US20070204668A1 - Method and apparatus for plastic working of hollow rack bar and hollow rack bar - Google Patents
Method and apparatus for plastic working of hollow rack bar and hollow rack bar Download PDFInfo
- Publication number
- US20070204668A1 US20070204668A1 US11/686,705 US68670507A US2007204668A1 US 20070204668 A1 US20070204668 A1 US 20070204668A1 US 68670507 A US68670507 A US 68670507A US 2007204668 A1 US2007204668 A1 US 2007204668A1
- Authority
- US
- United States
- Prior art keywords
- wall thickness
- work piece
- rack bar
- blank
- mandrel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Abandoned
Links
- 238000000034 method Methods 0.000 title claims description 34
- 230000009467 reduction Effects 0.000 claims abstract description 60
- 238000005242 forging Methods 0.000 claims abstract description 24
- 238000004519 manufacturing process Methods 0.000 claims description 5
- 230000006872 improvement Effects 0.000 claims description 4
- 230000003245 working effect Effects 0.000 claims description 3
- 230000008569 process Effects 0.000 description 28
- 239000000047 product Substances 0.000 description 21
- 230000007246 mechanism Effects 0.000 description 13
- 238000011946 reduction process Methods 0.000 description 12
- 239000000463 material Substances 0.000 description 10
- 238000010409 ironing Methods 0.000 description 9
- 239000012467 final product Substances 0.000 description 7
- 238000003754 machining Methods 0.000 description 6
- 229910019142 PO4 Inorganic materials 0.000 description 4
- 238000000576 coating method Methods 0.000 description 4
- NBIIXXVUZAFLBC-UHFFFAOYSA-K phosphate Chemical compound [O-]P([O-])([O-])=O NBIIXXVUZAFLBC-UHFFFAOYSA-K 0.000 description 4
- 239000010452 phosphate Substances 0.000 description 4
- 239000007787 solid Substances 0.000 description 4
- 239000013585 weight reducing agent Substances 0.000 description 4
- 230000015572 biosynthetic process Effects 0.000 description 3
- 239000002184 metal Substances 0.000 description 3
- 229910052751 metal Inorganic materials 0.000 description 3
- 238000010079 rubber tapping Methods 0.000 description 3
- 230000004323 axial length Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 239000000446 fuel Substances 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000010276 construction Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000003292 diminished effect Effects 0.000 description 1
- 239000011796 hollow space material Substances 0.000 description 1
- 239000013067 intermediate product Substances 0.000 description 1
- 150000002739 metals Chemical class 0.000 description 1
- 230000003746 surface roughness Effects 0.000 description 1
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21K—MAKING FORGED OR PRESSED METAL PRODUCTS, e.g. HORSE-SHOES, RIVETS, BOLTS OR WHEELS
- B21K1/00—Making machine elements
- B21K1/76—Making machine elements elements not mentioned in one of the preceding groups
- B21K1/767—Toothed racks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B21—MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
- B21K—MAKING FORGED OR PRESSED METAL PRODUCTS, e.g. HORSE-SHOES, RIVETS, BOLTS OR WHEELS
- B21K1/00—Making machine elements
- B21K1/76—Making machine elements elements not mentioned in one of the preceding groups
- B21K1/767—Toothed racks
- B21K1/768—Toothed racks hollow
Definitions
- the present invention relates to a production of rack bar in a steering mechanism of a vehicle from a pipe shaped blank by plastic working, and, more particularly, to its improvement, by which an increased reduction in the weight of the product is obtained in comparison with the prior art.
- a rack bar is a main part of a steering system of a vehicle and has conventionally been produced by machining from a solid bar of a rounded cross-sectional shape by using originally a hobbing machine and recently a broaching machine.
- a machining from a solid bar of rounded cross-sectional shape makes the product to be heavy. Therefore, a solution has been proposed, wherein the machined product is subjected to a subsequent boring by using a gun drill to obtain a hollow structure, thereby reducing the weight.
- this solution makes the production cost to be increased on one hand and, on the other hand, makes the resource consumption efficiency to be reduced.
- the present invention aims to overcome the above difficulties in the prior art and, in particular, to provide a technology, by which an effective use of the material along the entire length of the blank is realized, a desired performance as a rack bar is obtained and increased degrees of a weight reduction, a cost performance, a resource saving and a vehicle performance is realized.
- a method for forging a of a rack bar of radially outwardly copied type wherein a pipe shaped work piece is held by a die set, the material of the work piece is plastically flown to the die set located diametrically outward from the work piece in a manner that a toothed shape of the die set is copied to the work piece.
- the present invention features that an adjustment of the cross sectional area of the work piece is preliminary done by a local increase or decrease of wall thickness of the work piece prior to the execution of the rack forging process of radial expanded copied type.
- An adjustment of the cross-sectional area according to the present invention is carried out by an apparatus, which is constructed by a combined die set having an elongated mandrel and a plurality of dies and a vertical or horizontal hydraulic cylinder mechanism, which is cooperated with the die set in a manner that a desired local increase or decrease of the wall thickness of the blank pipe is obtained at respective positions of the blank pipe along its length.
- any suitable reciprocating mechanism such as a ball screw type, where a rotating movement is converted to a linear movement, may be employed.
- a rack bar of VGR (variable gear ratio) type is usually used.
- VGR variable gear ratio
- the electric operated type requires an increased bending strength of toothed portion, i.e., an increased size of tooth part as well as an increased thickness.
- the present invention can achieve this goal, while obtaining the maximum reduction of the weight of a rack bar.
- a forging of toothed portions is done by a radially outwardly directed plastic flow of metal of a pipe shaped blank while preventing fibrous metals from being broken.
- an adjustment of the cross sectional area of the blank pipe is essential and has been done by a grinding.
- a plastic working is done for obtaining a desired increase or decrease in the wall thickness at locations along the length of the work piece, so as to obtain desired values of cross-sectional area, corresponding to the desired functions required at the respective locations.
- a wall thickness corresponding to the wall thickness of the blank pipe is basically maintained, so that a desired toothed shape is obtained under the plastic flow, although a wall thickness increase by a diameter reduction can be taken when it is necessary.
- a wall thickness reduction is done so long as a desired strength within a permissible range is obtained.
- a wall thickness reduction may be done by ironing, which causes the work piece to be axially elongated. Namely, in the present invention, the length of the product must be decided while an axial elongation as generated by the reduction of the wall thickness of the blank pipe is taken into the consideration.
- a blank pipe of a reduced axial length for a value corresponding the axial elongation can be used, resulting in a corresponding reduction of the weight of product.
- the weight of a product is almost equal to that of the blank pipe and is about 1,236 kg when the blank of wall thickness of 4 mm and of a diameter of 25 mm has a length of 615 mm.
- the value of wall thickness at toothed portions is maintained to that of the blank pipe, i.e., 4 mm and the wall thickness of the portion other than the toothed portion is reduced to 2 mm by an ironing process, while keeping the desired strength of the product.
- a weight reduction of the present invention is 25.6% over the prior art as in '378, '204, '205 or '703 patent and is, even, better than 60% over the prior art where a solid blank rather than the pipe shaped blank is used. Irrespective of such an additional process like a swaging or ironing for obtaining a cross sectional area control, a substantial reduction of the cost is obtained.
- the redemption cost of the die set would be, at the most, 10 yen per one product. It will thus be understood that a material cost reduction of about 48 yen per one product is possible.
- a resultant reduction in the weight of a vehicle is obtained, which assists in an improvement of a drive ability of the vehicle, on one hand, and, on the other hand, in a reduction in a fuel consumption efficiency.
- the reduction in the fuel consumption efficiency per one car would be minimal but is significant in view of a huge automobile market, which might be amount to 70,000,000 cars in worldwide.
- FIGS. 1 a to 1 e are schematic views of a series of stages for producing a rack bar according to the present invention.
- FIG. 2 is a schematic view of a process for forging a rack bar from a pipe shaped blank by using a shuttle type rack bar forging system.
- FIGS. 3 a to 3 c are schematic views of a series of stages for carrying out a diameter reduction of a blank pipe.
- FIGS. 4 a to 4 g are schematic views of a series of stages for carrying out a wall thickness reduction of a blank after subjected to the diameter reduction process.
- FIGS. 5 a to 5 d are schematic views of a series of stages for obtaining, from an initial blank, under one shot principle, a worked blank suitably for a supply to a subsequent rack bar forging process.
- FIGS. 1 a to 1 e illustrates a series of steps or stages for forming a rack bar according to the present invention.
- a reference numeral 10 denotes a blank pipe (intermediate part) or a work piece supplied from a maker after subjected to a phosphate coating process.
- the wall thickness of a blank is designated by to and its length by L 0 , respectively.
- the wall thickness t 0 has a value of 4 mm, the material at a portion (tooth profile forming portion) of the blank pipe of this value of wall thickness is subjected to radially outwardly directed plastic flow, resulting in a formation of toothed portions of desired values of height and strength.
- a first stage diameter reduction is done only at the tooth profile forming portion. Namely, at the location 10 ′ of the blank pipe of a predetermined length from its left-hand end is subjected to a diameter reduction, so that the wall thickness t 1 is obtained, which is equal to or slightly increased over the wall thickness to of the blank pipe. Such a diameter reduction is done by a swaging process as will be explained later.
- the length of the reduced diameter part 10 ′ corresponds to that of a toothed part 11 ( FIG. 1 e ) of a rack bar.
- the remaining portion, which was not subjected to the diameter reduction, is designated by 10 ′′.
- a wall thickness reduction is done at a part of a rack bar, which becomes a connection part (axially extended part from the toothed part).
- a wall thickness t 0 of 4 mm of a blank pipe is suitable for the toothed part to obtain desired values of tooth height and strength needed for a rack bar product after the completion of a forging process.
- a value of wall thickness of 4 mm is excessive for the connection part in view of its designated function, since the connection part is less stressed when compared with the toothed part.
- a portion of a blank pipe, which becomes a connection part of a rack bar as a forged product, is subjected to a plastic working so that a wall thickness reduction is done from t 0 of a blank pipe to t 2 , which is, for example, about 1 ⁇ 2 of t 0 , i.e., t 2 ⁇ 0.5 ⁇ t 0 ( 2 mm).
- t 0 of a blank pipe
- an ironing process may be employed, which accompanies with an elongation of the blank pipe from a length of L 0 to L 1 .
- a wall thickness reduced portion 10 - 2 of a wall thickness of t 2 is formed as shown in FIG. 1 c .
- the length L 1 corresponds to a length of a rack bar as a final product.
- a blank pipe of a length corresponding to that of a product is needed.
- the length L 1 corresponding to that a product is obtained by a wall thickness reduction accompanied with the corresponding axial elongation.
- an initial blank pipe of a reduced length can be employed for a value corresponding to an axial elongation as obtained during a wall thickness reduction process.
- a blank pipe length can be reduced from a value of L 1 to a value of L 0 .
- a relatively short length portion 10 - 3 is left, which has a value of thickness to corresponding to that of the initial blank pipe.
- This value of wall thickness at the portion 10 - 3 is suitable for machining screw threads for an engagement with a part of a steering mechanism.
- a process for a diameter reduction is done so that a desired reduced value of inner diameter is obtained, which is suitable for the machining.
- the reduced diameter portion 10 - 1 is obtained by additionally reduce the diameter of the portion 10 ′ obtained at the second step in FIG. 2 b.
- a flattening is done at a location of the blank pipe where toothed portions are to be formed.
- the reduced diameter portion 10 - 1 of the blank is, at its upper surface 10 - 1 A, flattened, resulting in a semi-circular cross-sectional shape of the blank at the portion 10 - 1 .
- a fifth step is shown in FIG. 1 e , where a forging of toothed portions is done at the flattened portion 10 - 1 A of the blank pipe.
- the blank pipe is held by a die set and mandrels are inserted to the blank pipe alternately between left-handed and right-handed directions.
- a rack bar forging is done in a manner that toothed portions on the die set are copied to the blank pipe, so that toothed portions 11 are formed as shown in FIG. 1 e .
- the rack bar fording may be done by a system as describe in any of '378, '204, '205 and '703 patents.
- any of elongated type mandrel as in '378, '204 or '205 patent or a shuttle type mandrel as in '703 patent may be desirably used.
- the latter shuttle type mandrel as shown in FIG. 2 is used.
- FIG. 2 shows a combined type die set for a rack bar forging, which includes a bottom die 12 and a top die 14 , between which the blank pipe 10 is held.
- short sized mandrels (shuttles) 16 a and 16 b are arranged on the left-handed and the right-handed sides of the die set.
- pusher rods 17 a and 17 b are respectively arranged in a manner that the pusher rods 17 a and 17 engage, at respective ends, with recesses 15 a and 15 b at the ends of the shuttles 16 a and 16 b .
- the reduced diameter portion 10 - 1 of the blank pipe is arranged between the upper and lower dies 12 and 14 . Under a closed condition between the dies, the upper wall 10 - 1 A of the reduced diameter portion 10 - 1 of the blank pipe is pressed by toothed portion 14 A of the upper die 14 and is substantially flattened, thereby completing the flattening process as explained with reference to FIG. 1 d and allowing the rack forging process to be instantly commenced.
- a die set for practicing this step includes a die holder 20 , a die set constructed by a guide 22 , a drawing die 23 and a squeezing die 24 , which are, in series, inserted to the holder 20 , and a mandrel 26 of a three stepped shape.
- the mandrel 26 is connected to a hydraulic cylinder mechanism (not shown).
- the mandrel 26 is formed with a front portion 26 - 1 of reduced diameter and having a length corresponding to that of the toothed portion 11 ( FIG. 1 e ) of a rack bar as a final product. Furthermore, the mandrel 26 is, at its rear end, formed with a rear portion 26 - 2 of an increased diameter.
- FIGS. 3 a to 3 c A diameter reduction process as practiced by the device shown in FIGS. 3 a to 3 c will be explained. Namely, at the first stage as shown in FIG. 3 a , a blank pipe 10 after the completion of a phosphate coating process is mounted to the mandrel 8 . As explained in FIG. 1 a , the blank pipe 10 has a length of L 0 and a wall thickness of t 0 , which is uniform along the entire length.
- the mandrel 26 is moved forward as shown by an arrow a in FIG. 3 a , which causes the blank pipe 10 to be pushed as shown by arrows a′ in FIG.
- the blank 10 is, first, inserted into the die holder 20 and then into the guide 22 under a guide action of a tapered portion 22 A at the inlet end of the guide 22 .
- the blank 10 is substantially not subjected to any plastic deformation, thereby keeping the outer diameter of the blank pipe to be unchanged. In other words, a small clearance exists between the inner diameter of the blank pipe 10 and the front portion 26 - 1 of the mandrel 26 .
- a further forward movement of the blank 10 causes the latter to be introduced into the drawing die 23 via its tapered inlet portion 23 A, so that the blank 10 is subjected to a diameter reduction in a manner that a clearance with respect to the front portion 26 - 1 of the mandrel 26 is diminished.
- a portion of the blank 10 thus subjected to diameter reduction is designated by a reference numeral 10 ′ and a portion of the blank 10 of the original diameter not subjected to diameter reduction is designated by a reference numeral 10 ′′.
- the reduced diameter portion 10 ′ has a length, which corresponds to that of a toothed portion of a rack as the final product.
- a worked blank intermediate product
- the mandrel 26 is finally and additionally moved in the forward direction as shown in FIG. 3 c , so that the reduced diameter portion 10 ′ is, at its tip end, squeezed by a die 24 and the squeezed portion of the work piece is designated by a reference numeral 10 ′′′.
- a squeezed portion 10 ′′′ is not shown in the corresponding FIG. 1 b , it is used for an engagement with a mandrel during a subsequent wall thickness reduction process and is cut and removed after the completion of the use.
- FIGS. 4 a to 4 g illustrates the detail of a wall thickness reduction process and a diameter reduction process at the connecting portion of the rack bar as explained schematically in FIG. 1 c .
- a plastic working device for a wall thickness reduction is provided, which includes a long stroke hydraulic cylinder device (not shown), a mandrel 30 connected to the hydraulic cylinder device so that the mandrel 30 is axially reciprocated, a die 32 cooperating with the mandrel 30 for a diameter reduction, and a striker 34 for a diameter expansion at an axial end and which is shown in FIG. 4 a at its position radially outwardly retracted as illustrated by arrows b′.
- the mandrel 30 forms a stepped member constructed by an inlet or front part 30 - 1 , an intermediate part 30 - 2 of an increased diameter connected to the part 30 - 1 and a rear part 30 - 3 of a reduced diameter to that of the inlet part 30 - 1 for a connection with a hydraulic mechanism (not shown).
- the inlet part 30 - 1 and the increased diameter part 30 - 2 have values of length, which correspond, respectively, to those of a toothed part and a connection part (shaft) of a rack bar as a final product.
- FIG. 4 a illustrates a condition of the plastic working device, whereat a blank pipe 10 after subjected to the preliminary diameter reduction process by the device in FIG. 3 is held by the mandrel 30 .
- the mandrel 30 has an outer profile, which corresponds to an inner profile of the blank at an area from the portion 10 ′ to 10 ′′.
- the inlet part 30 - 1 of the mandrel 30 is, at its leading end, contacted with the squeezed part 10 ′′′ as obtained at the process as shown in FIG. 3 c .
- a hydraulic pressure is introduced into the hydraulic cylinder mechanism, causing its piston rod (not shown) to be extended, so that the mandrel 30 in connection with the piston is moved forwardly as shown by an arrow a. Due to the fact that the leading end of the inlet part 30 - 1 of the mandrel is in contact with the squeezed part 10 ′′′ of the mandrel 10 , the blank 10 is entrained by the movement of the mandrel 30 toward the die 32 as shown by the arrow a. As a result, the blank 10 is introduced into the die 32 from the squeezed part 10 ′′′.
- the portion 10 ′ of the blank after the squeezed part 10 ′′′ in the direction of its movement as shown by the arrow a has a value of an outer diameter, which is slightly larger than that of the inner diameter of the die 32 .
- the difference in these values substantially corresponds to a clearance of the portion 10 ′ with respect to the inlet part 30 - 1 . Therefore, the portion 10 ′ is subjected to a slight diameter reduction and the work piece is not substantially subjected to any wall thickness reduction or is subjected only to a very slight wall thickness reduction. Namely, it is shown in FIG. 4 b that no wall thickness change occurs in the portions 10 ′′′ and 10 ′ even after the passage of the die 32 .
- the portion 10 ′′ has a value of an outer diameter, which is properly larger than that of an inner diameter of the die 32 for a wall thickness of the work piece. The difference of these values is, for example, about one half of the wall thickness of the work piece. As a result, the portion 10 ′′ ( FIG.
- the length portion 10 ′′ of the work piece located rearward from the die 32 and of the same wall thickness as that of the initial blank pipe is gradually reduced, while moved toward the connection portion 30 - 3 on the increased diameter portion 30 - 2 of the mandrel 30 .
- a relatively short length of the portion 10 ′′ of the same wall thickness as that of the initial blank pipe is left on the connection portion 30 - 3 of the mandrel under a condition that the portion 10 ′′ is passed through the die 32 as shown in FIG. 4 b .
- the work piece is completely passed through the die 32 and the rearward end surface of the blank 10 exceeds slightly from the front end surface of the striker 34 , which is under in its retracted position.
- the striker 34 is, from the radially retracted position, moved radially inwardly as shown by arrows b toward a position, whereat the front end of the striker 34 is contacted with the connection part 30 - 3 of the mandrel.
- a part 10 - 3 is formed as shown in FIG. 4 d , which part has a value of wall thickness nearly equal to that of an initial blank pipe and which is radially outwardly expanded with respect to the wall thickness reduced part 10 - 2 .
- the part 10 - 3 may be subjected to a diameter reduction process, so as to obtain an increased wall thickness, which is suitable for a subsequent tapping operation.
- FIG. 4 d a fully retracted position of the mandrel 30 is illustrated.
- a device for diameter reduction which comprises a mandrel 36 and a die 37 .
- the mandrel 36 is formed with a front part 36 - 1 of reduced diameter, a taper part 36 - 2 and a base part 36 - 3 , which is in connection with a hydraulic cylinder (not shown).
- a hydraulic cylinder not shown.
- An introduction of a hydraulic pressure to the hydraulic cylinder causes the mandrel 36 to be moved forward, so that the work piece on the mandrel 36 is introduced into the die 37 .
- the portions 10 ′′′ and 10 ′ of the work are subjected to a diameter reduction for a value corresponding to a difference between the inner diameter of die 37 and the outer diameter of the work.
- FIG. 4 f illustrates the most forwardly moved position of the mandrel 36 with respect to the die 37 , whereat the shoulder portion 36 - 2 of the mandrel 36 is faced with the die at its inlet end.
- the part 10 ′ ( FIG. 4 e ) of the work is, at its entire length, subjected to a diameter reduction while keeping the wall thickness being unchanged, thereby obtaining a reduced diameter portion 10 - 1 as shown in FIG. 4 f having a tip end as illustrated by 10 - 1 ′.
- the mandrel 36 is retracted in the rearward or reverse direction as shown by an arrow c in FIG. 4 g .
- the part 10 - 1 of a reduced diameter as also illustrated in FIG. 1 c is thus obtained.
- FIGS. 5 a to 5 d illustrate a second embodiment of the present invention, wherein preliminary plastic working processes for obtaining a work piece, i.e., a diameter reduction at a location becoming a toothed part of a rack bar and a wall thickness reduction as a location becoming a connection part (shaft part) of the rack bar as illustrated in FIGS. 1 b and 1 c , respectively are done under one shot principle from a blank pipe after subjected to the phosphate coating process followed only by a squeezing at its tip end.
- a plastic working device is provided, which is constructed by a die set 38 and a mandrel 39 .
- the die set is constructed by an outer cylindrical body (die holder) 40 and an end-to-end connected structure of a series of members, which includes a first guide cylinder 42 , a squeeze die 44 , a second guide cylinder 46 and a diameter reduction die 48 .
- the outer cylindrical body 40 is, at its front end, formed with an inward projected portion 40 - 1 , with which the diameter reducing die 48 located at the front end of the end-to-end connected combined die structure is engaged, while a retainer member 49 is screwed to the rear end of the outer cylindrical body 40 in manner that the member 49 is engaged with the first guide cylinder 42 located at the rear end of the end-to-end connected structure, so that the structure is fixed to the outer cylindrical body 40 .
- the first guide cylinder 42 has a front end 42 A outwardly tapered for a smooth introduction of the blank by the mandrel 39 , which is followed by a remained part of a uniformed inner diameter.
- the squeeze die 44 is formed with an inner stepped part 44 A, which is cooperated with the mandrel for obtaining a wall thickness reduction of blank.
- the squeeze die 44 is connected, via the second guide cylinder 46 of an uniform inner diameter, to diameter reducing die 48 , which has a tapered par 48 A, which functions purely for diameter reduction of the tip end of the blank while keeping its wall thickness.
- the combined die structure is cooperated with the mandrel 50 for carrying out the designated working.
- the mandrel 39 is formed with a rear large diameter part 50 , a middle diameter part 52 and a front small diameter part 52 - 2 .
- the mandrel 39 is connected with a hydraulic cylinder mechanism (not shown) for obtaining a reciprocated movement of the mandrel 39 .
- the middle diameter part 52 is formed with a tapered part 52 - 1 , from which the small diameter part 52 - 2 is axially forwardly projected.
- the plastic working device is further provided with a blank knockout pin 54 for removing a product after completion of the designated processes.
- the work piece 10 is an original blank pipe supplied from a maker, to which a phosphate coating process has been completed.
- the work piece has been subjected a squeezing process only at its leading end, while the remaining part is left at a straight shape with a uniform wall thickness.
- the work piece (blank pipe) 10 is introduced into the plastic working device by means of the mandrel 39 moving in the left-handed direction as shown by an arrow a in FIG. 5 a .
- the mandrel receives the work piece 10 without substantial clearance at the middle diameter part 52 and engages with the squeezed tip end 10 a of the work piece at the front small diameter part 52 - 2 .
- the work piece 10 is entrained by the forward movement of the mandrel 39 as shown by the arrow a.
- any substantial working is not obtained, i.e., the diameter as well as the wall thickness of the work piece are unchanged, until a condition is obtained, where the front end of the work piece 10 is made contact with the stepped part 44 A of the squeezing die 44 as shown in FIG. 5 a.
- FIG. 5 a An introduction of the hydraulic pressure into the hydraulic cylinder device for operating the mandrel is continued from the condition as shown in FIG. 5 a , so that the mandrel is moved forwardly to a condition as shown in FIG. 5 b , where the tapered part 52 - 1 of the mandrel 39 is faced with the tapered part 44 A of the squeezing die 44 .
- the mandrel 39 is further forwardly moved from the condition as shown in FIG. 5 b , which causes the blank 10 to be also forwardly moved, while the contact of the blank with the squeezed part 10 a .
- the blank 10 is passed through the die 44 , so that the blank 10 is subjected to a diameter reduction process.
- the portion 10 ′′′′ of reduced diameter of the is made substantial contact with the front small diameter part 52 - 2 of the mandrel.
- the value of wall thickness of the portion 10 ′′′′ is slightly increased or substantially unchanged with respect to the value of wall thickness of the initial blank.
- the portion 10 ′′′′′ of the blank which is located on the middle diameter part 52 of the mandrel and which is engaged with the squeezing die 44 , is subjected to a wall thickness reduction.
- the remaining portion 10 - 3 of the blank located rearward from the die 44 is not subjected to diameter reduction, i.e., the outer diameter is maintained.
- this portion 10 - 3 of the unchanged outer diameter of the blank is pushed back on the middle diameter part 52 of the mandrel 39 in the rearward direction in accordance with the progress of the wall thickness reduction by the squeezing die 44 .
- a rearward push-back type wall thickness reduction is done.
- the further forward movement finally causes the blank to be engaged with the die 48 and to be subjected to a diameter reduction, so that a reduced diameter portion 10 - 1 of a substantially unchanged wall thickness is projected out of the die 48 as shown in FIG. 5 d .
- this second embodiment is advantageous in that a worked blank for forging a rack bar is obtained under one shot process from a straight blank pipe while preparatory works are eliminated except for a squeezing process at the tip end, resulting in a high efficiency of the process.
- the hydraulic cylinder device for operating a mandrel is illustrated as horizontal type.
- a hydraulic cylinder device of vertical type may also be used.
- a mechanism such as an elongated ball screw operated by a servomotor of a variable velocity may also be used.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Forging (AREA)
Abstract
Description
- 1. Field of Invention
- The present invention relates to a production of rack bar in a steering mechanism of a vehicle from a pipe shaped blank by plastic working, and, more particularly, to its improvement, by which an increased reduction in the weight of the product is obtained in comparison with the prior art.
- 2. Description of Related Art
- A rack bar is a main part of a steering system of a vehicle and has conventionally been produced by machining from a solid bar of a rounded cross-sectional shape by using originally a hobbing machine and recently a broaching machine. However, such a machining from a solid bar of rounded cross-sectional shape makes the product to be heavy. Therefore, a solution has been proposed, wherein the machined product is subjected to a subsequent boring by using a gun drill to obtain a hollow structure, thereby reducing the weight. However, this solution makes the production cost to be increased on one hand and, on the other hand, makes the resource consumption efficiency to be reduced.
- Thus, the applicants of this application et al have proposed an improvement, wherein a plastic working (forging) of a pipe shaped blank is done for obtaining a rack bar of a reduced weight while keeping a reduced resource consumption as well as an increased vehicle performance. In this rack forging technology, a pipe shaped blank is held by a die set having toothed portions at a side facing the blank and a mandrel is inserted into the hollow space of the blank, so that toothed portions corresponding to those of the die set are copied to the blank. See specifications of Japanese Patent No. 3547378, Japanese Patent No. 3607204 and Japanese Patent No. 3607205 and Japanese Un-Examined Patent Publication (Kokai) No. 2006-026703.
- In the prior art disclosed in above patents, pipe shaped blanks just supplied by manufacturers of predetermined fixed wall thickness of a value of about 4 mm are used. This predetermined wall thickness of the blank pipe is decided by the tooth height desired for the particular rack bar. In order to obtain an increased tooth height of a rack bare, a blank pipe of in increased wall thickness is needed at locations where the toothed portions are created. In the prior art, a blank pipe of a uniform value of wall thickness was used, resulting in an excessive wall thickness at the locations other than the toothed portions. Thus, the prior art is defective in an increased product weight and reduced material consumption efficiency. Thus, a long felt need has been existed as far as a reduced production cost, increased material consumption efficiency and increased performance are concerned.
- The present invention aims to overcome the above difficulties in the prior art and, in particular, to provide a technology, by which an effective use of the material along the entire length of the blank is realized, a desired performance as a rack bar is obtained and increased degrees of a weight reduction, a cost performance, a resource saving and a vehicle performance is realized.
- According to the present invention, a method for forging a of a rack bar of radially outwardly copied type is provided, wherein a pipe shaped work piece is held by a die set, the material of the work piece is plastically flown to the die set located diametrically outward from the work piece in a manner that a toothed shape of the die set is copied to the work piece. The present invention features that an adjustment of the cross sectional area of the work piece is preliminary done by a local increase or decrease of wall thickness of the work piece prior to the execution of the rack forging process of radial expanded copied type. Namely, upon the execution of the preliminary adjustment of the cross-sectional area, a work piece is subjected to plastic workings for desirably increasing or decreasing the wall thickness at the respective axial positions of the work piece along the length thereof. As a result, desired values of cross-sectional area corresponding to desired functions at the respective portions of the work piece along its length are obtained.
- The above mentioned adjustment of the wall thickness of work piece at the respective portions along its length is carried out by so-called swaging or ironing process under a single stage or a plurality of divided stages.
- An adjustment of the cross-sectional area according to the present invention is carried out by an apparatus, which is constructed by a combined die set having an elongated mandrel and a plurality of dies and a vertical or horizontal hydraulic cylinder mechanism, which is cooperated with the die set in a manner that a desired local increase or decrease of the wall thickness of the blank pipe is obtained at respective positions of the blank pipe along its length. In place of the hydraulic cylinder mechanism, any suitable reciprocating mechanism, such as a ball screw type, where a rotating movement is converted to a linear movement, may be employed.
- In a power steering mechanism of an electric operated type, a rack bar of VGR (variable gear ratio) type is usually used. In this type of mechanism, it is needed that values of the pitch as well as the inclination angle of toothed portions are varied along the length. Such a construction of the VGR rack bar makes it difficult that it is machined from a solid work piece. Therefore, a forging from a pipe shaped blank is usually employed. Furthermore, unlike the hydraulic operated type, the electric operated type requires an increased bending strength of toothed portion, i.e., an increased size of tooth part as well as an increased thickness.
- The present invention can achieve this goal, while obtaining the maximum reduction of the weight of a rack bar. Namely, according to the present invention, a forging of toothed portions is done by a radially outwardly directed plastic flow of metal of a pipe shaped blank while preventing fibrous metals from being broken. Under such principle of rack formation, an adjustment of the cross sectional area of the blank pipe is essential and has been done by a grinding. In contrast, according to the present invention, a plastic working is done for obtaining a desired increase or decrease in the wall thickness at locations along the length of the work piece, so as to obtain desired values of cross-sectional area, corresponding to the desired functions required at the respective locations. In more detail, at the location where a toothed form is to be formed, a wall thickness corresponding to the wall thickness of the blank pipe is basically maintained, so that a desired toothed shape is obtained under the plastic flow, although a wall thickness increase by a diameter reduction can be taken when it is necessary.
- In comparison, at locations other than the location for the formation of the toothed portions, a desired strength is obtained, even when the wall thickness is smaller than the wall thickness of the blank pipe. Therefore, according to the present invention, a wall thickness reduction is done so long as a desired strength within a permissible range is obtained. A wall thickness reduction may be done by ironing, which causes the work piece to be axially elongated. Namely, in the present invention, the length of the product must be decided while an axial elongation as generated by the reduction of the wall thickness of the blank pipe is taken into the consideration. In other words, in the present invention, a blank pipe of a reduced axial length for a value corresponding the axial elongation can be used, resulting in a corresponding reduction of the weight of product. Namely, in the prior art as in '378, '204, '205 or '703 patent, the weight of a product is almost equal to that of the blank pipe and is about 1,236 kg when the blank of wall thickness of 4 mm and of a diameter of 25 mm has a length of 615 mm. In contrast, in the present invention, the value of wall thickness at toothed portions is maintained to that of the blank pipe, i.e., 4 mm and the wall thickness of the portion other than the toothed portion is reduced to 2 mm by an ironing process, while keeping the desired strength of the product. Thus, according to the present invention, it is possible to use a blank pipe of a reduced length for a value corresponding to the lengthwise elongation as generated by the ironing. The inventor has found that a desired performance is obtained even when the length of a blank pipe is reduced so that the weight of a blank pipe, i.e., the weight of a product is reduced to 920 g, although the weight reduction depends on a length of toothed portions having a value of a wall thickness, corresponding to that of the blank pipe. In this example, a weight reduction of the present invention is 25.6% over the prior art as in '378, '204, '205 or '703 patent and is, even, better than 60% over the prior art where a solid blank rather than the pipe shaped blank is used. Irrespective of such an additional process like a swaging or ironing for obtaining a cross sectional area control, a substantial reduction of the cost is obtained. Assuming that a material cost is 170 yen/kg, a resultant reduction of the material cost would be (1.236−0.920)×170=53.7 yen per one product. In addition, the redemption cost of the die set would be, at the most, 10 yen per one product. It will thus be understood that a material cost reduction of about 48 yen per one product is possible. Furthermore, as a result of a reduction of a weight of a product, i.e., a rack bar, a resultant reduction in the weight of a vehicle is obtained, which assists in an improvement of a drive ability of the vehicle, on one hand, and, on the other hand, in a reduction in a fuel consumption efficiency. The reduction in the fuel consumption efficiency per one car would be minimal but is significant in view of a huge automobile market, which might be amount to 70,000,000 cars in worldwide.
- Furthermore, as a result of the ironing after the swaging, a highly improved surface roughness is obtained not only at the inner surface but also at the outer surface, which allows a dimension to be controlled within a tolerance of microns, thereby allowing a increased product quality and precision to be easily obtained.
-
FIGS. 1 a to 1 e are schematic views of a series of stages for producing a rack bar according to the present invention. -
FIG. 2 is a schematic view of a process for forging a rack bar from a pipe shaped blank by using a shuttle type rack bar forging system. -
FIGS. 3 a to 3 c are schematic views of a series of stages for carrying out a diameter reduction of a blank pipe. -
FIGS. 4 a to 4 g are schematic views of a series of stages for carrying out a wall thickness reduction of a blank after subjected to the diameter reduction process. -
FIGS. 5 a to 5 d are schematic views of a series of stages for obtaining, from an initial blank, under one shot principle, a worked blank suitably for a supply to a subsequent rack bar forging process. -
FIGS. 1 a to 1 e illustrates a series of steps or stages for forming a rack bar according to the present invention. InFIG. 1 a, areference numeral 10 denotes a blank pipe (intermediate part) or a work piece supplied from a maker after subjected to a phosphate coating process. InFIG. 1 a, the wall thickness of a blank is designated by to and its length by L0, respectively. In this particular embodiment, the wall thickness t0 has a value of 4 mm, the material at a portion (tooth profile forming portion) of the blank pipe of this value of wall thickness is subjected to radially outwardly directed plastic flow, resulting in a formation of toothed portions of desired values of height and strength. - At a second step as shown in
FIG. 1 b, a first stage diameter reduction is done only at the tooth profile forming portion. Namely, at thelocation 10′ of the blank pipe of a predetermined length from its left-hand end is subjected to a diameter reduction, so that the wall thickness t1 is obtained, which is equal to or slightly increased over the wall thickness to of the blank pipe. Such a diameter reduction is done by a swaging process as will be explained later. The length of the reduceddiameter part 10′ corresponds to that of a toothed part 11 (FIG. 1 e) of a rack bar. The remaining portion, which was not subjected to the diameter reduction, is designated by 10″. - At a third step as shown in
FIG. 1 c, a wall thickness reduction is done at a part of a rack bar, which becomes a connection part (axially extended part from the toothed part). As illustrated above, a wall thickness t0 of 4 mm of a blank pipe is suitable for the toothed part to obtain desired values of tooth height and strength needed for a rack bar product after the completion of a forging process. However, such a value of wall thickness of 4 mm is excessive for the connection part in view of its designated function, since the connection part is less stressed when compared with the toothed part. Thus, a portion of a blank pipe, which becomes a connection part of a rack bar as a forged product, is subjected to a plastic working so that a wall thickness reduction is done from t0 of a blank pipe to t2, which is, for example, about ½ of t0, i.e., t2≈0.5×t0 (=2 mm). For obtaining such a wall thickness reduction, an ironing process may be employed, which accompanies with an elongation of the blank pipe from a length of L0 to L1. In short, in a blank pipe, as an axial extension of a reduced diameter portion 10-1 of a wall thickness of t1 corresponding to theportion 10′ inFIG. 1 b, a wall thickness reduced portion 10-2 of a wall thickness of t2 is formed as shown inFIG. 1 c. The length L1 corresponds to a length of a rack bar as a final product. In the prior art, a blank pipe of a length corresponding to that of a product is needed. Contrary to this, the length L1 corresponding to that a product is obtained by a wall thickness reduction accompanied with the corresponding axial elongation. Thus, an initial blank pipe of a reduced length can be employed for a value corresponding to an axial elongation as obtained during a wall thickness reduction process. In short, in comparison with the prior art, a blank pipe length can be reduced from a value of L1 to a value of L0. Thus, a corresponding material consumption as well as weight reduction are obtained, thereby obtaining a material cost reduction as well as a running cost reduction. - In the third step shown in
FIG. 1 c, a relatively short length portion 10-3 is left, which has a value of thickness to corresponding to that of the initial blank pipe. This value of wall thickness at the portion 10-3 is suitable for machining screw threads for an engagement with a part of a steering mechanism. Preferably, prior to such a machining, a process for a diameter reduction is done so that a desired reduced value of inner diameter is obtained, which is suitable for the machining. - Also in the third step in
FIG. 1 c, the reduced diameter portion 10-1 is obtained by additionally reduce the diameter of theportion 10′ obtained at the second step inFIG. 2 b. - At a fourth step shown in
FIG. 1 d, in the blank pipe as obtained at the third step, a flattening is done at a location of the blank pipe where toothed portions are to be formed. Namely, the reduced diameter portion 10-1 of the blank is, at its upper surface 10-1A, flattened, resulting in a semi-circular cross-sectional shape of the blank at the portion 10-1. - A fifth step is shown in
FIG. 1 e, where a forging of toothed portions is done at the flattened portion 10-1A of the blank pipe. Namely, the blank pipe is held by a die set and mandrels are inserted to the blank pipe alternately between left-handed and right-handed directions. As a result, a rack bar forging is done in a manner that toothed portions on the die set are copied to the blank pipe, so thattoothed portions 11 are formed as shown inFIG. 1 e. The rack bar fording may be done by a system as describe in any of '378, '204, '205 and '703 patents. Namely, any of elongated type mandrel as in '378, '204 or '205 patent or a shuttle type mandrel as in '703 patent may be desirably used. In the embodiment, the latter shuttle type mandrel as shown inFIG. 2 is used. Namely,FIG. 2 shows a combined type die set for a rack bar forging, which includes abottom die 12 and atop die 14, between which theblank pipe 10 is held. As explained in detail in '703 patent, short sized mandrels (shuttles) 16 a and 16 b are arranged on the left-handed and the right-handed sides of the die set. Outwardly from theshuttles pusher rods pusher rods 17 a and 17 engage, at respective ends, withrecesses shuttles toothed portion 14A of theupper die 14 and is substantially flattened, thereby completing the flattening process as explained with reference toFIG. 1 d and allowing the rack forging process to be instantly commenced. Namely, a reciprocating movement of the shuttle shapedmandrels pusher rods mandrels blank pipe 10 held between the dies 12 and 14. As a result, the metal of the blank pipe at the diametric reduced portion 10-1 is plastically flown radially outwardly toward thetoothed portions 14A of theupper die 14, so that a forging of toothed portions on the flattened surface 10-1A of the diametric reduced portion 10-1 of the blank pipe is done in a manner that thetoothed shape 11 of the die is copied to theblank pipe 10. - After the completion of the forging of the rack bar, conventional processes for finishing to a product are done, which includes a correction of a curving, additional swaging at both ends, a working of grooves, a working of width-across-flat portion, an inner diameter tapping, a quench-and-temper process, an outer diameter machining, a test of meshed condition and anti-corrosive treatment, et al. The thus obtained final product is wrapped and shipped. Any more detailed explanation of these processes are omitted, since they are not directly related with the essence of the present invention.
- Now, a diameter reduction process as schematically illustrated in
FIG. 1 b and a wall thickness reducing process at a connection portion as schematically illustrated inFIG. 1 c, as preliminary steps for a cross-sectional area adjustment process prior to a rack bar forging process will be explained in more detail. First, the diameter reduction process inFIG. 1 b will be explained in more detail with reference toFIGS. 3 a to 3 c. A die set for practicing this step includes adie holder 20, a die set constructed by aguide 22, adrawing die 23 and a squeezingdie 24, which are, in series, inserted to theholder 20, and amandrel 26 of a three stepped shape. Themandrel 26 is connected to a hydraulic cylinder mechanism (not shown). Themandrel 26 is formed with a front portion 26-1 of reduced diameter and having a length corresponding to that of the toothed portion 11 (FIG. 1 e) of a rack bar as a final product. Furthermore, themandrel 26 is, at its rear end, formed with a rear portion 26-2 of an increased diameter. - A diameter reduction process as practiced by the device shown in
FIGS. 3 a to 3 c will be explained. Namely, at the first stage as shown inFIG. 3 a, ablank pipe 10 after the completion of a phosphate coating process is mounted to the mandrel 8. As explained inFIG. 1 a, theblank pipe 10 has a length of L0 and a wall thickness of t0, which is uniform along the entire length. Themandrel 26 is moved forward as shown by an arrow a inFIG. 3 a, which causes theblank pipe 10 to be pushed as shown by arrows a′ inFIG. 3 b due to the fact that the diameter expanded portion 26-2 of themandrel 26 contacts, at its end surface (shoulder), with the blank 10. As a result, the blank 10 is, first, inserted into thedie holder 20 and then into theguide 22 under a guide action of a taperedportion 22A at the inlet end of theguide 22. During the movement in theguide 22, the blank 10 is substantially not subjected to any plastic deformation, thereby keeping the outer diameter of the blank pipe to be unchanged. In other words, a small clearance exists between the inner diameter of theblank pipe 10 and the front portion 26-1 of themandrel 26. - A further forward movement of the blank 10 causes the latter to be introduced into the drawing die 23 via its tapered
inlet portion 23A, so that the blank 10 is subjected to a diameter reduction in a manner that a clearance with respect to the front portion 26-1 of themandrel 26 is diminished. InFIG. 3 b, a portion of the blank 10 thus subjected to diameter reduction is designated by areference numeral 10′ and a portion of the blank 10 of the original diameter not subjected to diameter reduction is designated by areference numeral 10″. The reduceddiameter portion 10′ has a length, which corresponds to that of a toothed portion of a rack as the final product. In short, a worked blank (intermediate product), which corresponds to the work piece shown inFIG. 1 b, is thus obtained. - In this embodiment, the
mandrel 26 is finally and additionally moved in the forward direction as shown inFIG. 3 c, so that the reduceddiameter portion 10′ is, at its tip end, squeezed by adie 24 and the squeezed portion of the work piece is designated by areference numeral 10′″. Although such a squeezedportion 10′″ is not shown in the correspondingFIG. 1 b, it is used for an engagement with a mandrel during a subsequent wall thickness reduction process and is cut and removed after the completion of the use. -
FIGS. 4 a to 4 g illustrates the detail of a wall thickness reduction process and a diameter reduction process at the connecting portion of the rack bar as explained schematically inFIG. 1 c. A plastic working device for a wall thickness reduction is provided, which includes a long stroke hydraulic cylinder device (not shown), amandrel 30 connected to the hydraulic cylinder device so that themandrel 30 is axially reciprocated, a die 32 cooperating with themandrel 30 for a diameter reduction, and astriker 34 for a diameter expansion at an axial end and which is shown inFIG. 4 a at its position radially outwardly retracted as illustrated by arrows b′. Themandrel 30 forms a stepped member constructed by an inlet or front part 30-1, an intermediate part 30-2 of an increased diameter connected to the part 30-1 and a rear part 30-3 of a reduced diameter to that of the inlet part 30-1 for a connection with a hydraulic mechanism (not shown). The inlet part 30-1 and the increased diameter part 30-2 have values of length, which correspond, respectively, to those of a toothed part and a connection part (shaft) of a rack bar as a final product. -
FIG. 4 a illustrates a condition of the plastic working device, whereat ablank pipe 10 after subjected to the preliminary diameter reduction process by the device inFIG. 3 is held by themandrel 30. As shown inFIG. 4 a, themandrel 30 has an outer profile, which corresponds to an inner profile of the blank at an area from theportion 10′ to 10″. The inlet part 30-1 of themandrel 30 is, at its leading end, contacted with the squeezedpart 10′″ as obtained at the process as shown inFIG. 3 c. Then, a hydraulic pressure is introduced into the hydraulic cylinder mechanism, causing its piston rod (not shown) to be extended, so that themandrel 30 in connection with the piston is moved forwardly as shown by an arrow a. Due to the fact that the leading end of the inlet part 30-1 of the mandrel is in contact with the squeezedpart 10′″ of themandrel 10, the blank 10 is entrained by the movement of themandrel 30 toward the die 32 as shown by the arrow a. As a result, the blank 10 is introduced into the die 32 from the squeezedpart 10′″. Theportion 10′ of the blank after the squeezedpart 10′″ in the direction of its movement as shown by the arrow a has a value of an outer diameter, which is slightly larger than that of the inner diameter of thedie 32. However, the difference in these values substantially corresponds to a clearance of theportion 10′ with respect to the inlet part 30-1. Therefore, theportion 10′ is subjected to a slight diameter reduction and the work piece is not substantially subjected to any wall thickness reduction or is subjected only to a very slight wall thickness reduction. Namely, it is shown inFIG. 4 b that no wall thickness change occurs in theportions 10′″ and 10′ even after the passage of thedie 32. - During the further forward movement of the
mandrel 30, its diameter expanded portion 30-2 is faced with the wall thickness reduction die 32 via theportion 10″ of values of the wall thickness and the outer diameter, which are substantially unchanged with respect to those of the initial blank pipe. Theportion 10″ has a value of an outer diameter, which is properly larger than that of an inner diameter of thedie 32 for a wall thickness of the work piece. The difference of these values is, for example, about one half of the wall thickness of the work piece. As a result, theportion 10″ (FIG. 4 a) of the blank is subjected to an ironing operation by the die 32 during the forward movement of the blank as shown by the arrow a, so that a wall thickness reduction as well as an axial elongation are occurred in theportion 10″ of the blank. This thin walled portion obtained from theportion 10″ on the increased diameter portion 30-2 inFIG. 4 a, which is passed through the die 32A and is subjected to a wall thickness reduction, is illustrated by 10-2 inFIG. 4 b. In accordance with the progress of this ironing process, thelength portion 10″ of the work piece located rearward from thedie 32 and of the same wall thickness as that of the initial blank pipe is gradually reduced, while moved toward the connection portion 30-3 on the increased diameter portion 30-2 of themandrel 30. Finally, a relatively short length of theportion 10″ of the same wall thickness as that of the initial blank pipe is left on the connection portion 30-3 of the mandrel under a condition that theportion 10″ is passed through the die 32 as shown inFIG. 4 b. At the extremity position in the forward stroke of the mandrel as shown by the arrow a as shown inFIG. 4 b, the work piece is completely passed through thedie 32 and the rearward end surface of the blank 10 exceeds slightly from the front end surface of thestriker 34, which is under in its retracted position. - At the next step as shown in
FIG. 4 c, thestriker 34 is, from the radially retracted position, moved radially inwardly as shown by arrows b toward a position, whereat the front end of thestriker 34 is contacted with the connection part 30-3 of the mandrel. - Then, a switching of the introduction of the hydraulic cylinder mechanism is done in a manner that the
mandrel 30 is retracted in the right-handed direction as shown by an arrow c. Due to the fact that therear end portion 10″ of the blank 10 is contacted with a shoulder portion 30-4 of the mandrel located between the diameter expanded part 30-2 and the inner diameter setting part 30-3, the blank 30 is entrained by the movement of themandrel 30 until thepart 10″ is made contacted with thestriker 34. However, when the rearward movement of themandrel 30 in the direction as shown by the arrow c is done until theportion 10″ is made contact with thestriker 34, the entrained movement of the blank 10 is ceased due to the fact that the blank is engaged with thestriker 34, on one hand and, on the other hand, the rearward movement of themandrel 30 in the direction as shown by the arrow c is continued. During such a rearward movement of themandrel 30 in the direction as shown by the arrow c, the large diameter part 30-2 is engaged with thepart 10″ of the work piece, so that the latter is radially outwardly displaced. Thus, at the rear end of the work piece, a part 10-3 is formed as shown inFIG. 4 d, which part has a value of wall thickness nearly equal to that of an initial blank pipe and which is radially outwardly expanded with respect to the wall thickness reduced part 10-2. At the later stage, the part 10-3 may be subjected to a diameter reduction process, so as to obtain an increased wall thickness, which is suitable for a subsequent tapping operation. InFIG. 4 d, a fully retracted position of themandrel 30 is illustrated. - At the following stage, the work piece in
FIG. 4 d after subjected to the wall thickness reduction and the axial elongation is subjected to the processes as shown inFIGS. 4 e to 4 g for obtaining a diameter reduction (second stage diameter reduction) of the work piece at location, which corresponds to a toothed part of a rack bar as a product. Thus, a device for diameter reduction is provided, which comprises amandrel 36 and adie 37. Themandrel 36 is formed with a front part 36-1 of reduced diameter, a taper part 36-2 and a base part 36-3, which is in connection with a hydraulic cylinder (not shown). At the first step inFIG. 4 e, to themandrel 36, the work piece as obtained at the step inFIG. 4 d is inserted. - An introduction of a hydraulic pressure to the hydraulic cylinder causes the
mandrel 36 to be moved forward, so that the work piece on themandrel 36 is introduced into thedie 37. As a result of the introduction of the mandrel into thedie 37, theportions 10′″ and 10′ of the work are subjected to a diameter reduction for a value corresponding to a difference between the inner diameter ofdie 37 and the outer diameter of the work. -
FIG. 4 f illustrates the most forwardly moved position of themandrel 36 with respect to thedie 37, whereat the shoulder portion 36-2 of themandrel 36 is faced with the die at its inlet end. Thepart 10′ (FIG. 4 e) of the work is, at its entire length, subjected to a diameter reduction while keeping the wall thickness being unchanged, thereby obtaining a reduced diameter portion 10-1 as shown inFIG. 4 f having a tip end as illustrated by 10-1′. From this extreme position, themandrel 36 is retracted in the rearward or reverse direction as shown by an arrow c inFIG. 4 g. The part 10-1 of a reduced diameter as also illustrated inFIG. 1 c is thus obtained. Then, the tip end portion 10-1′ needed only for the engagement with themandrel 36 during the execution of the diameter reduction is now unnecessary and thus cut off. The part 10-1 of a reduced diameter as also illustrated inFIG. 1 c is thus obtained. The worked blank pipe as illustrated inFIG. 1 c is thus obtained. The worked blank inFIG. 1 c is then subjected to the processes of a rack forging as already explained with reference toFIGS. 1 d and 1 e. -
FIGS. 5 a to 5 d illustrate a second embodiment of the present invention, wherein preliminary plastic working processes for obtaining a work piece, i.e., a diameter reduction at a location becoming a toothed part of a rack bar and a wall thickness reduction as a location becoming a connection part (shaft part) of the rack bar as illustrated inFIGS. 1 b and 1 c, respectively are done under one shot principle from a blank pipe after subjected to the phosphate coating process followed only by a squeezing at its tip end. In this embodiment, a plastic working device is provided, which is constructed by a die set 38 and amandrel 39. The die set is constructed by an outer cylindrical body (die holder) 40 and an end-to-end connected structure of a series of members, which includes afirst guide cylinder 42, asqueeze die 44, asecond guide cylinder 46 and a diameter reduction die 48. The outercylindrical body 40 is, at its front end, formed with an inward projected portion 40-1, with which the diameter reducing die 48 located at the front end of the end-to-end connected combined die structure is engaged, while aretainer member 49 is screwed to the rear end of the outercylindrical body 40 in manner that themember 49 is engaged with thefirst guide cylinder 42 located at the rear end of the end-to-end connected structure, so that the structure is fixed to the outercylindrical body 40. Thefirst guide cylinder 42 has afront end 42A outwardly tapered for a smooth introduction of the blank by themandrel 39, which is followed by a remained part of a uniformed inner diameter. The squeeze die 44 is formed with an inner steppedpart 44A, which is cooperated with the mandrel for obtaining a wall thickness reduction of blank. The squeeze die 44 is connected, via thesecond guide cylinder 46 of an uniform inner diameter, todiameter reducing die 48, which has a taperedpar 48A, which functions purely for diameter reduction of the tip end of the blank while keeping its wall thickness. In short, the combined die structure is cooperated with themandrel 50 for carrying out the designated working. - The
mandrel 39 is formed with a rearlarge diameter part 50, amiddle diameter part 52 and a front small diameter part 52-2. Themandrel 39 is connected with a hydraulic cylinder mechanism (not shown) for obtaining a reciprocated movement of themandrel 39. Themiddle diameter part 52 is formed with a tapered part 52-1, from which the small diameter part 52-2 is axially forwardly projected. Finally, the plastic working device is further provided with ablank knockout pin 54 for removing a product after completion of the designated processes. - An operation of the second embodiment of the present invention will now be explained. As illustrated with reference to
FIG. 1 a, thework piece 10 is an original blank pipe supplied from a maker, to which a phosphate coating process has been completed. In addition, the work piece has been subjected a squeezing process only at its leading end, while the remaining part is left at a straight shape with a uniform wall thickness. The work piece (blank pipe) 10 is introduced into the plastic working device by means of themandrel 39 moving in the left-handed direction as shown by an arrow a inFIG. 5 a. Namely, the mandrel receives thework piece 10 without substantial clearance at themiddle diameter part 52 and engages with the squeezed tip end 10 a of the work piece at the front small diameter part 52-2. As a result, thework piece 10 is entrained by the forward movement of themandrel 39 as shown by the arrow a. However, any substantial working is not obtained, i.e., the diameter as well as the wall thickness of the work piece are unchanged, until a condition is obtained, where the front end of thework piece 10 is made contact with the steppedpart 44A of the squeezingdie 44 as shown inFIG. 5 a. - An introduction of the hydraulic pressure into the hydraulic cylinder device for operating the mandrel is continued from the condition as shown in
FIG. 5 a, so that the mandrel is moved forwardly to a condition as shown inFIG. 5 b, where the tapered part 52-1 of themandrel 39 is faced with thetapered part 44A of the squeezingdie 44. Themandrel 39 is further forwardly moved from the condition as shown inFIG. 5 b, which causes the blank 10 to be also forwardly moved, while the contact of the blank with the squeezedpart 10 a. During the forward movement, the blank 10 is passed through thedie 44, so that the blank 10 is subjected to a diameter reduction process. After the completion of the diameter reduction process, theportion 10″″ of reduced diameter of the is made substantial contact with the front small diameter part 52-2 of the mandrel. However, the value of wall thickness of theportion 10″″ is slightly increased or substantially unchanged with respect to the value of wall thickness of the initial blank. However, theportion 10′″″ of the blank, which is located on themiddle diameter part 52 of the mandrel and which is engaged with the squeezingdie 44, is subjected to a wall thickness reduction. The remaining portion 10-3 of the blank located rearward from thedie 44 is not subjected to diameter reduction, i.e., the outer diameter is maintained. However, this portion 10-3 of the unchanged outer diameter of the blank is pushed back on themiddle diameter part 52 of themandrel 39 in the rearward direction in accordance with the progress of the wall thickness reduction by the squeezingdie 44. In short, a rearward push-back type wall thickness reduction is done. - When the
mandrel 39 is further moved in the forward direction from the condition as shown inFIGS. 5 b to 5 c, a cooperation of themiddle diameter portion 52 of the mandrel with thetaper portion 44A of the die 44 is obtained, which causes the blank pipe to be subjected to a wall thickness reduction, so that the wall thickness reducedportion 10′″″ is created, while the portion 10-3 of the unchanged wall thickness is pushed back in the rearward direction as shown by arrows b. As a result, an elongation of the axial length of the work, which corresponds to the degree of the wall thickness reduction, is obtained. The further forward movement finally causes the blank to be engaged with thedie 48 and to be subjected to a diameter reduction, so that a reduced diameter portion 10-1 of a substantially unchanged wall thickness is projected out of the die 48 as shown inFIG. 5 d. As a result, a worked blank member of substantially the same as that explained with reference toFIG. 1 c, is created, which is constructed by a diameter reduced part 10-1 of a value of wall thickness unchanged with respect to that of the initial blank pipe (a part becoming a toothed part of a rack bar as a final product), a wall thickness reduced part 10-2 of a value of the thickness reduced, for example, to one half of that of the blank pipe (a part becoming a connection part of the rack bar as a final product) and an end part 10-3 having a cross sectional area allowing an additional tapping working (a part for forming a screw portion for connection with an adjacent part). - In short, this second embodiment is advantageous in that a worked blank for forging a rack bar is obtained under one shot process from a straight blank pipe while preparatory works are eliminated except for a squeezing process at the tip end, resulting in a high efficiency of the process.
- In the embodiments as explained, the hydraulic cylinder device for operating a mandrel is illustrated as horizontal type. However, a hydraulic cylinder device of vertical type may also be used. In addition, in place of such a hydraulic cylinder device, a mechanism such as an elongated ball screw operated by a servomotor of a variable velocity may also be used.
Claims (9)
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2006-093190 | 2006-03-03 | ||
JP2006093190A JP2007275896A (en) | 2006-03-16 | 2006-03-30 | Method and device for plastic working of hollow rack, and hollow rack |
Publications (1)
Publication Number | Publication Date |
---|---|
US20070204668A1 true US20070204668A1 (en) | 2007-09-06 |
Family
ID=37969713
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US11/686,705 Abandoned US20070204668A1 (en) | 2006-03-03 | 2007-03-15 | Method and apparatus for plastic working of hollow rack bar and hollow rack bar |
Country Status (2)
Country | Link |
---|---|
US (1) | US20070204668A1 (en) |
EP (1) | EP1839772A1 (en) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140020228A1 (en) * | 2012-07-17 | 2014-01-23 | Benteler Automobiltechnik Gmbh | Method for producing a tubular stabilizer for a motor vehicle |
CN107405675A (en) * | 2015-03-10 | 2017-11-28 | 新日铁住金不锈钢株式会社 | Pipe thickens forming method and thickens pipe |
US20180031104A1 (en) * | 2015-03-23 | 2018-02-01 | Neturen Co., Ltd. | Rack bar and method for manufacturing rack bar |
WO2019102927A1 (en) * | 2017-11-21 | 2019-05-31 | Neturen Co., Ltd. | Manufacturing method for hollow rack bar and hollow rack bar manufacturing apparatus |
US20190247951A1 (en) * | 2016-07-06 | 2019-08-15 | Thyssenkrupp Presta Ag | Rack and method for producing a rack for a steering gear of a motor vehicle |
US10562138B2 (en) | 2015-11-04 | 2020-02-18 | Neturen Co., Ltd. | Method for manufacturing rack bar |
US11072360B2 (en) | 2016-07-06 | 2021-07-27 | Thyssenkrupp Presta Ag | Gear rack and method for producing a gear rack for a steering gear of a motor vehicle |
US20210229224A1 (en) * | 2020-01-27 | 2021-07-29 | Benteler Automobiltechnik Gmbh | Suspension strut fork and method for producing a suspension strut fork |
US11077875B2 (en) | 2016-07-06 | 2021-08-03 | Thyssenkrupp Presta Ag | Rack and a method for producing a rack for a steering gear of a motor vehicle |
US11247263B2 (en) * | 2017-03-16 | 2022-02-15 | Neturen Co., Ltd. | Method for manufacturing rack bar |
US11298765B2 (en) | 2016-07-06 | 2022-04-12 | Thyssenkrupp Presta Ag | Toothed rack and method for producing a toothed rack for a steering gear of a motor vehicle |
CN116787085A (en) * | 2023-07-21 | 2023-09-22 | 东风襄阳旋压技术有限公司 | Semi-hollow motor shaft and forming process and device thereof |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9670951B2 (en) | 2014-04-08 | 2017-06-06 | A.A.M International S.A.R.L. | Variable-wall light-weight axle shaft with an integral flange member and method for making the same |
US9400009B2 (en) * | 2014-04-08 | 2016-07-26 | U.S. Manufacturing Corporation | Method for forming a variable wall light weight axle shaft with friction welded flange |
US9630451B2 (en) | 2014-06-18 | 2017-04-25 | American Axle & Manufacturing, Inc. | Method of manufacturing hollow axle shaft for a vehicle |
DE102021201652A1 (en) | 2021-02-22 | 2022-08-25 | Thyssenkrupp Ag | Method for manufacturing a rack for a motor vehicle steering gear, rack for a motor vehicle steering gear and steering gear for a motor vehicle |
Family Cites Families (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2529983A1 (en) * | 1982-07-09 | 1984-01-13 | Vallourec | STEERING RACK FOR MOTOR VEHICLES |
US5241848A (en) * | 1990-07-09 | 1993-09-07 | Simon Joseph A | Light weight drive shaft |
JPH115138A (en) * | 1997-06-16 | 1999-01-12 | Tube Forming:Kk | Making of rack bar |
DE10049548B4 (en) * | 1999-10-06 | 2007-03-22 | Honda Giken Kogyo K.K. | Electric power steering device |
JP3547378B2 (en) * | 2000-08-28 | 2004-07-28 | 株式会社幸伸技研 | Hollow rack bar tooth form rolling jig |
JP3607205B2 (en) * | 2000-02-14 | 2005-01-05 | 株式会社幸伸技研 | Hollow rack bar manufacturing method and hollow rack bar |
JP3607204B2 (en) * | 2000-02-14 | 2005-01-05 | 株式会社幸伸技研 | Linear drive type rolling machine |
JP4504127B2 (en) * | 2004-07-20 | 2010-07-14 | 松岡 美奈子 | Hollow rack bar manufacturing equipment |
-
2007
- 2007-03-15 US US11/686,705 patent/US20070204668A1/en not_active Abandoned
- 2007-03-21 EP EP07005750A patent/EP1839772A1/en not_active Withdrawn
Cited By (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20140020228A1 (en) * | 2012-07-17 | 2014-01-23 | Benteler Automobiltechnik Gmbh | Method for producing a tubular stabilizer for a motor vehicle |
CN107405675A (en) * | 2015-03-10 | 2017-11-28 | 新日铁住金不锈钢株式会社 | Pipe thickens forming method and thickens pipe |
US10603712B2 (en) | 2015-03-10 | 2020-03-31 | Nippon Steel & Sumkin Stainless Steel Corporation | Method of increasing thickness of tube and increased thickness tube |
US20180031104A1 (en) * | 2015-03-23 | 2018-02-01 | Neturen Co., Ltd. | Rack bar and method for manufacturing rack bar |
US10562138B2 (en) | 2015-11-04 | 2020-02-18 | Neturen Co., Ltd. | Method for manufacturing rack bar |
US10919107B2 (en) * | 2016-07-06 | 2021-02-16 | Thyssenkrupp Presta Ag | Rack and method for producing a rack for a steering gear of a motor vehicle |
US20190247951A1 (en) * | 2016-07-06 | 2019-08-15 | Thyssenkrupp Presta Ag | Rack and method for producing a rack for a steering gear of a motor vehicle |
US11072360B2 (en) | 2016-07-06 | 2021-07-27 | Thyssenkrupp Presta Ag | Gear rack and method for producing a gear rack for a steering gear of a motor vehicle |
US11077875B2 (en) | 2016-07-06 | 2021-08-03 | Thyssenkrupp Presta Ag | Rack and a method for producing a rack for a steering gear of a motor vehicle |
US11298765B2 (en) | 2016-07-06 | 2022-04-12 | Thyssenkrupp Presta Ag | Toothed rack and method for producing a toothed rack for a steering gear of a motor vehicle |
US11247263B2 (en) * | 2017-03-16 | 2022-02-15 | Neturen Co., Ltd. | Method for manufacturing rack bar |
CN111372701A (en) * | 2017-11-21 | 2020-07-03 | 高周波热錬株式会社 | Method for manufacturing hollow rack bar and device for manufacturing hollow rack bar |
WO2019102927A1 (en) * | 2017-11-21 | 2019-05-31 | Neturen Co., Ltd. | Manufacturing method for hollow rack bar and hollow rack bar manufacturing apparatus |
US11980929B2 (en) | 2017-11-21 | 2024-05-14 | Neturen Co., Ltd. | Manufacturing method for hollow rack bar and hollow rack bar manufacturing apparatus |
US20210229224A1 (en) * | 2020-01-27 | 2021-07-29 | Benteler Automobiltechnik Gmbh | Suspension strut fork and method for producing a suspension strut fork |
US11738417B2 (en) * | 2020-01-27 | 2023-08-29 | Benteler Automobiltechnik Gmbh | Suspension strut fork and method for producing a suspension strut fork |
CN116787085A (en) * | 2023-07-21 | 2023-09-22 | 东风襄阳旋压技术有限公司 | Semi-hollow motor shaft and forming process and device thereof |
Also Published As
Publication number | Publication date |
---|---|
EP1839772A1 (en) | 2007-10-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20070204668A1 (en) | Method and apparatus for plastic working of hollow rack bar and hollow rack bar | |
US7168284B2 (en) | Method and apparatus for producing hollow rack bar and mandrel used for rack bar production | |
DE102008036226B4 (en) | Method for producing a hollow shaft | |
CN100554712C (en) | Manufacturing is used for the equipment of outer ring member of constant velocity joint and the middle formed body of method and outer ring member | |
KR20070094448A (en) | Method and apparatus for plastic working of hollow rack and hollow rack | |
EP1524044B1 (en) | Method for producing hollow rack bar | |
CN104741875A (en) | Processing process of axle shaft sleeve | |
US20080115552A1 (en) | Method of plastically forming splines on shaft-like workpiece | |
EP3713690B1 (en) | Manufacturing method for hollow rack bar | |
CN101545440A (en) | Method for manufacturing swivel of actuating lever for motorcycle | |
CN102728757B (en) | Hammer forging device for forming complicated long-axis forgings applied to radial forging machine | |
US6735998B2 (en) | Method of making metal ball bats | |
JP5246588B2 (en) | Gear manufacturing apparatus and method | |
CN213496268U (en) | Cold header die and cold header | |
DE102005057945A1 (en) | Production of pipe sections and tubular workpieces formed with a protrusion in the cylindrical inner contour comprises deforming in only one clamp with only one counter roller spinning step | |
US3310822A (en) | Method and apparatus for making socket head screws | |
CN109415081A (en) | The method of the rack gear of rack gear and the transfer for producing motor vehicles | |
CN108015146A (en) | A kind of tension force ball spinning method | |
CN207195485U (en) | New-energy automobile slidably engages set and its back extrusion concave | |
CN104226703B (en) | A kind of method making automotive pull rod joint | |
US11850655B2 (en) | Process and device for manufacturing hollow, internally cooled valves | |
KR102410811B1 (en) | A manufacturing method for input shaft | |
EP1769859B1 (en) | Method and apparatus for producing hollow rack bar | |
CN113059330B (en) | Integrated forming method for large-diameter shell | |
RU2591824C1 (en) | Method for producing a barrel |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
AS | Assignment |
Owner name: MATSUOKA, MINAKO, JAPAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SHIOKAWA, SEIJI;REEL/FRAME:019020/0705 Effective date: 20070303 Owner name: SHIOKAWA, AKIMASA, JAPAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SHIOKAWA, SEIJI;REEL/FRAME:019020/0705 Effective date: 20070303 Owner name: SHIOKAWA, HIROHISA, JAPAN Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:SHIOKAWA, SEIJI;REEL/FRAME:019020/0705 Effective date: 20070303 |
|
STCB | Information on status: application discontinuation |
Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION |