JPH02304197A - Shaft jointly excavating type shield excavator - Google Patents
Shaft jointly excavating type shield excavatorInfo
- Publication number
- JPH02304197A JPH02304197A JP12275089A JP12275089A JPH02304197A JP H02304197 A JPH02304197 A JP H02304197A JP 12275089 A JP12275089 A JP 12275089A JP 12275089 A JP12275089 A JP 12275089A JP H02304197 A JPH02304197 A JP H02304197A
- Authority
- JP
- Japan
- Prior art keywords
- frame
- tunnel
- cutter
- shaft
- excavated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009412 basement excavation Methods 0.000 claims abstract description 16
- 238000010276 construction Methods 0.000 abstract description 18
- 238000000034 method Methods 0.000 abstract description 13
- 230000000717 retained effect Effects 0.000 abstract 1
- 230000005641 tunneling Effects 0.000 description 7
- 230000000694 effects Effects 0.000 description 3
- 238000007796 conventional method Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Landscapes
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
Description
【発明の詳細な説明】
[産業上の利用分野]
本発明は1台の掘進機で立坑とトンネルの掘削を行える
ようにした立坑掘削併用型シールド掘進機に関するもの
である。DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a shaft excavation combined type shield tunneling machine that is capable of excavating a shaft and a tunnel using one tunneling machine.
[従来の技術]
トンネルの施工を行う場合、従来は、第5図に一例を示
す如く、立坑aを開削又はケーソン工法により施工した
後、上記立坑a内にシールド掘進pcを搬入し、該シー
ルド掘進機Cによ゛リドンネルbを掘削するようにして
いる。[Prior Art] When constructing a tunnel, conventionally, as shown in an example in FIG. An excavator C is used to excavate a redundnel b.
[発明が解決しようとする課題]
ところが、上記従来方式の場合、立坑aが大深度である
と、シールド掘進機Cの投入工事が大変であり、又、立
坑aの掘削とトンネルbの掘削のために別々の機械を用
意しなければならず費用も嵩む問題があった。[Problems to be Solved by the Invention] However, in the case of the above-mentioned conventional method, if the shaft a is deep, it is difficult to insert the shield tunneling machine C, and the excavation of the shaft a and the tunnel b are difficult. There was a problem in that separate machines had to be prepared for this purpose, which increased costs.
そこで、本発明は、立坑掘削から最終トンネル掘削まで
を1台の機械で併用して行うことができるような立坑掘
削併用型シールド掘進機を提供しようとするものである
。SUMMARY OF THE INVENTION Therefore, the present invention aims to provide a shield tunneling machine that can be used for both shaft excavation and tunnel excavation, which can be used in combination from shaft excavation to final tunnel excavation with one machine.
[課題を解決するための手段]
本発明は、上記課題を解決するために、外側フレームと
中間フレームと内側フレームとを互に軸心方向べ摺動自
在としてぞれぞれ切り離し可能な3重構造として備え、
且つ上記内側フレームに、径方向へ伸縮自在なカッター
スポークを有するカッターを回転自在に支持させてなる
構成とする。[Means for Solving the Problems] In order to solve the above-mentioned problems, the present invention provides a three-fold structure in which an outer frame, an intermediate frame, and an inner frame are slidable in the axial direction and can be separated from each other. Provided as a structure,
Further, the inner frame rotatably supports a cutter having cutter spokes that are expandable and retractable in the radial direction.
[作 用]
トンネル施工を行う場合、先ず、ケーソン二り法により
所定深さまで立坑を施工し、次に、外側フレームを切り
離して推進工法により曲線状の1〜ンネルを施工し、更
に、中間フレームを切り離してシールド工法により内側
ル−ムを掘進させて最終トンネルを施工する。[Operation] When constructing a tunnel, first construct a vertical shaft to a specified depth using the caisson double method, then cut off the outer frame and construct a curved tunnel using the propulsion method, and then remove the intermediate frame. The final tunnel will be constructed by separating the tunnel and excavating the inner room using the shield method.
[実 施 例] 以下、本発明の実施例を図面を参照して説明する。[Example] Embodiments of the present invention will be described below with reference to the drawings.
第1図に示す如く、本発明の立坑掘削併用型シールド掘
進機は、立坑施工時のシールドフレームとなる筒状の外
側フレーム1と、最終トンネル施工時のシールドフレー
ムとなるリング状の内側フレーム3と、立坑と最終トン
ネルとの間の曲線状のトンネル施工時のシールドフレー
ムとなるリング状の中間フレーム2とを、シール部4J
4を介在させてそれぞれ軸心方向へ摺動自在に重合させ
た3重フレーム構造としてあり、且つ上記外側フレーム
1には中間フレーム2の後端面へ向(ブて張り出す荷重
受構造体5を設(プて、該荷重受構造体5と中間フレー
ム2の後端面とをポル1〜又はピンにより@脱可能に固
定すると共に、上記中間フレーム2には内側フレーム3
の後端面へ向けて張り出す荷重受構造体6を設けで、該
仙重受構造体6と内側フレーム3の後端面とをボルト又
はピンにより着脱可能に固定し、内側フレーム3に作用
する前面側からのスラスト荷重を順次中間フレーム2、
外側フレーム1へと伝えられるようにする。As shown in FIG. 1, the shaft excavation type shield tunneling machine of the present invention includes a cylindrical outer frame 1 that serves as a shield frame during shaft construction, and a ring-shaped inner frame 3 that serves as a shield frame during final tunnel construction. and a ring-shaped intermediate frame 2 that will serve as a shield frame during construction of a curved tunnel between the shaft and the final tunnel.
The outer frame 1 has a load receiving structure 5 that extends toward the rear end surface of the intermediate frame 2. The load-receiving structure 5 and the rear end surface of the intermediate frame 2 are removably fixed to each other by pins or pins, and the inner frame 3 is attached to the intermediate frame 2.
A load receiving structure 6 extending toward the rear end surface is provided, and the load receiving structure 6 and the rear end surface of the inner frame 3 are removably fixed with bolts or pins, and the front surface acting on the inner frame 3 is provided. The thrust load from the side is sequentially transferred to the intermediate frame 2,
so that it can be transmitted to the outer frame 1.
上記外側フレーム1の内側には、曲線状のトンネル施工
時に用いる推進ジヤツキ7と曲線状のトンネル施工部の
セグメント組立装置8を装備させ、又、上記内側フレー
ム1には、該内側フレーム1の前面部に配したカッター
9をカッター軸受10及びカッターシール11を介して
回転自在に支持させると共に、上記カッター9を駆動覆
るだめのカッター駆動用モータ12を設置する。上記カ
ッター9は内側フレーム3と対応する外径を有し、且つ
ジ(/ツキ等の伸縮装置23の操作により外側フレーム
1の外径と対応する位置まで外周部から放射状に張り出
すことができるようにしたカッタースポーク13を有す
る崩成としである。更に上記内側フレーム3の後端面外
周部には、最終トンネル掘削時に分割状態で搬入して組
み立てるシールドジヤツキ14を装備したガーダ一部1
5とセグメント組立部となるゾール部16を取り付けら
れるようにする。The inner side of the outer frame 1 is equipped with a propulsion jack 7 used when constructing a curved tunnel and a segment assembly device 8 for the curved tunnel construction section. A cutter 9 disposed in a section is rotatably supported via a cutter bearing 10 and a cutter seal 11, and a cutter driving motor 12 is installed to drive the cutter 9. The cutter 9 has an outer diameter corresponding to that of the inner frame 3, and can be extended radially from the outer periphery to a position corresponding to the outer diameter of the outer frame 1 by operating a telescopic device 23 such as a lever. Furthermore, on the outer periphery of the rear end surface of the inner frame 3, there is a girder part 1 equipped with a shield jack 14, which is carried in the divided state and assembled at the time of final tunnel excavation.
5 and the sole part 16 which becomes the segment assembly part can be attached.
トンネル施工を行う場合、先ず、カッタースポーク13
をカッター9の外周より外側フレーム1の外径と対応す
る位置まで伸ばした状態にしておき、この状態で、第2
図に示す如く、掘進機を上記カッター9が下向きになる
ようにして配置し、カッター9の駆動により掘削を行い
ながらケーソン工法により所定深さ位置まで立坑17を
施工する。この際、推進力は立坑17の上部に設置した
元押し装置(図示せず〉により外側フレーム1に与えら
れる。When constructing a tunnel, first cutter spoke 13
is extended from the outer periphery of the cutter 9 to a position corresponding to the outer diameter of the outer frame 1, and in this state, the second
As shown in the figure, the excavator is placed so that the cutter 9 faces downward, and while excavating by driving the cutter 9, the shaft 17 is constructed to a predetermined depth using the caisson construction method. At this time, the propulsion force is applied to the outer frame 1 by a source pushing device (not shown) installed at the top of the shaft 17.
次に、掘進機は縦から横へ方向転換するために曲線施工
に入るが、その前に、外側フレーム1の外径と対応する
位置まで伸ばしてあいたカッタースポーク13を、伸縮
装置23の作動により中間フレーム2の外径と対応する
位置まで収縮させる。又、この時点で、外側フレーム1
の荷重受構造体5と中間フレーム2どの機械的結合を解
除し、外側フレーム1と中間フレーム2の縁を切る。こ
の状態において、推進工法により曲線状のトンネル18
を施工する。すなわち、外側フレーム1内にてセグメン
ト組立装置8により曲線施工用のテーパーセグメント2
0を組み立てて中間フレーム2の後端面上にセットする
。Next, the excavator starts a curved construction in order to change direction from vertical to horizontal, but before that, the cutter spoke 13, which has been extended to a position corresponding to the outer diameter of the outer frame 1, is moved by the operation of the expansion device 23. It is shrunk to a position corresponding to the outer diameter of the intermediate frame 2. Also, at this point, the outer frame 1
The mechanical connection between the load receiving structure 5 and the intermediate frame 2 is released, and the edge between the outer frame 1 and the intermediate frame 2 is cut. In this state, a curved tunnel 18 is formed using the propulsion method.
construction. That is, the tapered segment 2 for curved construction is assembled by the segment assembly device 8 within the outer frame 1.
0 is assembled and set on the rear end surface of the intermediate frame 2.
しかる後、推進ジヤツキ7により上記テーパーセグメン
ト20に押し力を与えながらカッター9で掘削を行う。Thereafter, excavation is performed with the cutter 9 while applying a pushing force to the tapered segment 20 with the propulsion jack 7.
この場合、外側フレーム1と中間フレーム2とは、上述
した如く縁が切っであるため、中間フレーム2はカッタ
ー9と共に外側フレーム1から押し出される。テーパー
セグメント20の1リング分の長さが押し終わると、上
記テーパーセグメント20の後部に次のテーパーセグメ
ント20を組み立てて固定し、同様に中−〇 −
問フレーム2を推進させる。かかる作業を所定回数繰り
返すことにより、第3図に示す如く曲線状の1〜ンネル
18が施工される。In this case, since the outer frame 1 and the intermediate frame 2 have a cut edge as described above, the intermediate frame 2 is pushed out from the outer frame 1 together with the cutter 9. When the length of one ring of the tapered segment 20 has been pushed, the next tapered segment 20 is assembled and fixed at the rear of the tapered segment 20, and the medium frame 2 is similarly propelled. By repeating this operation a predetermined number of times, curved channels 1 to 18 are constructed as shown in FIG.
方向変換が完了した時点で、内側フレーム3の後端面外
周部に、分割して搬入したガーダ一部15とテール部1
6を組み立てて取り付け、本来のシールド形態とする。When the direction change is completed, the girder part 15 and the tail part 1, which were carried in parts, are placed on the outer periphery of the rear end surface of the inner frame 3.
6 and attach it to the original shield form.
この際、カッタースポーク13は内側フレーム3の外径
と対応するように縮めた状態とし、更に中間フレーム2
と内側フレーム3の機械的結合を解除し、中間フレーム
2と内側フレーム3の縁を切る。かかる状態において、
内側フレーム3をシールド工法により推進させ、第4図
に示す如く、順次セグメント21を据え(qけて行くこ
とによりトンネル19を施工する。この場合、第4図の
二点鎖線で示す如く、既に施工済みの曲線状のトンネル
18内に、予め推進反力受構造体22を架設し、該構造
体22にシールドジヤツキ14にJ:る反力を受けさせ
るようにして内側フレーム3を掘進させながらセグメン
ト21を順次据え付けて行き、1〜ンネル19の施工が
完了した後、上記構造体22を撤去する。At this time, the cutter spokes 13 are contracted to correspond to the outer diameter of the inner frame 3, and
The mechanical connection between the intermediate frame 2 and the inner frame 3 is released, and the edge between the intermediate frame 2 and the inner frame 3 is cut. In such a situation,
The tunnel 19 is constructed by advancing the inner frame 3 by the shield construction method and sequentially installing the segments 21 as shown in FIG. A propulsion reaction force receiving structure 22 is installed in advance in the curved tunnel 18 that has already been constructed, and the inner frame 3 is excavated so that the structure 22 receives the reaction force of the shield jack 14. The segments 21 are installed one after another, and after the construction of channels 1 to 19 is completed, the structure 22 is removed.
このように、外側フレーム1と中間フレーム2を工法毎
に切り離して行くことにより、1台の掘進機でトンネル
の施工を簡単に行うことができる。In this way, by separating the outer frame 1 and the intermediate frame 2 for each construction method, it is possible to easily construct a tunnel with one excavator.
なお、上記実施例においては排土方式について言及して
いないが、排土方式としては流体輸送方式でもコンベヤ
排土方式でもよく、又、シールド機種としては泥水式や
土圧式等を採用することができ、更に各フレーム間の結
合及び切り離しには図示し説明した以外の方式を採用し
てもよく、その池水発明の要旨を逸脱しない範囲内にお
いて種々変更を加え得ることは勿論である。In addition, although the earth removal method is not mentioned in the above embodiment, the earth removal method may be a fluid transport method or a conveyor earth removal method, and as a shield model, a mud water type, an earth pressure type, etc. may be adopted. Moreover, methods other than those shown and described may be used for connecting and separating the frames, and it goes without saying that various changes can be made without departing from the gist of the invention.
[発明の効果]
以上述べた如く、本発明の立坑掘削併用型シールド掘進
機によれば、3重構造とした外側フレームと中間フレー
ムと内側フレームとを掘進に伴い順次切り離すことがで
きるようにしであるので、立坑施工から最終トンネル施
工に伴う掘削作業を一連の作業として行うことができ、
これにより、従来の如く立坑への掘進機の投入工事を不
要にでき、特に、大深度、大口径立坑の場合に工期の短
縮化及び経済的効果が向上し、又、立坑と1〜ンネルの
掘削のために別々の機械を用意する必要がないことから
、機械全体の製作費を従来に比して削減づることができ
る、という優れた効果を発揮する。[Effects of the Invention] As described above, according to the shield excavator combined with shaft excavation of the present invention, the triple-structured outer frame, intermediate frame, and inner frame can be successively separated as the excavation progresses. Therefore, the excavation work from shaft construction to final tunnel construction can be performed as a series of operations.
This eliminates the need for the conventional work of inserting an excavator into the shaft, shortens the construction period and improves the economic effect, especially in the case of deep, large-diameter shafts. Since there is no need to prepare a separate machine for excavation, the manufacturing cost of the entire machine can be reduced compared to conventional methods, which is an excellent effect.
第1図は本発明の立坑掘削併用型シールド掘進機の一実
施例の概要を示す切断側面図、第2図乃至第4図は本発
明のシールド掘進機によりトンネル施工を行っている状
態の作業要領を示す概略図、第5図は従来の1〜ンネル
施工の作業要領を示す概略図でおる。
1・・・外側フレーム、2・・・中間フレーム、3・・
・内側フレーム、5,6・・・荷重受構造体、7・・・
推進ジヤツキ、8・・・セグメント組立装置、9・・・
カッター、12・・・カッター駆動用モータ、13・・
・カッタースポーク、23・・・伸縮装置。FIG. 1 is a cutaway side view showing an outline of an embodiment of the shield tunneling machine combined with vertical shaft excavation of the present invention, and FIGS. 2 to 4 show tunnel construction work using the shield tunneling machine of the present invention. FIG. 5 is a schematic diagram showing the procedure for conventional tunnel construction. 1... Outer frame, 2... Middle frame, 3...
・Inner frame, 5, 6...Load receiving structure, 7...
Propulsion jack, 8... Segment assembly device, 9...
Cutter, 12... Cutter drive motor, 13...
・Cutter spoke, 23...Expansion device.
Claims (1)
互に軸心方向へ摺動自在としてそれぞれ切り離し可能な
3重構造として備え、且つ上記内側フレームに、径方向
へ伸縮自在なカッタースポークを有するカッターを回転
自在に支持させてなる構成を有することを特徴とする立
坑掘削併用型シールド掘進機。(1) A cutter having a triple structure in which an outer frame, an intermediate frame, and an inner frame are slidable in the axial direction and can be separated from each other, and the inner frame has cutter spokes that can be freely expanded and contracted in the radial direction. What is claimed is: 1. A shield excavator for combined shaft excavation, characterized in that it has a configuration in which a shaft is rotatably supported.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP12275089A JP2676548B2 (en) | 1989-05-18 | 1989-05-18 | Vertical shaft excavator combined shield machine |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP12275089A JP2676548B2 (en) | 1989-05-18 | 1989-05-18 | Vertical shaft excavator combined shield machine |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH02304197A true JPH02304197A (en) | 1990-12-17 |
JP2676548B2 JP2676548B2 (en) | 1997-11-17 |
Family
ID=14843675
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP12275089A Expired - Lifetime JP2676548B2 (en) | 1989-05-18 | 1989-05-18 | Vertical shaft excavator combined shield machine |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP2676548B2 (en) |
-
1989
- 1989-05-18 JP JP12275089A patent/JP2676548B2/en not_active Expired - Lifetime
Also Published As
Publication number | Publication date |
---|---|
JP2676548B2 (en) | 1997-11-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3483225B2 (en) | Tunnel excavator | |
US4618298A (en) | Method for constructing an enlarged tunnel and apparatus for forming the same | |
US4530621A (en) | Shield driving process for enlargement | |
JPH03180690A (en) | Tunnel excavator | |
JPH02304197A (en) | Shaft jointly excavating type shield excavator | |
JP3758722B2 (en) | Tunnel excavator | |
JPH0925789A (en) | Tunnel excavator and tunnel excavating method | |
JPH1122367A (en) | Connecting method of tunnel by use of different diameter-shielding excavator | |
JPS62296097A (en) | Annular shield construction method, annular shield and annular segment | |
JP3219746B2 (en) | Existing tunnel removal method and shield tunneling machine for removal of existing tunnel | |
JP2686487B2 (en) | Shield excavator | |
JP3375299B2 (en) | Telescopic spoke device for shield machine | |
JP2693904B2 (en) | Underground drilling method | |
JP3093437B2 (en) | Shield machine | |
JPH047493A (en) | Tunnel widening method and device | |
JPH10292786A (en) | Tunnel boring machine and method therefor | |
JPH0842281A (en) | Double drum type shield excavator and simultaneous excavation method thereof | |
JPS62202200A (en) | Method of lining shield tunnel | |
JPS6342075B2 (en) | ||
JPH05179886A (en) | Tunnel branching method by shield excavator and cutter plate for excavator | |
JPS6216310B2 (en) | ||
JPH10176479A (en) | Main and sub shield machine and departing method for sub-shield machine | |
JP3217073B2 (en) | Expanding method of existing buried pipe | |
JP2003293683A (en) | Excavating device | |
JPH0366897A (en) | Shield excavator |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080725 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080725 Year of fee payment: 11 |
|
S531 | Written request for registration of change of domicile |
Free format text: JAPANESE INTERMEDIATE CODE: R313531 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080725 Year of fee payment: 11 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080725 Year of fee payment: 11 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090725 Year of fee payment: 12 |
|
EXPY | Cancellation because of completion of term |