EP0044284A1 - Vorrichtung zum Verteilen des Schotterbettes von Eisenbahngleisen - Google Patents

Vorrichtung zum Verteilen des Schotterbettes von Eisenbahngleisen Download PDF

Info

Publication number
EP0044284A1
EP0044284A1 EP81830102A EP81830102A EP0044284A1 EP 0044284 A1 EP0044284 A1 EP 0044284A1 EP 81830102 A EP81830102 A EP 81830102A EP 81830102 A EP81830102 A EP 81830102A EP 0044284 A1 EP0044284 A1 EP 0044284A1
Authority
EP
European Patent Office
Prior art keywords
channel
metalling
ballast
machine
chain
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
EP81830102A
Other languages
English (en)
French (fr)
Inventor
S.P.A. Paganelli
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PAGANELLI SpA
Original Assignee
PAGANELLI SpA
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PAGANELLI SpA filed Critical PAGANELLI SpA
Publication of EP0044284A1 publication Critical patent/EP0044284A1/de
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/06Renewing or cleaning the ballast in situ, with or without concurrent work on the track
    • E01B27/10Renewing or cleaning the ballast in situ, with or without concurrent work on the track without taking-up track
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B27/00Placing, renewing, working, cleaning, or taking-up the ballast, with or without concurrent work on the track; Devices therefor; Packing sleepers
    • E01B27/02Placing the ballast; Making ballastway; Redistributing ballasting material; Machines or devices therefor; Levelling means
    • E01B27/023Spreading, levelling or redistributing ballast already placed
    • E01B27/026Spreading, levelling or redistributing ballast already placed by means of driven tools, e.g. rotating brooms or digging devices

Definitions

  • The.invention relates to a device for regulating the substructure of ballast on railway tracks.
  • the digging is generally done with a continuous chain cutter that extends transversely to the track, is placed underneath the substructure of the sleepers, and conveys the metalling to the purposely provided riddles where the minute parts are separated from the utilizable metalling, while conveyor belts attend to the distribution of the screened metalling to underneath the sleepers, and to the ejection of the non-utilizable metalling.
  • each claw equipped chain is powered by drive means placed on the end of the bar.
  • the regulating bar is able to rotate around its own axis, transversely to the track, and to be locked at a suitable inclination with respect to the railway track on which the screened metalling is to be distributed, while each of the aforementioned support arms is able, through oil hydraulic mechanism, to lengthen until it has coupled with the said bar, and to shorten once the latter has been removed at the end of the operation.
  • the renewal of the railway ballast is achieved in the way that it is carefully screened, redintegrated and redistributed underneath the substructure of the sleepers.
  • the essential object of the invention is, therefore, to overcome the aforementioned difficulties in a way that complies with the safety and railway standards, through a device with which it is possible to regulate the substructure of the ballast, at the time the latter is being renewed and, contemporaneously, to achieve a degree of finish that is sufficiently high to permit rolling stock to transit, at a decent speed, over the said section of the track that has just been subjected to maintenance but which does not require additional follow-up apparatus since, using extremely simple methods, the machine utilizes the device in question for this purpose.
  • the device according to the invention coupled to a riddling machine provided with a main digging channel for removing the metalling from the ballast and conveying it to a screening/dist- ributing group for the realization of a fresh substructure of ballast, characterized by the fact that it comprises: an endless chain, equipped with a plurality of claws, this sliding partially in the inside of a guide channel that is placed, over a given distance, transversely to the rails, underneath the substructure of the sleepers and downstream of the said digging channel with respect to the movement direction of the machine, the said guide channel having, bilaterally and symmetrically with respect to the vertical plane defined longitudinally by the movement direction, two sections that slope on to a vertical plane and converge in a horizontal plane towards the axis of the machine, the said sections being provided, in the region of the verticality at the extremity of the sleepers, with an aperture for the discharge on to the latter of ,part of the metalling conveyed by the chain, the said device comprising,
  • the said conveyor is of a length at least equal to the gauge of the track and it slides with a movement direction that- is in harmony with the one followed by the chain.
  • the advantage the said device offers consists in the fact that the ballast is levelled and that the excess metalling is distributed on to the lateral extremities of the sleepers, thereby creating a renewed ballast over which rolling stock is able to pass at an adequate speed.
  • a riddling-levelling machine hauled by a locomotive that is not depicted in Figure 1 but is positioned to the extreme left thereof.
  • the machine has a frame (3), sustained at the rear by a bogie (4), that is provided with a digging channel (5) carrying a non-illustrated chain, the front section (5') of which extends transversely to the track, destined to remove the metalling from the ballast (M) to be renewed and to channel it above a non-illustrated conveyor belt which, in turn, takes it to a riddle.
  • the device in question placed downstream of the said channel (5) and of the said hopper (7), which comprises an endless chain (10), equipped with a plurality of claws (11) for laying hold of and conveying the metalling, so placed that it slides partially inside a guide channel (12) under the action of a motor (13).
  • the said guide channel has a horizontal section (20), placed transversely to the rails underneath the substructure (P) of the sleepers, of a width greater than the length of the latter, and at a height that is generally above that of the digging channel (5) but can be varied by a pair of hydraulic cylinders (14) fixed by the body to the frame of the machine, with the rod on the lateral sections of the guide chain.
  • each channel is provided with a metalling discharge trap-door (15), the area of which is less than that of the channel itself, wherein the extent of the opening can be varied by means of a shutter; the two channels meet in the region of their terminal part close to the vertex (V) and discharge the remainder of the metalling into an underneath hopper (16) whose lower part opens on to a horizontal conveyor belt (17) that extends transversely above the track and is of a length at least equal to the gauge of the railway.
  • the said conveyor belt (17) is movable in the two directions, operated by a motor (18), similarly to the chain (10).
  • the operation of the device forming the subject of the invention is very simple: placed at a level higher than that of the digging channel (5), it flattens the unevenness in the fresh ballast formed by the hopper upstream of the device itself.
  • the said unevenness is due to the metalling in the new ballast being distributed in a different fashion.
  • the dual object is achieved of levelling the ballast substructure and of anchoring the sleepers (this being indispensable, particularly on bends).
  • the first of the said blades namely the one numbered (22), extends in a virtually vertical plane parallel to the axis x-x and has the twin task of preventing the material carried by the chain from continuing to move transversely without being charged along the sloping guide (12') or (12") and of restraining the metalling on the adjacent bank (in cases when there is a double track), stopping it from sliding along the line where there is the most gradient, coming into contact with the chain and thus being carried along by this.
  • the second of the said blades namely the one numbered (23), has the task, differently from the first blade numbered (22) which can be closed or disengaged, of restraining the metalling laterally outside the area along which the channel (20) passes.
  • the device is symmetrical with respect to the longitudinal axis x-x since the chain (10) can rotate clockwise, and the conveyor belt (17), consequently, in the reverse direction thereto.
  • the invention can also adopt forms that differ from what has been described above and, in particular, numerous modifications of a practical nature may be made without in any way deviating from the framework of protection afforded to the invention.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Machines For Laying And Maintaining Railways (AREA)
EP81830102A 1980-07-10 1981-06-23 Vorrichtung zum Verteilen des Schotterbettes von Eisenbahngleisen Withdrawn EP0044284A1 (de)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
IT346980 1980-07-10
IT03469/80A IT1135865B (it) 1980-07-10 1980-07-10 Dispositivo di regolazione del piano di masscciata nelle vie ferroviarie

Publications (1)

Publication Number Publication Date
EP0044284A1 true EP0044284A1 (de) 1982-01-20

Family

ID=11107956

Family Applications (1)

Application Number Title Priority Date Filing Date
EP81830102A Withdrawn EP0044284A1 (de) 1980-07-10 1981-06-23 Vorrichtung zum Verteilen des Schotterbettes von Eisenbahngleisen

Country Status (11)

Country Link
EP (1) EP0044284A1 (de)
AR (1) AR223624A1 (de)
AU (1) AU7245981A (de)
BR (1) BR8104390A (de)
DD (1) DD200031A5 (de)
ES (1) ES259120Y (de)
GR (1) GR75716B (de)
IT (1) IT1135865B (de)
PL (1) PL131995B1 (de)
YU (1) YU164681A (de)
ZA (1) ZA814174B (de)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2523166A1 (fr) * 1982-03-10 1983-09-16 Plasser Bahnbaumasch Franz Installation roulante pour le ramassage et l'epuration du ballast de voies ferrees
FR2533242A1 (fr) * 1982-09-20 1984-03-23 Plasser Bahnbaumasch Franz Systeme transporteur et a chaine degarnisseuse pour une machine de construction de voie ferree
NL1005713C2 (nl) * 1996-04-04 1997-11-28 Hattum & Blankevoort Bv Versnelde methode voor spoorwegverdieping.
CN109594435A (zh) * 2019-01-25 2019-04-09 泉州市劲力工程机械有限公司 一种应用于摆动式掏碴机构中的新型摆臂

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4858344A (en) * 1988-05-05 1989-08-22 Tamper Corp. Undercutter with rotary trencher

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR747941A (de) * 1933-06-24
FR47273E (de) * 1937-03-05
US3339493A (en) * 1964-08-03 1967-09-05 Jr John F Bryan Railroad ballast handling system
FR2339707A1 (fr) * 1976-02-02 1977-08-26 Plasser Bahnbaumasch Franz Dispositif servant a poser ou a remplacer par portions des voies ferrees

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR747941A (de) * 1933-06-24
FR47273E (de) * 1937-03-05
US3339493A (en) * 1964-08-03 1967-09-05 Jr John F Bryan Railroad ballast handling system
FR2339707A1 (fr) * 1976-02-02 1977-08-26 Plasser Bahnbaumasch Franz Dispositif servant a poser ou a remplacer par portions des voies ferrees

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2523166A1 (fr) * 1982-03-10 1983-09-16 Plasser Bahnbaumasch Franz Installation roulante pour le ramassage et l'epuration du ballast de voies ferrees
FR2533242A1 (fr) * 1982-09-20 1984-03-23 Plasser Bahnbaumasch Franz Systeme transporteur et a chaine degarnisseuse pour une machine de construction de voie ferree
GB2127468A (en) * 1982-09-20 1984-04-11 Plasser Bahnbaumasch Franz A conveying and clearing chain arrangement for a track maintenance machine
NL1005713C2 (nl) * 1996-04-04 1997-11-28 Hattum & Blankevoort Bv Versnelde methode voor spoorwegverdieping.
CN109594435A (zh) * 2019-01-25 2019-04-09 泉州市劲力工程机械有限公司 一种应用于摆动式掏碴机构中的新型摆臂
CN109594435B (zh) * 2019-01-25 2024-03-08 泉州市劲力工程机械有限公司 一种应用于摆动式掏碴机构中的摆臂

Also Published As

Publication number Publication date
ES259120Y (es) 1982-06-16
BR8104390A (pt) 1982-03-23
YU164681A (en) 1983-12-31
ZA814174B (en) 1982-07-28
AU7245981A (en) 1982-01-14
IT1135865B (it) 1986-08-27
ES259120U (es) 1982-01-01
AR223624A1 (es) 1981-08-31
IT8003469A0 (it) 1980-07-10
PL231887A1 (de) 1982-02-15
DD200031A5 (de) 1983-03-09
GR75716B (de) 1984-08-02
PL131995B1 (en) 1985-01-31

Similar Documents

Publication Publication Date Title
US4479439A (en) Mobile arrangement and method for improving a track bed
US4799430A (en) Mobile ballast cleaning apparatus
US3872929A (en) Method and apparatus for stablizing the sub-grade of a railroad ballast bed
CA1287263C (en) Mobile track renewal machines
US5090484A (en) Mobile ballast cleaning machine arrangement
US4611541A (en) Ballast cleaning method and machine
DE3036007A1 (de) Fahrbare schotterbett-reinigungsmaschine mit planier- und verdichtvorrichtungen
US3330219A (en) Method and apparatus for replacing an old track by a new track
GB2134574A (en) A conveying and clearing chain arrangement for railway track maintenance machines
US4094249A (en) Apparatus for laying track
EP1162312B1 (de) Maschine zur Erneuerung eines Gleises
AT398097B (de) Anlage zur herstellung einer planumschutzschichte
GB2186309A (en) A travelling machine combination for cleaning and then consolidating the ballast bed of railway tracks
AU642805B2 (en) A cleaning machine
US4534415A (en) Ballast cleaning machine with two ballast screening installations
EP0044284A1 (de) Vorrichtung zum Verteilen des Schotterbettes von Eisenbahngleisen
CZ296484B6 (cs) Cisticí stroj
SE444192B (sv) Sparbyggnadsmaskin med en anordning for rojande och planande av makadambedden
DE3634398C2 (de) Fahrbare Anlage zur kontinuierlichen Erneuerung der Schienen und Schwellen eines Gleises
US4043398A (en) Mobile ballast cleaning machine
CN1100919C (zh) 捣固机械
US2182139A (en) Dirt conveyer
EP0203642B1 (de) Vorrichtung zum Erneuern von Eisenbahnballast für Tunnel
US20180010303A1 (en) Method for track renewal
CS219869B2 (en) Travelling machine for the track construction mainly the scraper bed cleaner

Legal Events

Date Code Title Description
PUAI Public reference made under article 153(3) epc to a published international application that has entered the european phase

Free format text: ORIGINAL CODE: 0009012

AK Designated contracting states

Designated state(s): AT BE CH DE FR GB LU NL SE

STAA Information on the status of an ep patent application or granted ep patent

Free format text: STATUS: THE APPLICATION IS DEEMED TO BE WITHDRAWN

18D Application deemed to be withdrawn

Effective date: 19821225