CN110259512A CN201910635115.0A CN201910635115A CN110259512A CN 110259512 A CN110259512 A CN 110259512A CN 201910635115 A CN201910635115 A CN 201910635115A CN 110259512 A CN110259512 A CN 110259512A
Authority
CN
China
Prior art keywords
hole
shield
cover board
sealing structure
interim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910635115.0A
Other languages
Chinese (zh)
Other versions
CN110259512B (en
Inventor
赵星
王金龙
吕延豪
张海涛
胡金泉
许俊超
邓林恒
胡正波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201910635115.0A priority Critical patent/CN110259512B/en
Priority claimed from CN201910635115.0A external-priority patent/CN110259512B/en
Publication of CN110259512A publication Critical patent/CN110259512A/en
Application granted granted Critical
Publication of CN110259512B publication Critical patent/CN110259512B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Building Environments (AREA)

Abstract

The present invention relates to a kind of recyclable interim hole sealing structures in shield hole, and the cover board including being reserved with the structure roof in shield hole and for blocking the shield hole, the cover board is removably mounted in the structure roof.The interim hole sealing structure in shield hole provided by the invention can carry out sealing of hole to avoid cast-in-place concrete and long term is avoided to cut concrete by the way that cover board to be removably mounted in structure roof, it is easy for construction, time saving and energy saving, cover board can be recycled and be reused, and avoid the waste of engineering material.

Description

The recyclable interim hole sealing structure in shield hole
Technical field
The invention belongs to Tunnel Engineering technical fields, and in particular to a kind of recyclable interim hole sealing structure in shield hole.
Background technique
Shield method is the common construction in city underground underground section, and shield hole for hoist is the important composition of shield method Part is generally reserved for shield-tunneling construction use AT STATION in structural slab.And subway engineering is frequently encountered in current period Station Project In the case where reserving shield hole for hoist at a specified future date, used for shield tunnel construction at a specified future date.Traditional method is using cast-in-place concrete knot Structure backfills earthing after carrying out sealing of hole, carries out shield-tunneling construction after cutting cast-in-place concrete when shield-tunneling construction at a specified future date again.It is this to do Method is time-consuming and laborious and causes very large-engineering waste.
Summary of the invention
The present embodiments relate to a kind of recyclable interim hole sealing structures in shield hole, can at least solve the portion of the prior art Divide defect.
The present embodiments relate to a kind of recyclable interim hole sealing structure in shield hole, the structure including being reserved with shield hole Top plate and cover board for blocking the shield hole, the cover board are removably mounted in the structure roof.
As one of embodiment, knee wall is formed in Yu Suoshu structure roof, the cover board is removably mounted to described On knee wall.
As one of embodiment, multiple assembly bolts are reserved at the top of the knee wall, are correspondingly provided on Yu Suoshu cover board Multiple pilot holes, each assembly bolt are threaded through on each pilot hole correspondingly and are locked by nut.
As one of embodiment, the knee wall is concrete walls, and is integrally formed with the structure roof.
As one of embodiment, the knee wall and the structure roof formed by integrally casting or integral preform.
As one of embodiment, sealing structure is equipped at the lid conjunction between the cover board and the structure roof.
As one of embodiment, the sealing structure includes reserving in the structure roof and being located in the cover board With the Gask-O-Seal between the structure roof.
As one of embodiment, the gasket include ethylene propylene diene rubber matrix and be set to the ethylene propylene diene rubber The hydro-expansive rubber layer of baseline top.
As one of embodiment, which further includes shield, and the shield covers at It goes along with sb. to guard him in the structure roof and by the cover board in interior.
As one of embodiment, the cover board is prefabricated reinforced concrete cover board.
The embodiment of the present invention at least has the following beneficial effects:
The interim hole sealing structure in shield hole provided by the invention can be with by the way that cover board to be removably mounted in structure roof Avoid cast-in-place concrete from carrying out sealing of hole and long term being avoided to cut concrete, it is easy for construction, it is time saving and energy saving, cover board can recycle and Recycling, avoids the waste of engineering material.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with Other attached drawings are obtained according to these attached drawings.
Fig. 1 is the floor map of the interim hole sealing structure in shield hole provided in an embodiment of the present invention;
Fig. 2 is cross-sectional view of the Fig. 1 along A-A or B-B;
Fig. 3 is the enlarged structure schematic diagram of the part I in Fig. 2;
Fig. 4 is the structural schematic diagram of gasket provided in an embodiment of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts all other Embodiment shall fall within the protection scope of the present invention.
Such as Fig. 1-Fig. 3, the embodiment of the present invention provides a kind of recyclable interim hole sealing structure in shield hole, including is reserved with shield The structure roof 1 in structure hole and cover board 3 for blocking the shield hole, the cover board 3 are removably mounted to the structure top On plate 1.
Structure roof 1 is no different with station structure top plate in the prior art, and specific structure does not repeat herein.The structure The shield pore size and shape opened up on top plate 1 determines that this is this field routine techniques, is not made herein according to concrete engineering situation It is described in detail.
Above-mentioned cover board 3 can be metallic plate body, such as steel plate;It is preferably prefabricated reinforced concrete cover board 3, structure Intensity, corrosion resistance etc. are all easy to guarantee, and are easy to lift.It is to be appreciated that suspension hook 6 can be arranged at the top of the cover board 3, just In lifting installation or remove transhipment.
The interim hole sealing structure in shield hole provided in this embodiment, by the way that cover board 3 is removably mounted in structure roof 1, It can carry out sealing of hole and long term being avoided to cut concrete to avoid cast-in-place concrete, easy for construction, time saving and energy saving, cover board 3 can be with It recycles and reuses, avoid the waste of engineering material.
It, can be using bolt assembly, groove and tognue type assembly etc. often for the detachable connection method of cover board 3 and structure roof 1 Advise detachable assembling structure.Above-mentioned cover board 3 can directly cover conjunction in structure roof 1, such as spiral shell is reserved in structure roof 1 Bolt 4 realizes its being detachably connected with cover board 3;In a further preferred embodiment, such as Fig. 2 and Fig. 3, Yu Suoshu structure roof 1 On be formed with knee wall 2, the cover board 3 is removably mounted on the knee wall 2.
Above-mentioned knee wall 2 be preferably be concrete walls, and with the structure roof 1 be integrally formed, such as with structure top 1 formed by integrally casting of plate, or with 1 integral preform of structure roof.By the way that above-mentioned knee wall 2 is arranged, without changing the knot of structure roof 1 Structure and the detachable assembly for realizing cover board 3;On the other hand, the knee wall 2 can prevent 1 any standing water on top of structure roof flow over and from It is penetrated into the space of station in shield hole.
Correspondingly, the conventional detachable assembly knot such as bolt assembly, groove and tognue type assembly can be used between cover board 3 and knee wall 2 Structure.As preferred structure, such as Fig. 1-Fig. 3, it is reserved with multiple assembly bolts 4 at the top of the knee wall 2, it is right on Yu Suoshu cover board 3 Multiple pilot holes should be equipped with, each assembly bolt 4 is threaded through on each pilot hole correspondingly and locks by nut.
Based on the characteristic of above-mentioned 3 recoverable of cover board, in an alternate embodiment of the invention, so that the cover board 3 is applicable to not The closure in same specification shield hole, specifically: the cover board 3 includes central plate and multiple annular slabs, and the size of each annular slab is advised Lattice are sequentially increased, central plate with each annular slab from-inner-to-outer is successively nested is assembled into above-mentioned cover board 3 (for example, shield Kong Weifang Shape hole, above-mentioned central plate are square plate, and above-mentioned annular slab is square annular slab);Wherein, between most inner side annular slab and central plate with And spliced by bolt between adjacent two annular slab, it is possible to understand that ground opens up multiple blind-hole type spiral shells on the side wall of central plate Pit, correspondence opens up multiple through-hole type threaded holes on the side wall of each annular slab, also, it is preferred that be the threaded hole on annular slab being rank Terraced hole, including the large aperture section close to the annular slab outer rim side and for accommodating bolt head and close to the annular slab inner ring side And the small-bore section for being spirally connected with bolt spiro rod section, the assembly of other annular slabs can be influenced to avoid these radial bolts.It is logical Splicing between most inner side annular slab and central plate can be realized by crossing bolt, and can be used can be from most for the connecting method of exterior annular plate Exterior annular plate wears the splicing that the elongated bolt to central plate realizes each annular slab, or can also realize phase only with bolt Splicing (screw thread hole number can corresponding configuration) on each annular slab between adjacent two annular slabs.By the number for adjusting above-mentioned annular slab Amount and size, may be implemented the adjusting of 3 dimensions of cover board, to be suitable for the shield hole of different size.
In a further embodiment, which includes central plate and configures muti-piece exterior annular plate, each exterior annular plate Inner ring dimensions it is identical (identical as the dimensions of central plate) and the outer ring size specification of each exterior annular plate is different, Connecting method between exterior annular plate and central plate can refer to above-mentioned related content, not repeat herein.By using difference Exterior annular plate, the adjusting of 3 dimensions of cover board equally may be implemented, thus be suitable for different size shield hole.
In the adjustable embodiment of above-mentioned 3 dimensions of cover board, for the waterproof performance for guaranteeing the cover board 3, in cover board 3 After the completion of assembly, waterproof layer, such as waterproof membrane or brushing waterproof coating etc. can be set at the top of the cover board 3.
Above structure is advanced optimized, is equipped with sealing structure at the lid conjunction between the cover board 3 and the structure roof 1, The waterproof performance for guaranteeing the interim hole sealing structure in shield hole avoids the moisture in 1 upper layer earthing of structure roof from penetrating into from shield hole In the space of station.It is easy-to-understand to, the structure in structure roof 1 is directly covered on for cover board 3, above-mentioned sealing structure is set to two The junction of person;Structure on above-mentioned knee wall 2 is covered on for cover board 3, above-mentioned sealing structure is set to cover board 3 and knee wall 2 Junction.
Such as Fig. 3 and Fig. 4, which includes reserving in the structure roof 1 and being located in the cover board 3 and institute State the Gask-O-Seal 7 between structure roof 1.Common sealing material can be used in the gasket 7;In the present embodiment, it is preferable that Such as Fig. 4, the gasket 7 includes ethylene propylene diene rubber matrix 71 and the chance set on 71 top of ethylene propylene diene rubber matrix Water-expansible rubber layer 72, the ethylene propylene diene rubber matrix 71 are embedded in structure roof 1 in advance or are embedded on knee wall 2 in advance, can guarantee Seamless between the gasket 7 and lower component (1/ knee wall 2 of structure roof), hydro-expansive rubber layer 72 is swollen after absorbing water It is swollen, the gap eliminated between ethylene propylene diene rubber matrix 71 and cover board 3 is squeezed, the sealing performance of the gasket 7 is effectively improved. In a further embodiment, 7 slot of gasket is reserved to install above-mentioned gasket 7 in 3 bottom of cover board, be not described further herein.
Above structure, such as Fig. 2 are advanced optimized, which further includes shield 5, and the shield 5 covers It goes along with sb. to guard him in the structure roof 1 and by the cover board 3 in interior.The shield 5 is used to meet the force request after earthing backfill, Preferably cover sheet 3, meanwhile, further increase the waterproof performance of the interim hole sealing structure in shield hole.Above-mentioned shield 5 is preferably It is steel cage, structural strength is higher.The same settable suspension hook 6 in above-mentioned 5 top of shield, for lifting by crane installation or removing transhipment.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.

Claims (10)

1. a kind of recyclable interim hole sealing structure in shield hole, it is characterised in that: including be reserved with the structure roof in shield hole with And the cover board for blocking the shield hole, the cover board are removably mounted in the structure roof.
2. the interim hole sealing structure in shield hole that can be recycled as described in claim 1, it is characterised in that: in Yu Suoshu structure roof It is formed with knee wall, the cover board is removably mounted on the knee wall.
3. the interim hole sealing structure in shield hole that can be recycled as claimed in claim 2, it is characterised in that: pre- at the top of the knee wall There are multiple assembly bolts, multiple pilot holes are correspondingly provided on Yu Suoshu cover board, each assembly bolt is worn correspondingly It is locked on each pilot hole and through nut.
4. the interim hole sealing structure in shield hole that can be recycled as claimed in claim 2, it is characterised in that: the knee wall is coagulation Cob wall, and be integrally formed with the structure roof.
5. the interim hole sealing structure in shield hole that can be recycled as claimed in claim 4, it is characterised in that: the knee wall with it is described Structure roof formed by integrally casting or integral preform.
6. the recyclable interim hole sealing structure in shield hole as described in any one of claims 1 to 5, it is characterised in that: described Sealing structure is equipped at lid conjunction between cover board and the structure roof.
7. the interim hole sealing structure in shield hole that can be recycled as claimed in claim 6, it is characterised in that: the sealing structure includes It reserves in the structure roof and the Gask-O-Seal that is located between the cover board and the structure roof.
8. the interim hole sealing structure in shield hole that can be recycled as claimed in claim 7, it is characterised in that: the gasket includes three First EP rubbers matrix and hydro-expansive rubber layer set on the ethylene propylene diene rubber baseline top.
9. the recyclable interim hole sealing structure in shield hole as described in any one of claims 1 to 5, it is characterised in that: also wrap Shield is included, the shield covers in the structure roof and goes along with sb. to guard him the cover board in interior.
10. the interim hole sealing structure in shield hole that can be recycled as described in claim 1, it is characterised in that: the cover board is prefabricated Reinforced concrete cover plate.
CN201910635115.0A 2019-07-15 Recoverable shield constructs interim hole sealing structure in hole Active CN110259512B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910635115.0A CN110259512B (en) 2019-07-15 Recoverable shield constructs interim hole sealing structure in hole

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910635115.0A CN110259512B (en) 2019-07-15 Recoverable shield constructs interim hole sealing structure in hole

Publications (2)

Publication Number Publication Date
CN110259512A true CN110259512A (en) 2019-09-20
CN110259512B CN110259512B (en) 2024-11-12

Family

ID=

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333936A (en) * 1992-01-10 1994-08-02 Voest-Alpine Bergtechnik Gesellschaft M.B.H. Low profile mining machine having a cutter mounted on a slidable carriage
JPH1082279A (en) * 1996-09-05 1998-03-31 Chubu Electric Power Co Inc Earthquake resistant flexible joint of shield segment and execution method thereof
JP2001280078A (en) * 2001-03-08 2001-10-10 Ishikawajima Harima Heavy Ind Co Ltd Excavating method for excavator
JP2011122386A (en) * 2009-12-14 2011-06-23 Toda Constr Co Ltd Method of construction of underground structure, underground structure, and precast concrete side wall or intermediate wall/column for the same
CN104533426A (en) * 2014-11-10 2015-04-22 中铁第四勘察设计院集团有限公司 Method for constructing ultra-shallow buried tunnel under-passing highway by large-span covering excavating method
CN108590681A (en) * 2018-06-22 2018-09-28 中铁第勘察设计院集团有限公司 Shield well reserving hole quick blocking system and its construction method
CN208106480U (en) * 2018-04-27 2018-11-16 中铁八局集团电务工程有限公司 A kind of cover-plate type evacuation platform
CN109372541A (en) * 2018-11-27 2019-02-22 中铁第四勘察设计院集团有限公司 A kind of portal temporary plugging structure and its construction method suitable for shield tunnel
CN210599108U (en) * 2019-07-15 2020-05-22 中铁第四勘察设计院集团有限公司 Recoverable shield hole temporary sealing structure

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5333936A (en) * 1992-01-10 1994-08-02 Voest-Alpine Bergtechnik Gesellschaft M.B.H. Low profile mining machine having a cutter mounted on a slidable carriage
JPH1082279A (en) * 1996-09-05 1998-03-31 Chubu Electric Power Co Inc Earthquake resistant flexible joint of shield segment and execution method thereof
JP2001280078A (en) * 2001-03-08 2001-10-10 Ishikawajima Harima Heavy Ind Co Ltd Excavating method for excavator
JP2011122386A (en) * 2009-12-14 2011-06-23 Toda Constr Co Ltd Method of construction of underground structure, underground structure, and precast concrete side wall or intermediate wall/column for the same
CN104533426A (en) * 2014-11-10 2015-04-22 中铁第四勘察设计院集团有限公司 Method for constructing ultra-shallow buried tunnel under-passing highway by large-span covering excavating method
CN208106480U (en) * 2018-04-27 2018-11-16 中铁八局集团电务工程有限公司 A kind of cover-plate type evacuation platform
CN108590681A (en) * 2018-06-22 2018-09-28 中铁第勘察设计院集团有限公司 Shield well reserving hole quick blocking system and its construction method
CN109372541A (en) * 2018-11-27 2019-02-22 中铁第四勘察设计院集团有限公司 A kind of portal temporary plugging structure and its construction method suitable for shield tunnel
CN210599108U (en) * 2019-07-15 2020-05-22 中铁第四勘察设计院集团有限公司 Recoverable shield hole temporary sealing structure

Similar Documents

Publication Publication Date Title
CN105040685B (en) Prefabricated component with hollow structure
CN107628208B (en) Suitable for combining the precasting floating drum of the large-scale floating platform waterborne of building
CN107366297A (en) Offshore wind farm stake cladding vaseline coats anticorrosion structure and its construction method
CN107724261A (en) A kind of box culvert and caisson combining structure and construction method
EA010554B1 (en) Apparatus for nuclear waste disposal, method for manufacturing and installing the same
EP0248286B1 (en) Method and system for wet-decommissioning radioactively contaminated or activated components of nuclear reactor plants
CN102849186A (en) Overwater floating island
CN110042844A (en) A kind of construction method of cast-in-place major diameter foundation pit support pipe pile
CN109869028A (en) A kind of assembled steel reinforced concrete silo and preparation method thereof
CN205875736U (en) Sectional type shear force wall is to drawing sealing screw
WO2012049502A2 (en) Full-Contact Floating Roof for Liquid Storage Tanks
KR100729599B1 (en) Method and assembly for bridge pier mould construction using air steel pontoon
CN110259512A (en) The recyclable interim hole sealing structure in shield hole
CN204780883U (en) Prefab with hollow structure
CN107878697A (en) A kind of modular marine Multifunction working platform
CN206512730U (en) It is a kind of to realize the box that box wall body is used in turn
KR20100064452A (en) An artificial fishing banks
CN214832522U (en) Assembled drilling platform for reservoir bare rock group pile foundation
CN205576902U (en) Pile foundation of stress tube in advance of removable screw rod
CN213837199U (en) Assembled shear force wall of vertical connection
CN211446561U (en) Handle resistant environmental stress fracture's of bridge cable body PE sheath structure
CN207328757U (en) A kind of gravity foundation of marine stretching anode system
CN208733483U (en) A kind of underwater pillarwork of reinforced mesh reinforcement bridge
CN210766847U (en) Elastic transition section cylindrical foundation structure
CN208201737U (en) A kind of safeguard structure for bridge pier

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant