CN202260249U - High-voltage transmission line lifter for live working - Google Patents

High-voltage transmission line lifter for live working Download PDF

Info

Publication number
CN202260249U
CN202260249U CN201120358429XU CN201120358429U CN202260249U CN 202260249 U CN202260249 U CN 202260249U CN 201120358429X U CN201120358429X U CN 201120358429XU CN 201120358429 U CN201120358429 U CN 201120358429U CN 202260249 U CN202260249 U CN 202260249U
Authority
CN
China
Prior art keywords
yoke plate
transmission line
tie
line
triangle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN201120358429XU
Other languages
Chinese (zh)
Inventor
董胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN ELECTRIC POWER CO Ltd DAZHOU ELECTRIC POWER BUREAU
State Grid Corp of China SGCC
Original Assignee
Dazhou Electric Power Bureau Of Sichuan Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Dazhou Electric Power Bureau Of Sichuan Electric Power Co filed Critical Dazhou Electric Power Bureau Of Sichuan Electric Power Co
Priority to CN201120358429XU priority Critical patent/CN202260249U/en
Application granted granted Critical
Publication of CN202260249U publication Critical patent/CN202260249U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Insulators (AREA)

Abstract

The utility model discloses a high tension transmission line lifter for live working, the turn-buckle has, connect the insulating arm-tie of turn-buckle lower extreme and connect the hanging wire mechanism of insulating arm-tie lower extreme, still include a yoke plate fixture that can install on insulator chain triangle yoke plate, it has the interior concave surface of laminating mutually with the triangle yoke plate to open on the yoke plate fixture, interior concave surface left end edge is laminated mutually with the hypotenuse of triangle yoke plate, interior concave surface right-hand member is equipped with the first connecting hole that can be linked together with the trompil on the triangle yoke plate, the left end of yoke plate fixture is equipped with the second connecting hole of being connected with the turn-buckle upper end. The utility model discloses simple structure, convenience safe in utilization has solved the great problem of the change insulator degree of difficulty under the different topography conditions.

Description

The ultra-high-tension power transmission line line lifter is used in live line working
Technical field
The utility model relates to a kind of line apparatus of carrying, and belongs to ultra-high-tension power transmission line hotline maintenance and maintenance technology field.
Background technology
The insulator string that uses in the ultra-high-tension power transmission line all can face the replacing problem after the operation certain hour.People generally select to change under the live line working, to reduce frequency of power cut, ensure the continuity of power supply.But will realize changing under the live line working underslung insulator string in the reality but wastes time and energy very much, the one, and need many people to cooperate, operation simultaneously; Two are to use utensil more.Be used to change the ultra-high-tension power transmission line line lifter of the two insulator strings of 110kV-220kV ultra-high-tension power transmission line forthright at present, it is made up of cross-arm connector, wire grip, insulation arm-tie and metal hanger.During use, the cross-arm connector of this line lifter is connected to be positioned to be needed to change on the pinnacle of a pagoda cross-arm of insulator one side, and this line lifter is used for power transmission line and the Yan Shangke that the little and hanging point both sides circuit of contiguous iron tower difference in height is horizontal arrangement.But on the hills and the area, mountain area, contiguous iron tower height is also inconsistent, and this causes the transmission line of two insulator string hanging point both sides to be non-horizontal arrangement, adopts this moment existing line lifter to cause the replacing operational difficulty because of there is difference in height in the hanging point both sides again.Because under live line working, the wire grip metal section and part can not be long; Long easy single phase ground fault phenomenon; This has limited the process of tightening up of power transmission line naturally, and along with hanging point both sides difference in height increases, it is short then to be subject to the screw mandrel shrink process; Will constantly increase the tension force of labor intensity of operating personnel and wire grip insulation arm-tie, thereby let the complexity such as difficulty and uncertain factor of work strengthen greatly.Because wire grip process weak point is difficult to make insulator string lax, even the situation of getting that is connected of bulb and bowl head on the insulator string occurs, make live line working replacing insulator work be difficult to carry out again.
Summary of the invention
In view of this, the utility model purpose is to provide a kind of different geographical environments that are applicable to, more changing jobs can be light, electric wire line lifter flexibly.
For solving above technical problem; The technical scheme that the utility model provides is to provide live line working to use the ultra-high-tension power transmission line line lifter, the hanging wire mechanism that has wire grip, is connected the insulation arm-tie of wire grip lower end and connects insulation arm-tie lower end; It is characterized in that; Also comprise a yoke plate jig that can be installed on the insulator string triangle yoke plate, have the inner concave that fits with the triangle yoke plate on the said yoke plate jig, the hypotenuse of inner concave left end edge and triangle yoke plate fits; The inner concave right-hand member is provided with first connecting hole that can be connected with the perforate on the triangle yoke plate, and the left end of yoke plate jig is provided with second connecting hole that is connected with the wire grip upper end.
Said insulation arm-tie is telescopic insulation arm-tie.
Said hanging wire mechanism is hook structure or snap ring structure.
Compared with prior art, the utlity model has following advantage:
1, both had been applicable to that insulator string hanging point both sides circuit was horizontal arrangement, also is applicable to that hanging point both sides circuit is replacing and the maintenance of insulator string under the charged situation of circuit of non-horizontal arrangement.The yoke plate jig of the utility model directly is connected on the double insulator string triangle yoke plate; No matter whether the hanging point both sides overhead line structures discrepancy in elevation is horizontal arrangement; All not too need the long process of tightening up of wire grip (like screw mandrel), so as long as operating personnel adjust lower stretching wire device process a little and all can make the hanging wire mechanism power transmission line of slinging on the tower, and then make insulator string loose; Easy to replace and maintain, guaranteed the safe distance of operating personnel and electrified body.
2, the utility model is installed easily, and steadily.On the yoke plate jig of the utility model the inner concave edge with can with the corresponding connecting hole of existing perforate (being eyelet) on the triangle yoke plate, so the utility model be easy to the couplet connect on the triangle yoke plate; Have, because the needed wire grip process of tightening up is lacked again, the triangle yoke plate can not produce dancing in the circuit tightening process like this, has avoided the long generation that causes the single-line to ground fault accident of wire grip metal section and part yet again.
3, the difficulty of using the utility model obviously to reduce labour intensity and more to change jobs.Because install easily, take-up is steady, only need a people just can change insulator string light, neatly, so high efficiency and safety.
4, the utility model is simple and reasonable for structure, and application prospect is good.
Description of drawings
Fig. 1 is that existing line lifter is installed and used sketch map.
Fig. 2 is the structure chart of the utility model line lifter.
Fig. 3 is the front view of the yoke plate jig of the utility model line lifter.
Fig. 4 is the upward view of the yoke plate jig of the utility model line lifter.
Fig. 5 is that the utility model line lifter is installed and used sketch map.
Embodiment
Describe below in conjunction with accompanying drawing and specific embodiment.
Referring to Fig. 2 to Fig. 5; The ultra-high-tension power transmission line line lifter is used in live line working; The hanging wire mechanism 3 that has wire grip 1, is connected the insulation arm-tie 2 of wire grip lower end and connects insulation arm-tie lower end; Also comprise a yoke plate jig 4 that can be installed on the insulator string triangle yoke plate 7; Have the inner concave 4a that fits with triangle yoke plate 7 on the said yoke plate jig, the yoke plate jig inner concave 4a left end edge shown in Figure 3 and the hypotenuse of triangle yoke plate 7 fit, and inner concave 4a right-hand member is provided with first connecting hole 5 that can be connected with the perforate on the triangle yoke plate 7; The left end of yoke plate jig is provided with second connecting hole 6 that is connected with wire grip 1 upper end, and employed perforation connector is connecting bolt or connecting pin.Wire grip 1 can adopt prior art, and just wire grip 1 is made up of screw mandrel and the handle of screwing that is connected on the screw mandrel, and the length of screw mandrel changes with the rotation action of screwing handle; Insulation arm-tie 3 is the vertical bar pulling plate structure; Perhaps adopt telescopic pulling plate structure; The arm-tie that promptly insulate constitutes by two sections; Have corresponding perforate on its two sections, through connecting the adjustment that can realize insulation arm-tie length required under the different insulative substring length situation with bolt or connecting pin after the correspondence of different eyelets; Hanging wire mechanism 3 is a hook structure, also can adopt snap ring structure etc.During use; The side that the inner concave 4a of the utility model seton device is changed insulator string from need penetrates on the double insulator string triangle yoke plate 7; And with the intrinsic perforate on the connecting hole 5 aligning triangle yoke plates; Fastening with dismountable bolt or connecting pin, can easily seton device be connected on the triangle yoke plate 7; Rotate this moment and screw handle, tighten up screw mandrel and can the high voltage transmission line hook block.After insulator string to be replaced was loose, the bulb on the insulator string was connected with bowl head and just is easy to take down, and realizes replacing and maintenance activity.Because the utility model seton device is installed easily; The triangle yoke plate does not have swing in the power transmission line tightening process, add and tighten up process weak point, action not quite, so whole replacing process is operated easily; Labour intensity is low, only needs a people can accomplish more changing jobs of insulator string light, neatly.The insulator string of replacing opposite side also in like manner.
Only be the preferred implementation of the utility model below, should be pointed out that above-mentioned preferred implementation should not be regarded as the restriction to the utility model, the protection range of the utility model should be as the criterion with claim institute restricted portion.For those skilled in the art, in spirit that does not break away from the utility model and scope, can also make some improvement and retouching, these improvement and retouching also should be regarded as the protection range of the utility model.

Claims (4)

1. the ultra-high-tension power transmission line line lifter is used in a live line working; The hanging wire mechanism (3) that has wire grip (1), is connected the insulation arm-tie (2) of wire grip lower end and connects insulation arm-tie lower end; It is characterized in that; Also comprise a yoke plate jig (4) that can be installed on the insulator string triangle yoke plate (7); Have the inner concave that fits (4a) on the said yoke plate jig with triangle yoke plate (7); The hypotenuse of inner concave (4a) left end edge and triangle yoke plate (7) fits, and inner concave (4a) right-hand member is provided with first connecting hole (5) that can be connected with the perforate on the triangle yoke plate (7), and the left end of yoke plate jig is provided with second connecting hole (6) that is connected with wire grip (1) upper end.
2. the ultra-high-tension power transmission line line lifter is used in live line working according to claim 1, it is characterized in that, said insulation arm-tie (2) is telescopic insulation arm-tie.
3. the ultra-high-tension power transmission line line lifter is used in live line working according to claim 1, it is characterized in that, said hanging wire mechanism (3) is a hook structure.
4. the ultra-high-tension power transmission line line lifter is used in live line working according to claim 1, it is characterized in that, said hanging wire mechanism (3) is the snap ring structure.
CN201120358429XU 2011-09-23 2011-09-23 High-voltage transmission line lifter for live working Expired - Lifetime CN202260249U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201120358429XU CN202260249U (en) 2011-09-23 2011-09-23 High-voltage transmission line lifter for live working

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201120358429XU CN202260249U (en) 2011-09-23 2011-09-23 High-voltage transmission line lifter for live working

Publications (1)

Publication Number Publication Date
CN202260249U true CN202260249U (en) 2012-05-30

Family

ID=46121434

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201120358429XU Expired - Lifetime CN202260249U (en) 2011-09-23 2011-09-23 High-voltage transmission line lifter for live working

Country Status (1)

Country Link
CN (1) CN202260249U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102340114A (en) * 2011-09-23 2012-02-01 四川省电力公司达州电业局 High-voltage power transmission line lifter for live working
CN105305305A (en) * 2015-11-03 2016-02-03 国家电网公司 Device for live replacement of cross arm and insulator string and application method
CN107437770A (en) * 2017-09-11 2017-12-05 广州供电局有限公司 The servicing unit of grounding box coaxial cable installation
CN107706822A (en) * 2017-11-15 2018-02-16 国家电网公司 Equipotential suspension clamp changes instrument
CN109374283A (en) * 2018-12-13 2019-02-22 广东电网有限责任公司 A kind of experimental rig of thread-lifting hook

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102340114A (en) * 2011-09-23 2012-02-01 四川省电力公司达州电业局 High-voltage power transmission line lifter for live working
CN105305305A (en) * 2015-11-03 2016-02-03 国家电网公司 Device for live replacement of cross arm and insulator string and application method
CN105305305B (en) * 2015-11-03 2018-11-30 国家电网公司 The device and application method of charged for replacement cross-arm and insulator chain
CN107437770A (en) * 2017-09-11 2017-12-05 广州供电局有限公司 The servicing unit of grounding box coaxial cable installation
CN107706822A (en) * 2017-11-15 2018-02-16 国家电网公司 Equipotential suspension clamp changes instrument
CN109374283A (en) * 2018-12-13 2019-02-22 广东电网有限责任公司 A kind of experimental rig of thread-lifting hook
CN109374283B (en) * 2018-12-13 2024-04-05 广东电网有限责任公司 Test device of wire lifting hook

Similar Documents

Publication Publication Date Title
CN202260249U (en) High-voltage transmission line lifter for live working
WO2012088987A1 (en) Maintenance tool for insulator of direct current transmission line
CN105514877B (en) Common-tower double-return steel pipe pole replacement insulation subjob cross-arm fixture
CN102340114A (en) High-voltage power transmission line lifter for live working
CN102403674B (en) A kind of live-wire work insulating cross arm
CN101814707B (en) Tool for live replacement of 220kV line 'V' string insulator and method
CN203300937U (en) High-hitching ground wire operating lever
CN203103882U (en) Insulation bracing frame for live 10kV cable lead disconnection and connection operation
CN202712745U (en) Universal straight-line clamp for steel pipe pole tower head
CN102738737A (en) Straight line clamp universal for steel tube rod tower heads
CN202373939U (en) Live-working double-conductor lifting device
CN204240291U (en) A kind of side section bar of solar street light
CN204928039U (en) Trapezoidal weight piece
CN206004224U (en) Ground potential fast-assembling synthetic insulator preventing wind drift wire erector
CN103490291A (en) Fuse tube or disconnecting link fall-off preventing mechanism
CN203895861U (en) Portable multifunctional power source cable support
CN202474705U (en) Electrified installation tool for bird scarer
CN208835588U (en) A kind of bottle-holding rack fixture
CN207490436U (en) The double models for hanging V-type composite insulator string replacing options of ± 500kV DC power transmission lines duplex
CN204271535U (en) Transmission line is two hangs insulator yoke plate erection device
CN204240238U (en) A kind of solar street light
CN104810747A (en) Multi-purpose electric power overhaul tool
CN203660098U (en) Overturn-type grounding wire clamp
CN203434453U (en) Anti-falling device for fuse tube or switch
CN202663028U (en) Insulating baffle with hook

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20131224

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20131224

Address after: 635000 No. 816 Chaoyang East Road, Sichuan, Dazhou

Patentee after: Sichuan Electric Power Co.,Ltd. Dazhou Electric Power Bureau

Patentee after: State Grid Corporation of China

Address before: 635000 No. 816 Chaoyang East Road, Sichuan, Dazhou

Patentee before: Sichuan Electric Power Co.,Ltd. Dazhou Electric Power Bureau

CX01 Expiry of patent term

Granted publication date: 20120530

CX01 Expiry of patent term