JP2001032271A - Work execution method of cast-in-place concrete pile having long steel frame therein - Google Patents
Work execution method of cast-in-place concrete pile having long steel frame thereinInfo
- Publication number
- JP2001032271A JP2001032271A JP11210759A JP21075999A JP2001032271A JP 2001032271 A JP2001032271 A JP 2001032271A JP 11210759 A JP11210759 A JP 11210759A JP 21075999 A JP21075999 A JP 21075999A JP 2001032271 A JP2001032271 A JP 2001032271A
- Authority
- JP
- Japan
- Prior art keywords
- slime
- pipe
- treatment
- pile
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】この発明は、例えば構真柱そ
の他の鉄骨鉄筋コンクリート造杭(以下、SRC杭と略
す場合がある。)を構築する施工技術の分野に属し、さ
らに言えば、スライムが孔底に沈降することを防止して
先端支持性能を確保し、並びにスライムがコンクリート
中に混入することによるコンクリートの品質低下を防止
するSRC場所打ちコンクリート杭の施工方法に関す
る。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention belongs to the field of construction technology for constructing, for example, steel columns and other steel reinforced concrete piles (hereinafter, may be abbreviated as SRC piles). The present invention relates to a method for constructing an SRC cast-in-place concrete pile that prevents sinking to the bottom to secure tip support performance and prevents deterioration of concrete quality due to slime mixed into concrete.
【0002】[0002]
【従来の技術】従来、場所打ちコンクリート杭の施工に
おいては、安定液を用いたアースドリル工法などにより
杭孔を削孔しているが、掘り屑やスライムが孔底に沈降
することは周知である。コンクリートの打設時に、孔底
にスライムが残留していると、杭の先端支持性能が損な
われ、また、スライムがコンクリート中に混入してその
品質を低下させるので、通常、事前に一次、二次のスラ
イム処理を行うのが一般的である。しかし、現状なかな
か狙い通りに適切なスライム処理の効果を上げていな
い。2. Description of the Related Art Conventionally, in the construction of cast-in-place concrete piles, pile holes are drilled by an earth drill method using a stabilizing solution. However, it is well known that excavation dust and slime settle at the bottom of the hole. is there. If slime remains at the bottom of the hole when casting concrete, the tip support performance of the pile will be impaired, and slime will mix into the concrete and reduce its quality. The following slime treatment is generally performed. However, the slime treatment has not been effective as intended.
【0003】具体的に、従来一般のアースドリル工法に
より逆打ち工法のための構真柱を構築する場合につい
て、図6A〜Kに例示した現場打ちコンクリート杭の施
工方法を工程順に概説する。[0003] Concretely, in the case of constructing a straight pillar for a reverse hitting method by a conventional general earth drilling method, the method of constructing a cast-in-place concrete pile illustrated in Figs.
【0004】図6Aはアースドリル1による先行掘削の
段階を示し、Bはケーシング2を建て込み、安定液3を
注入した段階を示す。Cは杭孔軸部の掘削段階、Dは拡
底掘削機構4による拡底部掘削の段階を示している。E
は削孔完了後の第一次スライム処理の段階を示してい
る。この第一次スライム処理は、通例底浚い用バケット
を使用し、孔底に沈降した掘り屑やスライムを除去する
底浚いとして行われる。FIG. 6A shows a stage of pre-drilling by the earth drill 1, and FIG. 6B shows a stage where the casing 2 is erected and the stabilizer 3 is injected. C indicates the stage of excavation of the shaft portion of the pile hole, and D indicates the stage of excavation of the expanded bottom by the expanded bottom excavation mechanism 4. E
Indicates the stage of the primary slime treatment after the completion of drilling. This primary slime treatment is usually performed using a bottom dredge bucket as a bottom dredge for removing digging debris and slime settled at the bottom of the hole.
【0005】図6Fは杭孔内へ鉄筋籠5の建て込みを行
った段階を示し、Gは中心部へトレミー管6を挿入して
スライムの存在及び量を測定する段階を示す。図6Hは
第二次スライム処理の段階を示す。この第二次スライム
処理は、前記のトレミー管6を用いて沈降スライムを孔
外に吸引、排除する水中ポンプ方式、又はエアーリフト
方式などによる処理、或いは撹拌翼などを使用して機械
的に沈降スライムを撹拌し孔外へ排除する処理などが多
種多様に行われる。[0005] Fig. 6F shows a stage in which the reinforcing cage 5 is erected in the pile hole, and G shows a stage in which the presence and amount of the slime are measured by inserting the tremy tube 6 into the center. FIG. 6H shows the stage of the secondary slime treatment. This secondary slime treatment is performed by using a submersible pump method or an air lift method that sucks and removes sedimentation slime out of the hole using the tremy tube 6, or mechanically sediments using a stirring blade or the like. Various processes such as stirring the slime to remove the slime out of the hole are performed.
【0006】例えば特開昭52−8610号公報にはエ
アーリフトポンプによるスライム処理の方法が開示さ
れ、特開昭58−98525号公報及び特公平6−19
136号公報には、トレミー管の下端部からウオーター
ジエットを噴射してスライムを除去する方法が開示され
ている。特開平5−247940号公報にはサクション
ポンプなどによりスライム処理専用パイプを通じてスラ
イムを吸い上げて排除する方法が開示されている。For example, Japanese Patent Application Laid-Open No. Sho 52-8610 discloses a method of slime treatment using an air lift pump, which is disclosed in Japanese Patent Application Laid-Open No. 58-98525 and Japanese Patent Publication No. 6-19.
No. 136 discloses a method of removing slime by injecting a water jet from a lower end of a tremy tube. Japanese Patent Application Laid-Open No. Hei 5-247940 discloses a method of sucking and removing slime through a slime processing pipe using a suction pump or the like.
【0007】図6Iは、上記の第二次スライム処理を行
った後直ちに、前記のトレミー管6により孔底から順に
コンクリート打設を進める段階を示している。そして、
コンクリート打設を完了後は直ちに、図6Jのように構
真柱7の建て込みを行い、更に同図Kのようにケーシン
グ2の引き抜きと埋め戻し8を行って杭を完成する。FIG. 6I shows a stage in which concrete is sequentially poured from the bottom of the hole by the tremy tube 6 immediately after the secondary slime treatment is performed. And
Immediately after the completion of the concrete casting, the pillars 7 are erected as shown in FIG. 6J, and then the casing 2 is pulled out and backfilled 8 as shown in FIG.
【0008】[0008]
【本発明が解決しようとする課題】図6A〜Kに示した
従来の施工手順から明らかなように、第二次スライム処
理(図6H)において、トレミー管先端から沈降スライ
ムを吸引できる範囲はせいぜい管先端近傍に限られるた
め、杭孔内に鉄筋籠5以外は何もない(特に中心部は広
く空いている)状態でトレミー管先端を孔底全体にまん
べんなく移動させて沈降スライムを可能な限り吸引排除
するように行う。そして、第二次スライム処理後直ちに
コンクリート打設を進めることが条件である。As is clear from the conventional construction procedure shown in FIGS. 6A to 6K, in the secondary slime treatment (FIG. 6H), at most, the range in which sedimentation slime can be sucked from the tip of the tremie pipe is at most. Since there is nothing except the reinforcing bar 5 in the pile hole (especially the center is widely open), the tip of the tremee pipe is moved evenly over the entire bottom of the hole to reduce the sedimentation slime as much as possible. Perform so as to eliminate the suction. And it is a condition that concrete placement is immediately proceeded after the secondary slime treatment.
【0009】ところが、本発明のテーマである、孔底に
届くほど長い構真柱(又は通常の鉄骨鉄筋コンクリート
構造の構造用鉄骨、以下これを長尺鉄骨という。)を建
て込む場合には、その長さ故にコンクリート打設前に予
め長尺鉄骨を適正位置へ建て込んでおく必要がある。[0009] However, when a straight pillar (or a structural steel frame of a normal steel-framed reinforced concrete structure, hereinafter referred to as a long steel frame), which is the theme of the present invention, is long enough to reach the hole bottom. Because of its length, it is necessary to pre-install a long steel frame at an appropriate position before placing concrete.
【0010】従って、その場合の施工手順としては、
第二次スライム処理を行った後直ちに長尺鉄骨の建て込
みを行い、速やかにコンクリート打設の工程に進む手順
と、長尺鉄骨を建て込んだ後に第二次スライム処理を
行い、コンクリート打設へと進む手順、のいずれかを選
択するほかはない。Therefore, the construction procedure in that case is as follows:
Immediately after the secondary slime treatment, a long steel frame is erected and immediately proceed to the concrete casting process.After the long steel frame is erected, the second slime treatment is performed and concrete is cast. There is no choice but to choose one of the steps to go to.
【0011】しかし、上記の手順は、長尺鉄骨である
が故にその建て込み工程に時間がかかり、その間に再度
スライムが沈降する。上記従来技術の項で詳述したよう
に、既往の第二次スライム処理は、杭孔内に鉄筋籠以外
は何もない、孔中心部は広く空いている状態で行うこと
が条件である。即ち、邪魔な長尺鉄骨が建て込まれた状
態ではトレミー管先端を孔底全体に移動させることはで
きないから、再度孔底に沈降したスライムの多くが残留
することになり、それを完全に除去する方法、手段は現
状無いから、手順の実施は困難である。However, the above-mentioned procedure is a long steel frame, so that the building process takes a long time, during which time the slime is settled again. As described in detail in the section of the related art, it is a condition that the existing secondary slime treatment is performed in a state where there is nothing other than the reinforcing rod cage in the pile hole and the hole center is widely open. In other words, the tip of the tremy tube cannot be moved to the entire bottom of the hole when the long steel frame is in the way, so much of the slime that has settled at the bottom of the hole will remain and be completely removed. Since there is no method or means to perform the procedure at present, it is difficult to implement the procedure.
【0012】の手順もまたしかりで、杭孔内に邪魔な
長尺鉄骨が建て込まれた状態で、孔底に沈降したスライ
ムを完全に除去する第二次スライム処理の方法、手段が
無い以上、やはりこの手順の実施も困難である。[0012] The procedure of the above is also based on the fact that there is no secondary slime treatment method and means for completely removing the slime settled at the bottom of the hole in the state where the obstructive long steel frame is built in the pile hole. Again, implementation of this procedure is also difficult.
【0013】本発明の目的は、掘削した杭孔内の第二次
スライム処理を行った後に、コンクリート打設に先行し
て長尺鉄骨が建て込むことを前提に、第二次スライム処
理後からコンクリート打設までの間にスライムが孔底に
沈降することを防止し、杭の先端支持性能と健全性を十
分に確保できる、長尺鉄骨を入れる現場打ちコンクリー
ト杭の施工方法を提供することである。An object of the present invention is to perform a secondary slime treatment in an excavated pile hole, and then, after the secondary slime treatment, on the premise that a long steel frame is erected before concrete placing. By providing a construction method for cast-in-place concrete piles that can be used to prevent the slime from sinking to the bottom of the hole before concrete placement and ensure sufficient tip support performance and soundness. is there.
【0014】本発明の次の目的は、第二次スライム処理
後からコンクリート打設までの間、孔内の安定液を所定
の流速で対流又は循環させてスライムが孔底に沈降する
ことを防止し、或いは同時にスライムの除去までも行っ
て、杭の先端支持性能を確保し、また、スライムがコン
クリート中に混入してその品質が低下することを防止す
る、長尺鉄骨を入れる現場打ちコンクリート杭の施工方
法を提供することである。A second object of the present invention is to prevent the slime from settling at the bottom of the hole by convection or circulation of the stable liquid in the hole at a predetermined flow rate from after the secondary slime treatment to concrete placement. Cast-in-place concrete piles with long steel frames to secure the tip support performance of piles and to prevent slime from being mixed into concrete and reducing its quality by removing slime at the same time. Is to provide a construction method.
【0015】[0015]
【課題を解決するための手段】上述の課題を解決するた
めの手段として、請求項1に記載した発明に係る長尺入
れる現場打ちコンクリート杭の施工方法は、地盤に杭孔
を掘削し、スライムの処理をし、鉄筋を建て込み、更に
鉄骨を建て込んで構築される現場打ちコンクリート杭の
施工方法において、杭孔を掘削し、第一次のスライム処
理を行った杭孔の中に後記鉄筋籠の外周に位置する配置
でスライム処理用パイプを設置し、鉄筋籠を建て込んだ
後に第二次スライム処理を行い、その後前記スライム処
理用パイプを通じてスライムが安定液中に浮遊する状態
とする第三次のスライム処理を開始し、同第三次スライ
ム処理を継続したまま、杭孔中心部に孔底へ届く長さの
長尺鉄骨を建て込み、トレミー管等により孔底からコン
クリート打設を開始した後速やかに第三次スライム処理
を終了し、スライム処理用パイプを地上へ回収してコン
クリート打設を完成することをそれぞれ特徴とする。According to a first aspect of the present invention, there is provided a method for constructing a long cast-in-place concrete pile, comprising: excavating a pile hole in the ground; In the construction method of cast-in-place concrete piles constructed by embedding and reinforcing steel, and further embedding steel frames, the excavation of pile holes A slime treatment pipe is installed at an arrangement located on the outer periphery of the basket, a secondary slime treatment is performed after the reinforcing cage is built, and then the slime is suspended in the stable liquid through the slime treatment pipe. The tertiary slime treatment is started, and while the tertiary slime treatment is continued, a long steel frame that reaches the bottom of the pile is erected at the center of the pile hole, and concrete is poured from the bottom of the hole using a tremy tube or the like. Open Quickly exit the tertiary slime treatment after, to recover the slime treatment pipe to the ground and, respectively, characterized in that to complete the concreting.
【0016】請求項2記載の発明は、請求項1に記載し
た長尺鉄骨を入れる現場打ちコンクリート杭の施工方法
において、スライム処理用パイプを通じてスライムが安
定液中に浮遊する状態とする第三次スライム処理は、ス
ライム処理用パイプを、先端部にエア吹き出し孔を有す
るエア管となし、このエア管に地上から圧縮空気を供給
し、空気泡の上昇によって安定液を対流させることを特
徴とする。According to a second aspect of the present invention, in the method for constructing a cast-in-place concrete pile for inserting a long steel frame according to the first aspect, the slime is suspended in a stable liquid through a slime treatment pipe. The slime treatment is characterized in that the slime treatment pipe is an air pipe having an air blowing hole at the tip, and compressed air is supplied to the air pipe from the ground, and the stable liquid is convected by rising air bubbles. .
【0017】請求項3記載の発明は、請求項1に記載し
た長尺鉄骨を入れる現場打ちコンクリート杭の施工方法
において、スライム処理用パイプを通じてスライムが安
定液中に浮遊する状態とする第三次スライム処理は、ス
ライム処理用パイプの上部に水中ポンプを接続し、前記
水中ポンプを運転してパイプ先端から安定液を吸引さ
せ、杭頭部において孔内に戻し対流させることを特徴と
する。According to a third aspect of the present invention, in the method for constructing a cast-in-place concrete pile for inserting a long steel frame according to the first aspect, the slime is suspended in a stable liquid through a slime treatment pipe. The slime treatment is characterized in that a submersible pump is connected to the upper part of the slime treatment pipe, and the submersible pump is operated to suck the stable liquid from the pipe tip and return to the hole at the pile head for convection.
【0018】請求項4記載の発明は、請求項1に記載し
た長尺鉄骨を入れる現場打ちコンクリート杭の施工方法
スライム処理用パイプを通じてスライムが安定液中に浮
遊する状態とする第三次スライム処理は、スライム処理
用パイプの上部をポンプ及びスライム除去タンクと接続
し、同パイプの先端から安定液を吸引させ、スライム除
去タンクへ戻した後、同タンクから出る安定液を杭頭部
において孔内へ供給し循環させることを特徴とする。According to a fourth aspect of the present invention, there is provided a method for constructing a cast-in-place concrete pile into which a long steel frame according to the first aspect is put. A third slime treatment in which slime is suspended in a stable liquid through a slime treatment pipe. Connects the upper part of the slime treatment pipe to the pump and the slime removal tank, sucks the stable liquid from the end of the pipe, returns it to the slime removal tank, and then returns the stable liquid from the tank to the hole at the pile head. And circulate it.
【0019】請求項5記載の発明は、請求項1に記載し
た長尺鉄骨を入れる現場打ちコンクリート杭の施工方法
において、スライム処理用パイプを通じてスライムが安
定液中に浮遊する状態とする第三次スライム処理は、杭
頭部から吸引した安定液をスライム除去タンクへ戻した
後、同タンクから出る安定液をスライム処理用パイプの
先端から孔底付近へ供給して循環させることを特徴とす
る。According to a fifth aspect of the present invention, in the method for constructing a cast-in-place concrete pile into which a long steel frame is to be put according to the first aspect, a slime is suspended in a stable liquid through a slime treatment pipe. The slime treatment is characterized in that the stable liquid sucked from the pile head is returned to the slime removal tank, and then the stable liquid discharged from the tank is supplied from the tip of the slime processing pipe to the vicinity of the hole bottom and circulated.
【0020】[0020]
【発明の実施の形態】図1は、請求項1に記載した発明
に係る長尺鉄骨を入れる現場打ちコンクリート杭施工方
法の実施形態を枢要な工程順に示している。但し、本発
明もまた、地盤に杭孔を掘削し、スライムの処理をし、
鉄筋籠を建て込み、更に鉄骨を建て込んで構築する現場
打ちコンクリート杭の施工方法であるから、図6の従来
例と多く共通する。そこで図1は、共通する前半の工程
の図示は省略した。図1a〜gは第一次スライム処理の
工程の段階から示している。DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 shows an embodiment of a cast-in-place concrete pile construction method for inserting a long steel frame according to the first aspect of the present invention in the order of essential steps. However, the present invention also excavates a pile hole in the ground, treats slime,
Since this is a construction method of a cast-in-place concrete pile in which a steel cage is built and a steel frame is further built, the method is common to the conventional example of FIG. Therefore, FIG. 1 omits the illustration of the common first half process. 1a to 1g show the stage of the first slime treatment process.
【0021】即ち、杭孔10を掘削し、周知の底浚いそ
の他の方法で図1aのように一次のスライム処理を行っ
た後、杭孔10の中に後記鉄筋籠5の外周に位置する配
置でスライム処理用パイプ11を1本以上複数本を、第
二次スライム処理に適切な配置で先行して挿入し設置す
る(図1b)。That is, after the pile hole 10 is excavated and subjected to a primary slime treatment as shown in FIG. 1A by a well-known bottom dredge or other method, the arrangement located on the outer periphery of the steel cage 5 in the pile hole 10 will be described. Then, one or more slime treatment pipes 11 are inserted and installed in advance in an appropriate arrangement for the secondary slime treatment (FIG. 1b).
【0022】つづいて図1cのように鉄筋籠5を建て込
む。更に杭孔中心部へトレミー管6を挿入し、同トレミ
ー管6を利用して孔底へ沈降したスライムを吸引排除す
る公知の二次スライム処理を行う(図1d)。Subsequently, as shown in FIG. 1c, the reinforcing bar cage 5 is built. Furthermore, a known secondary slime process is performed in which the tremy tube 6 is inserted into the center of the pile hole and the slime that has settled to the bottom of the hole is removed by suction using the tremy tube 6 (FIG. 1d).
【0023】その後直ちに、前記スライム処理用パイプ
11を通じてスライムが安定液中を浮遊して沈降しない
ようにする第三次のスライム処理を後で詳述する内容、
要領で開始する。この第三次スライム処理の状態を継続
したまま、杭孔10の中心部に、孔底へ届くほど長い長
尺鉄骨7を前記トレミー管と並列に、又は同トレミー管
と交代する関係にて所定の深さ位置まで建て込む(図1
e)。Immediately thereafter, a third slime treatment for preventing the slime from floating in the stabilizing solution and settling through the slime treatment pipe 11 will be described in detail below.
Start with the trick. While continuing the state of the tertiary slime treatment, a long steel frame 7 that is long enough to reach the bottom of the pile hole 10 is provided in the center of the pile hole 10 in parallel with the tremy tube or in a relationship to replace the tremy tube. To the depth of the building (Fig. 1
e).
【0024】しかる後に、前記長尺鉄骨7と並列に建て
込まれた前記トレミー管6等により孔底から順にコンク
リート打設を開始する。そして、上記のスライム処理用
パイプ11が打設コンクリート12の天端に埋まる以前
に、速やかに第三次スライム処理を終了し、同スライム
処理用パイプ11を引き上げて地上へ回収し、その一方
では前記のコンクリート打設を進めて完成する(図1
f)。Thereafter, concrete casting is started in order from the bottom of the hole by the tremy tube 6 or the like built in parallel with the long steel frame 7. Before the slime processing pipe 11 is buried in the top end of the cast concrete 12, the tertiary slime processing is immediately terminated, and the slime processing pipe 11 is pulled up and collected on the ground. The concrete is cast and completed (Fig. 1
f).
【0025】従って、第二次スライム処理の後、コンク
リート打設の工程が開始するまでの間は、第三次スライ
ム処理によってスライムが孔底に沈降することは確実に
防止される。よって先端支持性能に優れ、スライムに害
されないで品質良好なSRC現場打ちコンクリート杭の
構築ができる。Therefore, after the secondary slime treatment, until the concrete casting step starts, the slime is reliably prevented from settling at the bottom of the hole by the third slime treatment. Therefore, it is possible to construct an SRC cast-in-place concrete pile having excellent tip support performance and good quality without being affected by slime.
【0026】なお、最終的には図1gのようにケーシン
グ2の引き抜きと埋め戻し8を行ってSRC現場打ちコ
ンクリート杭を完成することは、図6の従来技術と同じ
である。Finally, as shown in FIG. 1g, the casing 2 is pulled out and backfilled 8 to complete the SRC cast-in-place concrete pile, which is the same as the prior art shown in FIG.
【0027】ところで、上記のようにスライム処理用パ
イプ11を通じてスライムを安定液中に浮遊させ沈降さ
せないようにする第三次スライム処理は、要するに安定
液を全体的に対流させ、又は循環させる方法によるので
あり、次のように実施される。By the way, the third slime treatment for suspending the slime in the stabilizing liquid through the slime processing pipe 11 so as not to settle out as described above is based on the method of convection or circulation of the stabilizing liquid as a whole. It is implemented as follows.
【0028】先ず図2は、スライム処理用パイプ11
を、先端部にエア吹き出し孔を有するエア管として構成
し、このエア管に地上から圧縮空気を供給し、空気泡の
上昇によって安定液を対流させる処理方法を示している
(請求項2記載の発明)。First, FIG. 2 shows a slime processing pipe 11.
Is configured as an air pipe having an air blowing hole at the tip end, and a processing method in which compressed air is supplied to the air pipe from the ground and a stable liquid is convected by rising air bubbles (claim 2). invention).
【0029】図3は、スライム処理用パイプ11の上部
に水中ポンプ13を設置し、この水中ポンプ13を運転
してスライム処理用パイプ11の先端から安定液を吸引
させ、それを杭頭部において孔内に戻して上から下向き
に対流させる処理方法を示している(請求項3記載の発
明)。FIG. 3 shows that a submersible pump 13 is installed above the slime processing pipe 11, and the submersible pump 13 is operated to suck a stable liquid from the tip of the slime processing pipe 11, and the stable liquid is sucked at the pile head. This shows a processing method of returning to the inside of the hole and causing convection downward from above (the invention according to claim 3).
【0030】図4は、スライム処理用パイプ11の上部
を吸い上げポンプを含むスライム除去タンク14と接続
し、同スライム処理用パイプ11の先端から安定液を吸
引させ、スライム除去タンク14へ戻す。そして、スラ
イムの除去を行った後に同タンク14から出る安定液
を、杭頭部において孔内へ供給して孔内の安定液全体を
上から下へと循環させる処理方法を示している(請求項
4記載の発明)。In FIG. 4, the upper part of the slime treatment pipe 11 is connected to a slime removal tank 14 including a suction pump, and the stable liquid is sucked from the tip of the slime treatment pipe 11 and returned to the slime removal tank 14. Then, there is shown a processing method in which the stable liquid discharged from the tank 14 after the removal of the slime is supplied into the hole at the pile head and the entire stable liquid in the hole is circulated from top to bottom. Item 4).
【0031】図5は、杭頭部から水中ポンプ13で吸引
した安定液を、やはりスライム除去タンク14へ戻す。
そして、スライムを除去して同タンク14から出る安定
液は、前記スライム処理用パイプ11の先端から孔底付
近へ供給して孔内の安定液を下から上へと循環させる処
理方法を示している(請求項5記載の発明)。FIG. 5 shows that the stable liquid sucked from the pile head by the submersible pump 13 is also returned to the slime removal tank 14.
Then, a processing method is shown in which the stable liquid that is removed from the tank 14 after removing the slime is supplied from the tip of the slime processing pipe 11 to the vicinity of the bottom of the hole, and the stable liquid in the hole is circulated from bottom to top. (The invention according to claim 5).
【0032】[0032]
【本発明が奏する効果】請求項1〜5に記載した発明に
係る長尺鉄骨を入れる現場打ちコンクリート杭の施工方
法は、第二次スライム処理の直後から長尺鉄骨を入れ、
コンクリートを打設するまでの間を、第三次スライム処
理によってスライムを安定液中に浮遊させ孔底に沈降す
ることを防止するので、杭の先端支持性能を確保し、ま
た、スライムがコンクリート中に混入することを防止し
て、品質、健全性が高いSRC場所打ちコンクリート杭
を構築することができる。According to the present invention, there is provided a method for constructing a cast-in-place concrete pile in which a long steel frame is inserted according to the present invention, wherein the long steel frame is inserted immediately after the secondary slime treatment.
Until the concrete is poured, the slime is suspended in the stabilizing liquid by the tertiary slime treatment to prevent the slime from settling at the bottom of the hole. And SRC cast-in-place concrete piles with high quality and soundness can be constructed.
【0033】特に、入念な第一次及び第二次のスライム
処理をした後は、安定液中に浮遊するスライムは細粒土
が主体であるから、小さな流速でも浮遊し易いので、ス
ライムの沈降を防止する効果が大きいから、長尺鉄骨が
存在し、空きスペースが小さくても安定液の対流又は循
環作用によりスライムが孔底に沈降することを確実に防
止できる。孔底だけに限らず、杭孔軸部に突起物や拡径
部が在っても、そこに沈降することもない。その上、ス
ライムの沈降を防止する第三次処理に格別な設備は無用
であり、新たな作業スペースを必要とする事なく、比較
的簡単な設備で実施できる。In particular, after the elaborate primary and secondary slime treatments, the slime floating in the stabilizing solution is mainly composed of fine-grained soil, and therefore easily floats even at a small flow rate. Therefore, even if the long steel frame is present and the empty space is small, it is possible to reliably prevent the slime from settling at the bottom of the hole due to the convection or circulation of the stable liquid. Not only at the bottom of the hole, but also when there is a protrusion or an enlarged diameter portion at the shaft portion of the pile hole, it does not settle there. In addition, no special equipment is required for the tertiary treatment for preventing slime sedimentation, and it can be performed with relatively simple equipment without requiring a new work space.
【図1】a〜gは請求項1記載の発明に係る施工方法の
枢要な工程を順に示した説明図である。1 (a) to 1 (g) are explanatory diagrams sequentially showing the essential steps of a construction method according to the first aspect of the present invention.
【図2】第三次スライム処理の実施形態を示した平面図
と断面図である。FIG. 2 is a plan view and a cross-sectional view illustrating an embodiment of a third slime treatment.
【図3】第三次スライム処理の異なる実施形態を示した
平面図と断面図である。FIG. 3 is a plan view and a cross-sectional view showing different embodiments of the third slime processing.
【図4】第三次スライム処理の異なる実施形態を示した
平面図と断面図である。FIG. 4 is a plan view and a sectional view showing different embodiments of the third slime processing.
【図5】第三次スライム処理の更に異なる実施形態を示
した平面図と断面図である。FIG. 5 is a plan view and a sectional view showing still another embodiment of the third slime processing.
【図6】A〜Kは従来の施工方法の枢要な工程を順に示
した説明図である。FIGS. 6A to 6K are explanatory diagrams sequentially showing essential steps of a conventional construction method.
10 杭孔 5 鉄筋籠 11 スライム処理用パイプ 7 長尺鉄骨 6 トレミー管 12 コンクリート 13 水中ポンプ 14 スライム除去タンク 8 減衰装置 DESCRIPTION OF SYMBOLS 10 Pile hole 5 Reinforcing cage 11 Slime processing pipe 7 Long steel frame 6 Toremy pipe 12 Concrete 13 Submersible pump 14 Slime removal tank 8 Damping device
───────────────────────────────────────────────────── フロントページの続き (72)発明者 岡橋 稔 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 丸岡 正夫 千葉県印西市大塚一丁目5番地1 株式会 社竹中工務店技術研究所内 (72)発明者 川本 英一 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 土屋 敏明 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 (72)発明者 森 俊郎 東京都中央区銀座八丁目21番1号 株式会 社竹中工務店東京本店内 Fターム(参考) 2D041 AA01 BA14 BA44 DA03 EA04 EB02 2D045 AA02 AA04 BA04 CA11 CA23 ────────────────────────────────────────────────── ─── Continuing from the front page (72) Inventor Minoru Okahashi 1-5-1, Otsuka, Inzai City, Chiba Prefecture Inside the Technical Research Center, Takenaka Corporation (72) Inventor Masao Maruoka 1-5-1, Otsuka, Inzai City, Chiba Prefecture Inside Takenaka Corporation Technical Research Institute (72) Inventor Eiichi Kawamoto 8-21-1, Ginza, Chuo-ku, Tokyo Inside Tokyo Headquarters Takenaka Corporation (72) Inventor Toshiaki Tsuchiya Ginzahachi, Chuo-ku, Tokyo No. 21-1, Takenaka Corporation Tokyo Main Branch (72) Inventor Toshiro Mori 8-21-1, Ginza, Chuo-ku, Tokyo F-Terminal, Takenaka Corporation Tokyo Main Store F-term (reference) 2D041 AA01 BA14 BA44 DA03 EA04 EB02 2D045 AA02 AA04 BA04 CA11 CA23
Claims (5)
し、鉄筋を建て込み、更に鉄骨を建て込んで構築される
現場打ちコンクリート杭の施工方法において、 杭孔を掘削し、第一次のスライム処理を行った杭孔の中
に後記鉄筋籠の外周に位置する配置でスライム処理用パ
イプを設置し、鉄筋籠を建て込んだ後に第二次スライム
処理を行い、その後前記スライム処理用パイプを通じて
スライムが安定液中に浮遊する状態とする第三次のスラ
イム処理を開始し、同第三次スライム処理をを継続した
まま、杭孔中心部に孔底へ届く長さの長尺鉄骨を建て込
み、トレミー管等により孔底からコンクリート打設を開
始した後速やかに前記第三次スライム処理を終了し、ス
ライム処理用パイプを地上へ回収してコンクリート打設
を完成することをそれぞれ特徴とする、長尺鉄骨を入れ
る現場打ちコンクリート杭の施工方法。1. A method for constructing a cast-in-place concrete pile constructed by excavating a pile hole in the ground, treating slime, embedding a reinforcing bar, and further embedding a steel frame. A pipe for slime treatment is installed in the pile hole that has been subjected to the following slime treatment in an arrangement located on the outer periphery of the reinforcing rod cage, and the secondary slime processing is performed after the reinforcing cage is built, and then the slime processing is performed. Initiate the third slime treatment to make the slime float in the stable liquid through the pipe, and continue the third slime treatment, and reach the bottom of the hole at the center of the pile hole with a long steel frame After the concrete is started to be poured from the bottom of the hole using a tremy tube or the like, the tertiary slime treatment is immediately terminated, and the slime processing pipe is collected on the ground to complete the concrete placement. Construction method of cast-in-place concrete pile to put long steel frame.
安定液中に浮遊する状態とする第三次スライム処理は、
スライム処理用パイプを、先端部にエア吹き出し孔を有
するエア管となし、このエア管に地上から圧縮空気を供
給し、空気泡の上昇によって安定液を対流させることを
特徴とする、請求項1に記載した長尺鉄骨を入れる現場
打ちコンクリート杭の施工方法。2. A third slime treatment in which the slime floats in the stabilizing solution through the slime treatment pipe,
The slime processing pipe is an air pipe having an air outlet at an end thereof, and compressed air is supplied to the air pipe from the ground so that a stable liquid is convected by rising air bubbles. Construction method of cast-in-place concrete pile to put long steel frame described in section.
安定液中に浮遊する状態とする第三次スライム処理は、
スライム処理用パイプの上部に水中ポンプを接続し、前
記水中ポンプを運転してパイプ先端から安定液を吸引さ
せ、杭頭部において孔内に戻し対流させることを特徴と
する、請求項1に記載した長尺鉄骨を入れる現場打ちコ
ンクリート杭の施工方法。3. A third slime treatment in which the slime is suspended in the stabilizing solution through the slime treatment pipe,
The submersible pump is connected to the upper part of the slime processing pipe, and the submersible pump is operated to suck the stable liquid from the pipe tip and return to the inside of the hole at the pile head for convection. Construction method of cast-in-place concrete piles for placing long steel frames.
安定液中に浮遊する状態とする第三次スライム処理は、
スライム処理用パイプの上部をポンプ及びスライム除去
タンクと接続し、同パイプの先端から安定液を吸引さ
せ、スライム除去タンクへ戻した後、同タンクから出る
安定液を杭頭部において孔内へ供給し循環させることを
特徴とする、請求項1に記載した長尺鉄骨を入れる現場
打ちコンクリート杭の施工方法。4. A third slime treatment in which slime is suspended in a stabilizing solution through a slime treatment pipe,
The upper part of the slime treatment pipe is connected to a pump and a slime removal tank, and the stable liquid is sucked from the end of the pipe and returned to the slime removal tank, and then the stable liquid coming out of the tank is supplied into the hole at the pile head The method for constructing a cast-in-place concrete pile into which a long steel frame is inserted according to claim 1, wherein the pile is circulated.
安定液中に浮遊する状態とする第三次スライム処理は、
杭頭部から吸引した安定液をスライム除去タンクへ戻し
た後、同タンクから出る安定液をスライム処理用パイプ
の先端から孔底付近へ供給して循環させることを特徴と
する、請求項1に記載した長尺鉄骨を入れる現場打ちコ
ンクリート杭の施工方法。5. The third slime treatment in which the slime floats in the stabilizing solution through the slime treatment pipe,
The method according to claim 1, wherein after returning the stable liquid sucked from the pile head to the slime removal tank, the stable liquid discharged from the tank is supplied from the tip of the slime processing pipe to the vicinity of the hole bottom and circulated. Construction method of cast-in-place concrete pile to insert long steel frame described.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21075999A JP3878772B2 (en) | 1999-07-26 | 1999-07-26 | Construction method of cast-in-place concrete pile to put long steel frame |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP21075999A JP3878772B2 (en) | 1999-07-26 | 1999-07-26 | Construction method of cast-in-place concrete pile to put long steel frame |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2001032271A true JP2001032271A (en) | 2001-02-06 |
JP3878772B2 JP3878772B2 (en) | 2007-02-07 |
Family
ID=16594668
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP21075999A Expired - Fee Related JP3878772B2 (en) | 1999-07-26 | 1999-07-26 | Construction method of cast-in-place concrete pile to put long steel frame |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3878772B2 (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296612A (en) * | 2011-05-24 | 2011-12-28 | 天津二十冶建设有限公司 | Device and method for underwater pouring concrete in slurry retaining wall cast-in-situ bored pile |
CN104264679A (en) * | 2014-09-23 | 2015-01-07 | 国家电网公司 | Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles |
JP2017082416A (en) * | 2015-10-23 | 2017-05-18 | 鹿島建設株式会社 | Tremie pipe structure and pile construction method |
CN108086322A (en) * | 2017-12-25 | 2018-05-29 | 中冶交通建设集团有限公司 | The method removed mudcake device and pouring pile bearing capacity is improved using the device |
JP2018096169A (en) * | 2016-12-16 | 2018-06-21 | 鹿島建設株式会社 | Method for removing slime in cast-in-place concrete pile |
CN110258653A (en) * | 2019-05-31 | 2019-09-20 | 中国建筑第八工程局有限公司 | Basement pile foundation construction connects leading-in device and its construction method |
CN110700243A (en) * | 2019-10-25 | 2020-01-17 | 中航勘察设计研究院有限公司 | Method for treating pile bottom sediment of concrete cast-in-place pile |
CN118670352A (en) * | 2024-08-20 | 2024-09-20 | 贵州大学 | Hydraulic climbing form is with accurate measuring apparatu of level |
-
1999
- 1999-07-26 JP JP21075999A patent/JP3878772B2/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102296612A (en) * | 2011-05-24 | 2011-12-28 | 天津二十冶建设有限公司 | Device and method for underwater pouring concrete in slurry retaining wall cast-in-situ bored pile |
CN104264679A (en) * | 2014-09-23 | 2015-01-07 | 国家电网公司 | Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles |
CN104264679B (en) * | 2014-09-23 | 2016-03-30 | 国家电网公司 | A kind of electric power pylon basis heavy caliber Underwater pile construction method |
JP2017082416A (en) * | 2015-10-23 | 2017-05-18 | 鹿島建設株式会社 | Tremie pipe structure and pile construction method |
JP2018096169A (en) * | 2016-12-16 | 2018-06-21 | 鹿島建設株式会社 | Method for removing slime in cast-in-place concrete pile |
CN108086322A (en) * | 2017-12-25 | 2018-05-29 | 中冶交通建设集团有限公司 | The method removed mudcake device and pouring pile bearing capacity is improved using the device |
CN108086322B (en) * | 2017-12-25 | 2024-01-26 | 中冶交通建设集团有限公司 | Mud skin removing device and method for improving bearing capacity of cast-in-place pile by using same |
CN110258653A (en) * | 2019-05-31 | 2019-09-20 | 中国建筑第八工程局有限公司 | Basement pile foundation construction connects leading-in device and its construction method |
CN110700243A (en) * | 2019-10-25 | 2020-01-17 | 中航勘察设计研究院有限公司 | Method for treating pile bottom sediment of concrete cast-in-place pile |
CN118670352A (en) * | 2024-08-20 | 2024-09-20 | 贵州大学 | Hydraulic climbing form is with accurate measuring apparatu of level |
Also Published As
Publication number | Publication date |
---|---|
JP3878772B2 (en) | 2007-02-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4797031A (en) | Caisson sinking method | |
JP2010126996A (en) | Method for preventing lining body from floating up | |
JP2001032271A (en) | Work execution method of cast-in-place concrete pile having long steel frame therein | |
JPH05222729A (en) | Execution method for cast-in-place concrete pile, etc. | |
JP6378652B2 (en) | Underground continuous wall construction method | |
JP2002146811A (en) | Construction method for underwater structure foundation | |
JP4327639B2 (en) | Construction method of cast-in-place concrete pile | |
JPH0220720A (en) | Underground construction method by muddy water excavation | |
JP2640841B2 (en) | Slime treatment method in cast-in-place pile method | |
JPS59195925A (en) | Construction of on-site concrete pile | |
JPS5847823A (en) | Construction of in-place concrete pile | |
JPH10245843A (en) | Method of constructing cast in situ diaphragm wall just under underground obstruction | |
CN113404044A (en) | Hierarchical pore-forming construction method for rotary digging cast-in-place pile | |
JPS5918488B2 (en) | Slime processing method in stable liquid drilling method | |
JP2000130066A (en) | Construction method for vertical shaft | |
JPS6335767B2 (en) | ||
JP2874906B2 (en) | Shaft construction method | |
JPH059945A (en) | Underground skeleton constructing method | |
JPH10237865A (en) | Method for driving casing | |
JP2001336147A (en) | Rotary cap with pile top treatment function, pile top treatment method, and embedding method of pile | |
JPH08209687A (en) | Partial casing pile construction method | |
JP3375634B2 (en) | Caisson laying method and caisson | |
JP2971045B2 (en) | Casting method of bottom concrete in propulsion method | |
JPS5843523B2 (en) | Method for reducing pile head excess concrete of cast-in-place piles | |
JP2021123949A (en) | Drain device, and liquid drain method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20040618 |
|
A131 | Notification of reasons for refusal |
Free format text: JAPANESE INTERMEDIATE CODE: A131 Effective date: 20060606 |
|
A521 | Written amendment |
Free format text: JAPANESE INTERMEDIATE CODE: A523 Effective date: 20060803 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20061010 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20061106 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20101110 Year of fee payment: 4 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111110 Year of fee payment: 5 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20121110 Year of fee payment: 6 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20131110 Year of fee payment: 7 |
|
LAPS | Cancellation because of no payment of annual fees |