[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN106836851A - Deep basal pit hanging-type construction stair and its construction method - Google Patents

Deep basal pit hanging-type construction stair and its construction method Download PDF

Info

Publication number
CN106836851A
CN106836851A CN201611158065.4A CN201611158065A CN106836851A CN 106836851 A CN106836851 A CN 106836851A CN 201611158065 A CN201611158065 A CN 201611158065A CN 106836851 A CN106836851 A CN 106836851A
Authority
CN
China
Prior art keywords
bench
stair
basal pit
deep basal
type construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611158065.4A
Other languages
Chinese (zh)
Inventor
岳齐贤
王兴康
云勇
时连勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang 20 Smelter Construction Co ltd
China MCC20 Group Corp Ltd
Original Assignee
NINGBO MCC20 CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINGBO MCC20 CONSTRUCTION CO Ltd filed Critical NINGBO MCC20 CONSTRUCTION CO Ltd
Priority to CN201611158065.4A priority Critical patent/CN106836851A/en
Publication of CN106836851A publication Critical patent/CN106836851A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G27/00Temporary arrangements for giving access from one level to another for men or vehicles, e.g. steps, ramps

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The invention provides a kind of deep basal pit hanging-type construction stair and its construction method, between twice armored concrete horizontal support, wherein, including:First bench, the second step and the 3rd bench, and the first bench, the second step and the 3rd bench join end to end, and is set into " Z " character form structure.The deep basal pit hanging-type construction stair that the present invention is provided are hung in support stair using the armored concrete horizontal support in deep-foundation pit engineering, can greatly expand the installation environment of construction stair, improve performance;In addition, stair can carry out piecewise spreading or dismounting according to engineering progress, change shortcoming greatly in place between Construction stage of Deep Excavation is met, with good conformability.

Description

Deep basal pit hanging-type construction stair and its construction method
Technical field
The invention belongs to building engineering construction field, it is related to a kind of construction stair, particularly a kind of deep basal pit suspension type is applied Work stair and its construction method.
Background technology
In modern construction engineering, underground structure can be used as functional areas such as parking, equipment, people's air defense, traffic.With The large-scale development of underground structure, substantial amounts of deep-foundation pit engineering continuously emerges.Construction of Deep Excavation Engineering be with the earthwork by Layer excavates what is be done step-by-step, and construction period personnel, material need successively to enter underground.
Because deep foundation pit construction place variability is big, and it is to construct from top to bottom, the Stereotype stairway of factorial praluction makes With limited.Personnel's typically uses accommodation stairway up and down, is formed by connecting by live scaffolding steel pipe, this stair simple structure, But comfortableness, security is all poor.And, construction stair are typically all disposed within foundation ditch periphery, and deep basal pit is typically all first Row central excavation region, stair are installed serious delayed.
In sum, it is necessary to design a kind of flexibility high, comfort level preferably, and safety coefficient construction stair higher.
The content of the invention
The purpose of the present invention is directed to existing technology and there is above mentioned problem, it is proposed that a kind of flexibility is high, comfort level compared with It is good, and safety coefficient construction stair higher.
The purpose of the present invention can be realized by following technical proposal:A kind of deep basal pit hanging-type construction stair, positioned at two Between road armored concrete horizontal support, wherein, including:First bench, the second step and the 3rd bench, and the first bench, The second step and the 3rd bench join end to end, and are set into " Z " character form structure.
In a kind of above-mentioned deep basal pit hanging-type construction stair, the company between first bench and the second step It is connected in and is detachably connected, the connection between the second step and the 3rd bench is to be detachably connected.
In a kind of above-mentioned deep basal pit hanging-type construction stair, the structure of first bench and the structure of the 3rd bench It is identical, wherein, first bench is angularly disposed with the 3rd bench, and angle of inclination is identical, and the second step is It is horizontally disposed.
In a kind of above-mentioned deep basal pit hanging-type construction stair, the deep basal pit hanging-type construction stair are also included at least A piece support column, and support column is connected to the side of the second step.
In a kind of above-mentioned deep basal pit hanging-type construction stair, the deep basal pit hanging-type construction stair are also included at least One support frame, and one end of support frame is connected with the second step, the other end of support frame is connected with support column.
In a kind of above-mentioned deep basal pit hanging-type construction stair, support frame as described above includes:
Base plate, is installed on the bottom of the second step;
Swash plate, one end is connected with base plate, and the other end is connected with support column,
Wherein, base plate, swash plate and support column constitute a triangle.
In a kind of above-mentioned deep basal pit hanging-type construction stair, along first bench, the second step and institute The length direction for stating the 3rd bench sets accommodation rail, and accommodation rail is located at first bench, the second step respectively And two sides of the 3rd bench.
In a kind of above-mentioned deep basal pit hanging-type construction stair, first bench includes:
Some bench beams, are parallel to each other angularly disposed, and on same inclined-plane;
Some pieces of pedals, are set along the length direction of bench beam, and pedal is detachably connected with bench beam, wherein, it is each The tangent value of formed acute angle is equal with the slope of bench beam between block pedal and bench beam.
In a kind of above-mentioned deep basal pit hanging-type construction stair, the second step includes:
Some landing beams, and it is mutually horizontally disposed, and in same level;
Landing slab, is laid on landing beam, and is detachably connected with landing beam.
The present invention also provides a kind of construction method of deep basal pit hanging-type construction stair, and it includes:
Step one:According to foundation depth, the set location of armored concrete horizontal support, it is determined that the installation position of construction stair Put, and pre-buried several fixing bolts on armored concrete horizontal support;
Step 2:Install support post, and support post upper and lower ends respectively with armored concrete horizontal support in Pre-embedded bolt is connected;
Step 3:Installation is bolted between support frame, and support frame and support column;
Step 4:The second step is installed, the second step is installed on support frame by bolt;
Step 5:First bench is installed, and one end of the first bench is detachably connected with armored concrete horizontal support, the The other end of one bench is detachably connected with one end of the second step;
Step 6:3rd bench is installed, and one end of the 3rd bench is detachably connected with armored concrete horizontal support, the The other end of three bench is detachably connected with the other end of the second step;
Step 7:Accommodation rail is installed, accommodation rail is installed on the two ends of pedal and landing slab by bolt;
Step 8:Installation, construction stair are come into operation;
Step 9:According to project progress, stair are removed paragraph by paragraph from bottom to top, store standby.
Compared with prior art, beneficial effects of the present invention:
(1), the deep basal pit hanging-type construction stair that the present invention is provided are using the armored concrete level in deep-foundation pit engineering Support, stair are hung in support, can greatly expand the installation environment of construction stair, improve performance;In addition, stair can Piecewise spreading or dismounting are carried out according to engineering progress, change shortcoming greatly in place between Construction stage of Deep Excavation is met, with good Conformability;
(2), the construction method of a kind of deep basal pit hanging-type construction stair that the present invention is provided, wherein the first bench, second It is connected by screw bolts between bench and the 3rd bench and between bench and armored concrete horizontal support, its connected mode Simply, firmly, replaceable and detachable convenient, and the building block of stair is also used for multiple times, it is easy to lay in.
Brief description of the drawings
Fig. 1 is a kind of facade structures schematic diagram of deep basal pit hanging-type construction stair of the invention.
Fig. 2 is a kind of planar structure schematic diagram of deep basal pit hanging-type construction stair of the invention.
Fig. 3 is support frame, the facade structures schematic diagram of half space in a preferred embodiment of the present invention.
In figure, 100, armored concrete horizontal support;200th, the first bench;210th, bench beam;220th, pedal;300th, second Bench;310th, landing beam;320th, landing slab;400th, the 3rd bench;500th, support column;600th, support frame;610th, base plate;620th, tiltedly Plate;700th, accommodation rail.
Specific embodiment
The following is specific embodiment of the invention and with reference to accompanying drawing, technical scheme is further described, But the present invention is not limited to these embodiments.
As depicted in figs. 1 and 2, a kind of deep basal pit hanging-type construction stair that the present invention is provided, positioned at twice reinforced concrete Between native horizontal support 100, wherein, including:First bench 200, the bench 400 of the second step 300 and the 3rd, and the first bench 200th, the bench 400 of the second step 300 and the 3rd joins end to end, and is set into " Z " character form structure.
The deep basal pit hanging-type construction stair that the present invention is provided are using the armored concrete horizontal support in deep-foundation pit engineering 100, stair are hung in support, the installation environment of construction stair can be greatly expanded, improve performance;In addition, stair can Piecewise spreading or dismounting are carried out according to engineering progress, change shortcoming greatly in place between Construction stage of Deep Excavation is met, with good Conformability.
Preferably, as depicted in figs. 1 and 2, the connection between the first bench 200 and the second step 300 is to be detachably connected, Connection between the bench 400 of the second step 300 and the 3rd is to be detachably connected so that the first bench 200 and the second step 300 it Between and the bench 400 of the second step 300 and the 3rd between not only connected each other but also separate;When the first bench 200, the second step 300 and the 3rd bench 400 be connected when being spliced, connected each other between three, structure is integral, when dismantling the first bench 200th, the second step 300 and during three bench 400, after removing the 3rd bench 400, the first bench 200 and the second step 300 Still can be used.
Preferably, as depicted in figs. 1 and 2, the structure of the first bench 200 is identical with the structure of the 3rd bench 400, wherein, First bench 200 is angularly disposed with the 3rd bench 400, and the second step 300 is horizontally disposed, and the second step 300 is used as not Breath platform.
Preferably, as depicted in figs. 1 and 2, the first bench 200 is identical with the angle of inclination of the 3rd bench 400, is easy to workman It is more convenient in walking or transport process, in addition, identical angle of inclination also allows for the first bench 200 and the 3rd bench 400 Installation.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, deep basal pit hanging-type construction stair also include at least one support column 500, and support column 500 is connected to the side of the second step 300, the vertical load of the stair that are used to construct, and keep stair of constructing Horizontal direction stability.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, the quantity of support column 500 is two, and is respectively symmetrically positioned at second The two ends of bench 300, further improve the stability of construction stair.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, support column 500 is made from I-steel, the deadweight of structure compared with Gently, its usable floor area is larger, and intensity is higher.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, deep basal pit hanging-type construction stair also include at least one support frame 600, and one end of support frame 600 is connected with the second step 300, the other end of support frame 600 is connected with support column 500, will apply The load that work stair are born, by support frame 600, is transferred on support column 500, so as to mitigate the load-bearing of construction stair, carries The security of height construction stair.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, support frame 600 is made from I-steel, the deadweight of structure compared with Gently, its usable floor area is larger, and intensity is higher.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, support frame 600 includes:Base plate 610, is installed on the second step 300 Bottom;Swash plate 620, one end is connected with base plate 610, and the other end is connected with support column 500 so that base plate 610, swash plate 620 and Support column 500 constitutes a triangle, so as to improve the endurance of the second step 300, and then improves the security of construction stair And reliability.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, along the first bench 200, the bench 400 of the second step 300 and the 3rd Length direction accommodation rail 700 is set, and accommodation rail 700 is located at the first bench 200, the second step 300 and the respectively Two sides of three bench 400, are used to protect stair both sides, prevent workmen from falling accidentally when stair are walked about, and improve construction The security of stair.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, accommodation rail 700 is made from square steel, and its casting technique can It is made of hot rolling, forging or cold-drawn, intensity is high, good stability.
Preferably, as depicted in figs. 1 and 2, the first bench 200 includes:Some bench beams 210, be parallel to each other oblique setting Put, and on same inclined-plane;Some pieces of pedals 220, are set along the length direction of bench beam 210, and pedal 220 and bench beam 210 are detachably connected, wherein, the tangent value of formed acute angle and bench beam between each piece of pedal 220 and bench beam 210 210 slope is equal.
Preferably, as depicted in figs. 1 and 2, bench beam 210 is made from square steel, used as the load-bearing structure of bench load Part, its casting technique can be made of hot rolling, forging or cold-drawn, and intensity is high, good stability.
Preferably, as depicted in figs. 1 and 2, pedal 220 is made from steel plate, wherein, the length of pedal 220, width And thickness is respectively 900mm, 280mm and 3mm.
Preferably, as depicted in figs. 1 and 2, the second step 300 includes:Some landing beams 310, and it is mutually horizontally disposed, And in same level;Landing slab 320, is laid on landing beam 310, and is detachably connected with landing beam 310, used as applying Half space of the workman person during transporting goods.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, some landing beams 310 be located at landing slab 320 and base plate 610 it Between, and be easy to using being detachably connected between landing beam 310 and landing slab 320 and between base plate 610 and landing beam 310 Install and change.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, landing beam 310 is made from square steel, is carried as half space The supporting member of lotus, its casting technique can be made of hot rolling, forging or cold-drawn, and intensity is high, good stability.
Preferably, as shown in Figure 1, Figure 2 and shown in Fig. 3, landing slab 320 is made from steel plate, wherein, landing slab 320 Length, width and thickness be respectively 1100mm, 900mm and 3mm.
The present invention also provides a kind of construction method of deep basal pit hanging-type construction stair, by taking certain deep-foundation pit engineering as an example, opens Dig depth 17m, 20000 square metres of foundation ditch area.Three road armored concrete horizontal supports 100, workmen's lower channel are set Using deep basal pit hanging-type construction stair, per 2 bench are set between twice armored concrete horizontal support 100,1 rest is flat Platform.According to field partition, 4 groups of construction stair are set altogether.
According to construction number of staircases described above, its construction method comprises the following steps, wherein, with 2 bench of constructing As a example by 1 half space:
Step one:According to foundation depth, the set location of armored concrete horizontal support 100, it is determined that the peace of construction stair Holding position, and pre-buried several fixing bolts on armored concrete horizontal support 100;
Step 2:Install support post, and support post upper and lower ends respectively with armored concrete horizontal support 100 in Pre-embedded bolt be connected;
Step 3:Installation is bolted between support frame 600, and support frame 600 and support column 500;
Step 4:The second step 300 is installed, the second step 300 is installed on support frame 600 by bolt;
Wherein, mounting platform beam 310 first, landing beam 310 is uniformly layed on support frame 600, and is connected by bolt Connect;Then mounting platform plate 320, landing slab 320 is layed on landing beam 310, and be bolted;
Step 5:First bench 200 is installed, and one end of the first bench 200 is removable with armored concrete horizontal support 100 Connection is unloaded, the other end and one end of the second step 300 of the first bench 200 are detachably connected;
Wherein, of the bench beam 210 in the bench beam 210 in the first bench 200, and the first bench 200 is installed first Hold and be connected with the bolt being embedded in armored concrete horizontal support 100, the other end of the bench beam 210 in the first bench 200 It is connected with the landing beam 310 of wherein side by bolt;Then pedal 220 in first bench 200 is installed, by bolt by one Block block pedal 220 is installed on the bench beam 210 in the first bench 200 successively;
Step 6:3rd bench 400 is installed, and one end of the 3rd bench 400 is removable with armored concrete horizontal support 100 Connection is unloaded, the other end and the other end of the second step 300 of the 3rd bench 400 are detachably connected;
Wherein, the bench beam 210 in the 3rd bench 400 is installed first, and bench beam 210 in the 3rd bench 400 one Hold and be connected with the bolt being embedded in armored concrete horizontal support 100, the other end of the bench beam 210 in the 3rd bench 400 It is connected with the landing beam 310 of opposite side by bolt;Then pedal 220 in 3rd bench 400 is installed, by bolt by one piece Block pedal 220 is installed on the bench beam 210 in the 3rd bench 400 successively;
Step 7:Accommodation rail 700 is installed, accommodation rail 700 is installed on by pedal 220 and landing slab by bolt 320 two ends, are used to protect stair both sides, prevent workmen from being fallen accidentally when stair are walked about;
Step 8:Installation, construction stair are come into operation;
Step 9:According to project progress, stair are removed paragraph by paragraph from bottom to top, store standby.
The construction method of a kind of deep basal pit hanging-type construction stair that the present invention is provided, wherein first the 200, second ladder of bench It is connected by screw bolts between the bench 400 of section 300 and the 3rd and between bench and armored concrete horizontal support 100, its Connected mode is simple, firm, replaceable and detachable convenient, and the building block of stair is also used for multiple times, it is easy to lay in.
Specific embodiment described herein is only to the spiritual explanation for example of the present invention.Technology neck belonging to of the invention The technical staff in domain can be made various modifications or supplement to described specific embodiment or be replaced using similar mode Generation, but without departing from spirit of the invention or surmount scope defined in appended claims.

Claims (10)

1. a kind of deep basal pit hanging-type construction stair, between twice armored concrete horizontal support, it is characterised in that bag Include:First bench, the second step and the 3rd bench, and the first bench, the second step and the 3rd bench join end to end, into " Z " character form structure is set.
2. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that first bench and institute The connection between the second step is stated to be detachably connected, the connection between the second step and the 3rd bench is detachable Connection.
3. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that the knot of first bench Structure is identical with the structure of the 3rd bench, wherein, first bench and the 3rd bench are angularly disposed, and angle of inclination phase Together, the second step is horizontally disposed.
4. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that the deep basal pit suspension type Construction stair also include at least one support column, and support column is connected to the side of the second step.
5. a kind of deep basal pit hanging-type construction stair according to claim 4, it is characterised in that the deep basal pit suspension type Construction stair also include at least one support frame, and one end of support frame is connected with the second step, the other end of support frame It is connected with support column.
6. a kind of deep basal pit hanging-type construction stair according to claim 5, it is characterised in that support frame as described above includes:
Base plate, is installed on the bottom of the second step;
Swash plate, one end is connected with base plate, and the other end is connected with support column,
Wherein, base plate, swash plate and support column constitute a triangle.
7. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that along first bench, The length direction of the second step and the 3rd bench sets accommodation rail, and accommodation rail is located at described first respectively Two sides of bench, the second step and the 3rd bench.
8. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that the first bench bag Include:
Some bench beams, are parallel to each other angularly disposed, and on same inclined-plane;
Some pieces of pedals, are set along the length direction of bench beam, and pedal is detachably connected with bench beam, wherein, each piece is stepped on The tangent value of formed acute angle is equal with the slope of bench beam between plate and bench beam.
9. a kind of deep basal pit hanging-type construction stair according to claim 1, it is characterised in that the second step bag Include:
Some landing beams, and it is mutually horizontally disposed, and in same level;
Landing slab, is laid on landing beam, and is detachably connected with landing beam.
10. it is a kind of construct any deep basal pit hanging-type construction stair of claim 1 to 9 method, it is characterised in that bag Include:
Step one:According to foundation depth, the set location of armored concrete horizontal support, it is determined that the installation site of stair of constructing, And on armored concrete horizontal support pre-buried several fixing bolts;
Step 2:Install support post, and support post upper and lower ends respectively with armored concrete horizontal support in it is pre-buried Bolt is connected;
Step 3:Installation is bolted between support frame, and support frame and support column;
Step 4:The second step is installed, the second step is installed on support frame by bolt;
Step 5:First bench is installed, and one end of the first bench is detachably connected with armored concrete horizontal support, the first ladder The other end of section is detachably connected with one end of the second step;
Step 6:3rd bench is installed, and one end of the 3rd bench is detachably connected with armored concrete horizontal support, the 3rd ladder The other end of section is detachably connected with the other end of the second step;
Step 7:Accommodation rail is installed, accommodation rail is installed on the two ends of pedal and landing slab by bolt;
Step 8:Installation, construction stair are come into operation;
Step 9:According to project progress, stair are removed paragraph by paragraph from bottom to top, store standby.
CN201611158065.4A 2016-12-15 2016-12-15 Deep basal pit hanging-type construction stair and its construction method Pending CN106836851A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611158065.4A CN106836851A (en) 2016-12-15 2016-12-15 Deep basal pit hanging-type construction stair and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611158065.4A CN106836851A (en) 2016-12-15 2016-12-15 Deep basal pit hanging-type construction stair and its construction method

Publications (1)

Publication Number Publication Date
CN106836851A true CN106836851A (en) 2017-06-13

Family

ID=59140385

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611158065.4A Pending CN106836851A (en) 2016-12-15 2016-12-15 Deep basal pit hanging-type construction stair and its construction method

Country Status (1)

Country Link
CN (1) CN106836851A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505764A (en) * 2018-05-28 2018-09-07 山东新城建工股份有限公司 A kind of construction of underground depth large-engineering is marked time bench channel and its construction method
CN110965808A (en) * 2019-11-26 2020-04-07 上海二十冶建设有限公司 Construction method of externally hung stair and packway of fabricated building
CN111608429A (en) * 2020-05-06 2020-09-01 中国一冶集团有限公司 Assembled ultra-deep foundation pit ramp system and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11229610A (en) * 1998-02-13 1999-08-24 Taisei Corp Transportable stairs
CN204001822U (en) * 2014-08-08 2014-12-10 中国建筑第四工程局有限公司 A kind of steel pipe frame construction stair
CN204000932U (en) * 2014-06-03 2014-12-10 天津市达森城交钢结构有限公司 Lower channel in safety in a kind of deep foundation pit construction operation
CN204212450U (en) * 2014-11-05 2015-03-18 中建一局集团第六建筑有限公司 A kind of tool-type safe and convenient passage
CN204825915U (en) * 2015-07-30 2015-12-02 中国建筑第六工程局有限公司 A assembled cat ladder for in foundation ditch

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11229610A (en) * 1998-02-13 1999-08-24 Taisei Corp Transportable stairs
CN204000932U (en) * 2014-06-03 2014-12-10 天津市达森城交钢结构有限公司 Lower channel in safety in a kind of deep foundation pit construction operation
CN204001822U (en) * 2014-08-08 2014-12-10 中国建筑第四工程局有限公司 A kind of steel pipe frame construction stair
CN204212450U (en) * 2014-11-05 2015-03-18 中建一局集团第六建筑有限公司 A kind of tool-type safe and convenient passage
CN204825915U (en) * 2015-07-30 2015-12-02 中国建筑第六工程局有限公司 A assembled cat ladder for in foundation ditch

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108505764A (en) * 2018-05-28 2018-09-07 山东新城建工股份有限公司 A kind of construction of underground depth large-engineering is marked time bench channel and its construction method
CN110965808A (en) * 2019-11-26 2020-04-07 上海二十冶建设有限公司 Construction method of externally hung stair and packway of fabricated building
CN111608429A (en) * 2020-05-06 2020-09-01 中国一冶集团有限公司 Assembled ultra-deep foundation pit ramp system and construction method thereof
CN111608429B (en) * 2020-05-06 2022-03-22 中国一冶集团有限公司 Assembled ultra-deep foundation pit ramp system and construction method thereof

Similar Documents

Publication Publication Date Title
CN106223595A (en) A kind of rack high altitude bulk sliding platform and high altitude bulk construction method
CN106087752A (en) Multispan cable-carried arch bridge construction method
CN107013038A (en) A kind of steel structure slipping of building roof lighting Zhongting changes column construction method
CN105970811A (en) Construction technology for elevated bridge with large-span spatial 3D-surface fish-bellied box steel structure
CN107905114A (en) A kind of construction method of large span Successive interference cancellation
CN110886227B (en) Main tower cast-in-place lower cross beam support system and construction method
CN107780663A (en) A kind of network camber line displacement accumulation slippage construction method
CN106185543A (en) In lowering or hoisting gear, attachment basis supports, with section, the construction method being connected
CN106836851A (en) Deep basal pit hanging-type construction stair and its construction method
CN109505309B (en) Pipe gallery segment displacement system and pipe gallery installation method using same
CN105952133A (en) Suspended large-span reinforced concrete structure construction steel platform and construction method
CN112320611B (en) Overweight assembled prefabricated stair hoisting device and construction method
CN110409624A (en) A kind of installation of large scale equipment and main structure be inverse to be made to calculate and construction method
CN210507456U (en) Standardized lower pedestrian crossing of hanging down of deep basal pit can have enough to meet need
CN106930315B (en) Mobile tower crane foundation structure and construction method
CN205662832U (en) Under hold formula beiLei beam steel suspension bridge
JP6590512B2 (en) Staircase temporary scaffolding
CN107816209B (en) The large-scale Roof Truss construction technology of installation is lifted across outer two sides
CN104831928B (en) High-altitude long-span concrete conjoined structure shuttering supporting steel platform construction method
CN209538639U (en) Make track movable Scaffold by oneself
CN106121238A (en) High-altitude concrete conveying device
CN110886225A (en) Construction method of cable tower stay cable installation system
CN205976546U (en) Rail transport device for inclined working face
CN106437174B (en) Rail transport device for inclined operation surface and construction method thereof
CN109024290A (en) A kind of bowl fastening type full framing and its construction method for continuous beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant after: Zhejiang 20 Smelter Construction Co.,Ltd.

Address before: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant before: NINGBO MCC 20 CONSTRUCTION Co.,Ltd.

CB02 Change of applicant information
TA01 Transfer of patent application right

Effective date of registration: 20190613

Address after: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant after: Zhejiang 20 Smelter Construction Co.,Ltd.

Applicant after: CHINA MCC20 GROUP Corp.,Ltd.

Address before: 315 800 Pearl River Road 429 Xindan Street, Beilun District, Ningbo City, Zhejiang Province

Applicant before: Zhejiang 20 Smelter Construction Co.,Ltd.

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20170613

RJ01 Rejection of invention patent application after publication