[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JP2874906B2 - Shaft construction method - Google Patents

Shaft construction method

Info

Publication number
JP2874906B2
JP2874906B2 JP21660989A JP21660989A JP2874906B2 JP 2874906 B2 JP2874906 B2 JP 2874906B2 JP 21660989 A JP21660989 A JP 21660989A JP 21660989 A JP21660989 A JP 21660989A JP 2874906 B2 JP2874906 B2 JP 2874906B2
Authority
JP
Japan
Prior art keywords
shaft
wall
continuous
caisson
retaining water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP21660989A
Other languages
Japanese (ja)
Other versions
JPH0381421A (en
Inventor
光昭 岩田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
KYOWA EKUSHIO KK
Original Assignee
KYOWA EKUSHIO KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by KYOWA EKUSHIO KK filed Critical KYOWA EKUSHIO KK
Priority to JP21660989A priority Critical patent/JP2874906B2/en
Publication of JPH0381421A publication Critical patent/JPH0381421A/en
Application granted granted Critical
Publication of JP2874906B2 publication Critical patent/JP2874906B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は立坑構築工法の係り、特にとう道工事のため
のシールド掘削機の発進箇所や到達箇所となる立坑を簡
易に構築することができるように改良した立坑構築工法
に関する。
DETAILED DESCRIPTION OF THE INVENTION [Industrial Application Field] The present invention relates to a shaft construction method, and in particular, can easily construct a shaft as a starting point and a reaching point of a shield excavator for road construction. Shaft construction method improved in this way.

〔従来の技術〕[Conventional technology]

最近のとう道工事は、大深度、高水圧となり、一連の
とう道工事の中では立坑施工の難易度が増すと同時に施
工条件も厳しくなっている。このような条件の下で行わ
れている従来の立坑構築工法としては、連続壁と逆巻工
法によるもの、あるいはニューマチックケーソン工法が
知られている。前者は地中に堀り進みながら側壁を構築
するもので、最初一定深さ掘削した後に、周壁に鉄筋の
建込みをしてコンクリートの打設・養生を行う工程を1
工程とし、順次掘り下げつつ前記工程を繰り返し施工し
て所望の深さの立坑を築造するものである。また、後者
の方法はケーソン下部室に圧気を供給して地下水圧とバ
ランスさせつつ掘削し、ケーソンの水平状態を保持させ
ながら所定深さまで沈埋させて設置し、ケーソンをその
まま立坑壁体として利用する。
Recent road construction has become deeper and higher water pressure, and in a series of road constructions, the difficulty of vertical shaft construction has increased and the construction conditions have become more severe. As a conventional shaft construction method performed under such conditions, a method using a continuous wall and a reverse winding method, or a pneumatic caisson method is known. In the former method, the side wall is constructed while digging into the ground. First, after excavating to a certain depth, the process of laying a reinforcing bar on the surrounding wall and placing and curing concrete is performed.
In this process, the above-described process is repeatedly performed while sequentially digging down to build a shaft having a desired depth. In the latter method, excavation is performed while supplying pressure air to the caisson lower chamber and balancing it with the groundwater pressure, submerging it to a predetermined depth while maintaining the horizontal state of the caisson, installing the caisson as it is as a shaft wall .

〔発明が解決しようとする課題〕[Problems to be solved by the invention]

ところが、上記従来の工法では、立坑壁体を順次下方
に構築する方法であって鉄筋の建込みも必要とされるた
め、工事期間が長期化してしなう問題がある。また、後
者は圧気用コンプレッサの設置により騒音振動が発生し
てしまい周辺への環境破壊を生じてしまうおそれがあっ
た。しかも土質によっては周辺地盤が沈下してしまうお
それもあった。なお、圧気ケーソン工法において、刃口
下部の地盤改良をなして刃口の傾き防止と自沈防止を行
いつつ、掘削沈設する方法の知られているが、圧気を利
用するために、作業効率の悪化を生じる問題は改善され
ていない。
However, the above-mentioned conventional construction method is a method of sequentially constructing a shaft wall below, and also requires the installation of a reinforcing bar, which causes a problem that the construction period is prolonged. In the latter case, there is a possibility that noise and vibration may be generated due to the installation of the compressed air compressor, and environmental destruction to the surroundings may occur. In addition, depending on the soil properties, the surrounding ground may sink. In the pneumatic caisson method, there is a method of excavating and sinking while improving the ground at the lower part of the cutting edge to prevent inclination and self-settling of the cutting edge.However, due to the use of compressed air, work efficiency deteriorates. The problem of causing is not improved.

本発明は、上記従来の問題点に着目し、立坑の構築の
ための工事期間の大幅な短縮を図ることができ、また、
施工時の振動・騒音等の発生がなく、周辺地盤への悪影
響も生じない有効な立坑構築工法を提供することを目的
とする。
The present invention focuses on the above-mentioned conventional problems, and can significantly reduce the construction period for building a shaft,
It is an object of the present invention to provide an effective shaft construction method that does not generate vibration or noise during construction and does not adversely affect the surrounding ground.

〔課題を解決するための手段〕[Means for solving the problem]

上記目的を達成するために、本発明に係る立坑構築工
法は、予め泥水固化法により立坑予定部の周囲を囲む連
続土留止水壁を形成した後に、前記連続土留止水壁の内
部にオープンケーソンを構築し、前記連続土留止水壁の
内部において前記ケーソンを沈設することにより立坑を
構築するように構成した。この場合において、前記連続
土留止水壁は立坑底部より下方に突出する根切り長さを
立坑幅長さ程度に設定し、立坑予定部内に水が回り込む
ことを防止し、オープンケーソン工法をそのまま適用で
きるようにしている。また、他の発明として、予め泥水
固化法により立坑予定部の周囲を囲む連続土留止水壁を
形成するとともに、この連続土留止水壁の底部にジェッ
トグラウト等の地盤改良方法により地盤部を形成して立
坑予定部を周囲地盤から分離し、その後に、前記連続土
留止水壁の内部にオープンケーソンを構築し、前記連続
土留止水壁の内壁面に沿って前記ケーソンを沈設するこ
とにより立坑を構築するように構成した。
In order to achieve the above object, a shaft construction method according to the present invention comprises forming a continuous soil retaining wall surrounding the planned shaft portion in advance by a mud solidification method, and then forming an open caisson inside the continuous soil retaining water wall. Was constructed, and the caisson was laid down inside the continuous retaining water wall to construct a shaft. In this case, the continuous earth retaining wall sets the root length protruding downward from the shaft bottom to about the shaft width length, prevents water from flowing into the planned shaft part, and applies the open caisson method as it is. I can do it. Further, as another invention, a continuous soil retaining wall surrounding the planned shaft is formed in advance by a mud solidification method, and a ground portion is formed at the bottom of the continuous soil retaining wall by a ground improvement method such as jet grout. And separating the planned shaft part from the surrounding ground, then constructing an open caisson inside the continuous retaining water wall and sinking the caisson along the inner wall surface of the continuous retaining water wall, Was configured to be built.

〔作用〕[Action]

上記構成によれば、最初に立坑予定部の周壁に沿って
連続土留止水壁を泥水固化法によって形成するため、鉄
筋の建込みやコンクリート打設がなく、早期硬化するた
め大幅な後期短縮作用がある。そして、連続土留止水壁
の内部においてその内壁に沿ってオープンケーソンを沈
設するので安定した沈埋施工を行うことができる。この
場合、連続土留止水壁の内壁とケーソン側壁との間隔を
ケーソン傾斜を許容する範囲に設定することで、沈下ガ
イド機能を持たせることができる。地盤が軟弱で高水圧
である場合には、連続土留止水壁の根切り長さをその地
盤水圧や立坑断面積から水の回り込みが発生しない程度
の長さにすることにより、オープンケーソン工法をその
まま適用できる。また、連続土留止水壁の下部にはジェ
ットグラウト等の地盤改良方法により地盤部を形成し、
連続土留止水壁と相俟って周辺地盤から立坑予定部が分
離遮蔽するように構成すれば、深い連続土留止水壁を形
成するより水回りの防止効果が得られる。このため地下
水の立坑予定部内への回り込みがなく、周辺地盤の沈下
等の悪影響を与えることもない。この囲まれた立坑予定
部にはオープンケーソンが構築され、連続土留止水壁の
内壁に沿って沈設するので、安定した沈埋が行われ、か
つコンプレッサの使用もないので騒音や振動、その他圧
気の送排気等に伴う周辺住民への影響もなく、迅速に施
工することができる。
According to the above configuration, since the continuous retaining water blocking wall is first formed by the muddy water solidification method along the peripheral wall of the planned shaft, there is no rebar construction or concrete casting, and it hardens early, so a large late shortening effect. There is. And, since the open caisson is laid down along the inner wall inside the continuous retaining water stop wall, stable burying work can be performed. In this case, by setting the interval between the inner wall of the continuous soil retaining water wall and the caisson side wall in a range in which the caisson inclination is allowed, a settlement guide function can be provided. If the ground is soft and has high water pressure, the open caisson method is adopted by setting the root length of the continuous soil retaining wall to such a length that water does not flow in from the ground water pressure and the cross section of the shaft. Applicable as it is. In addition, the ground part is formed by the ground improvement method such as jet grout at the lower part of the continuous soil retaining water wall,
If it is configured so that the planned shaft portion is separated and shielded from the surrounding ground in conjunction with the continuous soil retaining wall, the effect of preventing water rotation can be obtained as compared with the case where a deep continuous soil retaining water wall is formed. Therefore, groundwater does not flow into the planned shaft, and there is no adverse effect such as settlement of the surrounding ground. An open caisson is constructed in the enclosed shaft and is laid along the inner wall of the continuous retaining water wall, so that stable burial is performed and there is no compressor, so noise, vibration, and other pressure The construction can be carried out quickly without affecting the local residents due to air supply and exhaust.

〔実施例〕〔Example〕

以下に、本発明に係る立坑構築工法の具体的実施例を
図面を参照して詳細に説明する。
Hereinafter, specific examples of the shaft construction method according to the present invention will be described in detail with reference to the drawings.

第1図は実施例に係る立坑構築工法により施工手順を
示す断面図である。この立坑構築工法は、立坑予定部の
周囲を囲む連続土留止水壁を最初に形成し、その根切り
長さを周辺地盤における地下水圧が連続土留止水壁によ
り囲まれた内部に回り込まないように設定する。その後
に、この分離された立坑予定部にオープンケーソンを連
続土留止水壁の内壁に沿わせて沈設施工することによっ
て立坑を構築するものである。
FIG. 1 is a sectional view showing a construction procedure by a shaft construction method according to an embodiment. This vertical shaft construction method first forms a continuous earth retaining wall surrounding the planned shaft, so that the root cut length does not allow groundwater pressure in the surrounding ground to sneak into the interior surrounded by the continuous earth retaining wall. Set to. Thereafter, an open caisson is laid along the inner wall of the continuous retaining water wall in the separated planned shaft portion to construct a shaft.

まず、立坑予定部10の周囲に連続土留止水壁12を構築
するが、これは泥水固化法により構築するようにしてい
る。すなわち、立坑予定部10の領域の周囲に取り囲むよ
うに溝14をクローラバケット等により掘削する。この溝
14はバケット幅に相当する幅で溝14長さ2〜3m程度を一
つのエレメントとして掘削する。最初の予掘の後に、泥
水処理設備を設置してベントナイトを主成分とする安定
液(比重1.15〜1.20)を溝14に供給して泥水化を図りつ
つ、ケーソン沈埋深さより深い位置まで掘削する。この
掘削後に前記泥水をエアジェットによって攪拌混合さ
せ、泥水中にケイ酸ソーダやセメント・添加剤から構成
される硬化剤を注入し、硬化させる。このような処理を
全周にわたって行い、第3図に示すような連続土留止水
壁12を構築するのである(第1図(1))。この場合に
必要に応じて溝14中に鉄筋やプレキャスト板を挿入して
補強処理を行った連続土留止水壁12とすることができ
る。この連続土留止水壁12は後述するケーソンとの間隔
を60〜70cmにとり、ケーソンの傾きを一定限度で許容す
るとともに、それ以上の傾斜を連続土留止水壁12によっ
て支承するものとしている。
First, the continuous soil retaining wall 12 is constructed around the planned shaft 10, which is constructed by mud solidification. That is, the groove 14 is excavated by a crawler bucket or the like so as to surround the area of the planned shaft 10. This groove
Reference numeral 14 denotes a width corresponding to the bucket width, and the groove 14 is excavated with a length of about 2 to 3 m as one element. After the first pre-drilling, a mud treatment facility is installed and a stable liquid (specific gravity: 1.15 to 1.20) mainly composed of bentonite is supplied to the groove 14 to excavate to a depth deeper than the caisson burial depth while muddy water is formed. . After the excavation, the muddy water is stirred and mixed by an air jet, and a hardening agent composed of sodium silicate and cement / additive is injected into the muddy water to be hardened. Such a process is performed over the entire circumference to construct a continuous retaining water stop wall 12 as shown in FIG. 3 (FIG. 1 (1)). In this case, if necessary, a continuous retaining water blocking wall 12 can be formed by inserting a reinforcing bar or a precast plate into the groove 14 and performing a reinforcing treatment. The continuous retaining water blocking wall 12 has an interval of 60 to 70 cm with a caisson described later, allows the caisson to be inclined at a certain limit, and supports a further inclination by the continuous retaining water blocking wall 12.

また、前記連続土留止水壁12は上述したようにケーソ
ンによる立坑予定深さHより深く設定するが、特に周辺
地盤から連続土留止水壁12によって囲まれた立坑予定部
10内への水の回り込みを防止するのに必要な根切り深さ
hだけ深く連続土留止水壁12を構築する。これは周辺地
盤の水圧や、立坑の断面積等を基準にして所定の設計手
順で決定すればよい。
As described above, the continuous soil retaining wall 12 is set to be deeper than the planned pit depth H by a caisson, but in particular, the planned vertical shaft portion surrounded by the continuous soil retaining wall 12 from the surrounding ground.
The continuous retaining water barrier wall 12 is constructed deeper by the root cutting depth h necessary to prevent the water from flowing into the inside. This may be determined by a predetermined design procedure based on the water pressure of the surrounding ground, the sectional area of the shaft, and the like.

上記のような前処理を行った後に、立坑予定部10にケ
ーソン20を構築する。この実施例では上記のように連続
土留止水壁12が立坑予定深さHより周辺からの水の回り
込みがない根切り深さhをもって構築されて止水壁が構
築されているのでオープンケーソン工法を採用でき、こ
のためケーソン20はオープンケーソンとしいる。まず、
立坑予定部10の地表に対し、最初ケーソン20の安定沈埋
のために一次掘削を行う。これはバックホー等を用い1
〜2m程度の深さを掘削し、ケーソン刃口22を据え付け、
第一ロット躯体241を構築する(第1図(2))。この
躯体24の構築後に刃口22の外周囲を埋め戻す。以後は第
二ロット躯体242を構築するとともに沈下掘削をなし、
立坑設定深さ(第nロット躯体24n)まで繰り返し施工
する(第1図(3))。
After performing the above pretreatment, a caisson 20 is constructed in the planned shaft 10. In this embodiment, as described above, since the continuous soil retaining wall 12 is constructed with the root cutting depth h that does not allow water to flow from the periphery than the planned shaft depth H and the waterproof wall is constructed, the open caisson method is used. The caisson 20 is an open caisson. First,
Firstly, primary excavation is performed on the surface of the planned shaft 10 for stable subsidence of the caisson 20. This is using a backhoe etc.
Drilling to a depth of ~ 2m, installing caisson blade 22,
Constructing the first lot skeleton 24 1 (FIG. 1 (2)). After the construction of the frame 24, the outer periphery of the blade 22 is backfilled. After that without a settlement excavation with building a second lot building frame 24 2,
The work is repeatedly performed up to the setting depth of the shaft (the n-th lot body 24 n ) (FIG. 1 (3)).

このようにしてケーソン20の沈設が立坑予定深さHま
で終了した後は、ケーソン20の刃口22部分の床面にコン
クリートを打設して床盤26を形成することによって立坑
28が構築されることになる。
After the caisson 20 has been laid down to the planned shaft depth H in this manner, concrete is poured into the floor of the cutting edge 22 of the caisson 20 to form the floor 26, thereby forming the shaft 26.
28 will be built.

上記立坑28をシールド掘削機の発進坑とする場合に
は、立坑28の内壁にシールドエントランス30を開口する
が、この開口に先立ち、ケーソン20と連続土留止水壁12
との間の地盤が崩落するおそれがある場合には、この壁
間地盤に薬液注入をして硬化する地盤改良を施す(第1
図(4))。これによって硬化した改良地盤32はシール
ドエントランス30を開口しても噴発することがないの
で、連続土留止水壁12内の地盤の沈下を生じることがな
い。このような処理の後に、立坑28内にシールド掘削機
34を降ろし、開口したシールドエントランス30からシー
ルド掘削機34を発進し、立坑28の後壁いバックトラス3
6、仮セグメント38を介して改良地盤32、連続土留止水
壁12を貫通させ、とう道を形成するのである(第1図
(5))。
When the shaft 28 is used as a starting shaft of a shield excavator, a shield entrance 30 is opened on the inner wall of the shaft 28, but before the opening, the caisson 20 and the continuous retaining water stop wall 12 are opened.
When there is a risk that the ground between the two walls may collapse, the ground between the walls is hardened by injecting a chemical solution into the ground.
(Fig. 4). The hardened improved ground 32 does not erupt even when the shield entrance 30 is opened, so that the ground in the continuous retaining water blocking wall 12 does not sink. After such processing, the shield excavator
34 is lowered, the shield excavator 34 is launched from the opened shield entrance 30, and the back truss 3
6. The improved ground 32 and the continuous retaining water blocking wall 12 are penetrated through the temporary segment 38 to form a road (FIG. 1 (5)).

このような第一実施例に係る立坑構築工法によれば、
立坑予定部10の周囲に予め泥水固化法により連続土留止
水壁12を構築するため、鉄筋の建込みやコンクリートの
打設がなく、しかも逆巻工法に比較しても大幅に工期の
短縮が図れる。しかも連続土留止水壁12によって周辺地
盤と隔離した状態でのケーソン工法であることから、立
坑予定部10内への地下水の回り込みがない上に、ケーソ
ン20の沈下による周辺地盤の沈下や地中水位等の変動を
防止できる。そして、立坑予定部10への水の回り込みが
防止されているため、圧気ケーソン工法を使用する必要
がない。これにより圧気に起因するコンプレッサの使用
に伴う騒音・振動がなく、周辺地下室や井戸への影響、
酸欠空気の発生、および潜函病の発生と圧気補正による
作業能率の低下の問題もなくなる。また、特にシールド
掘削機34の発進時に連続土留止水壁12とケーソン20の壁
感に形成する改良地盤32は、拘束された空間での改良で
あるため、改良効果が大きく、シールドエントランス30
の開口作業の安全性が向上し、経済的でもある。
According to the shaft construction method according to the first embodiment,
Since the continuous retaining water barrier wall 12 is constructed in advance around the planned shaft 10 by mud solidification in advance, there is no need to build steel bars or cast concrete, and the construction period is significantly reduced compared to the reverse winding method. I can do it. Moreover, since the caisson method is in a state of being isolated from the surrounding ground by the continuous retaining water blocking wall 12, there is no groundwater flowing into the planned shaft 10 and the settlement of the surrounding ground due to the settlement of the caisson 20 and the underground Fluctuations in water level can be prevented. Further, since water is prevented from flowing into the planned shaft 10, it is not necessary to use the pneumatic caisson method. As a result, there is no noise and vibration associated with the use of the compressor due to air pressure,
The problem of the generation of oxygen-deficient air, the occurrence of occult disease and the reduction of work efficiency due to the correction of air pressure are also eliminated. In addition, since the improved ground 32 formed in the feeling of the wall of the continuous earth retaining wall 12 and the caisson 20 particularly when the shield excavator 34 starts moving is an improvement in a confined space, the improvement effect is large, and the shield entrance 30
The safety of opening work is improved and it is also economical.

第2図は第二実施例に係る立坑構築工法による施工手
順を示す断面図である。この立坑構築工法は、立坑予定
部の周囲を囲む連続土留止水壁を最初に形成するととも
に、この連続土留止水壁の下部にジェットグラウトによ
って底盤部を形成して立坑予定部を周囲の地盤から分離
する。その後に、この分離された立坑予定部にオープン
ケーソンを連続土留止水壁の内壁に沿わせて沈設施工す
ることによって立坑を構築するものである。
FIG. 2 is a sectional view showing a construction procedure by a shaft construction method according to a second embodiment. In this shaft construction method, a continuous ground retaining wall surrounding the planned shaft is formed first, and a bottom part is formed by jet grout below the continuous ground retaining wall to make the planned shaft surrounding ground. Separate from Thereafter, an open caisson is laid along the inner wall of the continuous retaining water wall in the separated planned shaft portion to construct a shaft.

まず、立坑予定部10の周囲に連続土留止水壁12を構築
するが、これは前記第一実施例と同様に泥水固化法によ
り構築する。すなわち、各エレメント毎に安定液を溝14
に供給して泥水化を図りつつ、ケーソン沈埋深さより若
干深い位置まで掘削し、泥水をエアジェットによって攪
拌混合させつつ硬化剤を注入し、硬化させる。このよう
な処理を全周にわたって行い、第3図に示すような連続
土留止水壁12を構築するものである(第2図(1))。
この連続土留止水壁12もケーソンとの間隔を60〜70cmに
とり、ケーソンの傾きを一定限度で許容するとともに、
それ以上の傾斜を連続土留止水壁12によって支承するも
のとしている。
First, a continuous soil retaining wall 12 is constructed around the planned shaft 10, which is constructed by a mud solidification method as in the first embodiment. In other words, the stabilizing liquid is
And digging to a position slightly deeper than the caisson burial depth while muddy water is supplied. A hardener is injected and hardened while the muddy water is stirred and mixed by an air jet. Such processing is performed over the entire circumference to construct a continuous retaining water stop wall 12 as shown in FIG. 3 (FIG. 2 (1)).
This continuous soil retaining wall 12 also takes a distance of 60 to 70 cm with the caisson, allows the caisson to tilt at a certain limit,
Further inclinations are to be supported by the continuous retaining wall 12.

このような連続土留止水壁12を構築した後に、この第
二実施例では当該連続土留止水壁12の下部を閉塞して周
囲地盤と立坑予定部10とを分離する工程を行う。これは
例えばジットグラウトにより構築するもので、立坑予定
部10の地表からパイプを連続土留止水壁12の下端相当深
さまで挿入し、パイプ先端部分に穿設したジェットノズ
ルからセメントミルクを地中に浸透させて硬化させる。
これによってコア16が形成されるが、このコア16が連接
するように一定間隔をおいて前記パイプを挿入してグラ
ウチングする。このような処理によって、第2図(2)
に示すように連続土留止水壁12の下部に底盤部18を構築
し、立坑予定部10内部を周辺地盤から分離して遮水機能
をもたせている。
After constructing the continuous soil retaining wall 12, in the second embodiment, a step of closing the lower part of the continuous soil retaining wall 12 to separate the surrounding ground from the planned shaft 10 is performed. This is constructed by, for example, jig grout, and a pipe is inserted from the surface of the planned shaft 10 to a depth equivalent to the lower end of the continuous retaining water stop wall 12, and cement milk is introduced into the ground from a jet nozzle drilled at the tip of the pipe. Allow to penetrate and cure.
As a result, a core 16 is formed, and the pipe is inserted and grouted at regular intervals so that the core 16 is connected. By such processing, FIG. 2 (2)
As shown in the figure, a bottom portion 18 is constructed below the continuous retaining water blocking wall 12, and the inside of the planned shaft 10 is separated from the surrounding ground to provide a water blocking function.

上記のような二工程処理を行った後、立坑予定部10に
ケーソン20を構築する。この実施例においても連続土留
止水壁12オープン底盤部18により止水壁が構築されてい
るのでオープンケーソン工法を採用でき、このためケー
ソン20はオープンケーソンとしいる。まず、立坑予定部
10の地表に対し、最初ケーソン20の安定沈埋のために一
次掘削を行う。これはバックホー等を用い一次掘削し、
ケーソン刃口22を据え付け、第一ロット躯体241を構築
する(第2図(3))。この躯体24の構築後に刃口22の
外周囲を埋め戻す。以後は第二ロット躯体242を構築す
るとともに沈下掘削をなし、立坑設定深さ(第nロット
躯体24n)まで繰り返し施工する(第2図(4))。
After performing the two-step process as described above, a caisson 20 is constructed in the planned shaft 10. In this embodiment as well, the open caisson method can be adopted since the water blocking wall is constructed by the continuous retaining water blocking wall 12 and the open bottom portion 18, so that the caisson 20 is an open caisson. First, the planned shaft
The first excavation will be conducted on 10 surfaces for stable sinking of caisson 20 first. This is a primary excavation using a backhoe, etc.
Installation caisson cutting edge 22, to construct the first lot skeleton 24 1 (FIG. 2 (3)). After the construction of the frame 24, the outer periphery of the blade 22 is backfilled. Thereafter no subsidence drilling with constructing the second lot skeleton 24 2 repeatedly construction to shafts setting depth (the n lot skeleton 24 n) (FIG. 2 (4)).

このようにしてケーソン20の沈設が終了した後は、ケ
ーソン20の刃口22は底盤部18に当接あるいはその近傍深
さに達しており、床面にコンクリートを打設して床盤26
を形成することによって立坑28が構築されることにな
る。
After the caisson 20 has been submerged in this way, the cutting edge 22 of the caisson 20 has come into contact with the bottom portion 18 or has reached a depth near the bottom portion 18.
The shaft 28 will be constructed by forming

上記立坑28をシールド掘削機の発進坑とする場合に
は、立坑28の内壁にシールドエントランス30を開口する
が、この開口に先立ち、ケーソン20と連続土留止水壁12
との間の地盤が崩落するおそれがある場合には、この壁
間地盤に薬液注入をして硬化する地盤改良を施す(第2
図(5))。このような処理の後に、立坑28内にシール
ド掘削機34を降ろし、開口したシールドエントランス30
からシールド掘削機34を発進し、立坑28の後壁にバック
トラス36、仮セグメント38を介して改良地盤32、連続土
留止水壁12を貫通させ、とう道を形成するのである(第
2図(6))。
When the shaft 28 is used as a starting shaft of a shield excavator, a shield entrance 30 is opened on the inner wall of the shaft 28, but before the opening, the caisson 20 and the continuous retaining water stop wall 12 are opened.
If there is a risk that the ground between the two walls may collapse, a chemical solution is injected into the ground between the walls to improve the hardened ground (second ground).
(FIG. 5). After such processing, the shield excavator 34 is lowered into the shaft 28, and the opened shield entrance 30 is opened.
Then, the shield excavator 34 is started, and the improved ground 32 and the continuous retaining water stop wall 12 are penetrated through the back truss 36 and the temporary segment 38 on the rear wall of the shaft 28 to form a road (FIG. 2). (6)).

第5図に上記した第二実施例の工程を説明するフロー
チャートを示す。
FIG. 5 is a flowchart illustrating the steps of the second embodiment.

このような第二実施例に係る立坑構築工法によれば、
第一実施例と同様に、立坑予定部10の周囲に予め泥水固
化法により連続土留止水壁12を構築するため、鉄筋の建
込みやコンクリートの打設がなく、しかも逆巻工法に比
較しても大幅に工期の短縮が図れる。特にこの第二実施
例では、連続土留止水壁12と底盤部18によって周辺地盤
と隔離した状態でのケーソン工法であることから、立坑
予定部10内への地下水の回り込みを完全に防止すること
ができ、ケーソン20の沈下による周辺地盤の沈下や地中
水位等の変動をより確実に防止できる。そして、圧気ケ
ーソン工法を使用する必要がないため、圧気に起因する
コンプレッサの使用に伴う騒音・振動がなく、周辺地下
室や井戸への影響、酸欠空気の発生、および潜函病の発
生と圧気補正による作業能率の低下の問題もないのも第
一実施例と同様である。
According to the shaft construction method according to the second embodiment,
Similar to the first embodiment, since the continuous retaining water barrier wall 12 is constructed in advance around the planned shaft 10 by the mud solidification method, there is no need to lay a reinforcing bar or cast concrete, and compared with the reverse winding method. Even so, the construction period can be significantly reduced. In particular, in the second embodiment, since the caisson method is in a state of being isolated from the surrounding ground by the continuous retaining water stop wall 12 and the bottom portion 18, it is possible to completely prevent groundwater from flowing into the planned shaft 10. The settlement of the surrounding ground due to the settlement of the caisson 20 and the fluctuation of the underground water level can be more reliably prevented. Since there is no need to use the pneumatic caisson method, there is no noise and vibration associated with the use of the compressor due to the pneumatic pressure, the effect on the surrounding basement and wells, the generation of oxygen-deficient air, the occurrence of scabs and the correction of pneumatic pressure. As in the first embodiment, there is no problem of lowering the work efficiency due to the above.

なお、上記第一実施例と第二実施例では、連続土留止
水壁12の根切り深さhを長く取るか、これを短くして地
盤改良工法により底盤部18を構築するかで相違するが、
これは周辺地盤の現況から考慮して安定性と工費の少な
い工法を採用するようにすればよい。
Note that the first embodiment and the second embodiment differ depending on whether the root depth h of the continuous retaining water blocking wall 12 is set to be long, or is shortened to construct the bottom 18 by the ground improvement method. But,
It is sufficient to adopt a construction method with low stability and construction cost in consideration of the current situation of the surrounding ground.

〔発明の効果〕〔The invention's effect〕

以上説明したように、本発明に係る立坑構築工法によ
れば、立坑予定部の周囲を囲む連続土留止水壁を予め泥
水固化法により形成し、必要に応じて水回り込みのない
根切り深さhとするか、あるいは連続土留止水壁の底部
にジェットグラウト等の地盤改良工法により地盤部を形
成することにより立坑予定部を周囲地盤から分離し、そ
の後に、前記連続土留止水壁の内部にオープンケーソン
を構築し、前記連続土留止水壁の内壁に沿って前記ケー
ソンを沈設して立坑を構築するため、立坑の構築のため
の工事期間の大幅な短縮を図ることができ、また、施工
時の振動・騒音等の発生がなく、周辺地盤への悪影響の
生じないという優れた効果が得られる。
As described above, according to the shaft construction method according to the present invention, the continuous retaining water blocking wall surrounding the planned shaft is formed in advance by the muddy water solidification method, and if necessary, the root cutting depth without water spillage. h, or by forming a ground portion at the bottom of the continuous retaining water blocking wall by a ground improvement method such as jet grout, to separate the planned shaft from the surrounding ground, and thereafter, the inside of the continuous retaining water blocking wall In order to construct an open caisson, to sink the caisson along the inner wall of the continuous soil retaining wall to build a shaft, it is possible to significantly reduce the construction period for the construction of the shaft, An excellent effect is obtained in that there is no generation of vibration, noise, or the like at the time of construction, and no adverse effects on the surrounding ground.

【図面の簡単な説明】[Brief description of the drawings]

第1図(1)〜(5)は本発明の第一実施例に係る立坑
構築工法の作業工程を示す説明図、第2図(1)〜
(6)は同第二実施例に係る立坑構築工法の作業工程を
示す説明図、第3図は立坑構築状態の平面図、第4図は
同縦断面図、第5図は第二実施例における立坑構築工法
の作業工程のフローチャートである。 10……立坑予定部、12……連続土留止水壁、18……底盤
部、20……オープンケーソン、32……改良地盤。
FIGS. 1 (1) to 1 (5) are explanatory views showing working steps of a shaft construction method according to a first embodiment of the present invention, and FIGS.
(6) is an explanatory view showing the working process of the shaft construction method according to the second embodiment, FIG. 3 is a plan view of the shaft construction state, FIG. 4 is a longitudinal sectional view of the same, and FIG. 5 is the second embodiment. It is a flowchart of the working process of the shaft construction method in FIG. 10 ... Scheduled shaft, 12 ... Continuous earth retaining wall, 18 ... Bottom, 20 ... Open caisson, 32 ... Improved ground.

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】予め泥水固化法により立坑予定部の周囲を
囲む連続土留止水壁を立坑底部より下方に突出する根切
り長さを立坑幅長さ程度に設定して形成した後に、前記
連続土留止水壁の内部にオープンケーソンを構築し、前
記連続土留止水壁の内部において前記ケーソンを沈設す
ることにより立坑を構築することを特徴とする立坑構築
方法。
1. A method for solidifying a continuous retaining water wall surrounding a planned shaft portion by a mud solidification method in advance by setting a root cutting length projecting downward from a shaft bottom portion to approximately a shaft width length, and then forming the continuous water blocking wall. A shaft construction method, comprising: constructing an open caisson inside a retaining water wall, and constructing a shaft by sinking the caisson inside the continuous retaining water wall.
【請求項2】予め泥水固化法により立坑予定部の周囲を
囲む連続土留止水壁を形成するとともに、この連続土留
止水壁の底部にジェットグラウト等の地盤改良方法によ
り底盤部を形成して立坑予定部を周囲地盤から分離し、
その後に、前記連続土留止水壁の内部にオープンケーソ
ンを構築し、前記連続土留止水壁の内部において前記ケ
ーソンを沈設することにより立坑を構築することを特徴
とする立坑構築方法。
2. A continuous retaining water wall surrounding the planned shaft is formed in advance by a mud solidification method, and a bottom portion is formed on the bottom of the continuous retaining water wall by a ground improvement method such as jet grout. Separate the planned shaft from the surrounding ground,
Thereafter, an open caisson is constructed inside the continuous retaining water wall, and a shaft is constructed by sinking the caisson inside the continuous retaining water wall.
JP21660989A 1989-08-23 1989-08-23 Shaft construction method Expired - Lifetime JP2874906B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21660989A JP2874906B2 (en) 1989-08-23 1989-08-23 Shaft construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21660989A JP2874906B2 (en) 1989-08-23 1989-08-23 Shaft construction method

Publications (2)

Publication Number Publication Date
JPH0381421A JPH0381421A (en) 1991-04-05
JP2874906B2 true JP2874906B2 (en) 1999-03-24

Family

ID=16691111

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21660989A Expired - Lifetime JP2874906B2 (en) 1989-08-23 1989-08-23 Shaft construction method

Country Status (1)

Country Link
JP (1) JP2874906B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6182366B2 (en) * 2013-06-18 2017-08-16 鹿島建設株式会社 Excavation method, underground structure construction method, wall body member, excavation wall body
CN108824505B (en) * 2018-07-11 2020-06-02 上海市政建设有限公司 Sinking construction method for close-range sinking well group
CN115369902B (en) * 2022-08-12 2023-07-18 中国一冶集团有限公司 Water-rich geological open caisson structure and construction method thereof

Also Published As

Publication number Publication date
JPH0381421A (en) 1991-04-05

Similar Documents

Publication Publication Date Title
CN101270579B (en) Foundation pit guard method for expansion construction from deep foundation pit to shallow foundation pit
US4496268A (en) Method and apparatus for constructing reinforced concrete walls in the earth
JP2010126996A (en) Method for preventing lining body from floating up
KR101021915B1 (en) Order temporary construction method for earthquake construction
JP2003147782A (en) Foundation structure for constructing new building on existing basement and its construction method
JP3967473B2 (en) Construction method of underground structure
JP4485006B2 (en) Construction method for underground structures
JP2874906B2 (en) Shaft construction method
KR101021913B1 (en) Order temporary construction method for earthquake construction
JP2821934B2 (en) Underground structure construction method
JP2005146756A (en) Earth retaining impervious wall construction method and earth retaining impervious wall formed by it
JP3728659B2 (en) Basement extension method
JPS5936058B2 (en) How to construct a structure using underground continuous walls
JPH0470422A (en) Open caisson method
KR102610909B1 (en) Method and structure of steel pipe propulsion using anchor installation inside steel pipe to prevent sinking
JP2007046343A (en) Liquefaction preventive construction method of ground just under existing building
JP2764482B2 (en) Construction method of large depth human hole
JP3027685B2 (en) Earth retaining wall and construction method
JPH09125405A (en) Deep foundation for inclined tower leg
JP2010126998A (en) Method and structure for preventing deformation of ground
JPH01121414A (en) Excavation work of ground
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPS6192235A (en) Fixing of embedded pipe
JP5526532B2 (en) Shielding machine settlement prevention method and settlement prevention structure
JPS60181426A (en) Method of burying pipe in soft soil layer