[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN109811748B - A kind of highway subgrade treatment method in permafrost area - Google Patents

A kind of highway subgrade treatment method in permafrost area Download PDF

Info

Publication number
CN109811748B
CN109811748B CN201910018415.4A CN201910018415A CN109811748B CN 109811748 B CN109811748 B CN 109811748B CN 201910018415 A CN201910018415 A CN 201910018415A CN 109811748 B CN109811748 B CN 109811748B
Authority
CN
China
Prior art keywords
layer
soil
subgrade
permafrost
coarse
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201910018415.4A
Other languages
Chinese (zh)
Other versions
CN109811748A (en
Inventor
赖丰文
刘松玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201910018415.4A priority Critical patent/CN109811748B/en
Publication of CN109811748A publication Critical patent/CN109811748A/en
Application granted granted Critical
Publication of CN109811748B publication Critical patent/CN109811748B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)

Abstract

本发明公开了一种冻土地区高速公路路基处理方法,包括以下步骤:a.预融冻深线内冻土路基;b.挖除所有融土;c.在开挖层底部铺设一层粗粒土与反滤层,同时在两侧铺设灰土隔水层与砾石导胀层;d.逐层填充活性氧化镁碳化固化淤泥土并夯实加固;e.密实填筑路堤填土并在路面结构以下设置一层包含XPS保温板的粗颗粒土层;f.在路堤两侧分别设置隔水护脚。本发明充分结合了冻土地区路基预融、换填处理与软弱土碳化固化技术,有效加固了冻土路基,很好地避免了路基土回冻及冻胀等工程问题,进一步降低了路基不均匀沉降,大量减小了寒区高速公路次生病害问题。该法具有经济环保、安全高效、可控性强、易操作等优势。

Figure 201910018415

The invention discloses a method for treating a highway roadbed in a permafrost area, comprising the following steps: a. pre-thaw frozen soil roadbed within the deep-freezing line; b. excavate all thawed soil; c. lay a thick layer at the bottom of the excavation layer Grain soil and anti-filter layer, and lay lime-soil water-repellent layer and gravel dilatation layer on both sides at the same time; d. Fill layer by layer with activated magnesium oxide carbonized and solidify silt soil and compact it; e. A layer of coarse-grained soil layer containing XPS insulation board is set below; f. Waterproof foot guards are set on both sides of the embankment. The invention fully combines the subgrade pre-thaw, replacement treatment and soft soil carbonization and solidification technology in permafrost areas, effectively strengthens the frozen soil subgrade, well avoids engineering problems such as subgrade soil refreezing and frost heave, and further reduces the risk of subgrade failure. The uniform settlement greatly reduces the secondary disease problem of the expressway in the cold area. The method has the advantages of economy and environmental protection, safety and efficiency, strong controllability and easy operation.

Figure 201910018415

Description

一种冻土地区高速公路路基处理方法A kind of highway subgrade treatment method in permafrost area

技术领域technical field

本发明涉及岩土工程、道路工程领域,具体涉及一种冻土地区高速公路路基处理方法。The invention relates to the fields of geotechnical engineering and road engineering, in particular to a method for treating highway roadbeds in permafrost areas.

背景技术Background technique

中国位居全球第三大冻土国家,其多年冻土面积约占国土面积的22.3%,而季节性冻土面积约占53.5%;寒区冻土可谓占据了我国国土面积的“半壁江山”,对我国交通基础建设造成了显著影响。近年来,随着寒区经济的发展,冻土地区交通与基础设施建设的要求逐渐提高,铁路与普通公路线网已无法承载现有运输量;同时,为保护诸如“青藏高原”等珍贵而脆弱的生态圈,尽可能减少人为破坏,封闭的高速公路是最佳选择。然而,冻土地区高速公路建设属于世界难题,相比普通公路,其路面宽度增加,吸热量大幅上升,热阻效果严重受损,其技术含量成倍增加,高速公路路基稳定性受到了巨大挑战,暴露出严峻的公路运输安全与后期运营问题。China is the third largest permafrost country in the world. Its permafrost area accounts for about 22.3% of the country's land area, while the seasonally frozen soil area accounts for about 53.5%. It has a significant impact on my country's transportation infrastructure. In recent years, with the economic development of cold regions, the requirements for transportation and infrastructure construction in permafrost regions have gradually increased, and the railway and ordinary highway network can no longer carry the existing transportation volume; Fragile ecological circle, minimize human damage, closed highway is the best choice. However, the construction of highways in permafrost areas is a world problem. Compared with ordinary highways, the width of the road surface increases, the heat absorption increases significantly, the thermal resistance effect is seriously damaged, the technical content is doubled, and the stability of highway subgrades is greatly affected. challenges, exposing severe road transportation safety and later operation problems.

高速公路常见路面冻胀隆起、融沉及翻浆等次生病害问题;其根本是受气候变化或人为干扰导致冻土路基温度变化引起冻土上下限波动。现有设计原则主要采用保温措施,利用隔热效应限制或延缓多年冻土上限下移,从而保护冻土。但该技术目前尚不成熟,未能改变路基下覆冻土热收支的发展趋势,无法从根源上消除路基冻害问题。因此,一些特殊路基结构被采用,如热棒、通风管、片块石、隔热层等典型结构。这些处理方法大多针对冻土地区已有二级及以下公路整改与病害治理,主要围绕“公路病害治理”,而非“公路病害预防”。这也忽略了国家公路网内寒区冻土环境的相互作用性能、后期服役性能与运营寿命问题等。因此,能够有效预防“寒区冻土病害问题”,从根源上解决寒区路基冻害问题并能保证冻土地区高速公路路基稳定性能的处理技术有待完善。The secondary diseases such as frost heave, thaw, and pulping are common on highways. The fundamental reason is the fluctuation of the upper and lower limits of the frozen soil caused by the temperature change of the frozen soil subgrade caused by climate change or human interference. The existing design principles mainly adopt thermal insulation measures, and use the thermal insulation effect to limit or delay the downward movement of the upper limit of permafrost, thereby protecting the permafrost. However, this technology is still immature, and it cannot change the development trend of the heat budget of the permafrost under the subgrade, and it cannot eliminate the problem of freezing damage to the subgrade from the root. Therefore, some special subgrade structures are adopted, such as typical structures such as hot rods, ventilation pipes, flakes, and heat insulation layers. Most of these treatment methods are aimed at the rectification and disease control of existing second-level and lower roads in permafrost areas, mainly focusing on "road disease control" rather than "road disease prevention". This also ignores the interaction performance of the permafrost environment in the cold region of the national highway network, the later service performance and operational life issues. Therefore, the treatment technology that can effectively prevent the "permafrost disease problem in cold regions", solve the problem of subgrade freezing damage in cold regions from the root, and ensure the stability of highway subgrade performance in permafrost regions needs to be improved.

换填法施工简便,适用范围广,但难以消除或合理控制路基冻胀变形,且需在全部或部分冻结深度内进行换填,对填料要求较高。粗颗粒常作为冻土路基填料使用,但实际工程表明其仅能减少路基土冻胀,同时可能出现水分迁移;经反复冻融后,粗颗粒填料含水量将升高,从而诱发路基发生冻胀、翻浆、开裂、沉陷等病害,将对公路耐久性及稳定性构成一定的威胁。因此,改良路基填料是必然趋势,即将冻土地区普通路基填料改良为具有低含水率且非冻胀敏感性材料。在我国东北地区分布有大面积的沼泽地,其形成原因是地区气候湿冷、冻土发育、地势低平等。冻土地区沼泽地主要由泥炭土与淤泥土组成,其特点是土质疏松、含水率极高、强度低、硬度低,因此均不能作为路基填料。如何有效利用沼泽地带的泥炭土与淤泥土、充分实现资源化利用与“变废为宝”是目前岩土工程师们亟待解决的工程难题。The replacement filling method is simple in construction and has a wide range of applications, but it is difficult to eliminate or reasonably control the frost heave deformation of the subgrade, and it needs to be replaced in all or part of the freezing depth, which requires higher fillers. Coarse particles are often used as permafrost subgrade fillers, but actual engineering shows that they can only reduce the frost heave of subgrade soil, and at the same time, moisture migration may occur; after repeated freezing and thawing, the water content of coarse particles fillers will increase, which will induce subgrade frost heave , pulping, cracking, subsidence and other diseases will pose a certain threat to the durability and stability of the highway. Therefore, it is an inevitable trend to improve roadbed fillers, that is, to improve common roadbed fillers in permafrost areas into materials with low moisture content and non-frost heave sensitivity. There are large areas of swamps in the northeastern region of my country. The reasons for their formation are the cold and wet climate, the development of permafrost, and the low and equal terrain. The swamps in permafrost areas are mainly composed of peat soil and silt soil, which are characterized by loose soil, extremely high moisture content, low strength and low hardness, so they cannot be used as roadbed fillers. How to effectively utilize peat soil and silt soil in swampy areas, fully realize resource utilization and "turn waste into treasure" is an engineering problem that geotechnical engineers need to solve urgently.

发明内容SUMMARY OF THE INVENTION

技术问题:本发明的目的是提供一种冻土地区高速公路路基处理方法,为克服冻土地区高速公路路基处理方法的不足与缺陷,同时为了有效解决冻土地区沼泽地资源化利用问题,综合提出一种可用于冻土地区高速公路路基处理方法,显著改善路基填料,实现公路病害预防,从根源上限制路基土冻胀问题,提高路基稳定性与耐久性,增强寒区冻土高速公路服役性能。Technical problem: The purpose of the present invention is to provide a method for treating highway subgrades in permafrost areas, in order to overcome the deficiencies and defects of the method for treating highway subgrades in permafrost areas, and at the same time, in order to effectively solve the problem of resource utilization of swampy land in permafrost areas, comprehensive This paper proposes a treatment method for highway subgrade in permafrost areas, which can significantly improve subgrade fillers, achieve road disease prevention, limit subgrade soil frost heave from the root cause, improve subgrade stability and durability, and enhance the service of frozen soil highways in cold regions. performance.

技术方案:本发明的一种冻土地区高速公路路基处理方法,该处理方法包括下列步骤:Technical scheme: a method for treating highway roadbeds in permafrost areas of the present invention, the treatment method comprises the following steps:

a.根据路基勘察报告,确定寒区路基冻深线;根据冻结深度、现场条件选取预融的方法,预融冻深线以上的路基冻土,即粗颗粒层至地表范围的开挖区域内所有冻土;a. According to the subgrade survey report, determine the freezing depth line of the subgrade in cold regions; select the pre-thaw method according to the freezing depth and site conditions, and pre-thaw the subgrade frozen soil above the freezing depth line, that is, within the excavation area from the coarse-grained layer to the surface. all permafrost;

b.将融区内所有冻土挖除,并运输至存放地;b. Excavate all frozen soil in the thawing zone and transport it to the storage place;

c.在开挖层底部铺设一层底部粗颗粒土,随后铺设一层反滤层;同时在开挖区域两侧铺设隔水层与导胀层;c. Lay a layer of bottom coarse-grained soil at the bottom of the excavation layer, and then lay a layer of reverse filter layer; at the same time, lay a water-insulating layer and a dilatation layer on both sides of the excavation area;

d.逐层填充经活性氧化镁碳化固化的淤泥土或泥炭土,并夯实加固;d. Fill layer-by-layer silt soil or peat soil that has been carbonized and solidified by activated magnesium oxide, and tamp it for reinforcement;

e.密实填筑路堤填土并在路面结构以下设置一层包含XPS隔热层的粗颗粒土填筑层;e. Densely fill the embankment and set up a layer of coarse-grained soil filling containing XPS insulation layer below the pavement structure;

f.分别在路堤两侧设置隔水护脚。f. Set up water-proof foot guards on both sides of the embankment.

其中,in,

所述预融冻深线内路基冻土,选择冬季施工。The subgrade frozen soil in the pre-thawed deep line shall be constructed in winter.

所述将融区内所有冻土挖除,是在冻土融化后昼夜连续挖除融土,对应开挖区域坡度比为1:0.5~1。The excavation of all the permafrost in the thawing area is to continuously excavate the thawed soil day and night after the permafrost has thawed, and the slope ratio of the corresponding excavation area is 1:0.5-1.

所述在开挖层底部铺设一层底部粗颗粒土,填筑高度不小于50cm。A layer of bottom coarse-grained soil is laid at the bottom of the excavation layer, and the filling height is not less than 50cm.

所述反滤层,采用卵石、碎石及砂填料,按粒径从大到小的顺序分三层铺设。The anti-filter layer is made of pebbles, crushed stones and sand fillers, and is laid in three layers in descending order of particle size.

所述在开挖区域两侧铺设隔水层、路堤土两侧隔水护脚,采用拌料石灰与黏土,对应体积比控制在3~4:6~7,铺设厚度为30~50cm;路堤土两侧隔水护脚的坡脚比为1:3~5。The water-repellent layer is laid on both sides of the excavation area, and the water-repellent foot protection on both sides of the embankment soil is made of lime and clay, the corresponding volume ratio is controlled at 3-4:6-7, and the laying thickness is 30-50cm; The slope toe ratio of the water-proof foot protection on both sides of the soil is 1:3 to 5.

所述导胀层采用砂砾石填充,铺设厚度为30~50cm。The dilatation layer is filled with sand and gravel, and the laying thickness is 30-50 cm.

所述碳化固化的淤泥土或泥炭土,颗粒粒径控制在1cm~5cm范围内,以粒径小、填充密实度高的颗粒为宜。The particle size of the carbonized and solidified silt soil or peat soil is controlled within the range of 1 cm to 5 cm, and particles with small particle size and high packing density are suitable.

所述逐层填充经活性氧化镁碳化固化的淤泥土或泥炭土,一次填筑高度为50~100cm,保证充分夯实后再进行下一次填筑。The silt soil or peat soil that has been carbonized and solidified by activated magnesium oxide is filled layer by layer, and the height of one filling is 50-100 cm, and the next filling is carried out after ensuring sufficient compaction.

所述XPS隔热层,采用单层隔热板错缝拼接,隔热板尺寸统一采用200cm×100cm×5cm;当路堤土填筑至路面结构设计标高以下80~100cm时,整平路面,填筑粗颗粒土填筑层,填筑高度不小于50cm,在粗颗粒土填筑层中部铺设一层XPS隔热层。The XPS thermal insulation layer is staggered and spliced with a single-layer thermal insulation board, and the size of the thermal insulation board is uniformly 200cm × 100cm × 5cm; A coarse-grained soil filling layer shall be built, and the filling height shall not be less than 50cm, and a layer of XPS insulation layer shall be laid in the middle of the coarse-grained soil filling layer.

有益效果:本发明充分结合了传统、简单、易行的预融方法、换填方法与新型活性氧化镁碳化固化技术,通过改善路基填料,综合解决了冻土地区沼泽地资源化利用与寒区高速公路路基处理困难等问题。因碳化过程不断消耗二氧化碳,因此具有重要的环境保护意义。此外,使用碳化固化的淤泥土或泥炭土填料并辅助设置隔水层、导胀层与保温板,可有效避免路基土冻胀与融沉,实现公路病害预防,从根源上限制路基土冻胀问题,提高路基稳定性与耐久性,直接增强了寒区冻土高速公路服役性能。Beneficial effects: The present invention fully combines the traditional, simple and easy pre-thaw method, replacement method and new activated magnesium oxide carbonization and solidification technology, and comprehensively solves the problem of swampy land resource utilization in permafrost regions and cold regions by improving roadbed fillers. Problems such as difficult to deal with highway subgrade. Because carbon dioxide is continuously consumed in the carbonization process, it has important environmental protection significance. In addition, the use of carbonized and solidified silt soil or peat soil filler and auxiliary setting of water-proof layer, dilatation layer and thermal insulation board can effectively avoid the frost heave and thawing of subgrade soil, realize the prevention of road diseases, and limit the frost heave of subgrade soil from the root cause. problems, improve the stability and durability of the roadbed, and directly enhance the service performance of the permafrost expressway in cold regions.

附图说明Description of drawings

图1为一种冻土地区高速公路路基处理方法示意图;Fig. 1 is a schematic diagram of a method for treating highway subgrades in permafrost areas;

图中,碳化固化的淤泥土或泥炭土1,隔水层2,导胀层3,反滤层4,底部粗颗粒土5,隔水护脚6,粗颗粒土填筑层7,XPS隔热层8,路面结构9,路堤填土10、冻深线11。In the figure, carbonized and solidified silt soil or peat soil 1, water-proof layer 2, dilatation layer 3, reverse filter layer 4, bottom coarse-grained soil 5, water-proof foot protection 6, coarse-grained soil filling layer 7, XPS insulation layer Thermal layer 8, pavement structure 9, embankment fill 10, freezing depth line 11.

具体实施方式Detailed ways

下面对本发明技术方案进行详细说明,但是本发明的保护范围不局限于所述实施例。The technical solutions of the present invention are described in detail below, but the protection scope of the present invention is not limited to the embodiments.

实施例1:Example 1:

一种寒区冻土高速公路路基处理方法,如图1所示。其特征在于,包括下列步骤:A method for treating frozen soil highway subgrade in cold regions is shown in Figure 1. It is characterized in that, comprises the following steps:

a.首先根据路基勘察报告,确定寒区路基冻深线;根据冻结深度、现场条件等选取适宜的方法,选择冬季施工,优先采用电热法或蒸汽法预融冻深线11以上的路基冻土,即粗颗粒土5至地表范围的开挖区域内所有冻土。a. First, according to the subgrade survey report, determine the freezing depth line of the subgrade in cold areas; select the appropriate method according to the freezing depth, site conditions, etc., choose winter construction, and preferentially use the electric heating method or the steam method to pre-thaw the subgrade frozen soil above the freezing depth line 11 , that is, all frozen soils in the excavation area from the coarse-grained soil 5 to the surface.

b.采用挖掘机将融区内所有冻土挖除,并使用运土车将融土运输至存放地,对应开挖坡度为1:0.5;挖土工作应在冻土融化后昼夜连续挖除融土,避免再次结冰。b. Use an excavator to excavate all the frozen soil in the thawing area, and transport the thawed soil to the storage site with a truck, and the corresponding excavation slope is 1:0.5; Melt the soil to avoid freezing again.

c.在开挖层底部铺设底部粗颗粒土5,其填筑高度为50cm,随后采用卵石、碎石及砂填料,按粒径从大到小的顺序分三层铺设反滤层4;同时在开挖区域两侧沿开挖面铺设灰土隔水层2与砾石导胀层3,其中灰土拌料中的石灰与黏土体积比为3:7;隔水层2与导胀层3铺设厚度均为30cm。c. Lay the bottom coarse-grained soil 5 at the bottom of the excavation layer, and its filling height is 50cm, and then use pebble, gravel and sand filler, and lay the anti-filter layer 4 in three layers according to the order of particle size from large to small; On both sides of the excavation area, lay lime-soil water-insulating layer 2 and gravel expansion layer 3 along the excavation surface, wherein the volume ratio of lime and clay in the lime-soil mixture is 3:7; Both are 30cm.

d.逐层填充经碳化固化后的淤泥土或泥炭土1,碳化原料取自冻土地区沼泽地带,碳化固化制造的颗粒粒径控制在1cm-5cm左右,以粒径小、填充密实度高的颗粒为宜;每次填充高度为50cm,待充分夯实后进行下一次填充,循环操作直至路基填筑结束。d. Fill the silt or peat soil 1 after carbonization and solidification layer by layer. The carbonization raw material is taken from the swamp area of the frozen land. The particle size of the carbonized and solidified particles is controlled at about 1cm-5cm. The filling height is 50cm each time, and the next filling will be carried out after sufficient compaction, and the cycle operation will be carried out until the end of the subgrade filling.

e.密实填筑路堤填土10,并在路面结构9以下100cm处开始整平路面并填充粗颗粒土填筑层7,其填筑高度为70cm,并在粗颗粒土填筑层7中间设置一层XPS隔热层8;XPS隔热层8由尺寸为200×100×5cm的保温板错缝拼接而成。e. Densely fill the embankment and fill the soil 10, and start to level the road surface and fill the coarse-grained soil filling layer 7 at 100cm below the road structure 9. The filling height is 70cm, and set in the middle of the coarse-grained soil filling layer 7. A layer of XPS heat insulation layer 8; the XPS heat insulation layer 8 is formed by staggered splicing of insulation boards with a size of 200×100×5cm.

f.分别在路堤两侧设置灰土隔水护脚6,灰土拌料石灰与黏土体积比亦为3.5:6.5;灰土隔水护脚6坡度比为1:3。f. Set up lime-soil water-proofing feet 6 on both sides of the embankment respectively, and the volume ratio of lime-soil mixture lime to clay is also 3.5:6.5; the slope ratio of lime-soil water-proofing feet 6 is 1:3.

实施例2:Example 2:

一种寒区冻土高速公路路基处理方法,如图1所示。其特征在于,包括下列步骤:A method for treating frozen soil highway subgrade in cold regions is shown in Figure 1. It is characterized in that, comprises the following steps:

a.首先根据路基勘察报告,确定寒区路基冻深线;根据冻结深度、现场条件等选取适宜的方法,选择冬季施工,优先采用电热法或蒸汽法预融冻深线11以上的路基冻土,即粗颗粒土5至地表范围的开挖区域内所有冻土。a. First, according to the subgrade survey report, determine the freezing depth line of the subgrade in cold areas; select the appropriate method according to the freezing depth, site conditions, etc., choose winter construction, and preferentially use the electric heating method or the steam method to pre-thaw the subgrade frozen soil above the freezing depth line 11 , that is, all frozen soils in the excavation area from the coarse-grained soil 5 to the surface.

b.采用挖掘机将融区内所有冻土挖除,并使用运土车将融土运输至存放地,对应开挖坡度为1:0.75;挖土工作应在冻土融化后昼夜连续挖除融土,避免再次结冰。b. Use an excavator to excavate all the frozen soil in the thawing area, and transport the thawed soil to the storage site with a truck, and the corresponding excavation slope is 1:0.75; Melt the soil to avoid freezing again.

c.在开挖层底部铺设底部粗颗粒土5,其填筑高度为75cm,随后采用卵石、碎石及砂填料,按粒径从大到小的顺序分三层铺设反滤层4;同时在开挖区域两侧沿开挖面铺设灰土隔水层2与砾石导胀层3,其中灰土拌料中的石灰与黏土体积比为3.5:6.5;隔水层2与导胀层3铺设厚度均为40cm。c. Lay the bottom coarse-grained soil 5 at the bottom of the excavation layer, and its filling height is 75cm, and then use pebble, crushed stone and sand filler, and lay the anti-filter layer 4 in three layers according to the order of particle size from large to small; On both sides of the excavation area, lay lime-soil water-insulating layer 2 and gravel expansion layer 3 along the excavation surface, in which the volume ratio of lime and clay in the lime-soil mixture is 3.5:6.5; Both are 40cm.

d.逐层填充经碳化固化后的淤泥土或泥炭土1,碳化原料取自冻土地区沼泽地带,碳化固化制造的颗粒粒径控制在1cm-5cm左右,以粒径小、填充密实度高的颗粒为宜;每次填充高度为75cm,待充分夯实后进行下一次填充,循环操作直至路基填筑结束。d. Fill the silt or peat soil 1 after carbonization and solidification layer by layer. The carbonization raw material is taken from the swamp area of the frozen land. The particle size of the carbonized and solidified particles is controlled at about 1cm-5cm. The filling height is 75cm each time, and the next filling will be carried out after sufficient compaction, and the cycle operation will be carried out until the end of the subgrade filling.

e.密实填筑路堤填土10,并在路面结构9以下90cm处开始整平路面并填充粗颗粒土填筑层7,其填筑高度为60cm,并在粗颗粒土填筑层7中间设置一层XPS隔热层8;XPS隔热层8由尺寸为200×100×5cm的保温板错缝拼接而成。e. Densely fill the embankment and fill the soil 10, and start to level the road at 90cm below the road structure 9 and fill the coarse-grained soil filling layer 7, the filling height is 60cm, and set in the middle of the coarse-grained soil filling layer 7 A layer of XPS heat insulation layer 8; the XPS heat insulation layer 8 is formed by staggered splicing of insulation boards with a size of 200×100×5cm.

f.分别在路堤两侧设置灰土隔水护脚6,灰土拌料石灰与黏土体积比亦为3:7;灰土隔水护脚6坡度比为1:4。f. Set up lime-soil water-proof feet 6 on both sides of the embankment respectively, and the volume ratio of lime-soil mixed with lime to clay is also 3:7; the slope ratio of lime-soil water-proof feet 6 is 1:4.

实施例3:Example 3:

一种寒区冻土高速公路路基处理方法,如图1所示。其特征在于,包括下列步骤:A method for treating frozen soil highway subgrade in cold regions is shown in Figure 1. It is characterized in that, comprises the following steps:

a.首先根据路基勘察报告,确定寒区路基冻深线;根据冻结深度、现场条件等选取适宜的方法,选择冬季施工,优先采用电热法或蒸汽法预融冻深线11以上的路基冻土,即粗颗粒土5至地表范围的开挖区域内所有冻土。a. First, according to the subgrade survey report, determine the freezing depth line of the subgrade in cold areas; select the appropriate method according to the freezing depth, site conditions, etc., choose winter construction, and preferentially use the electric heating method or the steam method to pre-thaw the subgrade frozen soil above the freezing depth line 11 , that is, all frozen soils in the excavation area from the coarse-grained soil 5 to the surface.

b.采用挖掘机将融区内所有冻土挖除,并使用运土车将融土运输至存放地,对应开挖坡度为1:1;挖土工作应在冻土融化后昼夜连续挖除融土,避免再次结冰。b. Use an excavator to excavate all the frozen soil in the thawing area, and transport the thawed soil to the storage site with a truck, the corresponding excavation slope is 1:1; the excavation work should be continuously excavated day and night after the frozen soil thaws Melt the soil to avoid freezing again.

c.在开挖层底部铺设底部粗颗粒土5,其填筑高度为100cm,随后采用卵石、碎石及砂填料,按粒径从大到小的顺序分三层铺设反滤层4;同时在开挖区域两侧沿开挖面铺设灰土隔水层2与砾石导胀层3,其中灰土拌料中的石灰与黏土体积比为4:6;隔水层2与导胀层3铺设厚度均为50cm。c. Lay the bottom coarse-grained soil 5 at the bottom of the excavation layer, and its filling height is 100cm, and then use pebble, crushed stone and sand filler, and lay the anti-filter layer 4 in three layers according to the order of particle size from large to small; On both sides of the excavation area, lay lime-soil water-insulating layer 2 and gravel expansion layer 3 along the excavation surface, wherein the volume ratio of lime and clay in the lime-soil mixture is 4:6; Both are 50cm.

d.逐层填充经碳化固化后的淤泥土或泥炭土1,碳化原料取自冻土地区沼泽地带,碳化固化制造的颗粒粒径控制在1cm-5cm左右,以粒径小、填充密实度高的颗粒为宜;每次填充高度为100cm,待充分夯实后进行下一次填充,循环操作直至路基填筑结束。d. Fill the silt or peat soil 1 after carbonization and solidification layer by layer. The carbonization raw material is taken from the swamp area of the frozen land. The particle size of the carbonized and solidified particles is controlled at about 1cm-5cm. The filling height is 100cm each time, and the next filling will be carried out after sufficient compaction, and the cycle operation will be carried out until the end of the subgrade filling.

e.密实填筑路堤填土10,并在路面结构9以下80cm处开始整平路面并填充粗颗粒土填筑层7,其填筑高度为50cm,并在粗颗粒土填筑层7中间设置一层XPS隔热层8;XPS隔热层8由尺寸为200×100×5cm的保温板错缝拼接而成。e. Densely fill the embankment and fill the soil 10, and start to level the road at 80cm below the pavement structure 9 and fill the coarse-grained soil filling layer 7 with a filling height of 50cm, and set it in the middle of the coarse-grained soil filling layer 7 A layer of XPS heat insulation layer 8; the XPS heat insulation layer 8 is formed by staggered splicing of insulation boards with a size of 200×100×5cm.

f.分别在路堤两侧设置灰土隔水护脚6,灰土拌料石灰与黏土体积比亦为4:6;灰土隔水护脚6坡度比为1:5。f. Set up lime-soil water-proof feet 6 on both sides of the embankment respectively, and the volume ratio of lime-soil mixed with lime to clay is also 4:6; the slope ratio of lime-soil water-proof feet 6 is 1:5.

应该指出,以上所述仅是本发明的优选实施方式;对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也应视为本发明的保护范围。It should be pointed out that the above are only the preferred embodiments of the present invention; for those skilled in the art, without departing from the principles of the present invention, several improvements and modifications can also be made, and these improvements and modifications can also be It should be regarded as the protection scope of the present invention.

Claims (8)

1.一种冻土地区高速公路路基处理方法,其特征在于,该处理方法包括下列步骤:1. a method for treating highway roadbed in permafrost regions, is characterized in that, this processing method comprises the following steps: a. 根据路基勘察报告,确定寒区路基冻深线;根据冻结深度、现场条件选取预融的方法,预融冻深线(11)以上的路基冻土,即粗颗粒土(5)至地表范围的开挖区域内所有冻土;a. According to the subgrade survey report, determine the freezing depth line of the subgrade in cold regions; select the pre-thaw method according to the freezing depth and site conditions, and pre-thaw the subgrade frozen soil above the freezing depth line (11), that is, the coarse-grained soil (5) to the surface All permafrost within the excavation area of the range; b. 将融区内所有冻土挖除,并运输至存放地;b. Excavate all frozen soil in the thaw zone and transport it to the storage area; c. 在开挖层底部铺设一层底部粗颗粒土(5),随后铺设一层反滤层(4);同时在开挖区域两侧铺设隔水层(2)与导胀层(3);c. Lay a layer of bottom coarse-grained soil (5) at the bottom of the excavation layer, and then lay a layer of reverse filter layer (4); at the same time, lay a water-insulating layer (2) and an expansion layer (3) on both sides of the excavation area ; d. 逐层填充经活性氧化镁碳化固化的淤泥土或泥炭土(1),并夯实加固;d. Fill the silt soil or peat soil (1) which has been carbonized and solidified by activated magnesium oxide layer by layer, and ram it for reinforcement; e. 密实填筑路堤填土(10)并在路面结构(9)以下设置一层包含XPS隔热层(8)的粗颗粒土填筑层(7);e. Dense embankment filling (10) and a coarse-grained soil filling layer (7) containing an XPS thermal insulation layer (8) below the pavement structure (9); f. 分别在路堤两侧设置隔水护脚(6);f. Set water-proof feet (6) on both sides of the embankment; 所述XPS隔热层(8),采用单层隔热板错缝拼接,隔热板尺寸统一采用;当路堤填土(10)填筑至路面结构(9)设计标高以下80~100cm时,整平路面,填筑粗颗粒土填筑层(7),填筑高度不小于50cm,在粗颗粒土填筑层(7)中部铺设一层XPS隔热层(8)。The XPS thermal insulation layer (8) is staggered and spliced with single-layer thermal insulation boards, and the size of the thermal insulation boards is uniform; Level the road surface, fill with a coarse-grained soil filling layer (7), the filling height is not less than 50cm, and lay a layer of XPS insulation layer (8) in the middle of the coarse-grained soil filling layer (7). 2.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述预融冻深线内路基冻土,选择冬季施工。2 . The method for treating highway subgrades in permafrost areas according to claim 1 , wherein the subgrade frozen soil in the pre-thaw deep line is selected for winter construction. 3 . 3.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述将融区内所有冻土挖除,是在冻土融化后昼夜连续挖除融土,对应开挖区域坡度比为1:0.5~1。3. a kind of permafrost area highway subgrade treatment method according to claim 1, is characterized in that, described excavating all frozen soil in the thawing zone, is to continuously excavate the thawing soil day and night after the permafrost thaws, corresponding to thawed soil. The slope ratio of the excavation area is 1:0.5~1. 4.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述在开挖层底部铺设一层底部粗颗粒土(5),填筑高度不小于50cm。4 . The method for treating highway subgrades in permafrost areas according to claim 1 , wherein a layer of bottom coarse-grained soil ( 5 ) is laid at the bottom of the excavation layer, and the filling height is not less than 50 cm. 5 . 5.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述反滤层(4),采用卵石、碎石及砂填料,按粒径从大到小的顺序分三层铺设。5 . The method for treating highway roadbeds in permafrost areas according to claim 1 , wherein the filter layer ( 4 ) is made of pebbles, crushed stones and sand fillers, and the particle size ranges from large to small. 6 . The sequence is laid in three layers. 6.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述在开挖区域两侧铺设隔水层(2)、路堤两侧设置隔水护脚(6),采用拌料石灰与黏土,对应体积比控制在3~4:6~7,隔水层铺设厚度为30~50cm;路堤两侧设置隔水护脚(6)的坡脚比为1:3~5。6. A method for treating highway subgrades in permafrost areas according to claim 1, characterized in that the water barrier (2) is laid on both sides of the excavation area, and the water barrier feet (6) are arranged on both sides of the embankment. ), the mixture of lime and clay is used, the corresponding volume ratio is controlled at 3~4:6~7, the thickness of the water barrier layer is 30~50cm; the water barrier foot protection (6) on both sides of the embankment has a slope toe ratio of 1:1: 3~5. 7.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述导胀层(3)采用砂砾石填充,铺设厚度为30~50cm。7 . The method for treating highway subgrades in permafrost regions according to claim 1 , wherein the dilatation layer ( 3 ) is filled with sand and gravel, and the laying thickness is 30-50 cm. 8 . 8.根据权利要求1所述的一种冻土地区高速公路路基处理方法,其特征在于,所述碳化固化的淤泥土或泥炭土(1),颗粒粒径控制在1cm~5cm范围内,以粒径小、填充密实度高的颗粒为宜。8 . The method for treating highway roadbeds in permafrost regions according to claim 1 , wherein the carbonized and solidified silt soil or peat soil (1) has a particle size controlled within a range of 1 cm to 5 cm, and a Particles with small particle size and high packing density are suitable.
CN201910018415.4A 2019-01-09 2019-01-09 A kind of highway subgrade treatment method in permafrost area Expired - Fee Related CN109811748B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910018415.4A CN109811748B (en) 2019-01-09 2019-01-09 A kind of highway subgrade treatment method in permafrost area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910018415.4A CN109811748B (en) 2019-01-09 2019-01-09 A kind of highway subgrade treatment method in permafrost area

Publications (2)

Publication Number Publication Date
CN109811748A CN109811748A (en) 2019-05-28
CN109811748B true CN109811748B (en) 2020-10-16

Family

ID=66603267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910018415.4A Expired - Fee Related CN109811748B (en) 2019-01-09 2019-01-09 A kind of highway subgrade treatment method in permafrost area

Country Status (1)

Country Link
CN (1) CN109811748B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111304986A (en) * 2020-02-27 2020-06-19 中交二公局第四工程有限公司 Construction method for treating soft foundation settlement in plateau frozen soil area
CN111396678A (en) * 2020-03-05 2020-07-10 中国科学院寒区旱区环境与工程研究所 Through-laying type rubble tube dike cooling structure
CN112921726B (en) * 2021-01-28 2022-04-19 长安大学 Roadbed structure capable of preventing roadbed soil from being dry cracked or wet sunk and construction method thereof
CN115029976A (en) * 2022-06-15 2022-09-09 江苏交水建智能装备研究院有限公司 Roadbed coverage effect combined prevention and control method based on soil body solidification and partition technology

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892620A (en) * 2010-06-25 2010-11-24 中铁九局集团有限公司 High-strength antifreeze damage waterproof cushion
CA2738146A1 (en) * 2011-04-21 2012-10-21 John Bandura Subsurface insulation product and method for installing same
CN102493306B (en) * 2011-12-29 2013-12-04 中交第一公路勘察设计研究院有限公司 Construction method of expressway insulating regulation subgrade in permafrost areas
CN108128991B (en) * 2017-11-24 2018-11-09 东南大学 A kind of ectopic activities magnesia carbonization curing sludge soil processing system

Also Published As

Publication number Publication date
CN109811748A (en) 2019-05-28

Similar Documents

Publication Publication Date Title
CN109811748B (en) A kind of highway subgrade treatment method in permafrost area
CN110485228B (en) Hydrothermal closed type anti-frost-heaving slurry-turning high-strength highway subgrade structure and construction method
CN204401387U (en) A kind of seasonal frost region anti-freeze expansion road structure based on XPS warming plate and banket
CN105297570B (en) Special soil subgrade structure and construction method thereof
CN111979866B (en) A kind of antifreeze structure of subgrade in seasonally frozen soil area and its construction method
CN109736141A (en) The anti-freeze expansion structural body and paving method of Railway Roadbed in Permafrost Regions
CN204212018U (en) A kind of road structure preventing and treating the soft soil roadbed freeze thawing disease of high and cold mountain area cheuch section
Wu et al. Freeze-thaw erosion mechanism and preventive actions of highway subgrade soil in an alpine meadow on the Qinghai-Tibet Plateau
CN107938480A (en) A kind of microorganism cures the desert highway embankment and its construction method of joint TGXG
CN105421469B (en) A kind of Fill Reinforced With Geogrids covering wall construction and construction method
CN107288120A (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN211848680U (en) A steel plate structure and a steel plate pavement structure
CN207749375U (en) A kind of seasonal frost region anti-freeze expansion road structure
CN101418565A (en) Qinghai-tibet railway permafrost wetland ground treatment technique
CN103243624B (en) Construction method for salty soil district railway roadbed with water content lower than liquid limit
CN204825539U (en) Control difference in temperature prevents roadbed structure of cold mountain area highway inhomogeneous deformation
CN113265924B (en) Construction method for using red bed mudstone blocks as high-fill dynamic compaction roadbed filling
CN207032212U (en) A kind of stabilization by drainage structure of new and old roadbed in the firm splicing of watersplash
CN105256683A (en) Permafrost region roadbed thermal insulation construction method
CN204385575U (en) Fill Reinforced With Geogrids clay bound edge CHARACTERISTICS OF TAILINGS SAND roadbed
CN116556235A (en) Gear system for preventing and controlling hot-melt landslide in plateau frozen soil area
CN213804677U (en) Soft soil foundation structure
CN103449784B (en) Be applicable to the cement-based waterproof anticracking material of swelled ground area railway cutting bedding
CN103556558B (en) Pavement construction with hierarchically completely encapsulated roadbed and construction method thereof
CN112195701A (en) Soft soil foundation structure and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20201016