CN106065661B - The hanging steel corridor construction engineering method of large span - Google Patents

The hanging steel corridor construction engineering method of large span Download PDF

Info

Publication number
CN106065661B
CN106065661B CN201610420915.7A CN201610420915A CN106065661B CN 106065661 B CN106065661 B CN 106065661B CN 201610420915 A CN201610420915 A CN 201610420915A CN 106065661 B CN106065661 B CN 106065661B
Authority
CN
China
Prior art keywords
sliding
iii
lifting
lifter
pull
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610420915.7A
Other languages
Chinese (zh)
Other versions
CN106065661A (en
Inventor
郭颖
王占山
窦卫
周建峰
王安鑫
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Construction Co ltd Of China Construction Sixth Engineering Bureau
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd, Third Construction Engineering Co Ltd of China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201610420915.7A priority Critical patent/CN106065661B/en
Publication of CN106065661A publication Critical patent/CN106065661A/en
Application granted granted Critical
Publication of CN106065661B publication Critical patent/CN106065661B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0046Loggias
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of hanging steel corridor construction engineering method of large span, using following steps:1) multiple sliding and lifting devices are set;The shaping of steel superstructure is completed on annex;2) start the lifter of sliding and lifting device, steel superstructure is promoted to the first setting height;3) shaping of first time extension layer steel construction is completed on annex, layer steel structure connection is hung in the lower section of steel superstructure by first time, the lifter of startup sliding and lifting device, steel superstructure is promoted to the second setting height;4) repeat step 3), until completing all lower connections for hanging layer steel construction;5) start the lifter of all sliding and lifting devices, whole hanging steel vestibule Integral synchronous is promoted to mounting design height;6) load push-pull of sliding and lifting device is started, steel vestibule integral slipping is in place.The present invention can complete to transfinite, and high, large span is hanging, lifts the steel corridor construction without reliable hoist point using the operation of annex flooring and load force deficiency, using overall.

Description

The hanging steel corridor construction engineering method of large span
Technical field
The present invention relates to a kind of construction method of steel vestibule, more particularly to a kind of hanging steel corridor construction work of large span Method.
Background technology
With the development of the social economy, people are also being continuously increased and improved for the demand and needs of building, disjunctor is multiple Miscellaneous skyscraper emerges in multitude.Conjoined structure refers generally to be connected with each other by aerial connector between Building two or a few building skyscrapers, Meet architectural image and the requirement using function.Setting on the one hand for the requirement of building function for conjoined structure, can facilitate Contact between two high buildings.Current conjoined structure has good daylighting effect and wide visual field, due to conjoined structure Set, make to have more characteristic in architectural appearance.Disjunctor Construction of Steel Structure method in large span high-altitude mainly includes at present:High altitude bulk Method, slitting (piecemeal) lift-on/lift-off system, Integral Lifting, whole hanging method, cantilever Method for Installation, aerial sliding methed, inverse make Method for Installation etc..
The steel superstructure and lower extension layer steel construction that the Steel corridor of certain synthesis project is mainly formed by connecting by truss Composition.Vestibule integral planar is rectangular, including left and right two parts, and left-hand component is connected with A high buildings, by the knot on floorboard Structure inside points and connected part composition of encorbelmenting, right-hand component is the suspending part that A high buildings and B high buildings link together Point, overhanging portion divides and encorbelmented with inside configuration part while docks, and the overhanging portion of vestibule and part of encorbelmenting are in same plane It is interior L-shaped.Above-mentioned Steel corridor, which belongs to tall abnormity, to transfinite structure, and the maximum span of steel truss is 30m, height 4.4m.It is whole Body hoisting height is 68.63 meters, wherein the cantilever span for part of encorbelmenting is 11.050m, weight is 165 tons, and lifting is without reliable branch Point.Steel superstructure and lower extension all construction weights of layer steel construction are up to 425 tons.The scope of operation of above-mentioned component is in the flooring of podium Carried out on plate, but the floorboard of above-mentioned podium is without the ability for carrying 425 tons.In summary, A high buildings and B high buildings are connected The right overhanging portion being connected together is the hanging steel vestibule of large span, using existing large span high-altitude disjunctor Construction of Steel Structure side Method can not complete the construction of above-mentioned Steel corridor.
The content of the invention
The present invention provides a kind of large span hanging steel corridor construction work to solve technical problem present in known technology Method, the engineering method can complete to transfinite high, large span is hanging, lack the scope of operation, using the operation of annex flooring, floow load power not Enough, the steel corridor construction without reliable hoist point is lifted using overall.
The present invention is adopted the technical scheme that to solve technical problem present in known technology:A kind of large span is hanging Steel corridor construction engineering method, the hanging steel vestibule are connected between A high buildings and B high buildings, the top being mainly formed by connecting by truss Steel construction and lower extension layer steel construction composition, the hanging steel vestibule integral planar are rectangular;The construction uses following steps:
1) sliding and lifting device I and sliding and lifting device are set gradually from the inside to the outside close to the top at B high buildings end in A high buildings Ⅱ;Set and the sliding and lifting device I and the sliding and lifting device II 1 close to the edge of A high buildings in the roof of B high buildings Sliding and lifting device III corresponding to one and sliding and lifting device IV;
The sliding and lifting device I is fixed on the structural column of A high buildings, is provided with the sliding and lifting device I overhanging Sliding and lifting beam I, the sliding and lifting beam I is vertical with the end facade of A high buildings, on the sliding and lifting beam I from outside to inside It is sequentially provided with bearing I, load push-pull I and sliding push rod I, the bearing I to be slidably connected with the sliding and lifting beam I, the push-and-pull The telescopic end of device I is be hinged with the bearing I, and the inner and sliding push rod I of the load push-pull I is hinged, and is pushed away in the sliding Bar I is provided with axially disposed multiple clamps I, and postive stop baffle I is fixed with the sliding and lifting beam I, and the clamp I pushes up It is pressed on the outer face of the postive stop baffle I;Lifter I is fixed with the bearing I;
Overhanging sliding and lifting beam II, the sliding and lifting beam II and A high buildings are provided with the sliding and lifting device II End facade it is vertical, be sequentially provided with from outside to inside on the sliding and lifting beam II bearing II, load push-pull II and sliding push rod II, The bearing II is slidably connected with the sliding and lifting beam II, and the telescopic end of the load push-pull II is be hinged with the bearing II, institute The inner be hinged with the sliding push rod II of load push-pull II is stated, axially disposed multiple cards are provided with the sliding push rod II Plate II, postive stop baffle II is fixed with the sliding and lifting beam II, the top pressure of clamp II is in the outer of the postive stop baffle II On end face;Lifter II is fixed with the bearing II;
The sliding and lifting device III is located at B high building roof edge intermediate region, is set on the sliding and lifting device III There is overhanging sliding and lifting beam III, the sliding and lifting beam III is vertical with the end facade of A high buildings, on the sliding and lifting beam III Bearing III, load push-pull III and sliding pull bar III, the bearing III is sequentially provided with from outside to inside to slide with the sliding and lifting beam III Connection, the telescopic end of the load push-pull III is be hinged with the bearing III, the inner and sliding pull bar III of the load push-pull III It is be hinged, axially disposed multiple clamps III are provided with the sliding pull bar III, are fixed with the sliding and lifting beam III Postive stop baffle III, the tension and compression of clamp III are on the inner face of the postive stop baffle III;Lifting is fixed with the bearing III Device III;
The sliding and lifting device IV is located at the corner region of B high building roofs, the sliding and lifting device IV include with Roofing slab affixed lifting beam I and lifting beam II, the lifting beam I is stretched out along the direction vertical with B high building side elevations, described to carry The side elevation stretching that beam II is inclined to B high buildings is risen, sliding is fixed with the overhanging end of the lifting beam I and the lifting beam II Beam, the sliding beam are located at outside the side of B high buildings, and the sliding beam is parallel with the side elevation of B high buildings, in the lifting beam I It is affixed with the diagonal brace that is respectively arranged below with of the lifting beam II, the lower end of the diagonal brace and B high buildings;
It is sequentially provided with bearing IV, load push-pull IV and sliding pull bar IV, the bearing IV from outside to inside in the sliding beam It is slidably connected with the sliding beam, the telescopic end of the load push-pull IV is be hinged with the bearing IV, the inner of the load push-pull IV It is be hinged with the sliding pull bar IV, axially disposed multiple clamps IV are provided with the sliding pull bar IV, in the sliding A postive stop baffle IV is fixed with beam, the tension and compression of clamp IV are on the inner face of the postive stop baffle IV;In the bearing Lifter IV is fixed with IV;
The steel superstructure 1-3 operations for forming of the hanging steel vestibule is completed on the roof boarding of annex;
2) lifter I, the lifter II, the lifter III and the lifter IV are started, after shaping The steel superstructure 1-3 of the hanging steel vestibule is promoted to the first setting height;
3) operations for forming of first time extension layer steel construction of the hanging steel vestibule is completed on the roof boarding of annex, then Steel superstructure 1-3 of the layer steel structure connection in the hanging steel vestibule is hung by first time of the hanging steel vestibule after shaping Lower section, start the lifter I, the lifter II, the lifter III and the lifter IV, the vestibule is hanging Partial steel superstructure is promoted to the second setting height;
4) repeat step 3), until completing all lower connections for hanging layer steel construction of the hanging steel vestibule;
5) lifter I, the lifter II, the lifter III and the lifter IV are started, will be whole described Hanging steel vestibule Integral synchronous is promoted to mounting design height;
6) load push-pull I, the load push-pull II, the load push-pull III and the load push-pull IV are started, in the air will be whole The individual hanging steel vestibule integral level progressively sliding in place to the right, makes the right-hand member of the hanging steel vestibule be supported on slip support abutment On, the slip support abutment is fixed on bracket, and the bracket is arranged on the structural column of B high buildings;Then the hanging steel is connected The left end of corridor links together with the permanent structure on A high buildings.
The present invention has the advantages and positive effects of:
One) it is big for hanging steel vestibule overall weight, the problem of podium floorboard load force deficiency, applied using projecting method Work, by several times lifting are further added by the lower mode for hanging layer to high-order layer by layer postpone of lower extension, that is, solve podium floorboard Lack of support The problem of, hoisting weight is added again.The assembled moulding bed that the main assembly of steel construction, welding and paint etc. are operated in flooring is enterprising OK, loose mail lifting can be carried out with tower crane, efficiency of construction is high, and construction quality is easy to ensure.Hanging steel vestibule passes through after integrally being lifted Lengthening sliding pull bar realizes sliding (slip length 1700mm) over long distances;Hanging steel vestibule entirety and right side B high building column oxen Slip support abutment welding on leg, solves the problems, such as steel construction stress deformation.
Two) gradually it is molded by using the roof boarding higher slice block in annex, gradually hangs upside down, and is fallen completing global formation Implement the overall construction method lifted with aerial integral slipping after overall lifting after extension, solve transfinite height (68m), large span and hang Empty steel vestibule lacks the scope of operation, utilizes annex flooring operation, floow load power deficiency, using overall lifting without reliable hoist point Construction difficult problem.Avoid all using bulk-breaking high altitude bulk, reduce the workload of assembly and overhead welding, without large-scale Lifting machine equipment, using the existing equipment in scene with regard to lifting requirements can be met, and solve high-altitude spelling moulding bed and (set up Highly 68.63 meters) the problem of can not setting up, safety, quality risk are reduced, has saved construction cost, reduces difficulty of construction; Amount of high-altitude operation is down to and at least, is advantageous to the field erected safety of steel construction, quality and the control of duration.
Three) using the method construction slid after overall lifting+lifting, by the stress system for taking into full account elevated structure Feature, do not changing structure stress system, the stress ratio of structure and deformation is controlled and advising On the premise of in model allowed band, the multiple sliding and lifting points of reasonable Arrangement, multi-point high-altitude after overall lifting is successfully realized Horizontal direction sliding (skidding distance 1700mm) over long distances.The advantage of the above method is:
1) permanent structure is reasonably utilized, it is with strong points using a variety of lifting erection methods, and combine installation at high altitude, whole Body lifts the characteristics of method in place, synchronous hydraulic lifting so that maximizes the advantages of three kinds of methods.Save man-hour, fee of material, if It is standby to take, and meet many requirements integrally controlled such as construction technology, quality, safety, progress and cost.
2) ultra-large type hydraulic synchronizing lifting construction technology is used, lifting process is fool proof, and component can lifted During optional position locking, any lifter also can adjust individually, and Adjustment precision is high, is effectively improved structure and was lifted The controllability of installation accuracy in journey.Using flexible rigging load-bearing, there is a rational load-bearing suspension centre, hoisting depth is unrestricted.Lifting During component held stationary lifting posture, the high automation degree of equipment of synchronous control accuracy is high, flexible to operation, safety Property it is good, reliability is high, and use is wide, versatile.
3) air translation is guaranteed without moulding bed, the security of hoisting process.Lifting means small volume, from heavy and light, carrying Ability is big, the lifting operation particularly suitable for large-scale component.
4) lift the main temporary structure such as suspension centre to set using agent structure, hydraulic synchronizing lifting dynamic load is minimum in addition Advantage, and the recycling of the lifting special hanger of lifting platform, sliding and lifting platform and different tonnages, can face lifting When facility dosage minimize, be advantageous to construction cost control.
In summary, the present invention passes through lifting means using lifting by several times, the method for hanging upside down overall sliding and lifting after aggravating Extension combination, lifting weight, span and area is improved a lot.By the integral hoisting of steel construction, by work high above the ground Amount is down at least, and hydraulic pressure lift operation absolute time is shorter in addition, can effectively ensure that the overall duration of Steel Structure Installation.Break Current Long-span Cantilever abnormity transfinites the limitation of structural steel corridor construction.
Brief description of the drawings
Fig. 1 is the structural representation that the present invention applies;
Fig. 2 is the schematic diagram of step 1) of the present invention;
Fig. 3-1 is the structural representation for the sliding and lifting device I that the present invention applies;
Fig. 3-2 is the bearing I, load push-pull I and the sliding connection diagram of pull bar I for the sliding and lifting device I that the present invention applies;
Fig. 4 is the structural representation for the sliding and lifting device II that the present invention applies;
Fig. 5 is the structural representation for the sliding and lifting device III that the present invention applies;
Fig. 6-1 is the front view for the sliding and lifting device IV that the present invention applies;
Fig. 6-2 is Fig. 6-1 side view;
Fig. 6-3 is the sliding beam (including sliding beam) for the sliding and lifting device IV that the present invention applies with the vertical view of lower part Figure;
The schematic diagram of Fig. 7 steps 2) of the present invention;
Fig. 8 is the schematic diagram of step 3) of the present invention;
Fig. 9 is the schematic diagram of step 4) of the present invention.
Embodiment
In order to further understand the content, features and effects of the present invention, hereby enumerating following examples, and coordinate accompanying drawing Describe in detail as follows:
Refer to accompanying drawing, a kind of Long-span Cantilever abnormity transfinites structural steel vestibule 1, and the steel vestibule 1 connects A high buildings 2 and B High building 3, the steel superstructure being mainly formed by connecting by truss and lower extension layer steel construction form, and the integral planar of steel vestibule 1 is in Rectangle, including left and right two parts, left-hand component are connected with A high buildings 2, by the gallery structure inside points on the floorboard of A high buildings 2 With connected vestibule encorbelment part composition, right-hand component is the vestibule suspending part that A high buildings 2 and B high buildings 3 link together Point, the vestibule overhanging portion and the vestibule are encorbelmented part L-shaped arrangement in the same plane.Above-mentioned vestibule, which is encorbelmented, is partly The hanging steel vestibule of large span, the hanging steel vestibule are connected between A high buildings 2 and B high buildings 3, are mainly formed by connecting by truss Steel superstructure and lower extension layer steel construction composition, the hanging steel vestibule integral planar of large span are rectangular.
The construction of the above-mentioned hanging steel vestibule of large span uses following steps:
1) 4-1 of sliding and lifting device I is set gradually from the inside to the outside close to the top at the end of B high buildings 3 in A high buildings 2 and lifting is slided The 4-2 of moving device II;Set and the 4-1 of sliding and lifting device I and the lifting close to the edge of A high buildings in the roof of B high buildings 3 The 4-2 of the slide device II one-to-one 4-3 of sliding and lifting device III and the 4-4 of sliding and lifting device IV.
The 4-1 of sliding and lifting device I is fixed on the structural column 5 of A high buildings 2, on the 4-1 of sliding and lifting device I It is vertical with the end facade of A high buildings 2 provided with overhanging sliding and lifting beam I 4-1-1, the 4-1-1 of sliding and lifting beam I, carried described Rise and be sequentially provided with the 4-1-2 of bearing I, the 4-1-3 of load push-pull I and the sliding 4-1-4 of push rod I, the bearing I in sliding beam I from outside to inside 4-1-2 is slidably connected with the 4-1-1 of sliding and lifting beam I, the telescopic end of the 4-1-3 of load push-pull I and the 4-1-2 of bearing I Be hinged, the inner and sliding 4-1-4 of push rod I of the 4-1-3 of load push-pull I is hinged, and is set on sliding push rod I 4-1-4 There is the axially disposed 4-1-6 of multiple clamps I, the 4-1-5 of postive stop baffle I, institute are fixed with the 4-1-1 of sliding and lifting beam I The 4-1-6 top pressures of clamp I are stated on the outer face of the 4-1-5 of postive stop baffle I;Lifter is fixed with the 4-1-1 of bearing I Ⅰ4-1-7。
The overhanging 4-2-1 of sliding and lifting beam II, the sliding and lifting beam II are provided with the 4-2 of sliding and lifting device II 4-2-1 is vertical with the end facade of A high buildings 2, and the 4-2- of bearing II is sequentially provided with from outside to inside on the 4-2-1 of sliding and lifting beam II 2nd, the 4-2-3 of load push-pull II and sliding push rod II 4-2-4, the 4-2-2 of the bearing II and 4-2-1 of sliding and lifting beam II, which is slided, connects Connect, the telescopic end of the 4-2-3 of load push-pull II is hinged with the 4-2-2 of bearing II, the inner of the 4-2-3 of load push-pull II and institute State the sliding 4-2-4 of push rod II to be hinged, the axially disposed 4-2-6 of multiple clamps II be provided with sliding push rod II 4-2-4, The 4-2-5 of postive stop baffle II is fixed with the 4-2-1 of sliding and lifting beam II, the 4-2-6 top pressures of clamp II are described spacing On the 4-2-5 of baffle plate II outer face;The 4-2-7 of lifter II is fixed with the 4-2-2 of bearing II.
The 4-3 of sliding and lifting device III is located at the roof edge intermediate region of B high buildings 3, in the sliding and lifting device III 4-3 is vertical with the end facade of A high buildings 2 provided with overhanging sliding and lifting beam III 4-3-1, the 4-3-1 of sliding and lifting beam III, It is sequentially provided with the 4-3-2 of bearing III, the 4-3-3 of load push-pull III and sliding pull bar from outside to inside on the 4-3-1 of sliding and lifting beam III III 4-3-4, the 4-3-2 of bearing III are slidably connected with the 4-3-1 of sliding and lifting beam III, and the 4-3-3's of load push-pull III stretches Contracting end is hinged with the 4-3-2 of bearing III, and the inner and sliding 4-3-4 of pull bar III of the 4-3-3 of load push-pull III is hinged, The sliding 4-3-4 of pull bar III is provided with the axially disposed 4-3-6 of multiple clamps III, in the 4-3-1 of sliding and lifting beam III On be fixed with the 4-3-5 of postive stop baffle III, the 4-3-6 tension and compression of clamp III are on the inner face of the 4-3-5 of postive stop baffle III; The 4-3-7 of lifter III is fixed with the 4-3-2 of bearing III.
The 4-4 of sliding and lifting device IV is located at the corner region of the roof of B high buildings 3, the 4-4 of sliding and lifting device IV Including lifting beam I 4-4-8 affixed with Roofing slab and the 4-4-9 of lifting beam II, the 4-4-8 of lifting beam I edges and B high building side elevations Vertical direction is stretched out, and the side elevation of the 4-4-9 of the lifting beam II deviation B high buildings 3 stretches out, in the 4-4-8 of lifting beam I and institute State and sliding beam 4-4-1, the sliding beam 4-4-1 are fixed with the 4-4-9 of lifting beam II overhanging end are located at the side of B high buildings 1 Outside, the sliding beam 4-4-1 is parallel with the side elevation of B high buildings 3, in the 4-4-8 of lifting beam I and the 4-4- of the lifting beam II 9 are respectively arranged below with diagonal brace 4-4-10, and the lower end of the diagonal brace 4-4-10 and B high buildings be affixed.
It is sequentially provided with the 4-4-2 of bearing IV, the 4-4-3 of load push-pull IV from outside to inside on the sliding beam 4-4-1 and sliding is drawn Bar IV 4-4-4, the 4-4-2 of bearing IV are slidably connected with the sliding beam 4-4-1, the telescopic end of the 4-4-3 of load push-pull IV It is hinged with the 4-4-2 of bearing IV, the inner and sliding 4-4-4 of pull bar IV of the 4-4-3 of load push-pull IV is hinged, described The sliding 4-4-4 of pull bar IV is provided with the axially disposed 4-4-6 of multiple clamps IV, and one is fixed with the sliding beam 4-4-1 The individual 4-4-5 of postive stop baffle IV, the 4-4-6 tension and compression of clamp IV are on the inner face of the 4-4-5 of postive stop baffle IV;In the branch The 4-4-7 of lifter IV is fixed with IV 4-4-2 of seat;The upper steel knot of the hanging steel vestibule is completed on the roof boarding of annex 6 Structure 1-3 operations for forming.
2) 4-1-7 of lifter I, the 4-2-7 of the lifter II, the 4-3-7 of the lifter III and the lifting are started The 4-4-7 of device IV, the steel superstructure 1-3 of the hanging steel vestibule after shaping is promoted to the first setting height.
3) operations for forming of first time extension layer steel construction of the hanging steel vestibule is completed on the roof boarding of annex 6, so Afterwards steel superstructure of the layer steel structure connection in the hanging steel vestibule is hung by first time of the hanging steel vestibule after shaping 1-3 lower section, start the 4-1-7 of lifter I, the 4-2-7 of the lifter II, the 4-3-7 of the lifter III and the lifting The 4-4-7 of device IV, the steel superstructure of the vestibule overhanging portion is promoted to the second setting height.
4) repeat step 3), until completing all lower connections for hanging layer steel construction of the hanging steel vestibule.
5) 4-1-7 of lifter I, the 4-2-7 of the lifter II, the 4-3-7 of the lifter III and the lifting are started The 4-4-7 of device IV, the whole hanging steel vestibule Integral synchronous is promoted to mounting design height.
6) 4-1-3 of load push-pull I, the 4-2-3 of the load push-pull II, the 4-3-3 of the load push-pull III and the push-and-pull are started The 4-4-3 of device IV, in the air will the whole hanging steel vestibule integral level progressively sliding in place to the right, make the hanging steel vestibule Right-hand member be supported on slip support abutment, the slip support abutment is fixed on bracket, and the bracket is arranged on the structural column of B high buildings 3 On;Then the left end of the hanging steel vestibule is linked together with the permanent structure on A high buildings 2.
Above-mentioned hierarchical block be progressively molded progressively hang down the method lifted can solve the problem that podium floorboard bearing capacity deficiency Problem.In the lifting process of construction cell, need to carry out temperature pier to lifting region rod member to meet overall lifting demand, Offset in lifting and deform caused by weight stress, form it into it is stable overall to be lifted, using prior art, herein no longer Repeat.The structure division that is connected with sliding and lifting device need to carry out it is interim strengthen to meet lifting weight demand, use is existing Technology, it will not be repeated here.
Although the preferred embodiments of the present invention are described above in conjunction with accompanying drawing, the invention is not limited in upper The embodiment stated, above-mentioned embodiment is only schematical, be not it is restricted, this area it is common Technical staff is under the enlightenment of the present invention, in the case where not departing from present inventive concept and scope of the claimed protection, also Many forms can be made, these are belonged within protection scope of the present invention.

Claims (1)

1. a kind of hanging steel corridor construction engineering method of large span, the hanging steel vestibule is connected between A high buildings and B high buildings, mainly The steel superstructure and lower extension layer steel construction being formed by connecting by truss form, and the hanging steel vestibule integral planar is rectangular;Its It is characterised by, the construction uses following steps:
1) sliding and lifting device I and sliding and lifting device II are set gradually from the inside to the outside close to the top at B high buildings end in A high buildings; Set and a pair of the sliding and lifting device I and the sliding and lifting device II 1 close to the edge of A high buildings in the roof of B high buildings The sliding and lifting device III and sliding and lifting device IV answered;
The sliding and lifting device I is fixed on the structural column of A high buildings, and overhanging carry is provided with the sliding and lifting device I Sliding beam I is risen, the sliding and lifting beam I is vertical with the end facade of A high buildings, on the sliding and lifting beam I from outside to inside successively It is slidably connected provided with bearing I, load push-pull I and sliding push rod I, the bearing I with the sliding and lifting beam I, the load push-pull I Telescopic end is be hinged with the bearing I, and the inner and sliding push rod I of the load push-pull I is hinged, on the sliding push rod I Provided with axially disposed multiple clamps I, postive stop baffle I is fixed with the sliding and lifting beam I, the top pressure of clamp I exists On the outer face of the postive stop baffle I;Lifter I is fixed with the bearing I;
Overhanging sliding and lifting beam II, the end of the sliding and lifting beam II and A high buildings are provided with the sliding and lifting device II Facade is vertical, is sequentially provided with bearing II, load push-pull II and sliding push rod II from outside to inside on the sliding and lifting beam II, described Bearing II is slidably connected with the sliding and lifting beam II, and the telescopic end of the load push-pull II is be hinged with the bearing II, described to push away The inner be hinged with the sliding push rod II of device II is drawn, axially disposed multiple clamps are provided with the sliding push rod II II, postive stop baffle II is fixed with the sliding and lifting beam II, the top pressure of clamp II is in the outer end of the postive stop baffle II On face;Lifter II is fixed with the bearing II;
The sliding and lifting device III is located at B high building roof edge intermediate region, is provided with the sliding and lifting device III outer The sliding and lifting beam III stretched, the sliding and lifting beam III is vertical with the end facade of A high buildings, from outer on the sliding and lifting beam III It is slidably connected to interior bearing III, load push-pull III and sliding pull bar III, the bearing III of being sequentially provided with the sliding and lifting beam III, The telescopic end of the load push-pull III is be hinged with the bearing III, and the inner and sliding pull bar III of the load push-pull III is hinged, Axially disposed multiple clamps III are provided with the sliding pull bar III, limiting block is fixed with the sliding and lifting beam III Plate III, the tension and compression of clamp III are on the inner face of the postive stop baffle III;Lifter III is fixed with the bearing III;
The sliding and lifting device IV is located at the corner region of B high building roofs, and the sliding and lifting device IV includes and roof Plate affixed lifting beam I and lifting beam II, the lifting beam I are stretched out along the direction vertical with B high building side elevations, the lifting beam The side elevation of II deviation B high buildings is stretched out, and sliding beam is fixed with the overhanging end of the lifting beam I and the lifting beam II, The sliding beam is located at outside the side of B high buildings, and the sliding beam is parallel with the side elevation of B high buildings, in the lifting beam I and institute The diagonal brace that is respectively arranged below with of lifting beam II is stated, the lower end of the diagonal brace and B high buildings are affixed;
It is sequentially provided with bearing IV, load push-pull IV and sliding pull bar IV, the bearing IV and institute from outside to inside in the sliding beam State sliding beam to be slidably connected, the telescopic end of the load push-pull IV is be hinged with the bearing IV, the inner of the load push-pull IV and institute It is be hinged to state sliding pull bar IV, axially disposed multiple clamps IV are provided with the sliding pull bar IV, in the sliding beam A postive stop baffle IV is fixed with, the tension and compression of clamp IV are on the inner face of the postive stop baffle IV;On the bearing IV It is fixed with lifter IV;
The steel superstructure operations for forming of the hanging steel vestibule is completed on the roof boarding of annex;
2) lifter I, the lifter II, the lifter III and the lifter IV are started, described in after shaping The steel superstructure of hanging steel vestibule is promoted to the first setting height;
3) first time operations for forming for hanging layer steel construction of the hanging steel vestibule is completed on the roof boarding of annex, then will be into First time of the hanging steel vestibule after type hangs layer steel structure connection in the lower section of the vacantly steel superstructure of steel vestibule, Start the lifter I, the lifter II, the lifter III and the lifter IV, by the upper of the hanging steel vestibule Portion's lift up of steel structure is to the second setting height;
4) repeat step 3), until completing all lower connections for hanging layer steel construction of the hanging steel vestibule;
5) lifter I, the lifter II, the lifter III and the lifter IV are started, will be whole described hanging Steel vestibule Integral synchronous is promoted to mounting design height;
6) load push-pull I, the load push-pull II, the load push-pull III and the load push-pull IV are started, in the air by whole institute Hanging steel vestibule integral level progressively sliding in place to the right is stated, the right-hand member of the hanging steel vestibule is supported on slip support abutment, The slip support abutment is fixed on bracket, and the bracket is arranged on the structural column of B high buildings;Then by the hanging steel vestibule Left end links together with the permanent structure on A high buildings.
CN201610420915.7A 2016-06-13 2016-06-13 The hanging steel corridor construction engineering method of large span Active CN106065661B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610420915.7A CN106065661B (en) 2016-06-13 2016-06-13 The hanging steel corridor construction engineering method of large span

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610420915.7A CN106065661B (en) 2016-06-13 2016-06-13 The hanging steel corridor construction engineering method of large span

Publications (2)

Publication Number Publication Date
CN106065661A CN106065661A (en) 2016-11-02
CN106065661B true CN106065661B (en) 2018-03-20

Family

ID=57420644

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610420915.7A Active CN106065661B (en) 2016-06-13 2016-06-13 The hanging steel corridor construction engineering method of large span

Country Status (1)

Country Link
CN (1) CN106065661B (en)

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106437178B (en) * 2016-10-21 2018-08-14 中建八局第三建设有限公司 A kind of multi-storey steel structure vestibule construction method for lifting whole and device
CN106703423A (en) * 2016-12-07 2017-05-24 上海市机械施工集团有限公司 Automatic hovering wind-resistant device for integral lifting of air joint gallery
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor
CN106759845B (en) * 2016-12-29 2019-03-08 上海市机械施工集团有限公司 A kind of construction method of Steel corridor
CN106930541B (en) * 2017-05-10 2020-10-20 中国建筑第二工程局有限公司 Construction method of hanging type steel corridor
CN107012949B (en) * 2017-05-10 2019-06-07 中国建筑第二工程局有限公司 Lifting method of large-span steel corridor
CN107060105B (en) * 2017-05-10 2018-11-13 中国建筑第二工程局有限公司 Lifting construction method for multiple steel galleries between tower buildings
CN108571061A (en) * 2018-03-19 2018-09-25 中建三局基础设施建设投资有限公司 A kind of large public building suspension type shelter bridge structure
CN108532743A (en) * 2018-05-31 2018-09-14 上海建工四建集团有限公司 The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method
CN109826312B (en) * 2019-02-21 2024-03-15 深圳市建筑设计研究总院有限公司 Sectional assembly method of high-rise integrated structure and high-rise integrated structure
CN109989588A (en) * 2019-03-15 2019-07-09 上海建工七建集团有限公司 The installation of steel vestibule is promoted and high-altitude translation device and its installation method with whole
CN109941894A (en) * 2019-03-15 2019-06-28 上海建工七建集团有限公司 Steel vestibule integrally promotes peace and diverts from one use to another the double-deck suspension centre hoisting frame and its installation method
CN109779272A (en) * 2019-03-18 2019-05-21 济南四建(集团)有限责任公司 A kind of high-altitude steel structure corridor construction method
CN110778127A (en) * 2019-11-12 2020-02-11 上海宝冶集团有限公司 In-situ assembling and lifting construction aligning method for multilayer steel truss
CN110777938B (en) * 2019-11-21 2022-05-03 香港华艺设计顾问(深圳)有限公司 Suspension structure for additionally arranging prestressed steel stay cable in steel truss
CN112523357B (en) * 2020-09-04 2022-06-17 浙大城市学院 Steel supporting cylinder-lower hanging type truss system with arc-shaped vertical face and large open hole and application
CN114319576A (en) * 2022-01-17 2022-04-12 深圳嘉西亚建筑设计有限公司 Steel structure corridor structure and hoisting method thereof
CN114541567A (en) * 2022-03-04 2022-05-27 中建八局第二建设有限公司 Construction method for irregular conjoined steel corridor in narrow and small site

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103075025A (en) * 2013-01-30 2013-05-01 中国十九冶集团有限公司 Integral lifting construction method for giant cantilever steel asymmetric structure of high-rise building
CN203559597U (en) * 2013-10-23 2014-04-23 广州建筑股份有限公司 Sliding device convenient to operate
CN103835369A (en) * 2014-03-05 2014-06-04 江苏南通六建建设集团有限公司 Extensible high-altitude conjoined steel structure
CN104060844A (en) * 2014-04-30 2014-09-24 浙江东南网架股份有限公司 Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
JP6059526B2 (en) * 2012-12-18 2017-01-11 積水化学工業株式会社 Existing piping removal device and existing piping removal method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6059526B2 (en) * 2012-12-18 2017-01-11 積水化学工業株式会社 Existing piping removal device and existing piping removal method
CN103075025A (en) * 2013-01-30 2013-05-01 中国十九冶集团有限公司 Integral lifting construction method for giant cantilever steel asymmetric structure of high-rise building
CN203559597U (en) * 2013-10-23 2014-04-23 广州建筑股份有限公司 Sliding device convenient to operate
CN103835369A (en) * 2014-03-05 2014-06-04 江苏南通六建建设集团有限公司 Extensible high-altitude conjoined steel structure
CN104060844A (en) * 2014-04-30 2014-09-24 浙江东南网架股份有限公司 Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof

Also Published As

Publication number Publication date
CN106065661A (en) 2016-11-02

Similar Documents

Publication Publication Date Title
CN106065661B (en) The hanging steel corridor construction engineering method of large span
CN106013419B (en) Long-span Cantilever abnormity transfinites structural steel corridor construction engineering method
CN105201195B (en) One kind can lift supporting leg type elevator hoistway construction platform and construction method
CN204804298U (en) Building material hoist and mount construction scaffold
CN106013453B (en) Long-span Cantilever transfinites structure construction engineering method
CN206487087U (en) A kind of scissor stairs of sectional
CN102251483A (en) Construction method for hoisting concrete-filled steel tube lattice bridge pier through self-lifting attached crane
CN103899093A (en) Step-by-step hoisting construction method of mega-frame steel truss beam
CN103572703A (en) Construction method of outer wrapped concrete obliquely pulling and buckling and ring and section dividing combination method
CN204781927U (en) Elevartor shaft formwork and elevartor shaft concrete placement operation platform
CN202108242U (en) Elevator shaft construction scaffold device constructed and lifted together with a building main structure by layers
CN102777037B (en) Simple and practical hoisting construction method of long-span steel girder
CN202882376U (en) Elevator shaft template support platform
CN208280592U (en) Automatic climbing formula hoistway cylinder mould panel assembly
CN206088946U (en) A integrally lift up displacement device for unsettled steel gallery of large -span
CN203547125U (en) Column type overall steel platform hydraulic creeping formwork
CN105625732B (en) Superelevation overhanging steel structure truss support free construction method
CN204456816U (en) One can promote supporting leg type elevator hoistway construction platform
CN108331335A (en) A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support
CN203684708U (en) Hydraulic multipoint synchronous lifting device
CN206352387U (en) A kind of deformable hoistway operation steel platform of automatic climbing formula
CN205857749U (en) A kind of overall sliding and lifting device of the structure that transfinites for Long-span Cantilever
CN210002935U (en) safety protection shed capable of synchronously lifting along with creeping formwork
CN206267519U (en) A kind of light engine position hydraulic climbing die block system
CN204282796U (en) Collapsible hanging basket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20200323

Address after: 300451 No. 72, Hangzhou Road, Binhai New Area, Tianjin

Co-patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Address before: 300456 No. 75, Xingang Road, Tanggu District, Tianjin

Co-patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION NO.3 CONSTRUCTION ENGINEERING Co.,Ltd.

TR01 Transfer of patent right
CP03 Change of name, title or address

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: No. 72 Hangzhou Road, Tianjin Binhai New Area, 300451

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

CP03 Change of name, title or address
CP01 Change in the name or title of a patent holder

Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau

Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province

Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd.