[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN108104843A - Tunnel is without empty lining trolley - Google Patents

Tunnel is without empty lining trolley Download PDF

Info

Publication number
CN108104843A
CN108104843A CN201810126439.7A CN201810126439A CN108104843A CN 108104843 A CN108104843 A CN 108104843A CN 201810126439 A CN201810126439 A CN 201810126439A CN 108104843 A CN108104843 A CN 108104843A
Authority
CN
China
Prior art keywords
observation tube
observation
lining trolley
flange
bottom cover
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810126439.7A
Other languages
Chinese (zh)
Inventor
陈德斌
冯春田
夏真荣
傅强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 5 Engineering Group Co Ltd
Original Assignee
China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 5 Engineering Group Co Ltd filed Critical China Railway No 5 Engineering Group Co Ltd
Priority to CN201810126439.7A priority Critical patent/CN108104843A/en
Publication of CN108104843A publication Critical patent/CN108104843A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a kind of tunnel without empty lining trolley, including lining trolley, there is filling concrete hole in trolley crown template(3)And built-in slip casting pipe(1), observation tube is distributed in crown template(2).Filling concrete situation in template, effectively prevents the generation in cavity, multiple observation tubes can be installed in template, realize conduct monitoring at all levels from being put in using observation probe from observation tube.

Description

Tunnel is without empty lining trolley
Technical field
The present invention relates to a kind of tunnel lining trolley, more particularly to a kind of trolley vault liner structure.
Background technology
With lining trolley in Tunnel Second Lining, there is cavity in concrete, very big influence can be caused to its intensity, Lining trolley easily generates cavity in crown part under normal circumstances, and is not easy to find empty, lining cutting during perfusion Cavity is just found when trolley demoulds;After even demoulding, cavity is not seen, but has had cavity in inside concrete.It is main former Because being:(1)When crown upper part is perfused in lining trolley, due to no perfusion window, only perfusing hole, personnel are perfused, it is impossible to As window is being perfused, the perfusion situation of crown upper part is observed like that, i.e., the perfusion of crown upper part cannot be clearly viewed Situation.(2)At the closeer position of reinforcing bar or reserving hole and built-in fitting, concrete discharging is put, and is not vibrated and is continued to pour Layer concrete on note.(3)During pump concrete, it is too long that centre stops pump time.(4)Concrete flowability is poor.(5)Concrete Isolation, mortar separation, stone is in heaps, serious running pulp, and does not vibrate or the blanking of vertical structure dry concrete Excessively, blocked up, blanking is excessively high, and vibrator vibration is less than forming loose hole.(6)Concrete includes water, soil or other are miscellaneous Object.
In Tunnel Second Lining, just need to remove in the event of cavitation to be perfused again, it is time-consuming and laborious, it is of high cost. In order to avoid the above situation occurs, it is common practice to which, in one end that lining trolley is finally perfused, crown highest point installs one Camera, by perfusion situation of concrete during camera head monitor secondary lining in crown template, to prevent cavity, but It is since template is longer(10 meters or more), lining trolley crown highest point is longitudinal along tunnel, is generally evenly distributed with 4 perfusions Mouthful, each perfusing hole of secondary lining, in filling process, the concrete at perfusing hole is high, forms high at perfusing hole, perfusing hole The low gradient of surrounding, camera can only just observe the perfusion situation close to this one side of camera, due to the coagulation at perfusing hole It is native high, block the perfusion situation behind camera observation perfusing hole.
The content of the invention
The technical problem to be solved in the present invention:For present Observations Means not it is observed that the template second half section pours situation The problem of, provide a kind of trolley structure for being capable of comprehensive observation vault secondary lining.
Technical solution of the present invention:
, including lining trolley, there are filling concrete hole and pre-buried note in a kind of tunnel without empty lining trolley in trolley crown template Slurry is managed, and observation tube is distributed in crown template.
Crown die head perforate, lower section are welded and fixed flange, and locating flange, positioning mode is bolted in mounting flange There is the mounting hole of observation tube in blue center, and there are bottom cover, bottom cover central openings in mounting hole lower end.
There is one section of observation window at the top of observation tube, observation window is the transparent configuration of annular, is equipped on the column in observation window Camera and headlamp.
Operation lever is equipped in observation tube, observation probe is installed at the top of operation lever.
Mounting flange or locating flange upper surface offer sliding slot, and plate is installed in sliding slot.
Operation lever top connects closure plate, there is sealing terrace on the outer wall of observation tube upper end, seals and matches somebody with somebody on the inside of terrace and closure plate It closes.
Operation lever other end end is hinged closure plate, and the internal face of observation tube upper end has sealing ring, closure plate upper surface and sealing Ring lower surface coordinates.
Observation probe by camera and lighting lamp group into.
Bottom cover is connected by screw thread with locating flange.
There are card slot in bottom cover both sides, and locating flange lower end is hinged with lock.
Observation tube and built-in slip casting pipe are alternately arranged.
Observation tube and Grouting Pipe are arranged on same cross section, circumferentially among highest point be observation tube, the two of observation tube Each 1 Grouting Pipe in side.
Advantageous effect of the present invention:
Observation tube is installed in vault template, filling concrete situation in template, has from observation probe is put in from observation tube Effect prevents the generation in cavity.Multiple observation tubes in template can be installed, realize conduct monitoring at all levels.It is popped one's head in, can seen by observing The size in clear cavity, before empty slip casting is carried out, additionally it is possible to which the grouting amount in cavity is filled up in probably estimation, and observation grouting amount is made Whether to fill up empty reference.
There is closure plate in the upper end of observation tube, and for removing observation tube when seals upper end, blocks concrete and is not leaked from observation tube Go out.When observation probe pipe exits crown template, crown mouth is closed using plate and blocks concrete, after observation tube is removed, concrete It will not leak out.
Description of the drawings:
Fig. 1 is overall schematic of the present invention.
Fig. 2 is the structure diagram of observation tube in embodiment 1.
Fig. 3 is the mounting structure schematic diagram of observation tube in embodiment 2 and 3.
Fig. 4 is lining trolley overall structure diagram.
Fig. 5 is board plug structure schematic diagram.
Fig. 6 is the arrangement schematic diagram of embodiment 4.
Fig. 7 is the mounting structure schematic diagram of observation tube in embodiment 4.
Fig. 8 is the sealed structural representation of observation tube in embodiment 4.
Fig. 9 is the mounting structure schematic diagram of bottom cover 6 in embodiment 4.
Specific embodiment:
Embodiment 1:
Peep hole and injected hole are opened up in the vault template of lining trolley, flange 4 is welded and fixed below peep hole and injected hole, Bolt is welded on mounting flange 4, locating flange 5 is bolted.4 upper surface of mounting flange offers sliding slot, in sliding slot Plate 10 is set between vault template, and there is positioning tube 6 in 5 center of locating flange, pin hole is offered on barrel, by observation tube 2 Insertion positioning tube 16 is simultaneously extend into through peep hole close to the place of anchor bar of waterproof plate in tunnels 11.Grouting Pipe 1 is installed in injected hole again.
One section of observation window 18 is arranged at 2 top of observation tube, and observation window 18 is annular transparent configuration, is equipped with and takes the photograph in observation window 18 As head and headlamp, stepper motor and column 17, camera and headlamp are mounted on horizontal step motor axis, the stepper motor It is in turn mounted on another vertical step motor axis, realizes camera and 360 ° of headlamp rotates horizontally and 15 ° are rotated up and down sight It examines, vertical step motor is connected with column 17, and column 17 is fixed on observation tube 2.There is location hole on 2 hypomere side wall of observation tube, For the height of position observation pipe 2, the positioning tube 16 on observation tube 2 and locating flange 5 is linked together with bolt 19.
During lining trolley formwork erection, ensure the position of whole observation tubes 2 and Grouting Pipe 1, all in the space of reinforcing bar.
Embodiment 2:
It punches in the backform of lining trolley, in addition to two lining fill orifices 3 of vault, is beaten along the highest point of vault template longitudinal direction first 3 vault injected holes and 2 peep holes, 3 vault fill orifices are followed successively by injected hole, intermediate row stomata(Spare injected hole), end Parting line venting hole.Flange 4 is welded and fixed under hole, 4 upper surface of mounting flange offers sliding slot, plate 10, plate are installed in sliding slot There is hole in 10 centers, can slide plate 10 and open or close peep hole.Locating flange 5 is bolted in mounting flange 4, a kind of Locating flange 5 is for installing Grouting Pipe 1, and for another locating flange 5 for installing observation tube 2, there is observation tube in 5 center of locating flange 3 or the mounting hole of Grouting Pipe 1, the mounting hole lower end for installing observation tube 2 have bottom cover 6,6 central openings of bottom cover, the diameter in hole It is more smaller than 3 internal diameter of observation tube.There are card slot in 6 both sides of bottom cover, and 5 lower end of locating flange is hinged with lock 9, and lock 9 is having with nut Link bolt, the bolt head is hinged with locating flange 5, without removing nut, it is possible to which after rotation and the cooperation of the card slot of bottom cover 6 will Bottom cover 6 locks.
During lining trolley formwork erection, ensure the position of whole observation tubes 2 and Grouting Pipe 1, all in the space of reinforcing bar.
After trolley and template are in place, by ready RPC Grouting Pipes 1 and observation tube 2 by improved preformed hole at It carries out " trying on " to measure, whether the installation length and two thickness of the liner degree of detection for determining RPC Grouting Pipes 1 meet design requirement, specifically Standard is subject to RPC Grouting Pipes and withstands splash guard length+2cm.RPC pipe lengths of embedment are recorded on data board, cut slip casting Pipe 1 and observation tube 2 mark record RPC pipe lengths of embedment after RPC Grouting Pipes 1 withstand splash guard:Mark should be item Line, one is the line for serving as a contrast template exterior sheathings with two(For detecting whether two thickness of the liner degree meet the requirements);Another is two lining templates External mold printed line+2cm, i.e. RPC Grouting Pipes(Exhaust pipe)Cutting length.Observation tube 2 is than 1 short 5cm of Grouting Pipe or so.In slip casting 1 upper surface of pipe opens up cross recess.Grouting Pipe 1 and observation tube 2 are respectively installed in flange, and it is fixed.Grouting Pipe 1 is using connection Steel pipe is fixed, and observation tube 2 is fixed by bottom cover 6.Operation lever 7 is equipped in observation tube 2, observation probe 12 is installed in operation lever 7. 7 top of operation lever connects closure plate 8, there is sealing terrace on the outer wall of 2 upper end of observation tube, seals the 8 inside matching of terrace and closure plate.It sees Examine probe 12 by camera and lighting lamp group into.After observation tube 2 is put into peep hole, observation tube 2, Ran Houzhuan is held with bottom cover 6 Bottom cover 6 is fixed in dynamic lock 9, the 6 liang of side bayonet slot cooperations of lock 9 and bottom cover.
When pouring vault concrete, from being carried out using 7 controlled observation of operation lever probe 12 from 2 top of observation tube, coagulation is monitored Soil pours situation, and observation probe 12 makees 360 ° of horizontal rotations and 15 ° are rotated up and down observation, is driven and observed using stepper motor 22 Probe is horizontal and is rotated up and down or observes probe level using manual actuation and be rotated up and down.Until observing that concrete connects Nearly 2 upper end of observation tube removes observation probe, takes out observation tube 2, blocks peep hole and continues to pour until 1 bleeding of Grouting Pipe, stops Perfusion.
Embodiment 3:The present embodiment is that existing trolley is transformed, and transformation and construction procedure are as follows:
(1)Trolley openings in the ceiling mounting flange
It punches in the backform of lining trolley, in addition to two lining fill orifices 3 of vault, is beaten along the highest point of vault template longitudinal direction first 3 vault fill orifices and 2 peep holes, 3 vault fill orifices are followed successively by injected hole, intermediate row stomata(Spare injected hole), end mould Gas vent.Flange 4 is welded and fixed under five holes.Locating flange 5 is bolted in mounting flange 4, and a kind of locating flange 5 is used In installation Grouting Pipe 1, for another locating flange 5 for installing observation tube 2, there are observation tube 3 or Grouting Pipe 1 in 5 center of locating flange Mounting hole, there is bottom cover 6 in the mounting hole lower end for installing observation tube, and bottom cover 6 is connected by screw thread and locating flange 5.Bottom cover 6 Central openings, the diameter in hole are more smaller than 3 internal diameter of observation tube.5 upper surface of locating flange offers sliding slot, and sliding slot is used to install plate 10, there is hole in 10 center of plate.During lining trolley formwork erection, ensure the position of whole observation tubes 2 and Grouting Pipe 1, all sky in reinforcing bar In lattice.
(2)Make improved template in place according to two lining geometry requirements.
After trolley and template, by ready RPC Grouting Pipes 1 and observation tube 2 by being carried out at improved preformed hole " trying on " measures, and whether the installation length and two thickness of the liner degree of detection for determining RPC Grouting Pipes 1 meet design requirement, specific standards RPC Grouting Pipes of being subject to withstand splash guard length+2cm.
(3)RPC pipe lengths of embedment are recorded on data board, cut Grouting Pipe 1 and observation tube 2
According to(2)Middle operation marks record RPC pipe lengths of embedment after RPC Grouting Pipes 1 withstand splash guard:Mark A line is should be, one is the line for serving as a contrast template exterior sheathings with two(For detecting whether two thickness of the liner degree meet the requirements);Another is two Serve as a contrast template external mold printed line+2cm, i.e. RPC Grouting Pipes(Exhaust pipe)Cutting length.Observation tube 2 is than 1 short 5cm of Grouting Pipe or so. Cross recess is opened up in 1 upper surface of Grouting Pipe.Grouting Pipe 1 and observation tube 2 are respectively installed in flange, and it is fixed.Grouting Pipe 1 is adopted It is fixed with joint steel pipe, observation tube 2 is fixed by bottom cover 6.Sealing terrace is processed in 2 upper end of observation tube(Inclined-plane), in observation tube 2 Equipped with operation lever 7, observation probe 12 is installed, observation probe 12 can make 360 ° of horizontal rotations and 15 ° are rotated up and down in operation lever 7 Observation, drive observation probe horizontal using stepper motor 22 and be rotated up and down or using manual actuation observation probe it is horizontal and It is rotated up and down.7 top of operation lever connects closure plate 8, and for closure plate 8 outside observation tube 2, there is sealing terrace in 2 upper end of observation tube, seals terrace With 8 inside matching of closure plate.Observation probe 12 by camera and lighting lamp group into.
(4)Two lining 3 casting concretes of fill orifice simultaneously observe perfusion situation.
Two lining concrete should be poured symmetrically, and left and right sides concrete surface height difference must not exceed 0.5m, and front and rear height difference must not surpass 0.6m is crossed, concreting should successively self-template window pours by window, from bottom to top, symmetrical to be layered, and inclining falls free height and do not surpass Cross 2m.When pouring vault concrete, will observation probe from observation tube 2 extend into top carry out from, monitored concrete pours Situation, until observing concrete close to 2 upper end of observation tube, operation lever 7 pulls down, and is sealed 2 upper end of observation tube using closure plate 8, Plate 10 is inserted into when taking out observation tube 2 between 5 upper surface sliding slot of locating flange and mounting flange 4, prevents slurries from flowing out.Continue It pours until 1 bleeding of Grouting Pipe, stops perfusion.
(5)Prepared by injection slurry and band is molded into starching.
Vault slip casting in principle according to since low side toward slip casting high-end.After the completion of two lining concretings after 2~3h It carries out, injecting paste material is using filling mortar, the ratio of mud 0.18;Slip casting is operated using dedicated slurrying slip casting all-in-one machine. Slurries require continuous mixing, strictly monitor material utilization amount during mixing, it is ensured that the quality of slurries.Using Grouting Pipe 1 to secondary Lining cutting area of coming to nothing behind between splash guard carries out slip casting, prevents that two lining vaults from coming off and concrete leakiness.
Embodiment 4:
There are 4 fill orifices 3 in vault template in the present embodiment, punched first in the backform of lining trolley, fill orifice 3 is served as a contrast two Between and vault template both ends make a call to five groups of holes, shutoff device is installed under hole.Every group of three holes, centre are peep hole, and both sides are note Hole is starched, three pore size distributions are on same circumference.Flange 4 is welded and fixed under hole, 4 upper surface of mounting flange offers sliding slot, Plate 10 is installed, there is hole in 10 center of plate, can slide plate 10 and open or close peep hole in sliding slot.Mounting flange 4 passes through Locating flange 5 is bolted, for installing Grouting Pipe 1, another locating flange 5 is used to install observation tube a kind of locating flange 5 2, there are observation tube 3 or the mounting hole of Grouting Pipe 1 in 5 center of locating flange, and there is bottom cover 6 in the mounting hole lower end for installing observation tube 2, 6 central openings of bottom cover, the diameter in hole are more smaller than 3 internal diameter of observation tube.There are card slot in 6 both sides of bottom cover, and 5 lower end of locating flange is hinged with lock Button 9.During lining trolley formwork erection, ensure the position of whole observation tubes 2 and Grouting Pipe 1, all in the space of reinforcing bar.
After trolley and template are in place, ready RPC Grouting Pipes 1 and observation tube 2 are installed on trolley.In Grouting Pipe 1 upper surface opens up cross recess.Grouting Pipe 1 and observation tube 2 are respectively installed in flange, and it is fixed.Grouting Pipe 1 is using connection steel Pipe is fixed, and observation tube 2 is fixed by bottom cover 6.Operation lever 7 is equipped in observation tube 2,7 upper end of operation lever is equipped with observation probe 12, There are sealing ring, sealing ring lower surface and closure plate 8 in 7 lower end of operation lever by bulb hinged closure plate 8, the internal face of 2 upper end of observation tube Upper surface coordinates.Observation probe 12 by camera and lighting lamp group into, drive observation probe 12 horizontal using stepper motor 22 and It is rotated up and down or 12 level of probe is observed using manual actuation and is rotated up and down.After observation tube 2 is put into peep hole, bottom is used Lid 6 holds observation tube 2, then rotates lock 9, and bottom cover 6 is fixed in the 6 liang of side bayonet slot cooperations of lock 9 and bottom cover.
When pouring vault concrete, from being carried out using 7 controlled observation of operation lever probe from 2 top of observation tube, monitoring is mixed Solidifying soil pours situation, until observing that concrete close to 2 upper end of observation tube, removes observation probe 12, by operation lever 7 in turn Observation tube 2 is inserted into, closure plate 8 hinged in operation lever 7 is pushed up into 2 top of observation tube, observation tube 2 is sealed, rotates lock 9, remove Bottom cover 6 pulls up observation tube 2, blocks peep hole and continues to pour until 1 bleeding of Grouting Pipe, stops perfusion.

Claims (12)

1., including lining trolley, there is filling concrete hole in a kind of tunnel without empty lining trolley in trolley crown template(3)With it is pre- Bury Grouting Pipe(1), it is characterised in that:Observation tube is distributed in crown template(2).
2. tunnel according to claim 1 is without empty lining trolley, it is characterised in that:Crown die head perforate, lower section It is welded and fixed flange(4), mounting flange(4)Locating flange is bolted(5), locating flange(5)There is observation tube in center(2) Mounting hole, there is bottom cover in mounting hole lower end(6), bottom cover(6)Central openings.
3. tunnel according to claim 1 is without empty lining trolley, it is characterised in that:Observation tube(2)One section of sight is arranged at top Examine window(18), observation window(18)For the transparent configuration of annular, camera and headlamp are mounted on horizontal step motor axis, the step Stepper motor is in turn mounted on another vertical step motor axis, realizes that 360 ° of camera and headlamp rotate horizontally and about 15 ° Rotational view, vertical step motor and column(17)Connection, column(17)It is fixed on observation tube(2)On.
4. tunnel according to claim 2 is without empty lining trolley, it is characterised in that:Observation tube(2)It is interior to be equipped with operation lever (7), operation lever(7)Top is equipped with observation probe(12).
5. tunnel according to claim 2 is without empty lining trolley, it is characterised in that:Mounting flange(4)Or locating flange (5)Upper surface offers sliding slot, and plate is installed in sliding slot(10).
6. tunnel according to claim 4 is without empty lining trolley, it is characterised in that:Operation lever(7)Top connects closure plate (8), observation tube(2)There is sealing terrace on the outer wall of upper end, seal terrace and closure plate(8)Fit inside.
7. tunnel according to claim 4 is without empty lining trolley, it is characterised in that:Operation lever(7)It cuts with scissors other end end Connect closure plate(8), observation tube(2)The internal face of upper end has sealing ring, closure plate(8)Upper surface and the cooperation of sealing ring lower surface.
8. tunnel according to claim 4 is without empty lining trolley, it is characterised in that:Observation probe (12) by camera and Lighting lamp group into.
9. tunnel according to claim 5 is without empty lining trolley, it is characterised in that:Bottom cover(6)Pass through screw thread and positioning Flange(5)Connection.
10. tunnel according to claim 5 is without empty lining trolley, it is characterised in that:Bottom cover(6)There are card slot in both sides, fixed Position flange(5)Lower end is hinged with lock 9, lock(9)It is to have link bolt with nut, the bolt head and locating flange(5)Hinge It connects, without removing nut, it is possible to after rotation and bottom cover(6)Card slot cooperation by bottom cover(6)It locks.
11. according to claim 1-10 any one of them tunnel without empty lining trolley, it is characterised in that:Observation tube(2)With Built-in slip casting pipe(1)It is alternately arranged.
12. according to claim 1-10 any one of them tunnel without empty lining trolley, it is characterised in that:Observation tube(2)With Grouting Pipe(1)It is arranged on same cross section, circumferentially intermediate highest point is observation tube(2), observation tube(2)Each 1 of both sides Grouting Pipe(1).
CN201810126439.7A 2018-02-08 2018-02-08 Tunnel is without empty lining trolley Pending CN108104843A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810126439.7A CN108104843A (en) 2018-02-08 2018-02-08 Tunnel is without empty lining trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810126439.7A CN108104843A (en) 2018-02-08 2018-02-08 Tunnel is without empty lining trolley

Publications (1)

Publication Number Publication Date
CN108104843A true CN108104843A (en) 2018-06-01

Family

ID=62222157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810126439.7A Pending CN108104843A (en) 2018-02-08 2018-02-08 Tunnel is without empty lining trolley

Country Status (1)

Country Link
CN (1) CN108104843A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868836A (en) * 2018-07-06 2018-11-23 中铁二院工程集团有限责任公司 A kind of tunnel lining trolley splash guard supporting member with illumination functions
CN109184751A (en) * 2018-11-16 2019-01-11 中铁隧道集团处有限公司 Endoscopic bomb shelter monitoring device and monitoring method for tunnel-liner vault
CN110617085A (en) * 2019-11-14 2019-12-27 广西恩康机械设备有限公司 Tunnel secondary lining anti-hollow longitudinal strip mold grouting pipe
CN111365029A (en) * 2020-03-31 2020-07-03 中铁五局集团有限公司 Concrete grouting method based on variable-section adjustable lining trolley
CN112025972A (en) * 2020-09-17 2020-12-04 中州装备制造股份有限公司 Preparation process of building wall
CN112593978A (en) * 2020-12-04 2021-04-02 浙大城市学院 Secondary lining vault anti-disengaging device and construction method
CN112647981A (en) * 2021-01-11 2021-04-13 谢发腾 Tunnel lining platform truck grout hole shutoff system
CN114934787A (en) * 2022-06-08 2022-08-23 京昆高速铁路西昆有限公司 Visual tunnel secondary lining arch part longitudinal perfusion and satiation device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2550756Y (en) * 2002-07-08 2003-05-14 阚小勇 Observation instrument for steel bar in hole
JP2009091751A (en) * 2007-10-04 2009-04-30 Nishimatsu Constr Co Ltd Form for tunnel
CN204386614U (en) * 2014-04-09 2015-06-10 齐洪军 Realize the lining trolley of lining cutting vault filling and injecting slurry and tunnel lining synchronization implementation
CN104895585A (en) * 2015-04-30 2015-09-09 中铁二十一局集团第四工程有限公司 Construction method of reserved grouting pipe of tunnel vault
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN206329346U (en) * 2016-11-30 2017-07-14 北京中科昊隅新型材料有限公司 One kind is based on tunnel lining trolley slip casting pipe fixation structure
CN207934912U (en) * 2018-02-08 2018-10-02 中铁五局集团有限公司 Tunnel is without empty lining trolley

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2550756Y (en) * 2002-07-08 2003-05-14 阚小勇 Observation instrument for steel bar in hole
JP2009091751A (en) * 2007-10-04 2009-04-30 Nishimatsu Constr Co Ltd Form for tunnel
CN204386614U (en) * 2014-04-09 2015-06-10 齐洪军 Realize the lining trolley of lining cutting vault filling and injecting slurry and tunnel lining synchronization implementation
CN104895585A (en) * 2015-04-30 2015-09-09 中铁二十一局集团第四工程有限公司 Construction method of reserved grouting pipe of tunnel vault
CN106014454A (en) * 2016-07-11 2016-10-12 北京鸿锐嘉科技发展有限公司 Grouting device and grouting technique for tunnel lining vault with mould
CN206329346U (en) * 2016-11-30 2017-07-14 北京中科昊隅新型材料有限公司 One kind is based on tunnel lining trolley slip casting pipe fixation structure
CN207934912U (en) * 2018-02-08 2018-10-02 中铁五局集团有限公司 Tunnel is without empty lining trolley

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868836A (en) * 2018-07-06 2018-11-23 中铁二院工程集团有限责任公司 A kind of tunnel lining trolley splash guard supporting member with illumination functions
CN109184751A (en) * 2018-11-16 2019-01-11 中铁隧道集团处有限公司 Endoscopic bomb shelter monitoring device and monitoring method for tunnel-liner vault
CN109184751B (en) * 2018-11-16 2024-05-10 中铁隧道集团一处有限公司 Endoscopic type air-raid shelter monitoring device and monitoring method for tunnel lining vault
CN110617085A (en) * 2019-11-14 2019-12-27 广西恩康机械设备有限公司 Tunnel secondary lining anti-hollow longitudinal strip mold grouting pipe
CN111365029A (en) * 2020-03-31 2020-07-03 中铁五局集团有限公司 Concrete grouting method based on variable-section adjustable lining trolley
CN112025972A (en) * 2020-09-17 2020-12-04 中州装备制造股份有限公司 Preparation process of building wall
CN112593978A (en) * 2020-12-04 2021-04-02 浙大城市学院 Secondary lining vault anti-disengaging device and construction method
CN112647981A (en) * 2021-01-11 2021-04-13 谢发腾 Tunnel lining platform truck grout hole shutoff system
CN114934787A (en) * 2022-06-08 2022-08-23 京昆高速铁路西昆有限公司 Visual tunnel secondary lining arch part longitudinal perfusion and satiation device

Similar Documents

Publication Publication Date Title
CN108104843A (en) Tunnel is without empty lining trolley
CN108316949A (en) Umbrella arch is without empty lining process
CN108071406A (en) A kind of tunnel of follow shot is without empty lining trolley
CN206329346U (en) One kind is based on tunnel lining trolley slip casting pipe fixation structure
CN207934912U (en) Tunnel is without empty lining trolley
CN108661671A (en) Tunnel vault two serves as a contrast concrete vacuum and assists pouring procedure
CN106284335A (en) Piling quality defect handling method
CN108166990A (en) Device is observed in crown lining cutting
CN107217844A (en) The manufacture of the horizontal hole to be provided of wall and plugging device and method
CN207829915U (en) A kind of tunnel of follow shot is without empty lining trolley
CN115306446A (en) Tunnel secondary lining vault grouting anti-lost grouting pipe with mold and grouting method
CN207829906U (en) Device is observed in crown lining cutting
CN101545259B (en) Device and method for non-underwater concreting by using drilled pile
CN110485463A (en) Vertically to wall pouring construction method and pouring construction device
CN109812020A (en) A kind of band-like Full-face pouring tube assembly and construction method
CN107237408A (en) It is a kind of to prevent the construction method of expansion joint position seepage
CN114704293B (en) Tunnel secondary lining vault anti-run-out multi-angle slip casting device
CN217632473U (en) Tunnel secondary lining longitudinal perfusion device for arch-proof cavity
CN213297249U (en) Uneven settlement crack processing apparatus of building wall body
CN109595009B (en) Hole sealing device and hole sealing method for pumped concrete inlet
CN207813015U (en) Floor slab preformed hole tool-typed formwork support construction
CN210622817U (en) Secondary lining back backfill slip casting pipe and backfill slip casting system
CN217105180U (en) Novel curtain grouting detection equipment
JP2001248396A (en) Ground water collecting method
CN208981359U (en) The gang form structure of the inspection shaft cast-in-place construction of town road pipeline

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination