JP2007321475A - Barge for construction of bridge, and bridge removal method - Google Patents

Barge for construction of bridge, and bridge removal method Download PDF

Info

Publication number
JP2007321475A
JP2007321475A JP2006153977A JP2006153977A JP2007321475A JP 2007321475 A JP2007321475 A JP 2007321475A JP 2006153977 A JP2006153977 A JP 2006153977A JP 2006153977 A JP2006153977 A JP 2006153977A JP 2007321475 A JP2007321475 A JP 2007321475A
Authority
JP
Japan
Prior art keywords
bridge
construction
river
support
removal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2006153977A
Other languages
Japanese (ja)
Other versions
JP4727504B2 (en
Inventor
Shuji Onami
修二 大波
Masashi Sakakibara
正志 榊原
Tetsuji Yamagami
哲示 山上
Shuji Sato
修二 佐藤
Kozo Ishitani
浩蔵 石谷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MM Bridge Co Ltd
Original Assignee
Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd filed Critical Mitsubishi Heavy Industries Bridge and Steel Structures Engineering Co Ltd
Priority to JP2006153977A priority Critical patent/JP4727504B2/en
Publication of JP2007321475A publication Critical patent/JP2007321475A/en
Application granted granted Critical
Publication of JP4727504B2 publication Critical patent/JP4727504B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a barge capable of being also used for the removal of a bridge over a relatively small river, and a bridge removal method. <P>SOLUTION: Characteristically, this barge for the construction of the bridge, which is used for the removal of the bridge at least partially installed over the river, comprises: a barge fixing means for fixing the barge for the construction of the bridge in a prescribed place; a supporting and hoisting/lowering means which is installed on the barge for the construction of the bridge, which abuts on the lower section of the bridge so as to support it, and which enables the bridge to move upward and downward after being cut off; and a supporting means for preventing the barge from being sunk by the self-weight of the barge for the construction of the bridge. <P>COPYRIGHT: (C)2008,JPO&INPIT

Description

本発明は、橋梁施工用台船及び橋梁撤去工法に関するものである。   The present invention relates to a bridge construction carrier and a bridge removal method.

従来、橋梁の撤去工法としては、特許文献1に示されているような工法が用いられていた。つまり、台船で、橋梁の一部を支持し、その橋梁の一部を切断し、切断された橋梁の一部は台船ごと移動され、残存している橋梁の上に移される。そして、当該橋梁一部は、その後、撤去される。   Conventionally, as a method for removing a bridge, a method as shown in Patent Document 1 has been used. In other words, a part of the bridge is supported by the trolley, a part of the bridge is cut, and the part of the cut bridge is moved together with the trolley and transferred onto the remaining bridge. A part of the bridge is then removed.

特開平10−147912号公報Japanese Patent Laid-Open No. 10-147912

しかしながら、特許文献1に示されている工法では、撤去される橋梁を支持するだけの浮力を台船に与える必要があり、台船の大型化につながっていた。そのため、比較的小さい河川上にある橋梁(例えば、高速道路)の撤去に台船を用いることができず、河川全面に構台を設置してから橋梁を撤去することが行われていた。つまり、工事が大規模になり、工期の長期化、および、コストの増加という問題が生じていた。   However, in the construction method shown in Patent Document 1, it is necessary to give the trolley buoyancy enough to support the bridge to be removed, leading to an increase in the size of the trolley. For this reason, a trolley cannot be used to remove a bridge (for example, a highway) on a relatively small river, and a bridge is removed after a gantry is installed on the entire surface of the river. In other words, the construction has become large-scale, and there have been problems such as a prolonged construction period and an increase in cost.

そこで、この発明は、上記に鑑みてなされたものであって、比較的小さい河川上の橋梁の急速撤去などの施工に用いることができる台船および橋梁の撤去工法を提供することを目的とする。   Then, this invention is made | formed in view of the above, Comprising: It aims at providing the removal method of a trolley and a bridge which can be used for constructions, such as rapid removal of a bridge on a comparatively small river. .

上述の目的を達成するために、この発明に係る橋梁施工用台船は、少なくとも一部が河川に設置された橋梁の撤去等に用いられる橋梁施工用台船において、橋梁施工用台船を所定の位置で高さ方向と水平方向に固定する台船固定手段と、橋梁施工用台船上に設置され、橋梁の下部に当接され、支持すると共に、橋梁が切り取られた後に、橋梁を上下に移動可能とする支持昇降手段と、橋梁施工用台船の自重によって河川に沈まないようにする支持手段と、を有することを特徴とする。   In order to achieve the above-mentioned object, a bridge construction trolley according to the present invention is a bridge construction trolley that is used to remove at least a part of a bridge installed in a river. It is installed on the bridge construction trolley and is supported on and supported by the lower part of the bridge. After the bridge is cut, the bridge is moved up and down. It is characterized by having supporting lifting means that can be moved, and supporting means that prevents the bridge construction work from sinking into the river due to its own weight.

上述の構成によれば、橋梁施工用台船を所定の位置で高さ方向と水平方向に固定する台船固定手段固定が台船を河川に固定するので、橋梁の撤去作業中は河川の流れによって、当該橋梁施工用台船が流されることがない。また、当該台船固定手段は、橋梁の撤去予定部分の荷重をも支えるので、支持手段は橋梁施工用台船の自重を許容するものとすればよい。つまり、支持手段の小型化、ひいては、橋梁施工用台船の小型化を図ることができる。さらに、支持昇降手段が台船に設けられているので、撤去予定部分を上下に移動させ、作業員が作業しやすい位置に移動させた後に、当該撤去予定分を解体・撤去することができる。   According to the above configuration, since the base boat fixing means fixing the bridge construction base boat at a predetermined position in the height direction and the horizontal direction fixes the base boat to the river, the flow of the river during the bridge removal work This prevents the bridge construction carrier from being washed away. Moreover, since the said trolley fixing means also supports the load of the part to be removed of the bridge, the supporting means may allow the weight of the bridge construction trolley. That is, it is possible to reduce the size of the support means, and hence the bridge construction carrier. Furthermore, since the support lift is provided on the carriage, the planned removal part can be disassembled and removed after the part to be removed is moved up and down to a position where the worker can easily work.

次の発明に係る橋梁施工用台船は、上述の橋梁施工用台船において、支持昇降手段は、橋梁の下部との当接部に橋梁を水平方向にスライドさせるスライド手段を有していることを特徴とする。   The bridge construction carrier according to the next invention is the bridge construction carrier described above, wherein the support lifting means has a sliding means for sliding the bridge in a horizontal direction at a contact portion with the lower part of the bridge. It is characterized by.

上述の構成によれば、台船自体が移動せずとも、撤去予定部分(切断された橋梁)を切断されていない橋梁上に移動させることができる。即ち、台船自体が移動する必要がなく、工期の短縮を図ることができる。   According to the above-described configuration, the part to be removed (the cut bridge) can be moved onto the bridge that has not been cut without the carriage itself moving. That is, it is not necessary for the carriage itself to move, and the construction period can be shortened.

次の発明に係る橋梁施工用台船は、前記橋梁施工用台船において、前記施工用台船は、組立式であるようにしたものである。   The bridge construction base boat according to the next invention is the bridge construction base boat, wherein the construction base boat is an assembly type.

橋梁施工用台船を小さなブロックを組み合わせて形成する組立式にすると、施工現場まで曳航するのも容易となる。また、陸上でトラック、トレーラで現場近傍まで当該ブロックを搬送した後、特に大型でない起重機で着水させることも容易となる。   If the bridge construction trolley is an assembly type formed by combining small blocks, it is easy to tow to the construction site. In addition, after transporting the block to the vicinity of the site by truck or trailer on land, it is easy to land with a hoist that is not particularly large.

次の発明に係る橋梁撤去工法は、少なくとも一部が河川に設置された橋梁を撤去する橋梁撤去工法において、橋梁施工用台船を橋梁の撤去予定部分の下部に移動させ、河川に固定する工程と、支持昇降手段によって撤去予定部分の下部を支持する工程と、撤去予定部分を橋梁から切断する工程と、支持昇降手段によって撤去予定部分を下方に移動させる工程と、スライド手段によって撤去予定部分をスライド移動させる工程と、を含むことを特徴とする。   The bridge removal method according to the next invention is a bridge removal method in which at least a part of a bridge installed in a river is removed. A step of supporting the lower part of the part to be removed by the support lifting means, a step of cutting the part to be removed from the bridge, a step of moving the part to be removed downward by the support lifting means, and a part to be removed by the slide means. And a step of sliding.

上述の構成によれば、撤去予定部分を橋梁よりも下方に移動させることができ、その後、スライド手段によって、撤去予定部分を陸上や運搬用船に移すことができる。したがって、撤去予定部分を陸上に移動させた場合には、作業のしやすい陸上で、撤去予定部分の解体作業を行うことができる。また、撤去予定部分を運搬用船に移動させた場合には、その運搬船で、解体作業に適した場所に撤去用部分を移動させてから解体作業を行うことができる。   According to the above-described configuration, the part to be removed can be moved below the bridge, and then the part to be removed can be moved to the land or a transport ship by the sliding means. Therefore, when the part to be removed is moved to land, the part to be removed can be dismantled on land that is easy to work. In addition, when the part to be removed is moved to the transport ship, the dismantling work can be performed after the removal part is moved to a place suitable for the dismantling work with the transport ship.

次の発明に係る橋梁撤去工法は、少なくとも一部が河川に設置された橋梁を撤去する橋梁撤去工法において、橋梁施工用台船を橋梁の撤去予定部分の下部に移動させ、河川に固定する工程と、支持昇降手段によって撤去予定部分の下部を支持する工程と、撤去予定部分を橋梁から切断する工程と、支持昇降手段によって撤去予定部分を橋梁よりも高い位置に移動させる工程と、撤去予定部分を橋梁の上面に載るように、水平方向にスライドさせる工程と、橋梁の上で撤去予定部分を解体する工程と、解体した撤去予定部分を撤去する工程とを含むことを特徴とする。   The bridge removal method according to the next invention is a bridge removal method in which at least a part of a bridge installed in a river is removed. A step of supporting the lower part of the planned removal portion by the support lifting means, a step of cutting the planned removal portion from the bridge, a step of moving the planned removal portion to a position higher than the bridge by the support lifting means, and a removal planned portion The method includes a step of sliding horizontally so as to be placed on the upper surface of the bridge, a step of dismantling the part to be removed on the bridge, and a step of removing the part to be removed after dismantling.

上述の工程によれば、台船自体が移動せずとも、支持物(切断された橋梁)を切断されていない橋梁上に移動させることができる。即ち、台船自体が移動する必要がなく、工期の短縮を図ることができる。   According to the above-described process, the support (cut bridge) can be moved onto the bridge that has not been cut without the carriage itself moving. That is, it is not necessary for the carriage itself to move, and the construction period can be shortened.

次の発明に係る橋梁撤去工法は、少なくとも一部が河川に設置された第1の橋梁があり、河川に掛かる第2の橋梁が第1の橋梁の下方にある場合における第1の橋梁の橋梁撤去工法において、第2の橋梁の上方にある第1の橋梁を撤去し、続いて、第1の橋梁の下方に橋のない部分では、橋梁施工用台船を第1の橋梁の撤去予定部分の下部に移動させ、河川に固定する工程と、支持昇降手段によって撤去予定部分の下部を支持する工程と、撤去予定部分を第1の橋梁から切断する工程と、支持昇降手段によって撤去予定部分を第1の橋梁よりも高い位置に移動させる工程と、撤去予定部分を第1の橋梁の上面に載るように、水平方向にスライドさせる工程と、第1の橋梁の上で撤去予定部分を解体する工程と、解体した撤去予定部分を撤去する工程とを含むことを特徴とする。   The bridge removal method according to the next invention is the bridge of the first bridge when there is a first bridge at least partially installed in the river and the second bridge over the river is below the first bridge. In the removal method, the first bridge above the second bridge is removed, and then the bridge construction carrier is removed from the first bridge in the part where there is no bridge below the first bridge. Moving to the lower part of the frame, fixing to the river, supporting the lower part of the part to be removed by the supporting lifting means, cutting the part to be removed from the first bridge, and the part to be removed by the supporting lifting means The step of moving to a position higher than the first bridge, the step of sliding in a horizontal direction so that the portion to be removed is placed on the upper surface of the first bridge, and the portion to be removed on the first bridge are dismantled Remove the process and dismantled parts to be removed Characterized in that it comprises a step.

上述の工程によれば、第1の橋梁から切断され、撤去される予定の撤去予定部分と、それを支持する機器との荷重を第2の橋梁は支持するだけでよいので、第2の橋梁を補強する時間を短縮化することができる。さらに、橋の補強時間短縮化に伴って、コストの削減、作業負荷の低減も図ることができる。   According to the above-described process, the second bridge only needs to support the load of the part to be removed that is to be cut and removed from the first bridge and the equipment that supports the part. The time for reinforcing can be shortened. Furthermore, along with shortening of the bridge reinforcement time, it is possible to reduce costs and workload.

以上説明したように、この発明に係る橋梁施工用台船及び橋梁撤去工法によれば、比較的小さい河川上の橋梁の撤去に台船を用いることができ、さらに、橋梁を急速に撤去することができる。   As described above, according to the bridge construction trolley and the bridge removal method according to the present invention, the trolley can be used to remove a bridge on a relatively small river, and the bridge can be removed rapidly. Can do.

以下、この発明につき図面を参照しつつ詳細に説明する。なお、この発明を実施するための最良の形態(以下実施例という)によりこの発明が限定されるものではない。また、下記実施例における構成要素には、当業者が容易に想定できるもの、あるいは実質的に同一のものが含まれる。   Hereinafter, the present invention will be described in detail with reference to the drawings. It should be noted that the present invention is not limited by the best mode for carrying out the invention (hereinafter, referred to as examples). In addition, constituent elements in the following embodiments include those that can be easily assumed by those skilled in the art or those that are substantially the same.

図1は、本発明に係る橋梁施工用台船を示す図である。また、図2は橋梁施工用台船の上面図である。図2に示すように、橋梁施工用台船10(以下、台船という)の四隅には、台船を河川に固定するための台船固定手段11が設けられている。この台船固定手段11は、河川の川底に固定するために杭などの棒状部材を用いる。台船が移動する際には、台船に設けられている杭昇降装置によって、台船固定手段11が図1に示すA方向に移動され、河川の底から抜かれる。   FIG. 1 is a view showing a bridge construction carrier ship according to the present invention. FIG. 2 is a top view of the bridge construction carrier. As shown in FIG. 2, trolley fixing means 11 for fixing the trolley to the river is provided at the four corners of the bridge construction trolley 10 (hereinafter referred to as a trolley). This base boat fixing means 11 uses a rod-like member such as a pile in order to fix it to the riverbed. When the trolley moves, the pedestal fixing means 11 is moved in the direction A shown in FIG. 1 by the pile lifting device provided in the trolley and is pulled out from the bottom of the river.

橋梁を撤去する際、橋梁の撤去予定部分の荷重をも支える必要があるので、台船の荷重及び橋梁の撤去予定部分の荷重を許容できるだけの剛性を台船固定手段11にもたせておく必要がある。また、台船固定手段を用いて台船を河川に固定し、橋梁を撤去する際に、橋梁の荷重によって台船と台船固定手段との位置がずれないようにする。そのためには、例えば、台船固定手段の一例である杭に穴を穿設し、当該穴にピンを通して台船と固定する方法がある。   When removing a bridge, it is necessary to support the load of the planned removal part of the bridge, so it is necessary to allow the carriage support means 11 to have rigidity sufficient to allow the load of the carriage and the load of the planned removal part of the bridge. is there. Further, when the trolley is fixed to the river using the trolley fixing means and the bridge is removed, the position of the trolley and the trolley fixing means is not shifted due to the load of the bridge. For this purpose, for example, there is a method in which a hole is drilled in a pile which is an example of a carrier fixing means, and a pin is passed through the hole and fixed to the carrier.

台船の上面(B面)には、仮受け構台12と呼ばれる高架橋等の橋梁の撤去において橋体を支持するために設けられる仮のトラスト構造体またはラーメン構造体が設置されている。その仮受け構台12の上部には橋梁の撤去予定部分を上下に移動可能とする伸縮自在な支持昇降装置13(支持昇降手段)が設けられている。この支持昇降装置13は、例えば油圧によって作動するものなどがある。なお、支持昇降装置13は、撤去予定の橋梁を上下に移動可能とするだけの出力を有する必要がある。   On the upper surface (B surface) of the trolley, a temporary trust structure or a ramen structure provided to support the bridge body in removing a bridge such as a viaduct called the temporary receiving gantry 12 is installed. On the upper part of the temporary receiving gantry 12, a telescopic support lifting device 13 (supporting lifting means) is provided that can move the planned removal portion of the bridge up and down. This support elevating device 13 includes, for example, one that operates by hydraulic pressure. In addition, the support raising / lowering apparatus 13 needs to have an output which enables the bridge to be removed to move up and down.

例えば、この支持昇降装置13は図1に示すように3段階の油圧装置15、16、17とによって構成されており、それぞれの油圧装置15、16、17を作動させることによって、支持物を上下に昇降可能としている。具体的には、この装置は、1段階目の油圧装置15が2メートル、2段階目16の油圧装置が2メートル、3段階目の油圧装置17が1.5メートル昇降することができ、合計で5.5メートル昇降することができる。   For example, as shown in FIG. 1, the support lifting / lowering device 13 includes three stages of hydraulic devices 15, 16, and 17. By operating each of the hydraulic devices 15, 16, and 17, the support can be moved up and down. Can be moved up and down. Specifically, the first stage hydraulic device 15 can move up and down by 2 meters, the second stage 16 hydraulic device by 2 meters, and the third stage hydraulic device 17 can go up and down by 1.5 meters. Can go up and down 5.5 meters.

支持昇降装置13の上部には橋梁の撤去予定部分を水平方向にスライドさせるためのエンドレスローラ14(スライド手段)が設けられている。このエンドレスローラ(無限軌道装置)14は、駆動装置の動力によって駆動するローラーによって、当該ローラーの周囲に巻いてあるチェーンやベルトを動作させるものである。また、エンドレスローラ14は、一定の幅を有するので、橋梁の幅方向に一機のエンドスローラを設ければ、撤去予定部分を十分支持可能である。なお、スライド手段はエンドレスローラ以外でもよく、撤去予定部分をスライドさせることができるものであればタイヤなどでもよい。   An endless roller 14 (sliding means) is provided on the upper portion of the support lifting device 13 for sliding the bridge removal scheduled portion in the horizontal direction. The endless roller (endless track device) 14 is a device that operates a chain or belt wound around the roller by a roller driven by the power of a driving device. Moreover, since the endless roller 14 has a fixed width | variety, if one end slurer is provided in the width direction of a bridge, it can fully support the part to be removed. The slide means may be other than the endless roller, and may be a tire or the like as long as it can slide the portion to be removed.

また、上述した台船固定手段11、仮受け構台12、支持昇降装置13、エンドレスローラ14等を含む台船10が沈まないようにするためのフロートが、該台船10に設けられている。なお、台船10自体の底部に空気を充満させて台船10自体をフロートにしてもよい。   In addition, a float is provided in the trolley 10 so as to prevent the trolley 10 including the above-described trolley fixing means 11, the temporary receiving gantry 12, the support lifting device 13, the endless roller 14 and the like from sinking. The bottom of the trolley 10 itself may be filled with air to make the trolley 10 itself float.

橋梁撤去の際、台船10に設けられた台船固定手段11が河川の底に固定され、橋梁の荷重を支持するので、フロートは橋梁の重さを許容する必要がない。したがって、フロートの小型化、しいては、台船10の小型化を図ることができる。また、小型化によって水深の浅いところや、潮位差のないところでも使用できるようになる。   When the bridge is removed, the trolley fixing means 11 provided in the trolley 10 is fixed to the bottom of the river and supports the load of the bridge. Therefore, the float does not need to allow the weight of the bridge. Therefore, it is possible to reduce the size of the float, that is, the size of the carriage 10. In addition, it can be used in places where the water depth is shallow or where there is no difference in tide level due to downsizing.

なお、台船固定手段11を上下に移動させる杭昇降装置に撤去予定の橋梁を上下に移動させることができるだけの出力をもたせ、橋梁を上下に移動させる昇降手段としての機能を付加させてもよい。この構成をとることによって、上述の橋梁を上下に移動可能とする支持昇降装置13を省略することができる。   It should be noted that the pile lifting device for moving the base boat fixing means 11 up and down may have an output sufficient to move the bridge to be removed up and down, and the function as lifting means for moving the bridge up and down may be added. . By adopting this configuration, it is possible to omit the support elevating device 13 that enables the above-described bridge to move up and down.

次に上述した台船を用いた橋梁撤去工法について図3-1から図3-12を用いて説明する。   Next, the bridge removal method using the above-mentioned trolley will be described with reference to FIGS. 3-1 to 3-12.

図中の20は橋梁であり、20-1から20-nは、それぞれブロック単位に撤去される予定の橋梁である。なお、nは正の整数である。   In the figure, 20 is a bridge, and 20-1 to 20-n are bridges scheduled to be removed in block units. Note that n is a positive integer.

まず、台船21-1、21-2をブロック単位に分割・切断され撤去される予定の橋梁20-1の下部に移動させ、台船固定手段11を河川の底に刺して台船を河川に固定する。また、台船21-3を橋梁20-2の下部に移動させ、台船固定手段11を河川の底に固定して台船を固定する。   First, the base boats 21-1, 21-2 are moved to the lower part of the bridge 20-1, which is planned to be divided, cut and removed in blocks, and the base boat fixing means 11 is inserted into the bottom of the river to bring the base boat into the river. Secure to. Further, the trolley 21-3 is moved to the lower part of the bridge 20-2, and the trolley fixing means 11 is fixed to the bottom of the river to fix the trolley.

そして、それぞれの台船21-1、21-2に設けられている支持昇降装置13を伸ばし、エンドレスローラ14を介して、それぞれの橋梁20-1、20-2の下部を支持する(図3-1)。   Then, the support lifting and lowering devices 13 provided on the respective carrier ships 21-1 and 21-2 are extended, and the lower portions of the respective bridges 20-1 and 20-2 are supported via the endless rollers 14 (FIG. 3). -1).

その後、橋梁20-1を橋梁20から切断し、切断された橋梁20-1を橋梁20より高い位置に移動させる(図3-2)。そして、エンドレスローラ14を作動させ、橋梁20-1を橋梁20の上に水平移動させる(図3-3)。   Thereafter, the bridge 20-1 is cut from the bridge 20, and the cut bridge 20-1 is moved to a position higher than the bridge 20 (FIG. 3-2). Then, the endless roller 14 is operated, and the bridge 20-1 is moved horizontally on the bridge 20 (FIG. 3-3).

次に、台船21-2を橋梁20-2の下部に移動させ、橋梁20-2を支持する。砕削機や切断機等の撤去作業用機器を用いて、橋梁20-1を撤去しやすい大きさに解体し、トラック等で橋梁20上から撤去する(図3-4)。なお、橋梁20-2上で解体する必要はなく、他の場所に撤去してから解体してもよい。   Next, the carriage 21-2 is moved to the lower part of the bridge 20-2 to support the bridge 20-2. Using a removal machine such as a crusher or a cutting machine, the bridge 20-1 is dismantled to a size that can be easily removed, and removed from the bridge 20 with a truck or the like (FIG. 3-4). Note that it is not necessary to dismantle on the bridge 20-2, and it may be dismantled after being removed to another place.

橋梁20-1の撤去が終わると、台船21-3を橋梁20-3又は20-4の下部に移動させ、橋梁20を支持させる。台船21-1、21-2は、橋梁20-2の下部であって、橋梁20-2を支持しやすい場所に移動し、橋梁20-2を支持する(図3-5)。   When the removal of the bridge 20-1 is finished, the carriage 21-3 is moved to the lower part of the bridge 20-3 or 20-4 to support the bridge 20. The trolleys 21-1 and 21-2 move to a position below the bridge 20-2 where they can easily support the bridge 20-2, and support the bridge 20-2 (FIG. 3-5).

その後、図3-2乃至図3-4を用いて説明した作業と同様に、橋梁20-2を橋梁20から切断し、切断された橋梁20-2を橋梁20より高い位置に移動させる。そして、エンドレスローラ14を作動させ、橋梁20-2を水平方向にスライドさせて橋梁20の上面に移動させる。その後、橋梁20-2を解体・撤去する(図3-6)。   Thereafter, similarly to the work described with reference to FIGS. 3-2 to 3-4, the bridge 20-2 is cut from the bridge 20, and the cut bridge 20-2 is moved to a position higher than the bridge 20. Then, the endless roller 14 is operated, and the bridge 20-2 is slid in the horizontal direction and moved to the upper surface of the bridge 20. After that, the bridge 20-2 is dismantled and removed (Fig. 3-6).

次に、ブロック単位に分割・切断され撤去される予定の橋梁21-3を支える支柱P1がある場合(図3-7)には、支柱P1の周辺に台船21-2を移動させ、橋梁20-3を支持した後に、支柱P1を撤去する(図3-8)。   Next, when there is a support P1 that supports the bridge 21-3 that is to be divided, cut and removed in block units (FIG. 3-7), the carriage 21-2 is moved around the support P1, and the bridge is moved. After supporting 20-3, the support P1 is removed (FIG. 3-8).

支柱P1の撤去は、支柱P1の上部を支持手段で支持し、支柱P1の下方から撤去していく。支柱P1の下方を撤去した後、その上方に残っている支柱P1を当該撤去した部分に下ろす。この作業を繰り返しながら、支柱P1を撤去していく。   The support P1 is removed by supporting the upper part of the support P1 with support means and removing it from below the support P1. After removing the lower part of the pillar P1, the pillar P1 remaining above the pillar P1 is lowered to the removed part. The strut P1 is removed while repeating this operation.

その後、図3-2乃至図3-4を用いて説明した作業と同様に、橋梁20-3を橋梁20から切断し、切断された橋梁20-3を橋梁20より高い位置に移動させる。そして、エンドレスローラ14を作動させ、橋梁20-3を橋梁20の上に水平移動させて、解体・撤去する(図3-9)。   Thereafter, similarly to the work described with reference to FIGS. 3-2 to 3-4, the bridge 20-3 is cut from the bridge 20, and the cut bridge 20-3 is moved to a position higher than the bridge 20. Then, the endless roller 14 is operated, and the bridge 20-3 is moved horizontally on the bridge 20 to be disassembled and removed (FIG. 3-9).

河川に掛かる橋22が橋梁20の下方にある場合における橋梁20の撤去工法について、図3-10を用いて説明する。以下、橋22と橋梁20とを区別するために、橋梁20を第1の橋梁20と称し、橋22を第2の橋梁22と称する。この場合、台船21-3、21-4で第1の橋梁20-4の両端部を支持する。そして第2の橋梁22上に第1の橋梁20-4を支持する支持装置を有した移動台車23を移動させる。移動台車23で第1の橋梁20-4を支持した後、第1の橋梁20-4を第1の橋梁20から切断し、他の場所に移動させ、解体・撤去を行う。   A method for removing the bridge 20 when the bridge 22 over the river is below the bridge 20 will be described with reference to FIGS. Hereinafter, in order to distinguish the bridge 22 and the bridge 20, the bridge 20 is referred to as a first bridge 20, and the bridge 22 is referred to as a second bridge 22. In this case, both ends of the first bridge 20-4 are supported by the carriages 21-3 and 21-4. Then, the movable carriage 23 having a supporting device for supporting the first bridge 20-4 is moved on the second bridge 22. After the first bridge 20-4 is supported by the moving carriage 23, the first bridge 20-4 is cut from the first bridge 20, moved to another location, and disassembled / removed.

その後、台船21-1、21-2を第1の橋梁20-5の下部に移動させ、第1の橋梁20-5を支持する(図3-11)。次に、図3-2乃至図3-4を用いて説明した作業と同様に、第1の橋梁20-5を第1の橋梁20から切断し、切断された第1の橋梁20-5を第1の橋梁20より高い位置に移動させる。そして、エンドレスローラ14を作動させ、第1の橋梁20-5を第1の橋梁20の上に水平移動させて、解体・撤去する(図3-12)。このように、河川に掛かる橋のないところでは、図3-2乃至図3-4を用いて説明したのと同様の作業を繰り返すことによって、第1の橋梁20を撤去する。   Thereafter, the carriages 21-1, 21-2 are moved to the lower part of the first bridge 20-5 to support the first bridge 20-5 (FIG. 3-11). Next, similarly to the work described with reference to FIGS. 3-2 to 3-4, the first bridge 20-5 is cut from the first bridge 20, and the cut first bridge 20-5 is cut. Move to a position higher than the first bridge 20. Then, the endless roller 14 is operated, and the first bridge 20-5 is horizontally moved onto the first bridge 20 to be disassembled and removed (FIG. 3-12). As described above, where there is no bridge over the river, the first bridge 20 is removed by repeating the same operation as described with reference to FIGS. 3-2 to 3-4.

上述した台船によれば、杭を河川の底に固定することによって橋梁を支持している。したがって、フロートは台船自体が沈まないだけの浮力を有すればよく、小型化することができる。結果として、台船自体を小型化することができ、河川においても台船を使用して橋梁の撤去が行える。さらに、必要な位置に台船を設置すればよく、河川全面に構台を設置する必要がなくなるので、工事の大規模化を避けることができる。   According to the above-mentioned trolley, the bridge is supported by fixing the pile to the bottom of the river. Therefore, the float only needs to have buoyancy that does not cause the carriage to sink, and can be miniaturized. As a result, the trolley itself can be reduced in size, and bridges can be removed using trolleys in rivers. Furthermore, it is only necessary to install a trolley at a necessary position, and it is not necessary to install a gantry on the entire surface of the river.

また、河川全面に構台を設置する必要がないので、工事中でも船の通る航路等を確保することができる。また、本発明に係る台船は、小型化が可能なので、目的の場所まで浮いて移動できないような底の浅い河川であっても、目的の場所で組み立てて使用することができる。   In addition, since there is no need to install a gantry on the entire river surface, it is possible to secure a route through which the ship passes even during construction. Further, since the trolley according to the present invention can be miniaturized, even a shallow river that cannot float and move to a target location can be assembled and used at the target location.

橋梁撤去工法において、ブロック単位に分割・切断された撤去予定部分は、まだ、分割・切断されていない橋梁上に移動され、解体されてから撤去される。したがって、分割・切断された状態のままの大きな橋梁を運搬する必要がないので、小型の運搬手段(例えば、トラック)でも撤去作業を行うことができる。   In the bridge removal method, the part to be removed that has been divided and cut into blocks is moved to a bridge that has not yet been divided and cut, dismantled and then removed. Therefore, since it is not necessary to transport a large bridge that has been divided and cut, it is possible to perform the removal work even with a small transport means (for example, a truck).

なお、ブロック単位に撤去予定の橋梁を分割・切断して撤去することを繰り返すので、作業スペースを小さくすることが可能である。   The work space can be reduced because the bridge to be removed in blocks is repeatedly divided, cut and removed.

なお、上述の実施例では、撤去予定部をまだ切断されていない橋梁の上部に水平移動させて撤去をする工法を採用しているが、支持昇降手段で撤去予定部分を支持した後に、当該撤去予定部を下方に移動させてもよい。   In the above-mentioned embodiment, the construction method is adopted in which the removal planned part is horizontally moved to the upper part of the bridge that has not yet been cut and removed, but after the removal planned part is supported by the supporting lifting means, the removal is performed. The planned portion may be moved downward.

当該撤去予定部を下方に移動させ、その後、スライド手段によって、撤去予定部分を陸上や運搬用船に移す。そして、撤去予定部分を陸上に移動させた場合には、作業のしやすい陸上で撤去予定部分の解体作業を行うことができる。また、撤去予定部分を運搬用船に移動させた場合には、その運搬船で、解体作業に適した場所に撤去用部分を移動させてから解体作業を行うことができる。   The part to be removed is moved downward, and then the part to be removed is transferred to land or a transport ship by means of sliding. When the part to be removed is moved to the land, the part to be removed can be dismantled on the land where it is easy to work. In addition, when the part to be removed is moved to the transport ship, the dismantling work can be performed after the removal part is moved to a place suitable for the dismantling work with the transport ship.

この実施例2は、上記実施例1に係る橋梁撤去工法と略同一であるが、河川に掛かる橋上にある橋梁から先に撤去する点が異なる。その他の構成は実施例1と同様なのでその説明を省略すると共に、同一の構成要素には同一の符号を付する。   This Example 2 is substantially the same as the bridge removal method according to Example 1 described above, except that the bridge on the bridge over the river is removed first. Since the other configuration is the same as that of the first embodiment, the description thereof is omitted, and the same component is denoted by the same reference numeral.

図4-1及び図4-2を用いて、本実施例について説明する。図中の20は橋梁であり、20-1から20-nは、それぞれブロック単位に撤去される予定の橋梁である。   The present embodiment will be described with reference to FIGS. 4-1 and 4-2. In the figure, 20 is a bridge, and 20-1 to 20-n are bridges scheduled to be removed in block units.

まず、台船21-3で、第1の橋梁20-3と20-4とを支持し、台船21-4で第1の橋梁20-4と20-5を支持する。そして、第2の橋梁22上に第1の橋梁20-4を支持する支持装置を有した移動台車23を移動させる。移動台車23で第1の橋梁20-4を支持した後、第1の橋梁20-4を第1の橋梁20から切断し、他の場所に移動させ、解体・撤去を行う。   First, the first bridges 20-3 and 20-4 are supported by the carriage 21-3, and the first bridges 20-4 and 20-5 are supported by the carriage 21-4. Then, the movable carriage 23 having a support device for supporting the first bridge 20-4 is moved on the second bridge 22. After the first bridge 20-4 is supported by the moving carriage 23, the first bridge 20-4 is cut from the first bridge 20, moved to another location, and disassembled / removed.

その後、実施例1で述べたように、撤去する予定の第1の橋梁20-3を第1の橋梁20から切断し、切断された第1の橋梁20-3を第1の橋梁20より高い位置に移動させる。そして、エンドレスローラを作動させ、第1の橋梁20-3を第1の橋梁20の上に水平移動させて、解体・撤去する(図3-9)。   Thereafter, as described in the first embodiment, the first bridge 20-3 to be removed is cut from the first bridge 20, and the cut first bridge 20-3 is higher than the first bridge 20. Move to position. Then, the endless roller is operated, and the first bridge 20-3 is horizontally moved onto the first bridge 20 to be disassembled and removed (FIG. 3-9).

実施例1のように河川上の第1の橋梁20-1から順に撤去していくと、第1の橋梁20-3を撤去する際に、第1の橋梁20-4上に第1の橋梁20-3を移動させることとなる。この場合、第1の橋梁20-4を支えるために第2の橋梁22上に支持手段を設けて、第1の橋梁20-4を支持する必要がある。結果として、第1の橋梁20-4の自重以外に、第1の橋梁20-3及び撤去作業用機器等の重さをも第2の橋梁22が支持する必要がある。しかし、第2の橋梁22に大きな荷重をかけることは好ましいことではない。即ち第2の橋梁22に設計以上の荷重がかかると、第2の橋梁22が崩壊する虞がある。そこで、上述のように、河川に掛かる橋上にある橋梁から先に撤去すると、第2の橋梁22は、第1の橋梁20-4及び第1の橋梁20-4を支持する支持装置を有した移動台車23の荷重のみを許容できればよくなる。   When the first bridge 20-1 on the river is removed in order as in the first embodiment, when the first bridge 20-3 is removed, the first bridge is placed on the first bridge 20-4. 20-3 will be moved. In this case, in order to support the first bridge 20-4, it is necessary to provide support means on the second bridge 22 to support the first bridge 20-4. As a result, in addition to the weight of the first bridge 20-4, the second bridge 22 needs to support the weight of the first bridge 20-3 and the removal equipment. However, it is not preferable to apply a large load to the second bridge 22. That is, if a load higher than the design is applied to the second bridge 22, the second bridge 22 may collapse. Therefore, as described above, when the bridge on the bridge over the river is removed first, the second bridge 22 has a support device that supports the first bridge 20-4 and the first bridge 20-4. It is sufficient if only the load of the movable carriage 23 can be allowed.

以上のように、本発明に係る橋梁施工用台船及び橋梁撤去工法は、河川に沿った橋梁等の橋梁の撤去に有用である。   As described above, the bridge construction trolley and the bridge removing method according to the present invention are useful for removing a bridge such as a bridge along a river.

橋梁施工用台船を示す説明図である。It is explanatory drawing which shows the trolley for bridge construction. 橋梁施工用台船を示す説明図である。It is explanatory drawing which shows the trolley for bridge construction. 実施例1における橋梁支持状態を示す側面図である。It is a side view which shows the bridge support state in Example 1. FIG. 実施例1における橋梁せり上げ状態を示す側面図である。It is a side view which shows the bridge up state in Example 1. FIG. 実施例1における橋梁の水平移動状態を示す側面図である。It is a side view which shows the horizontal movement state of the bridge in Example 1. FIG. 実施例1における橋梁の解体状態を示す側面図である。It is a side view which shows the dismantling state of the bridge in Example 1. FIG. 実施例1における橋梁支持状態を示す側面図である。It is a side view which shows the bridge support state in Example 1. FIG. 実施例1における橋梁せり上げ、水平移動、および解体状態を示す側面図である。It is a side view which shows the bridge uplift, horizontal movement, and the dismantling state in Example 1. 実施例1における橋梁支持状態および支柱撤去の様子を示す側面図である。It is a side view which shows the bridge support state in Example 1, and the mode of support | pillar removal. 実施例1における橋梁支持状態を示す側面図である。It is a side view which shows the bridge support state in Example 1. FIG. 実施例1における橋梁せり上げ、および水平移動状態を示す側面図である。It is a side view which shows the bridge uplifting in Example 1, and a horizontal movement state. 実施例1において橋梁が交差するときの橋梁撤去工法を示す側面図である。It is a side view which shows the bridge removal construction method when a bridge cross | intersects in Example 1. FIG. 実施例1において橋梁が交差するときの橋梁撤去工法を示す側面図である。It is a side view which shows the bridge removal construction method when a bridge cross | intersects in Example 1. FIG. 実施例1において橋梁が交差するときの橋梁撤去工法を示す側面図である。It is a side view which shows the bridge removal construction method when a bridge cross | intersects in Example 1. FIG. 実施例2における橋梁撤去工法を示す側面図である。It is a side view which shows the bridge removal construction method in Example 2. FIG. 実施例2における橋梁撤去工法を示す側面図である。It is a side view which shows the bridge removal construction method in Example 2. FIG.

符号の説明Explanation of symbols

10、21-1〜21-4 橋梁施工用台船(台船)
11 杭
12 仮受け構台
13 昇降装置
14 エンドレスローラ
20 橋梁(第1の橋梁)
20−1〜20−n ブロック単位に撤去される予定の橋梁
22 橋(第2の橋梁)
23 支持装置を有した車両
P1 支柱
10, 21-1 to 21-4 Bridge ship for bridge construction (base ship)
11 Pile 12 Temporary receiving frame 13 Lifting device 14 Endless roller 20 Bridge (first bridge)
20-1 to 20-n Bridges planned to be removed in block units 22 Bridge (second bridge)
23 Vehicle P1 Prop with Support Device

Claims (7)

少なくとも一部が河川に設置された橋梁の撤去または架設に用いられる橋梁施工用台船において、
前記橋梁施工用台船を所定の位置で高さ方向と水平方向に固定する台船固定手段と、
前記橋梁施工用台船上に設置され、前記橋梁の下部に当接され、支持すると共に、前記橋梁が切り取られた後に、前記橋梁を上下に移動可能とする支持昇降手段と、
前記橋梁施工用台船の自重によって河川に沈まないようにする支持手段と、
を有することを特徴とする橋梁施工用台船。
In bridge construction trolleys used to remove or construct bridges at least partially installed in rivers,
A trolley fixing means for fixing the bridge construction trolley at a predetermined position in a height direction and a horizontal direction;
A support elevating means installed on the bridge construction carriage, abutting and supporting the lower part of the bridge, and allowing the bridge to move up and down after the bridge is cut;
Support means for preventing the bridge construction sinker from sinking into the river due to its own weight;
A bridge carrier for bridge construction, characterized by comprising:
前記支持昇降手段は、前記橋梁の下部との当接部に前記橋梁を水平方向にスライドさせるスライド手段を有していることを特徴とする請求項1に記載の橋梁施工用台船。   2. The bridge construction trolley according to claim 1, wherein the support elevating means includes slide means for sliding the bridge in a horizontal direction at a contact portion with a lower portion of the bridge. 施工用台船は、組立式であることを特徴とする請求項1または2に記載の橋梁施工用台船。   3. The bridge construction carrier according to claim 1, wherein the construction carrier is an assembly type. 少なくとも一部が河川に設置された橋梁を撤去する橋梁撤去工法において、
請求項2に記載の橋梁施工用台船を前記橋梁の撤去予定部分の下部に移動させ、河川に固定する工程と、
前記支持昇降手段によって前記撤去予定部分の下部を支持する工程と、
前記撤去予定部分を前記橋梁から切断する工程と、
前記支持昇降手段によって前記撤去予定部分を下方に移動させる工程と、
前記スライド手段によって前記撤去予定部分をスライド移動させる工程と、
を含むことを特徴とする橋梁撤去工法。
In the bridge removal method to remove at least part of the bridge installed in the river,
Moving the bridge construction carrier according to claim 2 to a lower part of the bridge removal planned portion and fixing the bridge to a river;
A step of supporting the lower part of the part to be removed by the support lifting means;
Cutting the part to be removed from the bridge;
A step of moving the part to be removed downward by the support lifting means;
Sliding the removal scheduled portion by the sliding means;
Bridge removal method characterized by including.
少なくとも一部が河川に設置された橋梁を撤去する橋梁撤去工法において、
請求項2に記載の橋梁施工用台船を前記橋梁の撤去予定部分の下部に移動させ、河川に固定する工程と、
前記支持昇降手段によって前記撤去予定部分の下部を支持する工程と、
前記撤去予定部分を前記橋梁から切断する工程と、
前記支持昇降手段によって前記撤去予定部分を前記橋梁よりも高い位置に移動させる工程と、
前記撤去予定部分を前記橋梁の上面に載るように、水平方向にスライドさせる工程と、
を含むことを特徴とする橋梁撤去工法。
In the bridge removal method to remove at least part of the bridge installed in the river,
Moving the bridge construction carrier according to claim 2 to a lower part of the bridge removal planned portion and fixing the bridge to a river;
A step of supporting the lower part of the part to be removed by the support lifting means;
Cutting the part to be removed from the bridge;
Moving the part to be removed to a position higher than the bridge by the supporting lifting means;
Sliding in a horizontal direction so that the part to be removed is placed on the upper surface of the bridge;
Bridge removal method characterized by including.
前記撤去予定部分を前記橋梁の上面に載るように、水平方向にスライドさせる工程の後に、
前記橋梁の上で前記撤去予定部分を解体する工程と、
前記解体した前記撤去予定部分を撤去する工程と、
を含むことを特徴とする請求項5に記載の橋梁撤去工法。
After the step of sliding horizontally so that the part to be removed is placed on the upper surface of the bridge,
Dismantling the part to be removed on the bridge;
Removing the dismantled part to be removed,
The bridge removal method according to claim 5, comprising:
少なくとも一部が河川に設置された第1の橋梁があり、前記河川に掛かる別の第2の橋梁が前記第1の橋梁の下方にある場合における橋梁撤去工法において、
前記第2の橋梁の上方にある前記第1の橋梁を撤去し、
続いて、前記第1の橋梁の下方に前記第2の橋梁がない部分では、請求項4乃至6のいずれか一つの橋梁撤去工法により前記橋梁を撤去する工程と、
を含むことを特徴とする橋梁撤去工法。
In the bridge removal method in the case where there is a first bridge at least partially installed in a river and another second bridge over the river is below the first bridge,
Removing the first bridge above the second bridge;
Subsequently, in a portion where the second bridge is not present below the first bridge, the step of removing the bridge by the bridge removing method according to any one of claims 4 to 6,
Bridge removal method characterized by including.
JP2006153977A 2006-06-01 2006-06-01 Bridge removal method Active JP4727504B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2006153977A JP4727504B2 (en) 2006-06-01 2006-06-01 Bridge removal method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2006153977A JP4727504B2 (en) 2006-06-01 2006-06-01 Bridge removal method

Publications (2)

Publication Number Publication Date
JP2007321475A true JP2007321475A (en) 2007-12-13
JP4727504B2 JP4727504B2 (en) 2011-07-20

Family

ID=38854530

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2006153977A Active JP4727504B2 (en) 2006-06-01 2006-06-01 Bridge removal method

Country Status (1)

Country Link
JP (1) JP4727504B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102008060388A1 (en) 2007-12-13 2009-06-18 Keyence Corporation Image processing control unit and test support system
JP2009287356A (en) * 2008-06-02 2009-12-10 Kajima Corp Removing method of structure with leg
CN102409623A (en) * 2011-09-05 2012-04-11 山东中宏路桥建设有限公司 Floating bridge dismantling method
CN113173114A (en) * 2021-05-10 2021-07-27 山东交通学院 Material transfer device for bridge construction
CN113215999A (en) * 2021-05-20 2021-08-06 中铁上海工程局集团有限公司 Auxiliary construction platform and using method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07247702A (en) * 1994-03-14 1995-09-26 Mitsubishi Heavy Ind Ltd Pullback construction method for removal and disassembly of bridge
JPH10167176A (en) * 1996-12-13 1998-06-23 Toa Tekko Kk Repair spud pontoon for pile or column-like structure and method for using the same
JPH10237823A (en) * 1997-02-27 1998-09-08 Nkk Corp Method for replacing overhead bridge
JPH10280328A (en) * 1997-04-01 1998-10-20 Nkk Corp Removal and erection method for bridge and pontoon equipment used to the method
JPH11172628A (en) * 1997-12-16 1999-06-29 Ishikawajima Harima Heavy Ind Co Ltd Device for continuously sending out bridge girder
JP2001253388A (en) * 2000-03-10 2001-09-18 Hitachi Zosen Corp Floating body for operation, and method for constructing and removing structure using it
JP2003291886A (en) * 2002-04-03 2003-10-15 Kuroyanagi Komuten:Kk Knockdown barge type platform
JP2004332222A (en) * 2003-04-30 2004-11-25 Mitsubishi Heavy Ind Ltd Rebuilding construction method for bridge and bridge
JP2006028739A (en) * 2004-07-12 2006-02-02 Kuramoto Tekko Kk Dust collector

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07247702A (en) * 1994-03-14 1995-09-26 Mitsubishi Heavy Ind Ltd Pullback construction method for removal and disassembly of bridge
JPH10167176A (en) * 1996-12-13 1998-06-23 Toa Tekko Kk Repair spud pontoon for pile or column-like structure and method for using the same
JPH10237823A (en) * 1997-02-27 1998-09-08 Nkk Corp Method for replacing overhead bridge
JPH10280328A (en) * 1997-04-01 1998-10-20 Nkk Corp Removal and erection method for bridge and pontoon equipment used to the method
JPH11172628A (en) * 1997-12-16 1999-06-29 Ishikawajima Harima Heavy Ind Co Ltd Device for continuously sending out bridge girder
JP2001253388A (en) * 2000-03-10 2001-09-18 Hitachi Zosen Corp Floating body for operation, and method for constructing and removing structure using it
JP2003291886A (en) * 2002-04-03 2003-10-15 Kuroyanagi Komuten:Kk Knockdown barge type platform
JP2004332222A (en) * 2003-04-30 2004-11-25 Mitsubishi Heavy Ind Ltd Rebuilding construction method for bridge and bridge
JP2006028739A (en) * 2004-07-12 2006-02-02 Kuramoto Tekko Kk Dust collector

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102008060388A1 (en) 2007-12-13 2009-06-18 Keyence Corporation Image processing control unit and test support system
JP2009287356A (en) * 2008-06-02 2009-12-10 Kajima Corp Removing method of structure with leg
CN102409623A (en) * 2011-09-05 2012-04-11 山东中宏路桥建设有限公司 Floating bridge dismantling method
CN113173114A (en) * 2021-05-10 2021-07-27 山东交通学院 Material transfer device for bridge construction
CN113215999A (en) * 2021-05-20 2021-08-06 中铁上海工程局集团有限公司 Auxiliary construction platform and using method thereof

Also Published As

Publication number Publication date
JP4727504B2 (en) 2011-07-20

Similar Documents

Publication Publication Date Title
KR101230424B1 (en) Structure for transporting, installing and dismantling the elements of a fixed oil platform and methods for using said structure
JP6421201B2 (en) Method for building a bridge and apparatus for building a bridge
KR102033794B1 (en) Offshore wind turbine foundation, corresponding offshore wind turbine and method for their installation on site
JP2011111155A (en) Foundation construction platform used in beach or offshore area
US20110305521A1 (en) Movable brace frame for self-installing platform
JP4727504B2 (en) Bridge removal method
CN102337736A (en) Installation process of upper module on offshore oil platform
KR101659500B1 (en) bridge constructing machine and the method of constructing bridge
CN111039169A (en) Ship equipment module hoisting method
CN101806053B (en) Integral installation method of cantilever beams of self lifting type well drilling platform
CN102409650A (en) Installation method of shallow water ocean jacket platform
KR101160273B1 (en) Straddle carrier for bridge construction
CN107499453B (en) Ocean platform device mounting system
CN103964300B (en) Jacking type increases equipment
JP4796411B2 (en) Bridge removal method
KR20130026102A (en) Installation method of bridge structure having long span
CN105692449A (en) Method for spud leg lengthening and folding of self-elevating drilling platform
TWI570047B (en) The Manufacturing Method and Disassembling Method of Giant Crane Crane
JP5555272B2 (en) Construction method for offshore wind power generation facilities
JP4884082B2 (en) Bridge replacement method
CN201128882Y (en) Lifting and supporting brackets integrated construction device for bridge arch rib
CN105926466A (en) Device and construction method for steel truss bridge integral transporting
KR20130117171A (en) Cone mounting method of top side deck
JPH10147912A (en) Method for removing and erecting bridge
JP2005263406A (en) Inclination angle adjusting device and inclination angle adjusting method of crawler crane

Legal Events

Date Code Title Description
A625 Written request for application examination (by other person)

Free format text: JAPANESE INTERMEDIATE CODE: A625

Effective date: 20081208

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20101001

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110118

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110318

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20110412

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20110413

R150 Certificate of patent or registration of utility model

Ref document number: 4727504

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140422

Year of fee payment: 3

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250