CN106088623A CN201610613135.4A CN201610613135A CN106088623A CN 106088623 A CN106088623 A CN 106088623A CN 201610613135 A CN201610613135 A CN 201610613135A CN 106088623 A CN106088623 A CN 106088623A
Authority
CN
China
Prior art keywords
flooring
autocrane
roofing
building structure
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610613135.4A
Other languages
Chinese (zh)
Inventor
应潇斐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI MUNICIPAL CONSTRUCTION Co Ltd
Original Assignee
SHANGHAI MUNICIPAL CONSTRUCTION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI MUNICIPAL CONSTRUCTION Co Ltd filed Critical SHANGHAI MUNICIPAL CONSTRUCTION Co Ltd
Priority to CN201610613135.4A priority Critical patent/CN106088623A/en
Publication of CN106088623A publication Critical patent/CN106088623A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples
    • B66C23/78Supports, e.g. outriggers, for mobile cranes

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The construction method of lifting implemented by the flooring utilizing building structure of the present invention or roofing, relates to technical field of building construction.Hang less economical for existing tower crane and self-control room/flooring or implement difficulty greatly, and the problem that effective utilization of autocrane is restricted.Construction method is as follows: according to model and the structural drawings of selected autocrane, the supporting leg of described autocrane is arranged in the center implementation lifting operation of the structural column of described building structure flooring or roofing.

Description

Utilize flooring or the construction method of roofing enforcement lifting of building structure
Technical field
The present invention relates to technical field of building construction, utilize autocrane at the flooring of building structure particularly to a kind of Or the construction method of roofing enforcement lifting operation.
Background technology
In building construction process, it is often necessary to flooring or roofing in building structure carry out lifting operation.At present, more Commonly utilize tower crane, self-control room/flooring to hang enforcement lifting operation, or below Hoisting Position, set up full framing prop up The weight of support autocrane, and then utilize autocrane to implement lifting operation.But, the lift heavy of tower crane is less, as met Heavier article, need multiple stage tower crane to work simultaneously, and economy is the best;Self-control room/flooring hangs the technology people needing construction enterprises Member possesses certain structurally and mechanically designed capacity, but not every construction enterprises all of a design such that ability;Full hall Setting up of support, needs to consume plenty of time, manpower and material, and work efficiency is low, and, at some in particular cases, as Some floor is in backing positions existing device installation, the water-retention of bottom cistern, thus cannot set up support;It addition, The hoisting weight of autocrane is big, although the reliability of himself is secure, but himself is plus the gross weight one after lift heavy As exceed the bearing capacity of building structure flooring or roofing, thus limit effective utilization of autocrane.
Therefore, how to design a kind of simple and easy to do, economical and practical hanging method, be that those of ordinary skill in the art need badly Solve the technical problem that.
Summary of the invention
Hang less economical for existing tower crane and self-control room/flooring or implement difficulty greatly, and effective profit of autocrane By the problem being restricted again.It is an object of the invention to provide a kind of flooring utilizing building structure or executing of lifting implemented by roofing Work method, is arranged on the supporting leg of autocrane on the structural column of building structure flooring or roofing and realizes lifting operation, construction Convenient and swift, economic benefit is good, effectively reduces technology difficulty of construction, saves a large amount of manpower and materials and ensure that construction peace Entirely.
The technical solution adopted for the present invention to solve the technical problems is: according to model and the structure of selected autocrane Drawing, is arranged in the center implementation lifting of the structural column of described building structure flooring or roofing by the supporting leg of described autocrane Operation.
Preferably, between the supporting leg and described structural column of described autocrane, it is also provided with cushion block.
Preferably, described cushion block is made up of timber or steel.
Preferably, the concreting that described structural column is more than or equal to C30 by strength grade forms.
Effect of the invention is that: in existing lifting operation, owing to building structure is held by those of ordinary skill in the art Load power and the deficiency of autocrane self understanding, thinking is confined to utilize the enforcement liftings such as tower crane, self-control room/flooring hang for a long time Operation, or below Hoisting Position, set up full framing to support autocrane, thus limit having of autocrane Effect utilizes, and the construction method of lifting implemented by the flooring utilizing building structure of the present invention or roofing, propping up autocrane Lower limb is arranged on the structural column of building structure flooring or roofing, makes full use of the bearing capacity of structural column self and autocrane Crane capacity realizes lifting operation, it is not necessary to check the bearing capacity of structural column, convenient and quick construction, it is not necessary to multiple stage tower crane, economic effect Benefit is good, it is not necessary to construction enterprises' designed, designed building/roofing hangs, and effectively reduces technology difficulty of construction, props up without setting up full hall Frame, saves a large amount of manpower and materials and ensure that construction safety.
Accompanying drawing explanation
Fig. 1 is the flooring of the building structure of one embodiment of the invention or roofing and the showing of automobile crane supporting leg position relationship It is intended to.
Detailed description of the invention
The flooring of building structure or roofing is utilized to implement to hang proposition of the present invention below in conjunction with the drawings and specific embodiments The construction method of dress is described in further detail.According to following explanation and claims, advantages and features of the invention will more Clear.It should be noted that, accompanying drawing all uses the form simplified very much and all uses non-ratio accurately, only in order to convenient, distinct Ground aids in illustrating the purpose of the embodiment of the present invention.
As a example by the present embodiment lifting operation in certain building construction process, this building side is for setting up full framing Position existing device installation, and, this building bottom cistern water-retention, therefore cannot set up full framing, for solving The certainly lifting problem of autocrane, illustrates the construction utilizing the flooring of building structure or roofing to implement lifting below in conjunction with Fig. 1 Method, specifically comprises the following steps that
Model according to selected autocrane and structural drawings, be arranged in building structure the supporting leg 3 of autocrane Flooring or the center implementation lifting operation of roofing 1 structural column 2.
Above-mentioned automobile crane supporting leg 3 and structural column 2 force analysis are as follows: according to " Code for design of concrete structures " (GB Computational methods 50010-2010) recorded, calculating the maximum support reaction design load of automobile crane supporting leg 3 is 294kN;Secondly, The bearing capacity of computation structure post 2, the bearing capacity of structural column 2 calculates according to equation below one:
Wherein, NdThe bearing capacity of structural column
The coefficient of stability of reinforced concrete member
fcThe comprcssive strength design load of structural column concrete
The sectional area of A structural column
f'yThe strength failure criterion of longitudinal regular reinforcement in structural column
A'sThe area of section of the most longitudinal regular reinforcement in structural column
In the present embodiment, structural column 2 uses C30 concreting to form, the comprcssive strength design load of structural column concrete fc=14.3MPa;The sectional area A=360000mm of structural column2;The strength failure criterion f' of longitudinal regular reinforcement in structural columny= 360MPa;The area of section A' of the most longitudinal regular reinforcement in structural columns=12 × 0.25 × π × 282=7389mm2;Structural column 2 height 5.5m, calculate its length lo=1.25 × 5.5=6.9m, structural column 2 length of side 600mm, then the corresponding reinforcing bar of structural column 2 mixes The coefficient of stability of solidifying soil componentThe bearing capacity N of structural column 2 is calculated by above-mentioned formula oned=0.9 × 0.95 × (14.3 × 360000+360 × 7389)=6676kN, it is seen then that calculate the bearing capacity N of structural column 2dAnti-more than maximum Power design load 294kN, the bearing capacity of this embodiment explanation structural column 2 is typically much deeper than the outrigger reaction of autocrane, typically Without calculation review.
To sum up, in existing lifting operation, owing to building structure bearing capacity and automobile are risen by those of ordinary skill in the art The deficiency of heavy-duty machine self understanding, thinking is confined to utilize tower crane, make the enforcement lifting operations such as room/flooring hangs by oneself for a long time, or Set up full framing below Hoisting Position to support autocrane, thus limit effective utilization of autocrane, and this The construction method of lifting implemented by the flooring utilizing building structure of invention or roofing, is arranged on by the supporting leg 3 of autocrane and builds On the structural column 2 of building structure flooring or roofing 1, make full use of the bearing capacity of structural column 2 self and the lifting energy of autocrane Power realizes lifting operation, it is not necessary to check the bearing capacity of structural column 2, convenient and quick construction, it is not necessary to multiple stage tower crane, and economic benefit is good Good, it is not necessary to construction enterprises' designed, designed building/roofing hangs, and effectively reduces technology difficulty of construction, without setting up full framing, joint Save a large amount of manpower and materials and ensure that construction safety.
More preferably, in order to avoid the supporting leg 3 of autocrane produces local damage to structural column 2, at supporting leg 3 and structural column Being also provided with cushion block 4 between 2, cushion block 4 can use timber or steel etc. to make, and should not use the fragility such as masonry or concrete Material.
The concreting that said structure post 2 uses strength grade to be more than or equal to C30 forms, to ensure its enough resistance to compression Intensity, the intensity of general structure post can meet above-mentioned condition.
Foregoing description is only the description to present pre-ferred embodiments, not any restriction to the scope of the invention, this Any change that the those of ordinary skill in bright field does according to the disclosure above content, modification, belong to right.

Claims (4)

1. utilize flooring or the construction method of roofing enforcement lifting of building structure, it is characterised in that step is as follows: according to selected The model of autocrane and structural drawings, be arranged in described building structure flooring or roofing by the supporting leg of described autocrane The center implementation lifting operation of structural column.
Construction method the most according to claim 1, it is characterised in that: in supporting leg and the described structure of described autocrane Cushion block it is also provided with between post.
Construction method the most according to claim 2, it is characterised in that: described cushion block is made up of timber or steel.
4. according to the construction method described in any one of claims 1 to 3, it is characterised in that: described structural column is big by strength grade Form in the concreting equal to C30.
CN201610613135.4A 2016-07-29 2016-07-29 Utilize flooring or the construction method of roofing enforcement lifting of building structure Pending CN106088623A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610613135.4A CN106088623A (en) 2016-07-29 2016-07-29 Utilize flooring or the construction method of roofing enforcement lifting of building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610613135.4A CN106088623A (en) 2016-07-29 2016-07-29 Utilize flooring or the construction method of roofing enforcement lifting of building structure

Publications (1)

Publication Number Publication Date
CN106088623A true CN106088623A (en) 2016-11-09

Family

ID=57479463

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610613135.4A Pending CN106088623A (en) 2016-07-29 2016-07-29 Utilize flooring or the construction method of roofing enforcement lifting of building structure

Country Status (1)

Country Link
CN (1) CN106088623A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123607A (en) * 2021-03-31 2021-07-16 中国五冶集团有限公司 Construction method for conveying prefabricated components on floor

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101028910A (en) * 2007-04-11 2007-09-05 三一重工股份有限公司 Front leg of mobile engineering machinery and mobile engineering machinery therewith
CN101068744A (en) * 2004-12-03 2007-11-07 曼尼托沃克起重机德国有限公司 Vehicle crane
CN201305409Y (en) * 2008-12-15 2009-09-09 付涛 Bridge crane
CN101717039A (en) * 2009-12-17 2010-06-02 三一电气有限责任公司 Supporting structure and crane with same
US20130315698A1 (en) * 2012-05-01 2013-11-28 Jay DiSandro Lifting and Mounting Apparatus and Method for a Salt/Sand Spreader
CN204873484U (en) * 2015-08-28 2015-12-16 河南省中原奥起实业有限公司 Road bridge hoist

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101068744A (en) * 2004-12-03 2007-11-07 曼尼托沃克起重机德国有限公司 Vehicle crane
CN101028910A (en) * 2007-04-11 2007-09-05 三一重工股份有限公司 Front leg of mobile engineering machinery and mobile engineering machinery therewith
CN201305409Y (en) * 2008-12-15 2009-09-09 付涛 Bridge crane
CN101717039A (en) * 2009-12-17 2010-06-02 三一电气有限责任公司 Supporting structure and crane with same
US20130315698A1 (en) * 2012-05-01 2013-11-28 Jay DiSandro Lifting and Mounting Apparatus and Method for a Salt/Sand Spreader
CN204873484U (en) * 2015-08-28 2015-12-16 河南省中原奥起实业有限公司 Road bridge hoist

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113123607A (en) * 2021-03-31 2021-07-16 中国五冶集团有限公司 Construction method for conveying prefabricated components on floor

Similar Documents

Publication Publication Date Title
CN106065661B (en) The hanging steel corridor construction engineering method of large span
CN103526949A (en) Lifting and slipping device for wall-attached vertical structure and construction method thereof
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN102080384B (en) Construction method for mounting lifter on top plate of underground parking garage
CN202370234U (en) Tool type elevator hoistway construction platform
CN102777037B (en) Simple and practical hoisting construction method of long-span steel girder
CN204781927U (en) Elevartor shaft formwork and elevartor shaft concrete placement operation platform
CN108468433A (en) A kind of construction tool of workshop metal Roof inner panel
CN202483154U (en) High bearing capacity suspending scaffold
CN209367677U (en) The mobile load distribution device of flooring operation short distance on truck crane
CN204876055U (en) Building foundation
CN105952129A (en) Elevator shaft combined type integral lifting operation platform and construction method thereof
CN106088623A (en) Utilize flooring or the construction method of roofing enforcement lifting of building structure
CN204938802U (en) For the rail supported system of tower crane
CN108331335A (en) A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support
CN205874987U (en) Simply put up bridge crane
CN210013445U (en) Floor edge scaffold fixing mechanism
CN203891442U (en) High-rise elevator shaft template supporting platform
CN208564047U (en) A kind of people's Cargo Lift overhanging aisle platform
CN203794505U (en) Internal climbing steel beam conveying device of internal climbing movable arm tower crane
CN205976394U (en) Convenient low layer construction scaffolding
CN205976396U (en) Portable operation platform that indoor construction and installation used
CN209924409U (en) Wall-attached self-climbing electric lifting platform
CN107313597A (en) Modularization ready-package discharging platform for assembled architecture
CN210976550U (en) Adjustable fastening tool type externally-hung protection frame system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161109