Method and device for placing of steel bar cage for deep foundation

Info

Publication number
JPH09177070A
JPH09177070A JP34060195A JP34060195A JPH09177070A JP H09177070 A JPH09177070 A JP H09177070A JP 34060195 A JP34060195 A JP 34060195A JP 34060195 A JP34060195 A JP 34060195A JP H09177070 A JPH09177070 A JP H09177070A
Authority
JP
Japan
Prior art keywords
support ring
cage
deep foundation
rebar cage
shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP34060195A
Other languages
Japanese (ja)
Inventor
Jinichi Taguchi
甚一 田口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SAKATA CONSTRUCTION CO Ltd
SAKATA KENSETSU KK
Original Assignee
SAKATA CONSTRUCTION CO Ltd
SAKATA KENSETSU KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SAKATA CONSTRUCTION CO Ltd, SAKATA KENSETSU KK filed Critical SAKATA CONSTRUCTION CO Ltd
Priority to JP34060195A priority Critical patent/JPH09177070A/en
Publication of JPH09177070A publication Critical patent/JPH09177070A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

PROBLEM TO BE SOLVED: To provide a method and device for placing a steel bar cage economically and effectively, with which operators are secured with safe and good working environment. SOLUTION: A derric-shaped provisional frame 2 is erected in the on-the- ground part of the mouth of a deep foundation pit 1. At the pit mouth, a plurality of chain wheel winches 3 capable of simultaneous operation are installed, and a support ring 4 is held suspendedly. On the ground, vertical steel bars 12 to constitute a cage 11 are attached one by one to this support ring 4, and hoops 13 are welded to the periphery of these vertical bars 12 one by one. In this manner the cage 11 is completed from below with necessary rigidity ensured, and the completed part is hung down together with the support ring 4 bit by bit into the deep foundation pit 1 with the aid of the chain wheel winch 3.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本願発明は、深礎工法による
深礎杭あるいは立坑の構築過程における鉄筋篭の建込み
方法およびその方法に用いる建込み装置に関するもので
ある。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a rebar cage in a process of constructing a deep foundation pile or a shaft by a deep foundation method and a construction device used for the method.

【0002】[0002]

【従来の技術】深礎用鉄筋篭の組立方法としては、深礎
の立坑内に人間が入って鉄筋作業足場を構築し、地上部
から坑内に鉄筋を吊り込み、人力で坑内組立てを行う方
法が一般的である。
2. Description of the Related Art As a method of assembling a rebar cage for deep foundations, a person enters the shaft of the deep foundation to construct a rebar work scaffold, suspends the rebar from the aboveground portion, and manually assembles the rebar. Is common.

【0003】また、深礎の立坑が比較的小口径で、大型
クレーン車が施工中の深礎に接近できる条件では、地上
で水平方向に鉄筋篭を組み立てた後、大型クレーン車に
よって鉄筋篭を吊り上げ、立坑内に吊り込む場合もあ
る。
Under the condition that the vertical shaft of the deep foundation has a relatively small diameter and the large crane truck can approach the deep foundation under construction, after the reinforcing cage is assembled horizontally on the ground, the reinforcing cage is constructed by the large crane truck. In some cases, it may be lifted or suspended in the shaft.

【0004】[0004]

【発明が解決しようとする課題】鉄筋篭を大型クレーン
車で吊り込む方法は、スペース等に関する制約を受ける
他、深礎の規模との関係で経済性の問題もあり、適用範
囲が限定される。
The method of suspending a reinforced basket with a large crane car is limited in its application range due to restrictions on space and the like, as well as economic problems due to the size of the deep foundation. .

【0005】一方、立坑内で人力によって鉄筋篭を組み
立てる方法は、作業者の安全確保や作業環境、作業効率
の面で多くの課題がある。
On the other hand, the method of manually assembling the rebar cage in the vertical shaft has many problems in terms of ensuring worker safety, working environment, and working efficiency.

【0006】すなわち、作業者の安全確保に関しては、
深礎工事は鉛直方向の工事となり、全作業工程が上下の
位置関係にあり、作業員や物の墜落、落下の危険度が高
く、安全防護施設の設置も難しい。
[0006] That is, regarding the safety of the worker,
The deep foundation work is vertical work, and all the work processes are in a vertical relationship, so there is a high risk of workers and objects falling or falling, and it is difficult to install a safety protection facility.

【0007】さらに、作業環境に関して、作業位置が立
坑の底部の場合、換気、照明、気温、湿気、じん肺被害
等に関し、地上作業に比べて悪環境となっている。
Further, regarding the work environment, when the work position is at the bottom of the shaft, the environment is more adverse than the ground work in terms of ventilation, lighting, temperature, humidity, pneumoconiosis damage and the like.

【0008】本願発明は、従来の深礎工事における鉄筋
篭の組立ておよび建込みに関する課題を解決し、経済
的、効率的で、かつ作業者の安全、良好な作業環境が確
保できる深礎用鉄筋篭の建込み方法および建込み装置を
提供することを目的としたものである。
The present invention solves the problems relating to the assembly and installation of the rebar cage in the conventional deep foundation work, and is economical and efficient, and the safety of the worker and the good working environment can be secured. The purpose of the present invention is to provide a cage building method and a cage building apparatus.

【0009】[0009]

【課題を解決するための手段】本願発明の深礎用鉄筋篭
の建込み方法は、深礎用立坑の坑口地上部に仮設架台
と、地上部で組み立てられて行く鉄筋篭を下方から支え
る支持リングと、この支持リングを仮設架台に対し昇降
可能に支持する吊り装置とを設置し、支持リングに、順
次、鉄筋篭を構成する縦筋(主筋)を設置して行き、そ
の後、縦筋を取り巻く帯筋(フープ筋)を縦筋と結合さ
せ、順次、下方より鉄筋篭としての剛性を確保し、吊り
装置により支持リングを深礎用立坑内に吊り降ろして行
くことで、地上部で組み立てた鉄筋篭を立坑内に設置す
ることを特徴とするものである。
The method for constructing the deep foundation rebar cage according to the present invention is a support for supporting from below a temporary mount and a rebar cage to be assembled on the ground section at the ground section above the entrance of the shaft for deep foundation. A ring and a suspension device that supports this support ring so that it can be raised and lowered with respect to a temporary mount are installed, and the vertical bars (main bars) that make up the reinforcing bar cage are sequentially installed on the support ring. The surrounding stirrup (hoop streak) is connected to the vertical stirrup, the rigidity of the rebar cage is secured from below, and the support ring is suspended from the bottom by the suspension device to assemble it on the ground. It is characterized by installing a rebar cage in the vertical shaft.

【0010】吊り装置としては、例えばチェーンブロッ
ク、チェーンホイルウインチ等があり、坑口の周辺に複
数配置したものを、同期運転することで、支持リングの
水平を保った状態で昇降させることができる。この他、
吊り装置としては、センターホールジャッキ、ウインチ
等でもよい。
As the suspension device, there are, for example, a chain block, a chain wheel winch, and the like. A plurality of suspension devices arranged around the wellhead can be moved up and down by synchronously operating the support ring while keeping the support ring horizontal. In addition,
The hanging device may be a center hole jack, a winch, or the like.

【0011】深礎は場合によっては数十m〜百数十mに
なる場合もあり、下端のみの支持では鉄筋、および鉄筋
篭が容易に変形してしまう場合もある。
In some cases, the deep foundation may have a length of several tens m to a hundred and several tens m, and the supporting of only the lower end may easily deform the reinforcing bar and the reinforcing bar cage.

【0012】本願の請求項2は、下部の支持リング位置
での支持に加え、鉄筋篭の深さ方向中間部も吊り支持す
る場合を限定したものである。また、請求項3は鉄筋篭
の吊り降ろし作業の進行に伴い、支持リングを上方に盛
り換えながら、鉄筋篭の組立ておよび吊り降ろしを行う
場合を限定したものである。
According to claim 2 of the present application, in addition to the support at the lower support ring position, the case of suspending and supporting the intermediate portion in the depth direction of the reinforcing bar basket is also limited. Further, claim 3 limits the case where the rebar cage is assembled and hoisted while the support ring is being relocated upward as the hoisting work of the rebar cage is advanced.

【0013】このようにして、鉄筋および鉄筋篭が長尺
となる場合に対処させることができる。
In this way, it is possible to deal with the case where the reinforcing bar and the reinforcing bar cage are long.

【0014】なお、鉄筋篭が内外2重、あるいはそれ以
上となる場合には、最初に外篭を施工し、次に内篭を施
工するようにすればよい。
When the number of rebar cages is two or more, the outer cage may be constructed first, and then the inner cage may be constructed.

【0015】本願発明の深礎用鉄筋篭の建込み装置は、
上記建込み方法に用いるための装置に係り、深礎用立坑
の坑口地上部の仮設架台と、地上部で組み立てられて行
く鉄筋篭を下方から支える支持リングと、支持リングを
仮設架台に対し昇降可能に支持する吊り装置とからなる
ことを特徴とするものである。
The construction device for the deep foundation rebar cage of the present invention is as follows:
With regard to the device used for the above-mentioned construction method, a temporary stand on the ground part of the well entrance shaft of the deep foundation shaft, a support ring that supports the reinforcing bar cage assembled from the bottom part from below, and a support ring are moved up and down with respect to the temporary mount. It is characterized in that it comprises a suspending device that supports it as much as possible.

【0016】請求項5は、この吊り装置が、互いに同期
運転が可能な複数のチェーンホイルウインチからなる場
合を限定したものである。
According to a fifth aspect of the present invention, the case where the suspension device comprises a plurality of chain wheel winches that can be operated in synchronization with each other is limited.

【0017】[0017]

【発明の実施の形態】図1〜図3は、本願発明の深礎用
鉄筋篭の建込み方法および建込み装置に関する一実施形
態を示したものである。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIGS. 1 to 3 show an embodiment of a method and apparatus for constructing a deep foundation rebar basket according to the present invention.

【0018】建込み装置は、深礎立坑1の坑口地上部に
構築したやぐら形の仮設架台2と、坑口を取り巻くよう
に配置した複数のチェーンホイルウインチ3、およびこ
れらのチェーンホールウインチ3によって水平に吊り支
持される支持リング4とからなる。
The erection device comprises a temporary tower 2 in the shape of a tower constructed on the ground above the pit of a deep foundation shaft 1, a plurality of chain wheel winches 3 arranged so as to surround the pit, and a chain hole winch 3 for horizontal movement. And a support ring 4 which is suspended and supported by the.

【0019】なお、図中、5は深礎立坑1の壁面に設置
されたライナープレート、6はチェーンホールウインチ
用リング鋼台、8は縦筋12を支持リング4に固定する
ための縦筋止め金具、9はチェーンホールウインチ3の
チェーン7を支持リング4に連結するためのチャッキン
グ装置、10は地上部の下部作業台を示す。
In the figure, 5 is a liner plate installed on the wall surface of the deep foundation shaft 1, 6 is a ring steel stand for a chain hole winch, and 8 is a vertical bar stopper for fixing the vertical bar 12 to the support ring 4. A metal fitting, 9 is a chucking device for connecting the chain 7 of the chain hole winch 3 to the support ring 4, and 10 is a lower workbench on the ground.

【0020】上記装置を用いた施工手順の一例を述べる
と以下の通りである。
An example of the construction procedure using the above apparatus is as follows.

【0021】 掘削が完了した深礎立坑1の坑口地上
部に仮設架台2を構築し、地上部分に吊り装置としての
複数のチェーンホイルウインチ3を設置する。
A temporary pedestal 2 is constructed on the aboveground part of the well foundation shaft 1 where the excavation is completed, and a plurality of chain wheel winches 3 as suspension devices are installed on the aboveground part.

【0022】 鉄筋篭支持リング4を設置し、チェー
ン7を介してチェーンホイルウインチ3で吊り支持す
る。なお、この例では吊り装置として、立坑の坑口地上
部を取り巻くように配置した複数のチェーンホイルウイ
ンチ3を用いており、これらを同期運転することで、鉄
筋篭11を支持する支持リング4が水平を保った状態で
昇降できるようになっている。
A reinforcing bar cage support ring 4 is installed, and is suspended and supported by a chain wheel winch 3 via a chain 7. In addition, in this example, a plurality of chain wheel winches 3 arranged so as to surround the aboveground part of the shaft of the vertical shaft are used as a suspension device, and the supporting ring 4 supporting the rebar cage 11 is horizontally operated by operating them in synchronization. It is possible to move up and down while maintaining.

【0023】 主筋としての縦筋12をクレーン等で
1本ずつ吊り込み、支持リング4に装着する。なお、安
定のために仮設架台2の上部にもリングを設け、鉄筋を
上下2箇所以上で支持することもできる。
The vertical bars 12 as main bars are hung one by one with a crane or the like and attached to the support ring 4. For stability, a ring may be provided on the upper part of the temporary pedestal 2 to support the reinforcing bar at two or more upper and lower positions.

【0024】 筒状に配置した縦筋12の周りに帯筋
13を配筋し、溶接等により結合させる。
The stirrup 13 is arranged around the vertical streak 12 arranged in a tubular shape, and is joined by welding or the like.

【0025】 帯筋13を結合して鉄筋篭11として
の剛性を確保した部分を、吊り装置としてのチェーンホ
イルウインチ3の操作により深礎立坑1内に沈降させて
行く。
A portion of the reinforcing bar cage 11 that is secured by connecting the stirrups 13 is settled into the deep pit 1 by operating the chain wheel winch 3 as a suspension device.

【0026】 続いて、上段部分において、縦筋12
の周囲に帯筋13を配筋し、、の作業を繰り返す。
なお、深礎が深くなる場合には、上側に縦筋12を継ぎ
足す。また、鉄筋篭11が長尺となり、下端部の支持で
は変位が大きくなる場合には、最下段にある支持リング
4を鉄筋篭1中段に盛り替える。
Subsequently, in the upper part, the vertical stripes 12
Arrange the stirrups 13 around and repeat the work of.
When the deep foundation becomes deeper, the vertical streak 12 is added to the upper side. If the reinforcing bar cage 11 is long and the displacement at the lower end is large, the support ring 4 at the bottom is replaced with the middle reinforcing bar 1.

【0027】なお、この盛り替え作業については、例え
ば既に結合した部分の帯筋13下に仮支持用の補助水平
部材等を挿入した後、吊り装置の荷重を解放して鉄筋篭
11の荷重を補助水平部材に預け、下段にあった支持リ
ング4を中段部分に移行して鉄筋篭11に装着し、再び
地上のチェーンホイルウインチ3に荷重を移行するとい
った方法で盛り替えを行うことができる。荷重の移行
後、帯筋13下の補助水平部材は撤去する。
For this refilling work, for example, after inserting an auxiliary horizontal member for temporary support under the stirrup 13 at the already joined portion, the load of the suspension device is released and the load of the rebar cage 11 is released. It is possible to carry out refilling by depositing it on an auxiliary horizontal member, transferring the lower support ring 4 to the middle part, mounting it on the rebar cage 11, and transferring the load to the chain wheel winch 3 on the ground again. After the transfer of the load, the auxiliary horizontal member below the stirrup 13 is removed.

【0028】 盛り替えが完了したら、再び、の
作業を繰り返す。
When the refilling is completed, the work of is repeated again.

【0029】 鉄筋篭11の組立て、建込みが完了し
た後、チェーンホイルウインチ3、支持リング4および
仮設架台2を撤去する。
After the rebar cage 11 has been assembled and installed, the chain wheel winch 3, the support ring 4 and the temporary mount 2 are removed.

【0030】[0030]

【発明の効果】 比較的簡易な小型の設備で経済的、効率的な施工が
可能であり、スペース等による制約も少なく、適用範囲
が広い。
[Effects of the Invention] Economical and efficient construction is possible with relatively simple and small equipment, there are few restrictions due to space, etc., and the applicable range is wide.

【0031】 鉄筋篭の組立て作業を、順次、鉄筋篭
を立坑内に沈降させながら、地上部で行うことができる
ため、作業者の安全、良好な作業環境が確保できる。
Since the work for assembling the rebar cages can be performed on the above-ground portion while the rebar cages are successively settled in the shaft, it is possible to secure the safety of the operator and a good working environment.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本願発明の深礎用鉄筋篭の建込み方法の概要を
示す斜視図である。
FIG. 1 is a perspective view showing an outline of a method of installing a deep reinforcement bar basket of the present invention.

【図2】支持リング部分における鉄筋取付け方法と、チ
ェーンホイルウインチによる支持方法の一例を示した斜
視図である。
FIG. 2 is a perspective view showing an example of a reinforcing bar attaching method in a supporting ring portion and a supporting method using a chain wheel winch.

【図3】仮設架台を利用した地上部での鉄筋篭の組立て
の様子を示す斜視図である。
FIG. 3 is a perspective view showing a state in which a reinforcing bar basket is assembled on the ground using a temporary mount.

【符号の説明】[Explanation of symbols]

1…深礎立坑、2…仮設架台、3…チェーンホールウイ
ンチ、4…支持リング、5…ライナープレート、6…チ
ェーンホールウインチ用リング鋼台、7…チェーン、8
…縦筋止め金具、9…チャッキング装置、10…下部作
業台、11…鉄筋篭、12…縦筋、13…帯筋、
1 ... Deep foundation shaft, 2 ... Temporary stand, 3 ... Chain hole winch, 4 ... Support ring, 5 ... Liner plate, 6 ... Chain hole winch ring steel stand, 7 ... Chain, 8
... Vertical bar stoppers, 9 ... Chucking device, 10 ... Lower workbench, 11 ... Reinforcing bar cage, 12 ... Vertical bar, 13 ... Belt bar,

Claims (5)

【特許請求の範囲】[Claims] 【請求項1】 深礎用立坑の坑口地上部に仮設架台と、
地上部で組み立てられて行く鉄筋篭を下方から支える支
持リングと、前記支持リングを仮設架台に対し昇降可能
に支持する吊り装置とを設置し、前記支持リングに、順
次、鉄筋篭を構成する縦筋を設置して行き、その後、前
記縦筋を取り巻く帯筋を前記縦筋と結合させ、順次、下
方より鉄筋篭としての剛性を確保し、前記吊り装置によ
り前記支持リングを深礎用立坑内に吊り降ろして行くこ
とで、地上部で組み立てた鉄筋篭を立坑内に設置するこ
とを特徴とする深礎用鉄筋篭の建込み方法。
1. A temporary pedestal at the aboveground part of the pit of the deep foundation shaft,
A support ring that supports the rebar cage that is being assembled on the ground from below and a suspension device that supports the support ring so that the support ring can move up and down with respect to the temporary frame are installed. After installing streaks, after that, the stirrups surrounding the vertical stirrup are connected to the vertical stirrup, and the rigidity of the rebar cage is secured from below, and the supporting ring is used to secure the support ring in the deep foundation shaft. A method of building a deep-reinforcing bar cage, which is characterized by installing the rebar cage assembled on the ground in the shaft by hanging it up to the ground.
【請求項2】 前記支持リング位置での支持に加え、鉄
筋篭の深さ方向中間部も吊り支持する請求項1記載の深
礎用鉄筋篭の建込み方法。
2. The method of constructing a rebar cage for deep foundation according to claim 1, wherein in addition to the support at the support ring position, an intermediate portion in the depth direction of the rebar cage is also suspended and supported.
【請求項3】 鉄筋篭の吊り降ろし作業の進行に伴い、
前記支持リングを上方に盛り換えながら、鉄筋篭の組立
ておよび吊り降ろしを行う請求項1または2記載の深礎
用鉄筋篭の建込み方法。
3. With the progress of the operation of hanging the rebar cage,
3. The method for constructing a deep foundation rebar cage according to claim 1, wherein the rebar cage is assembled and hung while the support ring is refilled upward.
【請求項4】 深礎用立坑の坑口地上部の仮設架台と、
地上部で組み立てられて行く鉄筋篭を下方から支える支
持リングと、前記支持リングを仮設架台に対し昇降可能
に支持する吊り装置とからなることを特徴とする深礎用
鉄筋篭の建込み装置。
4. A temporary pedestal on the aboveground part of the shaft of the shaft for deep foundation,
An apparatus for constructing a rebar cage for deep foundations, comprising: a support ring that supports a rebar cage that is being assembled on the ground from below and a suspension device that supports the support ring so that the support ring can move up and down with respect to a temporary frame.
【請求項5】 前記吊り装置が、互いに同期運転が可能
な複数のチェーンホイルウインチからなる請求項4記載
の深礎用鉄筋篭の建込み装置。
5. The apparatus for constructing a rebar cage for deep foundation according to claim 4, wherein the suspension device comprises a plurality of chain wheel winches that can be operated in synchronization with each other.
JP34060195A 1995-12-27 1995-12-27 Method and device for placing of steel bar cage for deep foundation Withdrawn JPH09177070A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34060195A JPH09177070A (en) 1995-12-27 1995-12-27 Method and device for placing of steel bar cage for deep foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34060195A JPH09177070A (en) 1995-12-27 1995-12-27 Method and device for placing of steel bar cage for deep foundation

Publications (1)

Publication Number Publication Date
JPH09177070A true JPH09177070A (en) 1997-07-08

Family

ID=18338549

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34060195A Withdrawn JPH09177070A (en) 1995-12-27 1995-12-27 Method and device for placing of steel bar cage for deep foundation

Country Status (1)

Country Link
JP (1) JPH09177070A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109505309A (en) * 2019-01-07 2019-03-22 浙江大学城市学院 A kind of shift system of piping lane segment and the piping lane installation method of application shift system
CN109706918A (en) * 2018-12-11 2019-05-03 中铁六局集团有限公司 A kind of lifting restricted clearance steel reinforcement cage aperture molding machine and its construction method
JP2019148070A (en) * 2018-02-26 2019-09-05 鹿島建設株式会社 Construction method of underground structure
CN112176987A (en) * 2020-10-12 2021-01-05 甘肃路桥建设集团有限公司 Adjustable drill hole lifting appliance for lowering pile foundation reinforcement cage
CN115305906A (en) * 2022-08-24 2022-11-08 中国一冶集团有限公司 Integrated device for manufacturing and hoisting reinforcement cage and construction method
JP2024011078A (en) * 2022-07-13 2024-01-25 辻 ふうな Construction method of earth retaining wall, and construction device of earth retaining wall

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019148070A (en) * 2018-02-26 2019-09-05 鹿島建設株式会社 Construction method of underground structure
CN109706918A (en) * 2018-12-11 2019-05-03 中铁六局集团有限公司 A kind of lifting restricted clearance steel reinforcement cage aperture molding machine and its construction method
CN109706918B (en) * 2018-12-11 2021-01-05 中铁六局集团有限公司 Reinforcing cage orifice forming device for hoisting limited space and construction method thereof
CN109505309A (en) * 2019-01-07 2019-03-22 浙江大学城市学院 A kind of shift system of piping lane segment and the piping lane installation method of application shift system
CN109505309B (en) * 2019-01-07 2023-09-26 浙江大学城市学院 Pipe gallery segment displacement system and pipe gallery installation method using same
CN112176987A (en) * 2020-10-12 2021-01-05 甘肃路桥建设集团有限公司 Adjustable drill hole lifting appliance for lowering pile foundation reinforcement cage
JP2024011078A (en) * 2022-07-13 2024-01-25 辻 ふうな Construction method of earth retaining wall, and construction device of earth retaining wall
CN115305906A (en) * 2022-08-24 2022-11-08 中国一冶集团有限公司 Integrated device for manufacturing and hoisting reinforcement cage and construction method
CN115305906B (en) * 2022-08-24 2023-11-24 中国一冶集团有限公司 Integrated device for manufacturing and hoisting reinforcement cage and construction method

Similar Documents

Publication Publication Date Title
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
JPH09177070A (en) Method and device for placing of steel bar cage for deep foundation
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
JPH09268778A (en) Disassembling method of water-contained gas holder and member used for the same method
JP3028071B2 (en) Top removal method and scaffold for removal work of ultra-high tubular structure
JP6646220B2 (en) Construction method of suspended steel frame for suspended ceiling
JP3242775B2 (en) Installation method of vertical container
JP2858205B2 (en) Reinforcing bar mounting method and rebar mounting device used for the same
JPH11303421A (en) Demolition method for steel tower type high-rise chimney
JP3220397B2 (en) Elevating scaffold
JP2003120037A (en) Construction lifting system for multistoried building
JP2681219B2 (en) Working scaffolding in the deep foundation method
JPH10184037A (en) Construction method of water-containing type gas holder
JP3864386B2 (en) Construction method of the water type gas holder.
JPH0718743A (en) Construction method for large span domelike roof
JP2013011119A (en) Construction method of multi-layer building and lifting device for continuous layer foothold used therefor
JPH1037527A (en) Method for constructing inner and outer cylinder of chimney simultaneously
JP2681218B2 (en) Working scaffolding in the deep foundation method
JPH05263531A (en) Automatic construction method and lifting-up device of structure
JPH06101348A (en) Method for constructing tower
JP6355801B2 (en) Construction method of dome-like roof structure
JP2843042B2 (en) Steel framing unit scaffolding method
JP2000170376A (en) Temporary work method for work scaffolding for tower- shaped structure
JPH0321777A (en) Construction method of iron-frame pillar
JPH09310484A (en) Large space applicable suspended scaffold constructing system

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20030304