WO2007082351A1 PCT/AU2007/000053 AU2007000053W WO2007082351A1 WO 2007082351 A1 WO2007082351 A1 WO 2007082351A1 AU 2007000053 W AU2007000053 W AU 2007000053W WO 2007082351 A1 WO2007082351 A1 WO 2007082351A1
Authority
WO
WIPO (PCT)
Prior art keywords
control system
data processing
power
processing units
power management
Prior art date
Application number
PCT/AU2007/000053
Other languages
French (fr)
Inventor
David Michael Hart
Murray Kenneth Thomas Stewart
Original Assignee
Datatainer Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2006900335A external-priority patent/AU2006900335A0/en
Application filed by Datatainer Pty Ltd filed Critical Datatainer Pty Ltd
Publication of WO2007082351A1 publication Critical patent/WO2007082351A1/en
Priority to US12/178,568 priority Critical patent/US20090050591A1/en

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/16Constructional details or arrangements
    • G06F1/20Cooling means
    • G06F1/206Cooling means comprising thermal management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/16Constructional details or arrangements
    • G06F1/18Packaging or power distribution
    • G06F1/181Enclosures
    • G06F1/182Enclosures with special features, e.g. for use in industrial environments; grounding or shielding against radio frequency interference [RFI] or electromagnetical interference [EMI]
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F1/00Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
    • G06F1/26Power supply means, e.g. regulation thereof
    • G06F1/32Means for saving power
    • G06F1/3203Power management, i.e. event-based initiation of a power-saving mode
    • G06F1/3234Power saving characterised by the action undertaken
    • G06F1/329Power saving characterised by the action undertaken by task scheduling
    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05KPRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
    • H05K7/00Constructional details common to different types of electric apparatus
    • H05K7/14Mounting supporting structure in casing or on frame or rack
    • H05K7/1485Servers; Data center rooms, e.g. 19-inch computer racks
    • H05K7/1497Rooms for data centers; Shipping containers therefor
    • HELECTRICITY
    • H05ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
    • H05KPRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
    • H05K7/00Constructional details common to different types of electric apparatus
    • H05K7/20Modifications to facilitate cooling, ventilating, or heating
    • H05K7/20709Modifications to facilitate cooling, ventilating, or heating for server racks or cabinets; for data centers, e.g. 19-inch computer racks
    • H05K7/20718Forced ventilation of a gaseous coolant
    • H05K7/20745Forced ventilation of a gaseous coolant within rooms for removing heat from cabinets, e.g. by air conditioning device
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02DCLIMATE CHANGE MITIGATION TECHNOLOGIES IN INFORMATION AND COMMUNICATION TECHNOLOGIES [ICT], I.E. INFORMATION AND COMMUNICATION TECHNOLOGIES AIMING AT THE REDUCTION OF THEIR OWN ENERGY USE
    • Y02D10/00Energy efficient computing, e.g. low power processors, power management or thermal management

Definitions

  • the present invention relates to apparatus for providing data processing capabilities, and in ' particular to transportable apparatus for providing portable or fixed data processing capabilities.
  • the present invention provides apparatus for providing data processing capabilities, the apparatus including a container defining: a) a first portion for housing a number of data processing units; and, b) a second portion including: i) a power management system for supplying power to the data processing units; ii) a climate control system for at least partially controlling the climate in the first portion; and, iii) a control system for at least partially controlling the power management system.
  • first and second portions are physically separated by a dividing wall.
  • the dividing wall is fireproof.
  • the container includes first and second sealed doors for providing access to the first and second portions respectively.
  • the container typically includes: a) an inner wall; b) an outer wall; and, c) an insulating layer provided between the inner and outer walls.
  • processing units are provided on moveable racks.
  • the power management system includes at least one of: a) a generator; b) at least one battery; c) solar panel; and, d) a connector for coupling to an external power source.
  • the climate control system includes at least one of: a) an air filtration unit; b) an absorption chiller; and, c) a phase change air conditioning unit.
  • the climate control system includes: a) a primary cooling mechanism; b) a secondary cooling mechanism; and, c) a thermostatic control for selectively activating the primary and secondary cooling systems.
  • the climate control system is for controlling at least one of: a) the temperature; and, b) the humidity.
  • the power management system includes a generator and wherein the climate control system includes an absorption chiller operable using waste heat from exhaust gases generated by the generator.
  • control system includes at least one processing system.
  • control system is for: a) monitoring power usage requirements; and, b) selectively activating one or more power supply mechanisms in accordance with the monitored usage requirements.
  • control system is for: a) monitoring data processing requirements; and, b) selectively activating data processing units in accordance with the data processing requirements.
  • Figure 1 is a schematic diagram of an example of data processing apparatus
  • Figure 2 is a schematic diagram of an example of a processing system for use in the apparatus of Figure 1;
  • Figure 3 is a flow chart of an example of the control process performed by the processing system of Figure 2;
  • Figure 4A is a schematic plan view of a second example of a data processing apparatus;
  • Figure 4B is a schematic cross sectional view of the data processing apparatus of Figure 4 A;
  • Figure 5 A is a schematic plan view of a first example of a rack arrangement
  • Figure 5B is a schematic plan view of a second example of a rack arrangement
  • Figure 6 is a schematic diagram of an absorption chiller; and, Figures 7 A and 7B are schematic diagrams of an example of a tent arrangement.
  • the apparatus is formed from a container 100, such as a shipping container or the like, having an outer wall 101 and a dividing wall 102, which operates to define a plant compartment 103 and a data processing compartment 104. Access to each of the plant compartment 103 and the data processing compartment 104 can be provided via respective doors 105, 106.
  • a container 100 such as a shipping container or the like, having an outer wall 101 and a dividing wall 102, which operates to define a plant compartment 103 and a data processing compartment 104. Access to each of the plant compartment 103 and the data processing compartment 104 can be provided via respective doors 105, 106.
  • the plant compartment 103 typically includes a control system 110, a power management system 120 and a climate control system 130.
  • the data processing compartment 104 includes data processing units shown generally at 140, as well as an access space 141 to allow physical access to the data processing units.
  • the data processing units 140 may be formed from a combination of one or more data processing devices, but typically include a number of servers or other processing systems, configured to provide required data processing capabilities.
  • the power is supplied to the processing units 140 using the power management system 120.
  • the power management system 120 may utilise one or more of a number of different power supply mechanisms depending on the circumstances in which the system is to be used, and the resources available. Thus, for example, power can be obtained via an external power supply, such as mains electricity, if this is available. Additionally, or alternatively, the power management system 120 can utilise a generator, batteries, solar panels, or the like, to provide electricity when external supplies are unavailable, or provide insufficient power. This allows the data processing systems to be used in a variety of remote environments.
  • the processing units 140 will generate a significantly amount of heat and it is therefore important to ensure the data compartment 104 is adequately cooled.
  • humidity and airborne contaminants, such as dust can represent a major problem.
  • the climate control system 130 is adapted to maintain the data compartment 104 within a predetermined climate range.
  • the climate control system 130 typically includes air conditioning equipment of one form or another, as well as air filtration and/or air scrubbing systems, to ensure the air is not overly contaminated with dust or the like.
  • the climate control system 130 operates to monitor the climate within the data compartment 104 and supply appropriately conditioned air via a suitable ducting system.
  • This control can be a simple thermostatic control system, or may utilise more complex control mechanisms depending on the implementation.
  • the configuration of the power management and climate control systems 120, 130 can be customised depending on the circumstances in which the apparatus is to be used. This can be achieved for example by providing specific component configurations based on the intended use, and/or by providing appropriate control of the power management and climate control systems 120, 130, using the control system 110.
  • the control system 110 is also typically capable of monitoring operation of the apparatus and controlling the operation of the power management and climate control systems 120, 130, as well as the processing units 140, as required. This can be performed by any suitable form of control system, but is typically achieved using one or more processing systems implementing appropriate control algorithms.
  • FIG. 2 An example processing system is shown in Figure 2.
  • the processing system 200 is formed from a processor 210, a memory 211, an input/output I/O device 212 such as a keyboard, mouse, display or the like, and an external interface 213, interconnected via a bus 214.
  • control system 110 is coupled to the power management system 120 and the climate control system 130, as well as any additional sensors 215, via the external interface 213.
  • the sensors 215 may include a range of different types of sensors, to allow the control system to monitor various operating parameters, such as the current processing unit utilisation, available power supplies, and the like.
  • processing system 200 may be any suitable form of control system such as a computer system, laptop, desktop, standard rack-mountable server or data/voice/video communications equipment, custom hardware, PLC (programmable logic controller), or the like.
  • control system such as a computer system, laptop, desktop, standard rack-mountable server or data/voice/video communications equipment, custom hardware, PLC (programmable logic controller), or the like.
  • the climate control system 130 operates based on a simple thermostatic control system, using a primary phase change cooling system and a back-up secondary system in case additional cooling is required.
  • control system 110 determines data processing power requirements, which will depend, for example, on the number of processing units 140 that are required to operate. In one example, this can be controlled using server virtualisation techniques, as will be described in more detail below.
  • the control system 110 monitors the climate control system to determine its current power usage requirements, based on the current load on the climate system, allowing total power management requirements to be calculated.
  • control system 110 determines power supply availability from the power management system 120, and uses this information to determine if sufficient power can be provided to satisfy total power requirements at step 340. If so the process can proceed to step 350, to control the power management system 120 if required, for example, by selectively activating/deactivating one or more additional power supplies, such as back-up supplies, if required.
  • control system 110 proceeds to step 360 to allow rescheduling of the data processing.
  • control system 110 can operate to adjust the operation of the climate control system 130, for example, to reduce the power supply requirements by altering the climate control mechanism used.
  • control system 110 can therefore control the various systems to balance the power supply requirements of both the climate control system 130 and the data processing units 140. This allows the control system 110 to maximise the ability of the system to provide required data processing capabilities, whilst maintaining the required climate in the data compartment 104, and using the available power supplies.
  • climate control system 130 and the data processing units 140 will be interdependent. For example, if there is an increase in data processing requirements, this typically leads to an increase in the power required by the processing units 140, as well as a consequent increase in temperature in the data compartment 104. In turn, this increases cooling requirements, which can further increase power supply requirements.
  • cooling mechanisms available may be dependent on the current power supply used. For example, if cooling is to be provided by way of an absorption chiller, as will be described in more detail below, this may require that the generator is operational or that a supplemental boiler is utilised.
  • control system 110 may include information, algorithms or other functions defining different operating scenarios. This information can specify for certain operating parameters, the cooling mechanism and power supply mechanisms that should be used. This information can be stored, for example, as a look-up table (LUT) in the memory 211, so that the control system 110 can access the LUT and allow appropriate control to be provided, or as a traditional control system, a fuzzy logic control system, or a neural network control system.
  • LUT look-up table
  • the use of controlling mechanisms described above can be implemented using similar arrangements to the "enterprise systems management platforms" such as the IBM Tivoli Framework, albeit extended to allow control of computing resources, power consumption, cooling and the like.
  • the container 400 includes an outer wall 401 and an inner wall 402, having insulation 403 provided therebetween. This operates to insulate the internal environment, to thereby reduce the climate control requirements.
  • the doors 105, 106 may also be provided in tents 405, 406 as shown. The tents act as airlocks, thereby helping to provide an additional level of environmental insulation.
  • the control system 110 is formed from a master controller (MC) 410 and a container management system (CMS) 411.
  • MC master controller
  • CMS container management system
  • each of the MC 410 and the CMS 411 may be implemented by a respective processing system 200, although other suitable control hardware may be used.
  • the power management system 120 includes a generator 420, a set of batteries 421 and optionally a roof mounted solar panels shown generally at 422.
  • the power management system is connected to the processing units via appropriate cables 423, 424 as will be described in more detail below. Connection (not shown) to an external power supply may also be provided.
  • the climate control system 130 includes an evaporator 430, an air filter system 431, an absorber 432 and a compressor 433.
  • the evaporator and the absorber 430, 432 can be used as an absorption chiller, whilst the compressor 433 can provide phase change air conditioning, and air filtering, as will be described in more detail below.
  • Ducting 434 having movable outlet vents 435, is provided to allow conditioned air to be supplied from the climate control system 130. Any number of ducts and vents can be provided and adjusted for various rack placement schemes such as hot/cold isles, and three vents 435 are shown for the purpose of example only. Similarly, whilst the duct 434 shown in Figure 4B is coupled to the air filtration system 431 this is for the purpose of clarity only and the ducting 434 may be coupled to any one or more of the climate control system components as required.
  • the data compartment 104 includes a ceiling framework apparatus 408 for supporting the cabling 423 and the ducting 434.
  • Racks 440 having shelves 443, are provided for housing the processing units 140.
  • the racks are movably mounted on floor mounted between rack tracks 441, and corresponding ceiling mounted rack guides 442, thereby allowing the racks 440 to be moved as shown by rack in dotted lines. This allows access to be provided to the processing units 140, whilst maximising the volume of plant compartment that can be used for containing processing units 140.
  • the processing units 140 In use, power is provided to the processing units 140 via the cabling 423, 424, which in this example is shown coupled to the generator 420 for the purpose of clarity only.
  • the cable 424 forms a flexible umbilical cable bundle that is capable of ensuring coupling between the power management system 120 and the racks 440 even when the racks are moved as shown by dotted lines.
  • Container 400 can have exterior physical properties (i.e. dimensions, corner fittings, structural integrity, etc.) that are fully compliant with ISO specifications for 20', 30' and 40' shipping containers. This allows for easy transport of the container 400 using existing transportation systems, thereby allowing the system to be readily shipped to remote areas as required.
  • exterior physical properties i.e. dimensions, corner fittings, structural integrity, etc.
  • the container 400 when used in an emergency relief situation, can be shipped together with other emergency supplies, allowing it to be provided onsite for controlling emergency supply distribution.
  • a typical ISO shipping container is constructed with corrugated single sheet steel and unsealed doors
  • the container 400 is constructed with exterior structural material, such as steel or aluminium, to form the outer wall 401.
  • the inner wall 402 is used to retain the insulation 403 in place, and can therefore be formed from a lining or the like, or can alternatively also be formed from structural material, such as steel, although in general, the inner wall is not required to provide structural strength. It will be appreciated that this arrangement is particularly suited for extreme environments, such as high or low temperature environments.
  • the exterior wall 401 may also be treated for protection against the elements before a final finish is applied. This can include, for example, the use of camouflage paint or armour, in the event that the system is used in a military context.
  • the dividing wall 102 is typically formed from a fire-rated wall, to thereby separate the data compartment 104 and plant compartment 103. This ensures that should a fire occur in the plant compartment 103, this will not effect data or equipment housed in the data compartment 104.
  • vents, access doors, panels and ports can be provided, including, but not limited to:
  • an external mains power connection port for example, with internally housed receptacles, eg. 3-phase 440V 30A receptacles, 10 ct); and,
  • a data connection port for example, with internal jacks, eg. RJ45 for copper Cat-5e or Cat6, SC connectors for multi-mode fibre, etc.
  • internal jacks eg. RJ45 for copper Cat-5e or Cat6, SC connectors for multi-mode fibre, etc.
  • the tent arrangement can also be extended to provide additional space, for example, to allow users work space, or the like.
  • An example tent arrangement is shown in more detail in Figures 7A and 7B.
  • the tent 706 extends along the length of the data compartment 104, as shown, to thereby provide the additional working space.
  • the tent is formed from a fold-out roof section 701, and a fold-out floor section 702, having feet 703.
  • the fold-out roof and floor sections 701, 702 can be folded against the side of the container 400, being folded out, as shown in dotted lines at 704, 705, when the system is being used.
  • the roof will typically clip into place using an appropriate locking mechanism (not shown), to retain the roof in place, whilst the feet 703 extend downwards as shown in Figure 7A to support the floor 702.
  • Suitable material 707 can then be attached to the floor and roof as required to form the tent 706, as shown.
  • the data compartment 104 can be sealed to allow it to be pressurised with a positive air pressure to help reduce environmental contamination, for example, from dust and the like. Additionally, air quality can be further maintained by having the air cooled and filtered by the climate control system 130.
  • the container walls 401, 402 provide acoustic and thermal insulation, whilst an internal static electricity control system can be provided through the use of anti-static floor tiles.
  • One or more additional optional features may be implemented, such as:
  • processing units 140 may provide any form of data processing capabilities, depending on the desired use.
  • Example configurations include: • mid density (standard): balanced storage, CPU and network throughput;
  • the racks are in the form of standard width "19-inch" racks for rack- mountable equipment, in vertical increments of standard rack units (RU), with approximately 40 RU spaces per rack. Individual rows of racks may vary in depth (eg. 600mm, 700mm, etc.), to be specified at build-time. All racks can include an integrated cable management system.
  • the rack configuration is typically designed to maximise the use of space with complimentary ceiling-hanging flexible power and data cabling umbilicals and ventilation ducts and vents with adjustable placement to maximise cooling efficacy and efficiency.
  • the example of Figure 5 A includes five rows of three racks 440 each.
  • the rack rows are placed adjacent to the wall opposite the door 106 and move in the direction of the arrows 500, along the length of the data compartment 104, using rack-mounted steel roller bearings, or the like, running over the floor tracks 441 and the guide rails 442.
  • Racks rows are positioned with pins and secured with bolts, both running through the roller bearing rail and into the steel track secured on the floor.
  • the number of rows may be varied depending on the size of the container 400 and the data compartment 104, or by altering the depth of the racks in each row
  • cabling management is used to provide specified power and data cabling to each rack through per-rack flexible umbilical cable bundles, and per-rack cable management.
  • the cabling will typically be adapted to provide, for each rack unit 444: • a single 120/240V 250W/500W (mean/peak) power lead with standard 3-prong plug; and,
  • the plant compartment 103 typically equipment housed in the plant compartment 103 is placed to maximise the use of space and allow for adequate serviceability.
  • the plant compartment is also typically acoustically baffled and actively fan- ventilated with outdoor air.
  • the integrated power management system is designed with several operating and backup modes, facility for multiple input power sources, facility for several power storage systems, and provides conditioned power with maximum efficiency during normal operation.
  • Power sources can include but are not limited to an external mains supply, solar panels 422 and the generator 420, while temporary backup can be provided by batteries 421 or by batteries distributed throughout racks 440. Power is typically conditioned to ensure proper operation of data compartment equipment; with operation being coordinated and monitored with the MC 410.
  • the system may also implement a power-up sequence to meet total power use specifications which is to be implemented by an appropriate network management system, the MC, or UPS control system, as required. This may be provided together with a per-rack power distribution controller for sequenced power-up and individual remote RU power up or down.
  • the integrated cooling system can include a range of cooling mechanisms, including passive solar, ventilation, air-to-air heat exchange, absorption cooling, and traditional phase change cooling.
  • the system uses a primary and back-up system using redundant independent thermostatic control with the primary system typically set to a range of 20-21 0 C and the backup system set to a range of 22-23 0 C.
  • Return air ducting is strategically placed on the ceiling to provide optimal air flow and cooling.
  • a HEPA air filtration system is integrated into the ducting system.
  • a bypass for outdoor air is used to create a small positive pressure.
  • the primary cooling system of data compartment is a phase change cooling system, backup for which is provided by an absorption cooling system.
  • An example of an absorption cooling system will now be described with reference to Figure 6.
  • the system uses the evaporator 430, which has an inlet 632 and an outlet 633.
  • the evaporator 430 is coupled to the absorber 432, via a pipe 635, which is in turn connected to a heating system 636 via pipes 637A, 637B as shown.
  • a pipe 641, having an inlet 642, and an outlet 643 receives heat in the form of waste gases from the generator 420, as shown at 640, and transfers this to a heat exchanger 636.
  • the heat exchanger 636 is connected to a condenser 638 via a pipe 639.
  • the condenser 638 typically generates waste heat as shown at 644 and is also coupled to the evaporator 430 via a pipe 645.
  • the system utilises a solution formed form a combination of a refrigerant and an absorber in order to provide heat transfer mechanisms, as will now be described.
  • the solution is either a water/lithium bromide or an ammonia/water combination as will be appreciated by a person skilled in the art.
  • the evaporator 430 operates to receive liquid refrigerant from the condenser 638, via the pipe 645.
  • the refrigerant is provided into a low-pressure environment within the evaporator 430, and evaporates, thereby extracting heat from air supplied to the inlet 632, via an appropriate heat exchanger.
  • the chilled air is then output via the outlet 633, to the duct 434, whilst the evaporated refrigerant is transferred via the pipe 635 to the absorber 432, where it is absorbed by a refrigerant-depleted solution.
  • the solution is transferred via the pipe 637A to the heat exchanger 636, which operates to heat the solution using fluid in the pipe 641, thereby causing the refrigerant to be evaporated.
  • the remaining refrigerant-depleted solution returns to the absorber 432 via the pipe 637B, whilst the vaporised refrigerant is transferred via the pipe 639 to the condenser 638.
  • the vaporised refrigerant is allowed to condense with waste heat being output at 644 before being transferred via the pipe 645 to the evaporator 430, thereby allowing the cycle to be repeated.
  • climate control features can be implemented, such as:
  • in-floor ducting and vents can be provided together with a shutter system to restrict airflow to special narrow vents for temporary operation in service configuration.
  • the racks can be designed to enhance airflow from underneath each rack to the front and back of each rack.
  • the absorption cooling component can also be adapted to provide 100% primary or backup to electrically powered phase change cooling in the data compartment.
  • the plant compartment 103 is designed to be cooled with outdoor air ventilation when the generator is not in use and with absorption cooling when the generator is in use or if the compartment overheats.
  • the energy required for basic absorption cooling is provided by surplus heat from the generator and is used to cool the generator, plus provide supplemental cooling to the data compartment, thereby reducing power requirements of the data compartment cooling system.
  • the CMS 411 can be used to monitor key plant components and vital statistics, and report faults via a customer-provided gateway such as IMPI, SNMP, or simpler SMTP.
  • the CMS includes a Linux-based controller which interfaces via serial or Ethernet connections to management/monitor modules on individual components such as the generator, AC systems, etc.
  • An external data port can be provided adjacent to the CMS 411 for allowing external connectivity.
  • any suitable arrangement may be used, including, for example, system integration with existing network management systems.
  • the container 400 can include independent fire suppression systems for the plant compartment and the data compartment, such as gas based suppression systems. Such systems would typically be controlled by the CMS 411.
  • the CMS 411 can also monitor and schedule servicing and maintenance for all included equipment and other moving parts.
  • Power management and service schedule management of the processing units 140 can be enhanced through the use of server virtualisation technologies traditionally used primarily for server consolidation (eg. virtual machines, hypervisors, clustering systems, message passing systems, etc.).
  • server virtualisation technologies traditionally used primarily for server consolidation (eg. virtual machines, hypervisors, clustering systems, message passing systems, etc.).
  • the use of virtualisation to manage power includes switching off processing units during periods of underutilisation. This is possible because virtualisation allows the "processing unit" which is visible to applications and users to be a collection of individual units from a pool, where units can enter or leave the active pool without applications or users taking notice.
  • An example of the use of virtualisation to manage service schedule management includes remote recovery from component failures and replacement of failed parts deferred to regularly scheduled times by removing affected units from the active pool.
  • Service and maintenance schedules for, including service for unscheduled failures, may be also be synchronised with plant compartment service schedules.
  • the container is shipped independently of the processing units 140, with the deployment and final systems integration for non-hardened customer-provided equipment occurring on site.
  • the tents 405, 406 can be used to provide an airlock between the container 400 and the delivery container/trailer, to help provide protection from the elements, including dust, rain and heat.
  • hardened equipment may be installed in the container 400 prior to shipping.
  • Interior space permitting, field-installable external apparatus (such as optional solar array or wireless communications equipment) may be stowed internally for shipping.
  • wheels, axles, lights and other fixtures may be permanently attached to the apparatus in consideration of continued transportability and/or local government classifications, requirements and regulations.
  • the above described system provides a configurable and self-contained "data processing system” packaged in a purpose-built container for field deployment which can be ISO standard size (10ft, 20ft, 30ft or 40ft), pallet size, or any other suitable size.
  • the container design and integrated systems management provides high reliability with a long service life, maximised power efficiency, and field serviceability balanced with optimised component density.
  • the container is designed to allow for rapid-deploy (and rapid- redeploy) permanent or semi-permanent installations (fixed, for example via bolts through corner castings or guy wires), while remaining cost-competitive with fixed data centre infrastructure and operations.
  • the system can be used in applications spanning multiple industries, including any corporation, organisation, project, government body or defence with data processing, media, or communications needs.
  • This provides an ideal solution for capacity planning (eg. carpark overflow of fixed data centres, data warehousing, etc.), continuity planning (eg. backup & disaster recovery), remote deployment (eg. branch offices, conventions and special events, etc.), military field deployment, and emergency deployment.
  • capacity planning eg. carpark overflow of fixed data centres, data warehousing, etc.
  • continuity planning eg. backup & disaster recovery
  • remote deployment eg. branch offices, conventions and special events, etc.
  • military field deployment e. branch offices, conventions and special events, etc.
  • emergency deployment e. branch offices, conventions and special events, etc.
  • the above described apparatus can provide an integrated self-contained transportable and modular (dual-mode, temporary or fixed) data processing centre that is capable of providing many or all of the features normally provided by a full-scale data centre, whilst maximising the use of energy and space.

Landscapes

  • Engineering & Computer Science (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Computer Hardware Design (AREA)
  • Microelectronics & Electronic Packaging (AREA)
  • Human Computer Interaction (AREA)
  • Thermal Sciences (AREA)
  • Electromagnetism (AREA)
  • Power Engineering (AREA)
  • Cooling Or The Like Of Electrical Apparatus (AREA)

Abstract

Apparatus for providing data processing capabilities. The apparatus includes a container defining a first portion for housing a number of data processing units and a second portion including a power management system for supplying power to the data processing units, a climate control system for at least partially controlling the climate in the first portion and a control system for at least partially controlling the power management system.

Description

DATA PROCESSING APPARATUS
Background of the Invention
The present invention relates to apparatus for providing data processing capabilities, and in ' particular to transportable apparatus for providing portable or fixed data processing capabilities.
Description of the Prior Art
The reference to any prior art in this specification is not, and should not be taken as, an acknowledgment or any form of suggestion that the prior art forms part of the common general knowledge.
In a number of situations it is necessary to provide data processing capabilities in environments where service infrastructure, space or deployment-time is limited or otherwise compromised. This can occur, for example, in emergency relief situations where it is necessary to provide a data processing capabilities to coordinate rescue or aid teams, as well as to identify and process individuals affected by the emergency, such as refugees, disaster victims or the like. Other situational examples include rapid-deployment, for reasons of business or military logistics. Non-situational examples include regions which are chronically underdeveloped or have development compromised by long-term environmental changes or conflict.
In such situations there is often no, or only limited, power available and it is therefore typical to use a low power battery operated device such as a laptop, PDA, or the like. However, this suffers from a number of disadvantages. For example, power sources are still required in order to recharge the batteries, and the data processing capabilities of such portable devices are typically limited thereby restricting the amount of processing that can be performed.
Consequently, in many cases it is necessary to arrange for data to be transferred to another location to allow suitable processing. However, this may require complex communications technology, such as a satellite link, which can inturn require significant power. Additionally, this suffers from time lag caused in transferring data for processing. Accordingly, there is a need to provide a system that can be used for implementing data processing capabilities in remote or otherwise restricted environments.
Summary of the Present Invention
In a first broad form the present invention provides apparatus for providing data processing capabilities, the apparatus including a container defining: a) a first portion for housing a number of data processing units; and, b) a second portion including: i) a power management system for supplying power to the data processing units; ii) a climate control system for at least partially controlling the climate in the first portion; and, iii) a control system for at least partially controlling the power management system.
Typically the first and second portions are physically separated by a dividing wall.
Typically the dividing wall is fireproof.
Typically the container includes first and second sealed doors for providing access to the first and second portions respectively.
Typically the container includes: a) an inner wall; b) an outer wall; and, c) an insulating layer provided between the inner and outer walls.
Typically the processing units are provided on moveable racks.
Typically the power management system includes at least one of: a) a generator; b) at least one battery; c) solar panel; and, d) a connector for coupling to an external power source.
Typically the climate control system includes at least one of: a) an air filtration unit; b) an absorption chiller; and, c) a phase change air conditioning unit.
Typically the climate control system includes: a) a primary cooling mechanism; b) a secondary cooling mechanism; and, c) a thermostatic control for selectively activating the primary and secondary cooling systems.
Typically the climate control system is for controlling at least one of: a) the temperature; and, b) the humidity.
Typically the power management system includes a generator and wherein the climate control system includes an absorption chiller operable using waste heat from exhaust gases generated by the generator.
Typically the control system includes at least one processing system.
Typically the control system is for: a) monitoring power usage requirements; and, b) selectively activating one or more power supply mechanisms in accordance with the monitored usage requirements.
Typically the control system is for: a) monitoring data processing requirements; and, b) selectively activating data processing units in accordance with the data processing requirements.
Brief Description of the Drawings
An example of the present invention will now be described with reference to the accompanying drawings, in which: -
Figure 1 is a schematic diagram of an example of data processing apparatus; Figure 2 is a schematic diagram of an example of a processing system for use in the apparatus of Figure 1;
Figure 3 is a flow chart of an example of the control process performed by the processing system of Figure 2; Figure 4A is a schematic plan view of a second example of a data processing apparatus;
Figure 4B is a schematic cross sectional view of the data processing apparatus of Figure 4 A;
Figure 5 A is a schematic plan view of a first example of a rack arrangement;
Figure 5B is a schematic plan view of a second example of a rack arrangement;
Figure 6 is a schematic diagram of an absorption chiller; and, Figures 7 A and 7B are schematic diagrams of an example of a tent arrangement.
Detailed Description of the Preferred Embodiments
An example of apparatus for providing data processing capabilities will now be described with reference to Figure 1.
In this example the apparatus is formed from a container 100, such as a shipping container or the like, having an outer wall 101 and a dividing wall 102, which operates to define a plant compartment 103 and a data processing compartment 104. Access to each of the plant compartment 103 and the data processing compartment 104 can be provided via respective doors 105, 106.
The plant compartment 103 typically includes a control system 110, a power management system 120 and a climate control system 130. The data processing compartment 104 includes data processing units shown generally at 140, as well as an access space 141 to allow physical access to the data processing units.
The data processing units 140 may be formed from a combination of one or more data processing devices, but typically include a number of servers or other processing systems, configured to provide required data processing capabilities.
In use, the power is supplied to the processing units 140 using the power management system 120. The power management system 120 may utilise one or more of a number of different power supply mechanisms depending on the circumstances in which the system is to be used, and the resources available. Thus, for example, power can be obtained via an external power supply, such as mains electricity, if this is available. Additionally, or alternatively, the power management system 120 can utilise a generator, batteries, solar panels, or the like, to provide electricity when external supplies are unavailable, or provide insufficient power. This allows the data processing systems to be used in a variety of remote environments.
Typically the processing units 140 will generate a significantly amount of heat and it is therefore important to ensure the data compartment 104 is adequately cooled. Similarly, in some environments, humidity and airborne contaminants, such as dust, can represent a major problem. Accordingly the climate control system 130 is adapted to maintain the data compartment 104 within a predetermined climate range.
To achieve this, the climate control system 130 typically includes air conditioning equipment of one form or another, as well as air filtration and/or air scrubbing systems, to ensure the air is not overly contaminated with dust or the like. In general, the climate control system 130 operates to monitor the climate within the data compartment 104 and supply appropriately conditioned air via a suitable ducting system. This control can be a simple thermostatic control system, or may utilise more complex control mechanisms depending on the implementation.
It will be appreciated that the configuration of the power management and climate control systems 120, 130 can be customised depending on the circumstances in which the apparatus is to be used. This can be achieved for example by providing specific component configurations based on the intended use, and/or by providing appropriate control of the power management and climate control systems 120, 130, using the control system 110.
The control system 110 is also typically capable of monitoring operation of the apparatus and controlling the operation of the power management and climate control systems 120, 130, as well as the processing units 140, as required. This can be performed by any suitable form of control system, but is typically achieved using one or more processing systems implementing appropriate control algorithms.
An example processing system is shown in Figure 2. In this example the processing system 200 is formed from a processor 210, a memory 211, an input/output I/O device 212 such as a keyboard, mouse, display or the like, and an external interface 213, interconnected via a bus 214.
In this example, the control system 110 is coupled to the power management system 120 and the climate control system 130, as well as any additional sensors 215, via the external interface 213. The sensors 215 may include a range of different types of sensors, to allow the control system to monitor various operating parameters, such as the current processing unit utilisation, available power supplies, and the like.
This allows the processing system 200 to receive data regarding the current operation of the power management and climate control systems 120, 130, and provide any appropriate control signals required. This may be achieved using suitable control algorithms stored in the memory 211.
From this, it would be appreciated that the processing system 200 may be any suitable form of control system such as a computer system, laptop, desktop, standard rack-mountable server or data/voice/video communications equipment, custom hardware, PLC (programmable logic controller), or the like.
An example control process implemented by the control system 110 will now be described with reference to Figure 3. For the purpose of this example, the climate control system 130 operates based on a simple thermostatic control system, using a primary phase change cooling system and a back-up secondary system in case additional cooling is required.
In this example, at step 300 the control system 110 determines data processing power requirements, which will depend, for example, on the number of processing units 140 that are required to operate. In one example, this can be controlled using server virtualisation techniques, as will be described in more detail below.
Simultaneously, at step 310, the control system 110 monitors the climate control system to determine its current power usage requirements, based on the current load on the climate system, allowing total power management requirements to be calculated.
At step 330, the control system 110 determines power supply availability from the power management system 120, and uses this information to determine if sufficient power can be provided to satisfy total power requirements at step 340. If so the process can proceed to step 350, to control the power management system 120 if required, for example, by selectively activating/deactivating one or more additional power supplies, such as back-up supplies, if required.
If sufficient power cannot be provided, the control system 110 proceeds to step 360 to allow rescheduling of the data processing. Alternatively, or additionally, the control system 110 can operate to adjust the operation of the climate control system 130, for example, to reduce the power supply requirements by altering the climate control mechanism used.
It will be appreciated that the control system 110 can therefore control the various systems to balance the power supply requirements of both the climate control system 130 and the data processing units 140. This allows the control system 110 to maximise the ability of the system to provide required data processing capabilities, whilst maintaining the required climate in the data compartment 104, and using the available power supplies.
It will be appreciated that operation of the climate control system 130 and the data processing units 140 will be interdependent. For example, if there is an increase in data processing requirements, this typically leads to an increase in the power required by the processing units 140, as well as a consequent increase in temperature in the data compartment 104. In turn, this increases cooling requirements, which can further increase power supply requirements.
Additionally, the cooling mechanisms available may be dependent on the current power supply used. For example, if cooling is to be provided by way of an absorption chiller, as will be described in more detail below, this may require that the generator is operational or that a supplemental boiler is utilised.
To take these issues into account, the control system 110 may include information, algorithms or other functions defining different operating scenarios. This information can specify for certain operating parameters, the cooling mechanism and power supply mechanisms that should be used. This information can be stored, for example, as a look-up table (LUT) in the memory 211, so that the control system 110 can access the LUT and allow appropriate control to be provided, or as a traditional control system, a fuzzy logic control system, or a neural network control system. The use of controlling mechanisms described above can be implemented using similar arrangements to the "enterprise systems management platforms" such as the IBM Tivoli Framework, albeit extended to allow control of computing resources, power consumption, cooling and the like.
A second specific example of a portable data processing apparatus will now be described with reference to Figures 4 A and 4B. In this example, similar reference numerals are used to denote similar features to the earlier examples.
The container 400 includes an outer wall 401 and an inner wall 402, having insulation 403 provided therebetween. This operates to insulate the internal environment, to thereby reduce the climate control requirements. The doors 105, 106 may also be provided in tents 405, 406 as shown. The tents act as airlocks, thereby helping to provide an additional level of environmental insulation.
The control system 110 is formed from a master controller (MC) 410 and a container management system (CMS) 411. In general each of the MC 410 and the CMS 411, may be implemented by a respective processing system 200, although other suitable control hardware may be used.
The power management system 120 includes a generator 420, a set of batteries 421 and optionally a roof mounted solar panels shown generally at 422. The power management system is connected to the processing units via appropriate cables 423, 424 as will be described in more detail below. Connection (not shown) to an external power supply may also be provided.
The climate control system 130 includes an evaporator 430, an air filter system 431, an absorber 432 and a compressor 433. In use, the evaporator and the absorber 430, 432 can be used as an absorption chiller, whilst the compressor 433 can provide phase change air conditioning, and air filtering, as will be described in more detail below.
Ducting 434, having movable outlet vents 435, is provided to allow conditioned air to be supplied from the climate control system 130. Any number of ducts and vents can be provided and adjusted for various rack placement schemes such as hot/cold isles, and three vents 435 are shown for the purpose of example only. Similarly, whilst the duct 434 shown in Figure 4B is coupled to the air filtration system 431 this is for the purpose of clarity only and the ducting 434 may be coupled to any one or more of the climate control system components as required.
The data compartment 104 includes a ceiling framework apparatus 408 for supporting the cabling 423 and the ducting 434. Racks 440, having shelves 443, are provided for housing the processing units 140. The racks are movably mounted on floor mounted between rack tracks 441, and corresponding ceiling mounted rack guides 442, thereby allowing the racks 440 to be moved as shown by rack in dotted lines. This allows access to be provided to the processing units 140, whilst maximising the volume of plant compartment that can be used for containing processing units 140.
In use, power is provided to the processing units 140 via the cabling 423, 424, which in this example is shown coupled to the generator 420 for the purpose of clarity only. As shown in this example the cable 424 forms a flexible umbilical cable bundle that is capable of ensuring coupling between the power management system 120 and the racks 440 even when the racks are moved as shown by dotted lines.
Each of the above described components and a specific example of their interoperation will now be described in more detail.
Container 400 The container 400 can have exterior physical properties (i.e. dimensions, corner fittings, structural integrity, etc.) that are fully compliant with ISO specifications for 20', 30' and 40' shipping containers. This allows for easy transport of the container 400 using existing transportation systems, thereby allowing the system to be readily shipped to remote areas as required.
Thus, for example, when used in an emergency relief situation, the container 400 can be shipped together with other emergency supplies, allowing it to be provided onsite for controlling emergency supply distribution. Whereas a typical ISO shipping container is constructed with corrugated single sheet steel and unsealed doors, in one example, the container 400 is constructed with exterior structural material, such as steel or aluminium, to form the outer wall 401. The inner wall 402 is used to retain the insulation 403 in place, and can therefore be formed from a lining or the like, or can alternatively also be formed from structural material, such as steel, although in general, the inner wall is not required to provide structural strength. It will be appreciated that this arrangement is particularly suited for extreme environments, such as high or low temperature environments.
Further insulation can be provided using sealed doors 105, 106, and external airlock tents 405, 406. This arrangement also the benefit that access to the plant compartment 103 will not greatly affect the temperature in the data compartment 104, and vice versa, thereby minimising internal environmental fluctuations.
The exterior wall 401 may also be treated for protection against the elements before a final finish is applied. This can include, for example, the use of camouflage paint or armour, in the event that the system is used in a military context.
The dividing wall 102 is typically formed from a fire-rated wall, to thereby separate the data compartment 104 and plant compartment 103. This ensures that should a fire occur in the plant compartment 103, this will not effect data or equipment housed in the data compartment 104.
While remaining in compliance with ISO specifications for external features (i.e. dimensions, corner fittings, structural integrity, etc.), multiple vents, access doors, panels and ports can be provided, including, but not limited to:
• plant and data compartment service doors;
• plant compartment exhaust and air intake vents; • an external MC access panel;
• an external mains power connection port (for example, with internally housed receptacles, eg. 3-phase 440V 30A receptacles, 10 ct); and,
• a data connection port (for example, with internal jacks, eg. RJ45 for copper Cat-5e or Cat6, SC connectors for multi-mode fibre, etc.). A number of additional optional features may also be implemented depending on the intended use of the system, such as:
• external airlock tent;
• side-telescoping or fold-out service corridor/annex tent for data compartment access; • water proofing (extra seals, etc.) to a particular height, for operation in standing water
(from flooding, for example);
• field-installable snorkels over vents and access panels for further water proofing;
• external security monitoring systems (eg. sensors, cameras, etc.);
• field-deployable satellite, microwave or other wireless communication system; • exterior final treatment with specialised solar-reflective coating;
• exterior final treatment with camouflage paint or netting; and,
• exterior amour.
The tent arrangement can also be extended to provide additional space, for example, to allow users work space, or the like. An example tent arrangement is shown in more detail in Figures 7A and 7B. In this example, the tent 706 extends along the length of the data compartment 104, as shown, to thereby provide the additional working space.
As shown in Figure 6B, the tent is formed from a fold-out roof section 701, and a fold-out floor section 702, having feet 703. During transport the fold-out roof and floor sections 701, 702 can be folded against the side of the container 400, being folded out, as shown in dotted lines at 704, 705, when the system is being used. In this instance, the roof will typically clip into place using an appropriate locking mechanism (not shown), to retain the roof in place, whilst the feet 703 extend downwards as shown in Figure 7A to support the floor 702. Suitable material 707 can then be attached to the floor and roof as required to form the tent 706, as shown.
Data Compartment 104
The data compartment 104 can be sealed to allow it to be pressurised with a positive air pressure to help reduce environmental contamination, for example, from dust and the like. Additionally, air quality can be further maintained by having the air cooled and filtered by the climate control system 130. The container walls 401, 402, provide acoustic and thermal insulation, whilst an internal static electricity control system can be provided through the use of anti-static floor tiles.
One or more additional optional features may be implemented, such as:
• static electricity discharge stations with tethers at each service door; • data compartment personnel and/or storage space (may reduce rack space; eg. work bench, desk, storage cabinet, etc.); and,
• internal security monitoring systems (eg. sensors, cameras, etc.).
It will be appreciated that the processing units 140 may provide any form of data processing capabilities, depending on the desired use. Example configurations include: • mid density (standard): balanced storage, CPU and network throughput;
• low density: reduced power use or increased service space (eg. to allow inclusion of a workbench or desk);
• high density: CPU optimised; and,
• high density: storage optimised.
Racks 440
In one example, the racks are in the form of standard width "19-inch" racks for rack- mountable equipment, in vertical increments of standard rack units (RU), with approximately 40 RU spaces per rack. Individual rows of racks may vary in depth (eg. 600mm, 700mm, etc.), to be specified at build-time. All racks can include an integrated cable management system.
The rack configuration is typically designed to maximise the use of space with complimentary ceiling-hanging flexible power and data cabling umbilicals and ventilation ducts and vents with adjustable placement to maximise cooling efficacy and efficiency.
The use of a rack based compression system can provide multiple configurations for three modes of operation:
• normal position (periodically spaced rack rows) for most efficient cooling;
• service positions (at least one for each rack row) for rack front and back access; and, • transportation positions with lock-down and space for re-packaged equipment or supplemental cargo.
A number of different rack configurations may be used, as will now be described with respect to Figures 5 A and 5B.
The example of Figure 5 A includes five rows of three racks 440 each. The rack rows are placed adjacent to the wall opposite the door 106 and move in the direction of the arrows 500, along the length of the data compartment 104, using rack-mounted steel roller bearings, or the like, running over the floor tracks 441 and the guide rails 442. Racks rows are positioned with pins and secured with bolts, both running through the roller bearing rail and into the steel track secured on the floor.
However, alternative configurations can be used, such as row configurations with, for example, two long rows running along the length of the data compartment, with the racks moveable in the direction of the arrows 501, as shown in Figure 5B.
It will be appreciated that the number of rows may be varied depending on the size of the container 400 and the data compartment 104, or by altering the depth of the racks in each row
(eg. six rows and a mixed configuration may be achieved with four 400mm depth racks and two 600mm depth racks). Similarly alternative compression system mechanisms, or no compression mechanism with racks fixed in place, can be used, and the rack depth may be adjustable by use of a telescoping system. Furthermore, whilst the above description focuses on the use of standard size racks, any suitable rack configuration can be used.
Cabling
In one example, cabling management is used to provide specified power and data cabling to each rack through per-rack flexible umbilical cable bundles, and per-rack cable management. The cabling will typically be adapted to provide, for each rack unit 444: • a single 120/240V 250W/500W (mean/peak) power lead with standard 3-prong plug; and,
• two Cat5e data leads with RJ45 connectors terminating (also with RJ45 connectors) at a top 4RU space designed for a network switching and/or routing equipment. Typically, this will include, for each rack 440:
• single flexible power bundle containing cabling for 4-6 single phase 120/240 V circuits; and,
• single flexible data bundle containing four multi-mode fibre leads terminated with SC connectors at the top 4RU network space.
However, any suitable connections and cabling may be used.
Plant Compartment 103
Typically equipment housed in the plant compartment 103 is placed to maximise the use of space and allow for adequate serviceability. The plant compartment is also typically acoustically baffled and actively fan- ventilated with outdoor air.
Power Management System 120
The integrated power management system is designed with several operating and backup modes, facility for multiple input power sources, facility for several power storage systems, and provides conditioned power with maximum efficiency during normal operation.
Power sources can include but are not limited to an external mains supply, solar panels 422 and the generator 420, while temporary backup can be provided by batteries 421 or by batteries distributed throughout racks 440. Power is typically conditioned to ensure proper operation of data compartment equipment; with operation being coordinated and monitored with the MC 410.
A number of alternative configurations can be used however, depending on the intended utilisation of the system, including for example:
• an Uninterruptible Power Supply (UPS) system;
• a configuration without UPS or battery backup;
• a configuration without local power generation; • ultra low power (solar power, for extreme remote or economy operation);
• a diesel generator for backup or main operation;
• a gas turbine power generator with mains natural gas, CNG, LPG or Hydrogen gas; • fuel cell power generator with natural gas, Hydrogen gas, ethanol, methanol, CNG, LPG or other hydrogen or hydrocarbon source;
• local hydrogen or hydrocarbon fuel generation (electrical or heat catalytic) and storage for use with fuel cell system (including rainwater collection and storage system); and,
• solar supplemental power generation to augment other power supplies;
The system may also implement a power-up sequence to meet total power use specifications which is to be implemented by an appropriate network management system, the MC, or UPS control system, as required. This may be provided together with a per-rack power distribution controller for sequenced power-up and individual remote RU power up or down.
Climate Control System 130
The integrated cooling system can include a range of cooling mechanisms, including passive solar, ventilation, air-to-air heat exchange, absorption cooling, and traditional phase change cooling.
Typically the system uses a primary and back-up system using redundant independent thermostatic control with the primary system typically set to a range of 20-210C and the backup system set to a range of 22-230C. Return air ducting is strategically placed on the ceiling to provide optimal air flow and cooling. A HEPA air filtration system is integrated into the ducting system. A bypass for outdoor air is used to create a small positive pressure.
The primary cooling system of data compartment is a phase change cooling system, backup for which is provided by an absorption cooling system. An example of an absorption cooling system will now be described with reference to Figure 6.
In particular, the system uses the evaporator 430, which has an inlet 632 and an outlet 633. The evaporator 430 is coupled to the absorber 432, via a pipe 635, which is in turn connected to a heating system 636 via pipes 637A, 637B as shown. A pipe 641, having an inlet 642, and an outlet 643 receives heat in the form of waste gases from the generator 420, as shown at 640, and transfers this to a heat exchanger 636. The heat exchanger 636 is connected to a condenser 638 via a pipe 639. The condenser 638 typically generates waste heat as shown at 644 and is also coupled to the evaporator 430 via a pipe 645. The system utilises a solution formed form a combination of a refrigerant and an absorber in order to provide heat transfer mechanisms, as will now be described. Typically the solution is either a water/lithium bromide or an ammonia/water combination as will be appreciated by a person skilled in the art.
In use, the evaporator 430 operates to receive liquid refrigerant from the condenser 638, via the pipe 645. The refrigerant is provided into a low-pressure environment within the evaporator 430, and evaporates, thereby extracting heat from air supplied to the inlet 632, via an appropriate heat exchanger. The chilled air is then output via the outlet 633, to the duct 434, whilst the evaporated refrigerant is transferred via the pipe 635 to the absorber 432, where it is absorbed by a refrigerant-depleted solution.
The solution is transferred via the pipe 637A to the heat exchanger 636, which operates to heat the solution using fluid in the pipe 641, thereby causing the refrigerant to be evaporated. The remaining refrigerant-depleted solution returns to the absorber 432 via the pipe 637B, whilst the vaporised refrigerant is transferred via the pipe 639 to the condenser 638. The vaporised refrigerant is allowed to condense with waste heat being output at 644 before being transferred via the pipe 645 to the evaporator 430, thereby allowing the cycle to be repeated.
In addition to the features outlined above, a number of additional optional climate control features can be implemented, such as:
• an air-to-air heat exchanger; • roof-mounted fold-out side shade flaps;
• natural or artificial shade barriers (trees, screens, etc.);
• active supplemental solar cooling; and,
• supplemental purpose-use boiler for absorption cooling only.
Additionally, in-floor ducting and vents can be provided together with a shutter system to restrict airflow to special narrow vents for temporary operation in service configuration. In this example, the racks can be designed to enhance airflow from underneath each rack to the front and back of each rack. The absorption cooling component can also be adapted to provide 100% primary or backup to electrically powered phase change cooling in the data compartment. Plant Compartment Cooling
The plant compartment 103 is designed to be cooled with outdoor air ventilation when the generator is not in use and with absorption cooling when the generator is in use or if the compartment overheats.
The energy required for basic absorption cooling is provided by surplus heat from the generator and is used to cool the generator, plus provide supplemental cooling to the data compartment, thereby reducing power requirements of the data compartment cooling system.
Container Management System 411
In the above-described example, the CMS 411 can be used to monitor key plant components and vital statistics, and report faults via a customer-provided gateway such as IMPI, SNMP, or simpler SMTP. In one example, the CMS includes a Linux-based controller which interfaces via serial or Ethernet connections to management/monitor modules on individual components such as the generator, AC systems, etc. An external data port can be provided adjacent to the CMS 411 for allowing external connectivity.
However, any suitable arrangement may be used, including, for example, system integration with existing network management systems.
In one example, the container 400 can include independent fire suppression systems for the plant compartment and the data compartment, such as gas based suppression systems. Such systems would typically be controlled by the CMS 411. The CMS 411 can also monitor and schedule servicing and maintenance for all included equipment and other moving parts.
Power management and service schedule management of the processing units 140 can be enhanced through the use of server virtualisation technologies traditionally used primarily for server consolidation (eg. virtual machines, hypervisors, clustering systems, message passing systems, etc.).
In one example, the use of virtualisation to manage power includes switching off processing units during periods of underutilisation. This is possible because virtualisation allows the "processing unit" which is visible to applications and users to be a collection of individual units from a pool, where units can enter or leave the active pool without applications or users taking notice.
An example of the use of virtualisation to manage service schedule management includes remote recovery from component failures and replacement of failed parts deferred to regularly scheduled times by removing affected units from the active pool.
Service and maintenance schedules for, including service for unscheduled failures, may be also be synchronised with plant compartment service schedules.
Shipping and Deployment
In one example, the container is shipped independently of the processing units 140, with the deployment and final systems integration for non-hardened customer-provided equipment occurring on site. During this process, the tents 405, 406 can be used to provide an airlock between the container 400 and the delivery container/trailer, to help provide protection from the elements, including dust, rain and heat.
However, alternatively, hardened equipment may be installed in the container 400 prior to shipping.
Interior space permitting, field-installable external apparatus (such as optional solar array or wireless communications equipment) may be stowed internally for shipping.
It will be appreciated that wheels, axles, lights and other fixtures may be permanently attached to the apparatus in consideration of continued transportability and/or local government classifications, requirements and regulations.
Use
Accordingly, the above described system provides a configurable and self-contained "data processing system" packaged in a purpose-built container for field deployment which can be ISO standard size (10ft, 20ft, 30ft or 40ft), pallet size, or any other suitable size.
The container design and integrated systems management provides high reliability with a long service life, maximised power efficiency, and field serviceability balanced with optimised component density. The container is designed to allow for rapid-deploy (and rapid- redeploy) permanent or semi-permanent installations (fixed, for example via bolts through corner castings or guy wires), while remaining cost-competitive with fixed data centre infrastructure and operations.
The system can be used in applications spanning multiple industries, including any corporation, organisation, project, government body or defence with data processing, media, or communications needs. This provides an ideal solution for capacity planning (eg. carpark overflow of fixed data centres, data warehousing, etc.), continuity planning (eg. backup & disaster recovery), remote deployment (eg. branch offices, conventions and special events, etc.), military field deployment, and emergency deployment. However, it will be appreciated that the system can be used in any circumstances in which there is a need for data processing capabilities.
Accordingly, the above described apparatus can provide an integrated self-contained transportable and modular (dual-mode, temporary or fixed) data processing centre that is capable of providing many or all of the features normally provided by a full-scale data centre, whilst maximising the use of energy and space.
Persons skilled in the art will appreciate that numerous variations and modifications will become apparent. All such variations and modifications which become apparent to persons skilled in the art, should be considered to fall within the spirit and scope that the invention broadly appearing before described.

Claims

THE CLAIMS:
1) Apparatus for providing data processing capabilities, the apparatus including a container defining: a) a first portion for housing a number of data processing units; and, b) a second portion including: i) a power management system for supplying power to the data processing units; ii) a climate control system for at least partially controlling the climate in the first portion; and, iii) a control system for at least partially controlling the power management system. 2) Apparatus according to claim 1, wherein the first and second portions are physically separated by a dividing wall.
3) Apparatus according to claim 2, wherein the dividing wall is fireproof.
4) Apparatus according to any one of the claims 1 to 3, wherein the container includes first and second sealed doors for providing access to the first and second portions respectively. 5) Apparatus according to any one of the claims 1 to 4, wherein the container includes: a) an inner wall; b) an outer wall; and, c) an insulating layer provided between the inner and outer walls.
6) Apparatus according to any one of the claims 1 to 5, wherein the processing units are provided on moveable racks.
7) Apparatus according to any one of the claims 1 to 6, wherein the power management system includes at least one of: a) a generator; b) at least one battery; c) solar panel; and, d) a connector for coupling to an external power source.
8) Apparatus according to any one of the claims 1 to 7, wherein the climate control system includes at least one of: a) an air filtration unit; b) an absorption chiller; and, c) a phase change air conditioning unit. 9) Apparatus according to any one of the claims 1 to 8, wherein the climate control system includes: a) a primary cooling mechanism; b) a secondary cooling mechanism; and, c) a thermostatic control for selectively activating the primary and secondary cooling systems.
10) Apparatus according to any one of the claims 1 to 9, wherein the climate control system is for controlling at least one of: a) the temperature; and, b) the humidity.
11) Apparatus according to any one of the claims 1 to 10, wherein the power management system includes a generator and wherein the climate control system includes an absorption chiller operable using waste heat from exhaust gases generated by the generator. 12) Apparatus according to any one of the claims 1 to 11, wherein the control system includes at least one processing system.
13) Apparatus according to any one of the claims 1 to 12, wherein the control system is for: a) monitoring power usage requirements; and, b) selectively activating one or more power supply mechanisms in accordance with the monitored usage requirements.
14) Apparatus according to any one of the claims 1 to 13, wherein the control system is for: a) monitoring data processing requirements; and, b) selectively activating data processing units in accordance with the data processing requirements.
PCT/AU2007/000053 2006-01-23 2007-01-18 Data processing apparatus WO2007082351A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US12/178,568 US20090050591A1 (en) 2006-01-23 2008-07-23 Mobile Data Center Unit

Applications Claiming Priority (4)

Application Number Priority Date Filing Date Title
AU2006900335A AU2006900335A0 (en) 2006-01-23 Data processing apparatus
AU2006900335 2006-01-23
US76226006P 2006-01-25 2006-01-25
US60/762,260 2006-01-25

Related Child Applications (1)

Application Number Title Priority Date Filing Date
US12/178,568 Continuation US20090050591A1 (en) 2006-01-23 2008-07-23 Mobile Data Center Unit

Publications (1)

Publication Number Publication Date
WO2007082351A1 true WO2007082351A1 (en) 2007-07-26

Family

ID=38287200

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/AU2007/000053 WO2007082351A1 (en) 2006-01-23 2007-01-18 Data processing apparatus

Country Status (2)

Country Link
US (1) US20090050591A1 (en)
WO (1) WO2007082351A1 (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US7511960B2 (en) 2006-09-13 2009-03-31 Sun Microsystems, Inc. Balanced chilled fluid cooling system for a data center in a shipping container
US7551971B2 (en) 2006-09-13 2009-06-23 Sun Microsystems, Inc. Operation ready transportable data center in a shipping container
US7738251B2 (en) * 2006-06-01 2010-06-15 Google Inc. Modular computing environments
GB2467808A (en) * 2009-06-03 2010-08-18 Moduleco Ltd Data centre cooling arrangements
US7854652B2 (en) 2006-09-13 2010-12-21 Oracle America, Inc. Server rack service utilities for a data center in a shipping container
EP2101017A3 (en) * 2008-03-11 2010-12-22 Advanced Shielding Technologies Europe S.L. Portable modular data center
US7856838B2 (en) 2006-09-13 2010-12-28 Oracle America, Inc. Cooling air flow loop for a data center in a shipping container
WO2011005643A1 (en) * 2009-07-07 2011-01-13 Prime Image / Greentec Systems Llc Combined computer device and facility air purification
US7898804B2 (en) 2008-10-28 2011-03-01 Oracle America, Inc. Air flow snorkel for computer system
US20110175499A1 (en) * 2010-01-20 2011-07-21 Huawei Technologies Co., Ltd. Container-type data center
US8047904B2 (en) 2006-09-13 2011-11-01 Oracle America, Inc. Cooling method for a data center in a shipping container
WO2013077858A1 (en) * 2011-11-22 2013-05-30 Le Groupe S.M. Inc. Data center cooling system
US8595515B1 (en) 2007-06-08 2013-11-26 Google Inc. Powering a data center
WO2014100495A3 (en) * 2012-12-19 2015-04-02 Microsoft Corporation Server rack fuel cell
US9009500B1 (en) 2012-01-18 2015-04-14 Google Inc. Method of correlating power in a data center by fitting a function to a plurality of pairs of actual power draw values and estimated power draw values determined from monitored CPU utilization of a statistical sample of computers in the data center
US9287710B2 (en) 2009-06-15 2016-03-15 Google Inc. Supplying grid ancillary services using controllable loads
US9874414B1 (en) 2013-12-06 2018-01-23 Google Llc Thermal control system

Families Citing this family (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB0519324D0 (en) * 2005-09-22 2005-11-02 Michael Sheridan & Company Ltd Display unit
US8783336B2 (en) * 2008-12-04 2014-07-22 Io Data Centers, Llc Apparatus and method of environmental condition management for electronic equipment
US8264840B2 (en) * 2009-05-15 2012-09-11 NxGen Modular, LLC Modular data center and associated methods
US9101080B2 (en) * 2009-09-28 2015-08-04 Amazon Technologies, Inc. Modular computing system for a data center
WO2011049033A1 (en) * 2009-10-23 2011-04-28 Okada Ryosuke Data center and computer storing rack therefor
US8116080B2 (en) * 2009-12-28 2012-02-14 International Business Machines Corporation Container-based data center having greater rack density
US8164897B2 (en) * 2010-02-19 2012-04-24 International Business Machines Corporation Airflow recirculation and cooling apparatus and method for an electronics rack
TW201214093A (en) * 2010-09-17 2012-04-01 Hon Hai Prec Ind Co Ltd Container data center and power supply system thereof
US20120080940A1 (en) * 2010-10-01 2012-04-05 The Boeing Company Load Coordinating Power Draw for Limited Ampacity Circuits
TW201222177A (en) * 2010-11-19 2012-06-01 Hon Hai Prec Ind Co Ltd Avoiding waterflooding apparatus and container data center including the same
US20120200206A1 (en) * 2011-02-07 2012-08-09 Dell Products L.P. System and method for designing a configurable modular data center
US9092209B2 (en) * 2011-06-17 2015-07-28 Microsoft Technology Licensing, Llc Wireless cloud-based computing for rural and developing areas
US8872361B2 (en) 2012-01-25 2014-10-28 Briggs & Stratton Corporation Standby generators including compressed fiberglass components
WO2014031605A1 (en) * 2012-08-20 2014-02-27 Phase Change Energy Solutions, Inc. Thermal energy storage systems
US9502893B2 (en) 2012-09-20 2016-11-22 Nova Greentech, Inc. Distributed power supply system and method
US10772239B2 (en) * 2012-11-09 2020-09-08 Lex Industries Ltd. Manufactured data center
US10381691B1 (en) 2012-11-15 2019-08-13 Nova Greentech, Inc. Modular battery network systems and methods for managing modular battery network systems
US11262089B2 (en) 2014-01-09 2022-03-01 Nautilus True, Llc Data center management systems and methods for compute density efficiency measurements
US10334762B2 (en) 2015-01-29 2019-06-25 Hewlett Packard Enterprise Development Lp Movable rack
WO2017039626A1 (en) * 2015-08-31 2017-03-09 Abb Technology Ltd. Emergency lighting, evacuation, and rescue routing with power over-ethernet
US20190059173A1 (en) * 2015-09-29 2019-02-21 The Data Exchange Network Ltd An Equipment Displacement System for a Containerised Data Centre
CN105468102A (en) * 2015-11-24 2016-04-06 浪潮电子信息产业股份有限公司 Modularized data center system capable of being deployed rapidly
WO2018097730A1 (en) * 2016-11-28 2018-05-31 Solo30 B.V. Datacentre
US10572563B2 (en) 2017-04-05 2020-02-25 Toyota Research Institute, Inc. Mobile computing systems and methods for accessing data
RU2731958C1 (en) * 2020-02-25 2020-09-09 Антон Владимирович Костенко Mobile center of data processing
CN113660820B (en) 2020-05-12 2024-08-20 富联精密电子(天津)有限公司 Container type data system
US11591977B2 (en) 2020-06-03 2023-02-28 Briggs & Stratton, Llc Inverter generator
US11705779B2 (en) 2020-06-03 2023-07-18 Briggs & Stratton, Llc Inverter generator
US11946269B2 (en) * 2022-03-21 2024-04-02 Nautilus True, Llc Modular integrated system modules

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4909557A (en) * 1986-05-30 1990-03-20 Arnaud De Weck Mobile computer clean room
US6141213A (en) * 1997-06-24 2000-10-31 Sun Microsystems, Inc. Computer with high airflow and low acoustic noise
US6722474B2 (en) * 2002-03-26 2004-04-20 Eran Golan Hatzor Smart service unit
US20040132398A1 (en) * 2002-10-25 2004-07-08 Sharp Anthony C. Integrated cabinet for containing electronic equipment
US20040160897A1 (en) * 1999-10-27 2004-08-19 Netbotz, Inc. Method and system for monitoring computer networks and equipment
US20060082263A1 (en) * 2004-10-15 2006-04-20 American Power Conversion Corporation Mobile data center

Family Cites Families (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1156693A (en) * 1915-03-30 1915-10-12 Marvin Vastine Koger Combination van-wagon.
US2765499A (en) * 1952-04-30 1956-10-09 Kibbey W Couse Collapsible hut
BE560029A (en) * 1956-08-14
US3925679A (en) * 1973-09-21 1975-12-09 Westinghouse Electric Corp Modular operating centers and methods of building same for use in electric power generating plants and other industrial and commercial plants, processes and systems
US4589712A (en) * 1977-08-25 1986-05-20 Hastings Otis Data processing equipment enclosures
US4549405A (en) * 1983-12-12 1985-10-29 Carrier Corporation Modular air conditioning unit for mobile cargo container
WO1986003089A1 (en) * 1984-11-15 1986-05-22 Fujitsu Limited Cooling structure of a rack for electronic devices
US4644705A (en) * 1986-05-07 1987-02-24 Societe D'etudes Techniques Et D'entreprise Generales Sodeteg Unfolding, movable hospital unit
WO1997011750A1 (en) * 1995-09-27 1997-04-03 United Defense, L.P. Integrated protective action system
US5740018A (en) * 1996-02-29 1998-04-14 The United States Of America As Represented By The Secretary Of The Navy Environmentally controlled circuit pack and cabinet
WO2001062060A1 (en) * 2000-02-18 2001-08-23 Rtkl Associates Inc. Computer rack heat extraction device
US6209979B1 (en) * 2000-02-22 2001-04-03 General Devices Co., Ltd. Telescoping slide with quick-mount system
US6407918B1 (en) * 2001-03-30 2002-06-18 General Electric Company Series-parallel fan system
US7752858B2 (en) * 2002-11-25 2010-07-13 American Power Conversion Corporation Exhaust air removal system
US6859366B2 (en) * 2003-03-19 2005-02-22 American Power Conversion Data center cooling system
US7170745B2 (en) * 2003-04-30 2007-01-30 Hewlett-Packard Development Company, L.P. Electronics rack having an angled panel
US7644970B2 (en) * 2003-10-23 2010-01-12 Health Sciences Authority Mobile containerized autopsy facility
US7278273B1 (en) * 2003-12-30 2007-10-09 Google Inc. Modular data center
JP2007537097A (en) * 2004-05-12 2007-12-20 シャーロット‐メクレンバーグ・ホスピタル・オーソリティ,ドゥーイング・ビジネス・アズ・キャロライナズ・メディカル・センター Mobile medical facility
DE102005010683B3 (en) * 2005-03-09 2006-09-28 Eads Deutschland Gmbh Mobile building
US8672732B2 (en) * 2006-01-19 2014-03-18 Schneider Electric It Corporation Cooling system and method
EP2310926B1 (en) * 2006-06-01 2013-11-20 Google Inc. Modular computing environments
US7768780B2 (en) * 2006-06-19 2010-08-03 Silicon Graphics International Corp. Flow-through cooling for computer systems
US7621580B2 (en) * 2006-08-10 2009-11-24 Pierce Manufacturing Company Ambulance seating system
US7551971B2 (en) * 2006-09-13 2009-06-23 Sun Microsystems, Inc. Operation ready transportable data center in a shipping container
US8047904B2 (en) * 2006-09-13 2011-11-01 Oracle America, Inc. Cooling method for a data center in a shipping container
WO2008039773A2 (en) * 2006-09-25 2008-04-03 Rackable Systems, Inc. Container-based data center
US7511959B2 (en) * 2007-04-25 2009-03-31 Hewlett-Packard Development Company, L.P. Scalable computing apparatus
US7477514B2 (en) * 2007-05-04 2009-01-13 International Business Machines Corporation Method of facilitating cooling of electronics racks of a data center employing multiple cooling stations
TWI331514B (en) * 2007-10-16 2010-10-11 Univ Nat Taiwan Science Tech Object access method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4909557A (en) * 1986-05-30 1990-03-20 Arnaud De Weck Mobile computer clean room
US6141213A (en) * 1997-06-24 2000-10-31 Sun Microsystems, Inc. Computer with high airflow and low acoustic noise
US20040160897A1 (en) * 1999-10-27 2004-08-19 Netbotz, Inc. Method and system for monitoring computer networks and equipment
US6722474B2 (en) * 2002-03-26 2004-04-20 Eran Golan Hatzor Smart service unit
US20040132398A1 (en) * 2002-10-25 2004-07-08 Sharp Anthony C. Integrated cabinet for containing electronic equipment
US20060082263A1 (en) * 2004-10-15 2006-04-20 American Power Conversion Corporation Mobile data center

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
PROJECT BLACKBOX, 17 October 2006 (2006-10-17), XP003015734, Retrieved from the Internet <URL:http://www.sun.com/emrkt/blackbox/index.jsp> *

Cited By (45)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8218322B2 (en) 2006-06-01 2012-07-10 Google Inc. Modular computing environments
US8743543B2 (en) 2006-06-01 2014-06-03 Google Inc. Modular computing environments
US7738251B2 (en) * 2006-06-01 2010-06-15 Google Inc. Modular computing environments
US7511960B2 (en) 2006-09-13 2009-03-31 Sun Microsystems, Inc. Balanced chilled fluid cooling system for a data center in a shipping container
US7894945B2 (en) 2006-09-13 2011-02-22 Oracle America, Inc. Operation ready transportable data center in a shipping container
US7551971B2 (en) 2006-09-13 2009-06-23 Sun Microsystems, Inc. Operation ready transportable data center in a shipping container
US7856838B2 (en) 2006-09-13 2010-12-28 Oracle America, Inc. Cooling air flow loop for a data center in a shipping container
US7854652B2 (en) 2006-09-13 2010-12-21 Oracle America, Inc. Server rack service utilities for a data center in a shipping container
US8047904B2 (en) 2006-09-13 2011-11-01 Oracle America, Inc. Cooling method for a data center in a shipping container
US10558768B1 (en) 2007-06-08 2020-02-11 Google Llc Computer and data center load determination
US8700929B1 (en) 2007-06-08 2014-04-15 Exaflop Llc Load control in a data center
US9946815B1 (en) 2007-06-08 2018-04-17 Google Llc Computer and data center load determination
US8621248B1 (en) 2007-06-08 2013-12-31 Exaflop Llc Load control in a data center
US10339227B1 (en) 2007-06-08 2019-07-02 Google Llc Data center design
US11017130B1 (en) 2007-06-08 2021-05-25 Google Llc Data center design
US8949646B1 (en) 2007-06-08 2015-02-03 Google Inc. Data center load monitoring for utilizing an access power amount based on a projected peak power usage and a monitored power usage
US8645722B1 (en) 2007-06-08 2014-02-04 Exaflop Llc Computer and data center load determination
US8595515B1 (en) 2007-06-08 2013-11-26 Google Inc. Powering a data center
US8601287B1 (en) 2007-06-08 2013-12-03 Exaflop Llc Computer and data center load determination
EP2101017A3 (en) * 2008-03-11 2010-12-22 Advanced Shielding Technologies Europe S.L. Portable modular data center
US7898804B2 (en) 2008-10-28 2011-03-01 Oracle America, Inc. Air flow snorkel for computer system
US9648787B2 (en) 2009-06-03 2017-05-09 Bripco Bvba Data centre
US8514572B2 (en) 2009-06-03 2013-08-20 Bripco Bvba Data centre
GB2467808B (en) * 2009-06-03 2011-01-12 Moduleco Ltd Data centre
US10485142B2 (en) 2009-06-03 2019-11-19 Bripco Bvba Data Centre
GB2467808A (en) * 2009-06-03 2010-08-18 Moduleco Ltd Data centre cooling arrangements
US9723761B2 (en) 2009-06-03 2017-08-01 Bripco Bvba Data centre
US9069534B2 (en) 2009-06-03 2015-06-30 Bripco Bvba Data centre
US9287710B2 (en) 2009-06-15 2016-03-15 Google Inc. Supplying grid ancillary services using controllable loads
WO2011005643A1 (en) * 2009-07-07 2011-01-13 Prime Image / Greentec Systems Llc Combined computer device and facility air purification
EP2852268A1 (en) * 2010-01-20 2015-03-25 Huawei Technologies Co., Ltd. Container-type data center
EP2348803A1 (en) * 2010-01-20 2011-07-27 Huawei Technologies Co., Ltd. Container-type data center
EP2685800A1 (en) * 2010-01-20 2014-01-15 Huawei Technologies Co., Ltd. Container-type data center
US20110175499A1 (en) * 2010-01-20 2011-07-21 Huawei Technologies Co., Ltd. Container-type data center
CN102131369B (en) * 2010-01-20 2014-09-17 华为技术有限公司 Container type data center
US9320177B2 (en) 2011-11-22 2016-04-19 Le Groupe S.M. Inc. Data center cooling system
EP3154324A3 (en) * 2011-11-22 2017-05-17 Le Groupe S.M. Inc. Data centre cooling system
US9706689B2 (en) 2011-11-22 2017-07-11 Le Group S.M. Inc. Data center cooling system
WO2013077858A1 (en) * 2011-11-22 2013-05-30 Le Groupe S.M. Inc. Data center cooling system
US9383791B1 (en) 2012-01-18 2016-07-05 Google Inc. Accurate power allotment
US9009500B1 (en) 2012-01-18 2015-04-14 Google Inc. Method of correlating power in a data center by fitting a function to a plurality of pairs of actual power draw values and estimated power draw values determined from monitored CPU utilization of a statistical sample of computers in the data center
WO2014100495A3 (en) * 2012-12-19 2015-04-02 Microsoft Corporation Server rack fuel cell
US10296073B2 (en) 2012-12-19 2019-05-21 Microsoft Technology Licensing, Llc Server rack fuel cell
EP3885879A1 (en) * 2012-12-19 2021-09-29 Microsoft Technology Licensing, LLC Server rack fuel cell
US9874414B1 (en) 2013-12-06 2018-01-23 Google Llc Thermal control system

Also Published As

Publication number Publication date
US20090050591A1 (en) 2009-02-26

Similar Documents

Publication Publication Date Title
US20090050591A1 (en) Mobile Data Center Unit
US10779441B2 (en) Energy saving system and method for cooling computer data center and telecom equipment
US7724513B2 (en) Container-based data center
US8498114B2 (en) Energy saving system and method for cooling computer data center and telecom equipment
US20130032310A1 (en) Transportable, environmentally-controlled equipment enclosure
US7867070B2 (en) Data center cooling
EP2556201B1 (en) Container based data center solutions
US9913407B2 (en) Energy efficient vertical data center
US9089077B2 (en) Energy center
US8264840B2 (en) Modular data center and associated methods
US20140359998A1 (en) Modular datacenter element and modular datacenter cooling element
CA2873088C (en) Method for operating a data centre with efficient cooling means
US11917788B1 (en) Modular data center
WO2011092333A1 (en) Modular datacenter element and modular datacenter cooling element
CN105205725A (en) Power distribution system and container type data center
WO2011051655A2 (en) A data centre
US20200413572A1 (en) Energy saving system and method for cooling computer data center and telecom equipment
RU2598355C2 (en) Modular data processing centre
CA2904518C (en) Energy efficient vertical data center
CA3101101A1 (en) Modular data center utilizing independent data center modules
US20220217861A1 (en) Computing centre module and method
CN218888920U (en) Modular container type data center
US20230397360A1 (en) Data center module formed from prefabricated and transportable segments, data center module construction method, data center formed from said module, and data center construction method

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 07701390

Country of ref document: EP

Kind code of ref document: A1