[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

KR100463715B1 - apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same - Google Patents

apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same Download PDF

Info

Publication number
KR100463715B1
KR100463715B1 KR10-2002-0014569A KR20020014569A KR100463715B1 KR 100463715 B1 KR100463715 B1 KR 100463715B1 KR 20020014569 A KR20020014569 A KR 20020014569A KR 100463715 B1 KR100463715 B1 KR 100463715B1
Authority
KR
South Korea
Prior art keywords
excavation
passageway
passage
aisle
visor
Prior art date
Application number
KR10-2002-0014569A
Other languages
Korean (ko)
Other versions
KR20030075383A (en
Inventor
김우진
Original Assignee
한 성 육
김우진
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 한 성 육, 김우진 filed Critical 한 성 육
Priority to KR10-2002-0014569A priority Critical patent/KR100463715B1/en
Publication of KR20030075383A publication Critical patent/KR20030075383A/en
Application granted granted Critical
Publication of KR100463715B1 publication Critical patent/KR100463715B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0642Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield having means for additional processing at the front end
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0692Cutter drive shields
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Environmental & Geological Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명은 기설 도로나 철도 등의 선로를 횡단하는 지하통로를 개설할 때 그 선로를 개착하지 않고 신속 간편하고 경제적으로 구축할 수 있는 비개착식 선로 횡단 지하통로 구축장치와 그 시공방법을 제공하기 위한 것으로서, 바닥과 벽 및 천장 일체형으로서 선단면에는 굴착챙 부착용 너트(5)를 설치한 통로거(1)와; 노반 굴진시 토사무너짐 방지용으로서 밑이 측벽(21)의 선단이 빗면(23)이고, 후단에는 통로거(1)의 너트(5)와 동수의 부착공(25)이 천공된 굴착챙(2)과; 굴착챙(2)의 천장(22)과 하부(11)의 선단에 부착되고 굴진각도조절구(6)로 굴진각도를 조절하도록 된 굴착날(3)과; 유압장치로 이루어진 통로거 압입장치(4)로 이루어진 비개착식 선로 횡단 지하통로 구축장치를 지하통로 개설지에 설치하고 점진적으로 노반을 굴착하면서 통로거를 압입하며, 관통된 통로공에 통로거를 정위치시킨 후에 주변정리하여 마감하는 순서에 따라 비개착식으로 기설 선로를 횡단하는 지하통로를 구축하는 방법이다.The present invention provides a non-adhesive track crossing underground passage construction device and construction method that can be quickly and easily and economically established without opening the track when opening an underground passage crossing a track such as an existing road or a railway. For the purpose, the floor and the wall and the ceiling integrally formed in the front end passage passage (1) for installing the excavation visor attachment nut (5); Excavation visor (2) in which the tip of the side wall (21) is the inclined surface (23), and the nut (5) of the aisle (1) and the same number of attachment holes (25) are drilled at the rear end to prevent soil collapse during roadbed excavation. and; An excavation blade 3 attached to the ends of the ceiling 22 and the lower portion 11 of the excavation visor 2 and configured to adjust the excavation angle with the excavation angle adjusting mechanism 6; A non-adhesive track crossing underground passage construction device consisting of a hydraulic passage indentation device (4) is installed in the underground passage establishment site, and the passage is press-fitted while gradually excavating the roadbed, and the passage is fixed in the through passage hole. It is a method of constructing underground passages that cross the existing tracks in a non-adhesive manner according to the order of finishing the surroundings after the location.

Description

비개착식 선로 횡단 지하통로 구축장치와 이를 이용한 노선 횡단 지하통로 시공방법 {apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same}Apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same}

본 발명은 기설 도로나 철도 등의 선로를 횡단하는 지하통로를 개설함에 있어서 기존 선로를 개착하지 않고 시공하는 장치와, 이 장치를 사용하여 짧은 공기에 경제적 효과적으로 선로 횡단 지하통로를 개설하는 방법에 관한 것이다.The present invention relates to an apparatus for constructing an underground passage that crosses a track such as an existing road or a railroad, without installing an existing track, and a method for economically and efficiently establishing a transverse underground passage for short air using the apparatus. will be.

기설 고속도로, 국도, 지방 도로나 철도 밑에 그 선로를 횡단하는 지하통로를 개설하던 보편적인 공법은 계획구간의 경계에 선로에 대해 직교방향을 따라 촘촘히 파일을 박아 토류벽을 설치하고, 선로 방향의 양쪽 파일 간에 받침빔을 가설한 다음 그 위에 복공판을 깔아 기존 선로의 통행을 유지하는 가운데 복공판 밑 도로를 설계지면까지 굴착하여 바닥 철근 콘크리트 기초를 구축하고, 바닥 콘크리트기초 위에 철근 콘크리트 벽 세우기와 철근 콘크리트 천장 구축의 순으로 지하통로를 구축하고, 복공판과 파일을 철거한 후 쇄석과 아스콘을 사용한 노면 복구의 순으로 진행하는 개착식이 다.The universal method of establishing underground passages crossing the track under existing highways, national roads, local roads or railways, installs earth walls by closely piled piles along the orthogonal direction of the track at the boundary of the planned section, and on both sides of the track. After constructing the supporting beam between the walls and laying the perforated plate on it, the road under the perforated plate is excavated to the design ground, while laying the reinforced concrete foundation on the floor concrete foundation, building the reinforced concrete wall and building the reinforced concrete ceiling on the ground concrete foundation. The opening ceremony is followed by the construction of underground passages, the removal of perforated plates and piles, and the restoration of roads using crushed stone and ascon.

그러나 개착식 선로 횡단 지하통로 시공방법은 파일 박기에서부터 복공판을 까는 데 소요되는 지하통로 개설 준비기간과 지하통로 구축 후 노면 복구기간만큼 공기가 길고, 그 비용도 추가돼 지하통로 개설비의 상승이 불가피하다. 또, 개설준비기간과 노면 복구기간 동안 선로 통행 차량과 보행자는 통행 불편을 감수해야 되고, 안전사고의 위험도 다분하다.However, the installation method of the open-track underground crossing is as long as the preparation period for the opening of the underground passage from the pile-up to the opening of the underground passage and the restoration of the road surface after the construction of the underground passage. . In addition, railroad vehicles and pedestrians must bear the inconvenience of traffic during the preparation period and during the road retrieval period.

본 발명의 목적은 선로를 횡단하는 지하통로를 비개착식으로 신속 간편하게 또한 경제적으로 개설할 수 있는 시공장치와, 이 장치를 이용하여 저비용으로 신속 간편하게 지하통로를 구축할 수 있는 선로 횡단 지하통로 시공방법을 제공하는 것이다.An object of the present invention is a construction device that can be opened quickly and simply and economically to the underground passage crossing the track non-separable, and the construction of the track crossing underground passage that can quickly and easily build an underground passage at low cost by using this device To provide a way.

상기의 제1 과제는 통로거와 굴착챙, 굴착날, 및 통로거 압입장치로 구성된 비개착식 선로 횡단 지하통로 구축장치로 달성할 수 있다.The first task can be achieved by a non-removable track crossing underground passage construction device consisting of aisle and excavation visor, excavation blade, and aisle indentation device.

제2 과제는 기설 선로에 대한 횡단 지하통로 개설위치의 외곽 지반을 정리하여 통로거와 통로거 압입장치를 수용할 기초 콘크리트를 타설하여 양생시키는 단계와; 상기 기초 콘크리트 위에 미끄럼 마찰저항의 감소를 위하여 시트(예를 들어: P.F. Film등)를 여러겹 깔고 그 위에 통로거를 바르게 올려놓는 단계와; 상기 통로거의 선단에 굴착챙의 후단을 대고 그 부착공을 통하여 너트에 보울트를 체결하여 고정하는 단계와; 상기 통로거의 뒤쪽 기초 콘크리트 상에 유압장치로 이루어진 통로거 압입장치를 설치하여 고정하고 그 유압장치로 통로거의 후단에 밀착시켜 유압장치에 유압을 가하여 통로거의 선단이 노반에 닿을 때까지 밀어서 이동시키는 단계와; 통로거의 후단으로 들어가 굴착챙 안과 그 전방의 노반을 굴착하여 통로공을 형성하고 그 바닥을 상기 기초 콘크리트의 상면과 같게 조정하는 단계와; 상기 통로거 유압장치를 재가동하여 통로거의 바닥 선단이 상기 통로공의 바닥끝에 가 닿도록 압입하고 통로공 앞쪽의 노반을 굴착하여 통로공을 개통하는 단계와; 통로거 압입장치로 통로거를 개통된 통로공에 관통시켜 정위치시키는 단계와; 통로거에서는 굴착챙을 그리고 기초 콘크리트상에서는 통로거 압입장치를 철거하고 주변을 정리하는 단계로 진행하여 비개착식으로 선로를 횡단하는 지하통로를 구축하는 시공방법에 의해 달성할 수 있다.The second task is to clean up the outer ground at the location of the opening of the transverse underground passages for the existing tracks to pour and cure the foundation concrete to accommodate the aisle and the passage indentation device; Placing a plurality of sheets (for example, P. F. Film, etc.) on the foundation concrete and placing the aisles on them in order to reduce sliding frictional resistance; Fastening the bolt to the nut through the attachment hole by applying the rear end of the excavation visor to the tip of the passageway; Installing and fixing the passageway indentation device consisting of a hydraulic device on the base concrete behind the passageway, and the hydraulic device is in close contact with the rear end of the passageway to apply hydraulic pressure to the hydraulic device to push the end of the passageway until it reaches the roadbed. Wow; Entering the rear end of the passageway to excavate the roadbed in and out of the excavation visor to form a passage hole and adjust its bottom to be the same as the upper surface of the foundation concrete; Re-activating the passageway hydraulic device to press the bottom end of the passageway to reach the bottom end of the passageway, and to excavate the roadbed in front of the passageway to open the passageway; Positioning the passageway through the passageway through the passageway through the passageway indentation device; This can be achieved by the construction method of constructing underground passages that cross the tracks by proceeding with the excavation visor in the aisle and the indentation device of the aisle in the foundation concrete and the surrounding arrangement.

도 1은 비개착식 노선 횡단 지하통로 구축장치의 분해도1 is an exploded view of a non-removable cross-section underground passage construction device

도 2는 조립상태의 부분절개 측면도2 is a partial cutaway side view of the assembled state

도 3은 지하통로를 굴진하기 위한 준비상태의 단면도3 is a sectional view of a state ready for excavating an underground passage;

도 4는 초기 노반 굴착단계의 단면도4 is a cross-sectional view of the initial roadbed excavation step

도 5는 중간 노반 굴진단계의 단면도5 is a cross-sectional view of the intermediate roadbed excavation step

도 6은 통로거의 설치에 의하여 선로 횡단 지하통로가 구축된 상태의 단면도Figure 6 is a cross-sectional view of the track crossing underground passage is built by the installation of passageway

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1 : 통로거 2 : 굴착챙1 aisle 2 excavation visor

3 : 굴착날 4 : 통로거 압입장치3: excavation blade 4: passage indenter

5 : 너트 6 : 고무판5: nut 6: rubber sheet

7 : 굴진각도조절구 8 : 시트7: excavation angle control device 8: sheet

11 : 하부 12 : 수직구획판11 bottom 12 vertical partition plate

21 : 측벽 23 : 빗면21: side wall 23: oblique side

24 : 답판 25 : 부착공24: reply 25: attachment hole

41 : 기판41: substrate

42 : 기둥 43 : 유압장치42: column 43: hydraulic device

a : 기초 콘크리트 b : 노반a: foundation concrete b: roadbed

c : 통로공 d : (통로공의) 바닥c: passage hole d: bottom of passage hole

비개착식 선로 횡단 지하통로 시공장치는 크게 통로거(1)와 굴착챙(2), 굴착날(3), 통로거용 압입장치(4)로 구분된다.The non-removable track crossing underground factory is largely divided into aisle (1), excavation visor (2), excavation blade (3), and indentation device (4) for aisle passage.

도 1에서, 통로거(1)는 선로 밑에 비개착식으로 지하통로를 개설할 때 천공작업의 안전을 도모하고, 지하통로를 개설한 후에는 그 지하통로의 바닥과 벽 및 천장 일체형 통로벽을 이루게 되는 것으로, 철근 콘크리트 또는 PC제, 충분한 강도를 지닌 내식성 후강판제, 후강판의 내외 전면에 철근을 배하고 숏크리트를 쳐 굳힌 것 등이 있다. 이러한 통로거(1)는 보행자, 농기구는 물론 규모에 따라서는 차량통행도 가능하다. 아치형과 사각관의 형태가 바람직하고, 길이는 기설 선로의 노폭에 맞춰 설계하여 제작한다.In Fig. 1, the passageway 1 promotes the safety of perforation when opening the underground passage in a non-adhesive way under the track, and after opening the underground passage, the floor, wall and ceiling integrated passage wall of the underground passage are opened. It is made of reinforced concrete or PC, corrosion-resistant thick steel plate with sufficient strength, and reinforced steel on the inside and outside of the thick steel plate and hardened by shotcrete. Such a passage 1 is also possible for pedestrians, farm equipment, as well as vehicle traffic depending on the size. Arched and square tubes are preferred, and their lengths are designed and manufactured to match the width of the existing track.

통로거(1)의 선단 상변과 양 측변에는 등간격마다 너트(5)를 심어 굴착챙(2)의 후단을 대고 보울트로 고정하게 하고, 후단의 모퉁이에는 완충용 고무판(6)을 부착하여 통로거 압입장치로 뒤를 밀어 굴진방향으로 나아가게 할 때 유압장치와 접촉해도 파손되지 않도록 보호하고 또한 유압장치의 선단이 미끄러지지 않도록 한다.A nut 5 is planted at the top and both sides of the passageway 1 at equal intervals so that the rear end of the excavation visor 2 is fixed with a bowl, and a cushioning rubber plate 6 is attached to the corner of the rear end. When pushing back with the push indenter to move in the digging direction, it is protected from being damaged even if it comes into contact with the hydraulic system, and also prevents the tip of the hydraulic system from slipping.

굴착챙(2)은 통로거(1)의 선단에 장착하여 선로 밑을 굴진해 들어갈 때 천장측 토사와 벽쪽 토사가 무너지지 않게 받치면서 지하통로 영역에 대한 굴착작업과 지반에 통로거(1)의 바닥을 고정하는 작업을 안전하게 수행하고 굴착날을 지지하는 것으로, 천장(22)과 하부(11)의 선단에 장착된 굴착날이 굴진한 후라야 통로공의 측면에 대한 굴착작업이 수월한 점에 착안하여 천장(22)의 선단에서 통로거(1)의 선단쪽 바닥을 향해 경사진 빗면(23)으로 형성한다. 이때, 빗면(23)은 흙의 안식각과 동일한 경사각을 갖게 한다.The excavation visor (2) is mounted on the tip of the aisle (1) to support the excavation work on the underground passage area and the ground (1) By securing the floor safely and supporting the drilling blade, the excavation work on the side of the Raya passage hole is easy because the drilling blades mounted on the ends of the ceiling 22 and the lower 11 are excavated. To form a slanted surface 23 that is inclined from the tip of the ceiling 22 toward the bottom of the tip of the passageway 1. At this time, the inclined surface 23 has the same inclination angle as the repose angle of the soil.

이 같은 굴착챙(2)의 외곽은 통로거(1)의 외곽과 동일하게 하여 굴착챙(2)과 굴착날(3)을 사용하여 통로공을 천공하면서 통로거(1)를 압입하기 쉽게 하고, 또한 통로거(1)를 설치한 후에는 통로공과 통로거(1) 사이에 되도록 틈이 남지 않게 하여 지하통로 개설 후 노반의 침하 가능성을 낮춘다.The outer periphery of the excavation visor (2) is the same as the outer periphery of the aisle (1) by using the excavation visor (2) and the excavation blade (3) to make it easy to press the aisle (1) while drilling the passage hole In addition, after the passageway (1) is installed, there is no gap between the passage hole and the passageway (1) to reduce the possibility of settlement of the roadbed after opening the underground passage.

통로공을 굴착할 때 손이 닿지 않는 높은 곳의 노반 토사를 파내려면 사다리같은 별도의 기구가 필요하다. 굴착챙(2) 내에서 사다리를 사용하는 것은 통로거(1)를 설치하기 위하여 진행하는 후속 작업에 장애물이 될 수 있고 거추장스럽기도 하다. 이 점을 고려하여 굴착챙(2) 내에 답판(24)을 설치하여 작업자가 올라가 높은 곳의 노반에 대한 굴착작업을 수월하게 진행할 수 있게 한다. 답판(24)은 앞이 뒤쪽보다 약간 높게 경사지게 하여 굴착된 토사를 뒤쪽으로 밀어내기 쉽게 한다. 또한, 굴착챙(2)내를 다수부분으로 구획분할 하는 수직구획판(12)을 답판(24)과 직각으로 설치하여 토사가 무너지는 것을 방지한다. 이때, 국착챙내를 분할 하는 구획개수는 굴진하고자하는 토사의 종류 및 굴착챙의 크기등에 따라 결정한다.In order to dig up roadbed soil that is out of reach when digging holes, a separate device such as a ladder is required. The use of ladders in the excavation visor 2 can be an obstacle and cumbersome to subsequent work going on to install the aisle 1. In view of this point, by installing the answer plate 24 in the excavation visor (2), the worker can go up easily to proceed with the excavation work for the roadbed. The answer plate 24 tilts the front slightly higher than the rear so that the excavated soil is easily pushed back. In addition, the vertical partition plate 12 for dividing the inside of the excavation visor 2 into a plurality of parts is installed at right angles to the answer plate 24 to prevent the soil from collapse. At this time, the number of partitions for dividing the stationary visor is determined according to the type of soil to be excavated and the size of the excavated visor.

굴착챙(2)의 후단에서 상기 너트(5)와 같은 자리마다 부착공(25)을 천공하여 통로거(1)의 선단에 대고 보울트로 너트(5)에 고정시키기 쉽게 한다. 답판(24)의 후단에는 슈트(미도시)를 부착하여 굴착토사를 운반차량에 적재하기 쉽게 한다.In the rear end of the excavation visor (2) perforation of the attachment hole 25 in the same position as the nut (5) to be easily fixed to the nut (5) with a bowl against the tip of the passageway (1). A chute (not shown) is attached to the rear end of the answer plate 24 so that the excavated soil is easily loaded on the transport vehicle.

굴착날(3)은 통로거(1)가 들어 갈 통로거공의 천장쪽을 먼저 파고 들어가 노반의 굴착작업과 통로거(1)의 굴진작업이 수월하게 이뤄지게 하는 것으로, 굴착챙(2)의 천장(22)과 하부(11)의 선단에 힌지식으로 부착하고, 굴진각도조절구(7)로 굴착챙(2)에서의 굴착날(3)의 각도를 조절할 수 있게 하거나 통로거(1)의 굴진 높낮이를 조절한다. 굴진각도조절구(7)의 양쪽 나사봉(71,72)은 굴착챙(2)의 빗면(23)과 굴착날(3)의 양측단 저면에 부착된 돌쩌귀(27,31)에 힌지식으로 설치한다. 굴착날(3)의 각도조절은 굴진각도 또는 통로거의 높낮이가 어긋났을 때 실시한다.The excavation blade (3) is to dig the ceiling side of the aisle through which the aisle (1) will enter first to facilitate the excavation work of the roadbed and the aisle (1), the ceiling of the excavation visor (2) (22) hingedly attached to the tip of the lower part (11), the angle of excavation (2) to adjust the angle of the excavation blade (3) in the excavation visor (2) with the excavation angle adjuster (7) Adjust the height of excavation. Both threaded rods 71 and 72 of the excavation angle adjusting mechanism 7 are hinged to the bevel 23 of the excavation visor 2 and the claws 27 and 31 attached to the bottom surfaces of both ends of the excavation blade 3. Install. Angle adjustment of the excavation blade 3 is performed when the excavation angle or the height of the passageway shifts.

도 3에서 통로거 압입장치(4)는 굴착챙(2)이 결합된 통로거(1)를 통로공의 굴진방향으로 뒤를 밀어 강제 진출시키는 것으로서 유압을 이용한 유압장치이다.In FIG. 3, the passage girder indentation apparatus 4 is a hydraulic apparatus using hydraulic pressure as the passage girder 1 coupled with the excavation visor 2 is pushed backward in the excavation direction of the passage hole.

다음으로, 상기 비개착식 선로 횡단 지하통로 구축장치를 사용하는 지하통로 시공방법에 대하여 설명한다.Next, an underground passage construction method using the non-adhesive track crossing underground passage construction device will be described.

도 3에서, 도로, 철도 등의 기설 선로를 횡단하는 지하통로가 개설될 곳의 외곽에 그 횡단방향의 연장선상에 있는 지반을 정리하고 통로거(1)의 바닥폭 보다도 넓고 통로거(1)와 유압식 통로거 압입장치(4)를 한꺼번에 올려 놓을 만한 길이로 기초 콘크리트(a)를 타설한 다음에 그 바닥을 반듯하게 정리하여 양생시킨다.In Fig. 3, the ground on the line extending in the transverse direction is arranged outside the place where the underground passage crossing the existing tracks such as roads, railways, etc., is wider than the bottom width of the passageway passage 1, and the passageway passage 1 And hydraulic passageway press-fitting device (4) to the foundation to put the length of the concrete (a) to the length and then arrange the bottom smoothly to cure.

기초 콘크리트(a) 위에 굴진방향으로 풀려나가도록 롤형 시트(8)(예를들면;P.F.Film등)를 여러겹 깔고, 시트(8) 위에 통로거(1)를 바르게 올려놓는다. 시트(8)는 기초 콘크리트(a)의 상면과 굴착된 통로공의 바닥에서 통로거(1)를 굴진방향으로 밀 때 마찰저항을 줄여 이동하기 쉽게 하는 것으로, 표면이 매끈하고 얇은 합성수지 필름 등이다.The rolled sheet 8 (e.g., P. F. Film, etc.) is laid several times so that it may be released to the excavation direction on the foundation concrete (a), and the channel | channel 1 is correctly mounted on the sheet 8. The sheet 8 is a synthetic resin film having a smooth and thin surface, which is easy to move by reducing frictional resistance when pushing the passageway 1 in the excavation direction from the upper surface of the foundation concrete a and the bottom of the excavated passage hole. .

통로거(1)의 선단에 굴착챙(2)의 후단을 대고 그 부착공(25)의 중심을 너트(5)의 중심에 일치시킨 다음에 부착공(25) 쪽에서 보울트(9)를 체결하여 고정한다.Place the rear end of the excavation visor 2 on the tip of the passageway 1, align the center of the attachment hole 25 with the center of the nut 5, and then tighten the bolt 9 from the attachment hole 25. Fix it.

그리고 통로거(1)의 뒤쪽에 통로거 압입장치(4)를 설치하여 뒤쪽으로 미끄러지지 않게 고정하고, 유압장치(43)의 선단은 통로거(1)의 고무판(6)에 닿도록 조정한다.And by installing the passage indentation device 4 in the rear of the passageway (1) and fixed so as not to slip backwards, the front end of the hydraulic device 43 is adjusted to reach the rubber plate (6) of the passageway (1).

도 4에서, 유압장치(43)에 유압을 가하여 통로거(1)를 민다. 밀리는 통로거(1)는 바닥(11)의 선단이 여러겹의 시트(8)를 풀어 깔면서 타고 미끄러져 나아간다. 이때, 굴착날(3)은 통로공의 천장과 바닥쪽을 파고든다. 이 작업은 통로거(1)의 바닥(11) 선단이 노반(b)의 측면 하단에 닿을 때까지 진행한다. 그리하면 굴착챙(2)도 노반(b)에 박힌다.In FIG. 4, hydraulic pressure is applied to the hydraulic device 43 to push the passageway 1. The pusher passage 1 pushes and slides while the front end of the bottom 11 releases the multiple sheets 8. At this time, the excavation blade (3) cuts into the ceiling and the bottom of the passage hole. This operation proceeds until the tip of the bottom 11 of the passageway 1 reaches the bottom of the side surface of the roadbed b. Then the excavation visor (2) is also embedded in the roadbed (b).

굴착 작업자는 통로거(1)의 후단을 통해 들어가서 굴착챙(2) 안의 노반(b)을 굴착하고, 굴착된 토사는 통로거(1)의 후단 쪽으로 배출한다. 노반(b)에 대한 굴착은 굴착된 통로공(c)이 바닥(d)이 기초 콘크리트(a)의 상면과 높이가 같게 하여 통로거(1)를 밀어 넣기 쉽게 하고, 바닥도 평탄하게 조정한다. 그리고 통로거(1)의 후속 압입이 가능하도록 깊숙이 굴착한다. 빗면 노반(b)을 굴착하는 동안 굴착챙(2)과 굴착챙(2)내를 다수부분으로 구획분할 하는 수직구획판(12)을 답판(24)과 직각으로 설치하여 굴착되지 아니한 노반 토사가 무너지는 것을 방지해 준다. 이때, 국착챙내를 분할 하는 구획개수는 굴진하고자하는 토사의 종류 및 굴착챙의 크기등에 따라 결정한다.The excavation worker enters through the rear end of the aisle 1 to excavate the roadbed b in the excavation visor 2, and the excavated soil is discharged toward the rear end of the aisle 1. The excavation on the roadbed (b) is such that the excavated passage hole (c) has the same height as the top surface of the foundation concrete (a) so that the passageway (1) can be easily pushed in, and the bottom is adjusted evenly. . And it drills deep so that the subsequent press-fit of the passageway 1 is possible. During excavation of the roadbed (b), a vertical partition plate (12) which divides the excavation visor (2) and the inside of the excavation visor (2) into a plurality of parts at right angles with the answer plate (24) is installed. It prevents it from falling down. At this time, the number of partitions for dividing the stationary visor is determined according to the type of soil to be excavated and the size of the excavated visor.

도 5에서, 유압장치(43)에 2차 유압을 가하여 바닥(11)의 선단이 굴착된 통로공(c)의 바닥(d) 끝에 가 닿을 때까지 압입한다. 이때도 그 바닥(11)의 선단은 여러겹의 시트(8)를 밀어서 풀고, 통로거(1)는 깔린 시트(8)를 미끄럼타고 압입된다. 그 위치에서 상기와 같은 요령으로 재차 노반(b)을 굴착한다. 이 작업은 통로공(c)이 완전 개통시까지 반복한다. 굴진각도와 통로거의 높낮이가 어긋나면 굴진각도조절구(7)를 조작하여 바로 잡는다.In FIG. 5, the second hydraulic pressure is applied to the hydraulic device 43 to press-fit until the tip of the bottom 11 reaches the bottom d end of the excavated passage hole c. At this time, the front end of the bottom 11 pushes and releases the multiple sheets 8, and the passageway 1 slides and press-fits the sheet 8. At the position, the roadbed b is again excavated in the same manner as described above. This operation is repeated until the passage hole c is fully opened. If the excavation angle and the height of the aisle shifts, operate the excavation angle adjusting mechanism (7) to correct it.

도 6에서, 개통된 통로공(c)에 통로거(1)를 완전히 압입하여 정위치시켜 통로거(1)를 안정시킨 후에 통로거(1)에서 굴착챙(2)을 철거하고, 기초 콘크리트(a)의 통로거 압입장치(4)를 철거한 다음에 주변을 정리한다. 이로써 선로를 개착하지 않고도 노선을 횡단하는 지하통로가 감쪽같이 구축되는 것이다.In Fig. 6, after the passage girder 1 is completely press-fitted into the opened passage hole c to stabilize the passage girder 1, the excavation visor 2 is removed from the passage girder 1, and the foundation concrete After disassembling the passage indenter 4 of (a), the surroundings are cleared up. As a result, underground passages crossing the route are constructed like a persimmon without having to open the track.

이상 설명한대로 본 발명의 비개착식 선로 횡단 지하통로 구축장치를 사용하여 선로를 횡단하는 지하통로를 개설하면 그 개설작업이 대단히 신속 간편하고, 또한 경제적 시공이 가능하다.As described above, when the underground passage crossing the track is opened using the non-removable track crossing underground passage construction device of the present invention, the construction work is very quick and simple, and economical construction is possible.

Claims (7)

바닥과 벽 및 천장 일체형으로서 선단면에는 굴착챙 부착용 너트(5)를 설치한 통로거(1)와; 노반 굴진시 토사무너짐 방지용으로서 밑이 측벽(21)의 선단이 빗면(23)이고, 후단에는 통로거(1)의 너트(5)와 동수의 부착공(25)이 천공된 굴착챙(2)과; 굴착챙(2)의 천장(22)과 하부(11)의 선단에 부착하는 굴착날(3)과; 유압장치를 구비한 통로거 압입장치(4)로 이루어진 비개착식 선로 횡단 지하통로 구축장치.An aisle (1) having an excavation visor attachment nut (5) on the front end as an integrated bottom, wall, and ceiling; Excavation visor (2) in which the tip of the side wall (21) is the inclined surface (23), and the nut (5) of the aisle (1) and the same number of attachment holes (25) are drilled at the rear end to prevent soil collapse during roadbed excavation. and; An excavation blade (3) attached to the tip of the ceiling (22) and the lower portion (11) of the excavation visor (2); A non-adhesive track crossing underground passage building device comprising an aisle indenter having a hydraulic device (4). 제1항에 있어서, 상기 통로거(1)는 후단 모퉁이에 완충용 고무판(6)이 부착된 비개착식 선로 횡단 지하통로 구축장치.2. The apparatus of claim 1, wherein the passageway (1) is a non-adhesive track crossing basement passage with a rubber plate (6) attached to the rear corner. 제1항에 있어서, 상기 굴착챙(2)은 내부에 답판(24)이 설치된 비개착식 선로 횡단 지하통로 구축장치.The method of claim 1, wherein the excavation visor (2) is a non-adhesive track crossing underground passage construction device installed in the answer plate 24. 제3항에 있어서, 상기 굴착챙(2) 내부를 다수부분으로 구획분할 하는 수직구획판(12)을 답판(24)과 직각으로 설치된 비개착식 선로 횡단 지하통로 구축장치.4. The apparatus of claim 3, wherein a vertical partition plate (12) for dividing the inside of the excavation visor (2) into a plurality of parts is installed at a right angle with the answer plate (24). 제4항에 있어서, 상기 답판(24)은 후단에 슈트가 설치된 비개착식 선로 횡단 지하통로 구축장치.5. The apparatus of claim 4, wherein the answer plate (24) has a chute installed at the rear end thereof. 제1항에 있어서, 상기 굴착날(3)은 굴진각도 및 통로거 높낮이 조절구(7)로 굴진각도 및 통로거 높낮이를 수정하도록 된 비개착식 선로 횡단 지하통로 구축장치.2. The apparatus of claim 1, wherein the excavation blade (3) is adapted to modify the excavation angle and the aisle height by the excavation angle and the aisle height adjustment mechanism (7). 선로 횡단 지하통로 개설위치에서 굴진방향의 외곽 지반을 정리하여 통로거와 통로거 압입장치를 수용하는 기초 콘크리트를 타설하여 양생시키는 단계와; 상기 기초 콘크리트 위에 미끄럼 마찰저항 감소를 위한 시트를 여러겹 깔고 그 위에 통로거를 바르게 올려놓는 단계와; 상기 통로거의 선단에 굴착챙의 후단을 대고 그 부착공을 통하여 너트에 보울트를 체결하여 고정하는 단계와; 상기 통로거의 뒤쪽 기초 콘크리트 상에 유압장치로 이루어진 통로거 압입장치를 설치하여 고정하고 그 유압장치의 선단을 통로거의 후단에 밀착시키는 단계와; 유압장치에 유압을 가하여 통로거의 선단이 노반에 닿을 때까지 밀어서 이동시키는 단계와; 통로거의 후단으로 들어가 굴착챙 안과 그 전방의 노반을 굴착하여 통로공을 형성하고 그 바닥을 상기 기초 콘크리트의 상면과 같게 조정하는 단계와; 상기 통로거 유압장치를 재가동하여 통로거의 바닥 선단이 상기 통로공의 바닥끝에 가 닿도록 압입하고 통로공 앞쪽의 노반을 굴착하여 통로공을 개통하는 단계와; 통로거 압입장치로 통로거를 개통된 통로공에 관통시켜 정위치시키는 단계와; 통로거에서는 굴착챙을 그리고 기초 콘크리트상에서는 통로거 압입장치를 철거하고 주변을 정리하는 단계로 진행하는 것을 특징으로 하는 비개착식 선로 횡단 지하통로 시공방법.Arranging the outer ground in the excavation direction at the opening position of the railroad crossing underground passage to pour and cure the base concrete for accommodating the aisle and the aisle indenter; Placing a plurality of sheets on the foundation concrete for reducing sliding friction resistance and placing the aisles on them; Fastening the bolt to the nut through the attachment hole by applying the rear end of the excavation visor to the tip of the passageway; Installing and fixing an aisle press indenter composed of a hydraulic device on the foundation concrete behind the aisle and closely attaching a front end of the aisle device to a rear end of the aisle; Applying hydraulic pressure to the hydraulic device to move the tip of the passageway until it reaches the roadbed; Entering the rear end of the passageway to excavate the roadbed in and out of the excavation visor to form a passage hole and adjust its bottom to be the same as the upper surface of the foundation concrete; Re-activating the passageway hydraulic device to press the bottom end of the passageway to reach the bottom end of the passageway, and to excavate the roadbed in front of the passageway to open the passageway; Positioning the passageway through the passageway through the passageway through the passageway indentation device; A method of constructing a non-adhesive track crossing underground passage, characterized in that the excavation visor in the aisle and the foundation concrete in the base concrete is removed and proceeds to clean up the surroundings.
KR10-2002-0014569A 2002-03-18 2002-03-18 apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same KR100463715B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2002-0014569A KR100463715B1 (en) 2002-03-18 2002-03-18 apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2002-0014569A KR100463715B1 (en) 2002-03-18 2002-03-18 apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020020007969U Division KR200290860Y1 (en) 2002-03-18 2002-03-18 apparatus for constructing unexcavated underground tunnel for railroad traverse

Publications (2)

Publication Number Publication Date
KR20030075383A KR20030075383A (en) 2003-09-26
KR100463715B1 true KR100463715B1 (en) 2004-12-29

Family

ID=32225215

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2002-0014569A KR100463715B1 (en) 2002-03-18 2002-03-18 apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same

Country Status (1)

Country Link
KR (1) KR100463715B1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110438913B (en) * 2018-05-03 2024-05-24 河北高达智能装备股份有限公司 Box culvert jacking elevation control system
KR102024698B1 (en) * 2019-02-26 2019-09-24 주식회사 마성건설 Construction method of underground structure using the trenchless intermediate base

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51110809A (en) * 1975-03-25 1976-09-30 Eishin Doboku Kk BUREEDOSHIIRUDOSUISHINKOHO
EP0245155A1 (en) * 1986-05-09 1987-11-11 Jean Marie Beauthier Process for carrying out works under railway tracks in operation
JPH02252892A (en) * 1989-03-25 1990-10-11 Okumura Corp Method for constructing underground structure
US5129760A (en) * 1989-12-07 1992-07-14 Aeb Jacked Structures Limited Forming a passageway through the ground
JPH0641963A (en) * 1992-04-17 1994-02-15 Koichi Uemura Open shield construction method and open shield machine
JPH0640096U (en) * 1992-11-05 1994-05-27 日本鉱機株式会社 Open shield machine
JPH07197781A (en) * 1993-12-29 1995-08-01 Okumura Corp Propulsion guide member for underground structure and burying method for the structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS51110809A (en) * 1975-03-25 1976-09-30 Eishin Doboku Kk BUREEDOSHIIRUDOSUISHINKOHO
EP0245155A1 (en) * 1986-05-09 1987-11-11 Jean Marie Beauthier Process for carrying out works under railway tracks in operation
JPH02252892A (en) * 1989-03-25 1990-10-11 Okumura Corp Method for constructing underground structure
US5129760A (en) * 1989-12-07 1992-07-14 Aeb Jacked Structures Limited Forming a passageway through the ground
JPH0641963A (en) * 1992-04-17 1994-02-15 Koichi Uemura Open shield construction method and open shield machine
JPH0640096U (en) * 1992-11-05 1994-05-27 日本鉱機株式会社 Open shield machine
JPH07197781A (en) * 1993-12-29 1995-08-01 Okumura Corp Propulsion guide member for underground structure and burying method for the structure

Also Published As

Publication number Publication date
KR20030075383A (en) 2003-09-26

Similar Documents

Publication Publication Date Title
KR20090100867A (en) The method construction work and unit metal tubing constructing system for the road underground driveway
KR102276610B1 (en) Precast Structure for Straigt Retaining Wall using Temporary Sheating Wall after Constructing Temporary Sheating Wall and Construction Method using Thereof
US5671584A (en) Method and apparatus for constructing a retaining wall
US20220162819A1 (en) Apparatus and method for installation of support posts for a vehicle restraint system
US20230349117A1 (en) System, apparatus and method for installation of street furniture
KR100463715B1 (en) apparatus for constructing unexcavated underground tunnel for railroad traverse and method for constructing underground tunnel for railroad traverse using the same
KR100626328B1 (en) method for extending and removing wall of subway structure in subway service line
KR200290860Y1 (en) apparatus for constructing unexcavated underground tunnel for railroad traverse
KR101194102B1 (en) The Excavation Method of Concrete Tunnel Construction
JPS622116B2 (en)
JP3450294B2 (en) Supporting structure of lining plate and lining method
KR100794810B1 (en) Excavation method of road and railroad lower part using deck unit jacking
JP3116098B2 (en) Construction method for underground structures
JPH0440519B2 (en)
CZ1392A3 (en) Method of foundation engineering along a traffic road, for instance soundproof walls
KR200371996Y1 (en) Holding plate assembly for engineering and construction
KR100959411B1 (en) Method for constructing arch structure of movable girder and arch structhre constructed by this method
JP5167578B2 (en) Construction method for underground structures
JPS5988593A (en) Construction of underpass
JP4195215B2 (en) Mountain retaining method and foundation construction method
JPH0555679B2 (en)
JPH0439559B2 (en)
JP2004183441A (en) Construction method for underground passage
KR20020056367A (en) A pipe shield tunneling method
JP2020066973A (en) Construction method of lifeline

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
N231 Notification of change of applicant
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121218

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20131211

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20151207

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20161118

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20171117

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20191114

Year of fee payment: 16