US20130205688A1 - Prefabricated compound masonry units - Google Patents
Prefabricated compound masonry units Download PDFInfo
- Publication number
- US20130205688A1 US20130205688A1 US13/846,470 US201313846470A US2013205688A1 US 20130205688 A1 US20130205688 A1 US 20130205688A1 US 201313846470 A US201313846470 A US 201313846470A US 2013205688 A1 US2013205688 A1 US 2013205688A1
- Authority
- US
- United States
- Prior art keywords
- course
- reinforcement
- bed
- blocks
- channel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/02—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
- E04B2/42—Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities
- E04B2/44—Walls having cavities between, as well as in, the elements; Walls of elements each consisting of two or more parts, kept in distance by means of spacers, at least one of the parts having cavities using elements having specially-designed means for stabilising the position; Spacers for cavity walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/02—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
- E04B2/14—Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element
- E04B2/16—Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element using elements having specially-designed means for stabilising the position
- E04B2/20—Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element using elements having specially-designed means for stabilising the position by filling material with or without reinforcements in small channels in, or in grooves between, the elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
- E04B1/04—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/02—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
- E04B2/14—Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element
- E04B2/24—Walls having cavities in, but not between, the elements, i.e. each cavity being enclosed by at least four sides forming part of one single element the walls being characterised by fillings in some of the cavities forming load-bearing pillars or beams
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C2/00—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels
- E04C2/02—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials
- E04C2/04—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres
- E04C2/041—Building elements of relatively thin form for the construction of parts of buildings, e.g. sheet materials, slabs, or panels characterised by specified materials of concrete or other stone-like material; of asbestos cement; of cement and other mineral fibres composed of a number of smaller elements, e.g. bricks, also combined with a slab of hardenable material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Definitions
- the present invention relates in general to reinforced prefabricated compound masonry units and in particular to compound units reinforced with fiber reinforced polymer.
- Structures including residential, commercial and industrial buildings, are made from masonry using individual masonry blocks laid and bound together by mortar.
- the common materials of masonry construction are clay masonry such as brick and terra cotta; stone, such as marble, granite, travertine, and limestone; concrete block, including without limitation conventional concrete masonry units and autoclaved aerated concrete blocks; glass block; stucco; and tile.
- Masonry is generally a highly durable form of construction. However, the materials used, the quality of the mortar and workmanship, and the pattern in which the blocks are assembled can significantly affect the durability of the overall masonry construction.
- Concrete masonry is a commonly used building material composed of individual blocks whose basic composition is concrete.
- the blocks can be hollow or solid. Concrete is strong in compression and weak in tension. For concrete that is cast at the building site, adding embedded reinforcement during pouring can provide tensile capacity. Reinforcement is not used in individual concrete masonry blocks, but masonry blocks constructed of hollow units require reinforcement at the build site to comply with building codes, and therefore receive the reinforcement at the build site as pluralities of blocks are mortared into units.
- Masonry grout is similar to concrete and is poured into the hollow concrete masonry units at the build site to hold the code required reinforcement. Concrete, concrete masonry blocks, mortar, and masonry grout all contain Portland cement. Care needs to be taken to properly cure the grout and achieve the required strength. However, proper curing can be a challenge as typical build sites are outdoor areas subjected to environmental conditions that are different depending on the location and time of year.
- a prefabricated compound masonry unit comprises a first course comprising a plurality of hollow blocks laid end to end with adjacent ends adhered with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core; at least one channel formed in a top surface of the first course, the channel having a length; and provisional reinforcement provided along at least a portion of the length of the channel and held within the channel with a bonding material different from the mortar.
- the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in the hollow core at the build location.
- a prefabricated compound masonry unit comprises a first course comprising a plurality of U-shaped blocks each having a bed extending between two side walls, the plurality of U-shaped blocks laid end to end with adjacent ends adhered with mortar and positioned to form a continuous bed along a length of the first course; and provisional reinforcement provided along at least a portion of the continuous bed of the first course and held with a bonding material different from the mortar, wherein the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in a cavity defined by the continuous bed and side walls at a build location.
- One such method comprises: (a) forming a first course from a plurality of hollow blocks by joining ends of adjacent blocks with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core; (b) forming at least one channel in a top surface of the first course, the at least one channel having a length; (c) placing provisional reinforcement along at least a portion of the length of the at least one channel; and (d) retaining the provisional reinforcement within the at least one channel of the first course with a bonding material different from the mortar, wherein (a)-(d) are performed at a fabrication location and the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from the fabrication location to a build location, the hollow core of the first course configured to receive permanent structural masonry reinforcement at the build location.
- FIG. 1 is a perspective view of an embodiment of a prefabricated compound masonry unit
- FIG. 2 is a cross sectional view of FIG. 1 along line 2 - 2 ;
- FIG. 3 is a perspective view of another embodiment of a prefabricated compound masonry unit
- FIG. 4 is a cross sectional view of FIG. 3 along line 4 - 4 ;
- FIG. 5 is an enlarged perspective view of a portion of FIG. 1 ;
- FIG. 6 is an enlarged perspective view of an uncompleted prefabricated compound masonry unit having a corner
- FIG. 7 is a perspective view of an embodiment of a prefabricated compound masonry unit at a fabrication site with post-tensioning rods added at the fabrication site;
- FIG. 8A is a schematic view of a prefabricated compound masonry unit being hoisted with a lifting beam
- FIG. 8B is a side view of a prefabricated compound masonry unit loaded on a means of transportation to a build site;
- FIG. 9 is a side view of another embodiment of a compound masonry unit as disclosed herein;
- FIG. 10 is a cross sectional view of FIG. 9 along line 10 - 10 ;
- FIG. 11 is a plan view of FIG. 9 ;
- FIG. 12 is a side view of another embodiment of a compound masonry unit as disclosed herein;
- FIG. 13 is a cross sectional view of FIG. 11 along line 13 - 13 ;
- FIG. 14 is a cross sectional view of an alternative embodiment of FIG. 12 ;
- FIG. 15 is a cross sectional view of another embodiment of a compound masonry unit as disclosed herein with a reusable carrier.
- Fabrication site refers to a site that is typically enclosed and that is a location removed from the building site.
- the prefabricated compound masonry units are built at the fabrication site and transported from there to the build site.
- the fabrication site is a controlled factory setting using the fabrications methods disclosed herein to produce prefabricated compound masonry units that can be easily and safely transported and easily integrated into field building applications. This procedure would use craftsmen currently trained in the discipline of masonry and schooled in the new methods disclosed herein of incorporating provisional frp reinforcement for strategic advantages of strength during transportation and handling.
- Process monitoring of the build would produce design compliance, assuring the ability of the units to meet strict code conformance with product quality regardless of the weather and the natural environment.
- the prefabricated compound masonry units can be made to any overall shape and size desired or required by those skilled in the art so long as the units can be transported.
- Examples of applications for which the use of the prefabricated compound masonry units is contemplated include but are not limited to the following: columns, decorative walls, corners, floors, roofs, footings “neat” or insulated, headers for doors and windows, lintels, beams, posts, key walls, knee walls, ledges, retaining walls, wall sections, wall sections with returns, gable ends, arches, piers and walkways.
- the bonding material 30 used to retain the provisional reinforcement 20 can be, as non-limiting examples, a high strength mortar that is a polymer modified, shrinkage compensated, rapid setting high strength, hydraulic cement-based mortar or an epoxy or epoxy grout. Similar materials known to those skilled in the art are also contemplated.
- the bonding material 30 is to be distinguished from adhesive material such as mortar typically used to adhere blocks to one another in masonry or grout used in other applications. Ordinary mortar or grout would not suffice for holding the provisional reinforcement 20 to the course 12 during transportation, handling, etc. of the prefabricated unit. Additionally, it would not be feasible to simply substitute the bonding material 30 used to retain the provisional reinforcement for traditional or ordinary mortar between blocks, as the bonding material 30 would be prohibitively expensive and lack the viscosity to hold together the blocks of the units in the same way mortar does.
- the dowels or biscuits can be placed along joints of adjacent blocks 40 in the channels 25 if provided, in existing openings in the individual units or in apertures cut into the individual units specifically to receive the shaped frp.
- the type and shape of frp used can depend on the type of hollow block used.
- the provisional reinforcement 20 can be located in channels 25 that can be cut into or molded into the individual blocks 40 or courses 12 of such blocks 40 .
- the channels 25 are sized and configured to receive the provisional reinforcement 20 .
- Bonding material 30 is applied to the channels 25 and the provisional reinforcement 20 is laid within the bonding material 30 in the channels 25 .
- Each of the first side 18 and second side 19 of the top surface 14 can have a channel 25 formed therein, with the provisional reinforcement 20 retained within each channel 25 with the bonding material 30 . Any spillover of epoxy outside the channel 25 is removed to ensure contact of the mortar to the block if another course is added over the first course at the fabrication site or at the build site.
- the course 12 may be made of any number of blocks 40 .
- Lintels for example, are typically a single course 12 made up of a plurality of blocks 40 .
- a prefabricated lintel would typically be transported as a single course.
- the methods herein also include adding one or more courses at the fabrication site depending on the type of unit being made.
- FIGS. 3 and 4 illustrate a prefabricated compound masonry unit 110 having three courses 12 by means of example only. When the first course is complete with the provisional reinforcement 20 retained within the channels with bonding material 30 , another course can be laid with mortar on top of the first course.
- One or more additional courses 12 of blocks 40 can be laid and mortared as required to achieve the final dimensions of the prefabricated compound masonry unit 110 .
- the provisional reinforcement 20 can extend along at least a portion of both the first side 18 and the second side 19 of one or both of the bottom surface 16 and top surface 14 of one or more of the courses 12 that form a unit and be held with bonding material 30 .
- the provisional reinforcement 20 can extend along substantially an entire length L of the course 12 or can extend at intervals along the course 12 .
- the prefabricated compound masonry unit 110 can have a plurality of courses 12 having a lowermost course and an uppermost course with the first side 18 and the second side 19 of the top surface 14 of each of the lowermost course and the uppermost course having the channel 25 formed therein, with the provisional reinforcement 20 retained within each channel 25 with the bonding material 30 .
- the bonding material 30 can be installed in the channels 25 before laying the provisional reinforcement 20 in the channel 25 and/or after laying the provisional reinforcement 20 in the channel.
- the bonding material 30 is cured as required.
- the prefabricated compound masonry units 100 , 110 are made at the fabrication location in any number of courses to be transportable to a build site without having all of the horizontal and vertical reinforcement that is necessary to meet building code requirements.
- the provisional reinforcement provided in the units at the fabrication location provides tensile strength (i.e., flexural strength and strength to resist shear) to the units only to enable transportation and handling of the hollow courses to a build site.
- “Hollow” refers to the fact that not all of the reinforcement required for a code-compliant, completed building has yet been incorporated into the units. Being able to transport the units in a hollow state provides flexibility to construction workers, enabling them to incorporate any number of courses as needed into the structure, such as a single course, also referred to as a lintel.
- FIG. 8A illustrates the lifting of a prefabricated compound masonry unit 110 when the unit 110 has a large number of courses, such as when making a hollow wall.
- a lifting beam 72 is connected to the vertical bars 70 that have been fitted with rings 74 to which the lifting beam 72 is attached.
- a crane is used to lift the prefabricated compound masonry unit 110 to and from the truck 112 or other means of transportation, with the provisional reinforcement provided by the disclosed embodiments to prevent the unit 110 from cracking.
- Shoring or bracing (not shown) can be provided to the prefabricated compound masonry unit 110 after it is on the truck for further protection and stabilization during travel.
- Other means of lifting and moving the units can be used and can be dependent on the size and weight of the unit to be transported.
- FIG. 10 is a cross-sectional view of FIG. 9 along line 10 - 10 .
- the U-shaped block 202 forms a bed 208 running the length of the block 202 between the walls 205 of the block 202 . Therefore, the bed 208 can run the length of the course.
- a thin layer 206 of bonding material 30 can be spread in the bed 208 of the unit 200 .
- the thin layer 206 can be approximately 0.25 inch to 1 inch. This thickness is not meant to be limiting and is provided as example only. Other thicknesses can be used as desired or required. However, increased thickness will increase the weight of the compound unit.
- Provisional reinforcement 210 is laid on the thin layer 206 of bonding material 30 .
- the layer 212 can be of the same thickness or a different thickness than the thin layer 206 .
- the layers 206 , 212 can be the same bonding material 30 or can be different bonding materials, i.e., the thin layer 206 can be epoxy grout and layer 212 can be high strength mortar.
- the layers 206 , 212 of bonding material 30 and provisional reinforcement 210 can run the length of the compound masonry unit 200 . It is also contemplated that at least the provisional reinforcement 210 only be placed in the bed 208 across the joints of individual units 202 . Alternatively, the provisional reinforcement 210 can be laid in multiple sections in any suitable lengths and any suitable interval that provide the requisite strength to the compound masonry unit 200 .
- the provisional reinforcement 210 in the bed 208 can also be combined with the provisional reinforcement 20 shown in FIGS. 1-4 .
- the course can be put together with the provisional reinforcement 210 in the bridge joints 211 , with the provisional reinforcement 210 in the bed 208 being laid after the course is made.
- the provisional reinforcement 210 can be installed in strips at each joint or continuous through all joints.
- FIGS. 12 and 13 Another embodiment of the compound unit 200 ′ is shown in FIGS. 12 and 13 .
- the compound unit 200 ′ is shown with two courses 201 , 203 of blocks 202 , 40 .
- the compound unit 200 ′ is shown having two courses 201 , 203 , it is contemplated that the compound unit 200 ′ can be made of more than two courses.
- the bottom course 201 is made of a plurality of U-shaped blocks 202 while the second course 203 is made of a plurality of hollow blocks 40 .
- provisional reinforcement 210 is added to the compound unit 200 ′ to bridge the joints 211 between individual blocks 202 at the top of the bottom course 201 , as well as to bridge the joints 211 between individual blocks 40 at the top of the second course 203 .
- the provisional reinforcement 210 is set in slots with bonding material 30 .
- using provisional reinforcement 210 to span joints 211 refers to using frp of any length and shape that contacts a portion up to a whole of the length of two adjacent blocks.
- the layers 206 , 212 of bonding material 30 and provisional reinforcement 210 ′ can run the length of the unit 200 ′. It is also contemplated that at least the provisional reinforcement 210 ′ only be placed in the bed 208 across the joints of individual units 202 ′. Alternatively, the provisional reinforcement 210 ′ can be laid in multiple sections in any suitable lengths that provide the requisite strength to the compound unit.
- FIG. 14 is another embodiment of a prefabricated compound masonry unit 200 ′′. This embodiment is the same in many respects as the embodiment in FIG. 13 , and thus the overlapping description will not be repeated.
- the provisional reinforcement 210 in the bottom course 201 is inserted in a different position than that in FIG. 13 . Rather than bridging the joints 211 of the blocks 202 at the top of the course 201 , the provisional reinforcement 210 bridges the joints 211 between the blocks 202 in two places along the bed 208 of the compound unit 200 ′′. A length of provisional reinforcement 210 is set in slots in the blocks 202 and set in place with bonding material 30 .
- FIG. 14 is another embodiment of a prefabricated compound masonry unit 200 ′′. This embodiment is the same in many respects as the embodiment in FIG. 13 , and thus the overlapping description will not be repeated.
- the provisional reinforcement 210 in the bottom course 201 is inserted in a different position than that in FIG. 13 . Rather than bridging the joints 211
- FIG. 15 is a cross-sectional view of an alternative embodiment of the compound masonry unit 200 ′′ that incorporates the provisional reinforcement 210 in the joints 211 between individual blocks 40 to bridge the joints 211 along the top surface as shown in FIG. 14 , and incorporates into the same course the provisional reinforcement 210 bridging the joints 211 between the blocks 202 along the bed 208 , also shown in FIG. 14 .
- FIG. 15 Also illustrated in FIG. 15 is an embodiment of a reusable carrier 220 for the prefabricated compound masonry units disclosed herein.
- the reusable carrier 220 allows for an alternate method for transportation of prefabricated compound masonry units manufactured as disclosed herein to the build sites.
- the reusable carrier 220 comprises a support member 222 having two support legs 224 extending from the support member 222 to form an inverted “U” shape.
- the support member 222 and support legs 224 can be made of lumber.
- a prefabricated compound masonry unit 200 ′′ is set on the support member 222 of the reusable carrier 220 .
- the prefabricated compound masonry unit 200 ′′ would be banded to the carrier 220 in a plurality of positions along their lengths.
- the slings of a crane would then be placed around the combined unit and the unit moved to the transporter for transportation to the build site.
- the combined unit would be removed in the same way from the transporter.
- the reusable carrier 220 can be used for a portion of the shoring support as well as shipping.
- the reusable carrier 220 would be brought back to the fabrication site for reuse.
- a coating can be applied to the compound masonry units prior to transporting to the build site to provide corrosion protection and abrasion resistance and fills joints.
- the coating can be, as a non-limiting example, a polymer coating that uses formulations of poly urea with different physical property ranges.
- a coating can also be used to water proof the compound masonry units as desired or required.
- One skilled in the art will recognize the various coating that can be used to achieve the desired results.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Retaining Walls (AREA)
Abstract
Embodiments of prefabricated compound masonry units in lieu of build site-constructed elements are provided, as well as methods of producing the same. One embodiment comprises a first course comprising hollow blocks laid end to end with adjacent ends adhered with mortar, the hollow blocks positioned such that the first course has a hollow core; at least one channel formed in a top surface of the first course, the channel having a length; and provisional reinforcement provided along at least a portion of the length of the channel and held within the channel with a bonding material different from the mortar. The provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in the hollow core at the build location.
Description
- This application is a continuation-in-part of U.S. patent application Ser. No. 13/307,704 filed on Nov. 30, 2011, which is a continuation application of U.S. patent application Ser. No. 13/274,502 filed on Oct. 17, 2011, which claims priority to U.S. Provisional Patent Application Ser. No. 61/393,599 filed on Oct. 15, 2010 and U.S. Provisional Patent Application Ser. No. 61/439,863 filed on Feb. 5, 2011, all of which are incorporated herein in their entirety.
- The present invention relates in general to reinforced prefabricated compound masonry units and in particular to compound units reinforced with fiber reinforced polymer.
- Structures, including residential, commercial and industrial buildings, are made from masonry using individual masonry blocks laid and bound together by mortar. The common materials of masonry construction are clay masonry such as brick and terra cotta; stone, such as marble, granite, travertine, and limestone; concrete block, including without limitation conventional concrete masonry units and autoclaved aerated concrete blocks; glass block; stucco; and tile. Masonry is generally a highly durable form of construction. However, the materials used, the quality of the mortar and workmanship, and the pattern in which the blocks are assembled can significantly affect the durability of the overall masonry construction.
- Concrete masonry is a commonly used building material composed of individual blocks whose basic composition is concrete. The blocks can be hollow or solid. Concrete is strong in compression and weak in tension. For concrete that is cast at the building site, adding embedded reinforcement during pouring can provide tensile capacity. Reinforcement is not used in individual concrete masonry blocks, but masonry blocks constructed of hollow units require reinforcement at the build site to comply with building codes, and therefore receive the reinforcement at the build site as pluralities of blocks are mortared into units.
- Masonry grout is similar to concrete and is poured into the hollow concrete masonry units at the build site to hold the code required reinforcement. Concrete, concrete masonry blocks, mortar, and masonry grout all contain Portland cement. Care needs to be taken to properly cure the grout and achieve the required strength. However, proper curing can be a challenge as typical build sites are outdoor areas subjected to environmental conditions that are different depending on the location and time of year.
- Currently, individual masonry blocks are transported to the build site where they are laid and mortared into courses, with code required reinforcement installed as and after the courses are laid. To build a structure over about five feet in height, scaffolding is usually necessary to support the masons while they work. Weather can affect the progress of the masonry when laid on site as well.
- Disclosed herein are embodiments of prefabricated compound masonry units or elements in lieu of build site-constructed elements, and methods of producing the same. One embodiment of a prefabricated compound masonry unit comprises a first course comprising a plurality of hollow blocks laid end to end with adjacent ends adhered with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core; at least one channel formed in a top surface of the first course, the channel having a length; and provisional reinforcement provided along at least a portion of the length of the channel and held within the channel with a bonding material different from the mortar. The provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in the hollow core at the build location.
- Another embodiment of a prefabricated compound masonry unit comprises a first course comprising a plurality of U-shaped blocks each having a bed extending between two side walls, the plurality of U-shaped blocks laid end to end with adjacent ends adhered with mortar and positioned to form a continuous bed along a length of the first course; and provisional reinforcement provided along at least a portion of the continuous bed of the first course and held with a bonding material different from the mortar, wherein the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in a cavity defined by the continuous bed and side walls at a build location.
- Also disclosed herein are methods of making a prefabricated compound masonry unit prior to transporting the unit to a building site. One such method comprises: (a) forming a first course from a plurality of hollow blocks by joining ends of adjacent blocks with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core; (b) forming at least one channel in a top surface of the first course, the at least one channel having a length; (c) placing provisional reinforcement along at least a portion of the length of the at least one channel; and (d) retaining the provisional reinforcement within the at least one channel of the first course with a bonding material different from the mortar, wherein (a)-(d) are performed at a fabrication location and the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from the fabrication location to a build location, the hollow core of the first course configured to receive permanent structural masonry reinforcement at the build location.
- The description herein makes reference to the accompanying drawings wherein like reference numerals refer to like parts throughout the several views, and wherein:
-
FIG. 1 is a perspective view of an embodiment of a prefabricated compound masonry unit; -
FIG. 2 is a cross sectional view ofFIG. 1 along line 2-2; -
FIG. 3 is a perspective view of another embodiment of a prefabricated compound masonry unit; -
FIG. 4 is a cross sectional view ofFIG. 3 along line 4-4; -
FIG. 5 is an enlarged perspective view of a portion ofFIG. 1 ; -
FIG. 6 is an enlarged perspective view of an uncompleted prefabricated compound masonry unit having a corner; -
FIG. 7 is a perspective view of an embodiment of a prefabricated compound masonry unit at a fabrication site with post-tensioning rods added at the fabrication site; -
FIG. 8A is a schematic view of a prefabricated compound masonry unit being hoisted with a lifting beam; -
FIG. 8B is a side view of a prefabricated compound masonry unit loaded on a means of transportation to a build site; -
FIG. 9 is a side view of another embodiment of a compound masonry unit as disclosed herein; -
FIG. 10 is a cross sectional view ofFIG. 9 along line 10-10; -
FIG. 11 is a plan view ofFIG. 9 ; -
FIG. 12 is a side view of another embodiment of a compound masonry unit as disclosed herein; -
FIG. 13 is a cross sectional view ofFIG. 11 along line 13-13; -
FIG. 14 is a cross sectional view of an alternative embodiment ofFIG. 12 ; and -
FIG. 15 is a cross sectional view of another embodiment of a compound masonry unit as disclosed herein with a reusable carrier. - The concept of prefabricated compound masonry units reinforced with fiber reinforced polymer (hereinafter “frp”) includes individual concrete masonry blocks combined into elements (walls, beams, lintels or other masonry elements) at a fabrication site and reinforced with provisional reinforcement of frp at the fabrication site to provide structural support so that the prefabricated units can be transported to the build site and there incorporated into a building structure. The frp provides tensile strength to the units so that they can be transported, handled and installed at the build site. Once installed, the prefabricated units receive the code required reinforcement.
- The prefabricated compound masonry units are provided hollow and without complete reinforcement. They have a provisional reinforcement of frp to facilitate lifting, handling, transport, delivery, and erection. The frp is not intended to replace the grouted steel reinforcement that is necessary to install at the build site to meet code requirements.
- Prefabricated compound masonry units are disclosed herein that are built at a fabrication site and transported to a build site where the units are incorporated into the structure being built at the build site. As used herein, “unit” and “compound unit” refer to the use of two or more individual blocks combined to prefabricate elements at the fabrication site. A block can be clay masonry, such as brick and terra cotta; stone, such as marble, granite, travertine, and limestone; concrete block, including without limitation conventional concrete masonry units and autoclaved aerated concrete block; glass block; stucco; and tile. Compound masonry units can comprise a plurality of these blocks with one or more layers each of frp, epoxy or high strength mortar. As used herein “build site” is the location where a structure is being installed and where the prefabricated compound masonry units are assembled into the structure and further supported to meet building code requirements.
- As used herein “fabrication site” refers to a site that is typically enclosed and that is a location removed from the building site. The prefabricated compound masonry units are built at the fabrication site and transported from there to the build site. The fabrication site is a controlled factory setting using the fabrications methods disclosed herein to produce prefabricated compound masonry units that can be easily and safely transported and easily integrated into field building applications. This procedure would use craftsmen currently trained in the discipline of masonry and schooled in the new methods disclosed herein of incorporating provisional frp reinforcement for strategic advantages of strength during transportation and handling. Process monitoring of the build would produce design compliance, assuring the ability of the units to meet strict code conformance with product quality regardless of the weather and the natural environment.
- The prefabricated compound masonry units have many advantages over using individual blocks assembled at the build site or concrete poured at the build site. The prefabricated compound masonry units are adaptable for add-ons for last minute owner requirements. The prefabricated compound masonry units are built using the existing contingent of building trades. Use of the prefabricated compound masonry units can eliminate work stoppage due to weather conditions and lessen site damage of the individual blocks and other components. The use of prefabricated compound masonry units can also lessen occurrences of theft of product from unguarded build sites as the compound masonry units are too large to be easily transported without the proper assist and truck. The use of the prefabricated compound masonry units can provide “ease of building” on tight or busy sites and also provide safe, dust free construction solutions.
- The prefabricated compound masonry units limit moisture-related shrinkage issues as the mortar will cure properly at the fabrication site and can be produced with consistent quality. Prefabricated units are manufactured in a weather-protected, controlled-temperature environment of between 60° F. and 85° F., so cold-weather protection, hot weather protection, and wind protection for masonry are not required. Cement-based materials require a moist, controlled environment to gain strength and harden fully. The cement paste hardens over time, initially setting and becoming rigid and gaining in strength in the days and weeks following. Hydration and hardening during the first three days can be critical. Fast drying and shrinkage due to factors such as evaporation may lead to increased tensile stresses at a time when the material has not yet gained significant strength, resulting in greater shrinkage cracking. During the curing period, it is preferable to maintain conditions with a controlled temperature and humid atmosphere. Properly curing concrete leads to increased strength and lower permeability, and avoids cracking from the surface drying out prematurely. Care must also be taken to avoid freezing or overheating. Improper curing can cause scaling, reduced strength, poor abrasion resistance and cracking. The methods herein address these concerns.
- These advantages are provided as examples and are not meant to be limiting. Those skilled in the art will recognize these advantages and more associated with the prefabricated compound masonry units and their use.
- The prefabricated compound masonry units can be made to any overall shape and size desired or required by those skilled in the art so long as the units can be transported. Examples of applications for which the use of the prefabricated compound masonry units is contemplated include but are not limited to the following: columns, decorative walls, corners, floors, roofs, footings “neat” or insulated, headers for doors and windows, lintels, beams, posts, key walls, knee walls, ledges, retaining walls, wall sections, wall sections with returns, gable ends, arches, piers and walkways.
- The prefabricated compound masonry units can be built on a
build base 10 as seen inFIG. 1 . Thebuild base 10 is shown near but slightly raised off the ground; however, thebuild base 10 can be raised to any level for the comfort of the builder. However, thebuild base 10 does not need to be raised off the ground. Thebuild base 10 is leveled so that the resulting prefabricatedcompound masonry unit 100 built on thebase 10 is level. The building materials can be laid directly on thebuild base 10 or a base cover can be used to cover thebuild base 10 to prevent build up of building materials such as epoxy and mortar on thebuild base 10. - One embodiment of a prefabricated compound masonry unit is illustrated in
FIGS. 1 and 2 and comprises at least onecourse 12 comprising a plurality ofblocks 40 mortared together. Thecourse 12 has atop surface 14 and abottom surface 16 each having afirst side 18 and asecond side 19.Provisional reinforcement 20 is provided along at least a portion of a length L of thecourse 12 and held withbonding material 30. As used herein, “provisional reinforcement” refers to the frp that is included in the units to provide the requisite support for transportation, handling, delivery and placing the unit to and at the build site. The provisional reinforcement may continue to provide some structural reinforcement after it is incorporated at the build site; however, the provisional reinforcement does not meet current code requirements for permanent reinforcement. Therefore, horizontal and/or vertical reinforcement as required by code must be added at the build site. - The
bonding material 30 used to retain theprovisional reinforcement 20 can be, as non-limiting examples, a high strength mortar that is a polymer modified, shrinkage compensated, rapid setting high strength, hydraulic cement-based mortar or an epoxy or epoxy grout. Similar materials known to those skilled in the art are also contemplated. Thebonding material 30 is to be distinguished from adhesive material such as mortar typically used to adhere blocks to one another in masonry or grout used in other applications. Ordinary mortar or grout would not suffice for holding theprovisional reinforcement 20 to thecourse 12 during transportation, handling, etc. of the prefabricated unit. Additionally, it would not be feasible to simply substitute thebonding material 30 used to retain the provisional reinforcement for traditional or ordinary mortar between blocks, as thebonding material 30 would be prohibitively expensive and lack the viscosity to hold together the blocks of the units in the same way mortar does. -
Provisional reinforcement 20 is frp and includes, as non-limiting examples, carbon fibers or aramid fibers which are set in the bonding material. The provisional reinforcement can come in different forms. For example, the provisional reinforcement can come in plate form. The plate is a somewhat stiff yet still flexible sheet, i.e., it will spring back after it is flexed. The plate is cut into strips for use as the provisional reinforcement. As another example, the provisional reinforcement can come in the form of toes. The toes come laced together (by Kevlar or nylon) into arrays, so that the array is one toe wide and more than one toe deep. The arrays are cut to the number of toes needed for a particular application. The toes themselves are flexible and are approximately 1/8 inch in diameter. The arrays of toes come coiled in rolls.Provisional reinforcement 20 has limited stretch, thereby providing the reinforcement required when the prefabricatedcompound masonry unit 100 is lifted, transported, etc. The amount and configuration of the provisional reinforcement will change depending on one or more of the dimensions, weight, lifting configuration and application of the resulting prefabricatedcompound masonry unit 100. Other embodiments of theprovisional reinforcement 20 are contemplated. For example, theprovisional reinforcement 20 can be mesh or shaped frp. The shapes can include, as non-limiting examples, dowels, biscuits and other joinery known to those skilled in the art. The dowels or biscuits can be placed along joints ofadjacent blocks 40 in thechannels 25 if provided, in existing openings in the individual units or in apertures cut into the individual units specifically to receive the shaped frp. The type and shape of frp used can depend on the type of hollow block used. - As seen in
FIGS. 1 and 2 , theprovisional reinforcement 20 can be located inchannels 25 that can be cut into or molded into the individual blocks 40 orcourses 12 ofsuch blocks 40. Thechannels 25 are sized and configured to receive theprovisional reinforcement 20.Bonding material 30 is applied to thechannels 25 and theprovisional reinforcement 20 is laid within thebonding material 30 in thechannels 25. Each of thefirst side 18 andsecond side 19 of thetop surface 14 can have achannel 25 formed therein, with theprovisional reinforcement 20 retained within eachchannel 25 with thebonding material 30. Any spillover of epoxy outside thechannel 25 is removed to ensure contact of the mortar to the block if another course is added over the first course at the fabrication site or at the build site. - Depending on the type and size of unit required, the
course 12 may be made of any number ofblocks 40. Lintels, for example, are typically asingle course 12 made up of a plurality ofblocks 40. A prefabricated lintel would typically be transported as a single course. However, the methods herein also include adding one or more courses at the fabrication site depending on the type of unit being made.FIGS. 3 and 4 illustrate a prefabricatedcompound masonry unit 110 having threecourses 12 by means of example only. When the first course is complete with theprovisional reinforcement 20 retained within the channels withbonding material 30, another course can be laid with mortar on top of the first course. One or moreadditional courses 12 ofblocks 40 can be laid and mortared as required to achieve the final dimensions of the prefabricatedcompound masonry unit 110. When the number of layers is complete, additionalprovisional reinforcement 20 is incorporated into the top layer as shown in the figures. Alternatively, when all courses but one are laid and mortared,channels 25 can be provided in the surface of the next to last course within which thebonding material 30 andprovisional reinforcement 20 is placed. When the final course is placed on top, thebonding material 30 andprovisional reinforcement 20 will be hidden from view to provide an aesthetically finished product. - It is also contemplated that
provisional reinforcement 20 andbonding material 30 can be used between one or more layers as required to assure the prefabricatedcompound masonry unit 110 has the necessary strength.FIG. 5 is an enlarged view of thechannel 25,bonding material 30 andprovisional reinforcement 20.FIG. 6 is an enlarged photo of a corner of a prefabricatedcompound masonry unit 100 made from autoclaved aerated concrete (AAC) blocks. An example is provided ofchannels 25 formed for provisional reinforcement in a corner. The prefabricatedcompound masonry unit 100 can have acourse 12 with at least onecorner 50 and theprovisional reinforcement 20 can extend across thecorner 50 on one or both of thetop surface 14 and thebottom surface 16 of the at least one course. - As non-limiting examples, the
provisional reinforcement 20 can extend along at least a portion of both thefirst side 18 and thesecond side 19 of one or both of thebottom surface 16 andtop surface 14 of one or more of thecourses 12 that form a unit and be held withbonding material 30. Theprovisional reinforcement 20 can extend along substantially an entire length L of thecourse 12 or can extend at intervals along thecourse 12. The prefabricatedcompound masonry unit 110 can have a plurality ofcourses 12 having a lowermost course and an uppermost course with thefirst side 18 and thesecond side 19 of thetop surface 14 of each of the lowermost course and the uppermost course having thechannel 25 formed therein, with theprovisional reinforcement 20 retained within eachchannel 25 with thebonding material 30. - The
bonding material 30 can be installed in thechannels 25 before laying theprovisional reinforcement 20 in thechannel 25 and/or after laying theprovisional reinforcement 20 in the channel. Thebonding material 30 is cured as required. - The prefabricated
compound masonry units -
FIG. 7 illustrates the use of vertical post-tensioning rods or bars 70 that have been incorporated into the prefabricatedcompound masonry unit 110 at the fabrication site by means of example. As shown inFIG. 7 , the post-tensioning 70 can be inserted vertically into existing openings in theblocks 40 to span a plurality ofcourses 12 in the prefabricatedcompound masonry unit 110. At the build site, the post-tensioning rods may sometimes be used for permanent vertical reinforcement. If required, the post-tensioning can be grouted in place withgrout 60, which is similar to mortar. Post-tensioning rods or bars can also be incorporated at the fabrication site horizontally in units made with hollow U shaped blocks. -
FIG. 8A illustrates the lifting of a prefabricatedcompound masonry unit 110 when theunit 110 has a large number of courses, such as when making a hollow wall. To lift the hollow wall onto a truck, shown inFIG. 8B , alifting beam 72 is connected to thevertical bars 70 that have been fitted withrings 74 to which thelifting beam 72 is attached. A crane is used to lift the prefabricatedcompound masonry unit 110 to and from thetruck 112 or other means of transportation, with the provisional reinforcement provided by the disclosed embodiments to prevent theunit 110 from cracking. Shoring or bracing (not shown) can be provided to the prefabricatedcompound masonry unit 110 after it is on the truck for further protection and stabilization during travel. Other means of lifting and moving the units can be used and can be dependent on the size and weight of the unit to be transported. -
FIG. 9 is a side view of another embodiment of acompound masonry unit 200. As shown inFIG. 9 , a single course ofU-shaped blocks 202 can be used to make thecompound unit 200. The individual blocks 202 are joined together withmortar 204 to make the course.FIG. 11 is a plan view of a portion of the course. -
FIG. 10 is a cross-sectional view ofFIG. 9 along line 10-10. As shown inFIG. 10 , theU-shaped block 202 forms abed 208 running the length of theblock 202 between thewalls 205 of theblock 202. Therefore, thebed 208 can run the length of the course. In one embodiment, athin layer 206 ofbonding material 30 can be spread in thebed 208 of theunit 200. Thethin layer 206 can be approximately 0.25 inch to 1 inch. This thickness is not meant to be limiting and is provided as example only. Other thicknesses can be used as desired or required. However, increased thickness will increase the weight of the compound unit.Provisional reinforcement 210 is laid on thethin layer 206 ofbonding material 30. Over the frp is placed anotherlayer 212 ofbonding material 30 to enclose the frp. Thelayer 212 can be of the same thickness or a different thickness than thethin layer 206. Thelayers same bonding material 30 or can be different bonding materials, i.e., thethin layer 206 can be epoxy grout andlayer 212 can be high strength mortar. - The
layers bonding material 30 andprovisional reinforcement 210 can run the length of thecompound masonry unit 200. It is also contemplated that at least theprovisional reinforcement 210 only be placed in thebed 208 across the joints ofindividual units 202. Alternatively, theprovisional reinforcement 210 can be laid in multiple sections in any suitable lengths and any suitable interval that provide the requisite strength to thecompound masonry unit 200. - In another embodiment,
provisional reinforcement 210 can be added to thecompound unit 200 to bridge thejoints 211 betweenindividual blocks 202 at the top of the course, as shown inFIGS. 10 and 11 .FIG. 11 is a plan view of a portion of the course that includes the joint 211 filled withmortar 204 between twoblocks 202. As shown inFIG. 10 , theprovisional reinforcement 210 bridges the joint 211 between the individual blocks 202. A length ofprovisional reinforcement 210 is set in slots formed in the top surface of theblocks 202 and set in place with bonding material 230.FIG. 10 illustrates the use of theprovisional reinforcement 210 in thebed 208 and spanning thejoints 211. These embodiments can be combined as shown or can be used individually. Theprovisional reinforcement 210 in thebed 208 can also be combined with theprovisional reinforcement 20 shown inFIGS. 1-4 . The course can be put together with theprovisional reinforcement 210 in the bridge joints 211, with theprovisional reinforcement 210 in thebed 208 being laid after the course is made. Theprovisional reinforcement 210 can be installed in strips at each joint or continuous through all joints. - Another embodiment of the
compound unit 200′ is shown inFIGS. 12 and 13 . In this embodiment, thecompound unit 200′ is shown with twocourses blocks compound unit 200′ is shown having twocourses compound unit 200′ can be made of more than two courses. Thebottom course 201 is made of a plurality ofU-shaped blocks 202 while thesecond course 203 is made of a plurality ofhollow blocks 40. - In this embodiment,
provisional reinforcement 210 is added to thecompound unit 200′ to bridge thejoints 211 betweenindividual blocks 202 at the top of thebottom course 201, as well as to bridge thejoints 211 betweenindividual blocks 40 at the top of thesecond course 203. Theprovisional reinforcement 210 is set in slots withbonding material 30. As withFIGS. 9-11 , usingprovisional reinforcement 210 to spanjoints 211 refers to using frp of any length and shape that contacts a portion up to a whole of the length of two adjacent blocks. - The embodiment of
FIG. 13 is shown without any additional reinforcement added to thebed 208. Alternatively, theprovisional reinforcement 210 added to thebed 208 described with regard toFIG. 10 can be incorporated into thecompound unit 200′. - The
layers bonding material 30 andprovisional reinforcement 210′ can run the length of theunit 200′. It is also contemplated that at least theprovisional reinforcement 210′ only be placed in thebed 208 across the joints ofindividual units 202′. Alternatively, theprovisional reinforcement 210′ can be laid in multiple sections in any suitable lengths that provide the requisite strength to the compound unit. -
FIG. 14 is another embodiment of a prefabricatedcompound masonry unit 200″. This embodiment is the same in many respects as the embodiment inFIG. 13 , and thus the overlapping description will not be repeated. As shown inFIG. 14 , theprovisional reinforcement 210 in thebottom course 201 is inserted in a different position than that inFIG. 13 . Rather than bridging thejoints 211 of theblocks 202 at the top of thecourse 201, theprovisional reinforcement 210 bridges thejoints 211 between theblocks 202 in two places along thebed 208 of thecompound unit 200″. A length ofprovisional reinforcement 210 is set in slots in theblocks 202 and set in place withbonding material 30.FIG. 14 only illustrates two places where theprovisional reinforcement 210 spans the joint 211 in thebed 208. However, this is not meant to be limiting. Theprovisional reinforcement 210 can be used to bridge thejoints 211 in any number of locations along thebed 208 andwalls 205 as desired or required. The position of theprovisional reinforcement 210 along thebed 208 is also provided by means of example and is not meant to be limiting. The positions can be located as desired or required along thebed 208 and/orwall 205. The depth of slots in which theprovisional reinforcement 210 is retained is also illustrative and not meant to be limiting. -
FIG. 15 is a cross-sectional view of an alternative embodiment of thecompound masonry unit 200″ that incorporates theprovisional reinforcement 210 in thejoints 211 betweenindividual blocks 40 to bridge thejoints 211 along the top surface as shown inFIG. 14 , and incorporates into the same course theprovisional reinforcement 210 bridging thejoints 211 between theblocks 202 along thebed 208, also shown inFIG. 14 . - Also illustrated in
FIG. 15 is an embodiment of areusable carrier 220 for the prefabricated compound masonry units disclosed herein. Thereusable carrier 220 allows for an alternate method for transportation of prefabricated compound masonry units manufactured as disclosed herein to the build sites. Thereusable carrier 220 comprises asupport member 222 having twosupport legs 224 extending from thesupport member 222 to form an inverted “U” shape. Thesupport member 222 and supportlegs 224 can be made of lumber. - As shown in
FIG. 15 , a prefabricatedcompound masonry unit 200″ is set on thesupport member 222 of thereusable carrier 220. The prefabricatedcompound masonry unit 200″ would be banded to thecarrier 220 in a plurality of positions along their lengths. The slings of a crane would then be placed around the combined unit and the unit moved to the transporter for transportation to the build site. At the build site, the combined unit would be removed in the same way from the transporter. Thereusable carrier 220 can be used for a portion of the shoring support as well as shipping. Thereusable carrier 220 would be brought back to the fabrication site for reuse. - In the embodiments described herein, a coating can be applied to the compound masonry units prior to transporting to the build site to provide corrosion protection and abrasion resistance and fills joints. The coating can be, as a non-limiting example, a polymer coating that uses formulations of poly urea with different physical property ranges. A coating can also be used to water proof the compound masonry units as desired or required. One skilled in the art will recognize the various coating that can be used to achieve the desired results.
- While the invention has been described in connection with certain embodiments, it is to be understood that the invention is not to be limited to the disclosed embodiments but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims, which scope is to be accorded the broadest interpretation so as to encompass all such modifications and equivalent structures as are permitted under the law.
Claims (20)
1. A prefabricated compound masonry unit made at a fabrication site and configured for transportation to a build site comprising:
a first course comprising a plurality of hollow blocks laid end to end with adjacent ends adhered with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core;
at least one channel formed in a top surface of the first course, the at least one channel having a length; and
provisional reinforcement provided along at least a portion of the length of the at least one channel and held within the at least one channel with a bonding material different from the mortar,
wherein the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in the hollow core at the build location.
2. The prefabricated compound masonry unit of claim 1 , wherein the at least one channel is two channels formed in spaced relation on the top surface of the first course with provisional reinforcement provided along at least a portion of the length of each of the two channels and held within the two channels with a bonding material.
3. The prefabricated compound masonry unit of claim 2 , wherein the plurality of hollow blocks are a plurality of U-shaped blocks such that the top surface of the course has a first side and a second side, with one of the two channels formed on the first side and another of the two channels formed on the second side.
4. The prefabricated compound masonry unit of claim 1 further comprising one or more additional courses laid in ascending order upon the first course and adhered to adjacent courses with mortar.
5. The prefabricated compound masonry unit of claim 4 , wherein a top course comprises:
at least one channel formed in a top surface of the top course, the at least one channel having a length; and
provisional reinforcement provided along at least a portion of the length of the at least one channel and held within the at least one channel with bonding material.
6. The prefabricated compound masonry unit of claim 3 , wherein the portion of the length that the provisional reinforcement extends is intervals along the length, each interval spanning a joint between adjacent U-shaped blocks.
7. The prefabricated compound masonry unit of claim 6 further comprising one or more additional courses laid in ascending order upon the first course and adhered to adjacent courses with mortar.
8. The prefabricated compound masonry unit of claim 7 , wherein a top course comprises:
at least one channel formed in a top surface of the top course, the at least one channel having a length; and
provisional reinforcement provided along at least a portion of the length of the at least one channel and held within the at least one channel with bonding material.
9. The prefabricated compound masonry unit of claim 3 , wherein the plurality of U-shaped blocks each have a bed between two side walls such that the first course has a bed extending along the length of the first course, and wherein additional provisional reinforcement is provided above a surface of the bed at least along a portion of the length of the bed.
10. The prefabricated compound masonry unit of claim 3 , wherein the blocks in the plurality of U-shaped blocks each has a bed between two side walls such that the first course has a bed extending along the length of the first course, and wherein additional provisional reinforcement is provided in one or more slits within ends of adjacent U-shaped blocks such that a joint between adjacent blocks is spanned, the slits formed within the surface of one or both of the bed and the two side walls.
11. The prefabricated compound masonry unit of claim 1 , wherein the provisional reinforcement extends along substantially an entire length of the first course.
12. The prefabricated compound masonry unit of claim 1 , wherein the provisional reinforcement is fiber reinforced polymer.
13. A prefabricated compound masonry unit comprising:
a first course comprising a plurality of U-shaped blocks each having a bed extending between two side walls, the plurality of U-shaped blocks laid end to end with adjacent ends adhered with mortar and positioned to form a continuous bed along a length of the first course; and
provisional reinforcement provided along at least a portion of the continuous bed of the first course and held with a bonding material different from the mortar,
wherein the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from a fabrication location to a build location where the first course is configured to receive permanent structural masonry reinforcement in a cavity defined by the continuous bed and side walls at a build location.
14. The prefabricated compound masonry unit of claim 13 , wherein the provisional reinforcement is laid above a surface of the continuous bed along a majority of the length of the continuous bed.
15. The prefabricated compound masonry unit of claim 13 , wherein the provisional reinforcement is provided in one or more slits within ends of adjacent U-shaped blocks such that a joint between adjacent blocks is spanned, the slits formed within the surface of one or both of the bed and the two side walls.
16. A method of making a prefabricated compound masonry unit prior to transporting the unit to a build site comprising:
(a) forming a first course from a plurality of hollow blocks by joining ends of adjacent blocks with mortar, the plurality of hollow blocks positioned such that the first course has a hollow core;
(b) forming at least one channel in a top surface of the first course, the at least one channel having a length;
(c) placing provisional reinforcement along at least a portion of the length of the at least one channel; and
(d) retaining the provisional reinforcement within the at least one channel of the first course with a bonding material different from the mortar, wherein (a)-(d) are performed at a fabrication location and the provisional reinforcement provides tensile strength to the first course for transportation and handling of the first course from the fabrication location to a build location, the hollow core of the first course configured to receive permanent structural masonry reinforcement at the build location.
17. The method of claim 16 , wherein the plurality of hollow blocks are U-shaped blocks having two side walls and a bed extending there between, and the at least one channel is two channels, and wherein:
step (b) comprises forming one of the two channels along a top surface of one of the two side walls and forming another of the two channels along a top surface of another of the two side walls;
step (c) comprises placing provisional reinforcement in each of the two channels; and
step (d) comprises retaining the provisional reinforcement within the two channels with the bonding material.
18. The method of claim 16 , wherein the first course has a bed extending along the length of the first course, the bed positioned between external walls of the first course, the method further comprising:
(e) providing bonding material along at least a bottom surface of the bed; and
(f) placing provisional reinforcement in the bonding material within the bed along at least a portion of the length, wherein (e) and (f) are performed at the fabrication location.
19. The method of claim 16 further comprising:
(e) forming a second course from a plurality of blocks by joining adjacent blocks with mortar, the second course having a top surface with a first side and a second side and a joint between each pair of adjacent blocks, wherein (e) is performed at the fabrication location and the provisional reinforcement provides tensile strength to the second course sufficient for transportation and handling of the first course and second course from the fabrication location to a build location.
20. The method of claim 16 wherein the first course has a bed extending along the length of the first course, the bed positioned between external walls of the first course, the method further comprising:
(e) providing slits in adjacent hollow blocks that span joints between the adjacent hollow blocks, the slits located along the bed; and
(f) placing provisional reinforcement in the slits and retaining the provisional reinforcement in the slits with bonding material, wherein (e) and (f) are performed at the fabrication location.
Priority Applications (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US13/846,470 US20130205688A1 (en) | 2010-10-15 | 2013-03-18 | Prefabricated compound masonry units |
CN201420082718.5U CN204139368U (en) | 2013-03-18 | 2014-02-26 | Prefabricated compound masonry units |
US15/188,906 US9932737B1 (en) | 2010-10-15 | 2016-06-21 | Prefabricated masonry lintels |
US15/188,747 US9926703B1 (en) | 2010-10-15 | 2016-06-21 | Prefabricated masonry wall panels |
US15/943,438 US10544583B2 (en) | 2010-10-15 | 2018-04-02 | Prefabricated masonry walls |
Applications Claiming Priority (5)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
US39359910P | 2010-10-15 | 2010-10-15 | |
US201161439863P | 2011-02-05 | 2011-02-05 | |
US13/274,502 US20120090259A1 (en) | 2010-10-15 | 2011-10-17 | Prefabricated compound masonry units |
US13/307,704 US20120090260A1 (en) | 2010-10-15 | 2011-11-30 | Prefabricated compound masonry units |
US13/846,470 US20130205688A1 (en) | 2010-10-15 | 2013-03-18 | Prefabricated compound masonry units |
Related Parent Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/307,704 Continuation-In-Part US20120090260A1 (en) | 2010-10-15 | 2011-11-30 | Prefabricated compound masonry units |
Related Child Applications (2)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US15/188,906 Continuation-In-Part US9932737B1 (en) | 2010-10-15 | 2016-06-21 | Prefabricated masonry lintels |
US15/188,747 Continuation-In-Part US9926703B1 (en) | 2010-10-15 | 2016-06-21 | Prefabricated masonry wall panels |
Publications (1)
Publication Number | Publication Date |
---|---|
US20130205688A1 true US20130205688A1 (en) | 2013-08-15 |
Family
ID=48944462
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/846,470 Abandoned US20130205688A1 (en) | 2010-10-15 | 2013-03-18 | Prefabricated compound masonry units |
Country Status (1)
Country | Link |
---|---|
US (1) | US20130205688A1 (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9086268B2 (en) * | 2013-10-02 | 2015-07-21 | Jonathan E Jones | Concrete block spacer system |
US20160160511A1 (en) * | 2014-12-08 | 2016-06-09 | Blox, Llc | Panel moving systems |
CN107532421A (en) * | 2015-01-07 | 2018-01-02 | 贾斯特生物纤维公司 | Interlocking structure block bracing means and modular architectural system |
US9890545B1 (en) * | 2016-11-14 | 2018-02-13 | Steven James Bongiorno | Erection system |
CN109680799A (en) * | 2018-12-28 | 2019-04-26 | 常州市武进建筑设计院有限公司 | The frame structure bean column node of the prefabricated floor girder and board of large span band connects and hanging method |
WO2020176530A1 (en) | 2019-02-26 | 2020-09-03 | Colin Felton | Interlocking composite construction block |
USD997387S1 (en) * | 2021-09-20 | 2023-08-29 | Allan Block, Llc | Modular block system |
Citations (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2994162A (en) * | 1957-07-05 | 1961-08-01 | Frantz Markey | Building block and wall construction made therefrom |
US3256657A (en) * | 1963-01-30 | 1966-06-21 | Idaho Invest Corp | Wall of interlocked, adhesively secured building blocks and sealing means therebetween |
US3314208A (en) * | 1964-03-02 | 1967-04-18 | United Res And Dev Company Inc | Grouted masonry wall |
US3936987A (en) * | 1975-01-13 | 1976-02-10 | Edward L Calvin | Interlocking brick or building block and walls constructed therefrom |
US4034529A (en) * | 1976-06-03 | 1977-07-12 | Lampus Donald L | Rebar bolster for solid grouted walls |
US4167840A (en) * | 1978-07-19 | 1979-09-18 | Ivany George R | Reinforced masonry wall construction |
US4769961A (en) * | 1986-02-07 | 1988-09-13 | Hanota Holdings Sa | Building block and structure made therefrom |
US4793104A (en) * | 1988-06-15 | 1988-12-27 | Delberg, Inc. | Guide for laying glass blocks |
US5099628A (en) * | 1989-11-27 | 1992-03-31 | Stt, Inc. | Apparatus for enhancing structural integrity of masonry structures |
US5465538A (en) * | 1993-09-07 | 1995-11-14 | Powers, Jr.; John | Prefabricated lintel |
US6088987A (en) * | 1995-12-21 | 2000-07-18 | Simmons; Scott | Modular building materials |
US6189282B1 (en) * | 1998-06-24 | 2001-02-20 | Building Works, Inc. | Mortarless concrete block |
US6240693B1 (en) * | 1999-05-28 | 2001-06-05 | Gary L. Komasara | Interlocking and insulating form pattern assembly for creating a wall structure for receiving poured concrete and method for producing a form pattern assembly |
DE10043609C1 (en) * | 2000-09-05 | 2001-10-18 | Octaplan Wandsysteme Gmbh & Co | Wall has prefabricated wall panels, each with several rows of blocks and having reinforcement rods and reinforcement loops passing around vertical rods in adjacent panels |
US20020148187A1 (en) * | 2001-04-17 | 2002-10-17 | Walters Donald L. | Construction blocks and structures therefrom |
US20030009970A1 (en) * | 2001-07-12 | 2003-01-16 | Macdonald Robert A. | Multi-channel retaining wall block and system |
US6735913B2 (en) * | 2002-08-01 | 2004-05-18 | Sanders & Associates Geostructural Engineering, Inc. | Block wall system |
US20040159068A1 (en) * | 2003-01-17 | 2004-08-19 | Yuriy Prokofyev | Universal modular building block and a method and structures based on the use of the aforementioned block |
US20060201082A1 (en) * | 2005-02-10 | 2006-09-14 | Westblock Systems, Inc. | Masonry block wall system |
US20090188186A1 (en) * | 2008-01-29 | 2009-07-30 | Ebanks Desmond A | Building Construction System and Structural Modules Thereof |
US7762033B2 (en) * | 2006-03-29 | 2010-07-27 | Scott Robert E | Wall construction system and method |
US7971407B2 (en) * | 2007-05-21 | 2011-07-05 | Keystone Retaining Wall Systems, Inc. | Wall block and wall block system for constructing walls |
US20110258957A1 (en) * | 2010-04-21 | 2011-10-27 | Virnich Andrew P | Masonry unit for constructing a multi-wythe wall |
-
2013
- 2013-03-18 US US13/846,470 patent/US20130205688A1/en not_active Abandoned
Patent Citations (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US2994162A (en) * | 1957-07-05 | 1961-08-01 | Frantz Markey | Building block and wall construction made therefrom |
US3256657A (en) * | 1963-01-30 | 1966-06-21 | Idaho Invest Corp | Wall of interlocked, adhesively secured building blocks and sealing means therebetween |
US3314208A (en) * | 1964-03-02 | 1967-04-18 | United Res And Dev Company Inc | Grouted masonry wall |
US3936987A (en) * | 1975-01-13 | 1976-02-10 | Edward L Calvin | Interlocking brick or building block and walls constructed therefrom |
US4034529A (en) * | 1976-06-03 | 1977-07-12 | Lampus Donald L | Rebar bolster for solid grouted walls |
US4167840A (en) * | 1978-07-19 | 1979-09-18 | Ivany George R | Reinforced masonry wall construction |
US4769961A (en) * | 1986-02-07 | 1988-09-13 | Hanota Holdings Sa | Building block and structure made therefrom |
US4793104A (en) * | 1988-06-15 | 1988-12-27 | Delberg, Inc. | Guide for laying glass blocks |
US5099628A (en) * | 1989-11-27 | 1992-03-31 | Stt, Inc. | Apparatus for enhancing structural integrity of masonry structures |
US5465538A (en) * | 1993-09-07 | 1995-11-14 | Powers, Jr.; John | Prefabricated lintel |
US6088987A (en) * | 1995-12-21 | 2000-07-18 | Simmons; Scott | Modular building materials |
US6189282B1 (en) * | 1998-06-24 | 2001-02-20 | Building Works, Inc. | Mortarless concrete block |
US6240693B1 (en) * | 1999-05-28 | 2001-06-05 | Gary L. Komasara | Interlocking and insulating form pattern assembly for creating a wall structure for receiving poured concrete and method for producing a form pattern assembly |
DE10043609C1 (en) * | 2000-09-05 | 2001-10-18 | Octaplan Wandsysteme Gmbh & Co | Wall has prefabricated wall panels, each with several rows of blocks and having reinforcement rods and reinforcement loops passing around vertical rods in adjacent panels |
US20020148187A1 (en) * | 2001-04-17 | 2002-10-17 | Walters Donald L. | Construction blocks and structures therefrom |
US6588168B2 (en) * | 2001-04-17 | 2003-07-08 | Donald L. Walters | Construction blocks and structures therefrom |
US20030009970A1 (en) * | 2001-07-12 | 2003-01-16 | Macdonald Robert A. | Multi-channel retaining wall block and system |
US6735913B2 (en) * | 2002-08-01 | 2004-05-18 | Sanders & Associates Geostructural Engineering, Inc. | Block wall system |
US20040159068A1 (en) * | 2003-01-17 | 2004-08-19 | Yuriy Prokofyev | Universal modular building block and a method and structures based on the use of the aforementioned block |
US20060201082A1 (en) * | 2005-02-10 | 2006-09-14 | Westblock Systems, Inc. | Masonry block wall system |
US7762033B2 (en) * | 2006-03-29 | 2010-07-27 | Scott Robert E | Wall construction system and method |
US7971407B2 (en) * | 2007-05-21 | 2011-07-05 | Keystone Retaining Wall Systems, Inc. | Wall block and wall block system for constructing walls |
US20090188186A1 (en) * | 2008-01-29 | 2009-07-30 | Ebanks Desmond A | Building Construction System and Structural Modules Thereof |
US20110258957A1 (en) * | 2010-04-21 | 2011-10-27 | Virnich Andrew P | Masonry unit for constructing a multi-wythe wall |
Non-Patent Citations (1)
Title |
---|
Machine translation of DE10043609, 2001.10.18, Germany * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9086268B2 (en) * | 2013-10-02 | 2015-07-21 | Jonathan E Jones | Concrete block spacer system |
US20160160511A1 (en) * | 2014-12-08 | 2016-06-09 | Blox, Llc | Panel moving systems |
CN107532421A (en) * | 2015-01-07 | 2018-01-02 | 贾斯特生物纤维公司 | Interlocking structure block bracing means and modular architectural system |
US9890545B1 (en) * | 2016-11-14 | 2018-02-13 | Steven James Bongiorno | Erection system |
CN109680799A (en) * | 2018-12-28 | 2019-04-26 | 常州市武进建筑设计院有限公司 | The frame structure bean column node of the prefabricated floor girder and board of large span band connects and hanging method |
WO2020176530A1 (en) | 2019-02-26 | 2020-09-03 | Colin Felton | Interlocking composite construction block |
USD997387S1 (en) * | 2021-09-20 | 2023-08-29 | Allan Block, Llc | Modular block system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20120090259A1 (en) | Prefabricated compound masonry units | |
US20130205688A1 (en) | Prefabricated compound masonry units | |
US9926703B1 (en) | Prefabricated masonry wall panels | |
US8745943B2 (en) | Composite insulated precast and tilt-up concrete structures | |
US11286667B2 (en) | Seismic foundation framer and method of forming a foundation using same | |
US6360505B1 (en) | Surface panel and associated ICF system for creating decorative and utilitarian surfaces on concrete structures | |
US8099918B2 (en) | Special and improved configurations for unitized post tension block systems for masonry structures | |
US7568321B2 (en) | Adobe building construction system and associated methods | |
US9932737B1 (en) | Prefabricated masonry lintels | |
CN103827415A (en) | Insulated concrete form and method of using same | |
WO2011021151A1 (en) | Method and system for in-situ construction of civil structures | |
KR100304861B1 (en) | Insulation Precast Concrete Panel | |
US10954665B1 (en) | Sprayed-in-place framed wall | |
US5894704A (en) | Wall construction process | |
EP3719229B1 (en) | Concrete floor panel, method of production of such panel and floor made of this panel | |
KR101616483B1 (en) | Construction Method Of Underground Parking Lot Using Precast Concrete Beam With Changing Cross Section | |
CN204139368U (en) | Prefabricated compound masonry units | |
US10344477B2 (en) | Weight-reducing discs, specially designed meshes and the method that includes the aforesaid, for producing weight-reduced structure such as slabs, pre-slabs, floors, partitions and beams | |
Palanichamy et al. | Prefabrication Technique for residential building” | |
RU61744U1 (en) | MONOLITHIC OVERLAP | |
RU2452824C2 (en) | Method to erect structures resistant to earthquake attacks | |
WO2002077380B1 (en) | Displaced structures for tall buildings and pouring method | |
McGuinness | Early Concrete Housing in Maidenhead and Elsewhere in the British Isles | |
SE0801962A1 (en) | Passivite | |
WO2014091047A1 (en) | Ecological reinforcement material for vaults in pre-existing constructions, and associated method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: CONSTRUCTIVE, L.L.C., MICHIGAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNORS:MUIRHEAD, DAVE;GENDRON, JIM;REEL/FRAME:030216/0735 Effective date: 20130320 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |