[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN114855519A - Saline soil roadbed laying method and roadbed structure - Google Patents

Saline soil roadbed laying method and roadbed structure Download PDF

Info

Publication number
CN114855519A
CN114855519A CN202210578103.0A CN202210578103A CN114855519A CN 114855519 A CN114855519 A CN 114855519A CN 202210578103 A CN202210578103 A CN 202210578103A CN 114855519 A CN114855519 A CN 114855519A
Authority
CN
China
Prior art keywords
layer
saline soil
geomembrane
embankment
laying
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202210578103.0A
Other languages
Chinese (zh)
Inventor
周凤玺
杨仕钊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Lanzhou University of Technology
Original Assignee
Lanzhou University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Lanzhou University of Technology filed Critical Lanzhou University of Technology
Priority to CN202210578103.0A priority Critical patent/CN114855519A/en
Publication of CN114855519A publication Critical patent/CN114855519A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/16Reinforcements
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/06Methods or arrangements for protecting foundations from destructive influences of moisture, frost or vibration
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • E01C7/34Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ made of several courses which are not bound to each other ; Separating means therefor, e.g. sliding layers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明涉及一种盐渍土路基铺设方法及路基结构,涉及盐渍土区域路基施工领域,方法包括:从地基开始进行分层填筑压实和填料得到路堤;在所述路堤上沿路线纵向铺设隔断层;在所述隔断层上回填基层。本发明能够解决土中气体在隔断层下聚集的问题提高盐渍土路基的安全性。

Figure 202210578103

The invention relates to a method for laying saline soil subgrade and a subgrade structure, and relates to the field of subgrade construction in saline soil areas. Lay a barrier layer; backfill the base layer on the barrier layer. The invention can solve the problem of gas accumulation in the soil under the barrier layer, and improve the safety of the saline soil roadbed.

Figure 202210578103

Description

一种盐渍土路基铺设方法及路基结构A kind of saline soil roadbed laying method and roadbed structure

技术领域technical field

本发明涉及盐渍土区域路基施工领域,特别是涉及一种盐渍土路基铺设方法及路基结构。The invention relates to the field of roadbed construction in saline soil areas, in particular to a method for laying saline soil roadbeds and a roadbed structure.

背景技术Background technique

在外部环境影响下,盐渍土中的水分和盐分均发生运移,会引发不同程度的病害,表现为盐胀、冻胀及翻浆等会导致路基开裂、隆起、膨胀,从而降低了路基的稳定性和强度。如果能够有效阻止路基下部盐分随地下水或毛细水的上升迁移,就能有效的解决盐渍土水盐迁移引起的破坏和影响。通过设置隔断层的方法来阻止盐分的上升是目前常用的一种盐渍土路基处理方法。按照隔断层的材料,可以将隔断层分为砂石材料隔断层和土工材料隔断层等。Under the influence of the external environment, the water and salt in the saline soil will migrate, which will cause different degrees of diseases, such as salt heave, frost heave and pulping, which will cause the subgrade to crack, bulge and swell, thereby reducing the subgrade. Stability and strength. If the salt at the bottom of the subgrade can be effectively prevented from migrating with the groundwater or capillary water, the damage and influence caused by the migration of water and salt in the saline soil can be effectively solved. It is a commonly used treatment method for saline soil roadbed to prevent the rise of salinity by setting a barrier layer. According to the material of the barrier layer, the barrier layer can be divided into sandstone material barrier layer and geotechnical material barrier layer.

其中,由砂石类材料填筑而成的隔断层称为砂石材料隔断层,但对砂石材料的选择以及施工有着严格的要求;由土工布材料构成的隔断层称为土工材料隔断层,一般设置在路堤和路床或底基层和上基层之间,土工膜隔断层虽然具有较好的隔水、隔盐、施工简便和降低路基高度的特点,但由于其具有不透水性,不利于路基中水气逸散,在其下面会形成气体聚积,造成软弱夹层。Among them, the barrier layer filled with sand and gravel materials is called sand and stone material barrier layer, but there are strict requirements for the selection and construction of sand and gravel materials; the barrier layer composed of geotextile materials is called geotechnical material barrier layer , Generally set between the embankment and the road bed or between the sub-base and the upper base. Although the geomembrane partition layer has the characteristics of good water resistance, salt isolation, easy construction and reduction of the height of the roadbed, it is impermeable due to its impermeability. It is conducive to the escape of water vapor in the roadbed, and gas accumulation will be formed under it, resulting in a weak interlayer.

发明内容SUMMARY OF THE INVENTION

本发明的目的是提供一种盐渍土路基铺设方法及路基结构,能够解决土中气体在隔断层下聚集的问题提高盐渍土路基的安全性。The purpose of the present invention is to provide a method for laying a saline soil roadbed and a roadbed structure, which can solve the problem of gas accumulation in the soil under the barrier layer and improve the safety of the saline soil roadbed.

为实现上述目的,本发明提供了如下方案:For achieving the above object, the present invention provides the following scheme:

一种盐渍土路基铺设方法,包括:A method for laying saline soil roadbed, comprising:

从地基开始进行分层填筑压实和填料得到路堤;The embankment is obtained by layering compaction and filling from the foundation;

在所述路堤上沿路线纵向铺设隔断层;laying a barrier layer longitudinally along the route on said embankment;

在所述隔断层上回填基层。The base layer is backfilled on the barrier layer.

可选地,所述在所述路堤上沿路线纵向铺设隔断层,具体包括:Optionally, the longitudinally laying a barrier layer along the route on the embankment specifically includes:

在所述路堤上沿路线全断面铺设所述隔断层的土工膜;Lay the geomembrane of the barrier layer along the entire section of the road on the embankment;

在所述土工膜上铺设所述隔断层的保护层。A protective layer of the barrier layer is laid on the geomembrane.

可选地,在所述土工膜上铺设隔断层的保护层之后,还包括:Optionally, after laying the protective layer of the insulating layer on the geomembrane, it also includes:

在所述保护层上铺设粗粒土并进行碾压;所述粗粒土与所述保护层的厚度和小于或者等于400mm。Coarse-grained soil is laid on the protective layer and rolled; the thickness of the coarse-grained soil and the protective layer is less than or equal to 400mm.

一种盐渍土路基结构,所述盐渍土路基结构应用上述所述的盐渍土路基铺设方法,所述盐渍土路基结构包括:路面层、基层、隔断层和路堤;A saline soil subgrade structure, the saline soil subgrade structure using the above-mentioned saline soil subgrade laying method, the saline soil subgrade structure comprising: a pavement layer, a base layer, a partition layer and an embankment;

所述隔断层设置在所述基层和所述路堤之间;所述基层设置在所述路面层和所述隔断层之间。The blocking layer is arranged between the base layer and the road embankment; the base layer is arranged between the road surface layer and the blocking layer.

可选地,所述路堤的松铺厚度小于或者等于300mm。Optionally, the loose thickness of the embankment is less than or equal to 300mm.

可选地,所述隔断层的路拱横坡坡度范围为2%-5%。Optionally, the slope of the cross slope of the road arch of the partition layer ranges from 2% to 5%.

可选地,所述隔断层包括土工膜和铺设在所述土工膜上的保护层;所述土工膜铺设在所述路堤上。Optionally, the blocking layer includes a geomembrane and a protective layer laid on the geomembrane; the geomembrane is laid on the road embankment.

可选地,所述路面层的边坡坡度范围为1:1.5-1:2。Optionally, the slope of the road surface layer ranges from 1:1.5 to 1:2.

可选地,所述土工膜包括依次铺设的上层、中间层和下层;所述上层结构为玻璃纤维网或疏松处置玻璃纤维网;中间层为孔直径为0.1-10μm的聚乙烯防水透气膜;下层为疏松处置玻璃纤维网。Optionally, the geomembrane comprises an upper layer, an intermediate layer and a lower layer laid in sequence; the upper layer structure is a glass fiber mesh or a loosely treated glass fiber mesh; the intermediate layer is a polyethylene waterproof and breathable membrane with a pore diameter of 0.1-10 μm; The lower layer is a loosely disposed glass fiber mesh.

根据本发明提供的具体实施例,本发明公开了以下技术效果:According to the specific embodiments provided by the present invention, the present invention discloses the following technical effects:

本发明从地基开始进行分层填筑压实和填料得到路堤;在所述路堤上沿路线纵向铺设隔断层;在所述隔断层上回填基层。通过在路堤上铺设隔断层,能够解决土中气体在隔断层下聚集的问题提高盐渍土路基的安全性。The present invention starts from the foundation, carries out layered filling, compaction and filling to obtain road embankment; lays a barrier layer on the road embankment longitudinally along the route; and backfills the base layer on the barrier layer. By laying a barrier layer on the embankment, the problem of gas accumulation in the soil under the barrier layer can be solved and the safety of the saline soil subgrade can be improved.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动性的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the accompanying drawings required in the embodiments will be briefly introduced below. Obviously, the drawings in the following description are only some of the present invention. In the embodiments, for those of ordinary skill in the art, other drawings can also be obtained according to these drawings without creative labor.

图1为本发明提供的盐渍土路基铺设方法流程图;Fig. 1 is the flow chart of the method for laying saline soil roadbed provided by the present invention;

图2为本发明提供的盐渍土路基结构示意图。Figure 2 is a schematic structural diagram of the saline soil roadbed provided by the present invention.

符号说明:Symbol Description:

4-土工膜与地基距离,5-路面层,6-基层,7-隔断层的路拱横坡,8-路堤,12-土工膜,14-边坡坡度,15-保护层。4- distance between geomembrane and foundation, 5- pavement layer, 6- base layer, 7- cross slope of road arch of partition layer, 8- embankment, 12- geomembrane, 14- slope of side slope, 15- protection layer.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

本发明的目的是提供一种盐渍土路基铺设方法及路基结构,能够解决土中气体在隔断层下聚集的问题提高盐渍土路基的安全性。The purpose of the present invention is to provide a method for laying a saline soil roadbed and a roadbed structure, which can solve the problem of gas accumulation in the soil under the barrier layer and improve the safety of the saline soil roadbed.

为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。In order to make the above objects, features and advantages of the present invention more clearly understood, the present invention will be described in further detail below with reference to the accompanying drawings and specific embodiments.

如图1所示,本发明提供的一种盐渍土路基铺设方法,包括:As shown in Figure 1, a method for laying saline soil roadbed provided by the present invention comprises:

步骤101:从地基开始进行分层填筑压实和填料得到路堤。Step 101: Starting from the foundation, perform layered filling, compaction and filling to obtain an embankment.

对于路堤8施工:For Embankment 8 construction:

1、沿线路侧取土坑应按设计要求做好排水,并符合环保要求。1. The borrow pit along the side of the line should be well drained according to the design requirements, and meet the environmental protection requirements.

2、路堤8应分层填筑压实,松铺厚度宜不超过300mm。碾压时宜按最佳含水率±1%控制,对于粗粒土含水率不应超过最佳含水率-2%~+3%。粗粒土的压实厚度不超过300mm,风积沙的压实层厚度不超过400mm,雨天不宜施工。2. Embankment 8 should be filled and compacted in layers, and the thickness of loose paving should not exceed 300mm. When rolling, it should be controlled according to the optimum moisture content ±1%, and the moisture content of coarse-grained soil should not exceed the optimum moisture content -2% to +3%. The compaction thickness of coarse-grained soil shall not exceed 300mm, the compaction thickness of aeolian sand shall not exceed 400mm, and construction shall not be carried out in rainy days.

3、路堤8的施工,应从基底处理开始连续施工,并连续填筑到隔断层的保护层15的顶部。3. For the construction of the embankment 8, it should be continuously constructed from the base treatment, and should be continuously filled to the top of the protective layer 15 of the partition layer.

4、地下水位高的黏性盐渍土地区,宜在夏季施工;砂性盐渍土地区,宜在春季和夏初施工;强盐渍土地区,宜在表层含盐低的春季施工。4. In the viscous saline soil area with high groundwater level, construction should be carried out in summer; in the sandy saline soil area, construction should be carried out in spring and early summer; in the strong saline soil area, construction should be carried out in spring when the surface salt content is low.

5、路堤8填料应加强施工过程中对于填料的含盐量控制,每10000m3应做一组含盐量测试,料源发生变化时应随时测试。测试结果达不到相应层位技术要求的填料严禁使用,并立即清理出场。5. The embankment 8 filler should strengthen the control of the salt content of the filler during the construction process, and a set of salt content tests should be done every 10,000m 3 , and should be tested at any time when the material source changes. Fillers whose test results do not meet the technical requirements of the corresponding horizon are strictly prohibited from use, and should be cleaned up immediately.

步骤102:在所述路堤上沿路线纵向铺设隔断层;其中,所述在所述路堤上沿路线纵向铺设隔断层,具体包括:在所述路堤上沿路线全断面铺设所述隔断层的土工膜;在所述土工膜上铺设所述隔断层的保护层。在所述在所述土工膜上铺设隔断层的保护层之后,还包括:在所述保护层上铺设粗粒土并进行碾压;所述粗粒土与所述保护层的厚度和小于或者等于400mm。Step 102: Lay a barrier layer on the embankment along the longitudinal direction of the route; wherein, the step of laying the barrier layer on the embankment along the longitudinal direction of the route specifically includes: laying the barrier layer on the embankment along the entire section of the route. membrane; laying the protective layer of the barrier layer on the geomembrane. After laying the protective layer of the isolation layer on the geomembrane, the method further includes: laying coarse-grained soil on the protective layer and rolling it; the sum of the thicknesses of the coarse-grained soil and the protective layer is less than or Equal to 400mm.

对于隔断层施工:For barrier construction:

1、土工膜12应沿路线纵向全断面铺设,铺展后应紧贴下承层,不得有褶皱。有破损时,应在破损处用2倍破损面积的膜材修补。1. Geomembrane 12 should be laid along the entire longitudinal section of the route. After spreading, it should be close to the lower bearing layer without wrinkles. When there is damage, the damaged area should be repaired with a membrane material with twice the damaged area.

2、土工膜12纵向搭接应内幅压外幅,搭接宽度不宜小于200mm,最外侧一幅搭接宽度应大于300mm;横向搭接宽度应大于500mm。2. The longitudinal lap of geomembrane 12 should press the inner width against the outer width, the lap width should not be less than 200mm, the outermost lap width should be greater than 300mm, and the horizontal lap width should be greater than 500mm.

3、土工膜12铺设完成后,并应及时上料保护层15覆盖,避免长时间暴晒。3. After the geomembrane 12 is laid, it should be covered with the protective layer 15 in time to avoid prolonged exposure to the sun.

4、土工膜12与土工膜12配合设置的保护层15中不得夹有带棱角的石块,并应严格控制土工膜12距离80mm以内的粒料最大粒径不得大于50mm,必要时应人工捡除。4. The protective layer 15 set by the geomembrane 12 and the geomembrane 12 shall not contain angular stones, and the maximum particle size of the particles within 80mm of the geomembrane 12 shall not be greater than 50mm, and shall be manually picked up if necessary. remove.

5、土工膜12上保护层15填料应采用轻型推土机或人工摊铺,运料车应倒行卸料或人工倒运。5. The filling of the protective layer 15 on the geomembrane 12 should be paved with light bulldozers or manually, and the material transporter should be unloaded or transported manually.

6、铺设在细粒土内的土工膜12,其上应设厚度不小于0.3m的保护层15,铺设在粗粒土内的土工膜12,其上保护层15厚度可采用0.1m。可采用中粗砂或砂砾,最大粒径不应大于50mm,粒径小于0.075mm的颗粒含量不应大于10%。6. The geomembrane 12 laid in the fine-grained soil should be provided with a protective layer 15 with a thickness of not less than 0.3m. The thickness of the geomembrane 12 laid in the coarse-grained soil can be 0.1m. Medium-coarse sand or gravel can be used, the maximum particle size should not be greater than 50mm, and the content of particles with a particle size smaller than 0.075mm should not be greater than 10%.

7、保护层15摊平后先碾压2~3遍,再铺一层粗粒土,与上保护层15一起碾压,两者厚度和应不超过400mm。7. After the protective layer 15 is flattened, roll it 2-3 times first, then lay a layer of coarse-grained soil, and roll it together with the upper protective layer 15. The sum of the thicknesses of the two should not exceed 400mm.

步骤103:在所述隔断层上回填基层。Step 103: Backfill the base layer on the insulating layer.

高速及一级公路施工中,路堤8至保护层15顶面压实度应≥96%;其他公路≥95%。高速及一级公路施工中,隔断层(土工膜12与保护层15)压实度应≥96%;其他公路≥94%。高速及一级公路施工中,隔断层(土工膜12与保护层15)至路面层5顶部压实度应≥94%;其他公路≥93%。In the construction of expressways and first-class highways, the compaction degree of the top surface of embankment 8 to protective layer 15 should be ≥96%; other highways should be ≥95%. In the construction of expressways and first-class highways, the compaction degree of the partition layer (geomembrane 12 and protective layer 15) should be ≥96%; other highways should be ≥94%. In the construction of expressways and first-class highways, the compaction degree of the partition layer (geomembrane 12 and protective layer 15) to the top of the pavement layer 5 should be ≥94%; other highways should be ≥93%.

如图2所示,本发明提供了一种盐渍土路基结构,所述盐渍土路基结构应用上述所述的盐渍土路基铺设方法,所述盐渍土路基结构包括:路面层5、基层6、隔断层和路堤8;所述隔断层设置在所述基层6和所述路堤8之间;所述基层6设置在所述路面层5和所述隔断层之间。路面层5、基层6和路堤8为从上而下的分布关系,其中,土工膜12与保护层15在基层6和路堤8之间铺设,且需根据土质和盐渍化程度决定边坡坡度14。As shown in FIG. 2, the present invention provides a saline soil subgrade structure, the saline soil subgrade structure is applied with the above-mentioned saline soil subgrade laying method, and the saline soil subgrade structure includes: a pavement layer 5, The base layer 6, the barrier layer and the road embankment 8; the barrier layer is arranged between the base layer 6 and the road embankment 8; the base layer 6 is arranged between the road surface layer 5 and the barrier layer. The pavement layer 5, the base layer 6 and the embankment 8 are distributed from top to bottom, in which the geomembrane 12 and the protective layer 15 are laid between the base layer 6 and the embankment 8, and the slope of the slope needs to be determined according to the soil quality and the degree of salinization 14.

作为一种可选地实施方式,所述路堤8的松铺厚度小于或者等于300mm。As an optional embodiment, the loose thickness of the road embankment 8 is less than or equal to 300 mm.

作为一种可选地实施方式,所述隔断层的路拱横坡7坡度范围为2%-5%。隔断层的路拱横坡7坡度不应小于2%,最大横坡不应超过5%。坡度百分比=高程增量/水平增量(正切值)*100%,工程中通常用百分率表示。As an optional implementation manner, the slope range of the road arch cross slope 7 of the partition layer is 2%-5%. The slope of the road arch cross slope 7 of the partition layer should not be less than 2%, and the maximum cross slope should not exceed 5%. Slope percentage=elevation increment/horizontal increment (tangent value)*100%, usually expressed as a percentage in engineering.

作为一种可选地实施方式,所述隔断层包括土工膜12和铺设在所述土工膜12上的保护层15;所述土工膜12铺设在所述路堤8上。隔断层设置在基层6以下,高出原地面0.5m以上,并不小于当地的最大冻深。本发明的土工膜12为隔水透气膜。土工膜与地基距离4≥0.5m。As an optional embodiment, the blocking layer includes a geomembrane 12 and a protective layer 15 laid on the geomembrane 12 ; the geomembrane 12 is laid on the embankment 8 . The partition layer is set below the base layer 6, higher than 0.5m above the original ground, and not less than the local maximum freezing depth. The geomembrane 12 of the present invention is a water-proof and breathable membrane. The distance between the geomembrane and the foundation is 4 ≥ 0.5m.

作为一种可选地实施方式,所述路面层5的边坡坡度14范围为1:1.5-1:2。边坡坡度同样也是正切值,设高程为单位1,即坡度=边坡高程\水平增量,通常用1:**表示,例如1:1.5换算为角度单位约为33°As an optional implementation manner, the slope 14 of the road surface layer 5 ranges from 1:1.5 to 1:2. The slope of the slope is also a tangent value, and the unit of elevation is set to 1, that is, slope = slope elevation\horizontal increment, usually expressed as 1:**, for example, 1:1.5 is converted into an angle unit of about 33°

作为一种可选地实施方式,所述土工膜12包括依次铺设的上层、中间层和下层;所述上层结构为玻璃纤维网或疏松处置玻璃纤维网;中间层为孔直径为0.1-10μm的聚乙烯防水透气膜;下层为疏松处置玻璃纤维网。本发明的土工膜12为复合膜,能够实现隔水透气。As an optional embodiment, the geomembrane 12 includes an upper layer, an intermediate layer and a lower layer laid in sequence; the upper layer structure is a glass fiber mesh or a loosely treated glass fiber mesh; the intermediate layer is a pore diameter of 0.1-10 μm. Polyethylene waterproof and breathable membrane; the lower layer is a loosely disposed glass fiber mesh. The geomembrane 12 of the present invention is a composite membrane, which can achieve water resistance and ventilation.

本发明在砂石材料质量不易控制或地下水位较高的情况下在盐渍土区域路基施工中解决病害,提高盐渍土路基施工的经济型和安全性。利用隔水透气膜形成隔断层,其原理是土体孔隙中的气体,通常在具有一定湿度的水蒸汽的状态下,水颗粒非常细小,根据毛细运动的原理,可以顺利渗透到毛细管到另一侧,从而发生透气现象。当孔隙中为液态水时,颗粒变大,由于水表面张力的作用,水分子就不能顺利渗透到另一侧,也就是防止了水的渗透发生,使透气膜有了防水的功能。具体应用时按照耐老化性、抗腐蚀性和耐冻性等的方面的要求进行选择隔水透气膜的材料。能够在隔断土中水盐迁移上升的同时,利于隔断层下部气体的逸散,具有较好的隔水、隔盐、施工简便等特点,可有效解决砂石类材料隔断层造价髙且施工较麻烦的不足以及传统土工膜隔断层不利于地基中气体逸散的缺点,从而更好地达到处治盐渍土地基病害的目的。The invention solves the disease in the subgrade construction in the saline soil area under the condition that the quality of the sand and gravel material is difficult to control or the groundwater level is high, and improves the economy and safety of the subgrade construction of the saline soil. The water-permeable membrane is used to form the barrier layer. The principle is that the gas in the soil pores, usually in the state of water vapor with a certain humidity, the water particles are very small. According to the principle of capillary motion, it can smoothly penetrate into the capillary to another side, so that the phenomenon of ventilation occurs. When the pores are liquid water, the particles become larger, and due to the surface tension of the water, the water molecules cannot smoothly penetrate to the other side, that is, the penetration of water is prevented, and the breathable membrane has a waterproof function. In specific applications, the material of the waterproof and breathable membrane is selected according to the requirements of aging resistance, corrosion resistance and freezing resistance. It can facilitate the escape of gas in the lower part of the partition layer while the water and salt in the partition soil migrate and rise. It has the characteristics of good water isolation, salt isolation, and simple construction. The lack of trouble and the disadvantage that the traditional geomembrane partition layer is not conducive to the escape of gas in the foundation, so as to better achieve the purpose of treating saline soil foundation diseases.

本发明的隔断层采用隔水透气土工膜,按路基处理宽度铺设隔水透气土工膜,应铺设平展并紧贴地基中,在膜上回填基层,并分层填筑碾压;用隔水透气土工膜将待处理区域包覆起来。本发明可有效防止盐渍土中水盐迁移引起的地基盐胀、腐蚀等病害,避免土中气体在隔断层下聚集,施工方便,工程造价低。The barrier layer of the present invention adopts a water-proof and breathable geomembrane. The water-proof and breathable geomembrane is laid according to the width of the roadbed treatment. It should be laid flat and close to the foundation. Geomembrane wraps the area to be treated. The invention can effectively prevent the foundation salt swelling, corrosion and other diseases caused by the migration of water and salt in the saline soil, avoid the accumulation of gas in the soil under the partition layer, and has convenient construction and low construction cost.

本说明书中各个实施例采用递进的方式描述,每个实施例重点说明的都是与其他实施例的不同之处,各个实施例之间相同相似部分互相参见即可。The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments, and the same and similar parts between the various embodiments can be referred to each other.

本文中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处。综上所述,本说明书内容不应理解为对本发明的限制。The principles and implementations of the present invention are described herein using specific examples. The descriptions of the above embodiments are only used to help understand the method and the core idea of the present invention; meanwhile, for those skilled in the art, according to the present invention There will be changes in the specific implementation and application scope. In conclusion, the contents of this specification should not be construed as limiting the present invention.

Claims (9)

1.一种盐渍土路基铺设方法,其特征在于,包括:1. a saline soil roadbed laying method, is characterized in that, comprising: 从地基开始进行分层填筑压实和填料得到路堤;The embankment is obtained by layering compaction and filling from the foundation; 在所述路堤上沿路线纵向铺设隔断层;laying a barrier layer longitudinally along the route on said embankment; 在所述隔断层上回填基层。The base layer is backfilled on the barrier layer. 2.根据权利要求1所述的盐渍土路基铺设方法,其特征在于,所述在所述路堤上沿路线纵向铺设隔断层,具体包括:2 . The method for laying saline soil roadbed according to claim 1 , wherein the longitudinally laying a barrier layer along the route on the embankment comprises: 2 . 在所述路堤上沿路线全断面铺设所述隔断层的土工膜;Lay the geomembrane of the barrier layer along the entire section of the road on the embankment; 在所述土工膜上铺设所述隔断层的保护层。A protective layer of the barrier layer is laid on the geomembrane. 3.根据权利要求2所述的盐渍土路基铺设方法,其特征在于,在所述土工膜上铺设隔断层的保护层之后,还包括:3. The method for laying saline soil roadbed according to claim 2, characterized in that, after laying the protective layer of the barrier layer on the geomembrane, the method further comprises: 在所述保护层上铺设粗粒土并进行碾压;所述粗粒土与所述保护层的厚度和小于或者等于400mm。Coarse-grained soil is laid on the protective layer and rolled; the thickness of the coarse-grained soil and the protective layer is less than or equal to 400mm. 4.一种盐渍土路基结构,其特征在于,所述盐渍土路基结构应用权利要求1-3任意一项所述的盐渍土路基铺设方法,所述盐渍土路基结构包括:路面层、基层、隔断层和路堤;4. A saline soil subgrade structure, wherein the saline soil subgrade structure is applied with the saline soil subgrade laying method according to any one of claims 1-3, and the saline soil subgrade structure comprises: a road surface Layers, base layers, barrier layers and embankments; 所述隔断层设置在所述基层和所述路堤之间;所述基层设置在所述路面层和所述隔断层之间。The blocking layer is arranged between the base layer and the road embankment; the base layer is arranged between the road surface layer and the blocking layer. 5.根据权利要求4所述的盐渍土路基结构,其特征在于,所述路堤的松铺厚度小于或者等于300mm。5 . The saline soil subgrade structure according to claim 4 , wherein the loose thickness of the embankment is less than or equal to 300 mm. 6 . 6.根据权利要求4所述的盐渍土路基结构,其特征在于,所述隔断层的路拱横坡坡度范围为2%-5%。6 . The saline soil subgrade structure according to claim 4 , wherein the cross slope of the road arch of the partition layer ranges from 2% to 5%. 7 . 7.根据权利要求4所述的盐渍土路基结构,其特征在于,所述隔断层包括土工膜和铺设在所述土工膜上的保护层;所述土工膜铺设在所述路堤上。7 . The saline soil roadbed structure according to claim 4 , wherein the blocking layer comprises a geomembrane and a protective layer laid on the geomembrane; the geomembrane is laid on the embankment. 8 . 8.根据权利要求4所述的盐渍土路基结构,其特征在于,所述路面层的边坡坡度范围为1:1.5-1:2。8 . The saline soil subgrade structure according to claim 4 , wherein the slope of the road surface layer ranges from 1:1.5 to 1:2. 9 . 9.根据权利要求7所述的盐渍土路基结构,其特征在于,所述土工膜包括依次铺设的上层、中间层和下层;所述上层结构为玻璃纤维网或疏松处置玻璃纤维网;中间层为孔直径为0.1-10μm的聚乙烯防水透气膜;下层为疏松处置玻璃纤维网。9 . The saline soil roadbed structure according to claim 7 , wherein the geomembrane comprises an upper layer, a middle layer and a lower layer laid in sequence; the upper layer structure is a glass fiber mesh or a loosely treated glass fiber mesh; the middle The layer is a polyethylene waterproof and breathable membrane with a hole diameter of 0.1-10 μm; the lower layer is a loosely disposed glass fiber mesh.
CN202210578103.0A 2022-05-25 2022-05-25 Saline soil roadbed laying method and roadbed structure Pending CN114855519A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210578103.0A CN114855519A (en) 2022-05-25 2022-05-25 Saline soil roadbed laying method and roadbed structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210578103.0A CN114855519A (en) 2022-05-25 2022-05-25 Saline soil roadbed laying method and roadbed structure

Publications (1)

Publication Number Publication Date
CN114855519A true CN114855519A (en) 2022-08-05

Family

ID=82639785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210578103.0A Pending CN114855519A (en) 2022-05-25 2022-05-25 Saline soil roadbed laying method and roadbed structure

Country Status (1)

Country Link
CN (1) CN114855519A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140771A (en) * 2011-01-27 2011-08-03 河南省新开元路桥工程咨询有限公司 Construction method for processing saline soil roadbed by separation layer
US20120263529A1 (en) * 2011-04-12 2012-10-18 Quackenboss John S Waterproof roadbed construction
CN202595703U (en) * 2012-03-31 2012-12-12 山东宏祥化纤集团有限公司 Waterproof gas-permeable film
CN103538260A (en) * 2012-07-09 2014-01-29 宏祥新材料股份有限公司 Production process for self-exhausting waterproof coiled material of water conservancy project
CN110195379A (en) * 2019-05-17 2019-09-03 中铁二院工程集团有限责任公司 Consider non-fragment orbit coarse grain salt marsh dirt road embankment structure and construction method that violent temperature influences
CN111455757A (en) * 2020-04-14 2020-07-28 黑龙江省龙建路桥第六工程有限公司 Road bed universe is hydrophobic-compound three-dimensional geomembrane that blocks water

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102140771A (en) * 2011-01-27 2011-08-03 河南省新开元路桥工程咨询有限公司 Construction method for processing saline soil roadbed by separation layer
US20120263529A1 (en) * 2011-04-12 2012-10-18 Quackenboss John S Waterproof roadbed construction
CN202595703U (en) * 2012-03-31 2012-12-12 山东宏祥化纤集团有限公司 Waterproof gas-permeable film
CN103538260A (en) * 2012-07-09 2014-01-29 宏祥新材料股份有限公司 Production process for self-exhausting waterproof coiled material of water conservancy project
CN110195379A (en) * 2019-05-17 2019-09-03 中铁二院工程集团有限责任公司 Consider non-fragment orbit coarse grain salt marsh dirt road embankment structure and construction method that violent temperature influences
CN111455757A (en) * 2020-04-14 2020-07-28 黑龙江省龙建路桥第六工程有限公司 Road bed universe is hydrophobic-compound three-dimensional geomembrane that blocks water

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
速宝玉等: "《土工膜作为防渗体的设计考虑》", 《河海科技进展》 *
郭超: "《克塔高速公路工程盐渍土路段施工技术》", 《水利水电施工》 *

Similar Documents

Publication Publication Date Title
CN113445396B (en) High-fill road foundation filling construction method for high liquid limit soil road section
CN110485228B (en) Hydrothermal closed type anti-frost-heaving slurry-turning high-strength highway subgrade structure and construction method
Keller Application of geosynthetics on low-volume roads
CN111622040B (en) Expansive soil composite roadbed structure type and construction method thereof
CN203212970U (en) Red clay roadbed structure
CN104631254A (en) Construction method of geogrid reinforced clay edge-covered tailing subgrade
CN101245574A (en) Method for building over loading railway road-bed on salting ground
CN105297570B (en) Special soil subgrade structure and construction method thereof
CN109958018A (en) A kind of heavy rainfall urban road water-permeable pavement structure and its construction method
CN109811748B (en) A kind of highway subgrade treatment method in permafrost area
CN111441211A (en) A carbonaceous soft rock-geosynthetic composite roadbed structure
CN106676991A (en) Expansive soil embankment structure improved and reinforced by sandwich method and construction method
CN105421469B (en) A kind of Fill Reinforced With Geogrids covering wall construction and construction method
CN107100047A (en) Suitable for the rock salt bittern road structure and construction method in playa area
CN111636443B (en) Guiding and sucking type swelling soil slope shallow water control covering system based on capillary retardation mechanism
CN101418565A (en) Qinghai-tibet railway permafrost wetland ground treatment technique
CN112982050A (en) Regenerated roadbed base filler and regenerated roadbed construction method
CN106087639A (en) A kind of highway, Irish bridge structure and Irish bridge construction method
CN108774931A (en) A kind of subgrade construction technique suitable for saline soil area
CN103243624B (en) Construction method for salty soil district railway roadbed with water content lower than liquid limit
CN111794030A (en) The method of widening the embankment foundation at the building through the embankment
CN113265924B (en) Construction method for using red bed mudstone blocks as high-fill dynamic compaction roadbed filling
CN204825539U (en) Control difference in temperature prevents roadbed structure of cold mountain area highway inhomogeneous deformation
CN106638545A (en) Expansive soil embankment structure improved and reinforced through core cladding method and construction method
CN106758628A (en) Treatment of Expansive Soil Embankment structure and construction method that the improvement of compound core-spun method is reinforced

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination