[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

KR100807276B1 - Slab construction method using reinforcing bar slab formwork - Google Patents

Slab construction method using reinforcing bar slab formwork Download PDF

Info

Publication number
KR100807276B1
KR100807276B1 KR1020070004844A KR20070004844A KR100807276B1 KR 100807276 B1 KR100807276 B1 KR 100807276B1 KR 1020070004844 A KR1020070004844 A KR 1020070004844A KR 20070004844 A KR20070004844 A KR 20070004844A KR 100807276 B1 KR100807276 B1 KR 100807276B1
Authority
KR
South Korea
Prior art keywords
formwork
slab
truss
reinforcing
chord
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
KR1020070004844A
Other languages
Korean (ko)
Inventor
장광윤
Original Assignee
장광윤
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 장광윤 filed Critical 장광윤
Application granted granted Critical
Publication of KR100807276B1 publication Critical patent/KR100807276B1/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/32Floor structures wholly cast in situ with or without form units or reinforcements
    • E04B5/36Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
    • E04B5/38Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor with slab-shaped form units acting simultaneously as reinforcement; Form slabs with reinforcements extending laterally outside the element
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/065Light-weight girders, e.g. with precast parts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/16Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
    • E04C5/168Spacers connecting parts for reinforcements and spacing the reinforcements from the form

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

본 발명은 철근트러스가 결합된 철근일체형 슬래브거푸집을 이용한 슬래브시공방법에 관한 것으로, 더욱 상세하게는 동바리 설치가 불필요한 철근일체형 슬래브거푸집을 소판 거푸집에서 대판 거푸집으로 완성하면서 간소하게 슬래브시공을 진행할 수 있게 한 슬래브시공방법에 관한 것이다.The present invention relates to a slab construction method using a reinforced steel slab formwork combined with a reinforcing truss, and more specifically, to complete the slab formwork from the plate formwork to the slab formwork without the need to install the copper bar can be carried out simply slab construction It is about a slab construction method.

본 발명의 철근일체형 슬래브거푸집을 이용한 슬래브시공방법은 (a)철근일체형 슬래브거푸집을 소판 거푸집으로 다수개 완성하는 단계; (b)상기 소판 거푸집 다수개를 병렬로 배열하여 대판 거푸집을 완성하는 단계; (c)병렬된 철근트러스의 하현재 또는 상현재 각각에 동시에 걸리도록 대판 거푸집(LF) 양쪽으로 양중보를 설치하는 단계; (d)양중보를 들어올리면서 크레인으로 대판 거푸집을 양중하여 슬래브 위치에 설치하는 단계; (e)상기 대판 거푸집 위로 슬래브콘크리트를 타설 양생하는 단계; 그리고, (f)고정구를 탈락시키면서 상기 대판 거푸집의 슬래브거푸집널을 탈형하는 단계;를 포함하여 이루어지는 것을 특징으로 한다.The slab construction method using the reinforcing bar slab formwork of the present invention comprises the steps of: (a) completing a plurality of reinforcing bar type slab formwork; (b) arranging a plurality of platelet formwork in parallel to complete a large formwork; (c) installing double beams on both sides of the base formwork (LF) so as to be simultaneously caught on each of the lower chords or the top chords of the parallel rebar trusses; (d) lifting the slab formwork with a crane while lifting the concession beam and installing it in the slab position; (e) curing the slab concrete onto the base formwork; And (f) demolding the slab formwork of the large formwork while dropping the fixing tool.

Description

철근일체형 슬래브거푸집을 이용한 슬래브시공방법{slab construction method using slab form with truss bar}Slab construction method using slab form with truss bar}

도 1은 본 발명에 따른 철근일체형 슬래브거푸집을 도시한 도면이다.1 is a view showing a single reinforcing bar slab formwork according to the present invention.

도 2는 본 발명에 따른 철근일체형 슬래브거푸집에서 슬래브거푸집널과 철근트러스를 결속시키는 연결구와 고정구의 다양한 실시예를 보여주는 도면이다.Figure 2 is a view showing various embodiments of the connector and the fixture for binding the slab formwork and the reinforcing truss in the reinforcing bar type slab formwork according to the present invention.

도 3 내지 도 6은 본 발명에 따른 철근일체형 슬래브거푸집을 이용한 슬래브시공방법을 보여주는 도면이다.3 to 6 is a view showing a slab construction method using a reinforced bar slab formwork according to the present invention.

<도면의 주요부분에 대한 부호의 설명><Description of the symbols for the main parts of the drawings>

100: 철근트러스 110: 상현재100: reinforced truss 110: present

120: 하현재 130: 웨브재120: present 130: web ash

200: 슬래브거푸집널 300: 연결구 200: slab formwork 300: connector

310: 철근결속부 320: 암나사부310: reinforcing bar 320: female thread

400: 고정구 500: 지지구400: fixture 500: support

SF: 소판 거푸집 LF: 대판 거푸집SF: plate formwork LF: plate formwork

LB: 양중보 B: 배력근LB: Double B

SC: 슬래브콘크리트SC: Slab Concrete

본 발명은 철근트러스가 결합된 철근일체형 슬래브거푸집을 이용한 슬래브시공방법에 관한 것으로, 더욱 상세하게는 동바리 설치가 불필요한 철근일체형 슬래브거푸집을 소판 거푸집에서 대판 거푸집으로 완성하면서 간소하게 슬래브시공을 진행할 수 있게 한 슬래브시공방법에 관한 것이다.The present invention relates to a slab construction method using a reinforcing bar truss combined slab formwork, and more specifically, to complete the slab formwork from the plate formwork to the slab formwork without the need to install the copper bar, so that the slab construction can be carried out simply It is about a slab construction method.

철근콘크리트구조는 철근과 콘크리트를 일체화한 구조로서 가장 보편적인 구조방식이다. 철근콘크리트공사는 거푸집을 설치하고 철근을 배근한 후 콘크리트를 타설하는 방법으로 진행되며, 특히 슬래브 시공함에 거푸집 설치과정에는 동바리 설치과정이 필수적으로 수반된다. 즉, 슬래브 시공을 위해서는 시공위치에 자재를 반입한 후 시공위치에서 설계에 따라 동바리로 지지하면서 거푸집을 설치하고 철근을 배근하며, 이어 콘크리트를 타설 양생시킨 후 거푸집 및 동바리를 해체하는 것이다. Reinforced concrete structure is the most common structural method integrating reinforcement with concrete. Reinforced concrete works are carried out by installing formwork, reinforcing reinforcing bars and placing concrete. In particular, the installation process of the formwork is essential to the installation process of the formwork for slab construction. In other words, for the slab construction, the material is brought into the construction location, and then the formwork is installed and the reinforcing bar is reinforced while supporting it with the copper bar according to the design at the construction site, followed by curing the concrete and dismantling the mold and the copper bar.

그러나, 동바리는 거푸집 설치와는 별도로 현장에서 직접 그 높이를 조절하면서 지지상태를 점검해야 하므로, 그 설치작업이 상당히 번거롭다. 또한, 콘크리트의 양생이 충분히 이루어진 후에야 비로소 동바리를 제거할 수 있기 때문에 동바 리가 설치된 해당층에서의 작업은 작업공간 확보에 문제가 있어 제한적일 수밖에 없다. 아울러, 다층 건축물의 시공은 하층부에 사용한 가설자재를 상층부로 운반하면서 이루어지는데, 이때 동바리는 부재 사이즈가 커 자재 운반시 불편함을 초래한다. 이와 같이 동바리 설치과정은 철근콘크리트공사에서 작업 전반에 걸쳐 시공효율성을 떨어뜨리는 하나의 요인이 된다.However, since the copper barriers need to check the support while adjusting their height directly on site, apart from the formwork installation, the installation work is quite cumbersome. In addition, since the copper bar can be removed only after sufficient curing of concrete is performed, work on the floor in which the copper bar is installed is limited due to problems in securing a working space. In addition, the construction of a multi-storey building is made while transporting the temporary materials used in the lower layer to the upper layer, where the copper group is large and the size of the member causes inconvenience in material transportation. In this way, the installation process of copper bar is one factor that lowers the construction efficiency in overall work in reinforced concrete construction.

위와 같은 동바리를 이용한 슬래브 시공방법을 개선하기 위해 철판 슬래브거푸집을 영구거푸집으로 활용하면서 철근을 미리 조립한 형태의 트러스데크를 이용한 공법이 제안되었다. 통상 트러스데크는 와렌형 트러스 내에 비렌딜형 트러스를 끼워넣는 방식으로 철근을 조립하여 철판에 용접접합하는 방법으로 제작되거나, 경사재가 하현재 아래로 연장되는 푸트를 가지는 삼각트러스 방식으로 철근을 조립하여 푸트를 철판에 용접접합하는 방법으로 제작되는 것이 일반적이며, 이러한 제작방법은 모두 철근의 피복두께를 고려하여 제안된 방법이다.In order to improve the slab construction method using the above-mentioned copper cladding, a method using a truss deck of pre-assembled reinforcing bars was proposed while using slab formwork as a permanent formwork. Normally, the truss deck is manufactured by assembling reinforcing bars by inserting non-rendil trusses into warren-type trusses and welding them to an iron plate, or by assembling reinforcing bars in a triangular truss method having a foot extending downward from the lower chord. It is common to be manufactured by the method of welding to the iron plate, all of these manufacturing methods are proposed in consideration of the coating thickness of the rebar.

하지만, 이와 같은 트러스데크를 이용한 공법은 철판이 노출되어 방청처리와 내화피복이 요구되며 슬래브거푸집의 재활용이 곤란하여 공사비가 증대되는 등 단점을 수반한다.However, such a method using the truss deck is accompanied by disadvantages, such as the steel plate is exposed and the antirust treatment and fireproof coating is required, and the construction cost is increased because it is difficult to recycle the slab formwork.

이에, 본 발명자는 종래의 트러스데크를 개선하여 철판 대신 제거용 슬래브거푸집을 사용하면서 동바리 설치가 불필요한 철근일체형 슬래브거푸집을 개발하게 되었다. Thus, the present inventors have improved the conventional truss deck to develop a reinforcing bar type slab formwork that does not need to install the copper bar while using the slab formwork for removal instead of the iron plate.

본 발명은 상기한 종래의 문제를 개선하고자 안출된 것으로서, 부재 자체의 자중과 콘크리트 하중은 물론 콘크리트 타설압과 작업하중을 충분히 지지할 수 있게 되어 동바리 설치가 불필요한 철근일체형 슬래브거푸집을 이용함으로 간편한 현장작업으로 경제적인 시공이 가능해진 슬래브시공방법을 제공하는데 기술적 목적이 있다.The present invention has been made to improve the above-mentioned conventional problems, it is possible to sufficiently support the self-loading and concrete load, as well as concrete placing pressure and work load of the member itself, the site is simple by using the reinforced slab formwork that does not need to install the copper bar The technical objective is to provide a slab construction method that enables economical construction.

본 발명의 다른 목적은 슬래브거푸집널의 착탈이 용이한 철근일체형 슬래브거푸집을 소판 거푸집에서 대판 거푸집으로 완성하면서 간소하게 슬래브시공을 진행할 수 있게 한 슬래브시공방법을 제공하는 것이다.It is another object of the present invention to provide a slab construction method that allows the slab construction to proceed with a simple slab formwork from the plate formwork to the slab formwork easily removable from the slab formwork.

삭제delete

상기한 목적달성을 위해 본 발명은, 1본의 상현재, 2본의 하현재 및 상기 상현재와 하현재를 경사지게 연결하는 한 쌍의 웨브재로 구성되며, 상기 웨브재는 연속적인 파형을 이루면서 상부의 마루가 상현재와 만나고 하부의 골이 하현재와 만나도록 접합되는 철근트러스; 상기 철근트러스의 하현재 아래에 이격하여 배치되며, 면내에 통공이 형성된 슬래브거푸집널; 상기 슬래브거푸집널 통공 위에 배치되면서 철근트러스의 하현재와 결속하는 연결구; 및, 상기 슬래브거푸집널 아래에서 통공을 통과하도록 배치되면서 상기 연결구에 탈락가능하게 결합된 고정구;를 포함하여 구성되는 철근일체형 슬래브거푸집을 이용한 방법으로서,
(a)상기 철근일체형 슬래브거푸집을 소판 거푸집으로 다수개 완성하는 단계; (b)상기 소판 거푸집 다수개를 병렬로 배열하여 대판 거푸집을 완성하는 단계; (c)병렬된 철근트러스의 하현재 또는 상현재 각각에 동시에 걸리도록 대판 거푸집(LF) 양쪽으로 양중보를 설치하는 단계; (d)양중보를 들어올리면서 크레인으로 대판 거푸집을 양중하여 슬래브 위치에 설치하는 단계; (e)상기 대판 거푸집 위로 슬래브콘크리트를 타설 양생하는 단계; 그리고, (f)고정구를 탈락시키면서 상기 대판 거푸집의 슬래브거푸집널을 탈형하는 단계;를 포함하여 이루어지는 것을 특징으로 하는 철근일체형 슬래브거푸집을 이용한 슬래브시공방법을 제공한다.
In order to achieve the above object, the present invention is composed of one upper chord, two lower chords, and a pair of web members which obliquely connect the upper chords and the lower chords, wherein the web material forms a continuous waveform in an upper portion. A reinforcing truss where the floor of the floor meets the upper chord and the lower valley meets the lower chord; A slab formwork disposed spaced below the lower chord of the reinforcing truss, the through-hole of which is formed; A connector which is disposed on the slab formwork through hole and binds to the lower chord of the reinforcing truss; And, a fixture disposed to pass through the hole under the slab formwork and detachably coupled to the connector, wherein the reinforcing bar type slab formwork is configured to include:
(a) completing a plurality of the one-piece slab formwork with plate formwork; (b) arranging a plurality of platelet formwork in parallel to complete a large formwork; (c) installing double beams on both sides of the base formwork (LF) so as to be simultaneously caught on each of the lower chords or the top chords of the parallel rebar trusses; (d) lifting the slab formwork with a crane while lifting the concession beam and installing it in the slab position; (e) curing the slab concrete onto the base formwork; And, (f) demolding the slab formwork of the large formwork while dropping the fixture; provides a slab construction method using a reinforced slab formwork, characterized in that it comprises a.

이하, 첨부한 도면 및 바람직한 실시예에 따라 본 발명을 상세히 설명한다.Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and preferred embodiments.

도 1은 본 발명에 따른 철근일체형 슬래브거푸집을 도시한 도면으로, 본 발명은 철근트러스(100), 슬래브거푸집널(200), 연결구(300) 및 고정구(400)를 포함하여 구성되며, 경우에 따라 지지구(500)를 더 포함하여 구성될 수 있다.1 is a view showing a single reinforcing bar slab formwork according to the present invention, the present invention comprises a reinforcing truss 100, a slab formwork 200, the connector 300 and the fixture 400, According to the support 500 may be configured to further include.

철근트러스(100)는 1본의 상현재(110), 2본의 하현재(120, 2본의 하현재는 약 6㎝정도의 간격으로 배치하면 적당함) 및 상기 상현재(110)와 하현재(120)를 경사지게 연결하는 한 쌍의 웨브재(130)로 구성되며, 상기 한 쌍의 웨브재(130)는 양방향으로 배치되어 연속적인 파형을 이루면서 상부의 마루는 상현재(110)와 만나고 하부의 골은 하현재(120)와 만나도록 접합된다. 이러한 철근트러스(100)는 슬래브콘크리트를 타설하는 과정에서는 콘크리트 타설하중과 작업하중을 지지하는 역할을 하고, 슬래브콘크리트를 타설한 후에는 슬래브철근으로 구조적인 내력을 발휘하는 역할을 한다. 본 발명의 철근트러스에서 철근은 통상 철근콘크리트 구조에서 사용하는 철근은 원형철근, 이형철근, 철선 등을 포괄하며, 다만 제작의 용이성을 감안할 때 상현재, 하현재, 웨브재를 철선으로 채택하여 제작하는 것이 바람직하다.Reinforcing truss 100 is one upper chord 110, two lower chords (120, two lower chords are suitable to be arranged at intervals of about 6cm) and the upper chord 110 and the lower Consists of a pair of web material 130 connecting the present 120 inclined, the pair of web material 130 is arranged in both directions to form a continuous waveform while the upper floor meets the upper chord 110 and The lower valley is joined to meet the lower chord 120. The reinforcing truss 100 serves to support the concrete placing load and the work load in the process of placing the slab concrete, and after placing the slab concrete, serves to exhibit structural strength as the slab reinforcing bar. In the reinforcing truss of the present invention, the reinforcing bar is usually used in reinforcing concrete structures, including circular reinforcing bars, deformed reinforcing bars, iron wires, etc., but considering the ease of manufacturing, it is manufactured by adopting upper and lower chords and web materials as steel wires. It is desirable to.

본 발명에서는 철근트러스(100)를 파형의 웨브재(130) 절점(마루와 골)이 상현재(110) 및 하현재(120)와 직접 만나도록 구성하고 있는데, 이는 콘크리트 타설하중과 작업하중에 의한 압축을 받는 상현재(110)의 횡변위를 충분히 지지하도록 감안한 것으로, 파형 웨브재(130)의 절점(마루와 골)이 상현재(110) 및 하현재(120)와 직접 만나기 때문에 상현재(110)에서 하현재(120)로 하중 전달이 원활하게 이루어지게 되어 상·하현재의 2차모멘트와 처짐을 줄일 수 있게 된다. 이러한 점이 종래의 트러스데크(철판에 조립철근이 접합된 것)에 적용되는 철근트러스와 다르다. 종래의 트러스데크는 바닥 철판과의 피복 두께를 유지하기 위해 경사재(웨브재)가 하현재 아래로 연장되는 푸트를 가지는 삼각트러스형태(파형 경사재의 하부 골이 하현재 아래에 위치한 형태임)의 철근트러스를 채택하였으나, 이러한 철근트러스는 상,하현재에 2차모멘트가 발생하고 처짐이 발생하였다. 본 발명에서는 파형 웨브재(130)의 절점(마루와 골)이 상현재(110) 및 하현재(120)와 만나도록 마련하여 상현재(110)와 하현재(120)의 상호간 하중전달을 극대화하는 방법으로 종래 철근트러스가 내재하는 문제를 해결하고 있으며, 특히 2본의 하현재의 좌우에 배치하는 연결구(300)가 피복두께를 확보하면서 하현재(120)를 지지하는 역할을 하기 때문에 상현재(110)의 횡변위를 효율적으로 지지할 수 있게 된다. 이와 같은 본 발명의 철근트러스(100)는 1본의 상현재(110)와 2본의 하현재(120) 및 웨브재(130)가 완전한 삼각형으로 이루어져 자립하므로 특히 현장조립이 매우 용이한 이점이 있다.In the present invention, the reinforcing truss 100 is configured so that the corrugated web material 130 nodes (floor and valleys) directly meet the upper chord 110 and the lower chord 120, which is used for concrete placing and working load. It is considered to fully support the lateral displacement of the upper chord (110) subjected to the compression by, because the node (floor and valley) of the corrugated web material 130 directly meets the upper chord (110) and the lower chord (120). Load transfer from the 110 to the lower chord 120 is made smoothly to reduce the secondary moment and deflection of the upper and lower chords. This is different from the reinforcing truss applied to the conventional truss deck (assembled steel is bonded to the steel plate). Conventional truss decks have a triangular truss shape (the lower valley of the corrugated bevel positioned below the lower chord) with a foot in which the warp member (web material) extends below the lower chord to maintain the coating thickness with the bottom plate. Reinforced truss was adopted, but the reinforced truss generated secondary moment and deflection in the upper and lower chords. In the present invention, the nodes (floor and valley) of the corrugated web material 130 are arranged to meet the upper chord 110 and the lower chord 120 to maximize the load transfer between the top chord 110 and the bottom chord 120. Solving the problems inherent in the conventional reinforcement truss, in particular, because the connector 300 arranged on the left and right of the two lower chords to support the lower chord 120 while securing the coating thickness The lateral displacement of the 110 can be efficiently supported. The rebar truss 100 of the present invention is self-standing because it is made up of a single top chord 110 and two bottom chords 120 and the web material 130 is made of a complete triangle, especially the field assembly is very easy have.

슬래브거푸집널(200)은 상기 철근트러스의 하현재(120) 아래에 이격하여 배치되며, 면내에 통공이 형성된다. 슬래브거푸집널(200)은 향후 탈형하기 때문에 재사용이 가능하므로 전체 공사비 절감에 유리한 작용을 한다. 상기 슬래브거푸집널(200)은 합판, 철판 등 어떤 재료를 사용해도 무방하다.The slab formwork 200 is disposed below the lower chord 120 of the reinforcing truss, the through-hole is formed in the plane. Since the slab formwork 200 can be reused in the future demoulding it has an advantageous effect on reducing the overall construction cost. The slab formwork 200 may use any material such as plywood, iron plate.

연결구(300)는 상기 슬래브거푸집널(200) 통공보다 큰 크기를 가지는 부재로 슬래브거푸집널(200) 통공 위에 배치되면서 철근트러스의 하현재(120)와 결합하도록 설치된다. 연결구(300)의 마련으로 철근트러스(100)의 고정 배치가 가능해지는 것은 물론 철근트러스 하현재(120)와 슬래브거푸집널(200)의 이격거리를 통해 피복두께의 확보가 가능해진다. 또한, 연결구(300)는 전술한 바와 같은 철근트러스(100, 파형의 웨브재 절점(마루와 골)이 상현재(110) 및 하현재(120)와 일치하는 형태)를 채택하는 것을 가능케 한다. The connector 300 is installed to be coupled to the lower chord 120 of the reinforcing truss while being disposed above the slab formwork 200 through the member having a larger size than the slab formwork 200 through the hole. The provision of the connector 300 allows the fixed arrangement of the reinforcing truss 100, as well as securing the coating thickness through the separation distance between the reinforcing truss lower chord 120 and the slab formwork 200. In addition, the connector 300 enables to adopt the reinforcement truss 100 (the form in which the corrugated web material nodes (floor and valley) coincide with the upper chord 110 and the lower chord 120) as described above.

상기 연결구(300)는 금속, 플라스틱(특히, PVC) 등 재료를 선택하여 제작할 수 있으며, 다만 슬래브시공 후 슬래브거푸집널(200)이 탈형될 때 연결구(300) 하부면이 노출된다는 점을 감안하면 플라스틱을 선택함이 바람직하다. 도 2에서는 다양한 형태의 연결구(300)를 보여주고 있는데, 관련해서는 후술하도록 한다.The connector 300 may be manufactured by selecting a material such as metal, plastic (particularly, PVC), but considering that the lower surface of the connector 300 is exposed when the slab formwork 200 is demolded after the slab construction. It is preferable to select a plastic. 2 shows various types of connectors 300, which will be described later.

고정구(400)는 상기 슬래브거푸집널(200) 아래에서 통공을 통과하도록 배치되면서 상기 연결구(300)에 탈락가능하게 결합되는 부재로, 연결구(300)와의 결합여부에 따라 슬래브거푸집널(200)을 고정 또는 탈형시키는 역할을 한다. 즉, 고정구가 연결구에 결속되면 연결구에 의해 슬래브거푸집널이 철근트러스에 매달려 설치되는 것이며, 고정구가 연결구에서 해체되면 슬래브거푸집널이 철근트러스에서 탈락하면서 탈형이 가능하게 되는 것이다. 고정구(400)는 연결구(300)와 마찬가지로 금속, 플라스틱(특히, PVC) 등 재료를 선택하여 제작할 수 있다.Fixture 400 is a member that is disposed to pass through the hole under the slab formwork 200 to be detachably coupled to the connector 300, the slab formwork 200 according to the coupling with the connector 300 It serves to fix or demould. In other words, when the fastener is bound to the connector, the slab formwork is installed on the reinforcement truss by the connector, and when the fastener is dismantled from the connector, the slab formwork is detached from the reinforcement truss and thus the mold can be demolished. The fixture 400 may be manufactured by selecting a material such as metal, plastic (particularly, PVC), similar to the connector 300.

상기 고정구(400)로는 상기 연결구(300)와 일체로 연장되면서 슬릿홀이 형성된 타이바와 슬래브거푸집널(200)의 통공을 통과한 타이바의 슬릿홀에 끼워져 결합하는 타이핀으로 구성할 수 있으나, 도 2에서와 같이 연결구(300)에 암나사구멍을 형성시킨 후 고정구(400)로 조임볼트로 마련하는 것이 견고하면서도 용이한 결합을 위해 바람직하다. The fastener 400 may be composed of a tie pin that is integrally extended with the connector 300 and inserted into the slit hole of the tie bar having passed through the through hole of the tie bar and the slab formwork 200 formed with a slit hole, After forming the female screw hole in the connector 300 as shown in Figure 2 it is preferable to provide a fastening bolt to the fastener 400 for a solid yet easy coupling.

한편, 본 발명에서는 연결구(300)와 비슷한 구성으로 지지구(500)를 더 포함할 것을 제안하고 있는데, 상기 지지구(500)는 슬래브거푸집널(200) 위에 배치되면서 철근트러스의 하현재(120)를 받치도록 설치되어 철근트러스(100)의 안정성을 확보케 하는 구성으로 역할하며, 이와 같은 지지구(500)는 고정구(400)와 결속하지 않는다는 점에서 연결구(300)와 차이가 있다.On the other hand, the present invention proposes to further include a support 500 in a configuration similar to the connector 300, the support 500 is disposed on the slab formwork 200 while the lower chord 120 of the reinforced truss It is installed to support the) serves to ensure the stability of the reinforcing truss 100, such a support 500 is different from the connector 300 in that it does not bind to the fixture 400.

특히, 상기 지지구(500)는 도 1에서와 같이 철근트러스의 웨브재(130) 양끝 단이 하현재(120)에 접합되도록 한 후 슬래브거푸집널(200) 양단부에서 철근트러스의 하현재(120) 중 웨브재(130) 끝단이 접합된 부분을 받치도록 설치하는 것이 바람직하다. 본원발명의 철근일체형 슬래브거푸집은 이미 안정적인 지지상태를 확보한 보거푸집 또는 브라켓 등의 지지대에 거치하면서 설치될 것인데, 이러한 설치상태를 감안할 때 철근일체형 슬래브거푸집이 받는 전체하중은 철근트러스(100)를 통해 양단부로 전달되면서 최종적으로 지지대로 전달될 것이므로, 지지구(500)를 슬래브거푸집널 양단부에 배치하면서 철근트러스의 하현재(120) 중 웨브재(130) 끝단이 접합된 부분을 받치도록 설치하면 철근트러스의 웨브재(130)에서 지지구(500)로 다시 지지대로 안정적인 하중전달이 이루어질 것으로 기대할 수 있기 때문이다. 물론, 지지구(500) 대신에 이와 유사한 연결구(300)의 설치를 고려해볼 수 있으나, 연결구(300)에는 반드시 고정구(400)가 결속되므로 슬래브거푸집널(200)의 양단부 하부에 고정구(400)가 설치되면 그 상태로 지지대 위에 거치하는 것이 곤란한 바, 이는 적절하지 못하다.In particular, the support 500 is a lower chord (120) of the reinforcing truss at both ends of the slab formwork 200 after the end of the web material 130 of the reinforcement truss as shown in Figure 1 to be bonded to the lower chord 120. It is preferable to install so that the end of the web material (130) to the bonded portion. The reinforcing bar slab formwork of the present invention will be installed while being mounted on a support such as a bobbin or a bracket, which has already secured a stable support state. Since it will be delivered to both ends through the end as it will be delivered to the support, if you install the support member 500 on both ends of the slab formwork to install the end of the web material 130 of the lower chord 120 of the reinforcing truss This is because it can be expected to achieve stable load transfer from the web material 130 of the reinforcement truss to the support 500 again. Of course, it is possible to consider the installation of a similar connector 300 instead of the supporter 500, but since the fastener 400 is necessarily bound to the connector 300, the fixture 400 in the lower end of both ends of the slab formwork 200 If is installed, it is difficult to mount on the support in that state, which is not appropriate.

도 2는 본 발명에 따른 철근일체형 슬래브거푸집에서 슬래브거푸집널(200)과 철근트러스(100)를 결속시키는 연결구(300)와 고정구(400)의 다양한 실시예를 보여주는 도면이다. 실시예 모두 연결구(300)를 철근트러스의 하현재(120)가 결속하는 상단의 철근결속부(310)와 암나사구멍이 형성된 하단의 암나사부(320)로 구성되도록 마련하면서 고정구(400)를 상기 연결구의 암나사부(320)와 나사결합하는 조임볼트로 채택한 예이며, 연결구의 철근결속부(310) 형태 및 철근트러스의 하현재(120) 와 철근결속구의 결속방법에 따라 구분하고 있다.2 is a view showing various embodiments of the connector 300 and the fixture 400 for binding the slab formwork 200 and the reinforcing truss 100 in the reinforcing bar type slab formwork according to the present invention. In the embodiment both the fastener 400 is provided to be composed of the reinforcing bar binding portion 310 of the upper end to which the lower chord 120 of the reinforcing truss is bound and the female threading portion 320 of the lower end formed with the female threaded hole (400) It is an example adopted as a tightening bolt for screwing the female thread portion 320 of the connector, and is divided according to the shape of the reinforcing bar 310 of the connector and the lower chord 120 of the reinforcing truss and the method of binding the reinforcing bar.

도 2(a)는 연결구의 철근결속부(310)를 철근트러스의 하현재(120)가 끼워져 안착하도록 안착홈으로 형성시킨 예로서, 철근트러스의 하현재(120)가 안착홈에 안착됨으로 연결구의 철근결속부(310)와 결속되는 예이다. 특히, 도 2(a)에서는 안착홈의 양 측면 동일한 위치에 관통홀이 형성되도록 마련하면서 상기 관통홀에 끼워져 결합하는 체결핀(315)을 더 마련하여 철근트러스의 하현재(120)가 체결핀(315)에 걸리면서 안착홈에서 이탈하지 않도록 처리하고 있다.2 (a) is an example in which the reinforcing bar 310 of the connector is formed as a seating groove so that the lower chord 120 of the reinforcing truss is fitted and seated, the lower chord 120 of the reinforcing truss is seated in the seating groove. This is an example of binding with the reinforcing bar binding portion 310. In particular, in Figure 2 (a) is provided so that the through-holes are formed at the same position on both sides of the seating groove, and further provided with a fastening pin 315 to be fitted into the through-hole to combine the lower chord 120 of the reinforcement truss 315 is being processed so as not to leave the seating groove.

도 2(b)는 도 2(a)와 전체적으로 동일하나 안착홈 대신에 연결구의 철근결속부(310)를 철근트러스의 하현재(120)가 기대어 설치되도록 가이드날개를 쌍줄로 돌출하여 형성시킨다는 점에서 차이가 있다. 물론 도시하고 있는 바와 같이 쌍줄 가이드날개는 양 측면 동일한 위치에 관통홀이 형성되도록 마련하고 상기 관통홀에 끼워져 결합하는 체결핀(315)을 더 마련하면, 철근트러스의 하현재(120)가 체결핀(315)에 걸리면서 쌍줄 가이드날개에서 이탈하지 않도록 처리할 수 있다.Figure 2 (b) is the same as Figure 2 (a) as a whole, but instead of the mounting groove, the reinforcing bar portion 310 of the connector is formed by protruding the guide wings in twin lines so that the lower chord 120 of the reinforcing truss is installed leaning There is a difference. Of course, as shown, the twin-row guide wings are provided so that the through-hole is formed at the same position on both sides, and further provided with a fastening pin 315 to be fitted into the through-hole, the lower chord 120 of the reinforced truss is fastening pin 315 can be processed so as not to escape from the twin-row guide wings.

도 2(c)는 도 2(a)와 전체적으로 동일하나 안착홈 대신에 연결구의 철근결속부(310)를 철근트러스의 하현재(120)를 덮으면서 정착되는 ∩자형 커버가 더 마련되도록 구성한다는 점에서 차이가 있다. 도 2(c)에서도 철근트러스 하현재(120)의 이탈을 방지하기 위해 ∩자형 커버를 양 측면 동일한 위치에 관통홀이 형성되도록 마련하면서 상기 관통홀에 체결핀(315)을 끼워 결합하고 있다.Figure 2 (c) is the same as Figure 2 (a) as a whole, but instead of the seating groove, the reinforcing bar portion 310 of the connector is configured to be provided with a more U-shaped cover that is fixed while covering the lower chord 120 of the reinforcing truss There is a difference in that. In FIG. 2 (c), the coupling pins 315 are inserted into the through holes while the U-shaped covers are formed to be formed at the same positions on both sides of the lower truss lower chord 120 so as to prevent their separation.

도 2(d)는 도 2(b)의 변형예로서 철근트러스의 하현재(120)를 쌍줄 가이드날개에 용접접합한 예이며, 도 2(e)는 도 2(d)의 변형예로서 외줄 가이드날개에 철근 트러스의 하현재(120)를 용접접합한 예이다. 물론 도시하지 않았지만, 철근트러스의 하현재(120)와 연결구(300)를 결속시키는 방법으로 철근트러스의 하현재(120)를 상기 연결구의 철근결속부(310)에 직접 용접접합하는 방법을 택할 수도 있다.FIG. 2 (d) shows an example in which the lower chord 120 of the reinforcing truss is welded to the twin-row guide blade as a modification of FIG. 2 (b), and FIG. The lower chord 120 of the rebar truss is welded to the guide vanes. Although not shown, of course, the lower chord 120 of the reinforcing truss and the connector 300 may be directly welded to the reinforcing bar 310 of the connector by binding the lower chord 120 and the connector 300. have.

도 3 내지 도 6은 본 발명에 따른 철근일체형 슬래브거푸집을 이용한 슬래브시공방법을 보여주는 도면이다.3 to 6 is a view showing a slab construction method using a reinforced bar slab formwork according to the present invention.

(a)소판 거푸집 완성단계- 도 3(a) the plate formwork completion step-Figure 3

전술한 철근일체형 슬래브거푸집을 소판 거푸집(SF)으로 다수개 완성한다. 즉, 슬래브거푸집널(200)과 철근트러스(100), 그리고 연결구(300)와 고정구(400)를 준비하여 조립하는 것이다. 물론, 소판 거푸집(SF)은 현장에서 간편하게 조립하면서 완성할 수 있을 것이다. 이때, 소판 거푸집(SF)의 크기로는 장비를 사용하지 않고 현장에서 조립할 때 작업자 2인이 1조가 되어 운반가능한 정도가 적당하며, 도 3에서는 철근트러스(100)를 3열로 배열한 상태의 소판 거푸집(SF)을 보여준다.A plurality of the above-mentioned reinforced bar slab formwork is completed by platelet formwork (SF). That is, to prepare and assemble the slab formwork 200 and the reinforcing truss 100, and the connector 300 and the fixture 400. Of course, the platelet formwork (SF) will be able to complete easily assembled on site. At this time, the size of plate formwork (SF) is suitable to transport two workers as a pair when assembling in the field without using the equipment, in Figure 3 plate plate in the state arranged the reinforcement truss 100 in three rows Show the formwork (SF).

(b)대판 거푸집 완성단계- 도 4(b) the base formwork completion step-Figure 4

소판 거푸집(SF) 다수개를 병렬로 배열하여 대판 거푸집(LF)을 완성한다. 도 4(a)에서와 같이 거치대를 마련하여 소판 거푸집(SF)의 슬래브거푸집널 상호간을 밀착시키는 방법으로 대판 거푸집(LF)을 완성하도록 한다. 본 단계에서는 도 4(b)에서와 같이 병렬된 철근트러스(100)에 교차하는 배력근(B)을 배근하는 단계를 포함할 수 있으며, 배력근(B)의 배근으로 소판 거푸집(SF) 상호간의 긴결 결합이 가능해져 해체의 우려 없는 대판 거푸집(LF)의 완성이 가능하게 된다. A large number of plate formwork (SF) is arranged in parallel to complete the large plate formwork (LF). As shown in Figure 4 (a) by providing a cradle to the slab formwork (SF) of the slab formwork to be in close contact with each other to complete the large formwork (LF). In this step, as shown in Figure 4 (b) may include the step of reinforcing the reinforcement bar (B) intersecting the parallel reinforcement truss 100, the platelet form (SF) between each other as the reinforcement of the reinforcement bar (B) Tight coupling can be achieved, which enables the completion of large formwork (LF) without fear of disassembly.

소판 거푸집에서 대판 거푸집으로의 완성은 이미 완성된 대판 거푸집에 위에서 적층시키는 방법으로도 진행할 수 있으므로, 공사의 공정에 지장이 없이 좁은 장소에서 많은 양의 대판 거푸집을 완성할 수 있을 것으로 기대된다. Since the completion of the plate formwork to the large formwork can be proceeded by laminating the finished formwork from the above, it is expected that a large amount of the formwork can be completed in a narrow place without disrupting the construction process.

(c)양중보 설치단계- 도 5(c) the step of setting up concession- Figure 5

병렬된 철근트러스의 하현재(120) 또는 상현재(110) 각각에 동시에 걸리도록 양중보(LB)를 설치한다. 양중보(LB)의 설치로 소판 거푸집(SF) 상호간의 긴결 결합이 가능해지며, 양중무게의 분산을 통해 안정적인 양중이 가능해진다. 양중보(LB)로는 휨성능이 우수한 부재를 채택하는 것이 바람직하며, 향후 제거할 수도 있으나 철근, 철골 등의 슬래브에 영구적으로 매입되는 매입형 부재를 채택할 수도 있다.A double beam (LB) is installed to be simultaneously caught by each of the lower chord 120 or the upper chord 110 of the parallel rebar truss. Due to the installation of the double beam (LB) it is possible to tight coupling between the platelet formwork (SF) mutual, and stable lifting is possible through the distribution of the weight of the weight. It is preferable to adopt a member having excellent bending performance as the double beam (LB), and may be removed in the future, but may be a buried member that is permanently embedded in slabs such as steel bars and steel frames.

특히, 본 발명에서는 도 5에서와 같이 양중보(LB)로 2본의 상현재(L1), 1본의 하현재(L2), 상현재와 하현재를 연결하는 웨브재(L3) 및 2본의 상현재 상호간을 연결하는 연결재(L4)를 포함하여 구성된 철근트러스를 채택할 것을 제안하고 있는데, 이와 같은 양중보(LB) 2개를 준비하여 이의 철근트러스 하현재(L2, 특히 웨브재의 골이 접합된 부분)를 대판 거푸집(LF)의 병렬된 철근트러스의 상현재(110) 끝단에 걸리도록 끼우는 방식으로 대판 거푸집(LF) 양쪽에 양중보(LB)를 설치하게 된다. 즉, 양중보(LB)의 철근트러스 하현재(L2)를 대판 거푸집(LF)의 병렬된 철근트러스의 상현재(110) 끝단에 걸리도록 양중보(LB) 2개를 대판 거푸집(LF) 양쪽에 끼우고 양중보(LB)의 철근트러스 2본의 상현재(L1) 중 바깥쪽 상현재에 연결끈으로 연결하여 연결끈에 크레인의 걸림고리를 건 후 양중하면, 양중 무게중심이 크레인 의 걸림고리가 위치한 대판 거푸집(LF)의 한가운데로 위치하면서 연결끈이 당겨지게 될 것이고, 연결끈이 당겨지면 양중보(LB)의 철근트러스 2본의 상현재(L1) 중 안쪽 상현재가 대판 거푸집(LF)의 병렬된 철근트러스의 상현재(110) 위를 누르면서 지지될 것이며, 이로써 양중보(LB))의 위치고정이 이루어지면서 안정적인 양중작업이 이루어지게 되는 것이다. 이때, 양중보(LB)의 철근트러스 2본의 상현재(L1)는 연결재(L4)에 의해 서로 연결 보강되어 있으므로, 양중과정에서 양중보(LB)의 철근트러스 상현재(L1)에 발생하는 압축좌굴을 억제할 수 있게 된다.Particularly, in the present invention, as shown in Fig. 5, two upper chords L1, one lower chord L2, two web chords L3 and two chords connecting the upper chord and the lower chord, as shown in Figs. It is proposed to adopt reinforcing truss including the connecting material (L4) to connect the phase currents of each other, and two such double beams (LB) are prepared, and the reinforcing truss of the lower truss (L2, especially web material) The bonded portion) is installed on both sides of the plate formwork LF so as to be fitted to the end of the upper chord 110 of the parallel reinforcement truss of the plate formwork LF. In other words, the two double beams (LB) on both sides of the large formwork (LF) so that the reinforcement truss lower chord (L2) of the double beam (LB) is caught on the end of the upper chord 110 of the parallel reinforcement truss (LF). If it is inserted into the upper stringer (L1) of the two reinforcement trusses of the double beam (LB) and connected to the outer upper string by hooking the hook of the crane on the hook, then the weight center of gravity is the hook of the crane. The connecting string will be pulled while being positioned in the middle of the plate formwork (LF) where the ring is located, and when the connecting string is pulled, the inner upper current (L1) of the two reinforcing trusses of the double beam (LB) The parallel reinforcement truss will be supported while pressing on the upper chord 110, whereby the position of the double beam (LB) is fixed while stable lifting operation is made. At this time, since the two reinforcement trusses L1 of the double beams LB are connected and reinforced with each other by the connecting member L4, the reinforcement truss upper chords L1 of the double beam LB are generated during the lifting process. Compression buckling can be suppressed.

(d)대판 거푸집 양중 설치단계- 도 5(d) step of lifting the formwork for the board-Figure 5

양중보(LB)를 들어올리면서 크레인으로 대판 거푸집(LF)을 양중하여 슬래브 위치에 설치한다. 철근트러스형 양중보와 같이 양중보(LB)로 임시 가설부재를 채택한 경우에는 본 단계에서 양중보(LB)를 제거해야 할 것이다. 대판 거푸집(LF)을 설치한 후에는 대판 거푸집 상호간을 연결하는 이음철근을 더 배근하도록 함이 바람직하다.Lifting the double beam (LB) while lifting the base plate formwork (LF) with a crane and installed in the slab position. If the temporary temporary member is adopted as a double beam (LB), such as a reinforced truss type double beam, it will be necessary to remove the double beam (LB) in this step. After installing the base formwork (LF), it is preferable to further reinforce the joint reinforcing bar connecting the base formwork with each other.

(e)슬래브콘크리트 타설 양생단계- 도 6(e) Slab concrete pouring curing step-Figure 6

대판 거푸집(LF) 위로 슬래브콘크리트(SC)를 타설 양생한다.Slab concrete (SC) is poured onto the formwork (LF).

(f)슬래브거푸집널(200) 탈형단계(f) slab formwork (200) demolding stage

슬래브콘크리트(SC)가 양생되면 고정구(400)를 탈락시키면서 상기 대판 거푸집의 슬래브거푸집널(200)을 탈형한다. 이로써, 철근콘크리트 슬래브가 완성되며, 철근콘크리트 슬래브 내에는 철근트러스(100), 연결구(300), 지지구(500)가 매입되게 된다.When the slab concrete (SC) is cured, the slab formwork 200 of the base formwork is demolded while dropping the fixture 400. As a result, the reinforced concrete slab is completed, and the reinforced truss 100, the connector 300, and the supporter 500 are embedded in the reinforced concrete slab.

이상에서 본 발명은 기재된 실시예를 참조하여 상세히 설명되었으나, 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 상기에서 설명된 기술적 사상을 벗어나지 않는 범위 내에서 여러가지 치환, 부가 및 변형이 가능할 것임은 당연한 것으로, 이와 같은 변형된 실시 형태들 역시 아래에 첨부한 특허청구범위에 의하여 정하여지는 본 발명의 보호 범위에 속하는 것으로 이해되어야 할 것이다.Although the present invention has been described in detail with reference to the described embodiments, those skilled in the art to which the present invention pertains will be capable of various substitutions, additions and modifications without departing from the technical spirit described above. It is to be understood that such modified embodiments also fall within the protection scope of the present invention as defined by the appended claims below.

이상과 같은 본 발명에 따르면 다음과 같은 효과를 기대할 수 있다.According to the present invention as described above can be expected the following effects.

첫째, 본 발명은 슬래브거푸집널에 결합되는 조립철근으로 파형 웨브재의 절점이 상현재 및 하현재에 접합된 철근트러스를 이용함으로 부재 자체의 자중과 콘크리트 하중은 물론 콘크리트 타설압과 작업하중을 충분히 지지할 수 있게 되어 동바리를 설치하지 않고 간편하면서도 신속한 슬래브시공이 가능해진다.First, the present invention fully supports the self-loading of concrete and concrete load as well as concrete placing pressure and working load by using reinforcing bar trusses of corrugated web material bonded to upper and lower chords as assembled reinforcing bars coupled to slab formwork. This makes it possible to install slabs easily and quickly without installing copper bars.

둘째, 본 발명은 슬래브거푸집널과 철근트러스의 조립이 간단하여 작업자에 의한 수작업으로 소판 거푸집에서 대판 거푸집으로 용이하게 완성하면서 간소하게 슬래브시공을 진행할 수 있게 된다.Secondly, the present invention allows the slab construction to be easily completed while the slab formwork and the reinforcement truss can be easily completed from the plate formwork to the large formwork by hand by a worker.

셋째, 본 발명은 소판 거푸집을 현장에서 적층하면서 대판 거푸집으로 완성할 수 있으므로 공사의 공정에 지장이 없이 좁은 장소에서도 다량의 대판 거푸집을 완성하면서 슬래브시공을 진행할 수 있게 된다.Third, the present invention can be completed as a large-sized formwork while laminating the formwork formwork in the field, it is possible to proceed with the slab construction while completing a large number of formwork in a narrow place without any obstacle to the construction process.

Claims (10)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 1본의 상현재(110), 2본의 하현재(120) 및 상기 상현재(110)와 하현재(120)를 경사지게 연결하는 한 쌍의 웨브재(130)로 구성되며, 상기 웨브재(130)는 연속적인 파형을 이루면서 상부의 마루가 상현재(110)와 만나고 하부의 골이 하현재(120)와 만나도록 접합되는 철근트러스(100);It consists of one upper chord 110, two lower chords 120, and a pair of web members 130 that inclined the upper chord 110 and the lower chord 120, the web material ( 130 is a reinforcing truss 100 is joined so that the upper floor meets the upper chord 110 and the lower valley meets the lower chord 120 while forming a continuous waveform; 상기 철근트러스의 하현재(120) 아래에 이격하여 배치되며, 면내에 통공이 형성된 슬래브거푸집널(200);A slab formwork 200 disposed below the lower chord 120 of the reinforcing truss and having a through hole formed in the plane; 상기 슬래브거푸집널 통공 위에 배치되면서 철근트러스의 하현재(120)와 결속하는 연결구(300); 및,A connector 300 which is disposed on the slab formwork through hole and binds to the lower chord 120 of the reinforcing truss; And, 상기 슬래브거푸집널(200) 아래에서 통공을 통과하도록 배치되면서 상기 연결구(300)에 탈락가능하게 결합된 고정구(400);를 포함하여 구성된 철근일체형 슬래브거푸집을 이용하여 슬래브를 시공하는 방법으로서,As a method of constructing a slab using a reinforced integral slab formwork comprising a; fastener 400 is disposed to pass through the hole under the slab formwork 200 to be detachably coupled to the connector 300, (a)상기 철근일체형 슬래브거푸집을 소판 거푸집(SF)으로 다수개 완성하는 단계;(a) completing a plurality of the one-piece slab formwork with platelet formwork (SF); (b)상기 소판 거푸집(SF) 다수개를 병렬로 배열하여 대판 거푸집(LF)을 완성하는 단계;(b) arranging a plurality of platelet forms (SF) in parallel to complete a plate formwork (LF); (c)병렬된 철근트러스의 하현재(120) 또는 상현재(110) 각각에 동시에 걸리도록 대판 거푸집(LF) 양쪽으로 양중보(LB)를 설치하는 단계;(c) installing double beams (LB) on both sides of the base formwork (LF) so as to be simultaneously caught on each of the lower chord 120 or the top chord 110 of the parallel rebar truss; (d)양중보(LB)를 들어올리면서 크레인으로 대판 거푸집(LF)을 양중하여 슬래브 위치에 설치하는 단계;(d) lifting the plate formwork LF with a crane while lifting the double beams LB and installing them in the slab position; (e)상기 대판 거푸집(LF) 위로 슬래브콘크리트(SC)를 타설 양생하는 단계;(e) curing the slab concrete (SC) onto the base formwork (LF); (f)고정구(400)를 탈락시키면서 상기 대판 거푸집의 슬래브거푸집널(200)을 탈형하는 단계;(f) demolding the slab formwork 200 of the base formwork while dropping the fixture 400; 를 포함하여 이루어지는 것을 특징으로 하는 철근일체형 슬래브거푸집을 이용한 슬래브시공방법.Slab construction method using a reinforcing bar integral slab formwork, characterized in that comprises a. 제8항에서,In claim 8, 상기 (b)단계는 병렬된 철근트러스(100)에 교차하는 배력근(B)을 배근하는 단계를 포함하여 이루어지는 것을 특징으로 하는 철근일체형 슬래브거푸집을 이용한 슬래브시공방법.The step (b) is a slab construction method using the integral reinforcing slab formwork, characterized in that comprising the step of reinforcing the reinforcement bar (B) intersecting the parallel rebar truss (100). 제8항에서,In claim 8, 상기 (c)단계는 양중보(LB)로 2본의 상현재(L1), 1본의 하현재(L2), 상현재와 하현재를 연결하는 웨브재(L3), 2본의 상현재를 상호 연결하는 연결재(L4)를 포함하여 구성된 철근트러스를 채택하여 양중보(LB)의 철근트러스 하현재(L2)를 대판 거푸집의 병렬된 철근트러스의 상현재(110) 끝단에 걸리도록 끼우는 방식으로 이루어지며,In the step (c), two upper chords L1, one lower chord L2, a web material L3 connecting the upper chord and the lower chord, and two upper chords with double beams LB By adopting the reinforcement truss including the interconnecting member (L4) to interconnect the reinforcement truss lower chord (L2) of the double beam (LB) to the end of the upper chord (110) of the parallel reinforcement truss of the large formwork Done, 상기 (d)단계는 상기 양중보(LB)의 철근트러스를 제거하는 단계를 포함하여 이루어지는 것을 특징으로 하는 철근일체형 슬래브거푸집을 이용한 슬래브시공방법.The step (d) is a slab construction method using the integral steel slab formwork, characterized in that comprising the step of removing the reinforcement truss of the double beam (LB).
KR1020070004844A 2006-09-18 2007-01-16 Slab construction method using reinforcing bar slab formwork Expired - Fee Related KR100807276B1 (en)

Applications Claiming Priority (6)

Application Number Priority Date Filing Date Title
KR1020060090174 2006-09-18
KR20060090174 2006-09-18
KR1020060115122 2006-11-21
KR20060115122 2006-11-21
KR20070002012 2007-01-08
KR1020070002012 2007-01-08

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR1020070118510A Division KR20080025656A (en) 2007-11-20 2007-11-20 Reinforcing bar type slab formwork and slab construction method using the same

Publications (1)

Publication Number Publication Date
KR100807276B1 true KR100807276B1 (en) 2008-02-28

Family

ID=39383293

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020070004844A Expired - Fee Related KR100807276B1 (en) 2006-09-18 2007-01-16 Slab construction method using reinforcing bar slab formwork

Country Status (1)

Country Link
KR (1) KR100807276B1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695605A (en) * 2015-03-19 2015-06-10 昆山生态屋建筑技术有限公司 Assembling type die of rib floor
CN106436996A (en) * 2016-09-26 2017-02-22 昆山生态屋建筑技术有限公司 Prestressed slab
KR20180060153A (en) * 2016-11-28 2018-06-07 노영곤 Truss Reinforced Concrete Joist Slab which is available for slab insulation
CN113202221A (en) * 2020-06-18 2021-08-03 中建二局第一建筑工程有限公司 Steel bar truss floor support plate construction system
CN113653239A (en) * 2021-09-24 2021-11-16 广东永和建设集团有限公司 Construction method of self-supporting steel bar truss template system
CN114872187A (en) * 2022-06-14 2022-08-09 四川省建筑设计研究院有限公司 Assembled coincide floor reinforcing bar rack and installation frock
CN116122478A (en) * 2023-01-17 2023-05-16 中南建筑设计院股份有限公司 A prefabricated floor formwork reinforcement integrated full-professional integrated system
CN119411734A (en) * 2025-01-08 2025-02-11 中铁十局集团城建工程有限公司 An assembled steel bar truss floor decking plate without formwork removal

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0469522U (en) * 1990-10-29 1992-06-19
JPH05256020A (en) * 1992-03-09 1993-10-05 Norihide Imagawa Network form construction for wall and floor
JPH1171817A (en) 1997-08-27 1999-03-16 Taisei Corp High-strength insert for deck plate, screw with drill, and insert construction method using these
KR20020033988A (en) * 2000-10-31 2002-05-08 이창남 Upgrading method of R.C. Structures
KR200360307Y1 (en) 2004-06-10 2004-08-25 인덱스엔지니어링 주식회사 Prefabricated slab deck using plywood
KR20050065500A (en) * 2005-06-08 2005-06-29 장광윤 Bar truss playwood deck
KR20070027431A (en) * 2005-09-06 2007-03-09 박경일 Binding tool for fixing rebar assemblies, formwork and ceiling panels by spot welding
JP2007093025A (en) * 2005-09-27 2007-04-12 Showa Denko Kk Heat exchanger and its manufacturing method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0469522U (en) * 1990-10-29 1992-06-19
JP2536267Y2 (en) * 1990-10-29 1997-05-21 株式会社長谷工コーポレーション Driving formwork for floor slabs and connecting device for self-supporting truss-like reinforcing bars
JPH05256020A (en) * 1992-03-09 1993-10-05 Norihide Imagawa Network form construction for wall and floor
JPH1171817A (en) 1997-08-27 1999-03-16 Taisei Corp High-strength insert for deck plate, screw with drill, and insert construction method using these
KR20020033988A (en) * 2000-10-31 2002-05-08 이창남 Upgrading method of R.C. Structures
KR200360307Y1 (en) 2004-06-10 2004-08-25 인덱스엔지니어링 주식회사 Prefabricated slab deck using plywood
KR20050065500A (en) * 2005-06-08 2005-06-29 장광윤 Bar truss playwood deck
KR20070027431A (en) * 2005-09-06 2007-03-09 박경일 Binding tool for fixing rebar assemblies, formwork and ceiling panels by spot welding
JP2007093025A (en) * 2005-09-27 2007-04-12 Showa Denko Kk Heat exchanger and its manufacturing method

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104695605A (en) * 2015-03-19 2015-06-10 昆山生态屋建筑技术有限公司 Assembling type die of rib floor
CN106436996A (en) * 2016-09-26 2017-02-22 昆山生态屋建筑技术有限公司 Prestressed slab
CN106436996B (en) * 2016-09-26 2019-05-21 昆山生态屋建筑技术有限公司 A kind of pre-stress floor
KR20180060153A (en) * 2016-11-28 2018-06-07 노영곤 Truss Reinforced Concrete Joist Slab which is available for slab insulation
CN113202221A (en) * 2020-06-18 2021-08-03 中建二局第一建筑工程有限公司 Steel bar truss floor support plate construction system
CN113653239A (en) * 2021-09-24 2021-11-16 广东永和建设集团有限公司 Construction method of self-supporting steel bar truss template system
CN114872187A (en) * 2022-06-14 2022-08-09 四川省建筑设计研究院有限公司 Assembled coincide floor reinforcing bar rack and installation frock
CN114872187B (en) * 2022-06-14 2024-05-28 四川省建筑设计研究院有限公司 Assembled coincide floor steel reinforcement rack and installation frock
CN116122478A (en) * 2023-01-17 2023-05-16 中南建筑设计院股份有限公司 A prefabricated floor formwork reinforcement integrated full-professional integrated system
CN119411734A (en) * 2025-01-08 2025-02-11 中铁十局集团城建工程有限公司 An assembled steel bar truss floor decking plate without formwork removal

Similar Documents

Publication Publication Date Title
KR20080025656A (en) Reinforcing bar type slab formwork and slab construction method using the same
KR100807276B1 (en) Slab construction method using reinforcing bar slab formwork
KR101937680B1 (en) Prefabricated Precast Structure and Construction Method Thereof
KR101086222B1 (en) PC slabs for building structures with set reinforcement
WO2009011516A2 (en) Form with reinforcing bars, non-support form system and non-support construction method using the same
KR101408545B1 (en) Half precast floor plank, and slab construction method using same
KR101067001B1 (en) Slab construction method of steel box girder bridge using rebar
KR102243984B1 (en) Non-supporting formwork system for retaining wall using self-supporting form and construction method thereof
KR101645462B1 (en) Precast crossing beam manufacturing method for bridge and precast crossing beam construction method for bridge
KR100343960B1 (en) Steel concrete structure
KR101004617B1 (en) Construction method of steel slab base plate and composite bridge using temporary steel reinforcement rib and permanent concrete reinforcement rib
CN110392758B (en) Inverted T-shaped section mixed prestressed concrete beam and panel construction method using same
KR100593664B1 (en) Prestressed Composite Floorboard Construction Method
KR20200136127A (en) Deck plate wall installation method using underground pavement
KR101036177B1 (en) Construction method of building structure using PPC composite method
KR20080093261A (en) Steel composite bridge construction method
KR101324884B1 (en) Hybrid building construction method combining dry type and wet type
KR100652353B1 (en) Construction method of floor slab of concrete building
KR102695935B1 (en) Deck-half beam module integrated preassembly module
KR20060022322A (en) Composite bottom plate and its connection structure
KR101058906B1 (en) Synthetic deck plate for maintenance and composite floor plate construction method
CN113863487B (en) Construction process for connecting joints of beam-end steel concrete combined notched beam and primary and secondary beams
KR101676841B1 (en) Steel Beam of Asymmetric Variable Section for Installation of High Deck Slab
KR102294174B1 (en) Temporary structure and construction method for formwork
KR102551807B1 (en) Construction method of post-tensioned PC beam system

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20070116

PA0201 Request for examination
E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20070921

Patent event code: PE09021S01D

A107 Divisional application of patent
PA0107 Divisional application

Comment text: Divisional Application of Patent

Patent event date: 20071120

Patent event code: PA01071R01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20080130

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20080219

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20080219

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
G170 Re-publication after modification of scope of protection [patent]
PG1701 Publication of correction
J204 Request for invalidation trial [patent]
PJ0204 Invalidation trial for patent

Patent event date: 20101004

Comment text: Request for Trial

Patent event code: PJ02042R01D

Patent event date: 20080219

Comment text: Registration of Establishment

Patent event code: PJ02041E01I

Appeal kind category: Invalidation

Request date: 20101004

Decision date: 20110110

Appeal identifier: 2010100002455

J121 Written withdrawal of request for trial
PJ1201 Withdrawal of trial

Patent event code: PJ12011R01D

Patent event date: 20110110

Comment text: Written Withdrawal of Request for Trial

Appeal identifier: 2010100002455

Request date: 20101004

Appeal kind category: Invalidation

Decision date: 20110110

FPAY Annual fee payment

Payment date: 20110216

Year of fee payment: 4

PR1001 Payment of annual fee

Payment date: 20110216

Start annual number: 4

End annual number: 4

LAPS Lapse due to unpaid annual fee
PC1903 Unpaid annual fee