KR100555251B1 - The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this - Google Patents

The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this Download PDF

Info

Publication number
KR100555251B1
KR100555251B1 KR1020040113474A KR20040113474A KR100555251B1 KR 100555251 B1 KR100555251 B1 KR 100555251B1 KR 1020040113474 A KR1020040113474 A KR 1020040113474A KR 20040113474 A KR20040113474 A KR 20040113474A KR 100555251 B1 KR100555251 B1 KR 100555251B1
Authority
KR
South Korea
Prior art keywords
fixing block
tension
mold
steel
delete delete
Prior art date
Application number
KR1020040113474A
Other languages
Korean (ko)
Inventor
노윤근
Original Assignee
노윤근
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 노윤근 filed Critical 노윤근
Priority to KR1020040113474A priority Critical patent/KR100555251B1/en
Application granted granted Critical
Publication of KR100555251B1 publication Critical patent/KR100555251B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced
    • E01D2101/28Concrete reinforced prestressed
    • E01D2101/285Composite prestressed concrete-metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

본 발명은 빔의 단부쪽 양측면에 측면돌출 정착블록을 정착하고, 단부에 단부 보강 겸용 솔플레이트를 설치하여 프리스트레스트 콘크리트빔의 역학적 한계를 극복하고, 시공성을 단순하게 한 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법을 제공하는데 그 목적이 있다.The present invention is to fix the side protrusion fixing block on both sides of the end of the beam, and to install the sole reinforcing sole plate at the end to overcome the mechanical limitations of the prestressed concrete beam, the side protrusion fixing capable of multi-purpose tensioning simple construction The purpose of the present invention is to provide a mold in which a block is fixed and a bridge construction method using the same.

상기한 목적을 달성하기 위한 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형은 상ㆍ하부플랜지 및 복부로 이루어지는 빔과; 상기 빔의 단부측 소정위치에 PC강재를 긴장시키기 위한 긴장력을 도입할 수 있도록 설치된 1차 인장용 정착구와; 상기 빔의 상부플랜지 일측단에 일정한 크기의 단위 빔의 연속화를 위해 고정 설치된 연속화 강재와; 상기 빔의 상부플랜지에 길이방향으로 고정 설치된 보강재와; 상기 빔의 양측면에 일정한 폭과 너비로 돌출 설치된 정착블록과; 상기 빔의 하부플랜지 일측단에 고정 설치된 단부 보강 겸용 솔플레이트로 구성됨을 특징으로 한다.To achieve the above object, a mold in which a multi-purpose tensionable side protrusion fixing block is fixed according to the present invention includes a beam consisting of upper and lower flanges and an abdomen; A primary tension fixing device installed to introduce a tension force for tensioning the PC steel at a predetermined position on the end side of the beam; A continuous steel fixedly installed at one end of the upper flange of the beam for continuation of a unit beam of a predetermined size; A reinforcement member fixed to the upper flange of the beam in the longitudinal direction; A fixing block protruding from both sides of the beam with a predetermined width and width; Characterized in that the end reinforcement combined sole plate fixed to one side of the lower flange of the beam.

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형을 이용한 교량시공방법은 빔을 형성하기 위하여 철근을 조립하는 단계(Ⅰ); 상기 조립된 철근 빔의 양측면에 다목적 인장용 측면돌출 정착블록을 부착하고, 주형의 양단부 소정위치에 1차 인장용 정착구를 설치하면서 PC강재를 연결하고, 상기 정착블록의 상단부에 연속화를 위하여 상하로 연속화 1차 및 2차 인장용 정착구를 설치하고, 상기 정착블록의 하단부에 주형의 2차 인장 용 정착구를 설치하고, 상기 2차 인장용 정착구의 바로 위에 유지관리용 정착구를 설치한 후, 빔의 상부플랜지에 일정한 길이를 갖는 보강재를 설치한 후에, 콘크리트를 타설 양생시켜 빔을 제작하고 1차 인장을 하는 단계(Ⅱ); 상기 제작된 빔을 교각 및 교대에 설치하고, 중앙의 교각에서는 인접하여 설치된 빔과 빔의 연결하기 위하여 상부플랜지내에 설치된 보강재를 연속화 강재와 고장력볼트로 연결하여 연속화 연결부를 설치하는 단계(Ⅲ); 상기 연속화 연결부에 콘크리트를 충전하면서 상기 빔과 빔의 측면에서 서로 접하는 부분은 에폭시 주입하거나 무수축몰탈을 충전하여 밀착시켜 마감하는 단계(Ⅳ); 상기 빔의 양측면에 부착된 정착블록 상단부내에 있는 연속화 1차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 빔의 연속화 1차 긴장을 한 후에 슬래브를 타설하여 양생시키는 단계(Ⅴ); 상기 슬래브 타설 양생후 정착블록 하단부에 있는 2차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 빔의 2차 긴장을 하는 단계(Ⅵ); 연속화 2차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 연속화 2차 인장을 하는 단계(Ⅶ)로 이루어짐을 특징으로 한다.In addition, the bridge construction method using a mold fixed to the multi-purpose side-projection fixing block according to the present invention for achieving the above object comprises the steps of assembling the reinforcing bars to form a beam (I); Attaching the multi-purpose tensioning side protruding fixing block to both sides of the assembled reinforcing beam, and connecting the PC steel while installing the primary tensioning fixture in the predetermined position at both ends of the mold, and up and down for continuity at the upper end of the fixing block After installing the sequential primary and secondary tension anchorages, installing the secondary tension anchorage of the mold at the lower end of the anchoring block, and installing the maintenance anchorage just above the secondary tension anchorage, After installing the reinforcement having a certain length in the upper flange, the step of curing the concrete to make a beam and the first tension (II); Installing the fabricated beams on bridge piers and alternating bridges, and connecting the reinforcement installed in the upper flange with the continuous steel and the high-strength bolt in order to connect the beams and the beams installed adjacent to each other (III); Filling the continuous connection portion with concrete and contacting each other at the side of the beam and the side of the beam by epoxy injection or filling with non-shrink mortar to close the finish (IV); (V) placing and curing the slab after introducing the tension force into the PC steel connected to the sequential primary tension anchorage in the upper end of the fixing block attached to both sides of the beam to perform the sequential primary tension of the beam; Performing secondary tension of the beam by introducing a tension force to the PC steel connected to the secondary tension anchor at the lower end of the anchoring block after curing the slab; It is characterized by consisting of a step (Ⅶ) of the continuous secondary tension by introducing a tension force to the PC steel connected to the continuous secondary tension anchorage.

다목적 인장, 측면돌출, 정착블록, 주형, 교량시공방법Multi-purpose tensile, side extrusion, fixing block, mold, bridge construction method

Description

다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법{The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this}The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this}

도 1은 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형으로 이루어진 2경간 연속교를 도시한 예시도, 1 is an exemplary view showing a two-span continuous bridge made of a mold in which a multi-purpose tensionable side protrusion fixing block according to the present invention is fixed;

도 2는 도 1의 연결부를 확대 도시한 상세도, 2 is an enlarged detailed view of the connection part of FIG. 1;

도 3은 도 1의 A-A선 단면도, 3 is a cross-sectional view taken along the line A-A of FIG.

도 4는 도 1의 B-B선 단면도, 4 is a cross-sectional view taken along the line B-B of FIG.

도 5는 도 1의 C-C선 단면도,5 is a cross-sectional view taken along the line C-C of FIG.

도 6은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 보강재를 도시한 사시도, Figure 6 is a perspective view showing the reinforcement of the mold fixed to the side protrusion fixing block according to the present invention,

도 7은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 보강재를 도시한 측면도, Figure 7 is a side view showing the reinforcement of the mold is fixed to the side protrusion fixing block according to the present invention,

도 8a 내지 8f는 본 발명의 다양한 측면돌출 정착블록을 도시한 예시도, 8a to 8f are exemplary views showing various side protrusion fixing blocks of the present invention;

도 9a 내지 도 9j는 본 발명의 다양한 측면돌출 정착블록에 쐐기형태의 돌출블록이 부가된 형태를 도시한 예시도,Figures 9a to 9j is an illustration showing a form in which the protruding block of the wedge shape is added to the various side protrusion fixing block of the present invention,

도 10은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 사시도, 10 is a perspective view showing the end reinforcement combined sole plate of the mold is fixed to the side protrusion fixing block according to the present invention,

도 11은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 측면도,11 is a side view showing an end reinforcement combined sole plate of a mold having a side protrusion fixing block according to the present invention,

도 12는 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형으로 이루어진 3경간 연속교를 도시한 예시도,12 is an exemplary view showing a three-span continuous bridge made of a mold in which a multi-purpose tensionable side protrusion fixing block according to the present invention is fixed;

도 13은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 사시도,Figure 13 is a perspective view showing the end reinforcement combined sole plate of the mold is fixed to the side protrusion fixing block according to the present invention,

도 14는 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 측면도,14 is a side view showing an end reinforcement combined sole plate of a mold having a side protrusion fixing block according to the present invention;

도 15는 본 발명에 따른 측면돌출 정착블록이 정착된 주형에 솔플레이트가 설치된 상태를 도시한 측면도. Figure 15 is a side view showing a state in which the sole plate is installed in the mold fixed side projection fixing block according to the present invention.

-도면의 주요부분에 대한 부호의 설명- Explanation of symbols on the main parts of the drawing

10 : 빔 12 : 상부플랜지10 beam 12 upper flange

14 : 하부플랜지 16 : 복부14: lower flange 16: abdomen

20 : PC강재 30 : 1차 인장용 정착구20: PC steel 30: primary tension fixing device

32 : 연속화 1차 인장용 정착구 34 : 연속화 2차 인장용 정착구32: continuous primary tension fixing device 34: continuous secondary tension fixing device

35 : 2차 인장용 정착구 및 연속화 1차 인장용 정착구 35: secondary tension anchorage and continuous primary tension anchorage

36 : 2차 인장용 정착구 38 : 유지관리용 정착구36: secondary tension anchorage 38: maintenance anchorage

39a : 정모멘트부 유지관리용 정착구 39a: Fixture for maintaining constant moment part

39b : 부모멘트부 유지관리용 정착구39b: Fixture for maintenance of parent section

40 : 연속화 강재 42 : 고장력볼트40: continuous steel 42: high tension bolt

50 : 보강재 52 : 판체50: reinforcing material 52: plate

54 : 스터드볼트 56 : 천공부54: stud bolt 56: drilling part

60 : 정착블록 62 : 돌출부60: fixing block 62: protrusion

70 : 단부 보강 겸용 솔플레이트 72 : 수평판70: end plate combined sole plate 72: horizontal plate

74 : 수직판 75 : 절곡판74: vertical plate 75: bending plate

76 : 스터드볼트 78 : 정착구76: stud bolt 78: anchorage

79 : 정착판 82 : 교각79: fixing plate 82: pier

84 : 교대 86 : 연속화 연결부84: shift 86: serial connection

88 : 교좌장치88: chair device

본 발명은 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법에 관한 것으로, 특히 빔의 단부쪽 양측면에 측면돌출 정착블록을 정착하고, 단부에 단부 보강 겸용 솔플레이트를 설치하여 프리스트레스트 콘크리트빔의 역학적 한계를 극복하고, 시공성을 단순하게 한 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법에 관한 것이다.The present invention relates to a mold in which a lateral protrusion fixing block capable of multi-purpose tension is fixed and a bridge construction method using the same. In particular, the lateral protrusion fixing block is fixed to both sides of an end of a beam, and an end reinforcing sole plate is installed at an end. The present invention relates to a mold on which side projection fixing blocks capable of multi-purpose tensioning which overcomes the mechanical limitations of prestressed concrete beams and simplify construction, and a bridge construction method using the same.

일반적으로 철근 콘크리트에 강연선을 설치하여 긴장력을 도입한 프리스트레스트 콘크리트빔은 강연선에 긴장력을 도입할 경우에는 프리스트레스트 콘크리트빔의 상부에 인장력에 의한 균열로 인하여 강연선을 도입할 수 있는 긴장력에 한계가 있으며, 또한 프리스트레스트 콘크리트빔의 지간이 짧아지면서 프리스트레스트 콘크리트빔의 높이가 커지는 문제점이 있다.In general, prestressed concrete beams in which tension wires are introduced by installing a stranded wire in reinforced concrete have a limitation in the tension force that can introduce the stranded wires due to cracking due to tensile force on the upper part of the prestressed concrete beams when a tensioning force is introduced into the stranded wires. In addition, there is a problem in that the height of the prestressed concrete beam is increased while the interval of the prestressed concrete beam is shortened.

또한, 교량은 시간이 경과함에 따라 프리스트레스트 콘크리트빔에 작용하는 정모멘트에 의하여 발생되는 인장력을 견디지 못하여 프리스트레스트 콘크리트빔의 하부에 균열이 발생되어, 교량으로서의 역할을 다하지 못하는 문제점이 있다.In addition, the bridge is not able to withstand the tensile force generated by the static moment acting on the prestressed concrete beam over time, so that a crack is generated in the lower portion of the prestressed concrete beam, there is a problem that does not serve as a bridge.

그리고, 교량은 균열로 인하여 철근이 부식이 발생될 뿐만 아니라 대기오염으로 인한 콘크리트와 철근과의 부착력이 떨어짐으로써 프리스트레스트 콘크리트빔의 강도에 심각한 영향을 주어, 교량의 내구연한을 감소시키는 문제가 있다.In addition, the bridge not only causes corrosion of reinforcing bars due to cracking, but also has a problem of seriously affecting the strength of the prestressed concrete beam by reducing adhesion between concrete and reinforcing bars due to air pollution, thereby reducing the durability of the bridge. .

이에, 본 발명은 상기한 바와 같은 제문제점을 해결하기 위해 안출된 것으로써, 빔의 단부쪽 양측면에 측면돌출 정착블록을 정착하고, 단부에 단부 보강 겸용 솔플레이트를 설치하여 프리스트레스트 콘크리트빔의 역학적 한계를 극복하고, 시공성을 단순하게 한 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법을 제공하는데 그 목적이 있다.Therefore, the present invention has been made to solve the problems described above, by fixing the side projection fixing block on both sides of the end side of the beam, by installing the end plate for both ends reinforcement sole plate dynamics of the prestressed concrete beam The object of the present invention is to provide a mold in which a lateral protrusion fixing block capable of multipurpose tensioning, which overcomes limitations and simplifies workability, and a bridge construction method using the same.

상기한 목적을 달성하기 위한 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형은 상ㆍ하부플랜지 및 복부로 이루어지는 빔과; 상기 빔 의 단부측 소정위치에 PC강재를 긴장시키기 위한 긴장력을 도입할 수 있도록 설치된 1차 인장용 정착구와; 상기 빔의 상부플랜지 일측단에 일정한 크기의 단위 빔의 연속화를 위해 고정 설치된 연속화 강재와; 상기 빔의 상부플랜지에 길이방향으로 고정 설치된 보강재와; 상기 빔의 양측면에 일정한 폭과 너비로 돌출 설치된 정착블록과; 상기 빔의 하부플랜지 일측단에 고정 설치된 단부 보강 겸용 솔플레이트로 구성됨을 특징으로 한다.To achieve the above object, a mold in which a multi-purpose tensionable side protrusion fixing block is fixed according to the present invention includes a beam consisting of upper and lower flanges and an abdomen; A primary tension fixing device installed to introduce a tension force for tensioning the PC steel at a predetermined position at the end side of the beam; A continuous steel fixedly installed at one end of the upper flange of the beam for continuation of a unit beam of a predetermined size; A reinforcement member fixed to the upper flange of the beam in the longitudinal direction; A fixing block protruding from both sides of the beam with a predetermined width and width; Characterized in that the end reinforcement combined sole plate fixed to one side of the lower flange of the beam.

또한, 상기한 목적을 달성하기 위한 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형을 이용한 교량시공방법은 빔을 형성하기 위하여 철근을 조립하는 단계(Ⅰ); 상기 조립된 철근 빔의 양측면에 다목적 인장용 측면돌출 정착블록을 부착하고, 주형의 양단부 소정위치에 1차 인장용 정착구를 설치하면서 PC강재를 연결하고, 상기 정착블록의 상단부에 연속화를 위하여 상하로 연속화 1차 및 2차 인장용 정착구를 설치하고, 상기 정착블록의 하단부에 주형의 2차 인장용 정착구를 설치하고, 상기 2차 인장용 정착구의 바로 위에 유지관리용 정착구를 설치한 후, 빔의 상부플랜지에 일정한 길이를 갖는 보강재를 설치한 후에, 콘크리트를 타설 양생시켜 빔을 제작하고 1차 인장을 하는 단계(Ⅱ); 상기 제작된 빔을 교각 및 교대에 설치하고, 중앙의 교각에서는 인접하여 설치된 빔과 빔의 연결하기 위하여 상부플랜지내에 설치된 보강재를 연속화 강재와 고장력볼트로 연결하여 연속화 연결부를 설치하는 단계(Ⅲ); 상기 연속화 연결부에 콘크리트를 충전하면서 상기 빔과 빔의 측면에서 서로 접하는 부분은 에폭시 주입하거나 무수축몰탈을 충전하여 밀착시켜 마감하는 단계(Ⅳ); 상기 빔의 양측면에 부착된 정착블록 상단부 내에 있는 연속화 1차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 빔의 연속화 1차 긴장을 한 후에 슬래브를 타설하여 양생시키는 단계(Ⅴ); 상기 슬래브 타설 양생후 정착블록 하단부에 있는 2차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 빔의 2차 긴장을 하는 단계(Ⅵ); 연속화 2차 인장용 정착구에 연결된 PC강재에 긴장력을 도입하여 연속화 2차 긴장을 하는 단계(Ⅶ)로 이루어짐을 특징으로 한다.In addition, the bridge construction method using a mold fixed to the multi-purpose side-projection fixing block according to the present invention for achieving the above object comprises the steps of assembling the reinforcing bars to form a beam (I); Attaching the multi-purpose tensioning side protruding fixing block to both sides of the assembled reinforcing beam, and connecting the PC steel while installing the primary tensioning fixture in the predetermined position at both ends of the mold, and up and down for continuity at the upper end of the fixing block After installing the sequential primary and secondary tension anchorages, installing the secondary tension anchorage of the mold at the lower end of the anchoring block, and installing the maintenance anchorage just above the secondary tension anchorage, After installing the reinforcement having a certain length in the upper flange, the step of curing the concrete to make a beam and the first tension (II); Installing the fabricated beams on bridge piers and alternating bridges, and connecting the reinforcement installed in the upper flange with the continuous steel and the high-strength bolt in order to connect the beams and the beams installed adjacent to each other (III); Filling the continuous connection portion with concrete and contacting each other at the side of the beam and the side of the beam by epoxy injection or filling with non-shrink mortar to close the finish (IV); (V) placing and curing the slab after introducing the tension force into the PC steel connected to the sequential primary tension anchorage in the upper end of the fixing block attached to both sides of the beam to perform the sequential primary tension of the beam; Performing secondary tension of the beam by introducing a tension force to the PC steel connected to the secondary tension anchor at the lower end of the anchoring block after curing the slab; It is characterized by consisting of the step (Ⅶ) to introduce the tension force to the PC steel connected to the sequential secondary tension anchorage.

이하, 본 발명을 첨부한 예시도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the accompanying drawings, the present invention will be described in detail.

도 1은 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형으로 이루어진 2경간 연속교를 도시한 예시도이며, 도 2는 도 1의 연결부를 확대 도시한 상세도이며, 도 3은 도 1의 A-A선 단면도이며, 도 4는 도 1의 B-B선 단면도이며, 도 5는 도 1의 C-C선 단면도이다.Figure 1 is an exemplary view showing a two-span continuous bridge made of a mold fixed to the multi-purpose stretchable side projection fixing block according to the present invention, Figure 2 is an enlarged view showing the connecting portion of Figure 1, Figure 3 It is AA sectional drawing of FIG. 1, FIG. 4 is sectional drawing of BB line of FIG. 1, and FIG. 5 is sectional drawing of CC line of FIG.

이들 도면에 도시된 바와 같이, 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형은 상ㆍ하부플랜지(12, 14) 및 복부(16)로 이루어지는 빔(10)과; 상기 빔(10)의 양단부측 소정위치에 PC강재(20)를 긴장시키기 위한 긴장력을 도입할 수 있도록 설치된 1차 인장용 정착구(30)와; 상기 빔(10)의 상부플랜지(12) 일측단에 일정한 크기의 단위 빔(10)의 연속화를 위해 고정 설치된 연속화 강재(40)와; 상기 빔(10)의 상부플랜지(12)에 길이방향으로 고정 설치된 보강재(50)와; 상기 빔(10)의 단부쪽 양측면에 일정한 폭과 너비로 돌출 설치된 정착블록(60)과; 상기 빔(10)의 하부플랜지(14) 일측단에 고정 설치된 단부 보강 겸 용 솔플레이트(70)로 구성된다.As shown in these figures, the mold on which the multi-purpose tensionable side protrusion fixing block is fixed according to the present invention includes a beam 10 including upper and lower flanges 12 and 14 and an abdomen 16; A primary tension fixing device (30) installed to introduce a tension force for tensioning the PC steel (20) at predetermined positions at both ends of the beam (10); A continuous steel member 40 fixedly installed at one end of the upper flange 12 of the beam 10 for continuity of the unit beam 10 having a predetermined size; A reinforcement member 50 fixedly installed in the longitudinal direction on the upper flange 12 of the beam 10; A fixing block (60) protruding from both sides of the end portion of the beam (10) at a predetermined width and width; The lower flange 14 of the beam 10 is fixed to one end of the end reinforcement combined sole plate 70 is composed of.

상기한 바와 같은 구성으로 이루어진 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형을 이용한 교량시공방법은 빔(10)을 형성하기 위하여 철근을 조립하는 단계(Ⅰ); 상기 조립된 철근 빔의 양측면에 다목적 인장용 측면돌출 정착블록(60)을 부착하고, 주형의 양단부 소정위치에 1차 인장용 정착구(30)를 설치하면서 PC강재(20)를 연결하고, 상기 정착블록(60)의 상단부에 연속화를 위하여 상하로 연속화 1차 및 2차 인장용 정착구(32, 34)를 설치하고, 상기 정착블록(60)의 하단부에 주형의 2차 인장용 정착구(36)를 설치하고, 상기 2차 인장용 정착구(36)의 바로 위에 유지관리용 정착구(38)를 설치한 후, 빔(10)의 상부플랜지(12)의 일측단부에 일정한 길이를 갖는 보강재(50)를 설치한 후에, 콘크리트를 타설 양생시켜 빔(10)을 제작하고 1차 인장을 하는 단계(Ⅱ); 상기 제작된 빔(10)을 교각(82) 및 교대(84)에 설치하고, 중앙의 교각(82)에서는 인접하여 설치된 빔(10)과 빔(10)의 연결하기 위하여 상부플랜지(12)내에 설치된 보강재(50)를 연속화 강재(40)와 고장력볼트(42)로 연결하여 연속화 연결부(86)를 설치하는 단계(Ⅲ); Bridge construction method using a mold fixed to the multi-purpose tensionable side protrusion fixing block according to the present invention having the configuration as described above step (I) assembling the reinforcing bars to form the beam (10); Attaching the multi-purpose tension side projection fixing block 60 on both sides of the assembled reinforcing beam, connecting the PC steel 20 while installing the primary tension fixing device 30 at both ends of the mold predetermined position, the fixing The continuous primary and secondary tension fixing devices 32 and 34 are installed vertically on the upper end of the block 60, and the secondary tension fixing device 36 of the mold is disposed on the lower end of the fixing block 60. After installing the maintenance anchorage 38 immediately above the secondary tension anchorage 36, a reinforcing material 50 having a predetermined length at one end of the upper flange 12 of the beam 10 After installation, the step of curing the concrete to make the beam 10 and the first tension (II); The fabricated beam 10 is installed in the pier 82 and the alternating 84, and in the central pier 82 in the upper flange 12 to connect the beam 10 and the beam 10 installed adjacently. Connecting the installed reinforcing material 50 to the continuous steel 40 and the high tension bolt 42 to install the continuous connection part 86 (III);

상기 연속화 연결부(86)에 콘크리트를 충전하면서 상기 빔(10)과 빔(10)의 측면에서 서로 접하는 부분은 에폭시 주입하거나 무수축몰탈을 충전하여 밀착시켜 마감하는 단계(Ⅳ);Filling the continuous connection portion 86 with concrete while contacting each other on the side of the beam 10 and the side of the beam 10 by epoxy injection or filling with non-condensation mortar to close the finishing portion (IV);

상기 빔(10)의 양측면에 부착된 정착블록(60) 상단부내에 있는 연속화 1차 인장용 정착구(32)에 연결된 PC강재(20)에 긴장력을 도입하여 빔(10)의 연속화 1차 긴장을 한 후에 슬래브를 타설하여 양생시키는 단계(Ⅴ); 상기 슬래브 타설 양생후 정착블록(60) 하단부에 있는 2차 인장용 정착구(36)에 연결된 PC강재(20)에 긴장력을 도입하여 빔(10)의 2차 긴장을 하는 단계(Ⅵ); Tension force is introduced into the PC steel 20 connected to the sequential primary tension fixing device 32 in the upper end of the fixing block 60 attached to both sides of the beam 10, so that the sequential primary tension of the beam 10 is applied. (V) after pouring the slab to cure; (II) applying a tension force to the PC steel 20 connected to the secondary tension fixing device 36 at the lower end of the fixing block 60 after the slab casting curing (VI);

연속화 2차 인장용 정착구(34)에 연결된 PC강재(20)에 긴장력을 도입하여 연속화 2차 인장을 하는 단계(Ⅶ)를 순차적으로 시행하여 구조물을 시공하는 것이다.The construction of the structure by sequentially performing the step (Ⅶ) of the continuous secondary tension by introducing a tension force to the PC steel 20 connected to the continuous secondary tension anchorage 34.

여기서, 상기 슬래브 타설 양생후 정착블록(60)의 상단부내에 있는 연속화 2차 인장용 정착구(34)에서 PC강재(20)에 긴장력을 도입하여 빔(10)을 2차 긴장하는 단계를 추가한다.Here, after the slab casting curing, the step of introducing the tension force to the PC steel 20 in the continuous secondary tension fixing device 34 in the upper end of the fixing block 60 to add a second tension of the beam (10).

또한, 상기 슬래브 타설 양생된 정착블록(60)의 하단부내에 있는 유지관리용 정착구(38)에서는 공용중 야기될 수 있는 주형의 처짐, 균열이 발생할 경우 PC강재(20)를 삽입후 PC강재(20)에 긴장력을 도입하여 빔(10)을 추가 긴장하는 단계를 추가한다.In addition, in the maintenance fixing unit 38 in the lower end of the slab cast curing fixing block 60, the PC steel 20 after inserting the PC steel 20 in the case of sagging or cracking of the mold that may be caused during common use Introduce a tension force to the) to add a further tension to the beam (10).

즉, 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형을 이용한 교량시공방법은 다목적 인장용 측면돌출 정착블록(60)이 부착된 빔(10)을 제작하되, 상기 빔(10)은 프리플렉스빔(Preflux beam), 프리스트레스트 콘크리트빔(prestressed concrete beam), 스틸플레이트거더(steel plate girder), 스틸박스거더(Steel Box girder), 기타 강재 콘크리트 합성거더 중 어느 하나로 제작한다.That is, the bridge construction method using the mold is fixed to the multi-purpose tension side projection fixing block according to the present invention to produce a beam 10 attached to the multi-purpose tension side projection fixing block 60, the beam 10 Is made of any one of a preflux beam, a prestressed concrete beam, a steel plate girder, a steel box girder, and other steel concrete composite girder.

여기서, 상기 측면돌출 정착블록(60)은 철근콘크리트구조, 강구조, 강합성구조로 빔(10) 제작시 같이 부착시켜 제작하되, 스틸박스거더의 경우는 박스내부에 정착블록(60)을 부착한다.Here, the side protrusion fixing block 60 is manufactured by attaching the beam 10 in a reinforced concrete structure, steel structure, and steel composite structure, but in the case of a steel box girder, the fixing block 60 is attached to the inside of the box. .

특히, 상기 정착블록(60)은 빔(10)의 양쪽에 각 1개씩 설치하거나 필요에 따라 다수개를 빔(10)의 양측면에 설치하도록 한다.In particular, the fixing block 60 is installed on each side of the beam 10 one by one or a plurality of them to be installed on both sides of the beam 10 as necessary.

이어서, 상기 빔(10)을 교각(82) 또는 교대(84)에 거치후 보강재(50)와 연속화 강재(40) 및 고장력볼트(42)로 연결하고, 교좌장치(88)를 셋팅한 후, 측면돌출 정착블록(60) 상단부에 있는 연속화 1차 인장용 정착구(32)에서 빔(10)의 연속화 1차 인장을 한다.Subsequently, the beam 10 is mounted on the pier 82 or the alternating 84, and then connected with the reinforcement 50, the continuous steel 40, and the high tension bolt 42, and after setting the stool device 88, The continuous primary tensioning of the beam 10 is performed in the continuous primary tensioning anchorage 32 at the upper end of the side protrusion fixing block 60.

이어서, 상기 빔(10)에 슬래브 타설 양생후 측면돌출 정착블록(60) 하단부에 있는 2차 인장용 정착구(36)에서 2차 인장을 하고, 경우에 따라서는 측면돌출 정착블록(60) 상단부내에 있는 연속화 2차 인장용 정착구(34)에서 연속화 2차 인장을 한다.Subsequently, after the slab casting is cured on the beam 10, the secondary tension is applied in the secondary tension fixing unit 36 at the lower end of the side protrusion fixing block 60, and in some cases, in the upper side of the side protrusion fixing block 60. A continuous secondary tension is performed in the continuous secondary tension fixing unit 34.

이때, 상기 2차 인장용 정착구(36)에서 연속화 2차 인장을 하지 않을 경우는 추후에 빔(10)의 연속화 유지관리용으로 사용한다.In this case, when the continuous secondary tension is not performed in the secondary tension fixing device 36, the secondary tension fixing device 36 is used for the continuous maintenance of the beam 10.

이어서, 상기 빔(10)과 빔(10)의 연속화 연결부(86)에 에폭시를 주입하거나 무수축몰탈을 주입하여 마감처리를 하여 구조물의 시공을 완료한다.Subsequently, epoxy is injected into the beam 10 and the continuous connection portion 86 of the beam 10, or non-shrink mortar is injected to finish the construction of the structure.

도 6은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 보강재를 도시한 사시도이며, 도 7은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 보강재를 도시한 측면도이다.Figure 6 is a perspective view showing the reinforcement of the mold is fixed to the side protrusion fixing block according to the present invention, Figure 7 is a side view showing the reinforcement of the mold is fixed to the side protrusion fixing block according to the present invention.

이들 도면에 도시된 바와 같이, 상기 보강재(50)는 소정의 크기로 이루어지는 판체(52)와; 상기 판체(52)의 상하면에 다수개가 부착된 스터드볼트(54)와; 상 기 스터드볼트(54)간의 판체(52)의 상하면을 관통하여 형성된 천공부(56)로 구성된다.As shown in these figures, the reinforcing material 50 includes a plate body 52 having a predetermined size; Stud bolts 54 are attached to the upper and lower surfaces of the plate body 52; It consists of a perforation 56 formed through the upper and lower surfaces of the plate body 52 between the stud bolts 54.

도 8a 내지 8f는 본 발명의 다양한 측면돌출 정착블록을 도시한 예시도이다.8A to 8F are exemplary views illustrating various side protrusion fixing blocks of the present invention.

이들 도면에 도시된 바와 같이, 상기 정착블록(60)은 빔(10)의 양측면에 돌출 설치되되, 상기 정착블록(60)의 상단부에 연속화를 위하여 상하로 각각 설치된 연속화 1차 및 2차 인장용 정착구(32, 34)와; 상기 정착블록(60)의 하단부에 설치된 2차 인장용 정착구(36)와; 상기 2차 인장용 정착구(36)의 상부 정착블록(60)에 고정 설치된 빔(10)의 유지관리용 정착구(38)로 구성된다.As shown in these figures, the fixing block 60 is protrudingly installed on both sides of the beam 10, and the continuous primary and secondary tensions respectively installed vertically on the upper end of the fixing block 60 for continuity Anchorages (32, 34); A secondary tension fixing unit (36) installed at the lower end of the fixing block (60); It consists of a fixing fixture 38 for the maintenance of the beam 10 fixed to the upper fixing block 60 of the secondary tension fixing unit 36.

특히, 상기 정착블록(60)은 철근콘크리트구조, 강구조, 강합성구조 중 어느 하나로 구성된다.In particular, the fixing block 60 is composed of any one of reinforced concrete structure, steel structure, steel composite structure.

또한, 상기 정착블록(60)은 빔(10)의 양측면에 적어도 하나 이상이 부착된다.In addition, at least one fixing block 60 is attached to both sides of the beam 10.

그리고, 상기 정착블록(60)은 그 단면형상이 마름모꼴, 사다리꼴, 사각형, 삼각형, 다각형, 평행사면형, 등각사다리꼴, 등변사다리꼴 중 어느 하나의 형상으로 형성되며, 그 외의 다양한 형상으로 용이하게 변경하여 사용할 수도 있음을 밝혀두는 바이다.In addition, the fixing block 60 is formed in any one of the cross-sectional shape of the lozenge, trapezoid, square, triangle, polygon, parallelogram, equilateral trapezoid, isosceles trapezoid, and easily changed to other various shapes Note that it can also be used.

도 9a 내지 도 9j는 본 발명의 다양한 측면돌출 정착블록에 쐐기형태의 돌출블록이 부가된 형태를 도시한 예시도이다. 9A to 9J are exemplary views illustrating a form in which a wedge-shaped protruding block is added to various side protrusion fixing blocks of the present invention.

이들 도면에 도시된 바와 같이, 상기 정착블록(60)은 각 모서리에 쐐기형상의 돌출부(62)가 일체로 부가 형성된 구조이다.As shown in these figures, the fixing block 60 has a structure in which wedge-shaped protrusions 62 are integrally added to each corner.

즉, 상기 정착블록(60)은 마름모꼴, 사다리꼴, 사각형, 삼각형 형상을 기본 형상으로 하고, 상기 형상에 정착구(32, 34, 36, 38) 정착과 PS강재(20) 인장시 구조적으로 강성을 유지하기 위해 각 모서리 부분에 쐐기형상의 돌출부(62)를 선택적으로 부가한 형상이다.That is, the fixing block 60 has a rhombic, trapezoidal, square, and triangular shape as a basic shape, and maintains structural rigidity when fixing the fixing holes 32, 34, 36, and 38 and tensioning the PS steel 20. In order to do this, the wedge-shaped protrusion 62 is selectively added to each corner portion.

도 10은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 사시도이며, 도 11은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 측면도이다.Figure 10 is a perspective view showing the end reinforcement combined sole plate of the mold fixed side projection fixing block according to the present invention, Figure 11 shows the end reinforcement combined sole plate of the mold fixed side projection fixing block according to the present invention. One side view.

이들 도면에 도시된 바와 같이, 상기 솔플레이트(70)는 소정의 크기로 수평하게 배치되는 수평판(72)과; 상기 수평판(72)의 일측에 직각으로 부착되는 수직판(74)과; 상기 수평 및 수직판(72, 74)에 각각 다수개가 부착되는 스터드볼트(76)로 구성된다.As shown in these figures, the sole plate 70 includes a horizontal plate 72 arranged horizontally in a predetermined size; A vertical plate 74 attached to one side of the horizontal plate 72 at a right angle; The stud bolt 76 is attached to the plurality of horizontal and vertical plates (72, 74), respectively.

따라서, 상기한 솔플레이트(70)는 빔(10)의 양단에 교좌장치(88)와 접하는 위치에 설치되어 빔(10)의 단부를 보강하는 효과가 있다.Therefore, the sole plate 70 is installed at both ends of the beam 10 in contact with the teaching device 88 has the effect of reinforcing the end of the beam (10).

도 12는 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형으로 이루어진 3경간 연속교를 도시한 예시도이다.Figure 12 is an exemplary view showing a three-span continuous bridge made of a mold fixed to the multi-purpose tension-protruding side projection fixing block according to the present invention.

이 도면에 도시된 바와 같이, 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형은 상ㆍ하부플랜지(12, 14) 및 복부(16)로 이루어지는 빔(10)과; 상기 빔(10)의 단부측 소정위치에 PC강재(20)를 긴장시키기 위한 긴장력을 도입할 수 있도록 설치된 1차 인장용 정착구(30)와; 상기 빔(10)의 상부플랜지(12) 일측단에 일정한 크기의 단위 빔(10)의 연속화를 위해 고정 설치된 연속화 강재(40)와; 상기 빔(10)의 상부플랜지(12)에 길이방향으로 고정 설치된 보강재(50)와; 상기 빔(10)의 양측면에 일정한 폭과 너비로 돌출 설치된 정착블록(60)과; 상기 빔(10)의 하부플랜지(14) 일측단에 고정 설치된 단부 보강 겸용 솔플레이트(70)로 구성되되, As shown in this figure, the mold on which the multi-purpose tensionable side protrusion fixing block is fixed according to the present invention includes a beam 10 including upper and lower flanges 12 and 14 and an abdomen 16; A primary tension fixing device (30) installed to introduce a tension force for tensioning the PC steel (20) at a predetermined position at the end side of the beam (10); A continuous steel member 40 fixedly installed at one end of the upper flange 12 of the beam 10 for continuity of the unit beam 10 having a predetermined size; A reinforcement member 50 fixedly installed in the longitudinal direction on the upper flange 12 of the beam 10; A fixing block (60) protruding from both sides of the beam (10) with a predetermined width and width; Is composed of the end reinforcement combined sole plate 70 is fixed to one side end of the lower flange 14 of the beam 10,

상기 정착블록(60)은 빔(10)의 양측면에 돌출 설치되며, The fixing block 60 is installed protruding on both sides of the beam 10,

상기 정착블록(60)은 정모멘트 및 부모멘트 구간에 설치되는 정ㆍ부모멘트부 유지관리용 정착구(39a, 39b)와; 상기 정모멘트부 유지관리용 정착구(39a)의 하부에 설치되는 주형의 2차 인장용 정착구 및 연속화 1차 인장용 정착구(32)로 구성된다.The fixing block 60 includes fixing fixtures 39a and 39b for maintaining the positive and sub-moment portions installed in the positive moment and the parent moment sections; It consists of a secondary tension anchorage of the mold and a sequential primary tension anchorage (32) installed in the lower portion of the constant moment maintenance fixing unit (39a).

상기한 바와 같은 구성으로 이루어진 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형을 이용한 교량시공방법은 Bridge construction method using a mold fixed to the multi-purpose tension-able side protrusion fixing block according to the present invention having the configuration as described above

빔(10)을 형성하기 위하여 철근을 조립하는 단계(Ⅰ);Assembling the reinforcing bars to form the beam 10 (I);

상기 조립된 철근 빔의 양측면에 다목적 인장용 측면돌출 정착블록(60)을 부착하고, 주형의 양단부 소정위치에 주형의 1차 인장용 정착구(30)를 설치하면서 PC강재(20)를 연결하고, 상기 정착블록(60)의 상, 하부분에 빔의 정모멘트 및 부모멘트 구간에 정ㆍ부모멘트부 유지관리용 정착구(39a, 39b)를 설치하고, 상기 정모멘트부 유지관리용 정착구(39a)의 하단부에 주형의 2차 인장용 정착구 및 연속화 1차 인장용 정착구(32)를 설치하며, 빔(10)의 상부플랜지(12)의 일측단부에 일정한 길이를 갖는 보강재(50)를 설치한 후에, 콘크리트를 타설 양생시켜 빔(10)을 제작하고 주형을 1차 인장하는 단계(Ⅱ); Attaching the multi-purpose tension side projection fixing block 60 on both sides of the assembled reinforcing beam, and connecting the PC steel 20 while installing the primary tension fixing device 30 of the mold at predetermined positions on both ends of the mold, The fixing block (39a, 39b) for maintaining the positive and sub-moment portion in the positive moment and the parent moment section of the upper and lower portions of the fixing block 60, and the fixing moment maintenance (39a) After installing the secondary tension anchorage and the sequential primary tension anchor 32 of the mold at the lower end of the, and the reinforcement 50 having a certain length at one end of the upper flange 12 of the beam 10 is installed Casting and curing the concrete to fabricate the beam 10 and firstly tensioning the mold (II);

상기 제작된 빔(10)을 교각(82) 및 교대(84)에 설치하고, 중앙의 교각(82)에서는 인접하여 설치된 빔(10)과 빔(10)의 연결하기 위하여 상부플랜지(12)내에 설치된 보강재(50)를 연속화 강재(40)와 고장력볼트(42)로 연결하여 연속화 연결부(86)를 설치하는 단계(Ⅲ); The fabricated beam 10 is installed in the pier 82 and the alternating 84, and in the central pier 82 in the upper flange 12 to connect the beam 10 and the beam 10 installed adjacently. Connecting the installed reinforcing material 50 to the continuous steel 40 and the high tension bolt 42 to install the continuous connection part 86 (III);

상기 연속화 연결부(86)에 콘크리트를 충전하면서 상기 빔(10)과 빔(10)의 측면에서 서로 접하는 부분은 에폭시 주입하거나 무수축몰탈을 충전하여 밀착시켜 마감하는 단계(Ⅳ);Filling the continuous connection portion 86 with concrete while contacting each other on the side of the beam 10 and the side of the beam 10 by epoxy injection or filling with non-condensation mortar to close the finishing portion (IV);

상기 빔(10)의 양측면에 부착된 정착블록(60) 상단부내에 있는 연속화 1차 인장용 정착구(32)에 연결된 PC강재(20)에 긴장력을 도입하여 빔(10)의 연속화 1차 긴장을 한 후에 슬래브를 타설하여 양생시키는 단계(Ⅴ);Tension force is introduced into the PC steel 20 connected to the sequential primary tension fixing device 32 in the upper end of the fixing block 60 attached to both sides of the beam 10, so that the sequential primary tension of the beam 10 is applied. (V) after pouring the slab to cure;

상기 슬래브 타설 양생후 정착블록(60) 하단부에 있는 2차 인장용 정착구 및 연속화 1차 인장용 정착구(35)에 연결된 PC강재(20)에 긴장력을 도입하여 빔(10)의 2차 긴장을 하는 단계(Ⅵ);The secondary tension of the beam 10 by introducing a tension force to the PC steel 20 connected to the secondary tension anchorage and the sequential primary tension anchorage 35 in the lower end of the fixing block 60 after the slab casting curing. Step (VI);

연속화 2차 인장용 정착구(34)에 연결된 PC강재(20)에 긴장력을 도입하여 연속화 2차 인장을 하는 단계(Ⅶ)를 순차적으로 시행하여 구조물을 시공하는 것이다.The construction of the structure by sequentially performing the step (Ⅶ) of the continuous secondary tension by introducing a tension force to the PC steel 20 connected to the continuous secondary tension anchorage 34.

따라서, 상기한 바와 같은 구성 및 시공으로 이루어진 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형은 정착블록(60)의 정ㆍ부모멘트부 유지관리용 정착구(39a, 39b)는 빔(10)의 정모멘트 구간과 부모멘트 구간에 설치하여, 빔의 정모멘트 구간에 부모멘트를 발생시키고, 부모멘트구간에 정모멘트를 발생시켜서, 발생된 모멘트는 빔(10)의 사하중 및 활하중에 의해 발생되는 정ㆍ 부모멘트에 저항하도록 하기 위함이다.Therefore, the mold having the multi-purpose tensionable side protrusion fixing block according to the present invention having the above-described configuration and construction is fixed to the fixing holes 39a and 39b for maintaining the positive and minor moments of the fixing block 60. It is installed in the constant moment section and the parent moment section of (10) to generate a parent moment in the positive moment section of the beam, and generate a constant moment in the parent moment section, the generated moment is the dead load and live load of the beam (10) This is to resist the positive and negative moment generated by the process.

도 13은 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 사시도이며, 도 14는 본 발명에 따른 측면돌출 정착블록이 정착된 주형의 단부 보강 겸용 솔플레이트를 도시한 측면도이며, 도 15는 본 발명에 따른 측면돌출 정착블록이 정착된 주형에 솔플레이트가 설치된 상태를 도시한 측면도이다. Figure 13 is a perspective view showing the end reinforcement combined sole plate of the mold fixed side projection fixing block according to the present invention, Figure 14 shows the end reinforcement combined sole plate of the mold fixed side projection fixing block according to the present invention. 15 is a side view, and FIG. 15 is a side view illustrating a state in which a sole plate is installed in a mold on which a side protrusion fixing block is mounted.

이들 도면에 도시된 바와 같이, 상기 솔플레이트(70)는 전체적으로 강판을 절곡시켜 형성되되, 소정의 크기로 수평하게 배치되는 수평판(72)과; 상기 수평판(72)의 일측에 직각으로 부착되는 수직판(74)과; 상기 수직판(74)으로부터 일체로 연결되며 소정의 각도로 절곡 형성된 절곡판(75)과; 상기 절곡판(75)에 천공 형성된 천공부(78)와; 상기 절곡판으로부터 상단으로 일체로 연장 형성된 정착판(79)으로 구성된다.As shown in these figures, the sole plate 70 is formed by bending the steel plate as a whole, the horizontal plate 72 is arranged horizontally to a predetermined size; A vertical plate 74 attached to one side of the horizontal plate 72 at a right angle; A bending plate 75 integrally connected to the vertical plate 74 and bent at a predetermined angle; A perforation portion 78 formed in the bending plate 75; It consists of a fixing plate 79 formed integrally extending from the bending plate to the upper end.

이와 같은 솔플레이트(70)는 빔(10)의 양단에 교좌장치(88)와 접하는 위치에 설치되어 빔(10)의 단부를 보강함과 동시에 PC강재(20)를 긴장할 수 있도록 한다.The sole plate 70 is installed at both ends of the beam 10 in contact with the chair device 88 so as to reinforce the end of the beam 10 and at the same time to tension the PC steel 20.

상기한 바와 같은 구성 및 시공으로 이루어진 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법은 프리스트레스트 콘크리트빔이 갖는 역학적 한계를 극복함과 동시에 시공성이 단순하며, 다양한 지간 또는 그 조합된 지간에 효율적으로 정착블록(60)을 적용할 수 있는 작용효과가 있다. The mold and the bridge construction method in which the multi-purpose tensionable side protrusion fixing block is fixed according to the present invention having the configuration and construction as described above overcome the mechanical limitations of the prestressed concrete beam, and at the same time, the construction is simple. There is an effect that can be applied to the fixing block 60 efficiently in various intervals or a combination thereof.

이상에서 설명한 바와 같이, 본 발명에 따른 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형과 이를 이용한 교량시공방법은 다음과 같은 효과가 있다.As described above, the mold and the bridge construction method using the side projection fixing block capable of multi-purpose tension in accordance with the present invention has the following effects.

첫째, 본 발명은 시공성이 우수하면서도 구조적으로 효율성을 가지는 공법으로서 교량의 장대화를 할 수 있으며, 인접 지간이 상이한 경우에도 단면형상에 관계없이 적용할 수 있는 효과가 있다. First, the present invention can increase the length of the bridge as a construction method with excellent construction efficiency and structural efficiency, there is an effect that can be applied regardless of the cross-sectional shape even when the adjacent space is different.

둘째, 본 발명은 교량의 연속화 시공시 효율적으로 균열을 제어할 수 있으며, 안정성과 내구성을 증대시킬 수 있는 효과가 있다.Second, the present invention can effectively control the cracks during the continuous construction of the bridge, there is an effect that can increase the stability and durability.

셋째, 본 발명은 선택적으로 유지관리용 정착구를 설치함으로써 추후 교량의 노화로 인한 슬래브의 교체시에도 빔의 성능이 그대로 유지되는 이점이 있다.
Third, the present invention has an advantage that the performance of the beam is maintained as it is, even when the slab is replaced due to the aging of the bridge after the installation of the maintenance anchorage selectively.

Claims (17)

삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 상ㆍ하부플랜지(12, 14) 및 복부(16)로 이루어지는 빔(10)과; 상기 빔(10)의 단부측 소정위치에 PC강재(20)를 긴장시키기 위한 긴장력을 도입할 수 있도록 설치된 1차 인장용 정착구(30)와; 상기 빔(10)의 상부플랜지(12) 일측단에 일정한 크기의 단위 빔(10)의 연속화를 위해 고정 설치된 연속화 강재(40)와; 상기 빔(10)의 상부플랜지(12)에 길이방향으로 고정 설치된 보강재(50)와; 상기 빔(10)의 양측면에 일정한 폭과 너비로 돌출 설치된 정착블록(60)과; 상기 빔(10)의 하부플랜지(14) 일측단에 고정 설치된 단부 보강 겸용 솔플레이트(70)로 구성되는 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형에 있어서,A beam 10 composed of upper and lower flanges 12 and 14 and an abdomen 16; A primary tension fixing device (30) installed to introduce a tension force for tensioning the PC steel (20) at a predetermined position at the end side of the beam (10); A continuous steel member 40 fixedly installed at one end of the upper flange 12 of the beam 10 for continuity of the unit beam 10 having a predetermined size; A reinforcement member 50 fixedly installed in the longitudinal direction on the upper flange 12 of the beam 10; A fixing block (60) protruding from both sides of the beam (10) with a predetermined width and width; In the mold with a multi-purpose tensionable side projection fixing block composed of the end reinforcement combined sole plate 70 is fixed to one side end of the lower flange 14 of the beam 10, 상기 솔플레이트(70)는 소정의 크기로 수평하게 배치되는 수평판(72)과; 상기 수평판(72)의 일측에 직각으로 부착되는 수직판(74)과; 상기 수직판(74)으로부터 일체로 연결되며 소정의 각도로 절곡 형성된 절곡판(75)과; 상기 절곡판(75)에 천공 형성된 천공부(78)와; 상기 절곡판으로부터 상단으로 일체로 연장 형성된 정착판(79)으로 구성됨을 특징으로 하는 다목적 인장이 가능한 측면돌출 정착블록이 정착된 주형.The sole plate 70 includes a horizontal plate 72 arranged horizontally with a predetermined size; A vertical plate 74 attached to one side of the horizontal plate 72 at a right angle; A bending plate 75 integrally connected to the vertical plate 74 and bent at a predetermined angle; A perforation portion 78 formed in the bending plate 75; A mold having a multi-purpose tensionable side projection fixing block, characterized in that it consists of a fixing plate 79 formed integrally extending from the bending plate to the upper end. 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete 삭제delete
KR1020040113474A 2004-12-28 2004-12-28 The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this KR100555251B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040113474A KR100555251B1 (en) 2004-12-28 2004-12-28 The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040113474A KR100555251B1 (en) 2004-12-28 2004-12-28 The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this

Publications (1)

Publication Number Publication Date
KR100555251B1 true KR100555251B1 (en) 2006-03-03

Family

ID=37179231

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040113474A KR100555251B1 (en) 2004-12-28 2004-12-28 The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this

Country Status (1)

Country Link
KR (1) KR100555251B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100814387B1 (en) 2007-12-03 2008-03-18 노윤근 Prestressed concrete girder manufacture method equipped with end anchorage for economical upkeeping
KR100872822B1 (en) * 2007-06-29 2008-12-09 노윤근 Prestressed concrete girder which symmetry and an asymmetrical anchorage block
KR100892137B1 (en) * 2008-06-23 2009-04-08 (주)비엔텍아이엔씨 Rahmen typed underground tunnel construction method using lateral psc beam
KR102057534B1 (en) * 2019-05-16 2019-12-18 에스오씨기술지주 주식회사 Innovative PSC continuous bridge construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100872822B1 (en) * 2007-06-29 2008-12-09 노윤근 Prestressed concrete girder which symmetry and an asymmetrical anchorage block
KR100814387B1 (en) 2007-12-03 2008-03-18 노윤근 Prestressed concrete girder manufacture method equipped with end anchorage for economical upkeeping
KR100892137B1 (en) * 2008-06-23 2009-04-08 (주)비엔텍아이엔씨 Rahmen typed underground tunnel construction method using lateral psc beam
KR102057534B1 (en) * 2019-05-16 2019-12-18 에스오씨기술지주 주식회사 Innovative PSC continuous bridge construction method

Similar Documents

Publication Publication Date Title
US6857156B1 (en) Modular bridge structure construction and repair system
US6588160B1 (en) Composite structural member with pre-compression assembly
KR100926969B1 (en) Prestressed reinforced concrete girder and it's construction method
KR100986207B1 (en) Precast psc t-type girder bridge and its construction method
KR100823448B1 (en) The improved seismic resistant continuation structure of prestressed concrete composite beam bridge and method thereof
KR101582599B1 (en) Bridge construction method for forming continuous point part of pier using copping for connecting girder
KR100555249B1 (en) Bridge constructing method using even-sectioned i-type rolled steel beam having increased section intensity and i-type rolled steel beam manufactured with uneven steel plate
KR100555251B1 (en) The bridge construction method of having used girder equipped with the side projection fixing block in which multiple-purpose tension is possible, and this
KR100860796B1 (en) Continuationization method by which psc which used upper and lower symmetry or asymmetric fixed bracket
KR100842062B1 (en) The steel composite rahmen bridge construction technique for which preflexion steel girder was used
KR100374284B1 (en) A psc beam having above typed anchor blocks and connecting method thereof
KR100583671B1 (en) Prestressed concrete beam manufactured by installing steel anchorage devices to various positions and reinforcing member to the upper and lower flanges, and construction method of bridge using the concrete beam
JPH0782709A (en) Reinforcing method for concrete structure, employing hollow pc steel bar
KR100547485B1 (en) Continuous multi-span bridge using bridge girder units and construction method thereof
KR20030094195A (en) Improved prestressed steel reinforced concrete beam and bridge construction method using the same beam
KR20060017949A (en) Field-fabricated prestressing steel-composed girder and construction method of continuous bridge using the girder
KR100696646B1 (en) External prestressing method of ps concrete composite girder bridge by tendon anchored/supported to prefabricated cross beam
KR200189311Y1 (en) A psc beam having above typed anchor blocks
KR100566653B1 (en) The middle point part continuous structure and the continuous method of prestressed concrete girder bridge
KR100989153B1 (en) Psc girder connection structure with strength connector detail for substitution of rebar placement in deck and bridge construction method using the same
KR100549046B1 (en) The pre-stressed concrete beam middle point part continuous structure and the method of having used the sole plate
KR101734304B1 (en) Manufacturing Method of Efficient Steel-Concrete Composite Girder, Construction Method of Continuous Bridges using such Composite Girder, and Continuous Bridges constructed by such Method
KR20090054511A (en) Pre-cast concrete elments and construction method using thereof for upper portion of bridge
KR100393132B1 (en) Construction method of composite steel-box bridge using prestress
KR100662814B1 (en) Prestressed concrete u-girder which the hollow pipe contained, and it's continuationized method of construction

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee