[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

CN106284019A - A kind of permeable tile work road surface and construction method thereof - Google Patents

A kind of permeable tile work road surface and construction method thereof Download PDF

Info

Publication number
CN106284019A
CN106284019A CN201610744231.2A CN201610744231A CN106284019A CN 106284019 A CN106284019 A CN 106284019A CN 201610744231 A CN201610744231 A CN 201610744231A CN 106284019 A CN106284019 A CN 106284019A
Authority
CN
China
Prior art keywords
road surface
building waste
permeable
tile work
particle diameter
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610744231.2A
Other languages
Chinese (zh)
Inventor
唐健发
唐玲
唐浩城
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201610744231.2A priority Critical patent/CN106284019A/en
Publication of CN106284019A publication Critical patent/CN106284019A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C11/00Details of pavings
    • E01C11/22Gutters; Kerbs ; Surface drainage of streets, roads or like traffic areas
    • E01C11/224Surface drainage of streets
    • E01C11/225Paving specially adapted for through-the-surfacing drainage, e.g. perforated, porous; Preformed paving elements comprising, or adapted to form, passageways for carrying off drainage
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00241Physical properties of the materials not provided for elsewhere in C04B2111/00
    • C04B2111/00284Materials permeable to liquids
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/40Porous or lightweight materials

Landscapes

  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Ceramic Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Road Paving Structures (AREA)

Abstract

The invention discloses a kind of permeable tile work road surface, be made up of the basic unit sorted the most successively, bearing bed and surface layer.Also disclose the construction method on permeable tile work road surface, including following sequence step: the construction of base layer construction, bearing bed, water-permeable brick are paved, the cementation of fissures, maintenance, on-the-spot cleaning.The present invention solves all kinds of social problems due to traditional concrete pavement row's infiltration effect difference band and environmental problem, and the method easy construction, low cost, is worth promoting.

Description

A kind of permeable tile work road surface and construction method thereof
Technical field
The invention belongs to pavement construction technical field, be specifically related to a kind of permeable tile work road surface and construction method thereof.
Background technology
At present, City surface more than 80% area is covered by building concrete road surface, city obtain the temperature in urban district than suburb and Rural area is high 2-3 degree Celsius, produces so-called " heat island phenomenon ".Along with the progress of science and technology, the mankind are right in daily engineering construction Keep environment more and more higher with the most harmonious requirement.The rainwater ecological environment to city that can not permeate the ground for a long time brings Liao Xu social problem: cause Urban Underground water level to decline, makes rainwater be blocked the supplementary of underground, thus affects ground surface Plant growing, city's green areas is few, and result causes urban ecological system to lack of proper care;Airborne dust makes PM2.5 particulate matter in urban air Increase;Rainfall is excessive causes surface gathered water seriously to make traffic be obstructed;Etc..
For the problems referred to above, arise at the historic moment in water-permeable brick road surface.Water-permeable brick road surface utilizes the Permeable characteristic of water-permeable brick and roadbed Reaching good permeable effect, rainwater can permeate the ground through road surface, thus solves series of problems recited above.
Summary of the invention
It is an object of the invention to provide a kind of permeable tile work road surface and construction method thereof, solve due to tradition coagulation All kinds of social problems of soil surface row's infiltration effect difference band and environmental problem, and the method easy construction, low cost, be worth big Try hard to recommend wide.
Concrete, that the present invention provides permeable tile work road surface, by by the basic unit sorted the most successively, bearing bed and Surface layer forms, and wherein, basic unit is foundation soil, and bearing bed is graded broken stone layer, and surface layer is permeable brick layer.
As further illustrating of permeable tile work road surface of the present invention, described graded broken stone be use particle diameter be 5mm, The cobble of five kinds of specifications of 10mm, 20mm, 40mm, 60mm, mixes compounding by the weight ratio of 2:2:2:1:1 and obtains.
Further, described bearing bed thickness is 150-300mm.
As further illustrating of permeable tile work road surface of the present invention, described water-permeable brick is by the component system of following parts by weight Standby and obtain: building waste aggregate 18-22 part, slag 15-18 part, portland cement 12-15 part, make pottery sand 10-12 part, Machine-made Sand 7- 10 parts, well as clay fines 5-7 part, cenosphere 5-7 part, flyash 3-5 part, pigment 3-5 part, water 6-8 part, 0.5-1 part water reducer.
Further, described building waste aggregate by building waste fine powder, building waste fine aggregate, building waste coarse aggregate, Building waste granule gathers materials and obtains by weight for 1:2:2:1 mixing is compounding;The particle diameter of described building waste fine powder is 0.1- 0.5mm, the particle diameter of building waste fine aggregate is 0.5-1mm, and the particle diameter of building waste coarse aggregate is 1-2.5mm, building waste The particle diameter that grain gathers materials is 2.5-5mm.
Further, the particle diameter of described slag is 2-4mm;The particle diameter of described well as clay fines is 0.05-0.1mm.
Further, coefficient of permeability >=1.5 × 10 of described water-permeable brick-2Cm/s, rupture strength >=4MPa, tensile splitting strength >=3.5 MPa, comprcssive strength >=30MPa.
The construction method on the permeable tile work road surface that the present invention additionally provides, including following sequence step:
(1) base layer construction: select construction site, according to physical features cleaning surface, construction site soil layer after measurement and positioning, and by soil layer Smooth compacting;
(2) bearing bed construction: with graded broken stone for bearing bed construction material, pave smooth and roll compacting;
(3) water-permeable brick is paved: casting concrete basic unit in carrying aspect, the most uniformly paves water-permeable brick;
(4) cementation of fissures: with the cementation of fissures sand cementation of fissures, carry out several times, until gap is full;
(5) maintenance: road surface is closed, more than maintenance 3d under field conditions (factors);
(8) on-the-spot cleaning: road cleaning is clean.
As the further illustrating of construction method on permeable tile work road surface of the present invention, in step (3), described concrete Use C15 Sand-free permeable concrete.
The bearing bed on permeable tile work road surface of the present invention and surface layer are respectively provided with good row's infiltration effect, and rainwater can quickly ooze Enter bearing bed and directly permeate the ground in soil layer, thus supplementing soil moisture, improving the growth conditions of floor vegetation.
Building waste refers to that all kinds of buildings, structures, pipe network etc. are built, spread by construction, unit in charge of construction or individual If or dregs, spoir, rejected material, mud and other garbages produced by dismounting, reparative processes.The water-permeable brick of the present invention is with powder After broken, classification, building waste is prepared as aggregate, can realize the recycling of building waste, can reduce again the preparation of water-permeable brick Cost, thus reduce the construction cost on permeable tile work road surface.
The present invention is conducive to alleviating city " heat island phenomenon " effect, regulates urban climate, reduces the PM2.5 granule in air Thing, prevents surface gathered water, has good social effect and environmental effect.
Construction method of the present invention is easy, and low cost should vigorously promote the use.
Detailed description of the invention
The present invention is described in further detail by following example, and the present embodiment is only to make the present invention more clearly Bright rather than limitation of the present invention.
Embodiment 1
The permeable tile work road surface of the present embodiment, is formed by by the basic unit sorted the most successively, bearing bed and surface layer, its In, basic unit is foundation soil, and bearing bed is graded broken stone layer, and surface layer is permeable brick layer.Its construction method comprises the following steps:
(1) base layer construction: select construction site, according to physical features cleaning surface, construction site soil layer after measurement and positioning, and by soil layer Smooth compacting;
(2) bearing bed construction: with graded broken stone for bearing bed construction material, paves smooth and rolls that to tamp into thickness be 150mm Bearing bed;Described graded broken stone is the cobble using particle diameter to be five kinds of specifications of 5mm, 10mm, 20mm, 40mm, 60mm, by 2:2: The weight ratio mixing of 2:1:1 is compounding and obtains;
(3) water-permeable brick is paved: pours C15 Sand-free permeable concrete basic unit in carrying aspect, the most uniformly paves water-permeable brick;
(4) cementation of fissures: with the cementation of fissures sand cementation of fissures, carry out several times, until gap is full;
(5) maintenance: road surface is closed, more than maintenance 3d under field conditions (factors);
(8) on-the-spot cleaning: road cleaning is clean.
Water-permeable brick described in the present embodiment step (3), is prepared by following methods step:
(1) primary raw material processes
1) building waste aggregate processing: building waste is pulverized and is sieved into the raw material of different-grain diameter, and particle diameter is at 0.1-0.5mm Between as building waste fine powder raw material, particle diameter is as building waste fine aggregate raw material between 0.5-1mm, and particle diameter is at 1- As building waste coarse aggregate raw material between 2.5mm, particle diameter gathers materials raw material as building waste granule between 2.5-5mm, presses Building waste fine powder, building waste fine aggregate, building waste coarse aggregate, building waste granule gather materials by weight for 1:2:2:1 Mixing is compounding, to obtain final product;
2) preparation of slag: by slag pulverize, sieve, control particle diameter at 3mm,;
3) preparation of well as clay fines: by clay pulverize, sieve, control particle diameter at 0.05mm,;
(2) raw material metering
Weigh the raw material of following parts by weight respectively: 18 parts of building waste aggregate, 17 parts of slag, portland cement 14 parts, pottery sand 12 parts, Machine-made Sand 9 parts, well as clay fines 6 parts, cenosphere 7 parts, 4 parts of flyash, pigment 5 parts, 8 parts, 0.5 part water reducer of water;
(3) brickmaking
Step (2) each component raw material is placed in blender mixing, then mixing raw material technique brick machine routinely is carried out Mechanical pressing, prepares adobe, then adobe is placed in curing kilns by after the natural curing of 28 days, prepare described water-permeable brick.
By measuring, the technical performance index of the present embodiment water-permeable brick is: coefficient of permeability: 1.8 × 10-2Cm/s, anti-folding is strong Degree: 4.2MPa, tensile splitting strength: 3.5 MPa, comprcssive strength: 31MPa.
Embodiment 2
The permeable tile work road surface of the present embodiment, is formed by by the basic unit sorted the most successively, bearing bed and surface layer, its In, basic unit is foundation soil, and bearing bed is graded broken stone layer, and surface layer is permeable brick layer.Its construction method comprises the following steps:
(1) base layer construction: select construction site, according to physical features cleaning surface, construction site soil layer after measurement and positioning, and by soil layer Smooth compacting;
(2) bearing bed construction: with graded broken stone for bearing bed construction material, paves smooth and rolls that to tamp into thickness be 300mm Bearing bed;Described graded broken stone is the cobble using particle diameter to be five kinds of specifications of 5mm, 10mm, 20mm, 40mm, 60mm, by 2:2: The weight ratio mixing of 2:1:1 is compounding and obtains;
(3) water-permeable brick is paved: pours C15 Sand-free permeable concrete basic unit in carrying aspect, the most uniformly paves water-permeable brick;
(4) cementation of fissures: with the cementation of fissures sand cementation of fissures, carry out several times, until gap is full;
(5) maintenance: road surface is closed, more than maintenance 3d under field conditions (factors);
(8) on-the-spot cleaning: road cleaning is clean.
Water-permeable brick described in the present embodiment step (3), is prepared by following methods step:
(1) primary raw material processes
1) building waste aggregate processing: building waste is pulverized and is sieved into the raw material of different-grain diameter, and particle diameter is at 0.1-0.5mm Between as building waste fine powder raw material, particle diameter is as building waste fine aggregate raw material between 0.5-1mm, and particle diameter is at 1- As building waste coarse aggregate raw material between 2.5mm, particle diameter gathers materials raw material as building waste granule between 2.5-5mm, presses Building waste fine powder, building waste fine aggregate, building waste coarse aggregate, building waste granule gather materials by weight for 1:2:2:1 Mixing is compounding, to obtain final product;
2) preparation of slag: by slag pulverize, sieve, control particle diameter at 2mm,;
3) preparation of well as clay fines: by clay pulverize, sieve, control particle diameter at 0.1mm,;
(2) raw material metering
Weigh the raw material of following parts by weight respectively: 22 parts of building waste aggregate, 16 parts of slag, portland cement 15 parts, pottery sand 11 parts, Machine-made Sand 10 parts, well as clay fines 7 parts, cenosphere 6 parts, 3 parts of flyash, pigment 4 parts, 6 parts, 1 part water reducer of water;
(3) brickmaking
Step (2) each component raw material is placed in blender mixing, then mixing raw material technique brick machine routinely is carried out Mechanical pressing, prepares adobe, then adobe is placed in curing kilns by after the natural curing of 28 days, prepare described water-permeable brick.
By measuring, the technical performance index of the present embodiment water-permeable brick is: coefficient of permeability: 1.5 × 10-2Cm/s, anti-folding is strong Degree: 4.5MPa, tensile splitting strength: 3.7MPa, comprcssive strength: 33MPa.
Embodiment 3
The permeable tile work road surface of the present embodiment, is formed by by the basic unit sorted the most successively, bearing bed and surface layer, its In, basic unit is foundation soil, and bearing bed is graded broken stone layer, and surface layer is permeable brick layer.Its construction method comprises the following steps:
(1) base layer construction: select construction site, according to physical features cleaning surface, construction site soil layer after measurement and positioning, and by soil layer Smooth compacting;
(2) bearing bed construction: with graded broken stone for bearing bed construction material, paves smooth and rolls that to tamp into thickness be 250mm Bearing bed;Described graded broken stone is the cobble using particle diameter to be five kinds of specifications of 5mm, 10mm, 20mm, 40mm, 60mm, by 2:2: The weight ratio mixing of 2:1:1 is compounding and obtains;
(3) water-permeable brick is paved: pours C15 Sand-free permeable concrete basic unit in carrying aspect, the most uniformly paves water-permeable brick;
(4) cementation of fissures: with the cementation of fissures sand cementation of fissures, carry out several times, until gap is full;
(5) maintenance: road surface is closed, more than maintenance 3d under field conditions (factors);
(8) on-the-spot cleaning: road cleaning is clean.
Water-permeable brick described in the present embodiment step (3), is prepared by following methods step:
(1) primary raw material processes
1) building waste aggregate processing: building waste is pulverized and is sieved into the raw material of different-grain diameter, and particle diameter is at 0.1-0.5mm Between as building waste fine powder raw material, particle diameter is as building waste fine aggregate raw material between 0.5-1mm, and particle diameter is at 1- As building waste coarse aggregate raw material between 2.5mm, particle diameter gathers materials raw material as building waste granule between 2.5-5mm, presses Building waste fine powder, building waste fine aggregate, building waste coarse aggregate, building waste granule gather materials by weight for 1:2:2:1 Mixing is compounding, to obtain final product;
2) preparation of slag: by slag pulverize, sieve, control particle diameter at 4mm,;
3) preparation of well as clay fines: by clay pulverize, sieve, control particle diameter at 0.08mm,;
(2) raw material metering
Weigh the raw material of following parts by weight respectively: 10 parts of building waste aggregate, 15 parts of slag, portland cement 13 parts, pottery sand 12 parts, Machine-made Sand 7 parts, well as clay fines 6 parts, cenosphere 5 parts, 4 parts of flyash, pigment 5 parts, 8 parts, 0.8 part water reducer of water;
(3) brickmaking
Step (2) each component raw material is placed in blender mixing, then mixing raw material technique brick machine routinely is carried out Mechanical pressing, prepares adobe, then adobe is placed in curing kilns by after the natural curing of 28 days, prepare described water-permeable brick.
By measuring, the technical performance index of the present embodiment water-permeable brick is: coefficient of permeability: 1.6 × 10-2Cm/s, anti-folding is strong Degree: 4.3MPa, tensile splitting strength: 3.6 MPa, comprcssive strength: 30MPa.
The ultimate principle of the present invention, principal character and advantage have more than been shown and described.Those skilled in the art should Understanding, the present invention is not restricted to the described embodiments, and the simply explanation present invention's described in above-described embodiment and description is former Reason, without departing from the spirit and scope of the present invention, the present invention also has various changes and modifications, these changes and improvements Both fall within scope of the claimed invention.Claimed scope is by appending claims and equivalent circle thereof Fixed.

Claims (9)

1. a permeable tile work road surface, it is characterised in that by the basic unit sorted the most successively, bearing bed and surface layer group Become;Described basic unit is foundation soil, and bearing bed is graded broken stone layer, and surface layer is permeable brick layer.
Permeable tile work road surface the most according to claim 1, it is characterised in that described graded broken stone is that employing particle diameter is The cobble of five kinds of specifications of 5mm, 10mm, 20mm, 40mm, 60mm, mixes compounding by the weight ratio of 2:2:2:1:1 and obtains.
3. according to the arbitrary described permeable tile work road surface of claim 1 or 2, it is characterised in that described bearing bed thickness is 150-300mm。
Permeable tile work road surface the most according to claim 3, it is characterised in that described water-permeable brick is by following parts by weight Component is prepared: building waste aggregate 18-22 part, slag 15-18 part, portland cement 12-15 part, pottery sand 10-12 part, machine Sand 7-10 part processed, well as clay fines 5-7 part, cenosphere 5-7 part, flyash 3-5 part, pigment 3-5 part, water 6-8 part, 0.5-1 part Water reducer.
Permeable tile work road surface the most according to claim 4, it is characterised in that described building waste aggregate is by building waste Fine powder, building waste fine aggregate, building waste coarse aggregate, building waste granule gather materials by weight compounding for 1:2:2:1 mixing And obtain;The particle diameter of described building waste fine powder is 0.1-0.5mm, and the particle diameter of building waste fine aggregate is 0.5-1mm, building waste The particle diameter of coarse aggregate is 1-2.5mm, and the particle diameter that building waste granule gathers materials is 2.5-5mm.
Permeable tile work road surface the most according to claim 4, it is characterised in that the particle diameter of described slag is 2-4mm;Described The particle diameter of well as clay fines is 0.05-0.1mm.
7. according to the arbitrary described permeable tile work road surface of claim 4-6, it is characterised in that the coefficient of permeability of described water-permeable brick ≥1.5×10-2Cm/s, rupture strength >=4MPa, tensile splitting strength >=3.5 MPa, comprcssive strength >=30MPa.
8. the construction method on permeable tile work road surface as described in claim 1-7 is arbitrary, it is characterised in that include that following sequence walks Rapid:
(1) base layer construction: select construction site, according to physical features cleaning surface, construction site soil layer after measurement and positioning, and by soil layer Smooth compacting;
(2) bearing bed construction: with graded broken stone for bearing bed construction material, pave smooth and roll compacting;
(3) water-permeable brick is paved: casting concrete basic unit in carrying aspect, the most uniformly paves water-permeable brick;
(4) cementation of fissures: with the cementation of fissures sand cementation of fissures, carry out several times, until gap is full;
(5) maintenance: road surface is closed, more than maintenance 3d under field conditions (factors);
(8) on-the-spot cleaning: road cleaning is clean.
The construction method on permeable tile work road surface the most according to claim 8, it is characterised in that in step (3), described mixed Solidifying soil uses C15 Sand-free permeable concrete.
CN201610744231.2A 2016-08-29 2016-08-29 A kind of permeable tile work road surface and construction method thereof Pending CN106284019A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610744231.2A CN106284019A (en) 2016-08-29 2016-08-29 A kind of permeable tile work road surface and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610744231.2A CN106284019A (en) 2016-08-29 2016-08-29 A kind of permeable tile work road surface and construction method thereof

Publications (1)

Publication Number Publication Date
CN106284019A true CN106284019A (en) 2017-01-04

Family

ID=57677200

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610744231.2A Pending CN106284019A (en) 2016-08-29 2016-08-29 A kind of permeable tile work road surface and construction method thereof

Country Status (1)

Country Link
CN (1) CN106284019A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107021700A (en) * 2017-04-13 2017-08-08 越艳 Concrete regenerating component containing building waste aggregate and preparation method thereof
CN108623257A (en) * 2018-05-23 2018-10-09 柳州紫荆生态工程科技有限公司 A method of utilizing building waste permeable pavement material
CN109734365A (en) * 2019-03-08 2019-05-10 重庆亲禾生态环境科技有限公司 A kind of concrete imitation Stone brick and preparation method thereof
CN110482961A (en) * 2019-09-18 2019-11-22 深圳市嘉达高科产业发展有限公司 A kind of building waste water-permeable brick and preparation method thereof
CN110790560A (en) * 2019-11-28 2020-02-14 贵州筑信达创科技有限公司 Permeable sidewalk and construction method thereof
CN113550191A (en) * 2020-04-24 2021-10-26 国川国际建设有限公司 Outdoor ground and laying method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100888883B1 (en) * 2008-09-04 2009-03-17 신보로드주식회사 Paving structure and method with block
CN101864716A (en) * 2010-07-13 2010-10-20 深圳市绿发鹏程环保科技有限公司 Pavior brick produced by utilizing building wastes and preparation method thereof
CN103352407A (en) * 2013-07-09 2013-10-16 宏盛建业投资集团有限公司 Construction process of roadbed structure with sand-based water-permeable bricks
CN104628346A (en) * 2015-02-02 2015-05-20 深圳市华威环保建材有限公司 Recycled aggregate ecological water permeable brick and production method thereof
CN104860593A (en) * 2015-05-13 2015-08-26 刘勇 Construction waste recycled aggregate water milled colorful paving brick and preparation method thereof
CN105819765A (en) * 2016-03-16 2016-08-03 广州世正环保科技发展有限公司 Water retaining and water permeable brick prepared from construction wastes and manufacturing method thereof
CN105884282A (en) * 2016-04-21 2016-08-24 江苏工程职业技术学院 Energy-saving water permeable bricks and preparation process thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100888883B1 (en) * 2008-09-04 2009-03-17 신보로드주식회사 Paving structure and method with block
CN101864716A (en) * 2010-07-13 2010-10-20 深圳市绿发鹏程环保科技有限公司 Pavior brick produced by utilizing building wastes and preparation method thereof
CN103352407A (en) * 2013-07-09 2013-10-16 宏盛建业投资集团有限公司 Construction process of roadbed structure with sand-based water-permeable bricks
CN104628346A (en) * 2015-02-02 2015-05-20 深圳市华威环保建材有限公司 Recycled aggregate ecological water permeable brick and production method thereof
CN104860593A (en) * 2015-05-13 2015-08-26 刘勇 Construction waste recycled aggregate water milled colorful paving brick and preparation method thereof
CN105819765A (en) * 2016-03-16 2016-08-03 广州世正环保科技发展有限公司 Water retaining and water permeable brick prepared from construction wastes and manufacturing method thereof
CN105884282A (en) * 2016-04-21 2016-08-24 江苏工程职业技术学院 Energy-saving water permeable bricks and preparation process thereof

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
住房和城乡建设部工程质量安全监管司等: "《土木建筑国家级工法汇编(2005-2006年度)中册》", 31 May 2009, 中国建筑工业出版社 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107021700A (en) * 2017-04-13 2017-08-08 越艳 Concrete regenerating component containing building waste aggregate and preparation method thereof
CN108623257A (en) * 2018-05-23 2018-10-09 柳州紫荆生态工程科技有限公司 A method of utilizing building waste permeable pavement material
CN109734365A (en) * 2019-03-08 2019-05-10 重庆亲禾生态环境科技有限公司 A kind of concrete imitation Stone brick and preparation method thereof
CN110482961A (en) * 2019-09-18 2019-11-22 深圳市嘉达高科产业发展有限公司 A kind of building waste water-permeable brick and preparation method thereof
CN110790560A (en) * 2019-11-28 2020-02-14 贵州筑信达创科技有限公司 Permeable sidewalk and construction method thereof
CN113550191A (en) * 2020-04-24 2021-10-26 国川国际建设有限公司 Outdoor ground and laying method thereof
CN113550191B (en) * 2020-04-24 2023-02-24 国川国际建设有限公司 Outdoor ground and laying method thereof

Similar Documents

Publication Publication Date Title
CN106284019A (en) A kind of permeable tile work road surface and construction method thereof
CN106365553A (en) Water-permeable brick and preparation method thereof, and pavement construction technique
CN107226648B (en) Diamond dust tailing composite sand-based ecological water permeable brick and preparation method thereof
CN106187004B (en) A kind of ecological permeable concrete and preparation method thereof
CN100453499C (en) Outdoor ceramic permeable brick and preparation method thereof
CN102249615B (en) Manufacture method for highly antifreezing concrete permeable bricks with ceramic waste as aggregates
CN105218003A (en) A kind of outdoor ceramic permeable brick and preparation method thereof
CN105753504A (en) Ceramic water permeable brick produced by utilizing ceramic waste material and straw and preparation method for ceramic water permeable brick
CN101182172A (en) High-strength high-water-permeability concrete and preparation method thereof
CN106245482A (en) A kind of construction technology on water-permeable brick road surface
CN106400639A (en) Permeable brick pavement and construction technology thereof
CN105544337A (en) Road construction method
CN112142416A (en) Permeable concrete with recycled aggregate from household garbage incinerator slag and preparation method thereof
CN106365554A (en) Novel water-permeable brick and pavement construction method thereof
CN110510960A (en) A kind of novel nucleus nanometer enhancing pervious concrete and its prepare forming method
KR100755202B1 (en) Pavement for using first class reproduction aggregate and fabrication method thereof
JP4456984B2 (en) Water-retaining concrete member
CN106348692A (en) Pavement construction method for environment-friendly water-permeable bricks
CN107986742B (en) Water-permeable and water-retaining material and preparation method thereof
CN110171943A (en) A kind of sponge city pavement water-permeable brick and preparation method thereof
JP6617043B2 (en) Construction method of drainage pavement
CN106242609A (en) A kind of preparation method of mine tailing flint clay water-permeable brick
JP2003306361A (en) Strength improving agent for cement hardened body and cement hardened body obtained by blending the strength improving agent
KR101616273B1 (en) Bottom ash to the main material for a eco-friendly composition permeable block
CN102180637A (en) Process method for producing ceramic water-permeable brick by using phosphogypsum

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20170104

WD01 Invention patent application deemed withdrawn after publication