Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same Download PDF

Info

Publication number
KR101038554B1
KR101038554B1 KR1020040018955A KR20040018955A KR101038554B1 KR 101038554 B1 KR101038554 B1 KR 101038554B1 KR 1020040018955 A KR1020040018955 A KR 1020040018955A KR 20040018955 A KR20040018955 A KR 20040018955A KR 101038554 B1 KR101038554 B1 KR 101038554B1
Authority
KR
South Korea
Prior art keywords
tundish
refractory
stud
hollow tube
forming
Prior art date
Application number
KR1020040018955A
Other languages
Korean (ko)
Other versions
KR20050093484A (en
Inventor
이찬섭
Original Assignee
주식회사 포스코
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 포스코 filed Critical 주식회사 포스코
Priority to KR1020040018955A priority Critical patent/KR101038554B1/en
Publication of KR20050093484A publication Critical patent/KR20050093484A/en
Application granted granted Critical
Publication of KR101038554B1 publication Critical patent/KR101038554B1/en

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B42BOOKBINDING; ALBUMS; FILES; SPECIAL PRINTED MATTER
    • B42FSHEETS TEMPORARILY ATTACHED TOGETHER; FILING APPLIANCES; FILE CARDS; INDEXING
    • B42F13/00Filing appliances with means for engaging perforations or slots
    • B42F13/16Filing appliances with means for engaging perforations or slots with claws or rings
    • B42F13/20Filing appliances with means for engaging perforations or slots with claws or rings pivotable about an axis or axes parallel to binding edges
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B42BOOKBINDING; ALBUMS; FILES; SPECIAL PRINTED MATTER
    • B42PINDEXING SCHEME RELATING TO BOOKS, FILING APPLIANCES OR THE LIKE
    • B42P2241/00Parts, details or accessories for books or filing appliances
    • B42P2241/02Fasteners; Closures

Landscapes

  • Casting Support Devices, Ladles, And Melt Control Thereby (AREA)

Abstract

본 발명은 턴디시 내화물을 시공할 때 턴디시 외부철피에 장착되어 턴디시 예열시 연소되어 수분통로를 형성할 수 있는 턴디시 내화물의 수분통로 형성용 Y스터드 및 이를 이용한 턴디시 내화물 시공방법에 관한 것이다.The present invention relates to a Y stud for forming a moisture passage of tundish refractory, which is attached to a tundish outer shell when the tundish refractories are installed and burned during preheating of the tundish to form a moisture passage, and a tundish refractory construction method using the same. will be.

이를 위하여, 본 발명은 가연성의 플라스틱 재질이면서, 중공형의 파이프 형태로 제작되는 Y형 중공관과, 상기 Y형 중공관 내부에 충진되는 불연성의 구로족 물질로 구성되는 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드 및 이러한 Y스터드를 턴디시의 외부철피에 형성된 수분 유출홀에 삽입 고정하는 단계와, 상기 Y스터드가 고정된 턴디시에 턴디시 코어를 고정하는 단계와, 상기 턴디시 외부철피와 턴디시 코어 사이의 공간부에 부정형 내화물을 유입시켜 경화시키는 단계와, 상기 부정형 내화물이 경화된 턴디시를 예열하여 Y스터드의 가연성 Y형 중공관을 연소시켜 제거하여 수분 유도로를 형성하는 단계로 구성되는 것을 특징으로 하는 턴디시 내화물 시공방법을 제공한다.To this end, the present invention is a flammable plastic, Y-type hollow tube produced in the form of a hollow pipe and a tundish refractory comprising a non-combustible Guro group material filled in the Y-shaped hollow tube Inserting and fixing the water channel forming quench stud and the wick stud into the water outlet hole formed in the outer shell of the tundish, fixing the tundish core in the tundish to which the chop stud is fixed, and the tundish A step of injecting an amorphous refractory into the space portion between the outer shell and the tundish core to cure, and preheating the cured tundish of the amorphous refractory to burn and remove the combustible Y type hollow tube of the Y stud to form a moisture induction furnace. Provides a tundish refractory construction method characterized in that consisting of a step.

Y스터드, 턴디시, 부정형내화물, 구로족, 중공관, 예열, 수분제거Y stud, tundish, irregular refractory, guro, hollow tube, preheat, moisture removal

Description

턴디시 내화물의 수분통로 형성용 Y스터드 및 이를 이용한 턴디시 내화물 시공방법{Y TYPE STUD FOR FORMING WATER PASSAGE IN THE REFRACTORY OF TUNDISH AND METHOD FOR FORMING REFRACTORY OF TUNDISH USING THE SAME}Y TST FOR FORFORMING WATER PASSAGE IN THE REFRACTORY OF TUNDISH AND METHOD FOR FORMING REFRACTORY OF TUNDISH USING THE SAME}

도 1은 연주설비에 턴디시가 이용되는 상태를 도시한 모식도;1 is a schematic diagram showing a state in which the tundish is used in the performance equipment.

도 2는 축조식 내화물로 형성된 턴디시의 예열상태를 도시한 모식도;Figure 2 is a schematic diagram showing a preheated state of the tundish formed of the building refractory;

도 3은 일체형 내화물로 형성된 턴디시의 예열상태를 도시한 모식도;3 is a schematic diagram showing a preheated state of a tundish formed of an integral refractory;

도 4는 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드를 도시한 사시도 및 정면도;4 is a perspective view and a front view showing a Y stud for forming a water passage of the tundish refractory according to the present invention;

도 5는 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드가 턴디시 외부 철피에 장착되는 상태를 도시한 모식도;5 is a schematic diagram showing a state in which the Y stud for forming the moisture passage of the tundish refractory according to the present invention is mounted on the tundish outer shell;

도 6은 본 발명에 따른 턴디시 턴디시 내화물의 수분통로 형성용 Y스터드를 이용한 턴디시 내화물 시공방법의 순서를 도시한 공정도;Figure 6 is a process chart showing the procedure of the tundish refractory construction method using the Y stud for forming the moisture passage of the tundish tundish refractory according to the present invention;

도 7은 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드를 이용한 턴디시 내화물 시공방법에 의하여 턴디시를 가열하여 내화물에 수분통로가 형성된 상태를 도시한 개념도이다.7 is a conceptual diagram illustrating a state in which a water passage is formed in the refractory by heating the tundish by the tundish refractory construction method using the Y stud for forming the water passage of the tundish refractory according to the present invention.

♣도면의 주요부분에 대한 부호의 설명♣♣ Explanation of symbols for main part of drawing ♣

1: 레이들 2: 용강 1: ladle 2: molten steel                 

3: 턴디시 4: 주형3: tundish 4: mold

10: 외부철피 12: 정형화 내화물10: outer shell 12: standardized refractory

15: 부정형 내화물 19: 수분유출홀15: amorphous refractory 19: moisture outflow hole

20: 스타트 캡 21: 잔존수분20: start cap 21: residual moisture

22: 유출수분 25: 턴디시 코어22: effluent 25: tundish core

30: Y스터드 31: 메인파이프30: Y stud 31: main pipe

32: 줄기파이프 35: 구로족 물질32: stem pipe 35: Guro matter

36: 수분 유도로36: moisture induction furnace

본 발명은 턴디시 내화물의 수분통로 형성용 Y스터드 및 이를 이용한 턴디시 내화물 시공방법에 관한 것으로서, 보다 상세하게는 턴디시 내화물을 시공할 때 턴디시 외부철피에 장착되어 턴디시 예열시 연소되어 수분통로를 형성할 수 있는 턴디시 내화물의 수분통로 형성용 Y스터드 및 이를 이용한 턴디시 내화물 시공방법에 관한 것이다.The present invention relates to a Y stud for forming a moisture passage of tundish refractory and a tundish refractory construction method using the same, and more particularly, when the tundish refractory is constructed, it is mounted on a tundish outer shell and combusts when preheated by tundish The present invention relates to a Y stud for forming a moisture passage of a tundish refractory capable of forming a passage, and a tundish refractory construction method using the same.

턴디시(3)는, 도 1에 도시된 바와 같이, 레이들(1)에 수강된 용강(2)의 흐름을 제어하여 주형(4)에 주입하는 중간용기 역할을 하는 것으로서, 이를 통과하여 주형(4)에 주입된 용강(2)은 연주롤(5)을 거쳐 주편(6)으로 연속주조되는 것이다.As shown in FIG. 1, the tundish 3 serves as an intermediate container for controlling the flow of the molten steel 2 received in the ladle 1 and injecting it into the mold 4. The molten steel 2 injected into (4) is continuously cast to the cast piece 6 via the performance roll 5.

상기 턴디시(3)는 연속주조 작업완료 후 턴디시 수리장으로 이동되어 턴디시(3) 내의 잔존물과 지금 등을 제거한 다음, 내화물 보수공정을 거쳐 다시 연속주조공정에 도입된다. 신규 또는 보수된 턴디시(3)를 연주공정에 도입하기 전에는 반드시 예열공정을 거쳐야 안정적으로 용강(2)을 수강하여 공급할 수 있다.The tundish 3 is moved to the tundish repair shop after completion of the continuous casting operation to remove the residue and now in the tundish 3, and then introduced into the continuous casting process through the refractory repair process. Before the new or repaired tundish 3 is introduced into the playing process, the molten steel 2 can be stably received and supplied through a preheating process.

상기 예열공정은 건조→중간예열→승열의 순서로 진행되는데, 이러한 작업은 통상적으로 약 5시간 정도 소요되고, 열원으로서 코크스 오븐가스(COG)와 고온의 공기 및 LPG, 경유 등이 사용되기도 한다.The preheating process is carried out in the order of drying → intermediate preheating → heating up, and this operation usually takes about 5 hours, and coke oven gas (COG), hot air, LPG, diesel, etc. may be used as a heat source.

이와 같은 턴디시(3)의 예열작업의 필요성은 다음과 같다.The necessity of such preheating of the tundish 3 is as follows.

첫째, 레이들(1)에 수강된 용강(2)을 턴디시(3)에 공급시 용강온도의 급격한 하락 예방하고,First, when supplying the molten steel (2) received in the ladle (1) to the tundish (3) to prevent a sharp drop in the molten steel temperature,

둘째, 용강(2)과 턴디시(3)의 높은 온도차이에 따른 턴디시 내화물 탈락 및 용강폭발의 위험성을 예방하며,Second, it prevents the risk of tungsten refractory dropout and molten steel explosion due to the high temperature difference between molten steel (2) and tundish (3),

셋째, 턴디시(3)의 내부 내화물에 잔존하는 수분을 제거하여 턴디시(3) 내의 수분이 용강(2)에 침투하는 것을 방지하고자 실시하는 것이다.Third, the moisture remaining in the internal refractory of the tundish 3 is removed to prevent the moisture in the tundish 3 from penetrating into the molten steel 2.

이러한 턴디시 예열공정에서 단순한 용강온도의 하락예방과 용강폭발 등은 턴디시(3)의 단순한 가열로 예방이 가능하지만, 턴디시(3) 내부 내화물에 잔존하는 수분을 제거하기 위한 턴디시 예열작업은 단순하지 않고 높은 예열로도 수분이 제거되지 않는 어려움이 있어 많은 연구와 기술의 개발 결과, 상기한 건조→중간예열→승열로 구분하여 실시하는 것이 일반적이다.In this tundish preheating process, a simple drop of the molten steel temperature and a molten steel explosion can be prevented by simple heating of the tundish 3, but a tundish preheating operation for removing moisture remaining in the internal refractory of the tundish 3 Is not simple and does not remove moisture even by high preheating, and as a result of many studies and technologies, it is common to carry out the above-described drying → medium preheating → heating.

건조는 전체 열원의 20%(765,000㎉l/H)로 약200~400분, 중간예열은 40%(1,350,000㎉l/H)로 150~90분, 승열은 60%(2,685,000㎉/H)로 약30분 이하가 되도록 실시하며, 수용되는 용강의 온도에 따라서 가열시간의 가감이 있다. 또한 건조시간이 길어지면 중간예열 시간이 짧아지고, 건조시간이 짧으면 중간 예열시간이 길어지는데, 이러한 예열방법은 일반적으로 사용되는 기술로 기 공지되어 있다.Drying takes about 200 ~ 400 minutes at 20% (765,000 열 l / H) of the total heat source, 150 ~ 90 minutes at 40% (1,350,000㎉l / H) for intermediate preheating, and 60% (2,685,000㎉ / H) of heating. It is carried out so that it may be about 30 minutes or less, and there is an increase and decrease of a heating time according to the temperature of molten steel accommodated. In addition, when the drying time is long, the intermediate preheating time is short, and when the drying time is short, the intermediate preheating time is long. Such a preheating method is known as a commonly used technique.

본 발명이 적용되는 턴디시(3)의 내부 내화물의 형태는 두가지 형태가 있다. 즉 정형화된 내화물(내화벽돌; 12)로 축조된 정형화 내화물 턴디시(도 2 참조)와 부정형 내화물(몰탈형으로 유동성 있는 내화물)로 유입 시공된 일체형 내화물 턴디시(도 3 참조)로 구분된다.There are two forms of the internal refractory material of the tundish 3 to which the present invention is applied. That is, it is divided into a structured refractory tundish (see FIG. 2) constructed with a standardized refractory (firebrick) 12 and an integral refractory tundish (see FIG. 3) that is flowed into an irregular refractory (mortal flowable refractory).

먼저, 도 2에 도시된 정형화 내화물 턴디시는 그 외부가 견고한 외부철피(10)로 되어 있으며, 단열 내화재(11), 정형화 내화물(12), 부정형 라밍재(13)로 구성되어 있다. 이러한 구조는 용강의 고열로부터 턴디시(3)를 보호하며 대기의 온도로부터 용강의 온도를 지속적으로 유지하기 위한 것이지만, 턴디시(3) 수리작업시 턴디시 지금과 술래그의 냉각을 위하여 살수되는 냉각수와 정형화 내화물(12)에 함유된 수분이 턴디시 외부철피(10)와 정형화 내화물(12) 사이에 침투하여 잔존하게 된다.First, the shaped refractory tundish shown in FIG. 2 is made of a rigid outer shell 10, and is composed of a heat insulating refractory material 11, a shaped refractory material 12, and an amorphous ramming material 13. This structure protects the tundish 3 from the high temperature of the molten steel and maintains the temperature of the molten steel from the ambient temperature, but the coolant is sprinkled for cooling the tundish now and the sag during the tundish 3 repair work. And moisture contained in the shaping refractory 12 penetrates and remains between the outer shell 10 and the shaping refractory 12.

이렇게 침투된 냉각수는 턴디시(3)의 건조→중간예열→승열작업 시에도 정형화 내화물(12)의 특성상 쉽게 건조되지 않는 문제점이 있으나, 내화물의 축조기술 발달과 턴디시 외부철피(10)에 일정간격으로 수분 유출홀(19)을 천공하여 수분이동 통로로 사용하는 등 다양한 방법과 예열기술로 거의 완벽에 가까울 정도로 턴디시(3) 내화물 부분의 수분을 제거하여 사용하고 있다.The cooling water thus penetrated is not easily dried due to the characteristics of the standardized refractory 12 even during drying → intermediate preheating → heating operation of the tundish (3), but the development of the construction of the refractory and constant tungsten outer shell (10) Perforated water outlet holes 19 at intervals are used to remove water from the refractory portion of the tundish 3 so as to be almost perfect by various methods and preheating techniques such as using it as a water moving passage.

그러나, 이러한 정형화 내화물 턴디시(도 2)의 구조적 특성상 정형화 내화물(12)과 정형화 내화물(12) 사이로 용강이 침투할 수 있는 위험성이 있고, 정형화 내화물(12) 축조에 많은 시간과 고도의 설계기술, 고기능의 축조기술자가 필요하며 잦은 내화물 교체에 따른 원가 상승요인이 발생하게 되어 최근에는 부정형 내화물(몰탈형으로 유동성 있는 내화물)로 유입 시공된 일체형 내화물 턴디시(도 3 참조)가 활용되고 있다.However, there is a risk that molten steel may penetrate between the shaped refractory 12 and the shaped refractory 12 due to the structural characteristics of the shaped refractory tundish (FIG. 2), and a lot of time and advanced design techniques are required to build the shaped refractory 12. In addition, a high-performance building technician is required, and a cost increase factor occurs due to frequent refractories replacement. Recently, an integral refractory tundish (see FIG. 3) that has been constructed and introduced into an indefinite refractory (mortal type fluid refractory) has been utilized.

이러한 부정형 내화물(몰탈형으로 유동성 있는 내화물)의 유입시공 기법은 턴디시 외부철피(10) 내에 좀더 작은 또 다른 턴디시 철피의 모형(턴디시 코어; 25)을 넣고 그 사이에 부정형 내화물(15)을 유입시켜 시공하는 기술로서, 신속하고 간편한 시공과 오랜 수명으로 각광을 받고 있다.The inflow construction technique of the amorphous refractory (mortalized fluid refractory) is to put another smaller tundish shell (tundish core; 25) in the tundish shell (10), and the amorphous refractory (15) in between. It is a technology to install by injecting oil, and it has been spotlighted for quick and easy construction and long life.

그러나, 상기와 같은 유입시공법으로 시공된 부정형 내화물(15)은 턴디시 내화물 전체가 1개의 일체형으로 되어 있어 턴디시 외부철피(10)의 수분 유출홀(19)이 막히게 되어 이로부터 유출되는 유출수분(22)이 거의 없으며, 또한 일체형이기 때문에 내화물 사이의 수분이동통로가 차단되므로 예열작업 시에 수분제거에 많은 시간과 열원을 사용하여도 충분한 수분제거가 이루어지지 않아 연속주조 작업시 턴디시(3)에 수강된 용강(2) 내로 수분이 침투하여 잔존하게 된다. 침투하여 잔존하는 수분(21)은 다음과 같은 문제점이 발생시킨다.However, the irregular refractory 15 constructed by the inflow construction method as described above has one whole tundish refractory, so that the water outlet hole 19 of the tundish outer shell 10 is blocked so that the outflow water flows out therefrom. (22) There is almost no, and because it is integral, water transfer path between refractory is blocked, so it is not enough water removal even when using heat source and time for water removal during preheating operation. Moisture penetrates into the molten steel (2) received in the) and remains. The moisture 21 that penetrates and remains causes the following problem.

첫째, 용강 내에 수소함량이 상승되어 최종 주편에 핀홀(Pin Holl)이 다량 발생하게 되어 주편의 품질불량 증가에 따른 연연주비용이 상승하고,First, the hydrogen content in the molten steel increases, causing a large amount of pinholes in the final cast, resulting in an increase in the cast cost due to an increase in the quality of the cast.

둘째, 주조 중 주편터짐(Break Out) 현상이 빈번하게 발생하여 생산이 중단되는 경우가 많으며, Second, the break out phenomenon occurs frequently during casting, and production is often stopped.                         

셋째, 턴디시 내부 예열지연으로 고온의 공기 및 COG 사용량증가하며,Third, the use of hot air and COG increases due to the internal preheating delay of tundish,

넷째, 턴디시 예열과 냉각에 따른 온도편차에 심하게 발생하여 턴디시 변형발생에 따른 턴디시의 수명이 단축되며,Fourth, the lifespan of tundish due to tundish deformation is shortened due to severe temperature variation due to tundish preheating and cooling.

다섯째, 과다예열에 의한 스타트캡(20)의 용손으로 초기 연주작업시 용강 배출노즐의 막힘현상이 발생하게 된다.Fifth, the clogging phenomenon of the molten steel discharge nozzle occurs during the initial performance of the start cap 20 due to excessive preheating.

상기한 문제점들을 해결하기 위하여, 본 발명은 부정형 내화물(몰탈형으로 유동성 있는 내화물)의 유입시공 기법으로 턴디시 내화물을 시공할 때 외부철피에 형성된 수분 유출홀에 장착되고, 시공 완료후 건조 및 예열과정에서 완전히 연소하여 턴디시 내화물에 수분통로를 형성할 수 있는 Y스터드를 제공하는데 그 목적이 있다.In order to solve the above problems, the present invention is mounted on the water outlet hole formed in the outer shell when construction of tundish refractory by the inflow construction technique of amorphous refractory (mortal refractory refractory), drying and preheating after completion of construction The purpose is to provide a Y stud capable of completely burning in the process to form a moisture passage in the tundish refractory.

또한, 본 발명은 Y스터드를 턴디시 외부철피에 형성된 수분 유출홀에 장착하고, 부정형 내화물(몰탈형으로 유동성 있는 내화물)의 유입시공하여 경화시킨 다음, 예열하여 수분통로를 형성하는 턴디시 내화물 시공방법을 제공하는데 또 다른 목적이 있다.In addition, the present invention is mounted to the Y-stud in the moisture outlet hole formed in the outer shell of the tundish, and the hardened by the inflow of the indefinite refractory (mortal refractory refractory), then preheated to form a tungsten refractory construction Another purpose is to provide a method.

상기한 목적을 달성하기 위하여, 본 발명은 가연성의 플라스틱 재질이면서, 중공형의 파이프 형태로 제작되는 Y형 중공관과, 상기 Y형 중공관 내부에 충진되는 불연성의 구로족 물질로 구성되는 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드를 제공한다.In order to achieve the above object, the present invention is a flammable plastic material, characterized in that the Y-type hollow tube made of a hollow pipe form, and the non-combustible Guro group material filled in the Y-shaped hollow tube Provided is a stud for forming a water passage of a tundish refractory.

또한, 본 발명은 상기 Y형 중공관의 길이가 전체 내화물 폭의 2/3 이하의 길이로 형성되고, 중앙의 메인파이프와 양측의 줄기파이프의 각도가 150~175도인 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드를 제공하게 된다.In addition, the present invention is a tundish refractory, characterized in that the length of the Y-shaped hollow tube is formed to a length of 2/3 or less of the total refractory width, the angle of the central main pipe and the stem pipes on both sides is 150 ~ 175 degrees It is to provide a chopped stud for forming a water passage.

한편, 본 발명은 상기의 Y스터드를 턴디시의 외부철피에 형성된 수분 유출홀에 삽입 고정하는 단계와, 상기 Y스터드가 고정된 턴디시에 턴디시 코어를 고정하는 단계와, 상기 턴디시 외부철피와 턴디시 코어 사이의 공간부에 부정형 내화물을 유입시켜 경화시키는 단계와, 상기 부정형 내화물이 경화된 턴디시를 예열하여 Y스터드의 가연성 Y형 중공관을 연소시켜 제거하여 수분 유도로를 형성하는 단계로 구성되는 것을 특징으로 하는 턴디시 내화물 시공방법을 제공한다.On the other hand, the present invention is the step of inserting and fixing the chopped studs in the water outlet hole formed in the outer shell of the tundish, the step of fixing the tundish core in the tundish fixed the chopped studs, the tundish outer shell Injecting and curing the amorphous refractory material into the space portion between the and tundish cores, and preheating the hardened refractory tundish to burn and remove the combustible Y type hollow tube of the Y stud to form a moisture induction furnace. Provides a tundish refractory construction method comprising a.

여기서, 상기 부철피의 측면에 고정되는 Y스터드는 턴디시 바닥면과의 각도가 20~30도가 되도록 고정되고, 외부철피 바닥부에 고정되는 Y스터드는 줄기파이프의 사이각도가 50~60도가 되도록 고정한다.Here, the stud is fixed to the side of the iron bar is fixed so that the angle with the tundish bottom surface is 20 to 30 degrees, the Y stud fixed to the bottom of the outer shell is fixed so that the angle between the stem pipe 50 to 60 degrees do.

또한, 본 발명은 가연성 Y형 중공관을 연소시켜 제거하여 수분 유도로를 형성하는 단계에서 상기 수분 유도로와 구로족 물질의 사이간격이 2~2.5㎜ 범위인 것을 특징으로 하는 턴디시 내화물 시공방법.In addition, the present invention is a tungsten refractory construction method characterized in that the interval between the moisture induction furnace and the Guro group material in the step of forming a moisture induction furnace by burning the combustible Y-type hollow tube to remove the range. .

이하, 첨부된 도면을 참조하여 본 발명의 구성을 상세하게 설명한다.Hereinafter, with reference to the accompanying drawings will be described in detail the configuration of the present invention.

도 4는 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드를 도시한 사시도 및 정면도이다.Figure 4 is a perspective view and a front view showing a Y stud for forming a moisture passage of tundish refractory according to the present invention.

도 4에 도시된 바와 같이, 본 발명의 Y스터드는 Y형 중공관(30)과 이의 내부공간에 충전되는 불연성의 구로족 물질(35)로 구성된다.As shown in FIG. 4, the Y stud of the present invention is composed of a Y-type hollow tube 30 and an incombustible Guro group material 35 filled in an inner space thereof.

상기 Y형 중공관(30)은 가연성이면서 소실(燒失; Burnout)되는 플라스틱(폴리머) 재질이면서 중공형의 파이프 형태로 제작되는데, 연소온도는 턴디시 예열온도범위인 500℃ 부근인 것을 이용하는 것이 바람직하다.The Y-type hollow tube 30 is a flammable and burned plastic (polymer) material and is manufactured in the form of a hollow pipe, the combustion temperature of which is used in the vicinity of the preheating temperature range 500 ℃ desirable.

상기 Y형 중공관(30)은 중앙의 메인파이프(31)와 이와 연통되어 형성된 양측의 줄기파이프(32)로 이루어지며, 상기 양측의 줄기파이프(32)가 메인파이프(31)가 이루는 각도는 150~175도 범위로 하는데, 이는 턴디시 외부철피(10)에 형성된 수분 유출홀(19)에 장착되었을 때 내화물 내부의 수분이 용이하게 배출하기 위함이며, 또한 이 범위보다 작은 각도로 줄기파이프(32)가 형성되면 부정형 내화물 유입이 어려워져 내화물 시공이 양호하게 되지 않으며, 이 범위보다 큰 각도로 줄기파이프(32)가 형성되면 저의 180도에 가까워져 내화물 내부의 여러 곳에 존재하는 수분의 유도가 어려워지기 때문이다.The Y-shaped hollow tube 30 is composed of the stem pipe 32 on both sides formed in communication with the main pipe 31 in the center, the angle formed by the main pipe 31 of the stem pipe 32 on both sides It is in the range of 150 to 175 degrees, which is for easily discharging moisture inside the refractory when mounted in the water outlet hole 19 formed in the outer shell 10 of the tundish, and also the stem pipe at an angle smaller than this range ( When the 32) is formed, the refractory construction becomes difficult due to inflow of irregular refractory materials, and when the stem pipe 32 is formed at an angle larger than this range, it becomes close to 180 degrees of me, and it is difficult to induce moisture existing in various places inside the refractory materials. For losing.

또한, Y형 중공관(30)의 메인파이프(31)의 단부에는 턴디시 외부철피(10)에 형성된 수분 유출홀(19)의 크기와 거의 유사한 돌출부(33)가 형성되어 있어 수분 유출홀(19)에 견고하면서도 안정적으로 고정될 수 있도록 한다.In addition, the end of the main pipe 31 of the Y-shaped hollow tube 30 is formed with a protrusion 33 which is almost similar to the size of the water outlet hole 19 formed in the outer shell 10 of the tundish, so that the water outlet hole ( 19) can be fixed firmly and stably.

상기와 같이 형성된 Y형 중공관(30) 내부에 충진되는 불연성(또는 내화성)의 구로족 물질이 충전된다. 구로족 물질은 내화물의 접착작업 또는 내화물의 보수작업에 이용되는 통상의 세라믹 재질로서, 그 물리적 특성상 약 1100℃ 이내에서는 부드럽고 높은 연성의 특성이 있어 턴디시(3)의 건조와 중간예열작업 시에는 부정형 내화물 속에서 Y자형 수분통로를 형성하여 예열작업시 수분이 턴디시 외부철피(10)의 수분 유출홀(19)을 통하여 용이하게 빠져 나갈 수 있도록 한다. The incombustible (or refractory) guro group material filled in the Y-shaped hollow tube 30 formed as described above is filled. Guro-based material is a common ceramic material used for bonding refractories or repairing refractory materials. Due to its physical properties, the Guro group material has soft and high ductility characteristics within about 1100 ° C. The Y-shaped moisture passage is formed in the irregular refractory to allow moisture to easily escape through the water outlet hole 19 of the outer shell 10 during the preheating operation.                     

그러나, 레이들(1)로부터 1400℃ 이상의 용강(2)이 턴디시(3)에 공급되어 턴디시 내화물의 온도가 상승되면, 구로족 물질은 그 물리적 특성상 1300℃ 이상에서는 견고하게 굳어지면서 부피가 1.25배 팽창되어 시공된 내화물의 수분 유도로를 폐쇄하여 턴디시(3) 내 용강의 유출을 방지함은 물론 유입시공 내화물을 더욱 견고하게 하여 안정적으로 연주조업에 이루어지도록 한다.However, when the molten steel 2 of 1400 ° C. or more is supplied from the ladle 1 to the tundish 3 and the temperature of the tundish refractory is increased, the Guro group material hardens and hardens at 1300 ° C. or higher due to its physical properties. 1.25 times expanded and closed the water induction path of the refractory to be constructed to prevent the leakage of molten steel in the tundish (3), as well as to make the inflow and refractories more robust to ensure a stable performance in the performance.

이하에서는 본 발명의 Y스터드를 이용한 턴디시 내화물 시공방법에 관하여 설명한다.Hereinafter, the tundish refractory construction method using the Y stud of the present invention will be described.

도 5는 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드가 턴디시 외부 철피에 장착되는 상태를 도시한 모식도이고, 도 6은 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드를 이용한 턴디시 내화물 시공방법의 순서를 도시한 공정도이며, 도 7은 본 발명에 따른 턴디시 내화물의 수분통로 형성용 Y스터드를 이용한 턴디시 내화물 시공방법에 의하여 턴디시를 가열하여 내화물에 수분통로가 형성된 상태를 도시한 개념도이다.Figure 5 is a schematic diagram showing a state in which the Y stud for forming the moisture passage of the tundish refractory according to the present invention is mounted on the outer shell of the tundish, Figure 6 is a Y stud for forming the moisture passage of the tundish refractory according to the present invention Figure 7 is a flow chart showing the sequence of the tundish refractory construction method used, Figure 7 is a tundish refractory construction method using a t-dish refractory construction method using the Y stud for forming a water passage of the tundish refractory according to the present invention to the moisture passage in the refractory It is a conceptual diagram which shows the state formed.

도 6에 도시된 순서와 같이 턴디시 내화물 시공방법이 진행되는데, 먼저 전술된 본 발명의 Y스터드를 턴디시(3)의 외부철피(10)의 측면 및 바닥부의 수분 유출홀(19)에 삽입 고정시킨다.As shown in FIG. 6, the tundish refractory construction method is performed. First, the above-described Y stud of the present invention is inserted into the water outlet hole 19 at the side and bottom of the outer shell 10 of the tundish 3. Fix it.

이 때 고정되는 형태는, 도 5에 도시된 바와 같이, 턴디시(3) 외부철피(10)의 측면에 형성된 수분 유출홀(19)에 삽입 고정되는 Y스터드는 턴디시 바닥면과의 각도가 20~30도가 되도록 고정되고, 외부철피(10) 바닥부에 형성된 수분 유출홀(19)에 고정되는 Y스터드는 줄기파이프(32)의 사이각도가 50~60도가 되도록 고정되도록 한다. 이는 모두 내화재 내부에 잔존하는 수분의 유출을 용이하게 하기 위함이다.At this time, the fixed form is, as shown in Figure 5, the tungsten insert and fixed to the water outlet hole 19 formed on the side of the tundish (3) outer shell 10 has an angle with the bottom surface of the tundish It is fixed to 20 to 30 degrees, the Y stud is fixed to the water outlet hole 19 formed in the bottom of the outer shell 10 to be fixed so that the angle between the stem pipe 32 is 50 to 60 degrees. This is all to facilitate the outflow of moisture remaining in the refractory material.

그런 다음 턴디시 철피(10) 내부공간에 위치하여 내화재 공간을 형성할 수 있는 턴디시 코어(25)를 고정시킨다. 상기 턴디시 코어(25)에 의하여 형성된 사이공간부에 부정형 내화물(15)을 유입 시공한 다음, 소정 시간동안 부정형 내화물(15)을 경화시키게 되는데, 어느 정도 경화가 진행된 다음에는 턴디시(3)를 서서히 예열하기 시작한다.Then, the tundish core 25 is fixed in the tundish core 25, which is positioned in the inner space of the tundish iron shell 10, to form a fireproof space. After the amorphous refractory material 15 is introduced into the interspace formed by the tundish core 25, the amorphous refractory material 15 is hardened for a predetermined time. Start to warm up slowly.

턴디시 예열온도가 500℃에 도달하면 구로족 물질이 충진된 Y스터드의 중공형 플라스틱 부분은 연소되어 소실되고, 도 7에 도시된 바와 같이, 부정형 내화물(15) 속에는 플라스틱이 차지하고 있던 부피만큼 Y자형으로 공간인 수분 유도로(36)가 생기게 된다. 이러한 수분 유도로(36)는 턴디시 철피(10)의 수분 유출홀(19)과 연결되어진다.When the preheating temperature of the tundish reaches 500 ° C., the hollow plastic portion of the Y stud filled with the Guro group material is burned and lost, and as shown in FIG. 7, the volume occupied by the plastic in the amorphous refractory 15 is Y. There is a water induction furnace 36 which is a space in a shape. The moisture induction furnace 36 is connected to the water outlet hole 19 of the tungsten shell 10.

이하, 본 발명의 실시예를 통하여 더욱 상세하게 설명한다.Hereinafter, the embodiment of the present invention will be described in more detail.

[실시예][Example]

본 발명의 Y스터드 구조는 다수의 줄기파이프(32- 외경;10㎜, 내경:8㎜, 두께:1㎜, 길이:130㎜)가 Y자 모양으로 배치되어 그 또 다른 선단부가 메인파이프(31-외경;15㎜, 내경:12.5㎜, 두께:1.75㎜, 길이:25㎜)와 취합된 일체형으로 내부에는 구로족 물질이 충전되어 있는 상태에서 메인파이프(18)의 선단부에 형성된 돌출부(33)를 턴디시 수분 유출홀(19)에 삽입 고정시키게 된다.In the Y stud structure of the present invention, a plurality of stem pipes (32-outer diameter; 10 mm, inner diameter: 8 mm, thickness: 1 mm, length: 130 mm) are arranged in a Y-shape, and the other end thereof is the main pipe (31). 15 mm, inner diameter: 12.5 mm, thickness: 1.75 mm, length: 25 mm), the protrusion 33 formed at the tip of the main pipe 18 in a state in which a guro group material is filled therein. T is inserted into and fixed in the moisture outlet hole 19.

이때 턴디시 바닥과 턴디시 하부(턴디시 바닥에서 500㎜높이까지) 부분의 수분 유출홀(19)에 Y스터드를 일정간격(150㎜)으로 고정하게 되며, 이 작업이 완료되면, 턴디시 내부에 턴디시 코어(25)를 도입하여 고정한 다음, 1차적으로 부정형 내화물(15)을 턴디시 바닥에서 500㎜ 높이까지 충전하게 된다.At this time, the Y stud is fixed at a predetermined interval (150 mm) in the water outlet hole 19 of the tundish bottom and the tundish bottom portion (up to 500 mm height from the tundish bottom). After the tundish core 25 is introduced and fixed, the amorphous refractory 15 is primarily filled up to a height of 500 mm from the bottom of the tundish.

이는 턴디시 상부에서 슬래그 라인이 형성되는 부분에서 하단으로 200㎜지점까지에 턴디시 철피(10)의 남은 수분 유출홀(19)에 Y스터드를 조립하고 부정형 내화물(15)을 완전히 충전한다.It assembles the Y studs in the remaining water outlet holes 19 of the tundish shells 10 to 200 mm from the portion where the slag line is formed at the top of the tundish to the bottom and completely fills the irregular refractory 15.

이때 고려하여할 중요한 사항은 간헐적으로 턴디시 내부로 유입되는 슬래그량이 급증할 경우 유입시공 내화물의 슬래그 라인부분이 과도하게 침식되는 경우가 있는데, 구로족 물질이 용강과 직접적으로 접촉되지 않도록 내화물을 시공하는 것이 중요하다.In this case, it is important to consider that when the amount of slag flowing into the tundish intermittently increases, the slag line portion of the inflow construction refractory may be excessively eroded. It is important to do.

상기와 같이, 유입 시공된 부정형 내화물이 어느정도 경화한 다음, 턴디시를 서서히 예열하기 시작하여 턴디시 예열온도가 500℃에 도달하면 구로족 물질이 충진된 Y스터드의 플라스틱 부분은 소실되어 없어지고, 부정형 내화물 속에는 플라스틱이 차지하고 있던 부피만큼 Y자형으로 공간이 생기게 된다.As described above, after the inflow-formed amorphous refractory has hardened to some extent, the tundish begins to preheat gradually, and when the tundish preheating temperature reaches 500 ° C., the plastic part of the Y stud filled with the Guro group material is lost and disappeared. In the amorphous refractory, the space is made in the shape of Y as much as the volume occupied by the plastic.

이 공간부는, 표 1에 나타낸 바와 같이, 턴디시 철피의 바닥부와 약 25도의 각도로 구로족 물질과 틈새공간이 2~2.5㎜정도를 유지할 경우 턴디시 건조작업시 턴디시 내부의 수분이 외부로 잘 빠져 나오지만 틈새가 그보다 작을 경우(1~1.5㎜) 구로족 물질과 내화물간의 표면장력에 의하여 외부로 쉽게 배출되지 않아 수분제거에 좀더 많은 시간이 소요되며, 틈새가 더욱 작을 경우(1㎜이하) 턴디시 내부의 수분이 건조단계에서는 외부로 극히 미세한량만 배출되며 중간 예열시에만 수증기 형태로 배출되므로 매우 많은 열원과 시간이 소요된다.As shown in Table 1, when the Guro-type material and the clearance space are maintained at about 2 to 2.5 mm at an angle of about 25 degrees with the bottom part of the tundish hull, the water inside the tundish is external during the tundish drying operation. If the gap is smaller than that (1 ~ 1.5㎜), it is not easily discharged to the outside due to the surface tension between the Guro-group material and the refractory, so it takes more time to remove moisture, and if the gap is smaller (less than 1㎜) In the drying stage, only a very small amount of moisture is discharged to the outside and in the form of steam only during intermediate preheating, very much heat source and time are required.

설치각도
(Deg)
Installation angle
(Deg)
수분유도로
(㎜)
Water induction
(Mm)
내화물 강도Refractory strength 수분제거상태Moisture removal 비고Remarks
3535 1 이하1 or less 양호Good 극히 불량Extremely poor 강도변화 없으나
수분제거불량
No change in strength
Water removal
3030 22 양호Good 불량Bad 강도변화 없으나
수분제거 불량
No change in strength
Water removal
2525 33 양호Good 양호Good 강도변화 없으며
수변제거 양호
No change in strength
Good water removal
2020 44 보통usually 양호Good 강도저하 미미
수분제거 양호
Strength reduction
Good moisture removal
1515 55 저하Lowering 매우 양호Very good 강도저하붕괴위험
수분제거 양호
Risk of strength degradation collapse
Good moisture removal

반대로 틈새가 지나치게 클경우(3.5~4㎜) 턴디시 이동이나 유입시공 내화물속의 구로족 물질이 유동성이 생기며, 틈새가 4.5㎜이상 시에는 부정형 내화물의 강도를 떨어뜨리게 되어 내화물의 크랙발생시 유입시공 내화물의 붕괴 위험이 있으므로 적절한 틈새의 설계는 매우 중요하다.On the contrary, when the gap is too large (3.5 ~ 4㎜), the tungsten material in tundish movement or inflowing refractories creates fluidity, and when the gap is more than 4.5mm, the strength of amorphous refractory is reduced. Because of the risk of collapse, the design of a suitable gap is very important.

또한, Y스터드의 길이는 전체 유입시공 내화물 폭의 2/3를 넘지 않아야 하는데, 이는 연속주조 작업시 턴디시 용강(2)과 내화물의 접촉으로 내화물 표면 일부가 침식 되는데 유입시공 내화물이 침식되어도 용강이 Y스터드와 직접 접촉하지 않도록 하기 위함이다. 일반적으로 턴디시 유입시공 내화물의 폭은 최대 침식량의 약 10배수로 설계하므로 빌렛의 경우 턴디시 유입시공 내화물 폭은 약 200㎜이므로 최대 침식량 2㎜ 발생시에도 약68㎜의 안전폭를 확보 할 수 있게 된다.In addition, the length of the Y stud should not exceed 2/3 of the total inflow refractory width, which is a part of the surface of the refractory eroded by the contact of the tungsten molten steel (2) and the refractory during continuous casting operation. This is to avoid direct contact with this Y stud. In general, the width of the tundish inflow refractories is designed to be about 10 times the maximum erosion, so in the case of billets, the width of the twirl inflow refractories is about 200 mm, so that a safety width of about 68 mm can be ensured even when a maximum erosion amount of 2 mm occurs. do.

상술한 바와 같이, 본 발명은 턴디시에 부정형 내화물 시공시 내부 수분을 배출하기 위한 수분유도로를 Y스터드를 이용하여 형성함으로써, 턴디시 예열시 수 분제거를 효율적으로 하여 주편 내에 핀홀과 같은 수소결함이 감소되는 효과가 있으며, 턴디시의 예열작업 시간단축으로 열원의 사용량 감소, 주편품질향상, 주편터짐(Breakout)발생 감소, 과다예열에 따른 턴디시 변형 예방과 같은 효과가 있다.As described above, the present invention forms a moisture flow path for discharging the internal moisture during construction of the irregular refractory at the time of tundish by using the Y studs, thereby effectively removing moisture during preheating the tundish, so that hydrogen such as pinholes in the slab can be efficiently removed. Defects are reduced, and the preheating time of the tundish is reduced, reducing the amount of heat source used, improving the quality of the cast, reducing the occurrence of breakout, and preventing the tundish deformation due to excessive preheating.

Claims (6)

가연성의 플라스틱 재질이면서, 중공형의 파이프 형태로 제작되는 Y형 중공관과;Y-type hollow tube made of a flammable plastic material, hollow pipe shape; 상기 Y형 중공관 내부에 충진되는 불연성의 구로족 물질로 구성되는 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드.A chopped stud for forming a water passage of the tundish refractory, characterized in that consisting of a non-combustible guro group material filled in the Y-type hollow tube. 청구항 1에 있어서, 상기 Y형 중공관은 그 길이가 전체 내화물 폭의 2/3 이하의 길이로 형성되는 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드.The chopped stud for forming a water passage of a tundish refractory according to claim 1, wherein the length of the Y-shaped hollow tube is formed to be 2/3 or less of the total width of the refractory. 청구항 1에 있어서, 상기 Y형 중공관은 중앙의 메인파이프와 양측의 줄기파이프의 각도가 150~175도인 것을 특징으로 하는 턴디시 내화물의 수분통로 형성용 Y스터드.The chopped stud for forming a water passage of the tundish refractory according to claim 1, wherein the Y-shaped hollow tube has an angle of 150 to 175 degrees between a central main pipe and a stem pipe on both sides. 청구항 1 내지 청구항 3 중 어느 한 항의 Y스터드를 턴디시의 외부철피에 형성된 수분 유출홀에 삽입 고정하는 단계와;Inserting and fixing the hex stud of any one of claims 1 to 3 into a water outlet hole formed in the outer shell of the tundish; 상기 Y스터드가 고정된 턴디시에 턴디시 코어를 고정하는 단계와;Fixing a tundish core to a tundish to which the chuck is fixed; 상기 턴디시 외부철피와 턴디시 코어 사이의 공간부에 부정형 내화물을 유입시켜 경화시키는 단계와;Introducing an amorphous refractory into the space portion between the tundish outer shell and the tundish core to harden it; 상기 부정형 내화물이 경화된 턴디시를 예열하여 Y스터드의 가연성 Y형 중공관을 연소시켜 제거하여 수분 유도로를 형성하는 단계로 구성되는 것을 특징으로 하는 턴디시 내화물 시공방법.Preheating the refractory hardened tundish by burning the combustible Y-type hollow tube of the Y studs to form a moisture induction furnace comprising the step of forming a moisture induction furnace. 청구항 4에 있어서, 상기 Y스터드를 턴디시의 외부철피에 형성된 수분 유출홀에 삽입 고정하는 단계에서 상기 외부철피의 측면에 고정되는 Y스터드는 턴디시 바닥면과의 각도가 20~30도가 되도록 고정되고, 외부철피 바닥부에 고정되는 Y스터드는 줄기파이프의 사이각도가 50~60도가 되도록 고정되는 것을 특징으로 하는 되는 것을 특징으로 하는 턴디시 내화물 시공방법.The method according to claim 4, wherein in the step of fixing the chopped studs to the water outlet hole formed in the outer shell of the tundish fixed to the side of the outer sheath is fixed to the angle of the tundish bottom surface 20 to 30 degrees And, the Y stud is fixed to the outer shell bottom portion tundish refractory construction method characterized in that the angle between the stem pipe is fixed to 50 to 60 degrees. 청구항 4에 있어서, 상기 가연성 Y형 중공관을 연소시켜 제거하여 수분 유도로를 형성하는 단계는 상기 수분 유도로와 구로족 물질의 사이간격이 2~2.5㎜ 범위인 것을 특징으로 하는 턴디시 내화물 시공방법.The method of claim 4, wherein the step of forming the water induction furnace by burning the combustible Y-type hollow tube to remove the tungsten refractory construction, characterized in that the interval between the water induction furnace and the Guro group material is in the range of 2 ~ 2.5mm Way.
KR1020040018955A 2004-03-19 2004-03-19 Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same KR101038554B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040018955A KR101038554B1 (en) 2004-03-19 2004-03-19 Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040018955A KR101038554B1 (en) 2004-03-19 2004-03-19 Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same

Publications (2)

Publication Number Publication Date
KR20050093484A KR20050093484A (en) 2005-09-23
KR101038554B1 true KR101038554B1 (en) 2011-06-02

Family

ID=37274588

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040018955A KR101038554B1 (en) 2004-03-19 2004-03-19 Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same

Country Status (1)

Country Link
KR (1) KR101038554B1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100967054B1 (en) * 2007-12-11 2010-06-29 주식회사 포스코 Apparatus for removing water from fireproofing wall of molten-metal container

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0647485A (en) * 1992-08-03 1994-02-22 Kubota Corp Lost foam pattern casting method for pipe with branched pipe
JPH06331280A (en) * 1993-05-20 1994-11-29 Kawasaki Refract Co Ltd Constructing method of monolithic refractory
JPH0827505A (en) * 1994-07-13 1996-01-30 Sumitomo Metal Ind Ltd Water cooled refractory panel for repairing blast furnace wall
JPH10156517A (en) 1996-11-28 1998-06-16 Nisshin Steel Co Ltd Method for working monolithic back up lining in molten metal vessel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0647485A (en) * 1992-08-03 1994-02-22 Kubota Corp Lost foam pattern casting method for pipe with branched pipe
JPH06331280A (en) * 1993-05-20 1994-11-29 Kawasaki Refract Co Ltd Constructing method of monolithic refractory
JPH0827505A (en) * 1994-07-13 1996-01-30 Sumitomo Metal Ind Ltd Water cooled refractory panel for repairing blast furnace wall
JPH10156517A (en) 1996-11-28 1998-06-16 Nisshin Steel Co Ltd Method for working monolithic back up lining in molten metal vessel

Also Published As

Publication number Publication date
KR20050093484A (en) 2005-09-23

Similar Documents

Publication Publication Date Title
CN102912051B (en) Method for exchanging cooling wall of blast furnace taphole online
KR101038554B1 (en) Y type stud for forming water passage in the refractory of tundish and method for forming refractory of tundish using the same
CN101693388A (en) Method for casting lining of blast furnace air supply device by using lost foam
CN101439399A (en) Horizontal casting method for ultralong cast holes of cast steel and iron casting
KR100939800B1 (en) Manufacturing process for radiant tube u-bend
JP2011056559A (en) Casting method using core
KR100543546B1 (en) Lost foam pattern casting method and fiber reinforced coating
CN105903898B (en) Shell mould sintering method and device
CN112458223A (en) Blast furnace tuyere belt structure
CN108193022B (en) Method for sequentially blowing argon to prolong comprehensive service life of bottom blowing integrated air brick
KR100321033B1 (en) The Method for Repairing of Furnace's Tap Hole
JP4464789B2 (en) Refractory brick for steel making preheated before use and its heat insulation method
CN104964565A (en) Method for online repair of regenerative burner nozzle of heating furnace
CN205834112U (en) Shell mould sintering equipment
KR100832427B1 (en) An Apparatus Keeping Temperature of Probe Nozzle
CN112662829B (en) Blast furnace tuyere small sleeve and manufacturing method thereof
KR102075894B1 (en) Copper casting method
CN219818022U (en) Durable ladle upper nozzle
TWM545002U (en) Shell mold sintering device
KR20060020384A (en) Manufacturing method for high permeability investment casting mould
CN108069404A (en) Sulfur furnace and its hot line pipe method for maintaining
WO2018126502A1 (en) Shell mold sintering device and method
KR200302659Y1 (en) Oxygen Pipe Lance for Ladle Opening
CN108977603B (en) Repairing method for iron notch frame burn-through of iron-making blast furnace
KR100333904B1 (en) manufacturing method of burner and the burner thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140527

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20150527

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20160527

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20170529

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20180525

Year of fee payment: 8

LAPS Lapse due to unpaid annual fee