に接合することにより
一体化した外枠部を組立てた後、 該外枠部の鉄骨交差位置にかぶり調整用の複数の鉄骨取
付台を固定し、 次いで、その上部に鉄骨を設置して前記鉄骨取付台に接
合するとともに、 他の加工台により別途組立てた前記外枠部をその縦筋及
び横筋を内側に配置すべく裏返して前記鉄骨上に接合す
る工程を順に行うことを特徴とする地中壁体の鉄骨鉄筋
籠を組立てる方法。 1. A processing table that is set horizontally above the ground
And a plurality of horizontal frames made of strip-shaped steel plate
Arranged in parallel with a gap, and vertical stripes perpendicular to the upper surface of the horizontal frame
Are arrayed and joined to the horizontal frame, and
By arranging the muscles orthogonally and joining the horizontal muscles to the vertical muscles
After assembling the integrated outer frame, a plurality of steel frames for adjusting fogging are placed at the intersections of the outer frames with the steel frame.
Fix the mounting , and then install a steel frame on top of it to connect to the steel mounting table.
At the same time, the outer frame part separately assembled by another
Turn it over and place it on the steel frame
Steel bars of underground walls characterized by performing the following steps sequentially
How to assemble a basket.
鋼の前後側フランジ部を前記鉄骨取付台に接合したこと
を特徴とする請求項1に記載の地中壁体の鉄骨鉄筋籠を
組立てる方法。 2. The steel column row is made of an H-shaped steel.
The front and rear flanges of steel are joined to the steel mounting base
The steel-framed steel cage of the underground wall according to claim 1, wherein
How to assemble.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30218996A JP3275738B2 (en) | 1996-11-13 | 1996-11-13 | How to assemble underground wall steel reinforced cage |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP30218996A JP3275738B2 (en) | 1996-11-13 | 1996-11-13 | How to assemble underground wall steel reinforced cage |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10140558A JPH10140558A (en) | 1998-05-26 |
JP3275738B2 true JP3275738B2 (en) | 2002-04-22 |
Family
ID=17906012
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP30218996A Expired - Lifetime JP3275738B2 (en) | 1996-11-13 | 1996-11-13 | How to assemble underground wall steel reinforced cage |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3275738B2 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103898900A (en) * | 2014-03-25 | 2014-07-02 | 东南大学 | Concrete-filled steel tube composite structure underground diaphragm wall with pull rods and construction method of underground diaphragm wall |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100519649B1 (en) * | 1998-05-07 | 2005-11-22 | 가부시키가이샤 오바야시구미 | Steel reinforcing basket of underground wall |
JP5504358B2 (en) * | 2013-01-22 | 2014-05-28 | 株式会社大林組 | Rebar cage, rebar cage assembly method |
CN103603368B (en) * | 2013-11-26 | 2015-11-18 | 中铁第四勘察设计院集团有限公司 | Diaphragm wall meets the inverse construction method done of underground utilities |
CN103924581B (en) * | 2014-03-25 | 2015-10-07 | 东南大学 | Prefabricated concrete-filled steel tube combining structure diaphragm wall and construction method thereof |
JP6688612B2 (en) * | 2015-12-24 | 2020-04-28 | 株式会社竹中工務店 | Pile structure and method of assembling piles |
JP6361007B1 (en) * | 2018-01-24 | 2018-07-25 | 有限会社久美川鉄工所 | Strong underground, ground, reinforcement, replenishment |
-
1996
- 1996-11-13 JP JP30218996A patent/JP3275738B2/en not_active Expired - Lifetime
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103898900A (en) * | 2014-03-25 | 2014-07-02 | 东南大学 | Concrete-filled steel tube composite structure underground diaphragm wall with pull rods and construction method of underground diaphragm wall |
CN103898900B (en) * | 2014-03-25 | 2016-01-06 | 东南大学 | Band pull bar steel tube-concrete composite structure diaphragm wall and construction method thereof |
Also Published As
Publication number | Publication date |
---|---|
JPH10140558A (en) | 1998-05-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3275738B2 (en) | How to assemble underground wall steel reinforced cage | |
JP3690437B2 (en) | Seismic reinforcement structure for existing buildings | |
JP3175586B2 (en) | Column and pile connection method | |
JP3564669B2 (en) | Reinforcement spacer and foundation pile method | |
JP3084654B2 (en) | Construction foundation, foundation structure using the same, and construction method thereof | |
JP3185129B2 (en) | Column-integrated column base fixed foundation structure and its construction method | |
KR100519649B1 (en) | Steel reinforcing basket of underground wall | |
JPH08109631A (en) | Underground wall | |
JP4003444B2 (en) | Support method | |
JP3109038B2 (en) | Underground skeleton structure and construction method | |
JP2000034732A (en) | Steel column mounting hardware, steel column mounting structure and steel column building method | |
KR101847036B1 (en) | Precast concrete assembled retaining wall block | |
JP2900840B2 (en) | How to build underground structures | |
JP6368758B2 (en) | Foundation structure and foundation structure | |
JP3246321B2 (en) | Column and pile joint structure | |
JPH09324418A (en) | Foundation pile structure and construction method therefor | |
JPH0841897A (en) | Foundation for building and construction method therefor | |
JP3319709B2 (en) | Construction method of prestressed concrete steel beam | |
JP3060195B2 (en) | Construction method of steel basement reinforced concrete continuous underground wall | |
JP2842149B2 (en) | Underground structure | |
JPH03199529A (en) | Mat foundation using steel structure | |
JP3142519B2 (en) | Formwork for building foundation | |
JP3721508B2 (en) | building | |
JP2959436B2 (en) | How to build underground structures | |
JP2940451B2 (en) | How to build underground structures |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080208 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090208 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100208 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20100208 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110208 Year of fee payment: 9 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20110208 Year of fee payment: 9 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20120208 Year of fee payment: 10 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130208 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20130208 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20140208 Year of fee payment: 12 |
|
EXPY | Cancellation because of completion of term |