CN103530826A - BIM (Building Information Modeling)-based shield method tunnel construction management method - Google Patents

BIM (Building Information Modeling)-based shield method tunnel construction management method Download PDF

Info

Publication number
CN103530826A
CN103530826A CN201310403893.XA CN201310403893A CN103530826A CN 103530826 A CN103530826 A CN 103530826A CN 201310403893 A CN201310403893 A CN 201310403893A CN 103530826 A CN103530826 A CN 103530826A
Authority
CN
China
Prior art keywords
jurisdiction
bim
bim model
section
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310403893.XA
Other languages
Chinese (zh)
Other versions
CN103530826B (en
Inventor
胡珉
周胜臣
周文波
陆俊宇
杜娟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Tunnel Engineering Co Ltd
University of Shanghai for Science and Technology
Original Assignee
University of Shanghai for Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of Shanghai for Science and Technology filed Critical University of Shanghai for Science and Technology
Priority to CN201310403893.XA priority Critical patent/CN103530826B/en
Publication of CN103530826A publication Critical patent/CN103530826A/en
Application granted granted Critical
Publication of CN103530826B publication Critical patent/CN103530826B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a BIM (Building Information Modeling)-based shield method tunnel construction management method. The method comprises the following steps: arranging an RFID (Radio Frequency Identification Devices) tag on a tunnel segment, wherein corresponding segment coded information is stored in the RFID tag; writing the segment coded information into the RFID tag with an RFID reader-writer; reading the segment coded information from the RFID tag with the RFID reader-writer; acquiring the segment coded information read by the RFID reader-writer by using a BIM system, calling a BIM model which corresponds to the tunnel segment, binding basic information of the corresponding segment, correlating each data source recorded in a segment construction process with the BIM model, and performing real-time data synchronizing operation to realize analogue simulation of a shield method tunnel construction process through the BIM system. According to the tunnel construction management method, the shield method tunnel construction process is subjected to analogue simulation, monitoring and analyzing by means of a BIM-based analogue simulation measure, so that the construction process and quality can be known intuitively and vividly, and scientific and effective construction management is facilitated.

Description

Shield method tunnel construction management method based on BIM
Technical field
The invention belongs to electronic information technical field, relate to a kind of constructing tunnel management system, relate in particular to a kind of shield method tunnel construction management method based on BIM.
Background technology
Constructing tunnel field now, in order to ensure construction speed and quality, existing way major part is all by professional, to be undertaken that a series of paper list is filled in and later stage computer data inputting is monitored work progress, but because form is numerous, the factors such as form presentation mode is directly perceived not so that later stage be loaded down with trivial details and inefficiency to reviewing of construction problem, and this has greatly weakened the control and monitoring of people for constructing tunnel.Therefore developing this type of constructing tunnel management system has very important engineering significance.
BIM(BIM) as a kind of novel vital computer application technology that is mainly used in engineering construction field, use digital modeling software, can carry out visual Simulation to work progress, lifting construction efficiency and science Ba Kong,Gei construction enterprises bring great value.According to literature survey, even BIM technology is not introduced in shield method tunnel construction process.
In view of this, nowadays in the urgent need to designing a kind of new constructing tunnel management system, to overcome the above-mentioned defect of existing construction management mode.
Summary of the invention
Technical matters to be solved by this invention is: a kind of shield method tunnel construction management method based on BIM is provided, can effective monitoring and review the work progress of section of jurisdiction, and improve monitoring efficiency, realize the life cycle management to constructing tunnel.
For solving the problems of the technologies described above, the present invention adopts following technical scheme:
A shield method tunnel construction management method of BIM, described execution management method therefor comprises:
RFID label is set on tunnel duct piece, in RFID label, stores respective tube slice encode information;
By rfid interrogator, to described RFID label, write section of jurisdiction coded message;
By rfid interrogator, from described RFID label, read section of jurisdiction coded message;
BIM model system is obtained the section of jurisdiction coded message that rfid interrogator reads, call the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to parameterized analogue simulation by BIM model system.
As a preferred embodiment of the present invention, described method specifically also comprises:
By front-end operations terminal control rfid interrogator, to described RFID label, write section of jurisdiction coded message, and control described rfid interrogator and call section of jurisdiction related data, by BIM model system, realize three-dimensional artificial, visual Data Integration analysis, management;
Background server receives from front end operating terminal the multidimensional the work progress of section of jurisdiction is checked to data, and is stored in described central database; Background server arrives front-end operations terminal by setting data by Internet Transmission, carries out monitoring and analysis based on BIM model system.
As a preferred embodiment of the present invention, described method specifically comprises the steps:
Step S0, RFID label is set on tunnel duct piece, in RFID label, stores respective tube slice encode information; By rfid interrogator, to described RFID label, write section of jurisdiction coded message;
Step S1, in front-end operations terminal, open software system interface, produce operational sequence and flow process;
Step S2, rfid interrogator scanning RFID label, identify the section of jurisdiction information of marching into the arena, and the inspection of marching into the arena, checks whether section of jurisdiction outward appearance, size etc. meet design objective and drawing;
Step S3, shield driving and pipe sheet assembling quality check, generate synchronous grouting record, shield driving process record and shield driving attitude form;
Step S4, judge whether qualifiedly, if qualified, turn to step S6, otherwise transfer the possession of step S5;
Step S5, utilize front-end operations terminal or and background server grouting parameter, propulsive parameter, shield attitude and axis parameter in constructing tunnel are combined with BIM model system, then rfid interrogator scans section of jurisdiction RFID label, in BIM model, in search acquisition practice of construction, grouting parameter, propulsive parameter, shield attitude and axis parameter are carried out simulation analysis in model, further verify the rationality of construction parameter;
Step S6, check result is uploaded to described central database;
Step S7, utilize front-end operations terminal or and background server call BIM model system grouting parameter, propulsive parameter, shield attitude and axis parameter in tunnel segment construction instructed, by rfid interrogator, scan section of jurisdiction RFID label, in BIM model, search for, deposit related data in model emulation;
Step S8, analysis result is uploaded to central server.
As a preferred embodiment of the present invention, described BIM model system is supported the visual progress of shield method tunnel construction, quality monitoring;
Described front-end operations terminal and background server support generate shield method tunnel construction progress and quality detection project, manage corresponding information data,, visual control and analysis construction progress integrated by BIM model system and detect data.
As a preferred embodiment of the present invention, described management method also comprises inspection of construction step, comprising the inspection step of marching into the arena, advancing assembled step, section of jurisdiction to repair step, quality management step and safety patrol inspection step;
Quality control personnel, by the logging data of front-end operations terminal filed, are sent to central database with network mode and analyze for BIM model system, and can generate respective electronic form; Inspection of construction system on background server can also be unified to browse and manage to the electronic report forms of uploading.
As a preferred embodiment of the present invention, described BIM model system is supported shield method tunnel construction, obtains pipe sheet assembling position and the construction parameter in footpath anyhow, and carry out visual progress, Analysis of Quality Control by BIM model;
In scanning, be arranged on after the RFID information on tunnel duct piece, described BIM model system is called the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to analogue simulation by BIM model system.
As a preferred embodiment of the present invention, described management method also comprises:
Described BIM model system, by rfid interrogator and front-end operations terminal compounding practice, is carried out quality testing to the section of jurisdiction of having constructed;
Front-end operations terminal is transferred to background server by information with network mode, and BIM model system is carried out visual description to situations such as tunnel duct piece repairing, percolating waters, and coordinates the scene photograph of taking as auxiliary.
The shield method tunnel construction management method based on BIM that the present invention proposes, beneficial effect is:
(1) the present invention carries out analogue simulation, monitoring, analysis with a kind of means of the analogue simulation based on BIM to shield method tunnel construction process, can be intuitively, image understands construction progress and quality, auxiliaryly carry out science, effectively construction management;
(2) by system of the present invention, realize with no paper, networking, the visualized operation of inspection of construction, greatly increased the work efficiency of construction quality inspection personnel;
(3) system of the present invention is as long as upgrade inspection item, and the O&M after also can be used for constructing tunnel and completing has increased the portability and reusability of system.
Accompanying drawing explanation
Fig. 1 is the composition schematic diagram of shield method tunnel construction management system of the present invention.
Fig. 2 is the process flow diagram of shield method tunnel construction management method of the present invention.
Embodiment
Below in conjunction with accompanying drawing, describe the preferred embodiments of the present invention in detail.
Embodiment mono-
Refer to Fig. 1, the present invention has disclosed a kind of shield method tunnel construction management system based on BIM, and described construction management system comprises: some RFID labels 1, one or more rfid interrogator 2, one or more front-end operations terminal 3, background server 4.
RFID label 1 is arranged on tunnel duct piece, in order to store respective tube slice encode information.Rfid interrogator 2, in order to write section of jurisdiction coded message to described RFID label 1, can also read section of jurisdiction coded message from described RFID label 1.
Front-end operations terminal 3, background server 4 are all mounted with BIM model system 5 and inspection of construction system 6.Described front-end operations terminal 3 connects rfid interrogator 2 and to described RFID label, writes section of jurisdiction coded message in order to control rfid interrogator, and control described rfid interrogator 2 and call section of jurisdiction related data, by BIM model system 5, realize three-dimensional artificial, visual Data Integration analysis, management.
Background server 4 comprises central database 7, and is mounted with BIM model system 5 and inspection of construction system 6; Described background server 4 connects described front-end operations terminal 3, in order to receive from front end operating terminal 3, the multidimensional the work progress of section of jurisdiction is checked to data, and is stored in described central database 7; Background server 4 also arrives front-end operations terminal by setting data by Internet Transmission, carries out monitoring and analysis based on BIM model system 5.
Described BIM model system 5 is supported shield method tunnel constructions, obtains pipe sheet assembling position and the construction parameter in footpath anyhow, and carry out visual progress, Analysis of Quality Control by BIM model; In scanning, be arranged on after the RFID information on tunnel duct piece, described BIM model system is called the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to parameterized analogue simulation by BIM model system; Described BIM model system, by rfid interrogator and front-end operations terminal compounding practice, is carried out quality testing to the section of jurisdiction of having constructed; Front-end operations terminal is transferred to background server by information with network mode, and BIM model system is carried out visual description to tunnel duct piece repairing, percolating water situation, and coordinates the scene photograph of taking as auxiliary.
Inspection of construction system 6 comprises with lower module: module, quality management module and safety patrol inspection module are repaired in the checking module of marching into the arena, propelling assembling module, section of jurisdiction.Quality control personnel, by the logging data of front-end operations terminal filed, are sent to central database with network mode and analyze for BIM model system, and can generate respective electronic form; Inspection of construction system on background server can also be unified to browse and manage to the electronic report forms of uploading.
In this example, front-end operations terminal 3 is by adopting Windows operating system, and the panel computer of subsidiary camera function is realized; Rfid interrogator 2 can adopt CSL ultrahigh frequency handheld terminal by ISO/IEC18000 agreement, come and the RFID label being arranged on tunnel duct piece is carried out to read-write operation; Between background server 4, front-end operations terminal 3, by WLAN (wireless local area network) ISO/IEC8802.11 agreement, realize the transmission of data.
More than introduced the shield method tunnel construction management system that the present invention is based on BIM, the present invention, when disclosing above-mentioned management system, also discloses a kind of shield method tunnel construction management method based on BIM, and described execution management method therefor comprises:
Step 1, RFID label is set on tunnel duct piece, in RFID label, stores respective tube slice encode information;
Step 2, by rfid interrogator, to described RFID label, write section of jurisdiction coded message;
Step 3, by rfid interrogator, from described RFID label, read section of jurisdiction coded message;
Step 4, by front-end operations terminal control rfid interrogator, to described RFID label, write section of jurisdiction coded message, and control described rfid interrogator and call section of jurisdiction related data;
Step 5, background server receive from front end operating terminal the multidimensional the work progress of section of jurisdiction are checked to data, and are stored in described central database; Background server arrives front-end operations terminal by setting data by Internet Transmission, carries out monitoring and analysis based on BIM model system.BIM model system is obtained the section of jurisdiction coded message that rfid interrogator reads, call the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to parameterized analogue simulation by BIM model system.
Particularly, refer to Fig. 2, described execution management method therefor specifically comprises the steps:
[step S0] arranges RFID label on tunnel duct piece, stores respective tube slice encode information in RFID label; By rfid interrogator, to described RFID label, write section of jurisdiction coded message;
[step S1] opens software system interface in front-end operations terminal, produces operational sequence and flow process;
[step S2] rfid interrogator scanning RFID label, identifies the section of jurisdiction information of marching into the arena, and the inspection of marching into the arena, checks whether section of jurisdiction outward appearance, size etc. meet design objective and drawing;
[step S3] shield driving and pipe sheet assembling quality check, generate synchronous grouting record, shield driving process record and shield driving attitude form;
It is qualified that [step S4] judges whether, if qualified, turns to step S6, otherwise transfer the possession of step S5;
[step S5] utilizes front-end operations terminal or with background server, grouting parameter, propulsive parameter, shield attitude and axis parameter in constructing tunnel combined with BIM model system, then rfid interrogator scans section of jurisdiction RFID label, in BIM model, in search acquisition practice of construction, grouting parameter, propulsive parameter, shield attitude and axis parameter are carried out parameterized simulation analysis in model, further verify the rationality of construction parameter;
[step S6] is uploaded to described central database by check result;
[step S7] utilizes front-end operations terminal or calls BIM model system with background server grouting parameter, propulsive parameter, shield attitude and axis parameter in tunnel segment construction are instructed, by rfid interrogator, scan section of jurisdiction RFID label, in BIM model, search for, related data is deposited in and in model, carries out parametric simulation;
[step S8] is uploaded to central server by analysis result.
In sum, shield method tunnel construction management system and method based on BIM that the present invention proposes, means with a kind of analogue simulation based on BIM are carried out analogue simulation, monitoring, analysis to shield method tunnel construction process, can be intuitively, image understands construction progress and quality, auxiliaryly carries out science, effectively construction management.By system of the present invention, realize with no paper, networking, the visualized operation of inspection of construction, greatly increased the work efficiency of construction quality inspection personnel; System of the present invention is as long as upgrades inspection item, and the O&M after also can be used for constructing tunnel and completing has increased the portability and reusability of system.
Here description of the invention and application is illustrative, not wants by scope restriction of the present invention in the above-described embodiments.Here the distortion of disclosed embodiment and change is possible, and for those those of ordinary skill in the art, the various parts of the replacement of embodiment and equivalence are known.Those skilled in the art are noted that in the situation that not departing from spirit of the present invention or essential characteristic, and the present invention can be with other form, structure, layout, ratio, and realizes with other assembly, material and parts.In the situation that not departing from the scope of the invention and spirit, can carry out other distortion and change to disclosed embodiment here.

Claims (7)

1. the shield method tunnel construction management method based on BIM, is characterized in that, described execution management method therefor comprises:
RFID label is set on tunnel duct piece, in RFID label, stores respective tube slice encode information;
By rfid interrogator, to described RFID label, write section of jurisdiction coded message;
By rfid interrogator, from described RFID label, read section of jurisdiction coded message;
BIM model system is obtained the section of jurisdiction coded message that rfid interrogator reads, call the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to parameterized analogue simulation by BIM model system.
2. the shield method tunnel construction management method based on BIM according to claim 1, is characterized in that:
Described method specifically also comprises:
By front-end operations terminal control rfid interrogator, to described RFID label, write section of jurisdiction coded message, and control described rfid interrogator and call section of jurisdiction related data, by BIM model system, realize three-dimensional artificial, visual Data Integration analysis, management;
Background server receives from front end operating terminal the multidimensional the work progress of section of jurisdiction is checked to data, and is stored in described central database; Background server arrives front-end operations terminal by setting data by Internet Transmission, carries out monitoring and analysis based on BIM model system.
3. the shield method tunnel construction management method based on BIM according to claim 2, is characterized in that:
Described method specifically comprises the steps:
Step S0, RFID label is set on tunnel duct piece, in RFID label, stores respective tube slice encode information; By rfid interrogator, to described RFID label, write section of jurisdiction coded message;
Step S1, in front-end operations terminal, open software system interface, produce operational sequence and flow process;
Step S2, rfid interrogator scanning RFID label, identify the section of jurisdiction information of marching into the arena, and the inspection of marching into the arena, checks whether section of jurisdiction outward appearance, size etc. meet design objective and drawing;
Step S3, shield driving and pipe sheet assembling quality check, generate synchronous grouting record, shield driving process record and shield driving attitude form;
Step S4, judge whether qualifiedly, if qualified, turn to step S6, otherwise transfer the possession of step S5;
Step S5, utilize front-end operations terminal or and background server grouting parameter, propulsive parameter, shield attitude and axis parameter in constructing tunnel are combined with BIM model system, then rfid interrogator scans section of jurisdiction RFID label, in BIM model, in search acquisition practice of construction, grouting parameter, propulsive parameter, shield attitude and axis parameter are carried out simulation analysis in model, further verify the rationality of construction parameter;
Step S6, check result is uploaded to described central database;
Step S7, utilize front-end operations terminal or and background server call BIM model system grouting parameter, propulsive parameter, shield attitude and axis parameter in tunnel segment construction instructed, by rfid interrogator, scan section of jurisdiction RFID label, in BIM model, search for, deposit related data in model emulation;
Step S8, analysis result is uploaded to central server.
4. the shield method tunnel construction management method based on BIM according to claim 1, is characterized in that:
Described BIM model system is supported the visual progress of shield method tunnel construction, quality monitoring;
Described front-end operations terminal and background server support generate shield method tunnel construction progress and quality detection project, manage corresponding information data,, visual control and analysis construction progress integrated by BIM model system and detect data.
5. the shield method tunnel construction management method based on BIM according to claim 1, is characterized in that:
Described management method also comprises inspection of construction step, comprising the inspection step of marching into the arena, advancing assembled step, section of jurisdiction to repair step, quality management step and safety patrol inspection step;
Quality control personnel, by the logging data of front-end operations terminal filed, are sent to central database with network mode and analyze for BIM model system, and can generate respective electronic form; Inspection of construction system on background server can also be unified to browse and manage to the electronic report forms of uploading.
6. the shield method tunnel construction management method based on BIM according to claim 1, is characterized in that:
Described BIM model system is supported shield method tunnel construction, obtains pipe sheet assembling position and the construction parameter in footpath anyhow, and carry out visual progress, Analysis of Quality Control by BIM model;
In scanning, be arranged on after the RFID information on tunnel duct piece, described BIM model system is called the corresponding BIM model of this tunnel duct piece, and bind corresponding section of jurisdiction essential information, the every data source recording in the work progress of section of jurisdiction is associated with BIM model, by real-time data synchronous operation, can realize shield method tunnel construction process is carried out to analogue simulation by BIM model system.
7. the shield method tunnel construction management method based on BIM according to claim 2, is characterized in that:
Described management method also comprises:
Described BIM model system, by rfid interrogator and front-end operations terminal compounding practice, is carried out quality testing to the section of jurisdiction of having constructed;
Front-end operations terminal is transferred to background server by information with network mode, and BIM model system is carried out visual description to situations such as tunnel duct piece repairing, percolating waters, and coordinates the scene photograph of taking as auxiliary.
CN201310403893.XA 2013-09-06 2013-09-06 BIM (Building Information Modeling)-based shield method tunnel construction management method Active CN103530826B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310403893.XA CN103530826B (en) 2013-09-06 2013-09-06 BIM (Building Information Modeling)-based shield method tunnel construction management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310403893.XA CN103530826B (en) 2013-09-06 2013-09-06 BIM (Building Information Modeling)-based shield method tunnel construction management method

Publications (2)

Publication Number Publication Date
CN103530826A true CN103530826A (en) 2014-01-22
CN103530826B CN103530826B (en) 2017-02-15

Family

ID=49932810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310403893.XA Active CN103530826B (en) 2013-09-06 2013-09-06 BIM (Building Information Modeling)-based shield method tunnel construction management method

Country Status (1)

Country Link
CN (1) CN103530826B (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104077653A (en) * 2014-06-25 2014-10-01 上海市建筑科学研究院(集团)有限公司 Building construction supervision method based on BIM
CN104499714A (en) * 2014-11-13 2015-04-08 中建三局第二建设工程有限责任公司 Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN106022560A (en) * 2016-05-05 2016-10-12 四川铁安达科技有限公司 Subway shield segment attitude monitoring and management system based on Internet of Things and cloud computing
CN106354943A (en) * 2016-08-31 2017-01-25 赖正伦 Engineering modularized manufacturing system and engineering modularized manufacturing method
CN106442576A (en) * 2016-11-30 2017-02-22 华中科技大学 Hidden quality nondestructive detection method and system of shield tunnel structure
CN106779447A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Builder's intelligent management system and method for a kind of RFID of fusion BIM
CN106761798A (en) * 2017-01-13 2017-05-31 同济大学 A kind of large diameter shield tunnel face management system based on BIM
CN106909749A (en) * 2017-03-08 2017-06-30 朱海涛 Mobile terminal is based on the Intelligent Recognition localization method of BIM
CN106919765A (en) * 2017-03-08 2017-07-04 朱海涛 Component processing method based on BIM and mobile terminal
CN108005725A (en) * 2017-12-31 2018-05-08 上海纽建信息科技有限公司 A kind of structural healthy monitoring system for Shield Tunnel in Soft Soil
CN108550086A (en) * 2018-04-13 2018-09-18 北京市轨道交通设计研究院有限公司 A kind of recognition methods of Station construction speed and system
CN108952734A (en) * 2018-05-15 2018-12-07 同济大学 A kind of shield-tunneling construction plane vertical section information mobile phone end real-time exhibition method
CN109145380A (en) * 2018-07-21 2019-01-04 中铁十八局集团有限公司 A kind of New Austrian Tunneling Method constructing tunnel management system based on BIM
CN109162730A (en) * 2018-07-21 2019-01-08 中铁十八局集团有限公司 A kind of slurry balance shield slurries parameter management system based on BIM
CN109242724A (en) * 2018-07-21 2019-01-18 中铁十八局集团有限公司 A kind of New Austrian Tunneling Method constructing tunnel management method based on BIM
CN109446716A (en) * 2018-11-15 2019-03-08 中铁第六勘察设计院集团有限公司 Based on BIM platform shield machine VMT and correction scheme three-dimensional display method
CN109882196A (en) * 2019-04-22 2019-06-14 中铁上海工程局集团有限公司 A kind of shield tunnel construction monitoring method based on BIM technology
CN110287566A (en) * 2019-06-18 2019-09-27 西安新视窗科技有限公司 A kind of system that tunnel piercing progress and process are controlled based on BIM
CN110990933A (en) * 2019-12-23 2020-04-10 中建八局轨道交通建设有限公司 Modeling method for shield tunnel
CN111709656A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Shield tunnel construction management system based on BIM
CN111832106A (en) * 2020-06-30 2020-10-27 中建八局轨道交通建设有限公司 Method for positioning shield well starting position by using unmanned aerial vehicle oblique photography technology
CN113486435A (en) * 2021-07-22 2021-10-08 华侨大学 Shield underground butt joint and abandoned shell disassembly construction method based on BIM and numerical simulation
CN113807685A (en) * 2021-09-06 2021-12-17 中国电建集团华东勘测设计研究院有限公司 BIM-based hydraulic tunnel construction progress informatization management method
CN117709884A (en) * 2023-12-18 2024-03-15 承德市工程建设造价管理站 Engineering construction progress management system based on BIM and RFID technology

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011022849A (en) * 2009-07-16 2011-02-03 Hitachi Plant Technologies Ltd Management system for material, equipment and construction in construction site, and management method
US20110063328A1 (en) * 2009-09-15 2011-03-17 HNTB Holdings, Ltd. Positioning labels in an engineering drawing
JP2012079085A (en) * 2010-10-01 2012-04-19 Seiko Epson Corp Printer with rfid writer, and rfid-attached printing medium issuing system
CN202512611U (en) * 2011-12-23 2012-10-31 上海大学 RFID electronic tag capable of tracing and monitoring PC component
CN103247004A (en) * 2013-04-28 2013-08-14 中建安装工程有限公司 Information management method and system based on electromechanical integrated BIM (building information model)
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2011022849A (en) * 2009-07-16 2011-02-03 Hitachi Plant Technologies Ltd Management system for material, equipment and construction in construction site, and management method
US20110063328A1 (en) * 2009-09-15 2011-03-17 HNTB Holdings, Ltd. Positioning labels in an engineering drawing
JP2012079085A (en) * 2010-10-01 2012-04-19 Seiko Epson Corp Printer with rfid writer, and rfid-attached printing medium issuing system
CN202512611U (en) * 2011-12-23 2012-10-31 上海大学 RFID electronic tag capable of tracing and monitoring PC component
CN103246951A (en) * 2012-12-11 2013-08-14 中建三局第一建设工程有限责任公司 Intelligent electromechanical equipment management system and method based on BIM (building information modeling)
CN103247004A (en) * 2013-04-28 2013-08-14 中建安装工程有限公司 Information management method and system based on electromechanical integrated BIM (building information model)

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李天华等: "装配式建筑全寿命周期管理中BIM与RFID的应用", 《工程管理学报》, vol. 26, no. 3, 30 June 2012 (2012-06-30) *
赵金汉: "盾构法隧道施工中的线形管理", 《安徽建筑》, no. 1, 28 February 2005 (2005-02-28) *

Cited By (32)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104077653A (en) * 2014-06-25 2014-10-01 上海市建筑科学研究院(集团)有限公司 Building construction supervision method based on BIM
CN104499714A (en) * 2014-11-13 2015-04-08 中建三局第二建设工程有限责任公司 Mechanical and electrical installation engineering construction method based on BIM platform and measuring robot
CN106022560A (en) * 2016-05-05 2016-10-12 四川铁安达科技有限公司 Subway shield segment attitude monitoring and management system based on Internet of Things and cloud computing
CN106354943A (en) * 2016-08-31 2017-01-25 赖正伦 Engineering modularized manufacturing system and engineering modularized manufacturing method
CN106442576A (en) * 2016-11-30 2017-02-22 华中科技大学 Hidden quality nondestructive detection method and system of shield tunnel structure
CN106442576B (en) * 2016-11-30 2023-03-31 华中科技大学 Shield method tunnel structure concealment quality nondestructive testing method and system
CN106779447A (en) * 2016-12-28 2017-05-31 南京建工集团有限公司 Builder's intelligent management system and method for a kind of RFID of fusion BIM
CN106761798B (en) * 2017-01-13 2019-05-14 同济大学 A kind of large diameter shield tunnel face management system based on BIM
CN106761798A (en) * 2017-01-13 2017-05-31 同济大学 A kind of large diameter shield tunnel face management system based on BIM
CN106919765A (en) * 2017-03-08 2017-07-04 朱海涛 Component processing method based on BIM and mobile terminal
CN106909749A (en) * 2017-03-08 2017-06-30 朱海涛 Mobile terminal is based on the Intelligent Recognition localization method of BIM
CN108005725A (en) * 2017-12-31 2018-05-08 上海纽建信息科技有限公司 A kind of structural healthy monitoring system for Shield Tunnel in Soft Soil
CN108550086A (en) * 2018-04-13 2018-09-18 北京市轨道交通设计研究院有限公司 A kind of recognition methods of Station construction speed and system
CN108952734B (en) * 2018-05-15 2020-02-14 同济大学 Shield construction flat longitudinal section information mobile phone end real-time display method
CN108952734A (en) * 2018-05-15 2018-12-07 同济大学 A kind of shield-tunneling construction plane vertical section information mobile phone end real-time exhibition method
CN109242724A (en) * 2018-07-21 2019-01-18 中铁十八局集团有限公司 A kind of New Austrian Tunneling Method constructing tunnel management method based on BIM
CN109162730A (en) * 2018-07-21 2019-01-08 中铁十八局集团有限公司 A kind of slurry balance shield slurries parameter management system based on BIM
CN109145380A (en) * 2018-07-21 2019-01-04 中铁十八局集团有限公司 A kind of New Austrian Tunneling Method constructing tunnel management system based on BIM
CN109162730B (en) * 2018-07-21 2020-08-11 中铁十八局集团有限公司 Slurry parameter management system of slurry balance shield based on BIM
CN109446716A (en) * 2018-11-15 2019-03-08 中铁第六勘察设计院集团有限公司 Based on BIM platform shield machine VMT and correction scheme three-dimensional display method
CN109882196A (en) * 2019-04-22 2019-06-14 中铁上海工程局集团有限公司 A kind of shield tunnel construction monitoring method based on BIM technology
CN109882196B (en) * 2019-04-22 2021-09-21 中铁上海工程局集团有限公司 Shield tunnel construction monitoring method based on BIM technology
CN110287566A (en) * 2019-06-18 2019-09-27 西安新视窗科技有限公司 A kind of system that tunnel piercing progress and process are controlled based on BIM
CN110990933A (en) * 2019-12-23 2020-04-10 中建八局轨道交通建设有限公司 Modeling method for shield tunnel
CN111709656A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Shield tunnel construction management system based on BIM
CN111832106A (en) * 2020-06-30 2020-10-27 中建八局轨道交通建设有限公司 Method for positioning shield well starting position by using unmanned aerial vehicle oblique photography technology
CN111832106B (en) * 2020-06-30 2023-11-14 中建八局轨道交通建设有限公司 Method for positioning shield well starting position by unmanned aerial vehicle oblique photography technology
CN113486435A (en) * 2021-07-22 2021-10-08 华侨大学 Shield underground butt joint and abandoned shell disassembly construction method based on BIM and numerical simulation
CN113486435B (en) * 2021-07-22 2023-07-28 华侨大学 Shield underground butt joint and shell discarding disassembly construction method based on BIM and numerical simulation
CN113807685A (en) * 2021-09-06 2021-12-17 中国电建集团华东勘测设计研究院有限公司 BIM-based hydraulic tunnel construction progress informatization management method
CN113807685B (en) * 2021-09-06 2023-12-12 中国电建集团华东勘测设计研究院有限公司 BIM-based hydraulic tunnel construction progress informatization management method
CN117709884A (en) * 2023-12-18 2024-03-15 承德市工程建设造价管理站 Engineering construction progress management system based on BIM and RFID technology

Also Published As

Publication number Publication date
CN103530826B (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN103530826A (en) BIM (Building Information Modeling)-based shield method tunnel construction management method
CN103473720A (en) Shield tunnel construction management system based on BIM
Ma et al. Construction quality management based on a collaborative system using BIM and indoor positioning
Akanmu et al. Scenarios for cyber-physical systems integration in construction
CN103544556B (en) Tunnel lifecycle management system and method
Kelly et al. BIM for facility management: a review and a case study investigating the value and challenges
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
CN104680320A (en) BIM-based project management system and method
US10127507B2 (en) Project management system providing interactive issue creation and management
Torres Calderon et al. Synthesizing pose sequences from 3D assets for vision-based activity analysis
CN111368507A (en) Product code generation method and device, computer equipment and storage medium
WO2019174009A1 (en) Machine room management method and dynamic environment system
CN103530664A (en) Production management system of tunnel segment
CN103810563A (en) RFID based electric power asset entire life-cycle management system
CN106557606A (en) For the method and system for positioning virtual objects in virtual simulation environment
CN109359895A (en) RFID habilimentation instructs system and its guidance method, production management system and method
CN103473641A (en) Tunnel segment production and management method
KR20090124621A (en) A product recovery management system
CN109978388A (en) A kind of building management system and method based on artificial intelligence
Dang et al. BIM-based innovative bridge maintenance system using augmented reality technology
Akanmu et al. Critical review of approaches to integrating virtual models and the physical construction
US20130067379A1 (en) Graphical comparison of geographic information system data
Wijeratne et al. BIM enabler for facilities management: A review of 33 cases
KR20150125238A (en) BIM Server Using QR-code and Method and Printed Documents
CN103649912A (en) Method, apparatus, and computer program product for generation of traceability matrices from video media

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20171221

Address after: 200444 Baoshan District Road, Shanghai, No. 99

Co-patentee after: Shanghai Tunnel Engineering Co., Ltd.

Patentee after: Shanghai University

Address before: 200444 Baoshan District Road, Shanghai, No. 99

Patentee before: Shanghai University