KR101723515B1 - A structure for strengthening masonry and reinforcing method of masonry buildings using the same - Google Patents

A structure for strengthening masonry and reinforcing method of masonry buildings using the same Download PDF

Info

Publication number
KR101723515B1
KR101723515B1 KR1020160119722A KR20160119722A KR101723515B1 KR 101723515 B1 KR101723515 B1 KR 101723515B1 KR 1020160119722 A KR1020160119722 A KR 1020160119722A KR 20160119722 A KR20160119722 A KR 20160119722A KR 101723515 B1 KR101723515 B1 KR 101723515B1
Authority
KR
South Korea
Prior art keywords
masonry
masonry building
plate
building
plate foam
Prior art date
Application number
KR1020160119722A
Other languages
Korean (ko)
Inventor
박춘욱
홍원화
최정택
Original Assignee
경북대학교 산학협력단
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 경북대학교 산학협력단 filed Critical 경북대학교 산학협력단
Priority to KR1020160119722A priority Critical patent/KR101723515B1/en
Application granted granted Critical
Publication of KR101723515B1 publication Critical patent/KR101723515B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/027Preventive constructional measures against earthquake damage in existing buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Emergency Management (AREA)
  • Business, Economics & Management (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Electrochemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Chemical & Material Sciences (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to a masonry reinforcing structure to reinforce masonry buildings. The masonry reinforcing structure comprises: a plate form installed in both wall surfaces of a masonry building, including a convex portion forming a filling space together with wall surfaces of a masonry building, and an attachment portion attached to the wall surfaces of the masonry building by an adhesive; a filler filled in a filling space; a filling space wherein a pair of plate forms installed in both the wall surfaces of the masonry building are facing each other; and a fixing member penetrating the masonry building to fixate the plate forms to the masonry building.

Description

조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법 {A STRUCTURE FOR STRENGTHENING MASONRY AND REINFORCING METHOD OF MASONRY BUILDINGS USING THE SAME}TECHNICAL FIELD [0001] The present invention relates to a masonry reinforcing structure and a masonry building reinforcing method using the masonry reinforcing structure.

본 발명은 조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법에 관한 것으로서, 보다 구체적으로는 조적조 건축물의 최대 내력 및 연성을 향상시키고 면외 방향 변형에도 효과적으로 조적조 건축물을 보강할 수 있는 조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법에 관한 것이다.The present invention relates to a masonry reinforcing structure and a masonry building reinforcing method using the masonry building, and more particularly, to a masonry reinforcing structure capable of enhancing maximum strength and ductility of a masonry building and effectively reinforcing the masonry building, And a method of reinforcing a building.

조적조 건축물의 경우 벽돌, 블록, 돌 등의 조적개체를 접착제와 같은 역할을 하는 모르타르(시멘트+모래+물)로 쌓아올리는 구조이다. 조적조 건축물의 장점으로는 짧은 공사 기간과 저렴한 공사비를 들 수 있으며, 또한 장중한 외관과 높은 내화성능 및 내구성능 등을 들 수 있다. 그러나, 이러한 장점과는 달리 보강이 이루어지지 않은 조적조 건축물의 경우 위에서부터 내려오는 힘(수직력)에는 상대적으로 강한 능력을 발휘하지만, 지진과 같이 옆에서 작용하는 힘에 대해서는 지지능력이 현저히 저하되는 것이 사실이다. 즉, 조적조 건축물의 경우 지진과 같이 옆에서 오는 힘에는 접착제의 역할을 하는 모르타르만으로 저항하기 때문에 일종의 무방비 상태이다. In the case of masonry buildings, masonry (cement + sand + water) is used to build up masonry objects such as bricks, blocks and stones. Advantages of the masonry building include short construction period and low construction cost, and also the excellent appearance, high fire resistance performance and durability performance. However, unlike the above advantages, the masonry buildings that are not reinforced have a relatively strong ability to descend from above (vertical force), but the supporting ability to the side acting force such as an earthquake is considerably deteriorated It is true. In other words, in the case of masonry buildings, the forces coming from the sides, such as earthquakes, are a kind of defenseless because they are resisted only by the mortar which acts as an adhesive.

더구나 조적조 건축물은 다른 구조형식과 달리 조적벽체가 면내 방향으로 작용하는 지진력에 대해서는 일정부분 저항능력을 가지는 반면에, 면외 방향으로 작용하는 지진력에 대해서는 거의 저항하지 못하기 때문에 면외 방향 파괴가 많이 발생한다. 또한, 면내 방향 지진력에 대한 조적벽체의 파괴모드는 축력, 벽체 형상비(벽체 길이에 대한 높이의 비) 등에 따라 달라지며, 특히 국내 조적조 건축물의 경우 형상비 1 미만의 벽체의 분포가 높은 상황으로 이렇게 형상비가 작은 벽체의 경우 미끄러짐 파괴가 발생할 가능성이 높기 때문에 내진 보강시 이에 대한 고려가 필요하다. Furthermore, unlike other structural types, masonry buildings have some resistance to seismic forces acting in the in-plane direction of the masonry wall, whereas they have little resistance to seismic forces acting in the out-of-plane direction. In addition, the mode of failure of the masonry wall in relation to the in-plane directional seismic force depends on the axial force, wall aspect ratio (ratio of height to wall length), and especially in domestic masonry buildings, In case of a small wall, slip failure is more likely to occur, so consideration should be given to the seismic reinforcement.

그러나, 종래의 조적조 건축물에 대한 보강 공법(등록특허 제10-0922386호 참조)은 면외 방향으로 작용하는 지진력에 효과적으로 대응하지 못하고, 또한 형상비가 작은 벽체에 대한 내진 보강에 대한 고려가 없다는 문제가 있어왔다.However, the conventional reinforcement method for masonry building (refer to Japanese Patent No. 10-0922386) does not effectively cope with the seismic force acting in the out-of-plane direction and there is no consideration of seismic reinforcement for the wall having a small aspect ratio come.

이러한 문제점을 해결하기 위하여, 비보강 조적조 건축물의 최대 내력 및 연성을 향상시키고 면외 방향 변형에도 효과적인 조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법의 필요성이 대두되고 있다.In order to solve these problems, there is a need for a masonry reinforcing structure that is effective for improving the maximum strength and ductility of a non-reinforced masonry building and is also effective in an out-of-plane direction deformation and a masonry building reinforcing method using the same.

본 발명이 해결하려는 과제는, 조적조 건축물을 변형시키지 않고서도 조적조 건축물의 최대 내력 및 연성을 향상시키고 면외 방향 변형에도 효과적인 조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법을 제공하는 데 있다.SUMMARY OF THE INVENTION It is an object of the present invention to provide a masonry reinforcing structure which is effective for improving maximum strength and ductility of a masonry building without deforming the masonry building and is also effective in an out-of-plane direction deformation and a masonry building reinforcing method using the same.

본 발명이 해결하려는 과제들은 이상에서 언급한 과제들로 제한되지 않으며, 언급되지 않은 또 다른 과제들은 아래의 기재로부터 당업자에게 명확하게 이해될 수 있을 것이다.The problems to be solved by the present invention are not limited to the above-mentioned problems, and other matters not mentioned can be clearly understood by those skilled in the art from the following description.

상기 과제를 해결하기 위한 본 발명의 일 실시예에 따른 조적조 보강 구조물은, 조적조 건축물을 보강하기 위한 조적조 보강 구조물로서, 볼록 부분 및 부착 부분을 포함하는 플레이트 폼으로서, 볼록 부분은 조적조 건축물의 벽면과 함께 충진 공간을 형성하고, 부착 부분은 접착제를 통해 조적조 건축물의 벽면에 부착되고, 조적조 건축물의 양 벽면에 설치되는 것인 플레이트 폼, 충진 공간에 충진되는 충진재 및 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 조적조 건축물을 관통하면서 한 쌍의 플레이트 폼을 조적조 건축물에 대하여 고정시키기 위한 고정 부재를 포함한다. According to an aspect of the present invention, there is provided a masonry reinforcement structure for reinforcing a masonry building, the masonry reinforcement structure including a convex portion and an attachment portion, wherein the convex portion is a wall surface of the masonry building A plate foam which is attached to the wall surface of the masonry building through an adhesive and which is installed on both wall surfaces of the masonry building, a filling material which is filled in the filling space and a masonry building which is installed on both walls of the masonry building And a fixing member for fixing the pair of plate foams to the masonry building while penetrating the masonry building and opposing filling spaces of the pair of plate foam.

상기 과제를 해결하기 위한 본 발명의 일 실시예에 따른 조적조 건축물 보강 공법은, 조적조 건축물의 벽면에 고정 부재를 관통시키기 위한 구멍을 천공하는 단계, 플레이트 폼의 부착 부분 및 부착 부분이 부착될 조적조 건축물의 벽면 부분에 접착제를 도포하는 단계, 플레이트 폼을 조적조 건축물의 양 벽면에 부착한 후에, 고정 부재를 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 조적조 건축물의 천공된 구멍에 관통시키면서 한 쌍의 플레이트 폼을 조적조 건축물에 대하여 고정시키는 단계 및 충진 공간을 충진재로 충진하는 단계를 포함를 포함한다.According to an aspect of the present invention, there is provided a method of reinforcing a masonry building, the method comprising: drilling a hole for passing a fixing member through a wall surface of a masonry building; attaching a plate foam and a masonry building After the plate form is attached to both wall surfaces of the masonry structure, the fixing member is moved to the opposite filling space of the pair of plate forms provided on both wall surfaces of the masonry structure and the punched space of the masonry structure Fixing the pair of plate foams to the masonry structure while penetrating the holes, and filling the filling space with the filler material.

상기 과제를 해결하기 위한 본 발명의 일 실시예에 따른 앵글형 하이브리드 빔 보강재의 시공 방법은, 철근 콘크리트 보 및 앵글형 하이브리드 빔 보강재에 접착제를 도포하고 철근 콘크리트 보와 앵글형 하이브리드 빔 보강재를 접합하는 단계 및 타정 공구의 정착핀을 이용하여 앵글형 하이브리드 빔 보강재를 철근 콘트리트 보에 고정하는 단계를 포함한다.According to an aspect of the present invention, there is provided a method of manufacturing an angle type hybrid beam stiffener, the method comprising: applying an adhesive to a reinforced concrete beam and an angle type hybrid beam reinforcement; bonding a reinforced concrete beam and an angle type hybrid beam reinforcement to each other; And fixing the angled hybrid beam stiffener to the reinforcing concrete beam using the fusing pin of the tool.

본 발명에 따르면, 조적조 건축물을 변형시키지 않고서도 조적조 건축물의 최대 내력 및 연성을 향상시키고 면외 방향 변형에도 효과적인 조적조 보강 구조물 및 이를 이용한 조적조 건축물 보강 공법을 제공할 수 있다.According to the present invention, it is possible to provide a masonry building reinforcing structure that is effective for improving the maximum strength and ductility of masonry building without deforming the masonry building, and is also effective in the out-of-plane direction deformation, and a masonry building reinforcing method using the same.

도 1 은 본 발명의 일 실시예에 따른 조적조 보강 구조물의 사시도이다.
도 2 는 본 발명의 일 실시예에 따른 조적조 보강 구조물의 평면도이다.
도 3 은 본 발명의 일 실시예에 따른 조적조 보강 구조물을 조적조 건축물에 설치한 상태를 나타낸 평면도이다.
도 4 는 도 3 의 A-A' 단면도이다.
도 5 는 본 발명의 일 실시예에 따른 조적조 건축물 보강 공법의 흐름도이다.
1 is a perspective view of a masonry reinforcement structure according to an embodiment of the present invention.
2 is a plan view of a masonry reinforcing structure according to an embodiment of the present invention.
FIG. 3 is a plan view showing a state in which a masonry reinforcing structure according to an embodiment of the present invention is installed in a masonry building.
4 is a cross-sectional view taken along line AA 'of FIG.
5 is a flowchart of a masonry building reinforcement method according to an embodiment of the present invention.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다. 그러나 본 발명은 이하에서 개시되는 실시예들에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 것이며, 단지 본 실시예들은 본 발명의 개시가 완전하도록 하며, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다. 명세서 전체에 걸쳐 동일 참조 부호는 동일 구성 요소를 지칭한다.BRIEF DESCRIPTION OF THE DRAWINGS The advantages and features of the present invention and the manner of achieving them will become apparent with reference to the embodiments described in detail below with reference to the accompanying drawings. The present invention may, however, be embodied in many different forms and should not be construed as being limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. Is provided to fully convey the scope of the invention to those skilled in the art, and the invention is only defined by the scope of the claims. Like reference numerals refer to like elements throughout the specification.

본 명세서에서 사용된 용어는 실시예들을 설명하기 위한 것이며 본 발명을 제한하고자 하는 것은 아니다. 본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 "포함한다(comprises)" 및/또는 "포함하는(comprising)"은 언급된 구성요소, 단계 및 동작은 하나 이상의 다른 구성요소, 단계 및 동작의 존재 또는 추가를 배제하지 않는다.The terminology used herein is for the purpose of illustrating embodiments and is not intended to be limiting of the present invention. In the present specification, the singular form includes plural forms unless otherwise specified in the specification. It is noted that the terms " comprises "and / or" comprising ", as used herein, do not exclude the presence or addition of one or more other elements, steps and operations.

도 1 내지 4 를 참조하여, 본 발명의 일 실시예에 따른 조적조 보강 구조물을 설명한다. 도 1 은 본 발명의 일 실시예에 따른 조적조 보강 구조물의 사시도이다. 도 2 는 본 발명의 일 실시예에 따른 조적조 보강 구조물의 평면도이다. 도 3 은 본 발명의 일 실시예에 따른 조적조 보강 구조물을 조적조 건축물에 설치한 상태를 나타낸 평면도이다. 도 4 는 도 3 의 A-A' 단면도이다. 1 to 4, a masonry reinforcing structure according to an embodiment of the present invention will be described. 1 is a perspective view of a masonry reinforcement structure according to an embodiment of the present invention. 2 is a plan view of a masonry reinforcing structure according to an embodiment of the present invention. FIG. 3 is a plan view showing a state in which a masonry reinforcing structure according to an embodiment of the present invention is installed in a masonry building. 4 is a cross-sectional view along the line A-A 'in Fig.

도 1 내지 4 를 참조하면, 본 발명의 일 실시예에 따른 조적조 보강 구조물은 플레이트 폼(form)(30), 충진재 및 고정 부재를 포함한다.Referring to FIGS. 1 to 4, a masonry reinforcing structure according to an embodiment of the present invention includes a plate 30, a filler, and a fixing member.

플레이트 폼(30)은 본 발명의 일 실시예에 따른 조적조 보강 구조물의 뼈대를 구성하는 부재이다. 플레이트 폼(30)은 조적조 건축물(60)의 벽면에 부착이 용이하도록 전체적으로 판 형상일 수 있고, 이 판 형상의 플레이트 폼(30)에 볼록 부분(10)과 부착 부분(20)이 교대로 형성될 수 있다. 볼록 부분(10)은 플레이트 폼(30)이 조적조 건축물(60)의 벽면에 부착되었을 때 조적조 건축물(60)의 반대 방향으로 돌출된 부분으로서 플레이트 폼(30)의 수직 방향(또는 상하 방향)을 따라 형성될 수 있고, 부착 부분(20)은 돌출이 되지 않은 부분으로서 인접한 볼록 부분(10) 사이에 형성될 수 있다.The plate foam 30 is a member constituting the framework of the masonry reinforcing structure according to an embodiment of the present invention. The plate foam 30 may be entirely plate-shaped so as to be easily attached to the wall surface of the masonry building 60 and the convex portion 10 and the attaching portion 20 are formed alternately in the plate- . The convex portion 10 is a portion protruding in the opposite direction of the masonry building 60 when the plate foam 30 is attached to the wall surface of the masonry building 60 and the vertical direction And the attachment portion 20 can be formed between the adjacent convex portions 10 as a non-protruded portion.

또한, 플레이트 폼(30)이 조적조 건축물(60)의 벽면에 부착되었을 때 볼록 부분(10)은 조적조 건축물(60)의 벽면과 함께 충진 공간(40)을 형성하고, 부착 부분(20)은 접착제를 통해 조적조 건축물(60)의 벽면에 부착되어 플레이트 폼(30)이 조적조 건축물(60)에 부착되도록 한다. 플레이트 폼(30)을 조적조 건축물(60)에 부착하기 위해 사용되는 접착제로는 에폭시 퍼티가 이용될 수 있으며, 에폭시 퍼티를 부착 부분(20) 및 부착 부분(20)이 부착될 조적조 건축물(60)의 벽면 부분에 도포한 후 부착 부분(20)을 조적조 건축물(60)의 벽면에 부착할 수 있다.The convex portion 10 forms the filling space 40 together with the wall surface of the masonry building 60 when the plate foam 30 is attached to the wall surface of the masonry building 60, To the wall surface of the masonry building 60 so that the plate foam 30 is attached to the masonry building 60. An epoxy putty may be used as an adhesive used to attach the plate foam 30 to the masonry structure 60 and the epoxy putty may be applied to the masonry building 60 to which the attachment portion 20 and the attachment portion 20 are to be attached, The attachment portion 20 can be attached to the wall surface of the masonry building 60. [

아울러, 플레이트 폼(30)은 조적조 건축물(60)의 양 벽면에 설치되는 바 한 쌍의 플레이트 폼(30)이 조적조 보강 구조물을 구성한다.In addition, the plate foam 30 is installed on both wall surfaces of the masonry building 60, and a pair of plate forms 30 constitute the masonry reinforcing structure.

이러한 플레이트 폼(30)은 유리 섬유 재질의 하이브리드 플레이트 폼(30)일 수 있다. 이렇게 부식이 발생될 염려가 전혀 없는 유리 섬유를 하이브리드 플레이트 폼(30)의 재료로 활용함으로써 영구적으로 기존 조적조 건축물(60)과 수명을 같이 할 수 있다.Such plate foam 30 may be a hybrid plate foam 30 of glass fiber material. By using the glass fiber having no fear of corrosion as the material of the hybrid plate foam 30, it is possible to permanently match the life of the existing masonry building 60.

충진재는 플레이트 폼(30)의 볼록 부분(10)과 조적조 건축물(60)의 벽면이 함께 형성하는 충진 공간(40)에 충진되는 물질로서, 본 발명의 경우에는 에폭시(80)가 이용될 수 있다. 즉, 충진 공간(40)을 형성하는 본 발명에 따른 플레이트 폼(30)은 영구적인 거푸집 역할을 할 수 있다. The filling material is filled in the filling space 40 formed by the convex portion 10 of the plate foam 30 and the wall surface of the masonry building 60. In the present invention, the epoxy 80 can be used . That is, the plate foam 30 according to the present invention forming the filling space 40 can serve as a permanent mold.

고정 부재는 플레이트 폼(30)을 조적조 건축물(60)에 대하여 고정시키기 위한 부재로서, 본 발명의 경우에는 앵커 볼트(50)가 사용될 수 있으나 이에 제한되는 것은 아니다. 앵커 볼트(50)의 체결을 위해 조적조 건축물(60)의 벽면에는 구멍, 즉 앵커홀이 형성되고, 앵커 볼트(50)는 조적조 건축물(60)의 양 벽면에 설치되는 한 쌍의 플레이트 폼(30)의 마주보는 충진 공간(40) 및 조적조 건축물(60)의 앵커홀을 관통하면서 한 쌍의 플레이트 폼(30)을 조적조 건축물(60)에 대하여 고정시킬 수 있다.The fixing member is a member for fixing the plate foam 30 to the masonry building 60. In the present invention, the anchor bolt 50 may be used, but is not limited thereto. Anchor holes are formed in the wall surface of the masonry building 60 for fastening the anchor bolts 50 and the anchor bolts 50 are mounted on the pair of plate foams 30 A pair of plate foams 30 can be fixed to the masonry building 60 while passing through the anchor holes of the masonry building 60 and the facing filling space 40 of the masonry building 60.

위에서 살펴본 바와 같이, 조적조 건축물(60)을 철거하지 않고서 조적조 건축물(60)의 양 벽면에 유리 섬유 재질의 하이브리드 플레이트로 형성된 폼을 부착하고, 플레이트 폼(30)의 볼록 부분(10)을 지나가는 앵커 볼트(50)를 이용하여 플레이트 폼(30)을 조적조 건축물(60)에 고정한다. 또한, 영구적인 거푸집으로 사용되는 플레이트 폼(30)의 충진 공간(40)에 에폭시(80)를 충진하고, 플레이트 폼(30)의 부착 부분(20)을 에폭시 퍼티로 조적조 건축물(60)의 벽면에 접착하여 플레이트 폼(30)을 조적조 건축물(60)의 벽면과 같이 거동되게 함으로써 조적조 건축물(60)을 전단벽식으로 변환하여 내력 및 연성을 향상시키고 면외 방향 탈락을 방지할 수 있다.A foam formed of a glass fiber hybrid plate is attached to both wall surfaces of the masonry building 60 without removing the masonry building 60 and the anchor passing through the convex portion 10 of the plate foam 30, And the plate foam 30 is fixed to the masonry building 60 by using the bolts 50. The filling space 40 of the plate foam 30 used as a permanent mold is filled with the epoxy 80 and the attachment portion 20 of the plate foam 30 is put into the wall surface of the masonry building 60 with the epoxy putty. So that the plate form 30 is made to behave like a wall surface of the masonry building 60, thereby converting the masonry building 60 into a front-end wall type to improve the proof and ductility, and prevent the masonry structure 60 from falling off.

이상 본 발명의 일 실시예에 따른 조적조 보강 구조물을 설명하였으며, 이하 도 5 를 참조하여 본 발명의 일 실시예에 따른 조적조 건축물 보강 공법을 설명한다. 도 5 는 본 발명의 일 실시예에 따른 조적조 건축물 보강 공법의 흐름도이다.Hereinafter, a masonry building reinforcing structure according to an embodiment of the present invention will be described. Referring to FIG. 5, a masonry building reinforcing method according to an embodiment of the present invention will be described. 5 is a flowchart of a masonry building reinforcement method according to an embodiment of the present invention.

도 5 를 참조하면, 본 발명의 일 실시예에 따른 조적조 건축물 보강 공법은, 조적조 건축물의 벽면에 고정 부재를 관통시키기 위한 구멍을 천공하는 단계(S110), 플레이트 폼의 부착 부분 및 부착 부분이 부착될 조적조 건축물의 벽면 부분에 접착제를 도포하는 단계(S130), 플레이트 폼을 조적조 건축물의 양 벽면에 부착한 후에, 고정 부재를 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 조적조 건축물의 천공된 구멍에 관통시키면서 한 쌍의 플레이트 폼을 조적조 건축물에 대하여 고정시키는 단계(S150) 및 충진 공간을 충진재로 충진하는 단계(S170)를 포함한다.Referring to FIG. 5, the method of reinforcing a masonry building according to an embodiment of the present invention includes the steps of (S110) drilling a hole for passing a fixing member through a wall surface of a masonry building, (S130). After the plate foam is attached to both wall surfaces of the masonry building, the fixing member is moved to the opposite filling spaces of the pair of plate forms, which are installed on both wall surfaces of the masonry building And fixing the pair of plate forms to the masonry structure while passing through the perforated holes of the masonry building (S150) and filling the filling space with the filling material (S170).

조적조 건축물의 벽면에 고정 부재를 관통시키기 위한 구멍을 천공하는 단계(S110)는, 본 발명의 경우 고정 부재로 앵커 볼트(50)를 이용할 수 있고, 앵커 볼트(50)로 플레이트 폼(30)을 조적조 건축물(60)의 벽면에 고정시키기 위해서 조적조 건축물(60)의 벽면에 구멍, 즉 앵커홀을 천공하게 된다.The step S110 of drilling a hole for penetrating the fixing member to the wall surface of the masonry building can be performed by using the anchor bolt 50 as the fixing member in the case of the present invention and by using the anchor bolt 50 as the plate foam 30 Holes, i.e., anchor holes, are drilled in the wall surface of the masonry building 60 for fixing the masonry building 60 to the wall surface thereof.

플레이트 폼의 부착 부분 및 부착 부분이 부착될 조적조 건축물의 벽면 부분에 접착제를 도포하는 단계(S130)는, 앵커 볼트(50)를 사용하여 플레이트 폼(30)을 조적조 건축물(60)의 벽면에 고정하기 전에, 플레이트 폼(30)을 조적조 건축물(60)에 부착하게 되는데, 이때 플레이트 폼(30)의 부착 부분(20) 및 부착 부분(20)이 부착될 조적조 건축물(60)의 벽면 부분에 접착제를 도포하고, 접착제로는 에폭시 퍼티가 사용될 수 있다.The step S130 of applying the adhesive to the wall surface portion of the masonry building to which the attachment portion and the attachment portion of the plate foam are to be attached is performed by using the anchor bolt 50 to fix the plate foam 30 to the wall surface of the masonry building 60 The plate foam 30 is attached to the masonry building 60 by attaching an adhesive agent 20 to the wall surface portion of the masonry building 60 to which the attachment portion 20 and the attachment portion 20 of the plate foam 30 are to be attached, And an epoxy putty may be used as the adhesive.

플레이트 폼을 조적조 건축물의 양 벽면에 부착한 후에, 고정 부재를 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 조적조 건축물의 천공된 구멍에 관통시키면서 한 쌍의 플레이트 폼을 조적조 건축물에 대하여 고정시키는 단계(S150)는, 우선 플레이트 폼(30)의 부착 부분(20) 및 부착 부분(20)이 부착될 조적조 건축물(60)의 벽면 부분에 접착제를 도포하고 한 쌍의 플레이트 폼(30)을 조적조 건축물(60)의 양 벽면에 부착한다. 이후, 조적조 건축물(60)의 양 벽면에 설치되는 한 쌍의 플레이트 폼(30)의 마주보는 충진 공간(40) 및 조적조 건축물(60)의 천공된 구멍에 고정 부재인 앵커 볼트(50)를 관통시키면서 한 쌍의 플레이트 폼(30)을 조적조 건축물(60)에 대하여 고정시킨다.After the plate foams are attached to both wall surfaces of the masonry building, the fixing members are passed through the perforated holes of the masonry building and the facing filling spaces of a pair of plate mounters installed on both wall surfaces of the masonry building, The step of fixing the masonry building S150 includes first applying an adhesive to the wall portion of the masonry building 60 to which the attachment portion 20 of the plate foam 30 and the attachment portion 20 are to be attached, The foam 30 is attached to both wall surfaces of the masonry building 60. Thereafter, an opposing filling space 40 of a pair of plate forms 30 provided on both wall surfaces of the masonry building 60 and an anchor bolt 50, which is a fixing member, are passed through the perforated holes of the masonry building 60 Thereby fixing a pair of plate foams 30 to the masonry building 60.

충진 공간을 충진재로 충진하는 단계(S170)는, 조적조 건축물(60)에 플레이트 폼(30)을 부착 및 고정시킨 후에 충진 공간(40)에 충진재인 에폭시(80)를 충진하게 된다.In step S170 of filling the filling space with the filling material, the plate foam 30 is attached and fixed to the masonry building 60 and then the filling space 40 is filled with the epoxy 80 as the filling material.

한편, 조적조 건축물(60)의 벽면에 구멍을 천공하는 단계 이전에, 조적조 건축물(60)의 벽면의 마감을 제거하고 조적조 건축물(60)의 벽면을 그라인딩하여 조적조 건축물(60)의 벽면을 정리하는 전처리 단계가 수행될 수 있다. 또한, 충진 공간(40)을 충진재로 충진하는 단계 이후에, 조적조 보강 구조물, 특히 플레이트 폼(30)의 면에 대하여 마감 처리하는 후처리 단계가 수행될 수 있다.On the other hand, prior to the step of drilling a hole in the wall surface of the masonry building 60, the wall surface of the masonry building 60 is removed, and the wall surface of the masonry building 60 is ground to clean the wall surface of the masonry building 60 A preprocessing step can be performed. Further, after filling the filling space 40 with the filling material, a post-treatment step of finishing the surface of the masonry reinforcing structure, particularly the plate foam 30, may be performed.

본 발명에 따른 조적조 건축물 보강 공법은 최대 내력, 연성, 에너지 흡수 능력의 측면에서 비보강 조적조 건축물에 비해서 우수하고, 조적조 건축물의 지진, 풍하중 등 수평력 보강에 매우 효과적인 공법이다. 또한, 형상비가 작아 미끄러짐 파괴가 일어나기 쉬운 조적조 건축물의 내력을 향상시킬 수 있다. 아울러, 조적조 건축물의 벽체 하부를 기초나 슬래브에 고정할 경우 보강 효과는 더욱 커질 수 있다.The masonry building reinforcing method according to the present invention is superior to the non-reinforced masonry building in terms of maximum strength, ductility and energy absorption capacity, and is a very effective method for reinforcing horizontal force such as earthquake and wind load of masonry building. Further, the proof ratio of the masonry building, which is susceptible to slip failure due to its small aspect ratio, can be improved. In addition, when the lower part of the wall of the masonry building is fixed to the foundation or the slab, the reinforcing effect can be further increased.

이상 첨부된 도면을 참조하여 본 발명의 실시예를 설명하였지만, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자는 본 발명이 그 기술적 사상이나 필수적인 특징을 변경하지 않고서 다른 구체적인 형태로 실시될 수 있다는 것을 이해할 수 있을 것이다. 그러므로 이상에서 기술한 실시예들은 모든 면에서 예시적인 것이며 한정적이 아닌 것으로 이해해야만 한다.While the present invention has been described in connection with what is presently considered to be practical exemplary embodiments, it is to be understood that the invention is not limited to the disclosed embodiments, but, on the contrary, You will understand. It is therefore to be understood that the above-described embodiments are illustrative in all aspects and not restrictive.

10: 볼록 부분 20: 부착 부분
30: 플레이트 폼 40: 충진 공간
50: 앵커 볼트 60: 조적조 건축물
80: 에폭시
10: convex portion 20: attachment portion
30: plate foam 40: filling space
50: Anchor bolt 60: masonry building
80: Epoxy

Claims (15)

조적조 건축물을 보강하기 위한 조적조 보강 구조물로서,
볼록 부분 및 부착 부분을 포함하는 플레이트 폼(form)으로서, 상기 볼록 부분은 상기 조적조 건축물의 벽면과 함께 충진 공간을 형성하고, 상기 부착 부분은 접착제를 통해 상기 조적조 건축물의 벽면에 부착되고, 상기 조적조 건축물의 양벽면에 설치되는 것인 플레이트 폼;
상기 충진 공간에 충진되는 충진재; 및
상기 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 상기 조적조 건축물을 관통하면서 상기 한 쌍의 플레이트 폼을 상기 조적조 건축물에 대하여 고정시키기 위한 고정 부재를 포함하되,
상기 조적조 건축물에는 앵커홀이 형성되고, 상기 고정 부재는 앵커 볼트로서 상기 플레이트 폼의 볼록 부분에 설치되며, 상기 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 상기 조적조 건축물의 앵커홀을 관통하면서 한 쌍의 플레이트 폼을 조적조 건축물에 대해 고정시키는 조적조 보강 구조물.
A masonry reinforcement structure for reinforcing a masonry building,
A plate form comprising a convex portion and an attachment portion, wherein the convex portion forms a filling space together with a wall surface of the masonry building, the attachment portion is attached to a wall surface of the masonry building through an adhesive, A plate foam disposed on both wall surfaces of the building;
A filling material filled in the filling space; And
And a fixing member for fixing the pair of plate foams to the masonry building while passing through the masonry building, wherein the pair of plate foams are provided on both wall surfaces of the masonry building,
The masonry building is provided with an anchor hole, the fixing member is provided as an anchor bolt on a convex portion of the plate foam, and a pair of plate foam provided on opposite wall surfaces of the masonry building, And a pair of plate forms are fixed to the mooring structure while passing through the anchor holes of the mooring structure of the mooring structure.
제 1 항에 있어서,
상기 볼록 부분은 상기 플레이트 폼의 수직 방향을 따라 형성된 조적조 보강 구조물.
The method according to claim 1,
Wherein the convex portion is formed along the vertical direction of the plate foam.
제 1 항에 있어서,
상기 플레이트 폼에 있어서 상기 볼록 부분과 상기 부착 부분은 교대로 형성된 조적조 보강 구조물.
The method according to claim 1,
Wherein the convex portion and the attachment portion are formed alternately in the plate foam.
제 1 항에 있어서,
상기 플레이트 폼은 유리 섬유 재질의 하이브리드 플레이트 폼인 조적조 보강 구조물.
The method according to claim 1,
Wherein the plate foam is a hybrid plate foam of glass fiber material.
제 1 항에 있어서,
상기 접착제는 에폭시 퍼티인 조적조 보강 구조물.
The method according to claim 1,
Wherein the adhesive is an epoxy putty.
제 1 항에 있어서,
상기 충진재는 에폭시인 조적조 보강 구조물.
The method according to claim 1,
Wherein the filler is an epoxy masonry reinforcement structure.
삭제delete 제 1 항에 기재된 조적조 보강 구조물을 이용한 조적조 건축물 보강 공법으로서,
조적조 건축물의 벽면에 고정 부재를 관통시키기 위한 구멍을 천공하는 단계;
플레이트 폼의 부착 부분 및 부착 부분이 부착될 조적조 건축물의 벽면 부분에 접착제를 도포하는 단계;
플레이트 폼을 조적조 건축물의 양 벽면에 부착한 후에, 고정 부재를 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 조적조 건축물의 천공된 구멍에 관통시키면서 한 쌍의 플레이트 폼을 조적조 건축물에 대하여 고정시키는 단계; 및
충진 공간을 충진재로 충진하는 단계를 포함하되,
상기 조적조 건축물에는 앵커홀이 형성되고, 상기 고정 부재는 앵커 볼트로서 상기 플레이트 폼의 볼록 부분에 설치되며, 상기 조적조 건축물의 양 벽면에 설치되는 한 쌍의 플레이트 폼의 마주보는 충진 공간 및 상기 조적조 건축물의 앵커홀을 관통하면서 한 쌍의 플레이트 폼을 조적조 건축물에 대해 고정시키는 조적조 건축물 보강 공법.
A method of reinforcing a masonry building using the masonry reinforcing structure according to claim 1,
Drilling a hole for penetrating the fixing member to the wall surface of the masonry building;
Applying an adhesive to a wall portion of the masonry structure to which the attachment portion and the attachment portion of the plate foam are to be attached;
After the plate foams are attached to both wall surfaces of the masonry building, the fixing members are passed through the perforated holes of the masonry building and the facing filling spaces of a pair of plate mounters installed on both wall surfaces of the masonry building, Fixing to the masonry building; And
Filling the filling space with a filler material,
The masonry building is provided with an anchor hole, the fixing member is provided as an anchor bolt on a convex portion of the plate foam, and a pair of plate foam provided on opposite wall surfaces of the masonry building, A method of reinforcing a masonry building through which a pair of plate forms are fixed to the masonry building while penetrating the anchor holes of the masonry building.
제 8 항에 있어서,
조적조 건축물의 벽면에 구멍을 천공하는 단계 이전에, 조적조 건축물의 벽면의 마감을 제거하고 조적조 건축물의 벽면을 그라인딩하는 단계를 더 포함하는 조적조 건축물 보강 공법.
9. The method of claim 8,
Further comprising the step of removing the finishing of the wall surface of the masonry building and grinding the wall surface of the masonry building prior to the step of perforating the wall of the masonry building.
제 8 항에 있어서,
충진 공간을 충진재로 충진하는 단계 이후에, 조적조 보강 구조물에 대하여 마감 처리를 하는 단계를 더 포함하는 조적조 건축물 보강 공법.
9. The method of claim 8,
Further comprising the step of finishing the mooring reinforcing structure after filling the filling space with the filler material.
삭제delete 제 8 항에 있어서,
상기 플레이트 폼은 유리 섬유 재질의 하이브리드 플레이트 폼인 조적조 건축물 보강 공법.
9. The method of claim 8,
Wherein the plate foam is a hybrid plate foam made of glass fiber material.
제 8 항에 있어서,
상기 충진재는 에폭시인 조적조 건축물 보강 공법.
9. The method of claim 8,
The filling material is an epoxy reinforced masonry building construction method.
제 8 항에 있어서,
상기 플레이트 폼은 유리 섬유 재질의 하이브리드 플레이트 폼인 조적조 건축물 보강 공법.
9. The method of claim 8,
Wherein the plate foam is a hybrid plate foam made of glass fiber material.
제 8 항에 있어서,
상기 접착제는 에폭시 퍼티인 조적조 건축물 보강 공법.
9. The method of claim 8,
The above adhesive is an epoxy putty method for reinforcing a masonry building structure.
KR1020160119722A 2016-09-20 2016-09-20 A structure for strengthening masonry and reinforcing method of masonry buildings using the same KR101723515B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020160119722A KR101723515B1 (en) 2016-09-20 2016-09-20 A structure for strengthening masonry and reinforcing method of masonry buildings using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020160119722A KR101723515B1 (en) 2016-09-20 2016-09-20 A structure for strengthening masonry and reinforcing method of masonry buildings using the same

Publications (1)

Publication Number Publication Date
KR101723515B1 true KR101723515B1 (en) 2017-04-06

Family

ID=58583927

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020160119722A KR101723515B1 (en) 2016-09-20 2016-09-20 A structure for strengthening masonry and reinforcing method of masonry buildings using the same

Country Status (1)

Country Link
KR (1) KR101723515B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200142352A (en) * 2019-06-12 2020-12-22 신성한 Anti-seismic reinforcing structure for preventing collapse of a masonry wall and a finishing structure for preventing collapse of the masonry wall having the same

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100991851B1 (en) * 2010-09-01 2010-11-04 신성종합건축사사무소(주) Earthquake retrofit structure for brick wall and construction method thereof
KR101090314B1 (en) * 2011-05-16 2011-12-07 비코비엔주식회사 Reinforced masonary structure using wave pannel and masonary reinforcing method using the same

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100991851B1 (en) * 2010-09-01 2010-11-04 신성종합건축사사무소(주) Earthquake retrofit structure for brick wall and construction method thereof
KR101090314B1 (en) * 2011-05-16 2011-12-07 비코비엔주식회사 Reinforced masonary structure using wave pannel and masonary reinforcing method using the same

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20200142352A (en) * 2019-06-12 2020-12-22 신성한 Anti-seismic reinforcing structure for preventing collapse of a masonry wall and a finishing structure for preventing collapse of the masonry wall having the same
KR102247640B1 (en) * 2019-06-12 2021-04-30 신성한 Anti-seismic reinforcing structure for preventing collapse of a masonry wall and a finishing structure for preventing collapse of the masonry wall having the same

Similar Documents

Publication Publication Date Title
CN104060717B (en) A kind of fabricated shear wall structural wall board fractionation-assemble method
CN107178163B (en) Energy dissipation and shock absorption horizontal connecting device for fabricated shear wall and construction method of energy dissipation and shock absorption horizontal connecting device
CN110306660B (en) Assembled anti-seismic steel skeleton and anti-seismic wall for steel structure building
CN103883025B (en) Assembling type combination steel plate shear wall
KR100956974B1 (en) Building remodeling construction method using precast concrete panel, and remodeled building thereof
KR101277752B1 (en) Remodelling Construction Method by Inserting External Precast Concrete Wall Panel into the Internal Area of Beam-column Frame of Building and that Precast Concrete Panel
KR101122659B1 (en) Method execution for jointing between precast concrete panels for building remodeling
KR101106259B1 (en) Construction method for building remodeling by using precast concrete panel, and connecting structure for precast concrete panel
CN101936074B (en) Fast building earthquake-resisting reinforcing method and device
CN110924562A (en) Flexible connection method for steel structure assembled exterior wall ALC wallboard
KR20130018343A (en) Seismic retrofit method of src enlarged section using connection joint with anchor plate and steel bar tie
EP3779101B1 (en) Method of anti-seismic protection of frames and filling walls in frame buildings
KR101670553B1 (en) Seismic reinforcement using precast concrete wall outside of building
KR102046573B1 (en) Reinforced structural system for secure seismic performance by reinforcing existing bricks walls
JP2008163646A (en) Method and structure for reinforcing existing column
KR101178168B1 (en) Inverted multi tee slab
KR101723515B1 (en) A structure for strengthening masonry and reinforcing method of masonry buildings using the same
KR102365116B1 (en) Seismic Reinforcement Construction Method And Structure Of Masonry Wall
CN107313516B (en) Autoclaved aerated concrete wallboard and steel girder connecting node structure and construction method thereof
CN207003673U (en) A kind of connecting node of beam and wallboard
CN106437261B (en) A kind of concrete frame seismic reinforcing structure using expanded metal lath
CN211369158U (en) Assembly type shear wall with strong horizontal connection nodes
KR102079964B1 (en) the improved brick support structure
CN111749328A (en) Novel assembly type beam joint and construction form thereof
KR101248509B1 (en) Building Remodeling Construction Method Using Precast Concrete Panel, and Remodeled Building Thereof

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20200227