US20150039281A1 - Optimizing Drilling Operations Using Petrotechnical Data - Google Patents
Optimizing Drilling Operations Using Petrotechnical Data Download PDFInfo
- Publication number
- US20150039281A1 US20150039281A1 US14/517,578 US201414517578A US2015039281A1 US 20150039281 A1 US20150039281 A1 US 20150039281A1 US 201414517578 A US201414517578 A US 201414517578A US 2015039281 A1 US2015039281 A1 US 2015039281A1
- Authority
- US
- United States
- Prior art keywords
- depth
- well
- model
- earth model
- drilling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 107
- 238000000034 method Methods 0.000 claims abstract description 69
- 230000005012 migration Effects 0.000 claims description 27
- 238000013508 migration Methods 0.000 claims description 27
- 238000003384 imaging method Methods 0.000 claims description 21
- 230000009471 action Effects 0.000 claims description 16
- 238000003325 tomography Methods 0.000 claims description 10
- 238000004458 analytical method Methods 0.000 claims description 9
- 238000010276 construction Methods 0.000 claims description 7
- 239000011148 porous material Substances 0.000 claims description 7
- 238000013461 design Methods 0.000 claims description 5
- 230000006870 function Effects 0.000 claims description 3
- 238000003860 storage Methods 0.000 description 23
- 238000005259 measurement Methods 0.000 description 17
- 238000012550 audit Methods 0.000 description 11
- 238000004891 communication Methods 0.000 description 10
- 230000008569 process Effects 0.000 description 10
- 238000005516 engineering process Methods 0.000 description 9
- 238000004519 manufacturing process Methods 0.000 description 7
- 238000012545 processing Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 6
- 238000013500 data storage Methods 0.000 description 5
- 230000005484 gravity Effects 0.000 description 5
- 238000011084 recovery Methods 0.000 description 5
- 230000008901 benefit Effects 0.000 description 4
- 230000002708 enhancing effect Effects 0.000 description 4
- 230000001965 increasing effect Effects 0.000 description 4
- 230000008859 change Effects 0.000 description 3
- 150000003839 salts Chemical class 0.000 description 3
- 239000004215 Carbon black (E152) Substances 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000012530 fluid Substances 0.000 description 2
- 229930195733 hydrocarbon Natural products 0.000 description 2
- 150000002430 hydrocarbons Chemical class 0.000 description 2
- 230000002452 interceptive effect Effects 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- VNWKTOKETHGBQD-UHFFFAOYSA-N methane Chemical compound C VNWKTOKETHGBQD-UHFFFAOYSA-N 0.000 description 2
- 238000005070 sampling Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000000052 comparative effect Effects 0.000 description 1
- 230000003750 conditioning effect Effects 0.000 description 1
- 238000013079 data visualisation Methods 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 238000005755 formation reaction Methods 0.000 description 1
- 239000007789 gas Substances 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000012804 iterative process Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000007726 management method Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 238000012544 monitoring process Methods 0.000 description 1
- 239000003345 natural gas Substances 0.000 description 1
- 230000003287 optical effect Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000035699 permeability Effects 0.000 description 1
- 238000013439 planning Methods 0.000 description 1
- 238000003908 quality control method Methods 0.000 description 1
- 230000004044 response Effects 0.000 description 1
- 238000012502 risk assessment Methods 0.000 description 1
- 238000013349 risk mitigation Methods 0.000 description 1
- 239000011435 rock Substances 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 238000012546 transfer Methods 0.000 description 1
- 230000007723 transport mechanism Effects 0.000 description 1
- 238000012384 transportation and delivery Methods 0.000 description 1
- 238000010200 validation analysis Methods 0.000 description 1
- 238000012800 visualization Methods 0.000 description 1
Images
Classifications
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01V—GEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
- G01V20/00—Geomodelling in general
-
- G01V99/005—
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B41/00—Equipment or details not covered by groups E21B15/00 - E21B40/00
-
- E21B41/0092—
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B44/00—Automatic control systems specially adapted for drilling operations, i.e. self-operating systems which function to carry out or modify a drilling operation without intervention of a human operator, e.g. computer-controlled drilling systems; Systems specially adapted for monitoring a plurality of drilling variables or conditions
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21B—EARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
- E21B7/00—Special methods or apparatus for drilling
- E21B7/04—Directional drilling
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01V—GEOPHYSICS; GRAVITATIONAL MEASUREMENTS; DETECTING MASSES OR OBJECTS; TAGS
- G01V1/00—Seismology; Seismic or acoustic prospecting or detecting
- G01V1/40—Seismology; Seismic or acoustic prospecting or detecting specially adapted for well-logging
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F17/00—Digital computing or data processing equipment or methods, specially adapted for specific functions
-
- G06F17/5009—
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
Definitions
- Implementations of various technologies described herein generally relate to drilling operations.
- the method includes providing an earth model of a volume having a well, obtaining petrotechnical data about the volume while drilling the well, comparing the petrotechnical data with the earth model, updating the earth model with the petrotechnical data based on the comparison, and modifying a drilling plan of the well using the updated earth model.
- the earth model may be updated by performing a migration imaging process on the volume.
- the earth model may be updated by creating a three dimensional (3D) anisotropic depth model with the petrotechnical data, merging the 3D anisotropic depth model in depth sections, performing a prestack depth migration, performing tomographic anisotropic properties update, performing interpretation, performing inversion for pore pressure or lithology properties of the earth model, or combinations thereof.
- the drilling plan may be modified by comparing a subsurface image, property volume or interpretation, or combinations thereof, derived from the earth model with a subsurface image, property volume or interpretation, or combinations thereof, derived from the updated earth model; and generating a set of three dimensional (3D) or two dimensional (2D) coordinates for a well trajectory based on the comparison.
- the drilling plan may be modified by providing a design of a well trajectory, performing an economic and technical analysis of the well trajectory, changing an existing casing plan, defining a well construction based on the well trajectory, defining a well construction based on interpretations or properties derived from the updated earth model, or combinations thereof.
- providing the earth model may include: conducting an audit and feasibility study on the volume; and selecting the earth model based on the audit and feasibility study.
- Conducting the audit and feasibility study on the volume may include assessing the quality and relevance of available petrotechnical information regarding the volume.
- the available petrotechnical information regarding the volume may include reports or documentations pertaining to the subsurface structure and properties at or around the volume.
- Selecting the earth model based on the audit and feasibility study may include selecting the earth model that is most congruent with the available petrotechnical information regarding the volume.
- Conducting the audit and feasibility study on the volume may include performing forward modeling on earth models and seismic images of the volume.
- the forward modeling may include ray tracing, wavefield modeling or finite difference techniques or combinations thereof.
- the method may further include highgrading the earth model prior to drilling the well.
- Highgrading the earth model may include enhancing the resolution of the earth model. Enhancing the resolution of the selected earth model may include increasing the vertical and spatial sampling rate.
- highgrading the earth model may include enhancing the calibration of the earth model and enhancing the calibration of the earth model may include calibrating the earth model to depth.
- the petrotechnical data may include wellbore measurements, gravity acquisition data, borehole seismic data, electromagnetic survey data, surface seismic data or combinations thereof.
- the earth model is updated only if the variance between the petrotechnical data and the earth model exceeds a predetermined value.
- the method for optimizing drilling operations of a well may include highgrading an earth model of a volume having the well, obtaining petrotechnical data about the volume while drilling the well, comparing the petrotechnical data with the highgraded earth model, updating the highgraded earth model with the petrotechnical data based on the comparison, and modifying a drilling plan of the well using the updated highgraded earth model.
- Various techniques described herein are also directed to a method for conducting an audit and feasibility study for drilling operations.
- the method may include evaluating the quality and relevance of available petrotechnical information regarding a volume having a well to be drilled, performing a forward modeling on earth models and seismic images of the volume and generating a scenario plan for the well.
- Various techniques described herein are also directed to a method for providing a set of actions for modifying a drilling plan of a well.
- the method may include comparing a subsurface image, property volume or interpretation of an earth model of the well with a subsurface image, property volume or interpretation of an updated earth model; generating a set of three dimensional (3D) coordinates for a well trajectory based on the comparison; and modifying the drilling plan based on the well trajectory.
- 3D three dimensional
- Various techniques described herein are also directed to a method for updating an earth model of a volume having a well.
- the method may include creating a three dimensional anisotropic depth model; comparing the three dimensional anisotropic depth model with petrotechnical data obtained while drilling the well; determining whether the three dimensional anisotropic depth model deviates from the petrotechnical data by greater than a predetermined amount; and if the deviation exceeds the predetermined amount, then updating the three dimensional anisotropic depth model.
- FIG. 1 illustrates a flow diagram of a method for optimizing drilling operations in accordance with implementations of various techniques described herein.
- FIG. 2 illustrates a flow diagram of a method for conducting the audit and feasibility study in accordance with various implementations described herein.
- FIG. 3 illustrates a process for generating the set of actions for modifying the drilling plan in accordance with implementations described herein.
- FIG. 4 illustrates an example of a well trajectory that has been modified in accordance with various implementations described herein.
- FIG. 5 illustrates a computing system, into which implementations of various techniques described herein may be implemented.
- FIG. 6 illustrates a flow diagram of a method for performing a migration imaging process in accordance with implementations of various techniques described herein.
- FIG. 1 illustrates a flow diagram of a method 100 for optimizing drilling operations in accordance with implementations of various techniques described herein.
- an audit of available information regarding an earth volume having the planned well to be drilled and feasibility study of drilling the planned well may be conducted.
- implementations of various techniques are described with reference to a well, it should be understood that some implementations may be applied to a system of well bores, sidetracks, multi-laterals and the like.
- the quality and relevance of the available information may be assessed.
- the result of the audit and feasibility study may be used to minimize uncertainties and mitigate risks associated with drilling the planned well.
- Available information regarding the planned well may include reports or documentations pertaining to the subsurface structure and properties at or around the planned well. They may also include reports or documentations pertaining to offset wells. Such reports may include well logs, drilling reports, incident analysis, completion practices of offset wells, production history of offset wells and existing surface seismic data.
- FIG. 2 illustrates a flow diagram of a method 200 for conducting the audit and feasibility study in accordance with various implementations described herein.
- the quality of existing seismic images, earth models, such as, geologic models, reservoir models and depth velocity models of the planned well and of offset wells and other petrotechnical data may be evaluated (step 210 ).
- petrotechnical data may refer to any reports or documentations obtained, wellbore measurements (e.g., sidetrack, multi-lateral or any well within the earth volume containing the planned well), gravity acquisition data, borehole acquired data (e.g., walkaway or 3D VSP), electromagnetic survey data or the assembled or updated earth model, images derived from the assembled or updated earth model in stacked or pre-stack domain, inversions or properties derived from the assembled or updated earth model, interpretations derived from the assembled or updated earth model, or any combinations thereof.
- Earth models may contain data that characterize the properties of geological features that form the earth's sub-surface, such as rock formations and faults.
- the data in an earth model may consist of measurements gathered during activities, such as the seismic, logging or drilling operations of the oil and gas industry, and of interpretations made from these measurements. The data may be gathered above, on, or below the earth's surface.
- the earth models to be evaluated are subsurface velocity models in the depth domain.
- the seismic images to be evaluated are prestack depth images.
- the earth models to be evaluated may be earth model property volumes.
- forward modeling may be performed on existing earth models of the earth volume, e.g., at the planned well and/or surrounding areas and seismic images of the planned well and/or surrounding areas (step 220 ).
- the forward modeling may be performed using ray tracing techniques or other seismic simulation techniques. In one implementation, this step may be performed to facilitate understanding whether the acquisition geometry illuminates the volume in which the planned well is located.
- a scenario plan for the drilling operation of the planned well may be created.
- the scenario plan may include evaluating and ranking risks associated with drilling the planned well and proposing appropriate contingency actions similar to an emergency response plan.
- the scenario plan may include recommendations for additional enhancements and/or interpretation of the subsurface earth model, such as prestack depth migration (PSDM) prior to drilling the well may be made.
- the scenario plan may include creating a fit-for-purpose catalog of migration algorithms for the construction of the well.
- the fit-for-purpose catalog of migration algorithms may include information on the quality and turn-around time (TAT) implication on the drilling operation.
- TAT quality and turn-around time
- the scenario plan may include establishing a pre-defined plan of earth model perturbations, which may facilitate understanding and quantifying possible impacts on the planned well trajectory as a result of changing seismic image volumes.
- a catalog of image volumes as a function of velocity field variations may be created. Such a catalog may be used as a look up utility while drilling, since it may include possible impacts in subsurface structural changes as a result of unexpected seismic velocity variations.
- the scenario plan may include revising the current well trajectory, preparing a drilling optimization contingency plan to reduce risk and minimize non productive time (NPT), workflows for inversion of reservoir properties for flowing wells, kicks, and the like.
- NPT non productive time
- the scenario plan may include integrating and visualizing well trajectory, predictive reservoir model, and resolved, calibrated depth imaged volumes to optimize well construction planning.
- the scenario plan may include using the seismic amplitude information to invert for material properties that can be vital not only to optimize ongoing drilling operations but also to assess reservoir sections yet to be drilled with respect to predicted hydrocarbon production and recovery.
- one earth model for the planned well and the surrounding areas based on the feasibility study may be selected.
- the earth model whose petrotechnical data are substantially similar or consistent is selected.
- the earth model whose gravity, borehole seismic, surface seismic and magnetotelluric data provide substantially the same depth, volume and shape of the planned well is selected as the most accurate earth model.
- a determination may be made as to whether the selected earth model may be highgraded. This determination may be made based on the scenario plan created at step 230 . If the answer is in the affirmative, then processing continues to step 130 . Otherwise, processing skips step 130 and continues to step 140 .
- the selected earth model may be highgraded.
- the resolution and/or calibration of the selected earth model may be enhanced.
- the resolution of the selected earth model may be enhanced, e.g., through multiple iterations of full 3D tomographic inversion.
- the resolution of the selected earth model may be enhanced by increasing the vertical and spatial sampling rate. The enhancement in resolution may improve the vertical, spatial and tomographic scale length resolution to levels required for various techniques to optimize drilling operations described herein.
- the selected earth model may be highgraded by calibrating the earth model to true depth, which may include obtaining wellbore measurements from nearby wells.
- the resolution and calibration of the selected earth model may be optimized in an iterative workflow using borehole-enhanced seismic processing techniques, measurements from offset wells and measurements from other sources, such as magnetotelluric, gravity and the like.
- the anisotropy components of the earth model may be calibrated. During this highgrading step, new earth models and images may be produced.
- a portion of the scenario plan may be modified.
- the integration and visualization of well trajectory, and predictive reservoir model may be modified using highgraded depth imaged volumes.
- drilling of the planned well may commence based on the scenario plan created at step 110 .
- petrotechnical data regarding the earth volume may be obtained during drilling.
- the petrotechnical data obtained at step 150 may be compared with the highgraded earth model.
- the petrotechnical data may be compared with the results of the feasibility study conducted at step 110 .
- the depth of the surface seismic data available from step 110 may be compared with the depth information obtained during drilling.
- the check-shot data may be compared with velocity data available from step 110 .
- the lithology report may be compared with the lithology from the selected earth model.
- the petrotechnical data may be compared with the initial earth model selected at step 120 .
- the petrotechnical data may be processed prior to being compared. For instance, the petrotechnical data may be processed to remove noise from the data.
- the comparison may be made on real time. In another implementation, the comparison may be made within a time period sufficient to modify or confirm the drilling plan.
- a determination may be made as to whether the deviation between the petrotechnical data obtained at step 150 and the initial selected earth model, the highgraded earth model or the results of the feasibility study exceeds a predetermined value. If the deviation is less than the predetermined value, then processing ends and the planned well is drilled according to the existing drilling plan. On the other hand, if the deviation exceeds the predetermined value, then processing continues to step 170 .
- one or more set of actions may be performed based on the extent to which the petrotechnical data obtained at step 150 deviate from the highgraded earth model, the initial earth model or the results of the feasibility study.
- the set of actions may include techniques of various levels of technical sophistication for depth imaging, which may range from vertical stretching, map migration, post-stack depth migration to pre-stack depth migration. The magnitude of the deviation may be used to determine the action to be performed.
- the set of actions may be part of the scenario plan developed at step 230 .
- the selected earth model may be updated, i.e., by relaunching the migration imaging process, when the wellbore measurements vary from the results of the feasibility study by a predetermined value, e.g., when the depth varies by more than 5%.
- the migration imaging process may range from creating a 3D anisotropic depth model, merging the 3D anisotropic depth model in depth sections, performing a prestack depth migration to performing tomographic anisotropic properties update.
- the level of technical sophistication and cost associated with the migration imaging process may be provided.
- the selected earth model may be updated using other types of measurements during drilling, e.g., gravity survey measurements, electromagnetic survey measurements and the like.
- the selected earth model may be updated at predetermined times in the drilling plan.
- FIG. 6 illustrates a flow diagram of a method 600 for performing a migration imaging process in accordance with implementations of various techniques described herein.
- the migration imaging process may be an iterative process.
- the earth model may be updated by creating a 3D anisotropic depth model.
- a comparison may then be made between the 3D anisotropic depth model and the petrotechnical data obtained at step 150 , and a determination may be made as to whether the deviation exceeds a predetermined value. If the answer is in the affirmative, then the earth model may be updated using the petrotechnical data obtained during drilling (step 630 ). In one implementation, this updating step may include merging the 3D anisotropic depth model in depth sections.
- the updated earth model may then be used to perform a prestack depth migration (step 640 ).
- a determination may then be made as to whether the quality of the output of the prestack depth migration falls below a predetermined value (step 650 ).
- the “flatness” of the prestack depth gathers may be evaluated, i.e., a determination may be made as to whether the prestack depth gathers are substantially flat.
- the prestack depth stack may be compared against the petrotechnical data obtained during drilling (at step 150 ). The “focus” of the prestack depth stack may be interpreted prior to comparison.
- the errors of the residual moveout cube may be evaluated. If the quality of the output falls below the predetermined value, then the earth model may be further updated by performing a tomographic anisotropic properties update (step 660 ).
- a set of actions for modifying the well trajectory for drilling the planned well may be performed based on the updated earth model and information gained from the audit and feasibility study.
- steps 150 through 180 may continue as long as drilling is in progress.
- FIG. 3 illustrates an example of the process 300 for performing the set of actions to modify the drilling plan in more detail.
- a comparison may be made between the subsurface image and property volume based on the updated earth model and the subsurface image and property volume based on the earth model prior to the update, e.g., the highgraded earth model.
- Variation between the subsurface image and property volume based on the updated earth model and the subsurface image and property volume based on the earth model prior to the update may be highlighted, characterized and interpreted in the context of the existing and future well location. The interpretation may be enhanced to include production related considerations, such as maximum reservoir contact, ultimate recovery, reservoir pressure, permeability and the like.
- a set of 3D coordinates (X,Y,Z) for a revised well trajectory may be generated based on the subsurface image and property volume of the updated earth model, the subsurface image and property volume of the earth model prior to the update and geosteering.
- the set of 3D coordinates (X,Y,Z) for the revised well trajectory may represent an optimal well trajectory for optimized production and recovery.
- a set of actions for reaching the new well based on the revised well trajectory may be performed.
- the set of actions may include providing a design of the revised well trajectory.
- the design may take into account various issues, such as effects on changing the drilling procedures, parameters and materials, a cost benefit and drilling risk analysis.
- economic and technical analysis may be performed to determine if the new well trajectory is adopted. Such economic analysis may include calculations of net present value, cost of drilling change, estimated ultimate recovery, safety and environmental implications.
- the set of actions for reaching the new well may include changing the casing plan, mud weights and the like.
- the set of actions for reaching the new well may include defining a new drilling plan and well construction, changing drilling, casing, coring, completion operations and production plans.
- the set of actions for reaching the new well may include recommendations for reducing drilling risk, e.g., by confirming, changing or modifying the drilling fluid, and/or deriving elastic properties from the updated earth model.
- FIG. 4 illustrates an example of a well trajectory that has been modified in accordance with various implementations described herein.
- the initial well trajectory 410 is shown to traverse through hazard 420 .
- a new well trajectory 430 is provided based on 3D coordinates 440 , 450 and 460 .
- the set of actions for reaching the new well may include full aperture, prestack, three dimensional depth imaging in real time (which may be referred to as SGD imaging) using the petrotechnical data acquired during drilling to improve the accuracy of the earth model with which the seismic data are depth imaged.
- SGD imaging may produce more structurally accurate images and common image gathers, which may be imaged hundreds to thousands of feet ahead of and around the drill bit, thereby providing a look ahead and around the drill bit.
- the resulting images, the common image gathers and the resulting earth model, the petrotechnical data acquired while drilling, petrotechnical data gathered prior to drilling, and/or inversions of any combination of the above mentioned petrotechnical data may be used to confirm or modify the drilling plan during the drilling operation.
- Common image gathers output from the SGD imaging in various domains, such as offset or angle, may be used to alter the earth model.
- the altered earth model may be used for additional iterations of SGD imaging or for possible inversions for fluid, porosity or pore pressure.
- Moveout estimates derived from the common image gathers provide input to tomography inversions to solve for depth velocity variations, and/or provide a measure of the quality of the image and/or input to anisotropy estimations.
- Depth velocity constitutes one of the properties of the earth model. Alterations to the depth velocity property and anisotropy parameters may be performed based on the petrotechnical data, such as check shot, mud log, sonic, seismicVision and VSP data acquired while drilling and/or gathered from prior drilling operations.
- various techniques described herein for optimizing drilling operations may include full aperture, three dimensional, prestack tomography inversion in real time to solve for depth velocity variations, which may include anisotropy parameters at, around and ahead of the drill bit during drilling operations.
- the tomography inversion and/or earth model may be constrained or altered by combining petrotechnical data acquired while drilling and/or gathered from prior drilling operations prior to and/or during the current drilling operation.
- Various techniques described herein may also make use of a-priori anisotropy estimates derived from any petrotechnical data source, such as prior drilling operations, walk-away vertical seismic profile (VSP) data and/or lithology knowledge.
- VSP walk-away vertical seismic profile
- A-priori anisotropy estimates may be used to constrain or alter tomography inversions for depth velocity properties and/or directly alter the current version of the earth model.
- Various techniques described herein may also make use of interpretations of events exhibited in the seismic image.
- the interpretation of exhibited seismic image events alone and/or in combination with petrotechnical data acquired while drilling and/or petrotechnical data gathered from prior drilling operations may constrain and/or validate the current earth model and/or results from tomography inversions to produce a new earth model.
- the common image gather flatness output from an iteration of SGD imaging may be used to confirm the quality of the image for structural positioning and the quality of the earth model used for SGD imaging.
- One measure of the quality of the image and the earth model is the degree to which they tie the depths measured in the current drilling operation and/or any other prior drilling operations (i.e., which may be referred to as offset wells) from which we may have gathered petrotechnical data.
- the convergence of results between petrotechnical data acquired during drilling, and/or gathered prior to drilling and/or produced with various techniques described herein, prior to and/or during drilling operations, may be another validation to increase the confidence of advice given regarding changes to the drilling plan.
- the validated earth model and gathers may be used directly for pore pressure inversion.
- the resulting pore pressure volume constitutes another property of the earth model.
- the pore pressure property of the earth model may be used to provide the pressure curves along any selected drilling trajectory to better understand the mud weights required during drilling operations. This feature may be of particular benefit to drilling operations that are at risk of encountering unexpected pressures that deviate from the drilling plan, e.g., when accurate position of the base of salt is unknown prior to drilling operations.
- the updated images, common image gathers, earth models including any property extracted from the earth model and/or interpretations generated with various techniques described herein may enable a better prediction of the location of base of salt in advance of the drilling operation reaching the base of salt.
- FIG. 5 illustrates a computing system 500 , into which implementations of various technologies described herein may be implemented.
- the computing system 500 may include one or more system computers 530 , which may be implemented as any conventional personal computer or server.
- the system computers 530 may include an engineering workstation, which may be configured to support interactive tasks, such as job set-up, job monitoring and quality control, parameter selection, data visualization and the like.
- the system computers 530 may include a batch computer system, which may be configured to run batch data conditioning jobs, run batch imaging jobs and the like.
- the system computers 530 may include a utility server, which may be configured to perform database services, resource control management, job submission, directory services, systems installation and maintenance, security services and the like.
- HTTP hypertext transfer protocol
- the system computer 530 may be in communication with disk storage devices 529 , 531 , and 533 , which may be external hard disk storage devices. It is contemplated that disk storage devices 529 , 531 , and 533 are conventional hard disk drives, and as such, will be implemented by way of a local area network or by remote access. Of course, while disk storage devices 529 , 531 , and 533 are illustrated as separate devices, a single disk storage device may be used to store any and all of the program instructions, measurement data, and results as desired.
- various measurements may be stored in disk storage device 531 .
- the system computer 530 may retrieve the appropriate data from the disk storage device 531 to process the various measurements according to program instructions that correspond to implementations of various technologies described herein.
- the program instructions may be written in a computer programming language, such as C++, Java and the like.
- the program instructions may be stored in a computer-readable medium, such as program disk storage device 533 .
- Such computer-readable media may include computer storage media and communication media.
- Computer storage media may include volatile and non-volatile, and removable and non-removable media implemented in any method or technology for storage of information, such as computer-readable instructions, data structures, program modules or other data.
- Computer storage media may further include RAM, ROM, erasable programmable read-only memory (EPROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other solid state memory technology, CD-ROM, digital versatile disks (DVD), or other optical storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other medium which can be used to store the desired information and which can be accessed by the system computer 530 .
- Communication media may embody computer readable instructions, data structures, program modules or other data in a modulated data signal, such as a carrier wave or other transport mechanism and may include any information delivery media.
- modulated data signal may mean a signal that has one or more of its characteristics set or changed in such a manner as to encode information in the signal.
- communication media may include wired media such as a wired network or direct-wired connection, and wireless media such as acoustic, RF, infrared and other wireless media. Combinations of any of the above may also be included within the scope of computer readable media.
- system computer 530 may present output primarily onto graphics display 527 , or alternatively via printer 528 .
- the system computer 530 may store the results of the methods described above on disk storage 529 , for later use and further analysis.
- the keyboard 526 and the pointing device (e.g., a mouse, trackball, or the like) 525 may be provided with the system computer 530 to enable interactive operation.
- the system computer 530 may be located at a data center remote from the drilling operation.
- the system computer 530 may be in communication with the various measuring tools to receive various signals indicative of the planned well. These signals, after conventional formatting and other initial processing, may be stored by the system computer 530 as digital data in the disk storage 531 for subsequent retrieval and processing in the manner described above. While FIG. 5 illustrates the disk storage 531 as directly connected to the system computer 530 , it is also contemplated that the disk storage device 531 may be accessible through a local area network or by remote access.
- disk storage devices 529 , 531 are illustrated as separate devices for storing petrotechnical data and analysis results, the disk storage devices 529 , 531 may be implemented within a single disk drive (either together with or separately from program disk storage device 533 ), or in any other conventional manner as will be fully understood by one of skill in the art having reference to this specification.
- the computing system 500 may further be in communication with data storage 560 , which is configured to store petrotechnical measurements.
- Data storage 560 may be located on a rig on site or away from the system computer 530 .
- data storage 560 may be on a drilling platform or a land rig.
- Communication between the system computer 530 and the data storage 560 may be facilitated by a communication network 550 .
- the communication network 550 may include a wide area network (WAN), a satellite link, local area network (LAN), or other suitable network or combinations thereof.
- the data storage 560 is shown to be connected to the system computer 530 via the communication network 550 , it should be understood that each component may be connected to another component in any way convenient.
- the display 527 may be connected to disk storage device 529 through the system computer 530 .
- the program storage 533 may be directly connected to the system computer 530 .
- the system computer 530 may have many computing nodes that are distributed in various locations.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Geology (AREA)
- Mining & Mineral Resources (AREA)
- Physics & Mathematics (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Geochemistry & Mineralogy (AREA)
- Fluid Mechanics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Geophysics (AREA)
- Operations Research (AREA)
- Data Mining & Analysis (AREA)
- Databases & Information Systems (AREA)
- Mathematical Physics (AREA)
- Software Systems (AREA)
- Acoustics & Sound (AREA)
- Remote Sensing (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- Geometry (AREA)
- Geophysics And Detection Of Objects (AREA)
- Earth Drilling (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
A method for optimizing drilling operations. The method includes providing an earth model of a volume having a well, obtaining petrotechnical data about the volume while drilling the well, comparing the petrotechnical data with the earth model, updating the earth model with the petrotechnical data based on the comparison, and modifying a drilling plan of the well using the updated earth model.
Description
- 1. Field of the Invention
- Implementations of various technologies described herein generally relate to drilling operations.
- 2. Description of the Related Art
- The following descriptions and examples do not constitute an admission as prior art by virtue of their inclusion within this section.
- There is a growing demand for better and more reliable three dimensional (3D) and four dimensional (4D) reservoir images and property analysis. This may be largely due to increasing complexity, operational cost and risk associated with oil and natural gas reservoirs exploration and production. As with medical applications, images with reduced uncertainties and higher quality may be created during drilling.
- Various techniques described herein are directed to a method for optimizing drilling operations. The method includes providing an earth model of a volume having a well, obtaining petrotechnical data about the volume while drilling the well, comparing the petrotechnical data with the earth model, updating the earth model with the petrotechnical data based on the comparison, and modifying a drilling plan of the well using the updated earth model.
- In one implementation, the earth model may be updated by performing a migration imaging process on the volume. In another implementation, the earth model may be updated by creating a three dimensional (3D) anisotropic depth model with the petrotechnical data, merging the 3D anisotropic depth model in depth sections, performing a prestack depth migration, performing tomographic anisotropic properties update, performing interpretation, performing inversion for pore pressure or lithology properties of the earth model, or combinations thereof.
- In yet another implementation, the drilling plan may be modified by comparing a subsurface image, property volume or interpretation, or combinations thereof, derived from the earth model with a subsurface image, property volume or interpretation, or combinations thereof, derived from the updated earth model; and generating a set of three dimensional (3D) or two dimensional (2D) coordinates for a well trajectory based on the comparison.
- In still another implementation, the drilling plan may be modified by providing a design of a well trajectory, performing an economic and technical analysis of the well trajectory, changing an existing casing plan, defining a well construction based on the well trajectory, defining a well construction based on interpretations or properties derived from the updated earth model, or combinations thereof.
- In one implementation, providing the earth model may include: conducting an audit and feasibility study on the volume; and selecting the earth model based on the audit and feasibility study. Conducting the audit and feasibility study on the volume may include assessing the quality and relevance of available petrotechnical information regarding the volume. The available petrotechnical information regarding the volume may include reports or documentations pertaining to the subsurface structure and properties at or around the volume. Selecting the earth model based on the audit and feasibility study may include selecting the earth model that is most congruent with the available petrotechnical information regarding the volume. Conducting the audit and feasibility study on the volume may include performing forward modeling on earth models and seismic images of the volume. The forward modeling may include ray tracing, wavefield modeling or finite difference techniques or combinations thereof.
- In yet another implementation, the method may further include highgrading the earth model prior to drilling the well. Highgrading the earth model may include enhancing the resolution of the earth model. Enhancing the resolution of the selected earth model may include increasing the vertical and spatial sampling rate. Alternatively, highgrading the earth model may include enhancing the calibration of the earth model and enhancing the calibration of the earth model may include calibrating the earth model to depth.
- In still another implementation, the petrotechnical data may include wellbore measurements, gravity acquisition data, borehole seismic data, electromagnetic survey data, surface seismic data or combinations thereof.
- In yet still another implementation, the earth model is updated only if the variance between the petrotechnical data and the earth model exceeds a predetermined value.
- In one implementation, the method for optimizing drilling operations of a well may include highgrading an earth model of a volume having the well, obtaining petrotechnical data about the volume while drilling the well, comparing the petrotechnical data with the highgraded earth model, updating the highgraded earth model with the petrotechnical data based on the comparison, and modifying a drilling plan of the well using the updated highgraded earth model.
- Various techniques described herein are also directed to a method for conducting an audit and feasibility study for drilling operations. The method may include evaluating the quality and relevance of available petrotechnical information regarding a volume having a well to be drilled, performing a forward modeling on earth models and seismic images of the volume and generating a scenario plan for the well.
- Various techniques described herein are also directed to a method for providing a set of actions for modifying a drilling plan of a well. The method may include comparing a subsurface image, property volume or interpretation of an earth model of the well with a subsurface image, property volume or interpretation of an updated earth model; generating a set of three dimensional (3D) coordinates for a well trajectory based on the comparison; and modifying the drilling plan based on the well trajectory.
- Various techniques described herein are also directed to a method for updating an earth model of a volume having a well. The method may include creating a three dimensional anisotropic depth model; comparing the three dimensional anisotropic depth model with petrotechnical data obtained while drilling the well; determining whether the three dimensional anisotropic depth model deviates from the petrotechnical data by greater than a predetermined amount; and if the deviation exceeds the predetermined amount, then updating the three dimensional anisotropic depth model.
- The above referenced summary section is provided to introduce a selection of concepts in a simplified form that are further described below in the detailed description section. The summary is not intended to identify key features or essential features of the claimed subject matter, nor is it intended to be used to limit the scope of the claimed subject matter. Furthermore, the claimed subject matter is not limited to implementations that solve any or all disadvantages noted in any part of this disclosure.
- Implementations of various technologies will hereafter be described with reference to the accompanying drawings. It should be understood, however, that the accompanying drawings illustrate only the various implementations described herein and are not meant to limit the scope of various technologies described herein.
-
FIG. 1 illustrates a flow diagram of a method for optimizing drilling operations in accordance with implementations of various techniques described herein. -
FIG. 2 illustrates a flow diagram of a method for conducting the audit and feasibility study in accordance with various implementations described herein. -
FIG. 3 illustrates a process for generating the set of actions for modifying the drilling plan in accordance with implementations described herein. -
FIG. 4 illustrates an example of a well trajectory that has been modified in accordance with various implementations described herein. -
FIG. 5 illustrates a computing system, into which implementations of various techniques described herein may be implemented. -
FIG. 6 illustrates a flow diagram of a method for performing a migration imaging process in accordance with implementations of various techniques described herein. - The discussion below is directed to certain specific implementations. It is to be understood that the discussion below is only for the purpose of enabling a person with ordinary skill in the art to make and use any subject matter defined now or later by the patent “claims” found in any issued patent herein.
-
FIG. 1 illustrates a flow diagram of amethod 100 for optimizing drilling operations in accordance with implementations of various techniques described herein. Atstep 110, an audit of available information regarding an earth volume having the planned well to be drilled and feasibility study of drilling the planned well may be conducted. Although implementations of various techniques are described with reference to a well, it should be understood that some implementations may be applied to a system of well bores, sidetracks, multi-laterals and the like. During this step, the quality and relevance of the available information may be assessed. The result of the audit and feasibility study may be used to minimize uncertainties and mitigate risks associated with drilling the planned well. - Available information regarding the planned well may include reports or documentations pertaining to the subsurface structure and properties at or around the planned well. They may also include reports or documentations pertaining to offset wells. Such reports may include well logs, drilling reports, incident analysis, completion practices of offset wells, production history of offset wells and existing surface seismic data.
-
FIG. 2 illustrates a flow diagram of amethod 200 for conducting the audit and feasibility study in accordance with various implementations described herein. In one implementation, the quality of existing seismic images, earth models, such as, geologic models, reservoir models and depth velocity models of the planned well and of offset wells and other petrotechnical data may be evaluated (step 210). As used herein, petrotechnical data may refer to any reports or documentations obtained, wellbore measurements (e.g., sidetrack, multi-lateral or any well within the earth volume containing the planned well), gravity acquisition data, borehole acquired data (e.g., walkaway or 3D VSP), electromagnetic survey data or the assembled or updated earth model, images derived from the assembled or updated earth model in stacked or pre-stack domain, inversions or properties derived from the assembled or updated earth model, interpretations derived from the assembled or updated earth model, or any combinations thereof. Earth models may contain data that characterize the properties of geological features that form the earth's sub-surface, such as rock formations and faults. The data in an earth model may consist of measurements gathered during activities, such as the seismic, logging or drilling operations of the oil and gas industry, and of interpretations made from these measurements. The data may be gathered above, on, or below the earth's surface. - In one implementation, the earth models to be evaluated are subsurface velocity models in the depth domain. In another implementation, the seismic images to be evaluated are prestack depth images. In yet another implementation, the earth models to be evaluated may be earth model property volumes. When evaluating earth models at the planned well or surrounding areas, vertical and spatial resolution of the earth models, structural constraints from surface geology and borehole measurements, borehole geologic imaging and the nature of model updates and calibration of the earth models by well logs and other available information may be evaluated.
- At
step 220, forward modeling may be performed on existing earth models of the earth volume, e.g., at the planned well and/or surrounding areas and seismic images of the planned well and/or surrounding areas (step 220). The forward modeling may be performed using ray tracing techniques or other seismic simulation techniques. In one implementation, this step may be performed to facilitate understanding whether the acquisition geometry illuminates the volume in which the planned well is located. - At
step 230, a scenario plan for the drilling operation of the planned well may be created. The scenario plan may include evaluating and ranking risks associated with drilling the planned well and proposing appropriate contingency actions similar to an emergency response plan. In one implementation, the scenario plan may include recommendations for additional enhancements and/or interpretation of the subsurface earth model, such as prestack depth migration (PSDM) prior to drilling the well may be made. In another implementation, the scenario plan may include creating a fit-for-purpose catalog of migration algorithms for the construction of the well. The fit-for-purpose catalog of migration algorithms may include information on the quality and turn-around time (TAT) implication on the drilling operation. In yet another implementation, the scenario plan may include establishing a pre-defined plan of earth model perturbations, which may facilitate understanding and quantifying possible impacts on the planned well trajectory as a result of changing seismic image volumes. A catalog of image volumes as a function of velocity field variations may be created. Such a catalog may be used as a look up utility while drilling, since it may include possible impacts in subsurface structural changes as a result of unexpected seismic velocity variations. In still another implementation, the scenario plan may include revising the current well trajectory, preparing a drilling optimization contingency plan to reduce risk and minimize non productive time (NPT), workflows for inversion of reservoir properties for flowing wells, kicks, and the like. In still yet another implementation, the scenario plan may include integrating and visualizing well trajectory, predictive reservoir model, and resolved, calibrated depth imaged volumes to optimize well construction planning. In still another implementation, the scenario plan may include using the seismic amplitude information to invert for material properties that can be vital not only to optimize ongoing drilling operations but also to assess reservoir sections yet to be drilled with respect to predicted hydrocarbon production and recovery. - Referring back to
FIG. 1 , atstep 120, one earth model for the planned well and the surrounding areas based on the feasibility study may be selected. In one implementation, the earth model whose petrotechnical data are substantially similar or consistent is selected. In another implementation, the earth model whose gravity, borehole seismic, surface seismic and magnetotelluric data provide substantially the same depth, volume and shape of the planned well is selected as the most accurate earth model. - At
step 125, a determination may be made as to whether the selected earth model may be highgraded. This determination may be made based on the scenario plan created atstep 230. If the answer is in the affirmative, then processing continues to step 130. Otherwise, processing skipsstep 130 and continues to step 140. - At
step 130, the selected earth model may be highgraded. During this highgrading step, the resolution and/or calibration of the selected earth model may be enhanced. In one implementation, the resolution of the selected earth model may be enhanced, e.g., through multiple iterations of full 3D tomographic inversion. In another implementation, the resolution of the selected earth model may be enhanced by increasing the vertical and spatial sampling rate. The enhancement in resolution may improve the vertical, spatial and tomographic scale length resolution to levels required for various techniques to optimize drilling operations described herein. In another implementation, the selected earth model may be highgraded by calibrating the earth model to true depth, which may include obtaining wellbore measurements from nearby wells. In yet another implementation, the resolution and calibration of the selected earth model may be optimized in an iterative workflow using borehole-enhanced seismic processing techniques, measurements from offset wells and measurements from other sources, such as magnetotelluric, gravity and the like. In yet another implementation, the anisotropy components of the earth model may be calibrated. During this highgrading step, new earth models and images may be produced. - As a result of highgrading the selected earth model, a portion of the scenario plan may be modified. For instance, the integration and visualization of well trajectory, and predictive reservoir model may be modified using highgraded depth imaged volumes.
- At
step 140, drilling of the planned well may commence based on the scenario plan created atstep 110. Atstep 150, petrotechnical data regarding the earth volume may be obtained during drilling. - At
step 160, the petrotechnical data obtained atstep 150 may be compared with the highgraded earth model. In one implementation, the petrotechnical data may be compared with the results of the feasibility study conducted atstep 110. For example, the depth of the surface seismic data available fromstep 110 may be compared with the depth information obtained during drilling. The check-shot data may be compared with velocity data available fromstep 110. The lithology report may be compared with the lithology from the selected earth model. In another implementation, the petrotechnical data may be compared with the initial earth model selected atstep 120. The petrotechnical data may be processed prior to being compared. For instance, the petrotechnical data may be processed to remove noise from the data. In one implementation, the comparison may be made on real time. In another implementation, the comparison may be made within a time period sufficient to modify or confirm the drilling plan. - At
step 165, a determination may be made as to whether the deviation between the petrotechnical data obtained atstep 150 and the initial selected earth model, the highgraded earth model or the results of the feasibility study exceeds a predetermined value. If the deviation is less than the predetermined value, then processing ends and the planned well is drilled according to the existing drilling plan. On the other hand, if the deviation exceeds the predetermined value, then processing continues to step 170. - At 170, one or more set of actions may be performed based on the extent to which the petrotechnical data obtained at
step 150 deviate from the highgraded earth model, the initial earth model or the results of the feasibility study. The set of actions may include techniques of various levels of technical sophistication for depth imaging, which may range from vertical stretching, map migration, post-stack depth migration to pre-stack depth migration. The magnitude of the deviation may be used to determine the action to be performed. The set of actions may be part of the scenario plan developed atstep 230. - In one implementation, the selected earth model may be updated, i.e., by relaunching the migration imaging process, when the wellbore measurements vary from the results of the feasibility study by a predetermined value, e.g., when the depth varies by more than 5%. The migration imaging process may range from creating a 3D anisotropic depth model, merging the 3D anisotropic depth model in depth sections, performing a prestack depth migration to performing tomographic anisotropic properties update. In another implementation, the level of technical sophistication and cost associated with the migration imaging process may be provided. In addition or in lieu of wellbore measurements, the selected earth model may be updated using other types of measurements during drilling, e.g., gravity survey measurements, electromagnetic survey measurements and the like. In one implementation, the selected earth model may be updated at predetermined times in the drilling plan.
-
FIG. 6 illustrates a flow diagram of amethod 600 for performing a migration imaging process in accordance with implementations of various techniques described herein. The migration imaging process may be an iterative process. Atstep 610, the earth model may be updated by creating a 3D anisotropic depth model. Atstep 620, a comparison may then be made between the 3D anisotropic depth model and the petrotechnical data obtained atstep 150, and a determination may be made as to whether the deviation exceeds a predetermined value. If the answer is in the affirmative, then the earth model may be updated using the petrotechnical data obtained during drilling (step 630). In one implementation, this updating step may include merging the 3D anisotropic depth model in depth sections. The updated earth model may then be used to perform a prestack depth migration (step 640). A determination may then be made as to whether the quality of the output of the prestack depth migration falls below a predetermined value (step 650). In one implementation, the “flatness” of the prestack depth gathers may be evaluated, i.e., a determination may be made as to whether the prestack depth gathers are substantially flat. In another implementation, the prestack depth stack may be compared against the petrotechnical data obtained during drilling (at step 150). The “focus” of the prestack depth stack may be interpreted prior to comparison. In yet another implementation, the errors of the residual moveout cube may be evaluated. If the quality of the output falls below the predetermined value, then the earth model may be further updated by performing a tomographic anisotropic properties update (step 660). - Referring back to
FIG. 1 , atstep 180, a set of actions for modifying the well trajectory for drilling the planned well may be performed based on the updated earth model and information gained from the audit and feasibility study. In one implementation, steps 150 through 180 may continue as long as drilling is in progress. -
FIG. 3 illustrates an example of theprocess 300 for performing the set of actions to modify the drilling plan in more detail. Atstep 310, a comparison may be made between the subsurface image and property volume based on the updated earth model and the subsurface image and property volume based on the earth model prior to the update, e.g., the highgraded earth model. Variation between the subsurface image and property volume based on the updated earth model and the subsurface image and property volume based on the earth model prior to the update may be highlighted, characterized and interpreted in the context of the existing and future well location. The interpretation may be enhanced to include production related considerations, such as maximum reservoir contact, ultimate recovery, reservoir pressure, permeability and the like. - At
step 320, a set of 3D coordinates (X,Y,Z) for a revised well trajectory may be generated based on the subsurface image and property volume of the updated earth model, the subsurface image and property volume of the earth model prior to the update and geosteering. In one implementation, the set of 3D coordinates (X,Y,Z) for the revised well trajectory may represent an optimal well trajectory for optimized production and recovery. - At
step 330, a set of actions for reaching the new well based on the revised well trajectory may be performed. In one implementation, the set of actions may include providing a design of the revised well trajectory. The design may take into account various issues, such as effects on changing the drilling procedures, parameters and materials, a cost benefit and drilling risk analysis. Further, economic and technical analysis may be performed to determine if the new well trajectory is adopted. Such economic analysis may include calculations of net present value, cost of drilling change, estimated ultimate recovery, safety and environmental implications. - In one implementation, the set of actions for reaching the new well may include changing the casing plan, mud weights and the like. In another implementation, the set of actions for reaching the new well may include defining a new drilling plan and well construction, changing drilling, casing, coring, completion operations and production plans. In yet another implementation, the set of actions for reaching the new well may include recommendations for reducing drilling risk, e.g., by confirming, changing or modifying the drilling fluid, and/or deriving elastic properties from the updated earth model.
-
FIG. 4 illustrates an example of a well trajectory that has been modified in accordance with various implementations described herein. In particular, theinitial well trajectory 410 is shown to traverse throughhazard 420. Anew well trajectory 430 is provided based on 3D coordinates 440, 450 and 460. - In this manner, various techniques described herein allow the modification of well trajectory and/or improve operational parameters while the well is being drilled. Benefits to the operators may include increased operational efficiency and safety, reduced cost, risk mitigation and improved reservoir production performance and hydrocarbon recovery.
- In one implementation, the set of actions for reaching the new well may include full aperture, prestack, three dimensional depth imaging in real time (which may be referred to as SGD imaging) using the petrotechnical data acquired during drilling to improve the accuracy of the earth model with which the seismic data are depth imaged. The SGD imaging may produce more structurally accurate images and common image gathers, which may be imaged hundreds to thousands of feet ahead of and around the drill bit, thereby providing a look ahead and around the drill bit. The resulting images, the common image gathers and the resulting earth model, the petrotechnical data acquired while drilling, petrotechnical data gathered prior to drilling, and/or inversions of any combination of the above mentioned petrotechnical data may be used to confirm or modify the drilling plan during the drilling operation.
- Common image gathers output from the SGD imaging in various domains, such as offset or angle, may be used to alter the earth model. The altered earth model may be used for additional iterations of SGD imaging or for possible inversions for fluid, porosity or pore pressure. Moveout estimates derived from the common image gathers provide input to tomography inversions to solve for depth velocity variations, and/or provide a measure of the quality of the image and/or input to anisotropy estimations. Depth velocity constitutes one of the properties of the earth model. Alterations to the depth velocity property and anisotropy parameters may be performed based on the petrotechnical data, such as check shot, mud log, sonic, seismicVision and VSP data acquired while drilling and/or gathered from prior drilling operations.
- As mentioned above, various techniques described herein for optimizing drilling operations may include full aperture, three dimensional, prestack tomography inversion in real time to solve for depth velocity variations, which may include anisotropy parameters at, around and ahead of the drill bit during drilling operations. The tomography inversion and/or earth model may be constrained or altered by combining petrotechnical data acquired while drilling and/or gathered from prior drilling operations prior to and/or during the current drilling operation. Various techniques described herein may also make use of a-priori anisotropy estimates derived from any petrotechnical data source, such as prior drilling operations, walk-away vertical seismic profile (VSP) data and/or lithology knowledge. A-priori anisotropy estimates may be used to constrain or alter tomography inversions for depth velocity properties and/or directly alter the current version of the earth model.
- Various techniques described herein may also make use of interpretations of events exhibited in the seismic image. The interpretation of exhibited seismic image events alone and/or in combination with petrotechnical data acquired while drilling and/or petrotechnical data gathered from prior drilling operations may constrain and/or validate the current earth model and/or results from tomography inversions to produce a new earth model.
- The common image gather flatness output from an iteration of SGD imaging may be used to confirm the quality of the image for structural positioning and the quality of the earth model used for SGD imaging. One measure of the quality of the image and the earth model is the degree to which they tie the depths measured in the current drilling operation and/or any other prior drilling operations (i.e., which may be referred to as offset wells) from which we may have gathered petrotechnical data. The convergence of results between petrotechnical data acquired during drilling, and/or gathered prior to drilling and/or produced with various techniques described herein, prior to and/or during drilling operations, may be another validation to increase the confidence of advice given regarding changes to the drilling plan.
- The validated earth model and gathers may be used directly for pore pressure inversion. The resulting pore pressure volume constitutes another property of the earth model. The pore pressure property of the earth model may be used to provide the pressure curves along any selected drilling trajectory to better understand the mud weights required during drilling operations. This feature may be of particular benefit to drilling operations that are at risk of encountering unexpected pressures that deviate from the drilling plan, e.g., when accurate position of the base of salt is unknown prior to drilling operations. The updated images, common image gathers, earth models including any property extracted from the earth model and/or interpretations generated with various techniques described herein may enable a better prediction of the location of base of salt in advance of the drilling operation reaching the base of salt.
- Various products generated during drilling, data acquired during drilling, and data gathered prior to drilling may constitute a sub-set of petrotechnical data, which may be integrated to the advantage of the drilling operation.
- Various techniques described herein may include multiple iterations of:
-
- a) full aperture, prestack, three dimensional depth imaging in real time during the drilling operation, which may be referred to as SGD imaging;
- b) updates to the earth model using any available petrotechnical data;
- c) full aperture, three dimensional, prestack tomography inversion in real time to solve for the variations in the depth velocity property of the earth model, which may include anisotropy parameters at, around and ahead, of the drill bit during the drilling operation;
- d) interpretation of initial and resulting images and any other petrotechnical data, which may result in advising changes to the drilling plan, including the drilling trajectory;
- e) inversions of products generated during drilling operations to solve for properties, such as depth velocity and pore pressure;
- f) the use of petrotechnical data available in comparative modes to increase the confidence of any of the individual data;
- g) generating advice to confirm the parameters of the current drilling plan or to change the parameters of the current drilling plan based on evidence produced from petrotechnical data obtained during drilling alone or in combination with petrotechnical data gathered prior to drilling. the change in drilling plan may include changing the drilling trajectory, mud weights, bit gauge etc.
-
FIG. 5 illustrates acomputing system 500, into which implementations of various technologies described herein may be implemented. Thecomputing system 500 may include one ormore system computers 530, which may be implemented as any conventional personal computer or server. In one implementation, thesystem computers 530 may include an engineering workstation, which may be configured to support interactive tasks, such as job set-up, job monitoring and quality control, parameter selection, data visualization and the like. In another implementation, thesystem computers 530 may include a batch computer system, which may be configured to run batch data conditioning jobs, run batch imaging jobs and the like. In yet another implementation, thesystem computers 530 may include a utility server, which may be configured to perform database services, resource control management, job submission, directory services, systems installation and maintenance, security services and the like. However, those skilled in the art will appreciate that implementations of various technologies described herein may be practiced in other computer system configurations, including hypertext transfer protocol (HTTP) servers, hand-held devices, multiprocessor systems, microprocessor-based or programmable consumer electronics, network PCs, computer clusters, minicomputers, mainframe computers, and the like. - The
system computer 530 may be in communication withdisk storage devices disk storage devices disk storage devices - In one implementation, various measurements, e.g., petrotechnical data, may be stored in
disk storage device 531. Thesystem computer 530 may retrieve the appropriate data from thedisk storage device 531 to process the various measurements according to program instructions that correspond to implementations of various technologies described herein. The program instructions may be written in a computer programming language, such as C++, Java and the like. The program instructions may be stored in a computer-readable medium, such as programdisk storage device 533. Such computer-readable media may include computer storage media and communication media. Computer storage media may include volatile and non-volatile, and removable and non-removable media implemented in any method or technology for storage of information, such as computer-readable instructions, data structures, program modules or other data. Computer storage media may further include RAM, ROM, erasable programmable read-only memory (EPROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other solid state memory technology, CD-ROM, digital versatile disks (DVD), or other optical storage, magnetic cassettes, magnetic tape, magnetic disk storage or other magnetic storage devices, or any other medium which can be used to store the desired information and which can be accessed by thesystem computer 530. Communication media may embody computer readable instructions, data structures, program modules or other data in a modulated data signal, such as a carrier wave or other transport mechanism and may include any information delivery media. The term “modulated data signal” may mean a signal that has one or more of its characteristics set or changed in such a manner as to encode information in the signal. By way of example, and not limitation, communication media may include wired media such as a wired network or direct-wired connection, and wireless media such as acoustic, RF, infrared and other wireless media. Combinations of any of the above may also be included within the scope of computer readable media. - In one implementation, the
system computer 530 may present output primarily onto graphics display 527, or alternatively viaprinter 528. Thesystem computer 530 may store the results of the methods described above ondisk storage 529, for later use and further analysis. Thekeyboard 526 and the pointing device (e.g., a mouse, trackball, or the like) 525 may be provided with thesystem computer 530 to enable interactive operation. - The
system computer 530 may be located at a data center remote from the drilling operation. Thesystem computer 530 may be in communication with the various measuring tools to receive various signals indicative of the planned well. These signals, after conventional formatting and other initial processing, may be stored by thesystem computer 530 as digital data in thedisk storage 531 for subsequent retrieval and processing in the manner described above. WhileFIG. 5 illustrates thedisk storage 531 as directly connected to thesystem computer 530, it is also contemplated that thedisk storage device 531 may be accessible through a local area network or by remote access. Furthermore, whiledisk storage devices disk storage devices - The
computing system 500 may further be in communication withdata storage 560, which is configured to store petrotechnical measurements.Data storage 560 may be located on a rig on site or away from thesystem computer 530. For instance,data storage 560 may be on a drilling platform or a land rig. Communication between thesystem computer 530 and thedata storage 560 may be facilitated by acommunication network 550. Thecommunication network 550 may include a wide area network (WAN), a satellite link, local area network (LAN), or other suitable network or combinations thereof. - Although the
data storage 560 is shown to be connected to thesystem computer 530 via thecommunication network 550, it should be understood that each component may be connected to another component in any way convenient. For instance, thedisplay 527 may be connected todisk storage device 529 through thesystem computer 530. Likewise, theprogram storage 533 may be directly connected to thesystem computer 530. Further, thesystem computer 530 may have many computing nodes that are distributed in various locations. - While the foregoing is directed to implementations of various technologies described herein, other and further implementations may be devised without departing from the basic scope thereof, which may be determined by the claims that follow. Although the subject matter has been described in language specific to structural features and/or methodological acts, it is to be understood that the subject matter defined in the appended claims is not necessarily limited to the specific features or acts described above. Rather, the specific features and acts described above are disclosed as example forms of implementing the claims.
Claims (24)
1-35. (canceled)
36. A method for providing a set of actions for modifying a drilling plan of a well, comprising:
comparing a subsurface image, property volume or interpretation of an earth model of the well with a subsurface image, property volume or interpretation of an updated earth model;
generating a set of three dimensional (3D) coordinates for a well trajectory based on the comparison; and
modifying the drilling plan based on the well trajectory.
37. The method of claim 36 , wherein the set of three dimensional (3D) coordinates is generated using geosteering.
38. The method of claim 36 , wherein modifying the drilling plan comprises providing a design of the well trajectory, performing an economic and technical analysis of the well trajectory, changing an existing casing plan, defining a well construction based on the well trajectory, or combinations thereof.
39. The method of claim 36 , wherein the earth model is updated by creating a three dimensional (3D) anisotropic depth model, merging the 3D anisotropic depth model in depth sections, performing a prestack depth migration, performing tomographic anisotropic properties update, performing interpretation, performing inversion for pore pressure or lithology properties of the earth model, or combinations thereof.
40. A method for updating an earth model of a volume having a well, comprising:
creating a three dimensional anisotropic depth model;
comparing the three dimensional anisotropic depth model with petrotechnical data obtained while drilling the well;
determining whether a deviation between the three dimensional anisotropic depth model and the petrotechnical data is greater than a first predetermined amount; and
if the deviation exceeds the first predetermined amount, then updating the three dimensional anisotropic depth model.
41. The method of claim 40 , further comprising merging the three dimensional anisotropic depth model in depth sections.
42. The method of claim 40 , further comprising performing a prestack depth migration using the updated three dimensional anisotropic depth model.
43. The method of claim 42 , further comprising:
determining whether a quality of an output of the prestack depth migration falls below a second predetermined value; and
if the output of the prestack depth migration falls below the second predetermined value, then performing a tomographic anisotropic properties update.
44. The method of claim 43 , wherein determining whether the quality of the output of the prestack depth migration falls below the second predetermined value comprises evaluating a flatness of one or more prestack depth gathers.
45. The method of claim 43 , wherein determining whether the quality of the output of the prestack depth migration falls below the second predetermined value comprises comparing a prestack depth stack against the petrotechnical data obtained during drilling.
46. The method of claim 43 , wherein determining whether the quality of the output of the prestack depth migration falls below the second predetermined value comprises evaluating errors of a residual moveout cube.
47-51. (canceled)
52. A computer system, comprising:
a processor; and
a memory comprising program instructions executable by the processor to:
compare a subsurface image, property volume or interpretation of an earth model of a well with a subsurface image, property volume or interpretation of an updated earth model;
generate a set of three dimensional (3D) coordinates for a well trajectory based on the comparison; and
modify a drilling plan based on the well trajectory.
53. The computer system of claim 52 , wherein the set of three dimensional (3D) coordinates is generated using geosteering.
54. The computer system of claim 52 , wherein the memory comprising program instructions executable by the processor to modify the drilling plan comprises program instructions executable by the processor to provide a design of the well trajectory, performing an economic and technical analysis of the well trajectory, changing an existing casing plan, defining a well construction based on the well trajectory, or combinations thereof.
55. A computer system, comprising:
a processor; and
a memory comprising program instructions executable by the processor to:
create a three dimensional anisotropic depth model of a volume having a well;
compare the three dimensional anisotropic depth model with petrotechnical data obtained while drilling the well;
determine whether a deviation between the three dimensional anisotropic depth model and the petrotechnical data is greater than a first predetermined amount; and
if the deviation exceeds the first predetermined amount, then update the three dimensional anisotropic depth model.
56. The computer system of claim 55 , wherein the memory further comprises program instructions executable by the processor to:
determine whether a quality of an output of the prestack depth migration falls below a second predetermined value; and
if the output of the prestack depth migration falls below the second predetermined value, then performing a tomographic anisotropic properties update.
57. The method of claim 36 , further comprising creating the earth model based on a full aperture, prestack, three dimensional depth imaging function and petrotechnical data obtained while drilling the well before updating the earth model.
58. The method of claim 40 , wherein the three dimensional anisotropic depth model is created based on a full aperture, prestack, three dimensional depth imaging function and petrotechnical data obtained while drilling the well.
59. The method of claim 36 , wherein the earth model is updated by performing a full aperture, prestack tomography inversion to solve for variations in depth velocity properties of the earth model.
60. The method of claim 40 , wherein the three dimensional anisotropic depth model is updated by performing a full aperture, prestack tomography inversion.
61. The computer system of claim 52 , wherein the memory further comprises program instructions executable by the processor to update the earth model by performing a full aperture, prestack tomography inversion to solve for variations in depth velocity properties of the earth model.
62. The computer system of claim 55 , wherein the memory further comprises program instructions executable by the processor to:
update the three dimensional anisotropic depth model by performing a full aperture, prestack tomography inversion; and
perform a prestack depth migration using the updated three dimensional anisotropic depth model.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US14/517,578 US20150039281A1 (en) | 2007-12-14 | 2014-10-17 | Optimizing Drilling Operations Using Petrotechnical Data |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US11/957,274 US9638830B2 (en) | 2007-12-14 | 2007-12-14 | Optimizing drilling operations using petrotechnical data |
US14/517,578 US20150039281A1 (en) | 2007-12-14 | 2014-10-17 | Optimizing Drilling Operations Using Petrotechnical Data |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/957,274 Division US9638830B2 (en) | 2007-12-14 | 2007-12-14 | Optimizing drilling operations using petrotechnical data |
Publications (1)
Publication Number | Publication Date |
---|---|
US20150039281A1 true US20150039281A1 (en) | 2015-02-05 |
Family
ID=40510594
Family Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/957,274 Active 2032-01-07 US9638830B2 (en) | 2007-12-14 | 2007-12-14 | Optimizing drilling operations using petrotechnical data |
US14/517,578 Abandoned US20150039281A1 (en) | 2007-12-14 | 2014-10-17 | Optimizing Drilling Operations Using Petrotechnical Data |
Family Applications Before (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/957,274 Active 2032-01-07 US9638830B2 (en) | 2007-12-14 | 2007-12-14 | Optimizing drilling operations using petrotechnical data |
Country Status (4)
Country | Link |
---|---|
US (2) | US9638830B2 (en) |
AU (1) | AU2008338779A1 (en) |
GB (2) | GB2488460B (en) |
WO (1) | WO2009079160A1 (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106050215A (en) * | 2015-04-03 | 2016-10-26 | 普拉德研究及开发股份有限公司 | Direct control over target property |
CN106156934A (en) * | 2015-04-17 | 2016-11-23 | 普拉德研究及开发股份有限公司 | Distributed well engineering and planning |
WO2018136448A1 (en) * | 2017-01-17 | 2018-07-26 | Schlumberger Technology Corporation | Systematic evaluation of shale plays |
CN109154809A (en) * | 2016-03-16 | 2019-01-04 | 通快机床两合公司 | Production programming system and method |
US10458125B2 (en) | 2005-05-20 | 2019-10-29 | Valinge Innovation Ab | Mechanical locking system for floor panels |
US10482202B2 (en) | 2016-06-30 | 2019-11-19 | The Procter & Gamble Company | Method for modeling a manufacturing process for a product |
WO2020167349A1 (en) * | 2019-02-12 | 2020-08-20 | Helmerich & Payne Technologies, Llc | Systems and methods of iterative well planning for optimized results |
US11319780B2 (en) | 2015-04-03 | 2022-05-03 | Schlumberger Technology Corporation | Wellsite system services |
WO2022204718A1 (en) * | 2021-03-25 | 2022-09-29 | Schlumberger Technology Corporation | Well intervention performance system |
US11989790B2 (en) | 2019-10-28 | 2024-05-21 | Schlumberger Technology Corporation | Drilling activity recommendation system and method |
US12136054B2 (en) | 2019-06-19 | 2024-11-05 | Helmerich & Payne Technologies, Llc | Systems and methods of iterative well planning for optimized results |
Families Citing this family (61)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8672055B2 (en) * | 2006-12-07 | 2014-03-18 | Canrig Drilling Technology Ltd. | Automated directional drilling apparatus and methods |
US11725494B2 (en) | 2006-12-07 | 2023-08-15 | Nabors Drilling Technologies Usa, Inc. | Method and apparatus for automatically modifying a drilling path in response to a reversal of a predicted trend |
AU2008335691B2 (en) | 2007-12-13 | 2013-12-05 | Exxonmobil Upstream Research Company | Iterative reservior surveillance |
JP5662804B2 (en) * | 2007-12-18 | 2015-02-04 | シュルンベルジェ ホールディングス リミテッドSchlnmberger Holdings Limited | System and method for improving surface electromagnetic exploration |
ES2651923T3 (en) * | 2008-03-21 | 2018-01-30 | Exxonmobil Upstream Research Company | An efficient method for geophysical data inversion |
US8527248B2 (en) * | 2008-04-18 | 2013-09-03 | Westerngeco L.L.C. | System and method for performing an adaptive drilling operation |
US8793111B2 (en) * | 2009-01-20 | 2014-07-29 | Schlumberger Technology Corporation | Automated field development planning |
AU2009238481B2 (en) | 2008-04-22 | 2014-01-30 | Exxonmobil Upstream Research Company | Functional-based knowledge analysis in a 2D and 3D visual environment |
WO2010039317A1 (en) * | 2008-10-01 | 2010-04-08 | Exxonmobil Upstream Research Company | Robust well trajectory planning |
US20100185395A1 (en) * | 2009-01-22 | 2010-07-22 | Pirovolou Dimitiros K | Selecting optimal wellbore trajectory while drilling |
EP2531694B1 (en) | 2010-02-03 | 2018-06-06 | Exxonmobil Upstream Research Company | Method for using dynamic target region for well path/drill center optimization |
EP2534605B1 (en) | 2010-02-12 | 2020-06-17 | Exxonmobil Upstream Research Company | Method and system for partitioning parallel simulation models |
AU2010347724B2 (en) | 2010-03-12 | 2016-06-23 | Exxonmobil Upstream Research Company | Dynamic grouping of domain objects via smart groups |
US8576663B2 (en) * | 2010-04-30 | 2013-11-05 | Schlumberger Technology Corporation | Multicomponent seismic inversion of VSP data |
US8914269B2 (en) * | 2010-07-08 | 2014-12-16 | Westerngeco L.L.C. | Methods and devices for transformation of collected data for improved visualization capability |
US9593558B2 (en) | 2010-08-24 | 2017-03-14 | Exxonmobil Upstream Research Company | System and method for planning a well path |
AU2011356658B2 (en) | 2011-01-26 | 2017-04-06 | Exxonmobil Upstream Research Company | Method of reservoir compartment analysis using topological structure in 3D earth model |
CA2826854C (en) * | 2011-02-08 | 2016-02-02 | Schlumberger Canada Limited | Three-dimensional modeling of parameters for oilfield drilling |
CA2822890A1 (en) | 2011-02-21 | 2012-08-30 | Exxonmobil Upstream Research Company | Reservoir connectivity analysis in a 3d earth model |
CN102322256A (en) * | 2011-06-02 | 2012-01-18 | 中国石油天然气股份有限公司 | Horizontal well landing guiding method |
US8983779B2 (en) | 2011-06-10 | 2015-03-17 | International Business Machines Corporation | RTM seismic imaging using incremental resolution methods |
US9063248B2 (en) | 2011-06-10 | 2015-06-23 | International Business Machines Corporation | RTM seismic imaging using combined shot data |
US9291735B2 (en) * | 2011-06-10 | 2016-03-22 | Globalfoundries Inc. | Probablistic subsurface modeling for improved drill control and real-time correction |
US9291734B2 (en) | 2011-06-10 | 2016-03-22 | International Business Machines Corporation | Full waveform inversion using combined shot data and no scratch disk |
US9223594B2 (en) | 2011-07-01 | 2015-12-29 | Exxonmobil Upstream Research Company | Plug-in installer framework |
WO2013169429A1 (en) | 2012-05-08 | 2013-11-14 | Exxonmobile Upstream Research Company | Canvas control for 3d data volume processing |
CA2886327C (en) * | 2012-09-28 | 2018-07-10 | Landmark Graphics Corporation | Self-guided geosteering assembly and method for optimizing well placement and quality |
US9388682B2 (en) | 2013-01-25 | 2016-07-12 | Schlumberger Technology Corporation | Hazard avoidance analysis |
AU2014225270A1 (en) * | 2013-03-05 | 2015-09-24 | Technological Resources Pty Ltd | Estimating material properties |
US11480705B2 (en) * | 2013-04-01 | 2022-10-25 | Oliden Technology, Llc | Antenna, tool, and methods for directional electromagnetic well logging |
EP3008281A2 (en) | 2013-06-10 | 2016-04-20 | Exxonmobil Upstream Research Company | Interactively planning a well site |
US10871584B2 (en) * | 2013-06-17 | 2020-12-22 | Westerngeco L.L.C. | Seismic data processing |
US9864098B2 (en) | 2013-09-30 | 2018-01-09 | Exxonmobil Upstream Research Company | Method and system of interactive drill center and well planning evaluation and optimization |
US10062044B2 (en) * | 2014-04-12 | 2018-08-28 | Schlumberger Technology Corporation | Method and system for prioritizing and allocating well operating tasks |
CA2963411C (en) * | 2014-10-03 | 2020-04-28 | Weatherford Technology Holdings, Llc | Integrated drilling control system and associated method |
US10339234B2 (en) * | 2014-11-25 | 2019-07-02 | Cgg Services Sas | Method for elastic model perturbation estimation from reverse time migration |
DE112014007031T5 (en) | 2014-12-31 | 2017-07-20 | Halliburton Energy Services, Inc. | Improved geosteering inversion using an electromagnetic look-ahead look-around tool |
WO2016111678A1 (en) * | 2015-01-06 | 2016-07-14 | Halliburton Energy Services, Inc. | Formation characteristics determination apparatus, methods, and systems |
CN104747165B (en) * | 2015-01-27 | 2017-06-13 | 中国石油天然气股份有限公司 | Three-dimensional horizontal well body profile design method |
US10415362B1 (en) | 2015-06-08 | 2019-09-17 | DataInfoCom USA Inc. | Systems and methods for analyzing resource production |
US20170103144A1 (en) * | 2015-10-08 | 2017-04-13 | Schlumbeger Technology Corporation | Well trajectory adjustment |
US11151762B2 (en) * | 2015-11-03 | 2021-10-19 | Ubiterra Corporation | Systems and methods for shared visualization and display of drilling information |
US11227372B2 (en) * | 2015-12-31 | 2022-01-18 | Schlumberger Technology Corporation | Geological imaging and inversion using object storage |
US10114135B2 (en) * | 2015-12-31 | 2018-10-30 | General Electric Company | System and method for optimizing seismic data analysis |
US20190048703A1 (en) * | 2016-04-15 | 2019-02-14 | Landmark Graphics Corporation | Real-time optimization and visualization of parameters for drilling operations |
US10872183B2 (en) * | 2016-10-21 | 2020-12-22 | Baker Hughes, A Ge Company, Llc | Geomechanical risk and hazard assessment and mitigation |
CN108005642A (en) * | 2016-10-31 | 2018-05-08 | 中石化石油工程技术服务有限公司 | Improve the standard the method for well oil-gas Layer Drilling ratio |
CN106897425A (en) * | 2017-02-24 | 2017-06-27 | 中国科学院电子学研究所 | A kind of three-dimensional visualization method of terrestrial gravitation field data |
EP3682087B1 (en) | 2017-09-11 | 2023-11-29 | Services Pétroliers Schlumberger | Well planning system |
US10866962B2 (en) | 2017-09-28 | 2020-12-15 | DatalnfoCom USA, Inc. | Database management system for merging data into a database |
WO2020061195A2 (en) * | 2018-09-19 | 2020-03-26 | Schlumberger Technology Corporation | Plan deviations visualization and interpretation |
US20200190960A1 (en) | 2018-12-12 | 2020-06-18 | Baker Hughes, A Ge Company, Llc | Systems and methods to control drilling operations based on formation orientations |
CA3121861A1 (en) | 2019-02-05 | 2020-08-13 | Motive Drilling Technologies, Inc. | Downhole display |
CA3133783A1 (en) | 2019-03-18 | 2020-09-24 | Magnetic Variation Services, Llc | Steering a wellbore using stratigraphic misfit heat maps |
US11946360B2 (en) | 2019-05-07 | 2024-04-02 | Magnetic Variation Services, Llc | Determining the likelihood and uncertainty of the wellbore being at a particular stratigraphic vertical depth |
CN112578445B (en) * | 2019-09-27 | 2024-07-26 | 中国石油天然气集团有限公司 | Method and device for seismic point-by-point guided drilling |
CN110765660B (en) * | 2019-11-21 | 2022-12-06 | 西南石油大学 | Method for quickly determining movable reserves of low-permeability gas under different gas production speeds |
CN113738276B (en) * | 2020-05-27 | 2024-06-07 | 中国石油化工股份有限公司 | Control method and system for drilling horizontal well and drilling system for horizontal well |
US11514382B2 (en) | 2020-12-10 | 2022-11-29 | Landmark Graphics Corporation | Utilizing micro-services for optimization workflows of borehole operations |
CN112983389B (en) * | 2021-03-12 | 2023-04-25 | 中国石油天然气股份有限公司 | Double-two-dimensional combined three-dimensional horizontal well track design method |
US11982174B2 (en) * | 2021-12-09 | 2024-05-14 | Saudi Arabian Oil Company | Method for determining pore pressures of a reservoir |
Family Cites Families (25)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US599544A (en) * | 1898-02-22 | Oil-well pump | ||
CA1315191C (en) | 1988-10-31 | 1993-03-30 | Chandra Shekhar Rai | Method and system for geophysical exploration |
US5012453A (en) | 1990-04-27 | 1991-04-30 | Katz Lewis J | Inverse vertical seismic profiling while drilling |
US5513150A (en) | 1993-06-30 | 1996-04-30 | Atlantic Richfield Company | Method of determining 3-D acoustic velocities for seismic surveys |
IT1277377B1 (en) | 1995-07-28 | 1997-11-10 | Agip Spa | METHOD FOR CONTINUOUS UPDATING OF THE TWO-DIMENSIONAL AND THREE-DIMENSIONAL DEPTH SEISMIC IMAGE BY MEANS |
US5995446A (en) * | 1998-04-21 | 1999-11-30 | Schlumberger Technology Corporation | Method of conducting drilling operations using vertical seismic profiles |
AU3229900A (en) | 1999-02-12 | 2000-08-29 | Prange, Michael | Uncertainty constrained subsurface modeling |
US6430507B1 (en) | 1999-04-02 | 2002-08-06 | Conoco Inc. | Method for integrating gravity and magnetic inversion with geopressure prediction for oil, gas and mineral exploration and production |
GB2363653B (en) | 1999-04-02 | 2004-01-14 | Conoco Inc | A method for gravity and magnetic data inversion using vector and tensor data with seismic imaging and geopressure prediction for oil gas and mineral explorat |
US6424918B1 (en) | 1999-04-02 | 2002-07-23 | Conoco Inc. | Method for integrating gravity and magnetic inversion data with model based seismic data for oil, gas and mineral exploration and production |
US6675097B2 (en) | 1999-04-02 | 2004-01-06 | Conoco Inc. | Nonlinear constrained inversion method to determine base of salt interface from gravity and gravity tensor data |
GB2354852B (en) | 1999-10-01 | 2001-11-28 | Schlumberger Holdings | Method for updating an earth model using measurements gathered during borehole construction |
US6344746B1 (en) * | 1999-12-03 | 2002-02-05 | Baker Hughes Incorporated | Method for processing the lapse measurements |
US6826486B1 (en) | 2000-02-11 | 2004-11-30 | Schlumberger Technology Corporation | Methods and apparatus for predicting pore and fracture pressures of a subsurface formation |
US7003439B2 (en) | 2001-01-30 | 2006-02-21 | Schlumberger Technology Corporation | Interactive method for real-time displaying, querying and forecasting drilling event and hazard information |
GB2398900A (en) | 2003-02-27 | 2004-09-01 | Schlumberger Holdings | Identification of best production potential oil wells and identification of drilling strategy to maximise production potential |
US8995224B2 (en) | 2003-08-22 | 2015-03-31 | Schlumberger Technology Corporation | Real-time velocity and pore-pressure prediction ahead of drill bit |
WO2005071222A1 (en) | 2004-01-20 | 2005-08-04 | Saudi Arabian Oil Company | Real time earth model for collaborative geosteering |
US7054750B2 (en) | 2004-03-04 | 2006-05-30 | Halliburton Energy Services, Inc. | Method and system to model, measure, recalibrate, and optimize control of the drilling of a borehole |
US7730967B2 (en) | 2004-06-22 | 2010-06-08 | Baker Hughes Incorporated | Drilling wellbores with optimal physical drill string conditions |
US7191850B2 (en) | 2004-10-28 | 2007-03-20 | Williams Danny T | Formation dip geo-steering method |
US9388680B2 (en) | 2005-02-01 | 2016-07-12 | Smith International, Inc. | System for optimizing drilling in real time |
US8812334B2 (en) | 2006-02-27 | 2014-08-19 | Schlumberger Technology Corporation | Well planning system and method |
US8942064B2 (en) | 2009-06-10 | 2015-01-27 | Baker Hughes Incorporated | Sending a seismic trace to surface after a vertical seismic profiling while drilling measurement |
US8947974B2 (en) | 2009-06-23 | 2015-02-03 | Baker Hughes Incorporated | Seismic measurements while drilling |
-
2007
- 2007-12-14 US US11/957,274 patent/US9638830B2/en active Active
-
2008
- 2008-11-22 GB GB1207680.8A patent/GB2488460B/en active Active
- 2008-11-22 GB GB1011523.6A patent/GB2468812B/en active Active
- 2008-11-22 AU AU2008338779A patent/AU2008338779A1/en not_active Abandoned
- 2008-11-22 WO PCT/US2008/084441 patent/WO2009079160A1/en active Application Filing
-
2014
- 2014-10-17 US US14/517,578 patent/US20150039281A1/en not_active Abandoned
Non-Patent Citations (6)
Title |
---|
Colombo et al. "Geophysical modeling via simultaenous joint inversion of seismic, gravity, and electromagnectic data: Application to prestack depth imaging", March 2007, The Leading Edge, pages 326-331. * |
Druzhinin, A. "Decoupled elastic prestack depth migration" 2003, Journal of Applied Geophysics 54, pages 369-389. * |
Jones, Ian F. "A Review of 3D PreSDM Model Building Techniques", 2003, First Break, v21, No. 3, 12 pages. * |
Mottahedeh, R. "Horizontal Well Geo-Navigation: Plannig, Monitoring, and Geosteering", 2005, Paper 2005-017, 5 pages * |
Qian et al. "A full-aperature anisotropic eikonal solver for quasi-P traveltimes" SEG Technical Program Expanded Abstracts 2001: pp. 129-132. * |
Zhang et al. "Delayed-shot 3D Prestack Depth Migration", 2005, 4 pages * |
Cited By (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US10458125B2 (en) | 2005-05-20 | 2019-10-29 | Valinge Innovation Ab | Mechanical locking system for floor panels |
US11319780B2 (en) | 2015-04-03 | 2022-05-03 | Schlumberger Technology Corporation | Wellsite system services |
US12057005B2 (en) | 2015-04-03 | 2024-08-06 | Schlumberger Technology Corporation | Wellsite system services |
CN106050215A (en) * | 2015-04-03 | 2016-10-26 | 普拉德研究及开发股份有限公司 | Direct control over target property |
US11333006B2 (en) | 2015-04-03 | 2022-05-17 | Schlumberger Technology Corporation | Wellsite system services |
CN106156934A (en) * | 2015-04-17 | 2016-11-23 | 普拉德研究及开发股份有限公司 | Distributed well engineering and planning |
CN109154809A (en) * | 2016-03-16 | 2019-01-04 | 通快机床两合公司 | Production programming system and method |
US10482202B2 (en) | 2016-06-30 | 2019-11-19 | The Procter & Gamble Company | Method for modeling a manufacturing process for a product |
US11519262B2 (en) | 2017-01-17 | 2022-12-06 | Schlumberger Technology Corporation | Systematic evaluation of shale plays |
WO2018136448A1 (en) * | 2017-01-17 | 2018-07-26 | Schlumberger Technology Corporation | Systematic evaluation of shale plays |
US11313217B2 (en) | 2019-02-12 | 2022-04-26 | Helmerich & Payne Technologies, Llc | Systems and methods of iterative well planning for optimized results |
WO2020167349A1 (en) * | 2019-02-12 | 2020-08-20 | Helmerich & Payne Technologies, Llc | Systems and methods of iterative well planning for optimized results |
US12136054B2 (en) | 2019-06-19 | 2024-11-05 | Helmerich & Payne Technologies, Llc | Systems and methods of iterative well planning for optimized results |
US11989790B2 (en) | 2019-10-28 | 2024-05-21 | Schlumberger Technology Corporation | Drilling activity recommendation system and method |
WO2022204718A1 (en) * | 2021-03-25 | 2022-09-29 | Schlumberger Technology Corporation | Well intervention performance system |
Also Published As
Publication number | Publication date |
---|---|
GB2488460B (en) | 2013-02-27 |
US20090157367A1 (en) | 2009-06-18 |
GB201207680D0 (en) | 2012-06-13 |
GB2488460A (en) | 2012-08-29 |
GB201011523D0 (en) | 2010-08-25 |
AU2008338779A1 (en) | 2009-06-25 |
WO2009079160A1 (en) | 2009-06-25 |
GB2468812B (en) | 2012-11-07 |
GB2468812A (en) | 2010-09-22 |
US9638830B2 (en) | 2017-05-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9638830B2 (en) | Optimizing drilling operations using petrotechnical data | |
US12104484B2 (en) | Well log correlation and propagation system | |
RU2687668C1 (en) | Method and system for combined tracking of a well drilling process | |
US9157318B2 (en) | Determining differential stress based on formation curvature and mechanical units using borehole logs | |
US9593558B2 (en) | System and method for planning a well path | |
US8457940B2 (en) | Model-consistent structural restoration for geomechanical and petroleum systems modeling | |
CA2826854C (en) | Three-dimensional modeling of parameters for oilfield drilling | |
US9665604B2 (en) | Modeling and manipulation of seismic reference datum (SRD) in a collaborative petro-technical application environment | |
US20110282634A1 (en) | Method and apparatus for near well structural modeling based on borehole dips | |
US9696441B2 (en) | Apparatus and method for predicting vertical stress fields | |
US10450860B2 (en) | Integrating reservoir modeling with modeling a perturbation | |
US9243476B2 (en) | System and method for simulating oilfield operations | |
CN104011564A (en) | 4D saturation modeling | |
BRPI0901747A2 (en) | a method for characterizing fluids in a formation, wellhead tool, and computer readable medium comprising instructions executable by a processor to perform a method | |
US11774631B2 (en) | Geologic formation neutron porosity system | |
CN110062897B (en) | Petrophysical field assessment using self-organizing maps | |
Ramjohn et al. | 3D Geomechanical Modeling for Wellbore Stability Analysis: Starfish, ECMA, Trinidad and Tobago | |
Bryant et al. | Understanding uncertainty | |
US20240264324A1 (en) | Automatic tying structure maps of subsurface horizons to well-derived orientation information | |
Gupta et al. | Assessment of Borehole Gravity (Density) Monitoring for CO2 Injection into the Dover 33 Reef |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
STCV | Information on status: appeal procedure |
Free format text: APPEAL BRIEF (OR SUPPLEMENTAL BRIEF) ENTERED AND FORWARDED TO EXAMINER |
|
STCV | Information on status: appeal procedure |
Free format text: EXAMINER'S ANSWER TO APPEAL BRIEF MAILED |
|
STCV | Information on status: appeal procedure |
Free format text: ON APPEAL -- AWAITING DECISION BY THE BOARD OF APPEALS |
|
STCV | Information on status: appeal procedure |
Free format text: BOARD OF APPEALS DECISION RENDERED |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- AFTER EXAMINER'S ANSWER OR BOARD OF APPEALS DECISION |