CN105279580B - Predict that the method and system of the number of external force destructive malfunction occurs for cable - Google Patents

Predict that the method and system of the number of external force destructive malfunction occurs for cable Download PDF

Info

Publication number
CN105279580B
CN105279580B CN201510780476.6A CN201510780476A CN105279580B CN 105279580 B CN105279580 B CN 105279580B CN 201510780476 A CN201510780476 A CN 201510780476A CN 105279580 B CN105279580 B CN 105279580B
Authority
CN
China
Prior art keywords
external force
measure
group
municipal works
cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510780476.6A
Other languages
Chinese (zh)
Other versions
CN105279580A (en
Inventor
徐涛
刘毅刚
徐研
张耿斌
朱妮妮
李艳飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Power Supply Bureau of Guangdong Power Grid Co Ltd
Original Assignee
Guangzhou Power Supply Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Power Supply Bureau Co Ltd filed Critical Guangzhou Power Supply Bureau Co Ltd
Priority to CN201510780476.6A priority Critical patent/CN105279580B/en
Publication of CN105279580A publication Critical patent/CN105279580A/en
Application granted granted Critical
Publication of CN105279580B publication Critical patent/CN105279580B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to the method and systems that the number of external force destructive malfunction occurs for a kind of prediction cable, this method comprises: obtaining the other municipal works initial data of setting group at least nearest two unit time and determining the weight of every group of original project data of municipal administration to be fitted to obtain municipal works amount curve according to municipal works initial data;The other anti-external force of setting group at least nearest two unit time is obtained to destroy measure initial data and determine that every group of anti-external force destroys the weight of measure and destroys measure curve to be fitted to obtain anti-external force according to anti-external force destruction measure initial data;Measure curve, which is destroyed, according to municipal works amount curve and anti-external force obtains cable external force damage curve;The current failure number of cable current one time generation external force destructive malfunction is obtained, and predicts that the number of external force destructive malfunction occurs for next unit time cable according to current failure number and cable external force damage curve.This method intuitively predicts that the number of destructive malfunction occurs for next unit time.

Description

Predict that the method and system of the number of external force destructive malfunction occurs for cable
Technical field
The present invention relates to power cable faults to predict field, and external force destructive malfunction occurs more particularly to a kind of prediction cable Number method and system.
Background technique
Research about cable external force destructive malfunction is largely divided into two parts: the reason of cable external force destructive malfunction occurs The research inquired into and anti-external force how to be taken to destroy measure.
(1) it is directed to the research of cable external force destructive malfunction occurrence cause
The reason of cable external force is destroyed research is segmented into 3 classes, and the first kind is to influence cable external force for human factor to break Research in terms of bad failure, predominantly power grid operation management personnel tour are not in place to be caused to find defect, Jin Eryin in time The cable external force destructive malfunction risen;Second class is that non-construction personnel realizes weakness to cable protection, and especially construction personnel is applying Working hour ignores the protection etc. of cable;Third class is the research for the unreasonable aspect of work progress method;Predominantly for construction Research in terms of environmental problem, such as the construction unknown cable distribution figure given such as power department in path do not timely update and cause Half-hearted inspection information blindly goes into operation before cable digging injury, construction and construction unit go into operation.
(2) it is directed to the research in terms of taking anti-external force destruction measure
Mainly there are reinforcement power grid operation management personnel to make an inspection tour dynamics, increase electricity currently, anti-external force destroys taken measure The propaganda strength of power cable importance reinforces construction site cable and effectively indicate, reinforces and units concerned's communication, timely update electricity Cable GIS figure etc..
And the research of the number about prediction cable generation external force destructive malfunction is seldom, existing research is also difficult to intuitive Predict that the number of external force destructive malfunction occurs for cable.
Summary of the invention
Based on this, it is necessary to the method and system of the number of external force destructive malfunction occur for intuitive prediction cable.
A method of the number of external force destructive malfunction occurs for prediction cable, comprising:
Obtain the other municipal works initial data of setting group at least nearest two unit time and according to municipal works Initial data determines the weight of every group of municipal works data to be fitted to obtain municipal works amount curve;
It obtains the other anti-external force of the setting group at least nearest two unit time and destroys measure initial data and according to anti- External force destroys measure initial data and determines that every group of anti-external force destroys the weight of measure to be fitted to obtain anti-external force destruction and arrange Apply curve;
Measure curve, which is destroyed, according to municipal works amount curve and anti-external force obtains cable external force damage curve;
The current failure number of cable current one time generation external force destructive malfunction is obtained, and according to current failure number And cable external force damage curve predicts that the number of external force destructive malfunction occurs for next unit time cable.
In a kind of wherein embodiment, the other municipal works of setting group obtained at least nearest two unit time are former Beginning data simultaneously determine the weight of every group of municipal works data according to municipal works initial data to be fitted to obtain municipal works Measure curve the step of include:
The other municipal works initial data of setting group at least two unit time is obtained, and according to the other relationship of each group Municipal works initial data is classified to obtain the municipal works classification data of corresponding classification;
Municipal works classification data is carried out including and normalized obtains the normalization of the other municipal works of each group Numerical value;
The growth rate of the other municipal works of each group is calculated according to municipal works initial data to obtain municipal works of all categories The weight of data;
It is determined according to the ratio of the growth rate of the other municipal works of each group in municipal works of all categories each under the category The weight of the other municipal works data of group;
It is fitted according to the normalization numerical value of the other municipal works of each group and the weight of the other municipal works data of each group Obtain municipal works amount curve.
In a kind of wherein embodiment, obtains the other anti-external force destruction of setting group at least nearest two unit time and arrange It applies initial data and measure initial data is destroyed according to anti-external force and determine that every group of anti-external force destroys the weight of measure initial data To be fitted to obtain the step of anti-external force destroys measure curve are as follows:
It obtains each other anti-external force of setting group at least nearest two unit time and destroys measure, and according to measure effect pair Each anti-external force of group destroys measure and scores to obtain the anti-external force of each group and destroy measure initial data;
Anti- external force the classification of measure original number is destroyed according to the other relationship of each group to destroy with the anti-external force for obtaining corresponding classification Measure classification data;
Measure classification data is destroyed to anti-external force to carry out destroying measure processing comprising processing to obtain the anti-external force of each group Data;
Measure process data, which is destroyed, according to anti-external force calculates the growth rate of the other anti-external force safeguard measure of each group to obtain respectively The anti-external force of classification destroys the weight of measure;
The ratio for the growth rate for destroying measure according to the other anti-external force of each group in anti-external force destruction measure of all categories determines The other anti-external force of each group under the category destroys the weight of measure;
The weight that measure process data destroys measure with the other anti-external force of each group is destroyed according to anti-external force to be fitted to obtain Anti- external force destroys measure curve.
In a kind of wherein embodiment, the current failure of cable current one time generation external force destructive malfunction is obtained Number, and predict that external force destructive malfunction occurs for next unit time cable according to current failure number and cable external force damage curve Number the step of include:
Obtain the current failure number of cable current one time generation external force destructive malfunction;
Correspondence numerical value in the cable external force damage curve of current one time is compared with current failure number To ratio;
Next unit time is predicted with ratio according to the correspondence numerical value in the cable external force damage curve of next unit time The number of inner cable generation external force destructive malfunction.
In a kind of wherein embodiment, formula used by normalized are as follows:
Wherein, x' indicates that the numerical value after normalization, X indicate to need normalized array, and x indicates to normalize in array X Numerical value before.
The present invention also provides the systems that the number of external force destructive malfunction occurs for a kind of prediction cable, comprising:
Municipal works amount curve generation module, for obtaining the other municipal administration of setting group at least nearest two unit time Engineering initial data simultaneously determines the weight of every group of municipal works data according to municipal works initial data to be fitted to obtain city Political affairs project amount curve;
Anti- external force destroys measure curve generation module, other for obtaining the setting group at least nearest two unit time Anti- external force, which destroys measure initial data and destroys measure initial data according to anti-external force, determines that every group of anti-external force destroys measure Weight destroys measure curve to be fitted to obtain anti-external force;
Cable external force damage curve generation module is obtained for destroying measure curve according to municipal works amount curve and anti-external force To cable external force damage curve;
The current failure number of external force destructive malfunction, and root occur for obtaining the cable current one time for prediction module Predict that the number of external force destructive malfunction occurs for next unit time cable according to current failure number and cable external force damage curve.
In a kind of wherein embodiment, municipal works amount curve generation module includes:
First taxon, for obtaining the other municipal works initial data of the setting group at least two unit time, And municipal works initial data is classified to obtain the municipal works classification data of corresponding classification according to each group other relationship;
First data processing unit, for carrying out including to municipal works classification data and normalized obtains each group The normalization numerical value of other municipal works;
First weight calculation unit, for calculating the growth rate of the other municipal works of each group according to municipal works initial data To obtain the weight of municipal works data of all categories;
Second weight calculation unit, for according to the growth rate of the other municipal works of each group in municipal works of all categories Ratio determines the weight of the other municipal works data of each group under the category;
Municipal works amount curve generation unit, for other according to the normalization numerical value and each group of the other municipal works of each group The weight of municipal works data is fitted to obtain municipal works amount curve.
In a kind of wherein embodiment, anti-external force destroys measure curve generation module and includes:
Acquiring unit destroys measure for obtaining each other anti-external force of setting group at least nearest two unit time, and Measure is destroyed to the anti-external force of each group according to measure effect to score to obtain the anti-external force of each group and destroy measure initial data;
Second taxon, for anti-external force to be destroyed the classification of measure original number to be corresponded to according to the other relationship of each group The anti-external force of classification destroys measure classification data;
Second data processing unit is carried out comprising processing for destroying measure classification data to anti-external force to obtain each group Not anti-external force destroys measure process data;
Third weight calculation unit calculates the other anti-external force protection of each group for destroying measure process data according to anti-external force The growth rate of measure is to obtain the weight that anti-external force of all categories destroys measure;
4th weight calculation unit, for being arranged according to the other anti-external force destruction of each group in anti-external force destruction measure of all categories The ratio for the growth rate applied determines that the other anti-external force of each group under the category destroys the weight of measure;
Anti- external force destroys measure curve generation unit, other anti-with each group for destroying measure process data according to anti-external force The weight that external force destroys measure is fitted to obtain anti-external force destruction measure curve.
In a kind of wherein embodiment, prediction module includes:
The current failure of external force destructive malfunction occurs for obtaining the cable current one time for number of stoppages acquiring unit Number;
Comparing unit, for the correspondence numerical value and current failure in the cable external force damage curve by the current one time Number is compared to obtain ratio;
Predicting unit is predicted for the correspondence numerical value in the cable external force damage curve according to next unit time with ratio The number of external force destructive malfunction occurs for next unit time inner cable.
In a kind of wherein embodiment, formula used by normalized are as follows:
Wherein, x' indicates that the numerical value after normalization, X indicate to need normalized array, and x indicates to normalize in array X Numerical value before.
The prediction cable occur external force destructive malfunction number method, by obtain history municipal works data and Anti- external force destroys measure initial data and obtains cable external force damage curve, and external force destructive malfunction occurs according to the current one time Number and cable external force damage curve predict that the number of destructive malfunction occurs for next unit time.This method passes through obtained electricity Cable external force damage curve can intuitively predict that the number of destructive malfunction occurs for next unit time, and data are history number According to, the efficacy data of measure is destroyed including municipal engineering construction and anti-external force, so as to balanced economy and validity it Between relationship, the construction for destroying measure to municipal works and anti-external force has directive significance.
Detailed description of the invention
Fig. 1 is the flow chart for the method that the number of external force destructive malfunction occurs for a kind of prediction cable of embodiment;
Fig. 2 is the flow chart of a kind of method for obtaining municipal works amount curve of embodiment;
Fig. 3 is a kind of flow chart for obtaining anti-external force and destroying the method for measure curve of embodiment;
Fig. 4 is a kind of embodiment according to current failure number and cable external force damage curve prediction next unit time The flow chart of the method for the number of external force destructive malfunction occurs for cable;
Fig. 5 is the functional module signal for the system that the number of external force destructive malfunction occurs for a kind of prediction cable of embodiment Figure.
Specific embodiment
A method of the number of external force destructive malfunction occurs for prediction cable, as shown in Figure 1, comprising:
S10: the other municipal works initial data of setting group at least nearest two unit time is obtained and according to municipal administration Engineering initial data determines the weight of every group of municipal works data to be fitted to obtain municipal works amount curve.
In the present embodiment, the unit time is year, and in other embodiments, the unit time can be the moon or season Degree.
Set the other municipal works of group include: link length (unit is kilometer), path area (unit be square kilometre), Bridge number (unit is a), bridge number-viaduct (unit is a), drainage pipeline length (unit is kilometer), water supplying pipe road length Spend (unit is kilometer), greening area coverage (unit is hectare), greening area coverage-built-up areas (unit is hectare), greenery patches Area (unit is hectare), greenery area-built-up areas (unit is hectare), park greenbelt (unit is hectare) and park face Product (unit is hectare).
It obtains above-mentioned group of other municipal works initial data at least in two years and is determined according to municipal works initial data The weight of every group of municipal works data is to obtain municipal works amount curve.
S30: it obtains the other anti-external force of the setting group at least nearest two unit time and destroys measure initial data and root Measure initial data, which is destroyed, according to anti-external force determines that every group of anti-external force is destroyed the weight of measure and broken to be fitted to obtain anti-external force Bad measure curve.
Common anti-external force, which destroys measure, mainly setting warning sign, personnel's tour etc., and anti-external force destroys measure original number According to destroying with anti-external force, the effect of measure is related, and by scoring measure application, it is former that available anti-external force destroys measure Beginning data, anti-external force destroy measure initial data and includes: the anti-external force of road area destroys measure application effect overall score, and (unit is Point), the anti-external force in bridge area destroys measure application effect overall score (unit is point), the anti-external force in bridge _ viaduct region is destroyed Measure application effect overall score (unit be point), the anti-external force in drainage pipeline region destroy measure application effect overall score, and (unit is Point), the anti-external force in water supply line region destroy measure application effect overall score (unit is point), the greening anti-external force in area coverage region Destruction measure application effect overall score (unit is point), greening area coverage _ build up the anti-external force destruction measure application effect of region Fruit overall score (unit is point), the anti-external force in greenery area region destroy measure application effect overall score (unit is point), greenery patches face It is broken accumulate _ to build up the anti-external force destruction measure application effect overall score of region (unit is point), the anti-external force in park greenbelt region Bad measure application effect overall score (unit is point) and the anti-external force of park surface area destroy measure application effect overall score (unit To divide).
The above-mentioned group of other anti-external force obtained at least in two years destroys measure initial data and destroys measure according to anti-external force Initial data determines that every group of anti-external force destroys the weight point of measure and destroys measure curve to obtain anti-external force.
S50: measure curve is destroyed according to municipal works amount curve and anti-external force and obtains cable external force damage curve.
Cable external force damage curve is obtained specifically, municipal works amount curve is subtracted anti-external force and destroys measure curve.
S70: the current failure number of cable current one time generation external force destructive malfunction is obtained, and according to current failure Number and cable external force damage curve predict that the number of external force destructive malfunction occurs for next unit time cable.
In the present embodiment, current failure number is the number for current year external force destructive malfunction occurring, next unit time The number that external force destructive malfunction occurs for next year cable for the number of external force destructive malfunction occurs for inner cable.
The prediction cable occur external force destructive malfunction number method, by obtain history municipal works data and Anti- external force destroys measure initial data and obtains cable external force damage curve, and external force destructive malfunction occurs according to the current one time Number and cable external force damage curve predict that the number of destructive malfunction occurs for next unit time.This method passes through obtained electricity Cable external force damage curve can intuitively predict that the number of destructive malfunction occurs for next unit time, and data are history number According to, the efficacy data of measure is destroyed including municipal engineering construction and anti-external force, so as to balanced economy and validity it Between relationship, the construction for destroying measure to municipal works and anti-external force has directive significance.
Specifically, as shown in Fig. 2, step S10 is specifically included:
S11: the other municipal works initial data of setting group at least two unit time is obtained, and other according to each group Relationship classifies municipal works initial data to obtain the municipal works classification data of corresponding classification.
Municipal works initial data other for the setting group of acquisition, according to the other relationship of each group by municipal works original number According to classification, for example, the long road of road and path area are all related with road, the long circuit-switched data of road can be classified as with path area data It is a kind of.In a specific embodiment, above-mentioned 12 groups of municipal works data can be divided into five classes, be respectively as follows: 1st class: link length and path area;2nd class: bridge number and viaduct number;3rd class: drainage pipeline length and water supply line Length;4th class: greening area coverage, greening area coverage built-up areas, greenery area and greenery area built-up areas;5th class: public Garden greenery area and park area.
Setting at least nine unit time is obtained in a kind of specific embodiment for the accuracy for improving prediction Surely other municipal works initial data is organized, for example, in one embodiment, obtaining 2000 to the 2013 city's political and ideological works in certain city Journey initial data.
S12: municipal works classification data is carried out including and normalized obtains returning for municipal works of all categories One changes numerical value.
In the data of classification, the case where being inclusion relation there are part group data and other group data, for example, bridge Beam number contains viaduct number, and greening area coverage includes greening area coverage built-up areas, and greenery area is built comprising greenery area At area etc., therefore, it is necessary to carry out that initial data is subtracted to the packet of inclusion relation comprising processing to municipal works classification data Containing data.
Meanwhile the measurement unit of five class data of front is different, is not easy to be compared data and operation, because This, needs that classification data is normalized.Normalization is a kind of dimensionless processing means, makes the exhausted of physical system numerical value Certain relative value relationship is become to value.The addition of data from now on for convenience, the method compared here by max min. Normalized formula is as follows:
Wherein, x' indicates that the numerical value after normalization, X indicate to need normalized array, and x indicates to normalize in array X Numerical value before.
S13: the growth rate of the other municipal works of each group is calculated to obtain municipal administration of all categories according to municipal works initial data The weight of project data.
Carry out initial data go to include and normalize after, it is thus necessary to determine that the power that each factor contributes project amount Weight.Annual annual rate of increase is the important indicator of engineering construction performance, although annual project amount further includes in addition to construction Daily maintenance, maintenance etc..But for a possibility that cable is destroyed by external force, it is clear that construction amount be it is most important, because This, can determine weight according to the annual annual growth of the other municipal works of each group.
The growth rate of the other municipal works of each group is calculated according to municipal works initial data respectively.Growth rate and unit time It is related, in the present embodiment, specially annual growth.City of all categories is calculated again according to the growth rate of the other municipal works of each group The weight of political affairs project data.Specifically, the weight of a classification municipal works data is the corresponding other municipal works of group under the category Growth rate average value.For example, the weight of primary sources is being averaged for both link length and path area annual growth Value.If there are the municipal works of negative growth rate, that is, show that the group engineering is removed, in the municipal works for calculating its generic When the weight of data, take absolute value.
In order to enable each index weights Data Matching, can set Various types of data weight and be not to be exceeded 50%, once being more than will It is calculated according to 50%, other kinds data are redistributed by annual growth.
S14: it is determined under the category according to the ratio of the growth rate of the other municipal works of each group in municipal works of all categories The other municipal works data of each group weight.
By taking primary sources as an example, after the weight for determining primary sources, according to the year according to link length and path area The ratio between growth rate determines the weight of this two groups of data of link length and path area.
S15: it is carried out according to the weight of the normalization numerical value of the other municipal works of each group and the other municipal works data of each group Fitting obtains municipal works amount curve.
Specifically, by the normalization data of the other municipal works of each group and its multiplied by weight, then every group of addition can be obtained Municipal works amount after the normalization of at least two unit time carries out the municipal works amount of different year according to the difference of time Curve matching, finally obtains a municipal works amount curve, and the municipal works amount curve prediction of the fitting has the municipal administration of next year Project amount.
In another embodiment, as shown in figure 3, step S30 is specifically included:
S31: it obtains each other anti-external force of setting group at least nearest two unit time and destroys measure, and imitated according to measure Fruit destroys measure to the anti-external force of each group and scores to obtain the anti-external force of each group and destroy measure initial data.
S32: anti-external force is destroyed to obtain the anti-external force of corresponding classification by the classification of measure original number according to the other relationship of each group Destruction measure classification data.
Anti- external force other for each group destroys measure initial data, and anti-external force is destroyed measure point according to the other relationship of each group Class.In a specific embodiment, above-mentioned 11 groups anti-external force can be destroyed measure and is divided into five classes, be respectively as follows: 1st class: the anti-external force of road area destroys measure application effect overall score;2nd class: the anti-external force destruction of bridge and viaduct region is arranged Apply application effect overall score;3rd class: the anti-external force of draining and water supply line region destroys measure application effect overall score;4th class: Greening area coverage, greening area coverage built-up areas, greenery area and greenery area build up the anti-external force destruction measure of region and answer With effect overall score;5th class: park greenbelt and the anti-external force of park surface area destroy measure application effect overall score.
S33: measure classification data is destroyed to anti-external force and carries out destroying measure comprising processing to obtain the anti-external force of each group Process data.
Go the processing for including identical as step S12's, details are not described herein.
S34: measure process data is destroyed according to anti-external force and calculates the growth rate of the other anti-external force safeguard measure of each group to obtain The weight of measure is destroyed to anti-external force of all categories.
The growth rate that measure process data calculates the other municipal works of each group is destroyed according to anti-external force respectively.Growth rate and list The position time is related, in the present embodiment, specially annual growth.Measure process data is destroyed again according to the other anti-external force of each group Calculate the weight that the anti-external force in city of all categories destroys measure.Specifically, the weight that the anti-external force of a classification destroys measure is under the category The corresponding other anti-external force of group destroys the average value of the growth rate of measure.If the anti-external force for negative growth rate occur destroys measure processing number According to when calculating the weight of municipal works data of its generic, take absolute value.
In order to enable each index weights Data Matching, can set Various types of data weight and be not to be exceeded 50%, once being more than will It is calculated according to 50%, other kinds data are redistributed by annual growth.
S35: the ratio of the growth rate of measure is destroyed according to the other anti-external force of each group in anti-external force destruction measure of all categories Determine that the other anti-external force of each group under the category destroys instrument weights.
S36: the weight that measure process data destroys measure with the other anti-external force of each group is destroyed according to anti-external force and is fitted It obtains anti-external force and destroys measure curve.
Specifically, the other anti-external force of each group is destroyed measure process data and multiplied by weight, then every group of addition can be obtained Anti- external force after the quantization of at least two unit time different years destroys action data, and the anti-external force destruction of different year is arranged Apply data to carry out curve fitting according to the difference of time, finally obtain an anti-external force and destroy measure curve, the fitting it is anti-outer Power, which destroys measure curve prediction, has the anti-external force in the city of next year to destroy action data.According to the municipal works amount curve of fitting and intend The anti-external force closed, which destroys the cable external force damage curve prediction that measure curve obtains, has next year cable external force to destroy data.
In another embodiment, as shown in figure 4, step S70 includes:
S71: the current failure number of cable current one time generation external force destructive malfunction is obtained.
If the unit time is year, current failure number is the number of current year external force destructive malfunction.
S72: the correspondence numerical value in the cable external force damage curve of current one time is compared with current failure number Relatively obtain ratio.
In a specific embodiment, by the correspondence numerical value and current year external force in the cable external force damage curve of current year The number of destructive malfunction obtains ratio K.
S73: according to the correspondence numerical value and the next unit of ratio prediction in the cable external force damage curve of next unit time The number of time inner cable generation external force destructive malfunction.
In a specific embodiment, the correspondence number of next unit time is found in cable external force damage curve Value, for example, the correspondence numerical value in the cable external force damage curve of next year is multiplied with ratio K, i.e., predictable next year cable The number of external force destructive malfunction occurs.
The prediction cable occur external force destructive malfunction number method, by obtain history municipal works data and Anti- external force destroys measure initial data and obtains cable external force damage curve, and external force destructive malfunction occurs according to the current one time Number and cable external force damage curve predict that the number of destructive malfunction occurs for next unit time.This method passes through obtained electricity Cable external force damage curve can intuitively predict that the number of destructive malfunction occurs for next unit time, and data are history number According to, the efficacy data of measure is destroyed including municipal engineering construction and anti-external force, so as to balanced economy and validity it Between relationship, the construction for destroying measure to municipal works and anti-external force has directive significance.For example, if the number that prediction obtains It is excessively high, it can suitably increase anti-external force and destroy measure;If number is less, it can temporarily be increased without anti-external force and destroy measure. Control cable external force destructive malfunction frequency within the scope of acceptable by this method.
The present invention also provides the systems that the number of external force destructive malfunction occurs for a kind of prediction cable, as shown in Figure 5, comprising:
Municipal works amount curve generation module 10, for obtaining the other city of setting group at least nearest two unit time Political and ideological work journey initial data simultaneously determines the weight of every group of municipal works data according to municipal works initial data to be fitted to obtain Municipal works amount curve.
In the present embodiment, the unit time is year, and in other embodiments, the unit time can be the moon or season Degree.
Set the other municipal works of group include: link length (unit is kilometer), path area (unit be square kilometre), Bridge number (unit is a), bridge number-viaduct (unit is a), drainage pipeline length (unit is kilometer), water supplying pipe road length Spend (unit is kilometer), greening area coverage (unit is hectare), greening area coverage-built-up areas (unit is hectare), greenery patches Area (unit is hectare), greenery area-built-up areas (unit is hectare), park greenbelt (unit is hectare) and park face Product (unit is hectare).
It obtains above-mentioned group of other municipal works initial data at least in two years and is determined according to municipal works initial data The weight of every group of municipal works data is to obtain municipal works amount curve.
Anti- external force destroys measure curve generation module 30, for obtaining the setting group at least nearest two unit time Anti- external force destroy measure initial data and according to anti-external force destroy measure initial data determine every group anti-external force destroy measure Weight destroy measure curve to be fitted to obtain anti-external force.
Common anti-external force, which destroys measure, mainly setting warning sign, personnel's tour etc., and anti-external force destroys measure original number According to destroying with anti-external force, the effect of measure is related, and by scoring measure application, it is former that available anti-external force destroys measure Beginning data, anti-external force destroy measure initial data and includes: the anti-external force of road area destroys measure application effect overall score, and (unit is Point), the anti-external force in bridge area destroys measure application effect overall score (unit is point), the anti-external force in bridge _ viaduct region is destroyed Measure application effect overall score (unit be point), the anti-external force in drainage pipeline region destroy measure application effect overall score, and (unit is Point), the anti-external force in water supply line region destroy measure application effect overall score (unit is point), the greening anti-external force in area coverage region Destruction measure application effect overall score (unit is point), greening area coverage _ build up the anti-external force destruction measure application effect of region Fruit overall score (unit is point), the anti-external force in greenery area region destroy measure application effect overall score (unit is point), greenery patches face It is broken accumulate _ to build up the anti-external force destruction measure application effect overall score of region (unit is point), the anti-external force in park greenbelt region Bad measure application effect overall score (unit is point) and the anti-external force of park surface area destroy measure application effect overall score (unit To divide).
The above-mentioned group of other anti-external force obtained at least in two years destroys measure initial data and destroys measure according to anti-external force Initial data determines that every group of anti-external force destroys the weight point of measure and destroys measure curve to obtain anti-external force.
Cable external force damage curve generation module 50, for destroying measure curve according to municipal works amount curve and anti-external force Obtain cable external force damage curve.
Cable external force damage curve is obtained specifically, municipal works amount curve is subtracted anti-external force and destroys measure curve.
The current failure number of external force destructive malfunction occurs for obtaining the cable current one time for prediction module 70, and Predict that time of external force destructive malfunction occurs for next unit time cable according to current failure number and cable external force damage curve Number.
In the present embodiment, current failure number is the number for current year external force destructive malfunction occurring, next unit time The number that external force destructive malfunction occurs for next year cable for the number of external force destructive malfunction occurs for inner cable.
The prediction cable occur external force destructive malfunction number system, by obtain history municipal works data and Anti- external force destroys measure initial data and obtains cable external force damage curve, and external force destructive malfunction occurs according to the current one time Number and cable external force damage curve predict that the number of destructive malfunction occurs for next unit time.The system passes through obtained electricity Cable external force damage curve can intuitively predict that the number of destructive malfunction occurs for next unit time, and data are history number According to, the efficacy data of measure is destroyed including municipal engineering construction and anti-external force, so as to balanced economy and validity it Between relationship, the construction for destroying measure to municipal works and anti-external force has directive significance.
Specifically, municipal works amount curve generation module 10 includes:
First taxon, for obtaining the other municipal works initial data of the setting group at least two unit time, And municipal works initial data is classified to obtain the municipal works classification data of corresponding classification according to each group other relationship.
Municipal works initial data other for the setting group of acquisition, according to the other relationship of each group by municipal works original number According to classification, for example, the long road of road and path area are all related with road, the long circuit-switched data of road can be classified as with path area data It is a kind of.In a specific embodiment, above-mentioned 12 groups of municipal works data can be divided into five classes, be respectively as follows: 1st class: link length and path area;2nd class: bridge number and viaduct number;3rd class: drainage pipeline length and water supply line Length;4th class: greening area coverage, greening area coverage built-up areas, greenery area and greenery area built-up areas;5th class: public Garden greenery area and park area.
Setting at least nine unit time is obtained in a kind of specific embodiment for the accuracy for improving prediction Surely other municipal works initial data is organized, for example, in one embodiment, obtaining 2000 to the 2013 city's political and ideological works in certain city Journey initial data.
First data processing unit, for carrying out including to municipal works classification data and normalized obtains each group The normalization numerical value of other municipal works.
In the data of classification, the case where being inclusion relation there are part group data and other group data, for example, bridge Beam number contains viaduct number, and greening area coverage includes greening area coverage built-up areas, and greenery area is built comprising greenery area At area etc., therefore, it is necessary to carry out that initial data is subtracted to the packet of inclusion relation comprising processing to municipal works classification data Containing data.
Meanwhile the measurement unit of five class data of front is different, is not easy to be compared data and operation, because This, needs that classification data is normalized.Normalization is a kind of dimensionless processing means, makes the exhausted of physical system numerical value Certain relative value relationship is become to value.The addition of data from now on for convenience, the method compared here by max min. Normalized formula is as follows:
Wherein, x' indicates that the numerical value after normalization, X indicate to need normalized array, and x indicates to normalize in array X Numerical value before.
First weight calculation unit, for calculating the growth rate of the other municipal works of each group according to municipal works initial data To obtain the weight of municipal works data of all categories.
Carry out initial data go to include and normalize after, it is thus necessary to determine that the power that each factor contributes project amount Weight.Annual annual rate of increase is the important indicator of engineering construction performance, although annual project amount further includes in addition to construction Daily maintenance, maintenance etc..But for a possibility that cable is destroyed by external force, it is clear that construction amount be it is most important, because This, can determine weight according to the annual annual growth of the other municipal works of each group.
The growth rate of the other municipal works of each group is calculated according to municipal works initial data respectively.Growth rate and unit time It is related, in the present embodiment, specially annual growth.City of all categories is calculated again according to the growth rate of the other municipal works of each group The weight of political affairs project data.Specifically, the weight of a classification municipal works data is the corresponding other municipal works of group under the category Growth rate average value.For example, the weight of primary sources is being averaged for both link length and path area annual growth Value.If there are the municipal works of negative growth rate, that is, show that the group engineering is removed, in the municipal works for calculating its generic When the weight of data, take absolute value.
In order to enable each index weights Data Matching, can set Various types of data weight and be not to be exceeded 50%, once being more than will It is calculated according to 50%, other kinds data are redistributed by annual growth.
Second weight calculation unit, for according to the growth rate of the other municipal works of each group in municipal works of all categories Ratio determines the weight of the other municipal works data of each group under the category.
By taking primary sources as an example, after the weight for determining primary sources, according to the year according to link length and path area The ratio between growth rate determines the weight of this two groups of data of link length and path area.
Municipal works amount curve generation unit, for other according to the normalization numerical value and each group of the other municipal works of each group The weight of municipal works data is fitted to obtain municipal works amount curve.
Specifically, by the normalization data of the other municipal works of each group and its multiplied by weight, then every group of addition can be obtained Municipal works amount after the normalization of at least two unit time carries out the municipal works amount of different year according to the difference of time Curve matching, finally obtains a municipal works amount curve, and the municipal works amount curve prediction of the fitting has the municipal administration of next year Project amount.
In another embodiment, anti-external force destruction measure curve generation module includes:
Acquiring unit destroys measure for obtaining each other anti-external force of setting group at least nearest two unit time, and Measure is destroyed to the anti-external force of each group according to measure effect to score to obtain the anti-external force of each group and destroy measure initial data.
Second taxon, for anti-external force to be destroyed the classification of measure original number to be corresponded to according to the other relationship of each group The anti-external force of classification destroys measure classification data.
Anti- external force other for each group destroys measure initial data, and anti-external force is destroyed measure point according to the other relationship of each group Class.In a specific embodiment, above-mentioned 11 groups anti-external force can be destroyed measure and is divided into five classes, be respectively as follows: 1st class: the anti-external force of road area destroys measure application effect overall score;2nd class: the anti-external force destruction of bridge and viaduct region is arranged Apply application effect overall score;3rd class: the anti-external force of draining and water supply line region destroys measure application effect overall score;4th class: Greening area coverage, greening area coverage built-up areas, greenery area and greenery area build up the anti-external force destruction measure of region and answer With effect overall score;5th class: park greenbelt and the anti-external force of park surface area destroy measure application effect overall score.
Second data processing unit is carried out comprising processing for destroying measure classification data to anti-external force to obtain each group Not anti-external force destroys measure process data.
Third weight calculation unit calculates the other anti-external force protection of each group for destroying measure process data according to anti-external force The growth rate of measure is to obtain the weight that anti-external force of all categories destroys measure.
The growth rate that measure process data calculates the other municipal works of each group is destroyed according to anti-external force respectively.Growth rate and list The position time is related, in the present embodiment, specially annual growth.Measure process data is destroyed again according to the other anti-external force of each group Calculate the weight that the anti-external force in city of all categories destroys measure.Specifically, the weight that the anti-external force of a classification destroys measure is under the category The corresponding other anti-external force of group destroys the average value of the growth rate of measure.If the anti-external force for negative growth rate occur destroys measure processing number According to when calculating the weight of municipal works data of its generic, take absolute value.
In order to enable each index weights Data Matching, can set Various types of data weight and be not to be exceeded 50%, once being more than will It is calculated according to 50%, other kinds data are redistributed by annual growth.
4th weight calculation unit, for being arranged according to the other anti-external force destruction of each group in anti-external force destruction measure of all categories The ratio for the growth rate applied determines that the other anti-external force of each group under the category destroys the weight of measure.
Anti- external force destroys measure curve generation unit, other anti-with each group for destroying measure process data according to anti-external force The weight that external force destroys measure is fitted to obtain anti-external force destruction measure curve.
Specifically, the other anti-external force of each group is destroyed measure process data and multiplied by weight, then every group of addition can be obtained Anti- external force after the quantization of at least two unit time different years destroys action data, and the anti-external force destruction of different year is arranged Apply data to carry out curve fitting according to the difference of time, finally obtain an anti-external force and destroy measure curve, the fitting it is anti-outer Power, which destroys measure curve prediction, has the anti-external force in the city of next year to destroy action data.According to the municipal works amount curve of fitting and intend The anti-external force closed, which destroys the cable external force damage curve prediction that measure curve obtains, has next year cable external force to destroy data.
In another embodiment, prediction module 70 includes:
The current failure of external force destructive malfunction occurs for obtaining the cable current one time for number of stoppages acquiring unit Number.
If the unit time is year, current failure number is the number of current year external force destructive malfunction.
Comparing unit, for the correspondence numerical value and current failure in the cable external force damage curve by the current one time Number is compared to obtain ratio.
In a specific embodiment, by the correspondence numerical value and current year external force in the cable external force damage curve of current year The number of destructive malfunction obtains ratio K.
Predicting unit is predicted for the correspondence numerical value in the cable external force damage curve according to next unit time with ratio The number of external force destructive malfunction occurs for next unit time inner cable.
In a specific embodiment, the correspondence number of next unit time is found in cable external force damage curve Value, for example, the correspondence numerical value in the cable external force damage curve of next year is multiplied with ratio K, i.e., predictable next year cable The number of external force destructive malfunction occurs.
The prediction cable occur external force destructive malfunction number system, by obtain history municipal works data and Anti- external force destroys measure initial data and obtains cable external force damage curve, and external force destructive malfunction occurs according to the current one time Number and cable external force damage curve predict that the number of destructive malfunction occurs for next unit time.The system passes through obtained electricity Cable external force damage curve can intuitively predict that the number of destructive malfunction occurs for next unit time, and data are history number According to, the efficacy data of measure is destroyed including municipal engineering construction and anti-external force, so as to balanced economy and validity it Between relationship, the construction for destroying measure to municipal works and anti-external force has directive significance.For example, if the number that prediction obtains It is excessively high, it can suitably increase anti-external force and destroy measure;If number is less, it can temporarily be increased without anti-external force and destroy measure. Cable external force destructive malfunction frequency is controlled by this system within the scope of acceptable.
Each technical characteristic of embodiment described above can be combined arbitrarily, for simplicity of description, not to above-mentioned reality It applies all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, all should be considered as described in this specification.
The embodiments described above only express several embodiments of the present invention, and the description thereof is more specific and detailed, but simultaneously It cannot therefore be construed as limiting the scope of the patent.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to protection of the invention Range.Therefore, the scope of protection of the patent of the invention shall be subject to the appended claims.

Claims (10)

1. a kind of method that the number of external force destructive malfunction occurs for prediction cable characterized by comprising
Obtain the other municipal works initial data of setting group at least nearest two unit time and according to the municipal works Initial data determines the weight of every group of municipal works data to be fitted to obtain municipal works amount curve;
It obtains the other anti-external force of the setting group at least nearest two unit time and destroys measure initial data and according to described anti- External force destroys measure initial data and determines that every group of anti-external force destroys the weight of measure to be fitted to obtain anti-external force destruction and arrange Apply curve;
Measure curve, which is destroyed, according to the municipal works amount curve and the anti-external force obtains cable external force damage curve;
The current failure number of cable current one time generation external force destructive malfunction is obtained, and according to the current failure number And the cable external force damage curve predicts that the number of external force destructive malfunction occurs for next unit time cable.
2. the method that the number of external force destructive malfunction occurs for prediction cable according to claim 1, which is characterized in that described Obtain the other municipal works initial data of setting group at least nearest two unit time and original according to the municipal works Data determine the weight of every group of municipal works data and include: the step of municipal works amount curve to be fitted to obtain
Obtain the other municipal works initial data of setting group at least two unit time, and according to the other relationship of each group by institute The classification of municipal works initial data is stated to obtain the municipal works classification data of corresponding classification;
The municipal works classification data is carried out including and normalized obtains the normalization of the other municipal works of each group Numerical value;
The growth rate of the other municipal works of each group is calculated according to the municipal works initial data to obtain municipal administration of all categories The weight of project data;
It is determined under the category according to the ratio of the growth rate of the other municipal works of each group described in the municipal works of all categories The other municipal works data of each group weight;
It is carried out according to the weight of the normalization numerical value of the other municipal works of each group and the other municipal works data of each group Fitting obtains municipal works amount curve.
3. the method that the number of external force destructive malfunction occurs for prediction cable according to claim 1, which is characterized in that described The other anti-external force of setting group at least nearest two unit time is obtained to destroy measure initial data and broken according to the anti-external force Bad measure initial data determines that every group of anti-external force is destroyed the weight of measure initial data and destroyed to be fitted to obtain anti-external force The step of measure curve are as follows:
It obtains each other anti-external force of setting group at least nearest two unit time and destroys measure, and according to measure effect to each group Not anti-external force destroys measure and scores to obtain the anti-external force of each group and destroy measure initial data;
The anti-external force classification of measure original number is destroyed according to the other relationship of each group to destroy with the anti-external force for obtaining corresponding classification Measure classification data;
Measure classification data is destroyed to the anti-external force to carry out destroying measure processing comprising processing to obtain the anti-external force of each group Data;
Measure process data, which is destroyed, according to the anti-external force calculates the growth rate of the other anti-external force safeguard measure of each group to obtain The weight of measure is destroyed to anti-external force of all categories;
The ratio for the growth rate for destroying measure according to the other anti-external force of each group in the anti-external force destruction measure of all categories determines The other anti-external force of each group under the category destroys the weight of measure;
The weight that measure process data destroys measure with the other anti-external force of each group is destroyed according to the anti-external force to be fitted It obtains anti-external force and destroys measure curve.
4. the method that the number of external force destructive malfunction occurs for prediction cable according to claim 1, which is characterized in that described Obtain the current failure number that external force destructive malfunction occurs for the cable current one time, and according to the current failure number and The cable external force damage curve predicts that the step of number of external force destructive malfunction occurs for next unit time cable includes:
Obtain the current failure number of cable current one time generation external force destructive malfunction;
Correspondence numerical value in the cable external force damage curve of current one time is compared with the current failure number To ratio;
Next unit time is predicted with the ratio according to the correspondence numerical value in the cable external force damage curve of next unit time The number of inner cable generation external force destructive malfunction.
5. the method that the number of external force destructive malfunction occurs for prediction cable according to claim 2, which is characterized in that described Formula used by normalized are as follows:
Wherein, before x' indicates that the numerical value after normalization, X indicate that normalized array, x is needed to indicate to normalize in array X Numerical value.
6. the system that the number of external force destructive malfunction occurs for a kind of prediction cable characterized by comprising
Municipal works amount curve generation module, for obtaining the other municipal works of setting group at least nearest two unit time Initial data and according to the municipal works initial data determine every group described in municipal works data weight to be fitted To municipal works amount curve;
Anti- external force destroys measure curve generation module, other anti-outer for obtaining the setting group at least nearest two unit time Power, which destroys measure initial data and destroys measure initial data according to the anti-external force, determines that every group of anti-external force destroys measure Weight destroys measure curve to be fitted to obtain anti-external force;
Cable external force damage curve generation module, it is bent for destroying measure according to the municipal works amount curve and the anti-external force Line obtains cable external force damage curve;
The current failure number of external force destructive malfunction occurs for obtaining the cable current one time for prediction module, and according to institute It states current failure number and the cable external force damage curve predicts that external force destructive malfunction occurs for next unit time cable Number.
7. the system that the number of external force destructive malfunction occurs for prediction cable according to claim 6, which is characterized in that described Municipal works amount curve generation module includes:
First taxon, for obtaining the other municipal works initial data of the setting group at least two unit time, and root The municipal works initial data is classified to obtain the municipal works classification data of corresponding classification according to each group other relationship;
First data processing unit, for carrying out including to the municipal works classification data and normalized obtains each group The normalization numerical value of other municipal works;
First weight calculation unit, for calculating the increasing of the other municipal works of each group according to the municipal works initial data Long rate is to obtain the weight of municipal works data of all categories;
Second weight calculation unit, the growth for the other municipal works of each group according to the municipal works of all categories The ratio of rate determines the weight of the other municipal works data of each group under the category;
Municipal works amount curve generation unit, for according to the normalization numerical value of the other municipal works of each group and each group The weight of other municipal works data is fitted to obtain municipal works amount curve.
8. the system that the number of external force destructive malfunction occurs for prediction cable according to claim 6, which is characterized in that described Anti- external force destroys measure curve generation module
Acquiring unit, for the other anti-external force destruction measure of setting group each in acquisition at least nearest two unit time, and according to Measure effect destroys measure to the anti-external force of each group and scores to obtain the anti-external force of each group and destroy measure initial data;
Second taxon, for the anti-external force to be destroyed the classification of measure original number to be corresponded to according to the other relationship of each group The anti-external force of classification destroys measure classification data;
Second data processing unit is carried out comprising processing for destroying measure classification data to the anti-external force to obtain each group Not anti-external force destroys measure process data;
Third weight calculation unit calculates the other anti-external force of each group for destroying measure process data according to the anti-external force The growth rate of safeguard measure is to obtain the weight that anti-external force of all categories destroys measure;
4th weight calculation unit, for being arranged according to the other anti-external force destruction of each group in the anti-external force destruction measure of all categories The ratio for the growth rate applied determines that the other anti-external force of each group under the category destroys the weight of measure;
Anti- external force destroys measure curve generation unit, for destroying measure process data and each group according to the anti-external force Anti- external force destroy the weight of measure and be fitted to obtain anti-external force and destroy measure curve.
9. the system that the number of external force destructive malfunction occurs for prediction cable according to claim 8, which is characterized in that described Prediction module includes:
The current failure number of external force destructive malfunction occurs for obtaining the cable current one time for number of stoppages acquiring unit;
Comparing unit, for the correspondence numerical value and the current failure in the cable external force damage curve by the current one time Number is compared to obtain ratio;
Predicting unit is predicted for the correspondence numerical value in the cable external force damage curve according to next unit time with the ratio The number of external force destructive malfunction occurs for next unit time inner cable.
10. the system that the number of external force destructive malfunction occurs for prediction cable according to claim 7, which is characterized in that institute State formula used by normalized are as follows:
Wherein, before x' indicates that the numerical value after normalization, X indicate that normalized array, x is needed to indicate to normalize in array X Numerical value.
CN201510780476.6A 2015-11-13 2015-11-13 Predict that the method and system of the number of external force destructive malfunction occurs for cable Active CN105279580B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510780476.6A CN105279580B (en) 2015-11-13 2015-11-13 Predict that the method and system of the number of external force destructive malfunction occurs for cable

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510780476.6A CN105279580B (en) 2015-11-13 2015-11-13 Predict that the method and system of the number of external force destructive malfunction occurs for cable

Publications (2)

Publication Number Publication Date
CN105279580A CN105279580A (en) 2016-01-27
CN105279580B true CN105279580B (en) 2018-12-25

Family

ID=55148556

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510780476.6A Active CN105279580B (en) 2015-11-13 2015-11-13 Predict that the method and system of the number of external force destructive malfunction occurs for cable

Country Status (1)

Country Link
CN (1) CN105279580B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110837898A (en) * 2019-10-25 2020-02-25 袁茂银 Method and device for repairing underground cable faults based on model selection

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102324068A (en) * 2011-08-31 2012-01-18 广东省电力调度中心 Power secondary equipment risk assessment method and system thereof
JP5518586B2 (en) * 2010-06-17 2014-06-11 公益財団法人鉄道総合技術研究所 Fatigue damage evaluation method of connector lead wire in connector of train line
CN104166788A (en) * 2014-07-22 2014-11-26 国家电网公司 Overhead transmission line optimal economic life range assessment method
CN104848885A (en) * 2015-06-04 2015-08-19 北京金控自动化技术有限公司 Method for predicting time of future failure of equipment
CN104899690A (en) * 2015-06-08 2015-09-09 江苏省电力公司苏州供电公司 Power cable operation maintenance method based on historical fault information and operating state

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5518586B2 (en) * 2010-06-17 2014-06-11 公益財団法人鉄道総合技術研究所 Fatigue damage evaluation method of connector lead wire in connector of train line
CN102324068A (en) * 2011-08-31 2012-01-18 广东省电力调度中心 Power secondary equipment risk assessment method and system thereof
CN104166788A (en) * 2014-07-22 2014-11-26 国家电网公司 Overhead transmission line optimal economic life range assessment method
CN104848885A (en) * 2015-06-04 2015-08-19 北京金控自动化技术有限公司 Method for predicting time of future failure of equipment
CN104899690A (en) * 2015-06-08 2015-09-09 江苏省电力公司苏州供电公司 Power cable operation maintenance method based on historical fault information and operating state

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
10kV及以上电力电缆运行故障统计分析;罗俊华 等;《高电压技术》;20030630;第29卷(第6期);第14-16页 *
基于统计模型的电缆故障数据分析;唐泽洋 等;《全国第九次电力电缆运行经验交流会论文集》;20131029;第967-970页 *

Also Published As

Publication number Publication date
CN105279580A (en) 2016-01-27

Similar Documents

Publication Publication Date Title
Arrighi et al. Indirect flood impacts and cascade risk across interdependent linear infrastructures
Walski Water distribution valve topology for reliability analysis
Phan et al. Managing water main breaks in distribution networks––A risk-based decision making
Chen et al. Simulating and mapping the spatial and seasonal effects of future climate and land-use changes on ecosystem services in the Yanhe watershed, China
CN118014185A (en) Municipal pipe network health degree on-line monitoring system based on big data
CN107609989A (en) A kind of bridge health monitoring intelligence CS architecture systems of road network level
CN115270527A (en) Real-time assessment method, equipment and storage medium for road collapse risk
CN107291991A (en) A kind of Wind turbines early defect method for early warning based on dynamic network mark
CN110234811A (en) Road collapsing risk assessment device and road collapsing risk assessment method and road collapsing risk assessment computer program
CN116824807B (en) Multi-disaster early warning alarm method and system
CN106780144A (en) A kind of pipeline coordination methods of risk assessment
CN115481940A (en) Oil and gas pipeline area risk monitoring system based on big data
CN105279580B (en) Predict that the method and system of the number of external force destructive malfunction occurs for cable
CN102799746B (en) Power grid information checking method and system, and power grid planning auxiliary system
CN114413832B (en) Road monitoring system and method based on optical fiber sensing
CN109507992A (en) A kind of failure prediction method, device and the equipment of locomotive braking system component
CN116957322A (en) Method and device for risk assessment of drainage pipe network
CN113128709A (en) Water supply pipe network leakage management system
CN103604624A (en) Damaged cable and concentrated load recognition method on basis of hybrid monitoring
CN103616214A (en) Damaged cable concentrated load recognition method based on spatial coordinate monitoring in process of linear displacement
Christodoulou et al. Rehabilitation and maintenance of water distribution network assets
CN114969068B (en) Urban pressure pipe network real-time flow monitoring data analysis method and system
CN115856470A (en) Distribution cable state monitoring method and device based on multi-sensor information fusion
Xiang et al. Construction and optimization strategy of Ecological Security Pattern in County-Level cities under spatial and temporal variation of Ecosystem services: Case Study of Mianzhu, China
CN112330516B (en) Method and device for generating highway pavement maintenance plan

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200922

Address after: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No.

Patentee after: Guangzhou Power Supply Bureau of Guangdong Power Grid Co.,Ltd.

Address before: 510620 Tianhe District, Guangzhou, Tianhe South Road, No. two, No. 2, No.

Patentee before: GUANGZHOU POWER SUPPLY Co.,Ltd.