WO2000028168A1 - Tension force adjustable prestressed girder - Google Patents

Tension force adjustable prestressed girder Download PDF

Info

Publication number
WO2000028168A1
WO2000028168A1 PCT/KR1999/000567 KR9900567W WO0028168A1 WO 2000028168 A1 WO2000028168 A1 WO 2000028168A1 KR 9900567 W KR9900567 W KR 9900567W WO 0028168 A1 WO0028168 A1 WO 0028168A1
Authority
WO
WIPO (PCT)
Prior art keywords
girder
tension
steel wires
bridge
load
Prior art date
Application number
PCT/KR1999/000567
Other languages
French (fr)
Inventor
Man Yop Han
Original Assignee
Interconstec Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Interconstec Co., Ltd. filed Critical Interconstec Co., Ltd.
Priority to AT99944909T priority Critical patent/ATE259020T1/en
Priority to AU57633/99A priority patent/AU750126B2/en
Priority to DE69914621T priority patent/DE69914621T2/en
Priority to UA2001042935A priority patent/UA70968C2/en
Priority to EP99944909A priority patent/EP1129263B1/en
Priority to CA002349855A priority patent/CA2349855C/en
Priority to JP2000581321A priority patent/JP2003501568A/en
Priority to BR9915041-7A priority patent/BR9915041A/en
Publication of WO2000028168A1 publication Critical patent/WO2000028168A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • E04C3/26Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members prestressed
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Definitions

  • the present invention relates to a girder, and more particularly, to a tension force adjustable prestressed girder which can compensate for sagging or cracks of a girder generated due to a long-term load and is capable of adjusting a tension force by increasing a load-resisting force of a bridge or building, if necessary, after the construction thereof.
  • a prestressed concrete (PSC) bridge is repaired and reinforced by means of an external steel wire reinforcement construction method.
  • an externally installed steel wire is to be fixed appropriately at an end portion of a girder.
  • no effective apparatuses have been developed yet. That is, when cracks and sagging occur in a PCS bridge, it is very difficult to repair and reinforce the bridge.
  • the height of a girder which is long in span is relatively high such that the girder itself is 2.00 m - 3.00 m high.
  • Such a fact entails an increase in the height of an upper deck of an overpass so that, to secure a longitudinal alignment of the overpass matching the designed vehicle speed, the length of the overpass becomes longer, thus raising the construction costs.
  • to lower the height of the girder as low as possible is inevitably needed for improving the usability and the economic value of the girder.
  • FIG. 1 shows the structure of a general bridge. As shown in the drawing, a plurality of I-type girders 12 are installed on a column 10. An upper deck slab (not shown) is installed on the girders 12 of the bridge.
  • FIG. 2 is a sectional view showing a girder in which steel wires are arranged according to the conventional technology.
  • a girder 20 consists of a body portion 22, an upper flange 28, and a lower flange 24.
  • a plurality of steel wires 26 are built in the body portion 22 in the lengthwise direction.
  • An upper deck of a bridge is installed on the upper flange 28 and the bottom surface of the lower flange 24 is supported by the column 10.
  • a tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge installed thereon, a body portion, and a lower flange, which includes tension steel wires provided in a lengthwise direction of the girder and tensioned to compensate for the load-resisting force, and at least one or more non-tension steel wires provided in the lengthwise direction of the girder, so that the load-resisting force of the bridge can be increased by tensioning the non-tension steel wires.
  • the tension force adjustable prestressed girder further comprises a cut-open portion at a predetermined portion in the lengthwise direction of the girder and a coupling member installed at the cut-open portion for fixing one ends of the steel wires of which the other ends are fixed at an end portion of the girder.
  • a tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge installed thereon, a body portion, and a lower flange, which includes tension steel wires provided in a lengthwise direction of the girder and tensioned to compensate for the load-resisting force, and one or more non-tension steel wires provided in the lengthwise direction of the girder, so that the load-resisting force of the bridge can be increased by tensioning the non-tension steel wires during construction of the girder and/or after the construction thereof.
  • the present invention can be applied to any type of girder regardless of the shape of the section of the girder such as an I-type girder or a bulb T-type girder, the I-type girder is described in the below preferred embodiment.
  • FIG. 1 is a perspective view showing the structure of a general bridge
  • FIG. 2 is a sectional view showing the arrangement of steel wires in the girder according to conventional technology
  • FIG. 3A is a sectional view showing the arrangement of steel wires in the middle portion of a girder according to the present invention
  • FIG. 3B is a sectional view showing the steel wires according to another preferred embodiment of the present invention
  • FIG. 4A is a sectional view showing the arrangement of steel wires at the end portion of the girder of FIG. 3A;
  • FIG. 4B is a sectional view showing the arrangement of steel wires at the end portion of the girder of FIG. 3B;
  • FIG. 5 is a view showing a cut-open portion located at the middle portion of the girder and the arrangement of the steel wires in the girder;
  • FIG. 6 is a side view showing an example of a steel wire fixed at the end portion of the girder.
  • FIG. 7 is a perspective view showing an example of the steel wires in the cut-open portion.
  • a girder 40 includes an upper flange 28, a lower flange 24, and a body portion 22.
  • One or more tension steel wires 26 and non- tension steel wires 27 are built in and across the lower portion of the body portion 22 and the lower flange 24 of the girder 40 in the lengthwise direction of the girder 40.
  • the non-tension steel wires 27 are built in the lower flange 28 horizontally parallel to each other, as shown in FIG. 3A.
  • the upper flange 28 is provided above the body portion 22 in the latitudinal direction in the section of the girder 40 and an upper deck of a bridge is installed on the upper flange 28.
  • the lower flange 24 is provided below the body portion 22 in the latitudinal direction in the section of the girder 40 and the bottom surface thereof is supported by a column (not shown).
  • FIG. 3B shows a steel wire according to another preferred embodiment of the present invention.
  • a plurality of non-tension steel wires 27a are provided in the lengthwise direction of the girder 40 outside the lower portion of the body portion 22.
  • the non- tension steel wires 27a have the same function as that of the non-tension steel wire 27 provided in the lower flange 24, as shown in FIG. 3A. That is, after a bridge is constructed, sagging of the girder 40 is compensated for by tensioning the non-tension steel wires 27a. Also, the non-tension steel wires 27a can be more easily installed compared to a case of being installed inside the lower flange 24.
  • FIG. 4A shows the arrangement of the steel wires built in the girder of FIG. 3A.
  • the tension steel wires 26 and the non-tension steel wires 27 concentrated at the lower portion of the girder 40 are distributed throughout the entire sectional portion of the girder 40. That is, the steel wires are evenly distributed symmetrically in up/down and left/right sides of the girder 40 so that the tension force by the tension steel wires 26 and the non-tension steel wires 27 can be evenly distributed throughout the entire portion of the girder 40.
  • FIG. 4B shows the arrangement of the steel wires at the end portion of the girder shown in FIG. 3B.
  • the tension steel wires 26 or the non-tension steel wires 27 and 27a concentrated at the lower portion of the girder as shown in FIG. 3B are evenly distributed symmetrically in the up/down and left/right sides so that the tension force by the tension or non-tension steel wires 26, 27 or 27a are evenly distributed throughout the entire portion of the girder 40.
  • FIG. 5 shows the arrangement of the steel wires in the lengthwise direction in the girder of FIG. 3A and a cut-open portion located in the middle of the girder.
  • the tension steel wires 26 and the non-tension steel wires 27 provided inside the girder 40 are concentrated in the lower portion at the middle portion of the girder 40 and evenly distributed throughout the entire sectional portion of the girder 40 at both end portions of the girder 40.
  • the tension and non-tension steel wires 26 and 27 are fixed at both ends of the girder 40 by a fixing means 32 which is an anchoring device.
  • the fixing member 32 is covered with concrete (not shown) after the girder 40 is constructed.
  • the girder is provided with a cut- open portion 36 for adjusting the tension force of the non-tension steel wires 27 at the middle portion of the girder or at another appropriated position.
  • the cut-open portion 36 is used as a space for accommodating a coupling member of the non-tension steel wires 27. That is, the cut-open portion 36 is used as a working space for adjusting the tension force of the non-tension steel wires 27 later.
  • cracks 34 or excessive sagging 35 indicated by a dotted line is generated to the girder 40 according to the present invention, as shown in FIG. 5, one or more non-tension steel wires 27 and 27a installed inside or outside the girder 40 are additionally tensioned for reinforcement.
  • the additional tensioning work for the non-tension steel wires 27 and 27a is performed using a hydraulic jack.
  • the tension forces of the non- tension steel wires 27 and 27a are adjusted during or after slab casting and after construction, the tension force is adjusted while the bridge is in use. That is, in the case of a continuous bridge, re-tensioning can be performed before slab casting. However, in the present invention, the re-tensioning is performed shortly after the slab casting before slab concrete is hardened to prevent application of a tension force on the slab.
  • FIG. 6 shows a preferred embodiment of fixing the steel wire at the end portion of the girder.
  • the steel wire 26 is anchored using a support member 50 as an anchoring device.
  • the steel wires 26 is inserted into a hole formed at the center of the support member 50 at one end of the girder 40.
  • a plurality of wedges 52 are inserted between the steel wire 26 and the support member 50.
  • the steel wire 26 is tensioned by a hydraulic jack and the tensioned steel wire 26 is fixed by the wedges 52.
  • FIG. 7 shows that steel wires are coupled by the coupling member as a preferred embodiment of a steel wire connection in the cut-open portion. As shown in the drawing, the cut-open portion 36 is formed in the middle of the bottom surface of the girder 40 in the lengthwise direction.
  • the steel wires 26 fixed at both ends of the girder 40 are connected to a coupling member 62 such that forces of different directions are applied.
  • the tension steel wire 26 to be connected at the coupling member 62 is connected using the support member 50 and the wedges 52.
  • the non-tension steel wires 27 connected to each other by the coupling member 62 is tensioned and fixed by using the wedges 52 so that the tension force by the tension steel wire 26 can be maintained. Also, by applying a tension force to the non-tension steel wires 27 and 27a provided at left and right sides of the girder 40, bending of the girder 40 to the left or right can be compensated for.
  • the steel wires 26 and 27 are connected to the coupling member 62 to be capable of moving to a degree, while the steel wires installed outside the girder 40 are not tensioned at all or tensioned by a small tension force so as to increase the tension forces of the steel wire later.
  • the tension force adjustable prestressed according to the present invention can be applied to other concrete structure such as a building as another preferred embodiment.

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Adhesives Or Adhesive Processes (AREA)
  • Polyurethanes Or Polyureas (AREA)

Abstract

A tension force adjustable prestressed girder is disclosed which can compensate for sagging or cracks of a girder generated due to overload or long-term creep or increase a load-resisting force of a bridge or a building. The tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange (28) supporting an upper deck of a bridge installed thereon, a body portion (22), and a lower flange (24) which includes tension steel wires (27) provided in a lengthwise direction of the girder (40) and tensioned to compensate for the load-resisting force, and at least one or more non-tension steel wires (27a) provided in the lengthwise direction of the girder, so that the load-resisting force of the bridge or building can be increased by tensioning the non-tension steel wires. Thus, cracks and sagging of a girder generated due to long-term deterioration, creep or overload can be corrected by additionally tensioning steel wires installed internally or externally at a girder of the bridge or building. Thus, repair and reinforcement of the bridge or building is easy so that the load-resisting force of the bridge or building can be easily increased. Also, by adjusting the tension force step by step, the girder can be economically manufactured or the height of the girder can be decreased.

Description

TENSION FORCE ADJUSTABLE PRESTRESSED GIRDER
Technical Field
The present invention relates to a girder, and more particularly, to a tension force adjustable prestressed girder which can compensate for sagging or cracks of a girder generated due to a long-term load and is capable of adjusting a tension force by increasing a load-resisting force of a bridge or building, if necessary, after the construction thereof.
Background Art
In general, when girders installed on a column of a concrete bridge become obsolete as time passes or heavy vehicles exceeding the originally designed weight allowance of a bridge pass over the bridge for a prolonged period, the beam of the bridge may become damaged and an excessive sagging may occur at the girders. Concurrently, bending/tensile cracks are generated and, when such damage continues, the bridge may ultimately collapse. Thus, appropriate repair and reinforcement of the bridge is required.
Meanwhile, a prestressed concrete (PSC) bridge is repaired and reinforced by means of an external steel wire reinforcement construction method. According to the above reinforcement construction method, an externally installed steel wire is to be fixed appropriately at an end portion of a girder. However, it is difficult to install a wire fixing apparatus at the end portion of a girder and reliability on the load-resisting force of the wire fixing apparatus is not assured. Thus, although other methods have been suggested and applied, no effective apparatuses have been developed yet. That is, when cracks and sagging occur in a PCS bridge, it is very difficult to repair and reinforce the bridge.
Also, as the traffic volume continuously increases and automobile manufacturing technologies develop, the weight of a vehicle increases. With an increase in the weight of a vehicle, the specifications which is a standard of designing a bridge must be modified. Modifications of the specifications necessarily results in an unbalanced load-resisting state, i.e., the load-resisting forces of the existing bridges are not matched. In other words, in a state in which roads allowing passage of heavy trucks and roads not allowing passage of heavy trucks exist together, the efficiency of transportation network system as a whole is severely lowered. Thus, to make the unbalanced load-resisting forces of these bridges consistent, an economical reinforcement method for upgrading the level of the bridge from 2 to 1 must be urgently found.
As the width of a road increases due to an increase in the number of lanes of a road, the development of a wide span girder for constructing an elevated road or an overpass crossing a wide road has proceeded. Although a preflex beam has been developed and used for the above purposes, conveying the girder is inconvenient due to the length thereof and because the costs are high. Currently, high strength concrete is used for a girder less than 30 m long that is not a wide span girder. However, as a high tension force is applied to the girder, the amount of creep generated becomes great. As the creep increases, the girder sags further which directly affects the longitudinal alignment of the road. When the longitudinal alignment deteriorates, a coefficient of impact by passing vehicles increases. Thus, in the case of a high strength girder or a wide span girder, when the girder is used for a long time, an appropriate construction method for compensating for sagging of the girder is required.
Also, the height of a girder which is long in span is relatively high such that the girder itself is 2.00 m - 3.00 m high. Such a fact entails an increase in the height of an upper deck of an overpass so that, to secure a longitudinal alignment of the overpass matching the designed vehicle speed, the length of the overpass becomes longer, thus raising the construction costs. In the case of a bridge crossing a river, to lower the height of the girder as low as possible is inevitably needed for improving the usability and the economic value of the girder.
FIG. 1 shows the structure of a general bridge. As shown in the drawing, a plurality of I-type girders 12 are installed on a column 10. An upper deck slab (not shown) is installed on the girders 12 of the bridge.
FIG. 2 is a sectional view showing a girder in which steel wires are arranged according to the conventional technology. As shown in the drawing, a girder 20 consists of a body portion 22, an upper flange 28, and a lower flange 24. A plurality of steel wires 26 are built in the body portion 22 in the lengthwise direction. An upper deck of a bridge is installed on the upper flange 28 and the bottom surface of the lower flange 24 is supported by the column 10. After the I-type girder 20 according to the conventional technology is constructed, when the bridge is damaged, that is, sagging or cracks are generated due to the increased traffic volume passing over the bridge, or when the designed passage load must be increased according to the revision of the specifications, reinforcement of the bridge is required. However, there are no economical and reliable reinforcement methods applicable therefor.
Disclosure of the Invention
It is an objective of the present invention to provide a prestressed girder of which a tension force can be adjusted by adjusting a tension force of a steel wire provided in a body portion or lower flange of the girder to easily increase a load-resisting force of a bridge or building, when excessive sagging or cracks are generated in a girder due to long-term use or when there is a need to increase the load-resisting force of the bridge or building without damaging the bridge or building.
Accordingly, to achieve the above objective, there is provided a tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge installed thereon, a body portion, and a lower flange, which includes tension steel wires provided in a lengthwise direction of the girder and tensioned to compensate for the load-resisting force, and at least one or more non-tension steel wires provided in the lengthwise direction of the girder, so that the load-resisting force of the bridge can be increased by tensioning the non-tension steel wires.
It is preferred in the present invention that the tension force adjustable prestressed girder further comprises a cut-open portion at a predetermined portion in the lengthwise direction of the girder and a coupling member installed at the cut-open portion for fixing one ends of the steel wires of which the other ends are fixed at an end portion of the girder. According to another preferred embodiment of the present invention, there is provided a tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge installed thereon, a body portion, and a lower flange, which includes tension steel wires provided in a lengthwise direction of the girder and tensioned to compensate for the load-resisting force, and one or more non-tension steel wires provided in the lengthwise direction of the girder, so that the load-resisting force of the bridge can be increased by tensioning the non-tension steel wires during construction of the girder and/or after the construction thereof.
Although the present invention can be applied to any type of girder regardless of the shape of the section of the girder such as an I-type girder or a bulb T-type girder, the I-type girder is described in the below preferred embodiment.
Brief Description of the Drawings
FIG. 1 is a perspective view showing the structure of a general bridge;
FIG. 2 is a sectional view showing the arrangement of steel wires in the girder according to conventional technology;
FIG. 3A is a sectional view showing the arrangement of steel wires in the middle portion of a girder according to the present invention; FIG. 3B is a sectional view showing the steel wires according to another preferred embodiment of the present invention;
FIG. 4A is a sectional view showing the arrangement of steel wires at the end portion of the girder of FIG. 3A;
FIG. 4B is a sectional view showing the arrangement of steel wires at the end portion of the girder of FIG. 3B;
FIG. 5 is a view showing a cut-open portion located at the middle portion of the girder and the arrangement of the steel wires in the girder;
FIG. 6 is a side view showing an example of a steel wire fixed at the end portion of the girder; and
FIG. 7 is a perspective view showing an example of the steel wires in the cut-open portion.
Best mode for carrying out the Invention
In FIG. 3A , a girder 40 includes an upper flange 28, a lower flange 24, and a body portion 22. One or more tension steel wires 26 and non- tension steel wires 27 are built in and across the lower portion of the body portion 22 and the lower flange 24 of the girder 40 in the lengthwise direction of the girder 40.
Preferably, the non-tension steel wires 27 are built in the lower flange 28 horizontally parallel to each other, as shown in FIG. 3A. The upper flange 28 is provided above the body portion 22 in the latitudinal direction in the section of the girder 40 and an upper deck of a bridge is installed on the upper flange 28. The lower flange 24 is provided below the body portion 22 in the latitudinal direction in the section of the girder 40 and the bottom surface thereof is supported by a column (not shown).
FIG. 3B shows a steel wire according to another preferred embodiment of the present invention. As shown in the drawing, a plurality of non-tension steel wires 27a are provided in the lengthwise direction of the girder 40 outside the lower portion of the body portion 22. The non- tension steel wires 27a have the same function as that of the non-tension steel wire 27 provided in the lower flange 24, as shown in FIG. 3A. That is, after a bridge is constructed, sagging of the girder 40 is compensated for by tensioning the non-tension steel wires 27a. Also, the non-tension steel wires 27a can be more easily installed compared to a case of being installed inside the lower flange 24.
FIG. 4A shows the arrangement of the steel wires built in the girder of FIG. 3A. As shown in the drawing, the tension steel wires 26 and the non-tension steel wires 27 concentrated at the lower portion of the girder 40 are distributed throughout the entire sectional portion of the girder 40. That is, the steel wires are evenly distributed symmetrically in up/down and left/right sides of the girder 40 so that the tension force by the tension steel wires 26 and the non-tension steel wires 27 can be evenly distributed throughout the entire portion of the girder 40. FIG. 4B shows the arrangement of the steel wires at the end portion of the girder shown in FIG. 3B. As shown in the drawing, the tension steel wires 26 or the non-tension steel wires 27 and 27a concentrated at the lower portion of the girder as shown in FIG. 3B are evenly distributed symmetrically in the up/down and left/right sides so that the tension force by the tension or non-tension steel wires 26, 27 or 27a are evenly distributed throughout the entire portion of the girder 40.
FIG. 5 shows the arrangement of the steel wires in the lengthwise direction in the girder of FIG. 3A and a cut-open portion located in the middle of the girder. The tension steel wires 26 and the non-tension steel wires 27 provided inside the girder 40 are concentrated in the lower portion at the middle portion of the girder 40 and evenly distributed throughout the entire sectional portion of the girder 40 at both end portions of the girder 40. The tension and non-tension steel wires 26 and 27 are fixed at both ends of the girder 40 by a fixing means 32 which is an anchoring device. The fixing member 32 is covered with concrete (not shown) after the girder 40 is constructed.
Here, when the girders are installed having intervals therebetween, or when a portion of the end of the girder is cut away, as shown in the drawing, a space is formed between the adjacent girders. Thus, a tensioning work can be performed in the space when the tension and non- tension steel wires 26 and 27 are to be re-tensioned later. However, in this case, the end portion of the girder 40 must not be covered with concrete. Here, one end of the non-tension steel wires 26 and 27 is exposed at either end portions of the girder 40 to apply a tension force.
Also, in a preferred embodiment, the girder is provided with a cut- open portion 36 for adjusting the tension force of the non-tension steel wires 27 at the middle portion of the girder or at another appropriated position. The cut-open portion 36 is used as a space for accommodating a coupling member of the non-tension steel wires 27. That is, the cut-open portion 36 is used as a working space for adjusting the tension force of the non-tension steel wires 27 later. When cracks 34 or excessive sagging 35 indicated by a dotted line is generated to the girder 40 according to the present invention, as shown in FIG. 5, one or more non-tension steel wires 27 and 27a installed inside or outside the girder 40 are additionally tensioned for reinforcement. Here, the additional tensioning work for the non-tension steel wires 27 and 27a is performed using a hydraulic jack. Also, the tension forces of the non- tension steel wires 27 and 27a are adjusted during or after slab casting and after construction, the tension force is adjusted while the bridge is in use. That is, in the case of a continuous bridge, re-tensioning can be performed before slab casting. However, in the present invention, the re-tensioning is performed shortly after the slab casting before slab concrete is hardened to prevent application of a tension force on the slab.
FIG. 6 shows a preferred embodiment of fixing the steel wire at the end portion of the girder. The steel wire 26 is anchored using a support member 50 as an anchoring device. For example, the steel wires 26 is inserted into a hole formed at the center of the support member 50 at one end of the girder 40. A plurality of wedges 52 are inserted between the steel wire 26 and the support member 50. Here, the steel wire 26 is tensioned by a hydraulic jack and the tensioned steel wire 26 is fixed by the wedges 52. FIG. 7 shows that steel wires are coupled by the coupling member as a preferred embodiment of a steel wire connection in the cut-open portion. As shown in the drawing, the cut-open portion 36 is formed in the middle of the bottom surface of the girder 40 in the lengthwise direction.
The steel wires 26 fixed at both ends of the girder 40 are connected to a coupling member 62 such that forces of different directions are applied.
Here, the tension steel wire 26 to be connected at the coupling member 62 is connected using the support member 50 and the wedges 52.
Thus, the non-tension steel wires 27 connected to each other by the coupling member 62 is tensioned and fixed by using the wedges 52 so that the tension force by the tension steel wire 26 can be maintained. Also, by applying a tension force to the non-tension steel wires 27 and 27a provided at left and right sides of the girder 40, bending of the girder 40 to the left or right can be compensated for.
According to the arrangement of steel wires and the coupling apparatus the present invention, when a bridge is constructed or at an initial stage of construction, the steel wires 26 and 27 are connected to the coupling member 62 to be capable of moving to a degree, while the steel wires installed outside the girder 40 are not tensioned at all or tensioned by a small tension force so as to increase the tension forces of the steel wire later.
Although a bridge is described as an example in the above preferred embodiment, the tension force adjustable prestressed according to the present invention can be applied to other concrete structure such as a building as another preferred embodiment.
It is noted that the present invention is not limited to the preferred embodiment described above, and it is apparent that variations and modifications by those skilled in the art can be effected within the spirit and scope of the present invention defined in the appended claims.
Industrial Applicability
As described above, according to the present invention, cracks and sagging of a bridge generated due to long-term deterioration, creep or overload can be corrected by additionally tensioning steel wires installed internally or externally at a girder of the bridge. Thus, repair and reinforcement of the bridge is easy so that the load-resisting force of the bridge can be easily increased. Also, by adjusting the tension force step by step, the girder can be economically manufactured or the height of the girder can be decreased.

Claims

What is claimed is:
1. A tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge or building installed thereon, a body portion, and a lower flange, said prestressed girder comprising: tension steel wires provided in a lengthwise direction of said girder and tensioned to compensate for said load-resisting force; and at least one or more non-tension steel wires provided in the lengthwise direction of said girder, so that the load-resisting force of said bridge or building can be increased by tensioning said non-tension steel wires.
2. The tension force adjustable prestressed girder as claimed in claim 1 , further comprising a cut-open portion at a predetermined portion in the lengthwise direction of said girder and a coupling member installed at said cut-open portion for fixing one ends of said steel wires of which the other ends are fixed at an end portion of said girder.
3. The tension force adjustable prestressed girder as claimed in claim 1 , wherein said coupling member comprises a support member having holes formed therein through which one ends of said steel wires having the other ends thereof fixed at an end portion of said girder penetrate, and wedges inserted between said steel wire and said support member.
4. The tension force adjustable prestressed girder as claimed in claim 1 , wherein one end of said non-tension steel wire is exposed at either end portions of said girder to apply a tension force.
5. A tension force adjustable prestressed girder for adjusting a load-resisting force which consists of an upper flange supporting an upper deck of a bridge or building installed thereon, a body portion, and a lower flange, said prestressed girder comprising: tension steel wires provided in a lengthwise direction of said girder and tensioned to compensate for said load-resisting force; and one or more non-tension steel wires provided in the lengthwise direction of said girder, so that the load-resisting force of said bridge or building can be increased by tensioning said non-tension steel wires during construction of said girder and/or after the construction thereof.
6. The tension force adjustable prestressed girder as claimed in claim 5, wherein, during construction, a tension force of said non-tension steel wires is adjusted during or after slab casting, and, after the construction, the tension force of said non-tension steel wires is adjusted while said bridge or building is being used.
PCT/KR1999/000567 1998-11-07 1999-09-20 Tension force adjustable prestressed girder WO2000028168A1 (en)

Priority Applications (8)

Application Number Priority Date Filing Date Title
AT99944909T ATE259020T1 (en) 1998-11-07 1999-09-20 PRE-TENSIONED TIE WITH ADJUSTABLE PRE-TENSION
AU57633/99A AU750126B2 (en) 1998-11-07 1999-09-20 Tension force adjustable prestressed girder
DE69914621T DE69914621T2 (en) 1998-11-07 1999-09-20 PRELOADED BINDER WITH ADJUSTABLE TENSION
UA2001042935A UA70968C2 (en) 1998-11-07 1999-09-20 Tension force adjustable prestressed girder
EP99944909A EP1129263B1 (en) 1998-11-07 1999-09-20 Tension force adjustable prestressed girder
CA002349855A CA2349855C (en) 1998-11-07 1999-09-20 Tension force adjustable prestressed girder
JP2000581321A JP2003501568A (en) 1998-11-07 1999-09-20 Prestressed girder with adjustable tension
BR9915041-7A BR9915041A (en) 1998-11-07 1999-09-20 Pre-tensioned beam adjustable by tension force

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR1998/47661 1998-11-07
KR1019980047661A KR100301431B1 (en) 1998-11-07 1998-11-07 Prestressed concrete girder with regulable tensile force

Publications (1)

Publication Number Publication Date
WO2000028168A1 true WO2000028168A1 (en) 2000-05-18

Family

ID=19557479

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR1999/000567 WO2000028168A1 (en) 1998-11-07 1999-09-20 Tension force adjustable prestressed girder

Country Status (15)

Country Link
EP (1) EP1129263B1 (en)
JP (1) JP2003501568A (en)
KR (1) KR100301431B1 (en)
CN (1) CN1115451C (en)
AT (1) ATE259020T1 (en)
AU (1) AU750126B2 (en)
BR (1) BR9915041A (en)
CA (1) CA2349855C (en)
DE (1) DE69914621T2 (en)
ES (1) ES2217805T3 (en)
RU (1) RU2213187C2 (en)
TR (1) TR200101267T2 (en)
UA (1) UA70968C2 (en)
WO (1) WO2000028168A1 (en)
ZA (1) ZA200103608B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006007660A1 (en) * 2004-07-21 2006-01-26 Murray Ellen Building methods
GB2431176B (en) * 2004-07-21 2009-12-02 S2 Holdings Pty Ltd Building Methods
RU2677188C1 (en) * 2018-02-26 2019-01-15 Федеральное государственное бюджетное образовательное учреждение высшего образования "Петербургский государственный университет путей сообщения Императора Александра I" Preliminary stress-bearing reinforced beam

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010036486A (en) * 1999-10-08 2001-05-07 박상일 Method for designing and fabricating multi-step tension prestressed girder
KR20020071611A (en) * 2001-03-07 2002-09-13 박재만 Pss beam
KR100427405B1 (en) * 2001-03-07 2004-04-17 박재만 Pssc complex girder
KR100466429B1 (en) * 2001-09-28 2005-01-13 허진구 PSC girder that possible an external tension
KR20040049590A (en) * 2002-12-06 2004-06-12 한국과학기술원 Multiple Stage prestressed Girder
KR100950027B1 (en) 2009-12-04 2010-03-29 영창중공업 주식회사 Composite girder for bridge
KR101263305B1 (en) 2011-10-25 2013-05-10 김상운 Correction structuer of bridge deck
KR101265544B1 (en) 2012-05-15 2013-05-20 주식회사 장헌산업 Pretensioned psc girder of i-type using debonding method
CN103147537B (en) * 2013-03-05 2016-08-03 哈尔滨工程大学 A kind of bending carrying girder steel
CH706630B1 (en) * 2013-05-14 2013-12-31 S & P Clever Reinforcement Company Ag Method for pretensioning steel structure e.g. iron bridge, involves vertically driving lifting element to polymer tapes in region between end anchorages for causing traction force tensioning between end regions of polymer tapes
KR101682923B1 (en) 2016-06-15 2016-12-06 주식회사 노빌테크 Manufacturing method of channel type prestressed girder and the construction method using the girder manufactured thereby
CN106758873A (en) * 2016-11-11 2017-05-31 太原理工大学 A kind of punching prestressing force strengthens the method that diaphragm plate is connected with girder
RU2669595C1 (en) * 2017-11-27 2018-10-12 Общество с ограниченной ответственностью "НПП СК МОСТ" Method of strengthening the flight structure of bridge structure with change of the cross section
CN113324848B (en) * 2021-05-20 2022-07-15 山东大学 Low-temperature bending strain test method for asphalt mixture trabecula test piece

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4604003A (en) * 1983-02-22 1986-08-05 Francoeur Ronald A Method and apparatus for retensioning prestressed concrete members
US4831800A (en) * 1987-06-24 1989-05-23 Nedelcu Lucian I Beam with an external reinforcement system
US5313749A (en) * 1992-04-28 1994-05-24 Conner Mitchel A Reinforced steel beam and girder
US5671572A (en) * 1994-02-11 1997-09-30 Siller-Franco; Jose Luis Method for externally reinforcing girders

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100261556B1 (en) * 1997-12-31 2000-07-15 박재만 Restrain apparatus for prestress structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4604003A (en) * 1983-02-22 1986-08-05 Francoeur Ronald A Method and apparatus for retensioning prestressed concrete members
US4831800A (en) * 1987-06-24 1989-05-23 Nedelcu Lucian I Beam with an external reinforcement system
US5313749A (en) * 1992-04-28 1994-05-24 Conner Mitchel A Reinforced steel beam and girder
US5671572A (en) * 1994-02-11 1997-09-30 Siller-Franco; Jose Luis Method for externally reinforcing girders

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
EIBL J: "DIE EXTERNE VORSPANNUNG IN DEUTSCHLAND - ENTWICKLUNG UND AUSBLICK", EXTERNE VORSPANNUNG UND SEGMENTBAUWEISE, XX, XX, 1 October 1998 (1998-10-01), XX, pages 71 - 90, XP002946477 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2006007660A1 (en) * 2004-07-21 2006-01-26 Murray Ellen Building methods
GB2431175A (en) * 2004-07-21 2007-04-18 Murray Ellen Building Methods
GB2431176B (en) * 2004-07-21 2009-12-02 S2 Holdings Pty Ltd Building Methods
GB2431175B (en) * 2004-07-21 2009-12-02 Murray Ellen Building Methods
US8443572B2 (en) 2004-07-21 2013-05-21 S2 Holdings Pty Limited Building methods
US8607528B2 (en) 2004-07-21 2013-12-17 Murray Ellen Building methods
RU2677188C1 (en) * 2018-02-26 2019-01-15 Федеральное государственное бюджетное образовательное учреждение высшего образования "Петербургский государственный университет путей сообщения Императора Александра I" Preliminary stress-bearing reinforced beam

Also Published As

Publication number Publication date
TR200101267T2 (en) 2002-03-21
ATE259020T1 (en) 2004-02-15
ES2217805T3 (en) 2004-11-01
DE69914621T2 (en) 2004-09-23
UA70968C2 (en) 2004-11-15
CN1331773A (en) 2002-01-16
EP1129263A1 (en) 2001-09-05
RU2213187C2 (en) 2003-09-27
AU5763399A (en) 2000-05-29
JP2003501568A (en) 2003-01-14
CA2349855A1 (en) 2000-05-18
BR9915041A (en) 2002-06-04
ZA200103608B (en) 2002-08-15
CN1115451C (en) 2003-07-23
KR100301431B1 (en) 2001-10-29
EP1129263B1 (en) 2004-02-04
DE69914621D1 (en) 2004-03-11
CA2349855C (en) 2004-12-14
AU750126B2 (en) 2002-07-11
KR19990078494A (en) 1999-11-05

Similar Documents

Publication Publication Date Title
AU750126B2 (en) Tension force adjustable prestressed girder
KR100380637B1 (en) Prestressed concrete girder of adjustable load bearing capacity for bridge and adjustment method for load bearing capacity of bridge
KR100699413B1 (en) Channel bridge construction method available to control channel bridge segment sag
KR100592196B1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
EP0861354B1 (en) Method for building a bridge and bridge built according to said method
KR100456471B1 (en) Open-type steel wire holding device and Metod for construction of continuous bridge using of prestressed concret beam having it
KR20040091350A (en) Prestressed steel girder
US5727272A (en) Composite structure, especially bridge
KR100554026B1 (en) Open-type steel wire holding device of bridge
KR100254056B1 (en) Method and apparatus for repairing and reinforcing beams of bridge
KR20050024804A (en) Section increasing and reinforcing apparatus for reinforcing section of the lower part of slab between girder and cross beam in girder bridge and installing method thereof
KR100616533B1 (en) Construction method for p.s.c. girder bridges and bridges production it
MXPA01004608A (en) Tension force adjustable prestressed girder
KR100442969B1 (en) Method and its devices to strengthen a bridge by external prestressing cable
KR100349880B1 (en) Adjusting apparatus for prestressing force of girder
KR100475585B1 (en) Method and apparatus for reinforcing P.S.C. beams for bridges
KR100493447B1 (en) Expansion joint for a bridge
KR200333780Y1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket
KR20040108229A (en) Fabricated repairing and reinforcing apparatus for reinforcing bearing force of beam in a bridge and construction method using the apparatus
RU2681048C1 (en) Reinforced beam of reinforced concrete span of the bridge
KR200332722Y1 (en) The structure load-carrying capacity improvement method of construction using steel beam and bracket
KR200310500Y1 (en) Expansion joint for a bridge
KR200291579Y1 (en) Apparatus for reinforcing P.S.C. beams for bridges
KR200328853Y1 (en) Fabricated repairing and reinforcing apparatus for reinforcing bearing force of beam in a bridge
KR20030000945A (en) The reinforcement method of slab bridge

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 99813000.1

Country of ref document: CN

AK Designated states

Kind code of ref document: A1

Designated state(s): AE AL AM AT AU AZ BA BB BG BR BY CA CH CN CU CZ DE DK EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KZ LC LK LR LS LT LU LV MD MG MK MN MW MX NO NZ PL PT RO RU SD SE SG SI SK SL TJ TM TR TT UA UG US UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
ENP Entry into the national phase

Ref document number: 2000 581321

Country of ref document: JP

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: IN/PCT/2001/100351/D

Country of ref document: IN

Ref document number: IN/PCT/2001/00351/DE

Country of ref document: IN

WWE Wipo information: entry into national phase

Ref document number: 57633/99

Country of ref document: AU

ENP Entry into the national phase

Ref document number: 2349855

Country of ref document: CA

Ref document number: 2349855

Country of ref document: CA

Kind code of ref document: A

WWE Wipo information: entry into national phase

Ref document number: 2001/03608

Country of ref document: ZA

Ref document number: 200103608

Country of ref document: ZA

Ref document number: 2001/01267

Country of ref document: TR

Ref document number: 1200100402

Country of ref document: VN

WWE Wipo information: entry into national phase

Ref document number: PA/a/2001/004608

Country of ref document: MX

WWE Wipo information: entry into national phase

Ref document number: 1999944909

Country of ref document: EP

WWP Wipo information: published in national office

Ref document number: 1999944909

Country of ref document: EP

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

WWE Wipo information: entry into national phase

Ref document number: 09831337

Country of ref document: US

WWG Wipo information: grant in national office

Ref document number: 57633/99

Country of ref document: AU

WWG Wipo information: grant in national office

Ref document number: 1999944909

Country of ref document: EP