Daily production and daily clearing accounting method, apparatus and device, and computer-readable storage medium Download PDFInfo
- Publication number
- WO2021068593A1 WO2021068593A1 PCT/CN2020/102776 CN2020102776W WO2021068593A1 WO 2021068593 A1 WO2021068593 A1 WO 2021068593A1 CN 2020102776 W CN2020102776 W CN 2020102776W WO 2021068593 A1 WO2021068593 A1 WO 2021068593A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- nissan
- finished product
- data
- work order
- product data
- Prior art date
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
Definitions
- This application relates to the field of data processing, and in particular to a method, device, equipment and computer-readable storage medium for Nissan’s daily settlement accounting.
- the supply chain collaboration SaaS platform is based on order collaboration, procurement collaboration, logistics collaboration, etc. It can quickly calculate how much a company’s daily investment and daily output, but it is impossible to know the company’s daily production input and production output. Whether the accounting is balanced, so that managers cannot accurately and timely grasp the daily production situation of the enterprise.
- the main purpose of this application is to propose a method, device, equipment, and computer-readable storage medium for daily settlement of Nissan, which aims to solve the problem that enterprise managers cannot grasp the production situation of the enterprise on that day.
- this application provides a Nissan daily settlement accounting method, and the Nissan daily settlement accounting method includes:
- the method further includes:
- the production work order is established.
- the step of establishing the production work order based on the bill of materials and preset loss calculation rules includes:
- the necessary material data for production is calculated based on the loss interval and the material usage data on the material list, and the production work order is established according to the necessary material data.
- the method further includes:
- the production work order is updated until the qualified finished product data is greater than or equal to the preset value.
- step of entering the over-collection process and establishing the over-collection list includes:
- an over-received order is created.
- Finished product data (material usage data + reasonable loss data + over-recovery data-returned material data)/unit finished product material data, where the material usage data, the reasonable loss data, the over-collected data, and the returned material
- the material usage data, the reasonable loss data, the over-collected data, and the returned material Both the quantity and the unit finished product material data are the material parameters.
- the method further includes:
- the finished product After determining that the calculation result is still invalid, the finished product is determined to be lost, and/or the material is lost, and the instruction information attributable to the production department is output.
- this application also provides a Nissan daily settlement accounting device, which includes:
- Obtaining module configured to obtain the production work order to be accounted
- An extraction module configured to extract finished product data in the production work order
- the substitution module is configured to, after determining that the qualified finished product data in the finished product data is greater than or equal to a preset value, substitute the finished product data and the material parameters in the production work order into the Nissan Nisshin constant equation;
- the judgment module is configured to judge whether to close the production work order according to the calculation result of the Nissan Nissin Heng equation
- the closing module after determining that the calculation result is that the identity is established, closes the production work order.
- this application also provides a Nissan daily settlement accounting device, which includes a memory, a processor, and a Nissan daily that is stored in the memory and can run on the processor.
- a liquidation accounting program which implements the steps of the above-mentioned Nissan daily accounting method when the Nissan daily accounting program is executed by the processor.
- the present application also provides a computer-readable storage medium on which the Nissan daily settlement accounting program is stored, which is realized when the Nissan daily settlement accounting program is executed by a processor.
- This application obtains the production work order to be calculated and extracts the finished product data in the production work order. After confirming that the qualified finished product data in the finished product data is greater than or equal to the preset value, the finished product data and the material parameters in the production work order are substituted into Nissan In the Nissin Heng equation, it is judged whether to close the production work order according to whether the Nissan Nissin Heng equation is established. If it is, the production work order is closed, which realizes the judgment of whether the calculation of the daily input and output of the enterprise is balanced, and further enables the management of the enterprise The person knows the daily production situation of the enterprise in a timely and accurate manner, and tracks whether materials and products are lost.
- FIG. 1 is a schematic diagram of the hardware structure of a device that implements each embodiment of the present application
- Fig. 2 is a schematic flow chart of the first embodiment of the daily settlement accounting method for applying for Nissan.
- FIG. 1 is a schematic structural diagram of a hardware operating environment involved in a solution of an embodiment of this application.
- Fig. 1 can be a structural diagram of the hardware operating environment of the Nissan Nissan’s accounting equipment.
- the Nissan daily settlement accounting equipment in the embodiment of the present application may be a PC, a portable computer, a server and other equipment.
- the Nissan daily settlement accounting device may include: a processor 1001, such as a CPU, a memory 1005, a user interface 1003, a network interface 1004, and a communication bus 1002.
- the communication bus 1002 is used to implement connection and communication between these components.
- the user interface 1003 may include a display screen (Display) and an input unit such as a keyboard (Keyboard), and the optional user interface 1003 may also include a standard wired interface and a wireless interface.
- the network interface 1004 may optionally include a standard wired interface and a wireless interface (such as a WI-FI interface).
- the memory 1005 may be a high-speed RAM memory, or a stable memory (non-volatile memory), such as a magnetic disk memory.
- the memory 1005 may also be a storage device independent of the aforementioned processor 1001.
- the Nissan Nissin accounting device may also include an RF (Radio Frequency, radio frequency) circuit, sensor, WiFi module, and so on.
- RF Radio Frequency, radio frequency
- the memory 1005 which is a computer-readable storage medium, may include an operating system, a network communication module, a user interface module, and a Nissan daily settlement accounting program.
- the operating system is a program that manages and controls the hardware and software resources of Nissan's Nissan Nissan's accounting equipment, and supports the operation of Nissan's Nissan's accounting and other software or programs.
- the Nissan Nissin accounting device shown in Figure 1 can be configured as Nissan Nissin accounting.
- the user interface 1003 is mainly used to detect or output various information, such as detecting finished product data and outputting information that the Nissan Nissin constant equation is not established;
- the network interface 1004 is mainly used to interact with the background server and communicate;
- the processor 1001 can be used to call the Nissan daily settlement accounting program stored in the memory 1005, and perform the following operations:
- the processor 1001 is also used to call the daily settlement accounting program stored in the memory 1005 and perform the following operations :
- the production work order is established.
- the step of establishing the production work order based on the bill of materials and preset loss calculation rules includes:
- the necessary material data for production is calculated based on the loss interval and the material usage data on the material list, and the production work order is established according to the necessary material data.
- the processor 1001 is further configured to call the daily settlement accounting program of Nissan stored in the memory 1005, and perform the following operations :
- the production work order is updated until the qualified finished product data is greater than or equal to the preset value.
- step of entering the over-collection process and establishing the over-collection list includes:
- an over-received order is created.
- Finished product data (material usage data + reasonable loss data + over-recovery data-returned material data)/unit finished product material data, where the material usage data, the reasonable loss data, the over-collected data, and the returned material
- the material usage data, the reasonable loss data, the over-collected data, and the returned material Both the quantity and the unit finished product material data are the material parameters.
- the processor 1001 is further configured to call the Nissan Nissan accounting program stored in the memory 1005, and perform the following operations:
- the finished product After determining that the calculation result is still invalid, the finished product is determined to be lost, and/or the material is lost, and the instruction information attributable to the production department is output.
- the finished product data and the material parameters in the production work order are substituted into In the Nissan Nissin Heng equation, it is judged whether to close the production work order based on whether the Nissan Nissin Heng equation is established. If it is, the production work order is closed, which realizes the judgment of whether the production input and output is balanced, so that the manager can grasp the production of the enterprise in time Circumstances, and track whether materials and products are missing.
- the implementation of the mobile terminal of this application is basically the same as the following various embodiments of the Nissan daily settlement accounting method, and will not be repeated here.
- This application provides an accounting method for Nissan's daily settlement.
- Fig. 1 is a schematic flowchart of a first embodiment of a method for calculating daily settlement of Nissan according to the application.
- the daily settlement accounting method of Nissan includes:
- Step S10 Obtain the production work order to be calculated, and extract the finished product data in the production work order.
- the Nissan Nissan’s accounting method is applied to the supply chain collaboration SaaS platform. First, obtain the production work order that needs to be accounted, and extract the finished product data from the production work order. It is understandable that what needs to be calculated is the data in the production work order, and the finished product data is one of all the data in the production work order. It should be noted that the data mentioned in all the examples agree with the quantity.
- Step S20 After it is determined that the qualified finished product data in the finished product data is greater than or equal to a preset value, the finished product data and the material parameters in the production work order are substituted into the daily production and daily clearing identity.
- the preset value is set manually, and the size of the preset value can be the number of products required by the customer on the day, or greater than the number of products required by the customer on the day.
- the finished product data includes the qualified finished product data and the unqualified finished product data. The products required by the customer should be qualified finished products. When the qualified finished product data in the finished product data is greater than or equal to the preset value, it means that the daily production volume has met the customer's requirements.
- step S30 it is judged whether to close the production work order according to the calculation result of the Nissan Nissin constant equation.
- Nissan Nissin's constant equation There are two calculation results of Nissan Nissin's constant equation, namely, the identity is established and the identity is not established. Whether the Nissan Nissin constant equation is established is the standard for judging whether the daily input and output of the enterprise are balanced. When the data of the finished product is equal to the input material. When the finished product data is output, it indicates that the production input and output of the enterprise are balanced at this time, and step S30 is executed.
- the finished product data calculated by the formula (1) is equal to the finished product data calculated by the formula (2), the input and output of the enterprise's production are balanced.
- the material usage data, reasonable loss data, over-claim data, returned material data and unit finished product material data are all material parameters. These material parameters are calculated based on the number of products required by the customer and the built-in calculation rules .
- the material usage data is the total amount of materials needed to produce the products required by the customer; the reasonable loss data is the amount of wastage inevitably caused during production; the over-required data is the qualified finished product data obtained when the materials are used up for the first time. Does not meet customer requirements, and needs to continue production to complete the material requested for the second time; the returned material data is the amount of unused materials remaining after the number of products required by the customer is produced; the unit finished product material data is the production of a single finished product The amount of material required.
- Step S40 after determining that the calculation result is that the identity is established, the production work order is closed.
- step S20 it further includes:
- Step a After determining that the calculation result is that the identity is not established, re-acquire the finished product data and the material parameters, and substitute the re-acquired finished product data and the material parameters into the Nissan Nisshin identity;
- Step b After determining that the Nissan Nissin Constant Equation is still invalid, it is determined that the finished product is lost and/or the material is lost, and the instruction information attributable to the production department is output.
- the finished product data produced is not equal to the finished product data of the input materials, it means that the production input and output of the enterprise are imbalanced at this time, that is to say, the Nissan Nissan Constant equation is not established, then the Nissan Nissan’s accounting is not Finished, the production work order cannot be closed.
- the Nissan Nissin constant equation is not established, the output is attributable to the production department's instruction information, reminding the staff that the finished product has not been put in the warehouse, or there are surplus materials involved in the production, but not in the warehouse, that is, the remaining materials are not completely put in. The situation of the library. The finished products and remaining materials that have not been put in storage are likely to be lost on the production line.
- the finished product data and material data are also material parameters
- they are substituted into the Nissan Nissin Heng equation.
- the Nissan Nissin Heng equation is invalid, it indicates that the finished product or the remaining materials are lost, and the output is attributable to the production
- the department s instruction information to tell the manager; after confirming that the Nissan Nissin constant equation is established, close the production work order.
- a prompt message is output to urge the staff to check the production line to prevent the loss of finished products or remaining materials.
- the access status of the materials can be checked, the used materials can be settled with the customer in a timely manner, and the materials that need to be returned to the customer can be counted. Return material.
- This embodiment obtains the production work order to be calculated, extracts the finished product data in the production work order, and determines that the qualified finished product data in the finished product data is greater than or equal to the preset value, and then substitutes the finished product data and the material parameters in the production work order into Nissan In the Nisshin Heng equation, judge whether to close the production work order according to whether the Nissan Nissin Heng equation is established or not. If it is, the production work order is closed, and the finished product data and material parameters are put into the Nissan Nissin Heng equation to realize the production input and production output. Whether to balance the accounting, so that the company’s managers can know the company’s production in a timely and accurate manner based on the accounting results, and track whether materials and products are lost.
- the second embodiment of the daily settlement accounting method for Nissan in this application is proposed.
- the difference between the second embodiment of the Nissan daily settlement accounting method and the first embodiment of the Nissan daily settlement accounting method is that before the step of obtaining the production work order to be calculated and extracting the finished product data in the production work order, Also includes:
- Step c create a bill of materials according to the customer's order.
- Step d Establish the production work order based on the material list and preset loss calculation rules.
- the amount of materials used for production is calculated according to the bill of materials and preset loss calculation rules, and a production work order is established to record the calculated data.
- step d also includes:
- Step e Calculate the loss interval of the bill of materials according to a preset loss calculation rule.
- the batch wastage is a value estimated by the staff based on production experience, which is artificially set.
- the loss on the ladder and the loss under the ladder do not exist at the same time, it is determined according to the situation.
- the down-step loss is taken; when the number of work orders is greater than the number of steps or the number of steps is zero, the up-step loss is taken.
- the number of work orders is the number of products required by the customer, and the number of steps is set by the staff based on production experience.
- Three scenarios are set up below and three calculation formulas for total loss are proposed:
- Scenario 2 The number of work orders is less than or equal to the number of steps, and the loss rate under the steps is less than 1, and the loss under the steps is taken.
- Scenario 3 The number of work orders is less than or equal to the number of steps, and the loss rate under the steps is greater than or equal to 1, and the loss under the steps is still taken.
- the total loss is calculated, and then the loss interval is estimated based on the total loss.
- the calculated total loss must belong to the loss interval.
- Step f Calculate the necessary material data for production based on the loss interval and the material usage data on the material list, and establish the production work order according to the necessary material data.
- the material list is established according to the customer order, and then the loss interval of the material list is calculated based on the material list and preset loss calculation rules, and the necessary material data for production is calculated according to the loss interval and the material usage data on the material list, and the establishment Production work orders.
- This method of establishing production work orders provides staff with a reliable data reference for the quantity of materials received, avoiding the difficulty of follow-up accounting caused by blind receipt of staff, and avoiding staff from taking less and increasing the process of overtaking. The number of times.
- the third embodiment of the daily settlement accounting method of Nissan in this application is proposed.
- the difference between the third embodiment of the Nissan daily settlement accounting method and the first or second embodiment of the Nissan daily settlement accounting method is that the method of obtaining the production work order to be calculated and extracting the finished product data in the production work order After the steps, it also includes:
- Step g After determining that the qualified finished product data in the finished product data is less than the preset value, enter the over-collection process to create an over-collection order.
- the qualified finished product data in the finished product data is less than the preset value, indicating that the number of qualified finished products produced by the company has not reached the number of products required by the customer.
- Leading process First, estimate the difference based on the difference between the qualified finished product data and the preset value, and calculate the material data required to produce the product with the difference based on the difference, and then calculate the production again according to the loss calculation rule described in the second embodiment Necessary material data to create an over-collection list.
- Step h based on the over-receipt order, update the production work order until the qualified finished product data is greater than or equal to the preset value.
- step of entering the over-collection process in step g and establishing the over-collection list includes:
- Step i Enter the over-receiving process, and estimate the over-received material data based on the difference between the qualified finished product data and the preset value.
- the difference is estimated based on the difference between the qualified finished product data and the preset value, and the material data required to produce the product with the difference is calculated based on the difference, and again according to the loss calculation rules described in the second embodiment Calculate the over-required material data.
- Step j Create an over-receiving list based on the over-received material data and the returned material data after the end of production.
- the qualified finished product data when it enters the over-recovery process, estimates the over-required material data based on the difference between the qualified finished product data and the preset value, and then based on the over-required material data and after the end of production
- the return data is used to create an over-receiving order, and the original production work order is updated according to the over-receiving order until the qualified finished product data is greater than or equal to the preset value.
- This kind of re-production is carried out when the qualified finished product data does not meet the customer’s required product volume.
- the re-recording of the data changes caused by reproduction reflects the flexibility of Nissan's daily settlement accounting process, and the timely update of production work orders also improves the accuracy of the data used for Nissan's daily settlement accounting.
- the embodiment of the present application also proposes a Nissan daily settlement accounting device, and the Nissan daily settlement accounting device includes:
- Obtaining module configured to obtain the production work order to be accounted
- An extraction module configured to extract finished product data in the production work order
- the substitution module is configured to, after determining that the qualified finished product data in the finished product data is greater than or equal to a preset value, substitute the finished product data and the material parameters in the production work order into the Nissan Nisshin constant equation;
- the judgment module is configured to judge whether to close the production work order according to the calculation result of the Nissan Nissin Heng equation
- the closing module is configured to close the production work order after determining that the calculation result is that the identity is established.
- Nissan daily settlement accounting module further includes:
- Establish a module which is configured to create a bill of materials according to customer orders
- the establishment module is further configured to establish the production work order based on the bill of materials and preset loss calculation rules.
- the establishment module further includes:
- the calculation unit is configured to calculate the loss interval of the bill of materials according to a preset loss calculation rule
- the calculation unit is further configured to calculate necessary material data for production based on the loss interval and the material usage data on the material list;
- the establishment unit is configured to establish the production work order according to the necessary material data.
- the Nissan daily settlement accounting device further includes:
- Enter the module configured to enter the over-collaring process after determining that the qualified finished product data in the finished product data is less than the preset value
- the establishment module is also configured to establish over-collection orders
- the update module is configured to update the production work order based on the over-receipt order until the qualified finished product data is greater than or equal to the preset value.
- the entry module further includes:
- the estimating unit is configured to estimate the over-required material data based on the difference between the qualified finished product data and the preset value;
- the establishing unit is further configured to create an over-receiving list based on the over-received material data and the returned material data after the production ends.
- the obtaining module is further configured to obtain the finished product data and the material parameters again after determining that the calculation result is that the identity is not established;
- the substitution module is further configured to substitute the re-acquired finished product data and the material parameters into the Nissan Nissin constant equation;
- the determining module is configured to determine that the finished product is lost and/or the material is lost after determining that the calculation result is still invalid.
- the output module is configured to output the instruction information attributed to the production department.
- the implementation of the Nissan daily clearing accounting device described in this application is basically the same as the above-mentioned various embodiments of the Nissan daily clearing accounting method, and will not be repeated here.
- an embodiment of the present application also proposes a computer-readable storage medium that stores a Nissan daily settlement accounting program, and when the Nissan daily settlement accounting program is executed by a processor, the above-mentioned Nissan daily The various steps of the Nissin accounting method.
- the computer-readable storage medium may be set in the Nissan Nissan’s accounting equipment.
- the implementation of the computer-readable storage medium of the present application is basically the same as the above-mentioned various embodiments of the Nissan daily settlement accounting method, and will not be repeated here.
- the technical solution of this application essentially or the part that contributes to the existing technology can be embodied in the form of a software product, and the computer software product is stored in a storage medium (such as ROM/RAM, magnetic disk, The optical disc) includes several instructions to enable a terminal device (which can be a mobile phone, a computer, a server, an air conditioner, or a network device, etc.) to execute the method described in each embodiment of the present application.
- a terminal device which can be a mobile phone, a computer, a server, an air conditioner, or a network device, etc.
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Game Theory and Decision Science (AREA)
- Educational Administration (AREA)
- Development Economics (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
Description
Claims (10)
- 一种日产日清核算方法,其中,所述日产日清核算方法应用于供应链协同SaaS平台,所述日产日清核算方法包括以下步骤:A Nissan daily settlement accounting method, wherein the Nissan daily settlement accounting method is applied to a supply chain collaboration SaaS platform, and the Nissan daily settlement accounting method includes the following steps:获取待核算的生产工单,并提取所述生产工单中的成品数据;Obtain the production work order to be calculated, and extract the finished product data in the production work order;确定所述成品数据中的合格成品数据大于或等于预设值后,将所述成品数据和所述生产工单中的物料参数代入日产日清恒等式中;After determining that the qualified finished product data in the finished product data is greater than or equal to a preset value, substitute the finished product data and the material parameters in the production work order into the Nissan Nisshin constant equation;根据所述日产日清恒等式计算结果,确定关闭所述生产工单;Determine to close the production work order according to the calculation result of the Nissan Nissin Heng equation;确定所述计算结果为恒等式成立后,关闭所述生产工单。After it is determined that the calculation result is that the identity is established, the production work order is closed.
- 如权利要求1所述的日产日清核算方法,其中,所述获取待核算的生产工单,并提取所述生产工单中的成品数据的步骤之前,还包括:5. The Nissan daily settlement accounting method according to claim 1, wherein before the step of obtaining the production work order to be calculated and extracting the finished product data in the production work order, the method further comprises:根据客户订单建立物料清单;Create a bill of materials according to customer orders;基于所述物料清单和预设的损耗计算规则,建立所述生产工单。Based on the bill of materials and preset loss calculation rules, the production work order is established.
- 如权利要求2所述的日产日清核算方法,其中,所述基于所述物料清单和预设的损耗计算规则,建立所述生产工单的步骤包括:3. The Nissan daily settlement accounting method according to claim 2, wherein the step of establishing the production work order based on the bill of materials and preset loss calculation rules comprises:根据预设的损耗计算规则,计算出所述物料清单的损耗区间;Calculate the loss interval of the bill of materials according to the preset loss calculation rules;基于所述损耗区间和所述物料清单上的物料用量数据计算出生产的必需物料数据,并根据所述必需物料数据建立所述生产工单。The necessary material data for production is calculated based on the loss interval and the material usage data on the material list, and the production work order is established according to the necessary material data.
- 如权利要求1所述的日产日清核算方法,其中,所述获取待核算的生产工单,并提取所述生产工单中的成品数据的步骤之后,还包括:The Nissan daily settlement accounting method according to claim 1, wherein after the step of obtaining the production work order to be calculated and extracting the finished product data in the production work order, the method further comprises:确定所述成品数据中的合格成品数据小于所述预设值后,进入超领流程,建立超领单;After determining that the qualified finished product data in the finished product data is less than the preset value, enter the over-collection process, and create an over-collection order;基于所述超领单,更新所述生产工单,直至所述合格成品数据大于或等于所述预设值。Based on the over-receiving order, the production work order is updated until the qualified finished product data is greater than or equal to the preset value.
- 如权利要求4所述的日产日清核算方法,其中,所述进入超领流程,建立超领单的步骤包括:The Nissan daily settlement accounting method according to claim 4, wherein the step of entering the over-collection process and establishing the over-collection slip comprises:进入超领流程,根据所述合格成品数据与所述预设值之间的差值,估算超领物料数据;Enter the over-collection process, and estimate the over-collected material data based on the difference between the qualified finished product data and the preset value;根据所述超领物料数据和生产结束后的退料数据,建立超领单。According to the over-received material data and the returned material data after the end of production, an over-received order is created.
- 如权利要求1所述的日产日清核算方法,其中,所述日产日清恒等式为:成品数据=合格成品数据+不合格成品数据;The Nissan daily settlement accounting method according to claim 1, wherein the Nissan daily settlement constant equation is: finished product data = qualified finished product data + unqualified finished product data;成品数据=(物料用量数据+合理损耗数据+超领数据-退料数据)/单位成品物料数据,其中,所述物料用量数据、所述合理损耗数据、所述超领数据、所述退料数量和所述单位成品物料数据均为所述物料参数。Finished product data = (material usage data + reasonable loss data + over-recovery data-returned material data)/unit finished product material data, where the material usage data, the reasonable loss data, the over-collected data, and the returned material Both the quantity and the unit finished product material data are the material parameters.
- 如权利要求1至6任一项所述的日产日清核算方法,其中,所述根据所述日产日清恒等式计算结果,确定关闭所述生产工单的步骤之后,还包括:7. The Nissan Nissan's daily settlement accounting method according to any one of claims 1 to 6, wherein, after determining the step of closing the production work order according to the calculation result of the Nissan Nissan's constant equation, the method further comprises:确定所述计算结果为恒等式不成立后,重新获取所述成品数据和所述物料参数,将重新获取的所述成品数据和所述物料参数代入所述日产日清恒等式中;After determining that the calculation result is that the identity is not established, re-acquire the finished product data and the material parameter, and substitute the re-acquired finished product data and the material parameter into the Nissan Nisshin identity;确定所述计算结果仍为恒等式不成立后,确定成品丢失,和/或物料丢失,输出归责于生产部门的指示信息。After determining that the calculation result is still invalid, the finished product is determined to be lost, and/or the material is lost, and the instruction information attributable to the production department is output.
- 一种日产日清核算装置,其中,所述日产日清核算装置包括:A Nissan daily settlement accounting device, wherein the Nissan daily settlement accounting device includes:获取模块,设置为获取待核算的生产工单;The acquisition module is set to acquire the production work order to be accounted;提取模块,设置为提取所述生产工单中的成品数据;An extraction module, configured to extract the finished product data in the production work order;代入模块,设置为确定所述成品数据中的合格成品数据大于或等于预设值后,将所述成品数据和所述生产工单中的物料参数代入日产日清恒等式中;Substitution module, set to determine that the qualified finished product data in the finished product data is greater than or equal to a preset value, and then substitute the finished product data and the material parameters in the production work order into the Nissan Nissan Constant Equation;判断模块,设置为根据所述日产日清恒等式计算结果,确定关闭所述生产工单;以及The judgment module is configured to determine to close the production work order according to the calculation result of the Nissan Nissin Heng equation; and关闭模块,设置为确定所述计算结果为恒等式成立后,关闭所述生产工单。The closing module is configured to close the production work order after determining that the calculation result is that the identity is established.
- 一种日产日清核算设备,其中,所述日产日清核算设备包括存储器、处理器及存储在所述存储器上并可在所述处理器上运行的日产日清核算程序,所述日产日清核算程序被所述处理器执行时实现如权利要求1至7中任一项所述的日产日清核算方法的步骤。A Nissan daily clearing accounting device, wherein the Nissan daily clearing accounting device includes a memory, a processor, and a Nissan daily clearing accounting program stored on the memory and running on the processor, and the Nissan daily clearing accounting program When the accounting program is executed by the processor, the steps of the Nissan daily settlement accounting method according to any one of claims 1 to 7 are realized.
- 一种可读存储介质,其中,所述可读存储介质上存储有日产日清核算程序,所述日产日清核算程序被处理器执行时实现如权利要求1至7中任一项所述的日产日清核算方法的步骤。A readable storage medium, wherein a Nissan daily settlement accounting program is stored on the readable storage medium, and when the Nissan daily settlement accounting program is executed by a processor, the method according to any one of claims 1 to 7 is realized. Steps of Nissan Nissan’s accounting method.
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910971754.4A CN110782142A (en) | 2019-10-10 | 2019-10-10 | Daily birth daily clearing accounting method, device, equipment and computer readable storage medium |
CN201910971754.4 | 2019-10-10 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2021068593A1 true WO2021068593A1 (en) | 2021-04-15 |
Family
ID=69385288
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2020/102776 WO2021068593A1 (en) | 2019-10-10 | 2020-07-17 | Daily production and daily clearing accounting method, apparatus and device, and computer-readable storage medium |
Country Status (2)
Country | Link |
---|---|
CN (1) | CN110782142A (en) |
WO (1) | WO2021068593A1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115423390A (en) * | 2022-08-01 | 2022-12-02 | 深圳智汇创想科技有限责任公司 | Method, device, equipment and medium for identifying size of container product |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110782142A (en) * | 2019-10-10 | 2020-02-11 | 深圳点链科技有限公司 | Daily birth daily clearing accounting method, device, equipment and computer readable storage medium |
CN112837171A (en) * | 2021-01-12 | 2021-05-25 | 柏丽德珠宝(广州)有限公司 | Material information calculation method and device for ornament process flow |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1414499A (en) * | 2001-10-26 | 2003-04-30 | 英业达股份有限公司 | Method of automatic calculating manufacturer's record, usance from feed stock inspection result |
US20100138256A1 (en) * | 2007-12-05 | 2010-06-03 | Management Systems Resources, Inc. | Free trade qualification method and system |
CN109784631A (en) * | 2018-12-12 | 2019-05-21 | 广州永霸信息科技股份有限公司 | A kind of production work order generates processing method, system, platform and storage medium |
CN110060110A (en) * | 2019-04-28 | 2019-07-26 | 锋泾(中国)建材集团有限公司 | A kind of the determination method, apparatus and computer readable storage medium of product cost |
CN110782142A (en) * | 2019-10-10 | 2020-02-11 | 深圳点链科技有限公司 | Daily birth daily clearing accounting method, device, equipment and computer readable storage medium |
-
2019
- 2019-10-10 CN CN201910971754.4A patent/CN110782142A/en active Pending
-
2020
- 2020-07-17 WO PCT/CN2020/102776 patent/WO2021068593A1/en active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1414499A (en) * | 2001-10-26 | 2003-04-30 | 英业达股份有限公司 | Method of automatic calculating manufacturer's record, usance from feed stock inspection result |
US20100138256A1 (en) * | 2007-12-05 | 2010-06-03 | Management Systems Resources, Inc. | Free trade qualification method and system |
CN109784631A (en) * | 2018-12-12 | 2019-05-21 | 广州永霸信息科技股份有限公司 | A kind of production work order generates processing method, system, platform and storage medium |
CN110060110A (en) * | 2019-04-28 | 2019-07-26 | 锋泾(中国)建材集团有限公司 | A kind of the determination method, apparatus and computer readable storage medium of product cost |
CN110782142A (en) * | 2019-10-10 | 2020-02-11 | 深圳点链科技有限公司 | Daily birth daily clearing accounting method, device, equipment and computer readable storage medium |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN115423390A (en) * | 2022-08-01 | 2022-12-02 | 深圳智汇创想科技有限责任公司 | Method, device, equipment and medium for identifying size of container product |
Also Published As
Publication number | Publication date |
---|---|
CN110782142A (en) | 2020-02-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021068593A1 (en) | Daily production and daily clearing accounting method, apparatus and device, and computer-readable storage medium | |
US8527317B2 (en) | Service level agreement work prioritization system | |
US8705723B2 (en) | Systems and methods for scheduling contact center agents | |
US20120221709A1 (en) | Mechanism to allow hosted and on-site implementations to manage product assets as specified by a third party | |
US10410152B2 (en) | System and method for automatically and efficiently monitoring software development life cycles | |
WO2021068591A1 (en) | Blockchain-based daily production and daily clearing accounting method, apparatus and device, and storage medium | |
CN109543891A (en) | Method for building up, equipment and the computer readable storage medium of capacity prediction model | |
CN111695877A (en) | Computer-implemented project resource management method, system, device and readable medium | |
CN111367530A (en) | Code auditing method, terminal and server based on self-defined auditing rule | |
US7640531B1 (en) | Productivity measurement and management tool | |
US20200027043A1 (en) | Construction project management system and method thereof | |
CN115471200A (en) | Cloud computing-based human resource data management system, method and device | |
CN113129036A (en) | Intelligent management method and device | |
CN106651290A (en) | Flow management software system and the authority management method thereof | |
CN113570175B (en) | Method for establishing industrial refined working hour and quantity management platform | |
CN107016573B (en) | Application evaluation method and evaluation system | |
JP2010140430A (en) | System, method and program for managing attendance | |
Kang et al. | A framework for measuring and managing value achievement in business processes | |
Simonova | Identification of IT-service metrics for a business process when planning a transition to outsourcing | |
CN114912880A (en) | False duty processing method and device, computer equipment and storage medium | |
CN114519626A (en) | Salary management method and system based on BIM model | |
US20200097870A1 (en) | Work task commitment manager | |
CN108683551A (en) | A kind of method and device of duct type flow control | |
CN111754120A (en) | Technical resource productivity analysis method, device, storage medium and equipment | |
CN111159988A (en) | Model processing method and device, computer equipment and storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 20873787 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20873787 Country of ref document: EP Kind code of ref document: A1 |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20873787 Country of ref document: EP Kind code of ref document: A1 |
|
32PN | Ep: public notification in the ep bulletin as address of the adressee cannot be established |
Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 23.09.2022) |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 20873787 Country of ref document: EP Kind code of ref document: A1 |