[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN110439560A - A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu - Google Patents

A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu Download PDF

Info

Publication number
CN110439560A
CN110439560A CN201910704092.4A CN201910704092A CN110439560A CN 110439560 A CN110439560 A CN 110439560A CN 201910704092 A CN201910704092 A CN 201910704092A CN 110439560 A CN110439560 A CN 110439560A
Authority
CN
China
Prior art keywords
steel
working face
coal working
tunnel
along
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910704092.4A
Other languages
Chinese (zh)
Inventor
范凯
王强
何立菊
卓军
汪胜
郭富生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SICHUAN HUAYINGSHAN LONGTAN COAL CO Ltd
Original Assignee
SICHUAN HUAYINGSHAN LONGTAN COAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SICHUAN HUAYINGSHAN LONGTAN COAL CO Ltd filed Critical SICHUAN HUAYINGSHAN LONGTAN COAL CO Ltd
Priority to CN201910704092.4A priority Critical patent/CN110439560A/en
Publication of CN110439560A publication Critical patent/CN110439560A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • E21C41/18Methods of underground mining; Layouts therefor for brown or hard coal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D15/00Props; Chocks, e.g. made of flexible containers filled with backfilling material
    • E21D15/14Telescopic props
    • E21D15/44Hydraulic, pneumatic, or hydraulic-pneumatic props
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/005Methods or devices for placing filling-up materials in underground workings characterised by the kind or composition of the backfilling material
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F42AMMUNITION; BLASTING
    • F42DBLASTING
    • F42D3/00Particular applications of blasting techniques
    • F42D3/04Particular applications of blasting techniques for rock blasting

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Remote Sensing (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The present invention relates to coal mining technology field, provides a kind of medium-thickness seam coal working face and be included in reserved tunnel along the construction technology in the lane Kong Hu and install hydraulic prop cooperation I-steel, and set anchor cable cooperation channel steel shield top;Presplit blasting hole is opened up on top plate;Monomer hydraulic supporting cooperation I-steel is installed at reserved tunnel and the fork of coal working face;I-steel is set up at the coal working face lag, moves towards first successively to be laid with steel mesh and metal mesh along tunnel, then installs hydraulic prop cooperation I-steel, then install oblique volumn supporting to I-steel strengthening supporting;Outside coal working face hysteresis region, hydraulic prop is withdrawn;Tunneling boring whitewashing processing is carried out to tunnel;Built-in slip casting pipe carries out slip casting below the top plate of coal working face.The present invention, which has, can be improved resource recovery, save production cost;It reduces on tunnel dynamic pressure influence is closed on, reduces the secondary maintenance capacity in tunnel;Reduce the technical effect of the labor intensity of worker.

Description

A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu
Technical field
The invention belongs to coal mining technology fields, specifically, being related to a kind of empty shield in medium-thickness seam coal working face edge The construction technology in lane.
Background technique
Previous Some Domestic mine is studied and realizes fender even without coal pillar mining, but has roadway surrounding rock more and answer Maintenance cost is excessive when power is high, roadway deformation amount is big, tunnel uses, and stays the fender set that crisp deformation, filling method is pressed to realize completely Without coal column then obturation oxygen blast cyanidation, or even needing to help brush to expand in coal again, roadway maintenance cost has even surmounted new pick tunnel, Tracing sth. to its source is that roof pressure is not released, and causes roadway deformation amount big, and the release of General Explosive means is due to its side To uncontrollable, in some instances it may even be possible to cause to damage to tunnel, show to carry out using directional cumulation explosion to cut top by development test and unload Pressure can solve the above problems.
Summary of the invention
For deficiency above-mentioned in the prior art, the purpose of the present invention is to provide a kind of medium-thickness seam coal working face edges Resource recovery can be improved using this method in the construction technology in the lane Kong Hu, reduces digging ratio, saves production cost;It reduces to facing Nearly tunnel dynamic pressure influences, reduces maintenance cost, reduces the secondary maintenance capacity in tunnel;The labor intensity of worker is reduced, labour is improved The ventilation of Y type may be implemented in efficiency, gob side entry retaining.
In order to achieve the above object, the solution that the present invention uses is:
A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu, comprising the following steps:
S1 installs hydraulic prop cooperation I-steel, advanced work of constructing close to the side of coal working face in reserved tunnel Make to complete in the 20m of face;Row's anchor cable is set close to the side of coal working face in reserved tunnel, anchor cable is connected and matched by anchor beam Channel steel shield top is closed, is completed in construction first advance 20m~50m;
S2 opens up presplit blasting hole on top plate between reserved tunnel is close to coal working face side and construction anchor cable, Installation cumulative presplitting pipe and powder charge progress explosion in pre- blast hole;
S3 installs monomer hydraulic supporting cooperation I-steel at reserved tunnel and the fork of coal working face;
S4 sets up I-steel in coal working face lag 3m, and I-steel top is beaten in channel steel, I-steel top and slot Steel uses wooden wedge wedging, is successively laid with steel mesh and metal mesh along tunnel trend, steel mesh and metal mesh and I-steel are consolidated It is fixed;Coal working face lags in 3m~30m, installs hydraulic prop cooperation I-steel, then install oblique volumn supporting to I-steel Strengthening supporting;Coal working face lags outside 30m, withdraws hydraulic prop;Gob side entry retaining goaf wall sets up I-steel simultaneously Setting is moved towards along tunnel;
S5 carries out tunneling boring whitewashing processing to tunnel, and closes steel mesh and metal mesh;
S6 built-in slip casting pipe below the top plate of coal working face carries out slip casting.
Preferably, in the S1, the trend of the vertical coal working face of I-steel is evenly arranged, between the two adjacent I-steel Away from for 0.5m~1.0m.
Preferably, in the S1, channel steel is 14# channel steel, and anchor cable spacing is 1~2m, anchor beam spacing 0.1m~0.5m.
Preferably, in the S2, the spacing in presplit blasting hole is 0.2m~0.7m, and presplit blasting hole is arranged in a linear, in advance The hole depth for splitting blast hole is 5m~8m, and presplit blasting hole aperture is 0.03m~0.07m.
Preferably, the spacing of presplit blasting hole and anchor cable is 0.1m~0.3m.
Preferably, in the S2, the two sides of cumulative presplitting pipe are provided with several jewel holes being equally spaced, the spacing between jewel hole For 0.01m~0.03m, the aperture of jewel hole is 0.003m~0.008m.
Preferably, in the S2, the horizontal sextant angle of presplit blasting hole and reserved back is 75 °~90 °.
Preferably, in the S5, spray head when whitewashing is perpendicular to by spray plane, and distance is by spray plane 0.8m~1.0m;Using point Zone circular mode is sprayed.
Preferably, if shield lane shoulder nest local segment goaf is caving insufficient, empty position is filled using perlite.
The beneficial effects of the present invention are:
(1) using cut top unloading technology can be effectively reduced stress in chain pillar concentrate and coal column in plastic failure Range ensure that the safety during working face extraction;
(2) it takes along the advanced one emissions groove steel of complement of working face wall and connects anchor cable progress reinforcement supporting roof, it is quick-fried to cut top I-steel deviates from steel mesh before broken, and girder steel top is beaten in channel steel, forms integer support top plate, girder steel point stress is avoided to obtain disadvantage End, supporting effect are obvious;
(3) it cuts the top lane explosion Hou Hu shoulder nest local segment goaf top plate and is caving insufficient, change traditional coal (cash) filling sky Hole mode, creative use perlite fill empty position, and realization is safely and fast constructed;
(4) the logical wind action of Y type not only may be implemented in gob side entry retaining construction technology, solves fully-mechanized mining working upper corner watt This problem that transfinites;
(5) use is cut top release edge air gallery technology and is compared than building gob side entry retaining by former lane, alleviates worker's physical strength labor It is dynamic, improve labor efficiency.
Appended drawing reference
Fig. 1 is medium-thickness seam coal working face in the present embodiment 1 along the structural schematic diagram of the construction technology in the lane Kong Hu.
In figure: 1- reserves tunnel;2- coal working face;The goaf 3-;4- hydraulic prop;5- I-steel;6- anchor cable; 7- channel steel;8- presplit blasting hole;9- Double-protection net;10- clashes column.
Specific embodiment
It in order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below will be in the embodiment of the present invention Technical solution be clearly and completely described.The person that is not specified actual conditions in embodiment, according to normal conditions or manufacturer builds The condition of view carries out.Below to a kind of medium-thickness seam coal working face provided in an embodiment of the present invention along the construction technology in the lane Kong Hu It is specifically described.
Embodiment 1
Present embodiment discloses a kind of medium-thickness seam coal working faces along the construction technology in the lane Kong Hu, comprising the following steps:
S1 installs hydraulic prop 4 close to the side of coal working face 2 in reserved tunnel 1 and cooperates I-steel 5, and construction is super It is completed in leading face 20m, the trend of the vertical coal working face 2 of I-steel 5 is evenly arranged, and two adjacent 2 spacing of I-steel are 0.6m~1.0m, preferably 0.7m~0.9m;Row's anchor cable 6, anchor are set close to the side of coal working face 2 in reserved tunnel 1 Rope 6 connects by anchor beam and cooperates the shield of channel steel 7 top, completes in construction first advance 20m~50m, channel steel 7 is 14# channel steel, anchor 6 spacing of rope is 1~2m, preferably 1.2m~1.8m;Anchor cable length is 5m~8m, preferably 6m~8m, using two double speed trees Rouge Anchor Agent fixes anchor cable, and anchor cable 6 selects steel strand wires to cut;Anchor beam spacing 0.1m~0.5m, preferably 0.2m~0.4m.
S2 opens up presplit blasting on top plate between reserved tunnel 1 is close to 2 side of coal working face and construction anchor cable Hole 8, the interior installation cumulative presplitting pipe in presplit blasting hole 8 and powder charge progress explosion;The spacing in presplit blasting hole 8 is 0.2m~0.7m, Preferably 0.3m~0.5m;Presplit blasting hole 8 is arranged in a linear, and the hole depth in presplit blasting hole 8 is 5m~8m, with presplit blasting hole 8 ends reach subject to K2 roof, and 8 aperture of presplit blasting hole is 0.03m~0.07m, preferably 0.03m~0.05m;Presplitting The horizontal sextant angle of blast hole 8 and reserved 1 top plate of tunnel is 75 °~90 °, preferably 80 °~90 °;Presplit blasting hole 8 and anchor cable 6 Spacing be 0.1m~0.3m;The two sides of cumulative presplitting pipe are provided with several jewel holes being equally spaced, and the spacing between jewel hole is 0.01m~0.03m, the aperture of jewel hole are 0.003m~0.008m.
S3 installs hydraulic prop 4 at reserved tunnel 1 and the fork of coal working face 2 and cooperates I-steel 5, pillar cloth It is placed on same straight line, I-steel 5 connects top tightly by wooden wedge, and it is integral to use rope to be connected with each other.
S4 is lagged in coal working face 2 and is set up I-steel 5 in 3m, and I-steel top beats in channel steel 7, I-steel top and Channel steel 7 uses wooden wedge wedging, is successively laid with steel mesh and metal mesh, steel mesh and metal mesh and I-steel along tunnel trend 5 are fixed by 8# iron wire, carry out overlapping and being connected firmly with iron wire between steel mesh and metal mesh, and steel mesh and metal mesh are constituted Double-protection net 9;Coal working face lags in 3m~30m, installs hydraulic prop 4 and cooperates I-steel 5, then installs column in an opposite direction 10 pairs of 5 strengthening supportings of I-steel;Coal working face 1 lags outside 30m, withdraws hydraulic prop;Gob side entry retaining goaf wall It sets up I-steel 5 and moves towards setting along tunnel, 5 spacing of I-steel is 0.5m~1.0m, preferably 0.6m~0.8m, using timber wedge Son is fixed, branch intercolumniation 4m.
S5 carries out tunneling boring (tunnel tripartite) whitewashing processing to along sky shield tunnel section, and closes steel mesh and metal mesh, and Tight wall crack can be closed, guarantees that goaf is not leaked out;To being handled in coal working face lag 30m, spray when whitewashing Head is perpendicular to by spray plane, and distance is by spray plane 0.8m~1.0m;It is sprayed using subregion circular pattern.Light is wanted on concrete surface after spray Sliding, smooth, arch circle, no dew steel mesh and metal mesh, dry and cracked phenomenon, no dry spot, do not slide, do not trickle, is glossy, bonding, Rebound is few.
S6 built-in slip casting pipe below the top plate of coal working face 2 carries out slip casting, slip casting tube spacing 20m~50m/, excellent 30m~40m/ are selected as, slip casting length of tube is 1.0m.
If shield lane shoulder nest local segment goaf is caving insufficient, empty position is filled using expanding material, is expanded Material is perlite.
I-steel also becomes girder steel, and I-steel is No. 11 mine I-steel in the present embodiment.
Working face manages top plate using whole caving methods using long-armed drawing back technique, goaf is moved towards.
The present invention is mined using retrusive, the Y-shaped ventilating system constituted with machine lane, air way air inlet, gob side entry retaining section return air. The existing two tunnels air inlet of coal working face makes the opposite reduction of air quantity by working face, facilitates fire extinguishing and prevent from mining Working face coal dust is flown upward, and improves environment on coalface, reduces goaf air leaking and Gas, so that having prevents coal working face The effect of Gas Accumulation in Upper-Corner by Pulsed.Y-shaped ventilating system is since its gob side entry retaining changes goaf air leaking direction, and gas is with leaking out It directly pours into along backlash air way, is preventing Gas Accumulation in Upper-Corner by Pulsed and face gas from transfiniting aspect better than U-shaped ventilating system.
In conclusion cutting top release edge air gallery technology is to form unloading space by cutting top, pressure is transferred to from lane The farther away place in road achievees the purpose that tunnel mitigates and is pressurized, to realize the impact for avoiding reserved coal pillar to cause without coal pillar mining Ground pressure, the disasters such as Gas Outburst.Resource recovery can be improved in the implementation for cutting top release gob side entry retaining, reduces digging ratio, saves life Produce cost;It reduces on closing on tunnel dynamic pressure influence, reducing maintenance cost, reduces the secondary maintenance capacity in tunnel;Reduce the labor of worker Fatigue resistance is improved labor efficiency.The ventilation of Y type may be implemented in gob side entry retaining, is to solve the problems, such as face upper corner angle gas accumulation The implementation of effective means, the technology increases production and improves productivity with certain meaning to mine.
The foregoing is only a preferred embodiment of the present invention, is not intended to restrict the invention, for the skill of this field For art personnel, the invention may be variously modified and varied.All within the spirits and principles of the present invention, made any to repair Change, equivalent replacement, improvement etc., should all be included in the protection scope of the present invention.

Claims (9)

1. a kind of medium-thickness seam coal working face is along the construction technology in the lane Kong Hu, which comprises the following steps:
S1 installs hydraulic prop cooperation I-steel, first advance of constructing close to the side of coal working face in reserved tunnel It is completed in 20m;Row's anchor cable is set close to the side of coal working face in reserved tunnel, anchor cable passes through anchor beam connection and mating groove Steel shield top, construction first advance 20m~50m is interior to be completed;
S2 opens up presplit blasting hole on top plate between reserved tunnel is close to coal working face side and construction anchor cable, pre- quick-fried Installation cumulative presplitting pipe and powder charge progress explosion in holes;
S3 installs monomer hydraulic supporting cooperation I-steel at reserved tunnel and the fork of coal working face;
S4 sets up I-steel in coal working face lag 3m, and I-steel top is beaten in channel steel, and I-steel top is adopted with channel steel With wooden wedge wedging, steel mesh and metal mesh, steel mesh and metal mesh are successively laid with along tunnel trend and is fixed with I-steel;It adopts Coal working face lags in 3m~30m, installs hydraulic prop cooperation I-steel, then install oblique volumn supporting and reinforce branch to I-steel Shield;Coal working face lags outside 30m, withdraws hydraulic prop;Gob side entry retaining goaf wall sets up I-steel and along tunnel Move towards setting;
S5 carries out tunneling boring whitewashing processing to tunnel, and closes steel mesh and metal mesh;
S6 built-in slip casting pipe below the top plate of coal working face carries out slip casting.
2. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S1, the trend of the vertical coal working face of I-steel is evenly arranged, and the two adjacent I-steel spacing are 0.5m~1.0m.
3. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S1, channel steel is 14# channel steel, and anchor cable spacing is 1~2m, anchor beam spacing 0.1m~0.5m.
4. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S2, the spacing in presplit blasting hole is 0.2m~0.7m, and presplit blasting hole is arranged in a linear, and the hole depth in presplit blasting hole is 5m~8m, presplit blasting hole aperture are 0.03m~0.07m.
5. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that The spacing of presplit blasting hole and anchor cable is 0.1m~0.3m.
6. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S2, the two sides of cumulative presplitting pipe are provided with several jewel holes being equally spaced, and the spacing between jewel hole is 0.01m~0.03m, The aperture of jewel hole is 0.003m~0.008m.
7. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S2, the horizontal sextant angle of presplit blasting hole and reserved back is 75 °~90 °.
8. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that In the S5, spray head when whitewashing is perpendicular to by spray plane, and distance is by spray plane 0.8m~1.0m;It is carried out using subregion circular pattern Injection.
9. medium-thickness seam coal working face according to claim 1 is along the construction technology of the lane Kong Hu method, which is characterized in that If shield lane shoulder nest local segment goaf is caving insufficient, empty position is filled using perlite.
CN201910704092.4A 2019-07-31 2019-07-31 A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu Pending CN110439560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910704092.4A CN110439560A (en) 2019-07-31 2019-07-31 A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910704092.4A CN110439560A (en) 2019-07-31 2019-07-31 A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu

Publications (1)

Publication Number Publication Date
CN110439560A true CN110439560A (en) 2019-11-12

Family

ID=68432804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910704092.4A Pending CN110439560A (en) 2019-07-31 2019-07-31 A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu

Country Status (1)

Country Link
CN (1) CN110439560A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939464A (en) * 2019-11-29 2020-03-31 天地科技股份有限公司 Gob-side entry retaining combined supporting method for adjacent working faces
CN111335900A (en) * 2020-03-25 2020-06-26 王�琦 High-strength anchoring and grouting self-tunneling method and system
CN112112668A (en) * 2020-09-25 2020-12-22 陕西煤业化工技术研究院有限责任公司 Gob-side entry retaining gob gangue blocking closed structure and manufacturing method thereof
CN113356907A (en) * 2021-07-15 2021-09-07 中煤第一建设有限公司 Gob-side entry retaining construction process for coal seam disaster prevention and control
CN116927809A (en) * 2023-09-12 2023-10-24 北京中京矿安科技有限公司 Roadway support structure and construction method thereof

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1983000357A1 (en) * 1981-07-24 1983-02-03 Gill, Arthur A method of and apparatus for hydraulic mining
CN101526001A (en) * 2008-11-26 2009-09-09 枣庄矿业(集团)有限责任公司滨湖煤矿 Comprehensive mining opposite-pull working face coal excavating process for thin coal bed
CN103726844A (en) * 2013-11-01 2014-04-16 神华集团有限责任公司 Automatic coal mining method based on coal mining work surface
CN108457651A (en) * 2018-01-24 2018-08-28 河南理工大学 A kind of coal mine roadside packing gob side entry retaining hydraulic splitting cuts top method
CN108643907A (en) * 2018-05-11 2018-10-12 山东科技大学 One kind being crushed direct top edge sky caving into lane without pillar mining method
CN108979638A (en) * 2018-09-10 2018-12-11 四川达竹煤电(集团)有限责任公司金刚煤矿 Coal cutting roadway wedge shape regenerates wall and the compound gob-side entry retaining method of one-leg shed beam
CN109098714A (en) * 2018-09-19 2018-12-28 三门峡龙王庄煤业有限责任公司 A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three
CN109854247A (en) * 2019-02-01 2019-06-07 何满潮 That stays lane cuts top method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1983000357A1 (en) * 1981-07-24 1983-02-03 Gill, Arthur A method of and apparatus for hydraulic mining
CN101526001A (en) * 2008-11-26 2009-09-09 枣庄矿业(集团)有限责任公司滨湖煤矿 Comprehensive mining opposite-pull working face coal excavating process for thin coal bed
CN103726844A (en) * 2013-11-01 2014-04-16 神华集团有限责任公司 Automatic coal mining method based on coal mining work surface
CN108457651A (en) * 2018-01-24 2018-08-28 河南理工大学 A kind of coal mine roadside packing gob side entry retaining hydraulic splitting cuts top method
CN108643907A (en) * 2018-05-11 2018-10-12 山东科技大学 One kind being crushed direct top edge sky caving into lane without pillar mining method
CN108979638A (en) * 2018-09-10 2018-12-11 四川达竹煤电(集团)有限责任公司金刚煤矿 Coal cutting roadway wedge shape regenerates wall and the compound gob-side entry retaining method of one-leg shed beam
CN109098714A (en) * 2018-09-19 2018-12-28 三门峡龙王庄煤业有限责任公司 A kind of soft extremely irregularcoal seam fully mechanized coal face gob-side entry retaining method of high methane three
CN109854247A (en) * 2019-02-01 2019-06-07 何满潮 That stays lane cuts top method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
东北煤炭技术编辑部: "《东北煤炭技术》", 31 December 1986, 东北内蒙古工业联合公司科学技术情报所 *
何俊等: "《峰峰矿区瓦斯地质规律与瓦斯治理技术》", 30 November 2012 *
李明: "《爆破切顶与联合支护技术在沿空留巷中的应用研究》", 《能源与环保》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939464A (en) * 2019-11-29 2020-03-31 天地科技股份有限公司 Gob-side entry retaining combined supporting method for adjacent working faces
CN111335900A (en) * 2020-03-25 2020-06-26 王�琦 High-strength anchoring and grouting self-tunneling method and system
CN111335900B (en) * 2020-03-25 2021-04-27 王�琦 High-strength anchoring and grouting self-tunneling method and system
CN112112668A (en) * 2020-09-25 2020-12-22 陕西煤业化工技术研究院有限责任公司 Gob-side entry retaining gob gangue blocking closed structure and manufacturing method thereof
CN113356907A (en) * 2021-07-15 2021-09-07 中煤第一建设有限公司 Gob-side entry retaining construction process for coal seam disaster prevention and control
CN116927809A (en) * 2023-09-12 2023-10-24 北京中京矿安科技有限公司 Roadway support structure and construction method thereof
CN116927809B (en) * 2023-09-12 2023-12-05 北京中京矿安科技有限公司 Roadway support structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN110439560A (en) A kind of construction technology of medium-thickness seam coal working face along the lane Kong Hu
CN101457651B (en) Filling stack advanced support method along empty tunnel in coal-gas co-milling Y-shaped ventilating system
CN108661643B (en) It a kind of coal working face end adopts return channel and cuts top release shield lane method
CN102661169B (en) Gob-side entry retaining method for anchor bolt network gangue bag wall body for coal mining without pillars
CN103161480B (en) Initiatively support the method for roadside packing gob side entry retaining
CN108894787A (en) Leave the pressure break release method of ore pillar stress concentration in Overburden gob area
CN108661646A (en) A kind of false top house column type shrink afterwards filling mining method
CN105735995A (en) Gob-side roadway retaining method based on roof cutting of soft roof plate
CN103061771B (en) Second mining mine fully mechanized coal face cuts eye driving and supporting method thereof
CN108049896B (en) A kind of fully mechanized coal face gob-side entry retaining method
CN110331978B (en) Environment reconstruction segmented medium-length hole subsequent filling mining method
CN104806246A (en) Gob-side entry retaining method for coal mine gateway by directional-predetermined crack blasting and truncating crest and pressure relief mode
CN110529144A (en) A kind of hybrid advanced support method of light section stope drift active workings
CN109488329A (en) A kind of broken water drenching country rock administering method of Deep Soft Rock Tunnel large deformation
CN104265294B (en) Coal pillar-free mining method for blasting mining face of steeply dipping seam
CN103982186B (en) The vertical Inclined strips sublevel caving of oper cylinler retrusive
CN111810197B (en) Pre-grouting reinforcement method for fault structural zone of working face
CN109779652A (en) A kind of expansion of coal-mine soft-rock tailentry is repaired and method for protecting support
CN102678123A (en) Gob-side entry retaining method for thin coal layer under hard limestone top plate
CN110219650B (en) Deep hole subsequent filling mining method in environment reconstruction stage
CN106285692B (en) A kind of construction method of gob side entry retaining
CN105888664A (en) Mining method for extremely-thick hard coal
CN105569699A (en) Inclined shaft development support technology for isolated coal pillar
CN105240012A (en) F-type section coal-mining method allowing commingled mining of coal pillars
CN203978443U (en) A kind of suspension device of gob side entry retaining

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191112

RJ01 Rejection of invention patent application after publication