KR100448221B1 - Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same - Google Patents

Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same Download PDF

Info

Publication number
KR100448221B1
KR100448221B1 KR10-2001-0070237A KR20010070237A KR100448221B1 KR 100448221 B1 KR100448221 B1 KR 100448221B1 KR 20010070237 A KR20010070237 A KR 20010070237A KR 100448221 B1 KR100448221 B1 KR 100448221B1
Authority
KR
South Korea
Prior art keywords
culvert
formwork
slab
plate member
side wall
Prior art date
Application number
KR10-2001-0070237A
Other languages
Korean (ko)
Other versions
KR20020005537A (en
Inventor
이석태
이호석
최시덕
Original Assignee
주식회사 토암건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 토암건설 filed Critical 주식회사 토암건설
Priority to KR10-2001-0070237A priority Critical patent/KR100448221B1/en
Publication of KR20020005537A publication Critical patent/KR20020005537A/en
Application granted granted Critical
Publication of KR100448221B1 publication Critical patent/KR100448221B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/34Horizontally-travelling moulds for making walls blockwise or section-wise
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/02Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for rooms as a whole by which walls and floors are cast simultaneously, whole storeys, or whole buildings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/50Girders, beams, or the like as supporting members for forms
    • E04G11/54Girders, beams, or the like as supporting members for forms of extensible type, with or without adjustable supporting shoes, fishplates, or the like
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/102Removable shuttering; Bearing or supporting devices therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
  • Sewage (AREA)

Abstract

본 발명은 암거의 시공속도가 빠르고, 시공 후 즉시 되메우기 할 수 있도록 이동식 철재 거푸집장치를 사용하여 구체를 연속적으로 형성함과 동시에 현장에서 증기를 이용하여 촉진 양생하므로써 양생기간을 단축시켜 거푸집 존치기간을 최소화하고 연속적으로 암거를 제작하여 불필요한 공기지연 등의 문제를 해소하고 현재의 공법보다 월등하게 시공기간을 단축시킬 수 있도록 한 것이다.The present invention is a fast construction speed of the culvert, to form a sphere continuously by using a mobile steel formwork to be able to refill immediately after construction and at the same time by using a steam in the field to accelerate curing curing time to shorten the curing period By minimizing and making culverts continuously, it is possible to solve the problem of unnecessary air delay and to shorten the construction period much better than the current method.

본 발명의 구성은 상기 암거(300)의 바닥슬래브(310)를 형성하기 위한 기초슬래브 거푸집부재(10)와, 상기 기초슬래브 거푸집부재(10)의 상면을 따라 전후 이동이 가능하고 증기공급관(50)이 외면에 설치되어 있어 암거 콘크리트 타설 후 증기를 공급하여 콘크리트를 증기촉진양생시킬 수 있는 외부 측벽 거푸집부재(30)와, 상기 암거(300)의 바닥슬래브(310)의 전후면을 형성하기 위한 기초슬래브 마감판부재(102)와, 상기 암거(300)의 전후면을 형성하기 위한 전후면 마감판부재(104)를 포함하는 외부 거푸집장치; 및 상기 외부 거푸집장치와 소정 간격 이격되어 설치되므로써 암거(300)의 내부면을 형성하게 되는 내부 거푸집장치(60)로서, 측벽판부재(66)와, 상부슬래브판부재(64), 신축되어 측벽판부재(66)를 좌우로 움직이며 상부슬래브판부재(64)를 상하로 움직여서 내부 거푸집장치(60)를 확장/수축시킬 수 있는 신축수단(70,71,72)과, 전후로 이동할 수 있도록 구동장치(62)가 구비된 내부 거푸집장치(60)로 이루어져 있다.The configuration of the present invention is the base slab formwork member 10 for forming the bottom slab 310 of the culvert 300, and the front and rear movement along the upper surface of the foundation slab formwork member 10 and the steam supply pipe 50 ) Is installed on the outer surface to form the front and rear surfaces of the outer side wall formwork member 30 and the bottom slab 310 of the culvert 300 to supply steam after culvert concrete is poured to promote steam curing. An external formwork device including a foundation slab closing plate member 102 and a front and rear closing plate member 104 for forming a front and rear surface of the culvert 300; And an inner formwork device 60 which forms an inner surface of the culvert 300 by being spaced apart from the outer formwork device by a predetermined distance, wherein the sidewall plate member 66 and the upper slab plate member 64 are stretched and sidewalls. Extension means (70, 71, 72) capable of expanding and contracting the internal formwork device (60) by moving the upper and lower slab plate members (64) up and down while moving the plate member 66 to the left and right, and to move back and forth It consists of an internal formwork device 60 with a device 62.

이러한 구성을 가지는 본 발명은 이동식 철재거푸집을 사용함으로써 제품면이 미려하고, 연속작업이 가능하며 시공속도가 빨라 공기를 단축시킬 수 있는 것이다.The present invention having such a configuration is that by using a mobile iron formwork, the product surface is beautiful, continuous work is possible and the construction speed is fast to shorten the air.

또한, 콘크리트의 양생기간을 단축시킴으로 해서 공기를 단축시킬 수 있고, 동절기 및 기상악화시에도 적응력이 우수하여 별도의 양생비가 들지 않는다.In addition, it is possible to shorten the air by shortening the curing period of the concrete, and even in winter and weather worsening adaptability is excellent, does not cost a separate curing cost.

Description

암거 제작용 이동식 철재 거푸집장치 및 이를 이용한 암거의 증기촉진양생 연속시공방법{Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same}Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same}

본 발명은 암거 제작용 이동식 철재 거푸집장치 및 이를 이용한 암거의 증기촉진양생 연속시공방법에 관한 것으로, 더욱 상세하게는 암거 제작용 철재 거푸집장치를 분해, 조립과 이동이 자유로운 이동식으로 구성하여 1지간의 암거 시공이 완료되면 철재 거푸집장치를 진출시켜 후속 지간의 암거를 연속하여 시공할 수 있으며 증기를 이용한 암거의 촉진양생이 가능한 새로운 구조의 암거 제작용 이동식 철재 거푸집장치 및 이를 이용하여 암거를 증기촉진양생시켜 연속적으로 시공할 수 있는 시공방법에 관한 것이다.The present invention relates to a portable steel formwork device for culvert production and a steam-promoting curing continuous construction method of the culvert using the same, more specifically, the steel formwork device for culvert production by disassembling, assembling and moving freely configured When the culvert construction is completed, the steel formwork can be advanced to construct the culvert between the subsequent lands, and the mobile steel formwork for the production of the culvert with a new structure capable of promoting curing of the culvert using steam and the cultivation of the culvert using the same It relates to a construction method that can be installed continuously.

대단위 택지 개발 및 밀집 주택의 증대로 각종 하수도를 만들거나 전력구, 통신구 또는 공동구 등의 시설 수요가 급증하고 있는 추세이다. 이러한 용도로 사용되는 암거를 시공하는 종래의 방법은 콘크리트를 현장에서 타설하여 양생시켜 암거를 구축하는 현장타설 시공공법이 주로 이용되어 왔다. 그러나, 이러한 현장타설 시공공법은, 콘크리트의 양생에 많은 시간이 소요되어 전체적으로 공기가 지연되는 원인이 되었고, 양생시 철저한 관리가 필요하여 부대비용이 많이 들었으며, 동절기 공사일 때는 특히 양생관리가 어려운 문제점이 대두되었다. 또한, 공기가 지연됨에 따라 도심지 공사일 경우 교통체증의 원인이 되는 등 각종 민원이 발생하였다.Due to the development of large-scale housing sites and the increase of dense houses, the demand for facilities such as electric power districts, communication districts, and community districts is rapidly increasing. The conventional method of constructing a culvert used for such a purpose has been mainly used a site-installation construction method of constructing a culvert by pouring concrete in the field. However, this method of cast-in-place construction, which takes a lot of time to cure concrete, caused the delay of the air as a whole, and it required a thorough management during curing, resulting in a lot of incidental costs, especially during winter construction. Problems have arisen. In addition, due to the delay of air, various civil complaints occurred in the case of urban construction, causing traffic jams.

이에 따라 최근 들어 공기, 경제성, 민원해소 등의 문제를 해소하기 위해 공장에서 미리 제작한 제품을 현장에서 조립, 시공하는 PC(Precast Concrete) 조립식 공법을 많이 사용하고 있으나, 이 또한 분기구 등의 현장 타설 접합 부분의 처리에 많은 주의를 필요로 하고, 종단 및 선형변화 부분에 설치할 별도의 이형제품이 필요하여 시공비의 상승을 초래하였고, 특히 구조물의 공사비가 많이 소요되어 대규모 암거 시공시에는 원가문제로 오히려 현장타설식 공법을 선호하는 경우도 있었다.Accordingly, in order to solve the problems of air, economics and civil complaints, PC (Precast Concrete) prefabricated construction methods are often used to assemble and construct products pre-fabricated at the factory. It requires a lot of attention to the processing of pour joints, and it requires a separate release product to be installed in the end and linear change part, which leads to an increase in construction cost. Rather, in some cases, cast-in-place methods were preferred.

이에 본 발명은 상기와 같은 종래의 제반 문제점을 감안하여 개발된 것으로서, 암거의 시공속도가 빠르고, 시공 후 즉시 되메우기 할 수 있도록 이동식 철재 거푸집장치를 사용하여 구체를 연속적으로 형성함과 동시에 현장에서 증기를 이용하여 촉진 양생하므로써 양생기간을 단축시켜 거푸집 존치기간을 최소화하고 연속적으로 암거를 제작하여 불필요한 공기지연 등의 문제를 해소하고 현재의 공법보다 월등하게 시공기간을 단축시킬 수 있도록 하는 것을 목적으로 개발되었다.Therefore, the present invention was developed in view of the above-mentioned conventional problems, and the construction speed of the culvert is fast, and using the movable steel formwork to continuously fill the sphere immediately after construction to form a sphere continuously and at the same time steam in the field The purpose is to reduce the curing period by minimizing the curing period by stimulating curing by using squeeze, and to make the culvert continuously to solve the problems such as unnecessary air delay and to shorten the construction period much better than the current method. It became.

도 1은 본 발명의 이동식거푸집장치의 일실시예와 암거를 개략적으로 도시한 분해사시도1 is an exploded perspective view schematically showing an embodiment and a culvert of the mobile formwork of the present invention;

도 2는 본 발명의 이동식거푸집장치의 조립상태를 도시한 사시도Figure 2 is a perspective view showing the assembled state of the mobile formwork of the present invention

도 3a는 본 발명의 기초슬래브 거푸집부재의 일실시예를 도시한 정면도와 부분상세도Figure 3a is a front view and a partial detailed view showing an embodiment of the foundation slab formwork member of the present invention

도 3b는 본 발명의 기초슬래브 거푸집부재의 또 다른 실시예에 대한 부분상세도Figure 3b is a partial detailed view of another embodiment of the foundation slab formwork member of the present invention

도 4는 본 발명의 암거의 바닥슬래브를 제작하는 형상을 개략적으로 도시한 사시도Figure 4 is a perspective view schematically showing the shape of manufacturing the floor slab of the culvert of the present invention

도 5는 본 발명의 기초슬래브 마감판부재를 도시한 정면도Figure 5 is a front view showing the foundation slab closing plate member of the present invention

도 6은 본 발명의 외부 측벽 거푸집부재의 일실시예를 도시한 정면도6 is a front view showing one embodiment of the outer side wall formwork member of the present invention;

도 7은 본 발명의 외부 측벽 거푸집부재의 구동부를 도시한 정면도7 is a front view showing the driving portion of the outer side wall formwork member of the present invention;

도 8은 본 발명의 외부 측벽 거푸집부재의 구동부를 도시한 측면도8 is a side view showing a drive unit of the outer side wall formwork member of the present invention;

도 9는 본 발명의 외부 측벽 거푸집부재의 구동부를 도시한 평면도9 is a plan view showing a drive unit of the outer side wall formwork member of the present invention;

도 10은 본 발명의 외부 측벽 거푸집부재의 작업대를 도시한 정면도10 is a front view showing a work table of the outer side wall formwork member of the present invention.

도 11은 본 발명의 내부 거푸집장치의 일실시예를 도시한 정면도11 is a front view showing an embodiment of the internal formwork apparatus of the present invention;

도 12는 본 발명의 전후면 마감판부재를 도시한 정면도12 is a front view showing the front and rear closing plate member of the present invention.

도 13은 본 발명의 측벽 및 상부슬래브 보강철근을 배근한 상태를 도시한 사시도Figure 13 is a perspective view showing a state in which the side wall and the upper slab reinforcement of the present invention is placed

도 14는 본 발명의 이동식거푸집장치의 설치상태를 도시한 정면도14 is a front view showing an installation state of the mobile formwork of the present invention.

도 15는 본 발명의 이동식거푸집장치의 이동할 때의 상태를 도시한 정면도15 is a front view showing a state when the mobile formwork of the present invention moves.

도 16은 본 발명의 이동식거푸집장치에 콘크리트를 타설하는 상태를 도시한 전체사시도Figure 16 is a full perspective view showing a state in which the concrete is poured into the mobile formwork of the present invention

*도면의 주요부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

10 : 기초슬래브 거푸집부재 12 : 평면부10: foundation slab formwork member 12: flat part

13 : 볼트 14 : 보강부13 bolt 14 reinforcement

15 : 연결부재 16, 312 : 레일부15: connecting member 16, 312: rail portion

18 : 파이프관 27 : 볼트구멍18 pipe pipe 27 bolt hole

28 : 블럭아웃부 30 : 외부 측벽 거푸집부재28 block-out part 30 outer side wall formwork member

32 : 구동부 33, 63 : 조절부재32: drive unit 33, 63: adjustment member

38 : 작업대 42 : 간격유지장치38: workbench 42: spacing device

44 : 구동부하우징 46 : 고정볼트44: drive part housing 46: fixed bolt

48 : 구동체 50, 61 : 증기공급관48: driving body 50, 61: steam supply pipe

51 : 구동바퀴 54 : 지지대51: driving wheel 54: support

57 : 안전난간 58 : 보행판57: safety rail 58: walking board

60 : 내부 거푸집장치 62 : 구동장치60: internal formwork device 62: drive device

64 : 상부슬래브판부재 66 : 측벽판부재64 upper slab plate member 66 side wall plate member

68 : 헌치부판부재 70, 71, 72 : 신축수단68: haunting plate member 70, 71, 72: expansion means

80 : 베이스 84 : 승하강장치80: base 84: lifting device

102 : 기초슬래브 마감판부재 104 : 전후면 마감판부재102: foundation slab closing plate member 104: front and back closing plate member

106 : ㄱ자형강 108 : ㅁ자형강106: angled steel 108: angled steel

150 : 바닥슬래브 보강철근 152 : 측벽 및 상부슬래브 보강철근150: bottom slab reinforcement 152: side walls and upper slab reinforcement

200 : 이동식거푸집장치 300 : 암거200: mobile formwork device 300: culvert

310 : 바닥슬래브 320 : 측벽부310: floor slab 320: side wall

상기와 같은 목적을 달성하기 위한 본 발명의 구성은 콘크리트 암거를 연속적으로 제작하기 위한 이동식 거푸집장치로서, 상기 암거의 바닥슬래브를 형성하기 위한 기초슬래브 거푸집부재와, 상기 기초슬래브 거푸집부재의 상면을 따라 전후 이동이 가능하여 1지간의 암거 시공이 완료되면 상기 기초슬래브 거푸집부재로부터 분리되어 이웃하는 지간의 암거 시공을 위하여 이동하며, 암거의 측벽부를 형성하도록 암거의 측벽부 외부에 설치되고 증기공급관이 외면에 설치되어 있어 암거 콘크리트 타설 후 증기를 공급하여 콘크리트를 증기촉진양생시킬 수 있는 외부 측벽 거푸집부재와, 상기 암거의 바닥슬래브의 전후면을 형성하기 위한 기초슬래브 마감판부재와, 상기 암거의 전후면을 형성하기 위한 전후면 마감판부재를 포함하는 외부 거푸집장치; 및 상기 외부 거푸집장치와 소정 간격 이격되어 설치되므로써 암거의 내부면을 형성하게 되는 내부 거푸집장치로서, 암거의 측벽 콘크리트 내면과 마주하게 되는 측벽판부재와, 암거의 상부슬래브 콘크리트의 하부면과 마주하게 되는 상부슬래브판부재와, 신축되어 측벽판부재를 좌우로 움직이며 상부슬래브판부재를 상하로 움직여서 내부 거푸집장치를 확장/수축시킬 수 있는 신축수단과, 전후로 이동할 수 있도록 구동장치가 구비되어 있어, 암거 시공을 위한 콘크리트 타설시에는 상기 신축수단을 신장시켜 상기 측벽판부재와 상부슬래브판부재를 확장상태로 만들고, 암거 시공이 완료되면 상기 신축수단을 수축시켜 상기 측벽판부재와 상부슬래브판부재를 수축상태로 함과 동시에 상기 구동장치가 구동가능상태로 되어 1지간의 암거 시공이 완료되면 이웃하는 지간의 암거 시공을 위하여 이동할 수 있는 베이스를 포함하는 내부 거푸집장치를 구비하고 있는 것을 기술적 특징으로 한다.The configuration of the present invention for achieving the above object is a mobile formwork for continuously manufacturing a concrete culvert, the base slab formwork member for forming the bottom slab of the culvert, and along the upper surface of the base slab formwork member It is possible to move back and forth, and when the construction of one site is completed, it is separated from the foundation slab formwork member and moved for the construction of the neighboring site.It is installed outside the side wall of the culvert to form the side wall of the culvert, and the steam supply pipe is external It is installed in the outer side wall formwork member to supply steam after pouring the culvert concrete, and to promote steam curing, and the base slab finishing plate member for forming the front and rear surfaces of the bottom slab of the culvert, and the front and rear surfaces of the culvert External formwork device including a front and rear closing plate member to form a ; And an inner formwork device which forms an inner surface of the culvert by being spaced apart from the outer formwork by a predetermined distance, the sidewall plate member facing the inner surface of the culvert sidewall, and facing the lower surface of the upper slab concrete of the culvert. It is provided with an upper slab plate member, an expansion and contraction means for expanding and contracting the internal formwork device by moving the upper and lower slab plate members to the left and right and moving the upper slab plate member up and down, and a driving device to move back and forth, When placing concrete for culling construction, the expansion means is extended to make the side wall plate member and the upper slab plate member expanded, and when the culling construction is completed, the expansion means is shrunk to contract the side wall plate member and the upper slab plate member. At the same time as the contracted state, the drive device becomes the driveable state, and the culling construction between the one ground is completed. The technical feature is that it has an internal formwork including a base that can move for the culvert construction between neighboring grounds.

상기 기초슬래브 거푸집부재에는 외부 측벽 거푸집부재의 이동을 위한 레일부가 구비되어 있으며, 상기 외부 측벽 거푸집부재에는 상기 레일부를 따라 구동되어 상기 외부 측벽 거푸집부재를 전후로 이동시키는 구동부가 구비되어 있는 것을 특징으로 한다.The foundation slab formwork member is provided with a rail portion for the movement of the outer sidewall formwork member, the outer sidewall formwork member is characterized in that it is provided with a drive unit for driving along the rail portion to move the outer sidewall formwork member back and forth. .

상기 암거의 바닥슬래브 상에는 상기 내부 거푸집장치가 이동할 수 있도록 레일부가 구비되고, 상기 외부 측면 거푸집부재에 구비된 증기공급관과 아울러 암거 콘크리트 타설후 증기를 공급하여 콘크리트를 양생시킬 수 있도록 상기 레일부의 일측으로 증기공급관이 구비되는 것을 특징으로 한다.A rail part is provided on the bottom slab of the culvert to move the inner formwork device, and one side of the rail part so as to cure concrete by supplying steam after pouring culvert concrete with the steam supply pipe provided on the outer side formwork member. It characterized in that the steam supply pipe is provided.

상기 외부 측벽 거푸집부재의 상부에는 접철식으로 구성되어 외부 측벽 거푸집부재의 고정설치 상태에서는 펼쳐져서 작업자가 보행할 수 있는 보행가능상태가되고, 외부 측벽 거푸집부재의 이동시에는 접혀져서 작업자가 보행할 수 없는 보행불능상태로 되는 안전난간이 구비된 작업자 보행용 작업대가 설치되어 있는 것을 특징으로 한다.The top of the outer side wall formwork member is foldable and is expanded in a fixed installation state of the outer side wall formwork member so that the worker can walk, and when the outer side wall formwork member is moved, it is folded so that the worker cannot walk. Characterized in that the worker walking work platform is provided with a safety railing that becomes impossible to walk.

상기 베이스의 하부에는 베이스를 승하강시킬 수 있는 승하강장치가 구비되며, 상기 베이스의 상부에는 상기 상부슬래브판부재를 지지하는 지지기둥이 설치되어 있고, 상기 지지기둥에는 신축에 의하여 양측의 측벽판부재를 좌우로 움직일 수 있는 신축수단이 각각 설치되어 있는 것을 특징으로 한다.The lower part of the base is provided with a lifting device capable of raising and lowering the base, and a support pillar for supporting the upper slab plate member is installed at an upper portion of the base, and the support pillar is provided with side wall plates on both sides by expansion and contraction. It is characterized in that the elastic means for moving the member to the left and right, respectively.

상기 내부 거푸집장치의 측벽판부재와 상기 외부 측벽 거푸집부재에는 그 일부로써, 규격이 다른 암거의 제작시 높이방향으로의 길이를 늘리거나 줄일 수 있도록 착탈이 가능한 조절부재가 구비되어 있는 것을 특징으로 한다.The side wall plate member and the outer side wall formwork member of the inner formwork device, as a part thereof, is characterized in that the removable member is provided so that the length can be increased or reduced in the height direction during the manufacture of different culverts. .

또한, 본 발명은 암거의 바닥슬래브를 형성하기 위한 기초슬래브 거푸집부재와, 상기 기초슬래브 거푸집부재의 상면을 따라 전후 이동이 가능하며 암거의 측벽부를 형성하도록 암거의 측벽부 외부에 설치되고 증기공급관이 외면에 설치되어 있는 외부 측벽 거푸집부재와, 상기 암거의 바닥슬래브의 전후면을 형성하기 위한 기초슬래브 마감판부재와, 상기 암거의 전후면을 형성하기 위한 전후면 마감판부재를 포함하는 외부 거푸집장치; 및 상기 외부 거푸집장치와 소정 간격 이격되어 설치되므로써 암거의 내부면을 형성하게 되는 내부 거푸집장치로서, 암거의 측벽 콘크리트 내면과 마주하게 되는 측벽판부재와, 암거의 상부슬래브 콘크리트의 하부면과 마주하게 되는 상부슬래브판부재와, 신축되어 측벽판부재를 좌우로 움직이며 상부슬래브판부재를 상하로 움직여서 내부 거푸집장치를 확장/수축시킬 수 있는 신축수단과, 전후로 이동할 수 있도록 구동장치가 구비되어 있는 베이스를 포함하는 내부 거푸집장치를 구비하고 있는 암거 제작용 이동식 거푸집장치를 이용한 암거의 증기촉진양생 연속시공방법으로서, 상기 기초슬래브 거푸집부재, 기초슬래브 마감판부재를 결합하고, 그 내측으로 바닥슬래브 보강철근과 암거의 측벽 및 상부슬래브 보강철근을 배근한 후 콘크리트를 타설하여 바닥슬래브를 시공하고, 상기 기초슬래브 거푸집부재 및 기초슬래브 마감판부재와 외부 측벽 거푸집부재 및 전후면마감판부재를 결합하여 외부 거푸집장치의 설치를 완료하고, 상기 보강철근의 내측으로 수축상태의 내부 거푸집장치를 설치하고, 상기 내부 거푸집장치에 구비된 신축수단을 신장시키고 상기 베이스의 승하강장치를 상승시켜 상기 측벽판부재와 상부슬래브판부재를 확장시킴으로써 내부 거푸집장치를 확장상태로 만들고, 상기 외부 거푸집장치와 내부 거푸집장치 사이의 공간에 콘크리트를 타설하여 암거를 시공하고, 외부 거푸집장치와 암거의 상부슬래브 전체가 덮이도록 양생커버를 덮은 후 외부 측벽 거푸집부재의 증기공급관과 암거의 바닥슬래브 상의 증기공급관으로 증기를 공급하여 암거를 증기에 의한 촉진양생을 시키며, 암거의 양생이 완료되면, 외측 거푸집장치의 결합을 해제하고, 내부 거푸집장치의 신축수단을 수축시키고 상기 베이스의 승하강장치를 하강시켜 상기 측벽판부재와 상부슬래브판부재를 수축시킴과 동시에 상기 베이스의 구동장치를 구동가능상태가 되도록 함으로써 상기 내부 거푸집장치를 수축상태로 만들고, 상기 내부 거푸집장치와 상기 외부 거푸집장치를 이웃하는 지간의 암거 시공을 위하여 이동시키는 것을 기술적 특징으로 한다.In addition, the present invention is the base slab formwork member for forming the bottom slab of the culvert, and the front and rear movement along the upper surface of the base slab formwork member and is installed outside the sidewall portion of the culvert to form a sidewall portion of the culvert and the steam supply pipe External formwork device including an external side wall formwork member installed on an outer surface, a foundation slab closing plate member for forming front and rear surfaces of the bottom slab of the culvert, and a front and rear finishing plate member for forming front and rear surfaces of the culvert. ; And an inner formwork device which forms an inner surface of the culvert by being spaced apart from the outer formwork by a predetermined distance, the sidewall plate member facing the inner surface of the culvert sidewall, and facing the lower surface of the upper slab concrete of the culvert. The upper slab plate member is expanded, and the expansion and contraction means to expand and contract the internal formwork by moving the upper side slab plate member to the left and right and the upper slab plate member to move up and down, and the base is provided with a drive device to move back and forth As a steam-promoting curing continuous construction method of the culvert using a portable formwork for making a culvert equipped with an internal formwork device, comprising: combining the foundation slab formwork member, the foundation slab finishing plate member, the inner side of the bottom slab reinforcement Reinforce the sidewalls and upper slab reinforcements of the By installing the bottom slab, combining the foundation slab formwork member, the foundation slab closing plate member, the outer sidewall formwork member and the front and rear side finishing plate member to complete the installation of the external formwork device, and the contracted state of the reinforcing bar Install the inner formwork device of the inner formwork, and expand the expansion means provided in the inner formwork device and raise the lifting device of the base to expand the sidewall plate member and the upper slab plate member to make the inner formwork device in an expanded state, Construct the culvert by placing concrete in the space between the external formwork and the internal formwork, and cover the curing cover to cover the entire upper slab of the external formwork and the culvert, and then the steam supply pipe of the external sidewall formwork member and the bottom slab of the culvert. Steam is supplied to the steam supply pipe on the When curing of the culvert is completed, the coupling of the outer formwork device is released, the expansion means of the inner formwork device are contracted, and the lifting device of the base is lowered to contract the sidewall plate member and the upper slab plate member. By making the driving device of the base into a driveable state, the inner formwork device is made in a contracted state, and the inner formwork device and the outer formwork device are characterized in that they are moved for culling construction between neighboring grounds.

또한, 상술한 바와 같이 내부 거푸집장치를 수축상태로 만든 후에, 이웃하는 지간의 암거의 연속시공을 위하여 상기의 과정에서 완성된 암거의 이웃한 지간에 다시 상기 기초슬래브 거푸집부재, 기초슬래브 마감판부재를 결합하여 그 내측으로 바닥슬래브 보강철근과 암거의 측벽 및 상부슬래브 보강철근을 배근한 후 콘크리트를 타설하여 바닥슬래브를 시공하고, 상기 완성된 암거로부터 탈거된 외부 측벽 거푸집부재를 이동시켜 다시 결합하여 외부 거푸집장치를 설치하고, 상기 수축상태의 내부 거푸집장치를 이웃한 암거의 완성된 바닥슬래브 상부로 이동시켜 확장상태로 만들고 다시 콘크리트를 타설하여 연속적인 암거를 시공하는 것을 특징으로 한다.In addition, as described above, after the internal formwork device is in a contracted state, the foundation slab formwork member and the foundation slab closing plate member are placed back to the neighboring space of the culvert completed in the above process for continuous construction of the culvert between neighboring lands. Combining the bottom slab reinforcement and the sidewalls of the culvert and the upper slab reinforcement to the inside and then placing the concrete to construct the floor slab, and moving the outer sidewall formwork member removed from the completed culvert to combine again An external formwork device is installed, and the contracted internal formwork device is moved to an upper part of the completed bottom slab of a neighboring culvert to an expanded state, and the concrete is poured again to construct a continuous culvert.

이하, 첨부도면을 참조하여 본 발명에 따른 암거 제작용 이동식 철재 거푸집장치의 실시예 및 이를 이용한 암거의 촉진양생 시공방법의 실시예를 살펴봄으로써 본 발명의 구성을 설명한다.Hereinafter, with reference to the accompanying drawings will be described the configuration of the present invention by looking at an embodiment of a mobile steel formwork device for culvert production according to the present invention and an embodiment of the method for promoting curing culvert using the same.

우선, 콘크리트 암거를 제작하기 위한 본 발명의 이동식 거푸집장치는, 암거(300)의 외부면에 설치되는 외부 거푸집장치와, 상기 암거(300)의 내부면에 설치되는 내부 거푸집장치(60)로 구성된다.First, the mobile formwork of the present invention for producing a concrete culvert is composed of an external formwork device installed on the outer surface of the culvert 300, and an internal formwork device 60 installed on the inner surface of the culvert 300. do.

도 1에는 본 발명에 따른 이동식 거푸집장치(200)의 일실시예와 암거(300)를 분해 사시도로 도시한 개략도가 도시되어 있으며, 도 2에는 본 발명에 따른 이동식 거푸집장치(200)의 일실시예가 조립되어 있는 상태를 개략적으로 도시한 사시도가 도시되어 있다.1 is a schematic view showing an embodiment of the mobile formwork 200 and the culvert 300 according to the present invention in an exploded perspective view, Figure 2 one embodiment of the mobile formwork 200 according to the present invention A perspective view is shown schematically showing a state in which an example is assembled.

구체적으로, 상기 외부 거푸집장치는, 상기 암거(300)의 바닥슬래브(310)를 형성하기 위한 기초슬래브 거푸집부재(10)와, 상기 기초슬래브 거푸집부재(10)의 상면을 따라 이동이 가능하며 암거의 측벽부(320)를 형성하도록 암거(300)의 측벽부 외부에 설치되는 외부 측벽 거푸집부재(30)와, 기초슬래브 마감판부재(102)와, 암거(300)의 전후면을 형성하도록 암거(300)의 전후면에 설치되는 전후면 마감판부재(104)로 구성된다.Specifically, the external formwork device, the base slab formwork member 10 for forming the bottom slab 310 of the culvert 300 and the base slab formwork member 10 is movable along the upper surface of the culvert Culvert to form the outer sidewall formwork member 30, the foundation slab closing plate member 102, and the front and rear surfaces of the culvert 300, which are installed outside the sidewall portion of the culvert 300 to form the sidewall portion 320 of the culvert 300. It consists of a front and rear surface closing plate member 104 is installed on the front and rear surfaces of (300).

도 3a에는 본 발명의 이동식 거푸집장치(200)에 구비된 상기 기초슬래브 거푸집부재(10)의 일실시예에 대한 정면도와 부분상세도가 도시되어 있으며, 도 3b에는 상기 기초슬래브 거푸집부재(10)의 또 다른 실시예에 대한 부분상세도가 도시되어 있다.Figure 3a is a front view and a partial detailed view of an embodiment of the foundation slab formwork member 10 provided in the movable formwork device 200 of the present invention, Figure 3b is the foundation slab formwork member 10 A partial detail is shown for another embodiment of.

상기 기초슬래브 거푸집부재(10)는 암거의 바닥슬래브(310)의 길이방향 측면을 형성하도록 암거(300)의 길이 방향으로 연장되어 있으며, 암거(300)의 단면 크기에 맞추어 양측으로 한쌍이 구비된다. 상기 기초슬래브 거푸집부재(10)는 암거(300)의 바닥슬래브 콘크리트 측면과 접하는 평면부(12)와, 상기 평면부(12)의 배면에 설치되어 상기 평면부(12)의 강성을 보강하는 보강부(14)로 구성된다.The foundation slab formwork member 10 extends in the longitudinal direction of the culvert 300 to form a longitudinal side surface of the bottom slab 310 of the culvert, and is provided with a pair on both sides in accordance with the cross-sectional size of the culvert 300. . The base slab formwork member 10 is provided with a flat portion 12 in contact with the bottom slab concrete side of the culvert 300, and is provided on the rear surface of the flat portion 12 to reinforce the rigidity of the flat portion 12 It is comprised by the part 14.

후술하겠지만, 암거(300)의 측벽을 형성하는 외부 측벽 거푸집부재(30)는 암거의 길이방향으로 이동할 수 있도록 상기 기초슬래브 거푸집부재(10)의 상측에 설치되는데, 이를 위하여 기초슬래브 거푸집부재(10)의 보강부(14) 상면에는 외부 측벽 거푸집부재(30)의 이동을 위한 레일부(16)가 구비되어 있다.As will be described later, the outer side wall formwork member 30 forming the side wall of the culvert 300 is installed on the upper side of the base slab formwork member 10 to move in the longitudinal direction of the culvert, for this purpose the base slab formwork member 10 The upper side of the reinforcing portion 14 of the) is provided with a rail portion 16 for the movement of the outer side wall formwork member (30).

도 3a를 참조하여 상기 기초슬래브 거푸집부재(10)의 일실시예 구성을 살펴보면, 도 3a에 도시된 실시예에서 상기 기초슬래브 거푸집부재(10)는 2개의 H형강이 상하로 포개어져 구성되어 있는데, 상기 H형강의 플랜지가 상기 평면부(12)를 형성하며, H형강의 웨브 및 하부플랜지가 보강부(14)를 형성한다. 상기 2개의 H형강은 그 하부플랜지가 연결부재(15)와 볼트(13)로 결합되어 일체화된다. 상기 기초슬래브 거푸집부재(10)의 상부에 위치한 H형강의 웨브 상부에는 레일부(16)가 설치되는데, 도 3a에 도시된 실시예에서 상기 레일부(16)는 길이방향으로 연장되어 위치한 L형강으로 구성되어 있다. 그러나, 상기 레일부(16)는 반드시 L형강으로 한정되지 아니하며, 강봉 등으로 구성될 수도 있다. 또한, 도 3a에 도시된 실시예에서는 상기 기초슬래브 거푸집부재(10)가 2개의 H형강으로 이루어져 있으나, 사용되는 H형강의 갯수, 즉 기초슬래브 거푸집부재(10)의 두께는 암거의 바닥부(310)와 그 하부에 형성되는 버림 콘크리트의 두께에 따라 결정되는 것으로서, 암거의 바닥부(310) 두께가 더 두꺼운 경우에는 다수개의 H형강을 포개어서 기초슬래브 거푸집부재(10)를 형성할 수도 있으며, 반면에 암거의 바닥슬래브(310) 두께가 얇은 경우에는 하나의 H형강으로도 기초슬래브 거푸집부재(10)를 형성할 수 있다. 한편, 상기 기초슬래브 거푸집부재(10)는 도 3b에 도시된 바와 같이, 평면부(12)가 단순한 수직판재로 구성되고, 보강부(14)가 사각형 형강으로 구성되며, 상기 레일부(16)가 강봉으로 구성될 수도 있다.Looking at an embodiment of the foundation slab formwork member 10 with reference to Figure 3a, in the embodiment shown in Figure 3a the foundation slab formwork member 10 is composed of two H-shaped steel is stacked up and down The flange of the H-shaped steel forms the flat portion 12, and the web and the lower flange of the H-shaped steel form the reinforcing portion 14. The two H-shaped steels are integrated by combining their lower flanges with the connecting member 15 and the bolts 13. A rail portion 16 is installed on an upper portion of the web of the H-shaped steel positioned above the foundation slab formwork member 10. In the embodiment shown in FIG. 3A, the rail portion 16 extends in the longitudinal direction. It consists of. However, the rail portion 16 is not necessarily limited to the L-shaped steel, it may be composed of a steel bar or the like. In addition, in the embodiment shown in Figure 3a the base slab formwork member 10 is made of two H-shaped steel, the number of H-shaped steel used, that is, the thickness of the base slab formwork member 10 is the bottom portion of the culvert ( As determined by the thickness of the cast concrete formed at 310 and the lower portion thereof, when the thickness of the bottom portion 310 of the culvert is thicker, a plurality of H-beams may be stacked to form the foundation slab formwork member 10. On the other hand, when the thickness of the bottom slab 310 of the culvert is thin, the base slab formwork member 10 may be formed of one H-shaped steel. On the other hand, the foundation slab formwork member 10, as shown in Figure 3b, the planar portion 12 is composed of a simple vertical plate material, the reinforcement portion 14 is composed of a square-shaped steel, the rail portion 16 It may be composed of a steel rod.

또한, 암거(300)의 바닥슬래브(310)의 형성을 위한 콘크리트와 버림 콘크리트가 타설될 때, 굳지 않은 콘크리트의 압력에 의하여 나란하게 위치한 기초슬래브 거푸집부재(10)의 간격이 벌어질 수 있다. 이를 방지하기 위하여 양측의 기초슬래브 거푸집부재(10)에 횡방향(암거의 길이방향에 수직한 방향)으로 강선을 이용한 프리스트레싱을 가할 수 있는데, 강선을 설치하기 위하여 양측 기초슬래브 거푸집부재(10)의 사이에 강선이 통과할 파이프(18)를 가로질러 설치할 수 있다. 상기 파이프(18)는 첨부도면에는 미도시되었지만, 상기 기초슬래브 거푸집부재(10)와 볼트 등의 쐐기를 통해 결합됨으로써, 상기 기초슬래브 거푸집부재(10)의 사이에 거치될 수 있고, 다른 실시예로써, 접착제를 사용하여 상기 기초슬래브 거푸집부재(10)에 부착될 수도 있다. 상기 파이프(18)는 암거의 바닥슬래브(310) 콘크리트가 타설되면 콘크리트 속에 매설되며, 상술한 바와 같이 상기 기초슬래브 거푸집부재(10)의 사이에 거치된 파이프(18)를 통해 삽입된 강선은, 이후 1지간의 암거 시공이 완료되면 상기 파이프(18)로부터 빼내어 이웃하는 지간의 암거 시공에 재활용할 수 있게 된다.In addition, when the concrete and the discarded concrete for forming the bottom slab 310 of the culvert 300 is poured, the spacing of the base slab formwork member 10 positioned side by side by the pressure of the hardened concrete can be opened. In order to prevent this, prestressing using steel wire can be applied to both sides of the base slab formwork member 10 in the lateral direction (the direction perpendicular to the longitudinal direction of the culvert). It can be installed across the pipe 18 through which the steel wire will pass. Although not shown in the accompanying drawings, the pipe 18 may be mounted between the foundation slab formwork member 10 and the foundation slab formwork member 10 by being coupled to the foundation slab formwork member 10 through a wedge such as a bolt. As such, it may be attached to the foundation slab formwork member 10 using an adhesive. The pipe 18 is embedded in the concrete when the concrete slab bottom slab 310 is poured, the steel wire inserted through the pipe 18 mounted between the base slab formwork member 10, as described above, After completion of the culvert construction between the 1 area, the pipe 18 can be removed and recycled to the culvert construction between neighboring lands.

한편, 기초슬래브 거푸집부재(10)의 보강부(14)에는 외부 측벽 거푸집부재(30)가 볼트에 의하여 결합될 수 있도록 하는 볼트구멍(27)과, 상기 외부 측벽 거푸집부재(30)의 볼트 결합작업을 위한 블럭아웃부(28)가 형성된다(도 2 참조).Meanwhile, the reinforcing portion 14 of the foundation slab formwork member 10 includes a bolt hole 27 for allowing the outer sidewall formwork member 30 to be coupled by a bolt, and a bolt coupling of the outer sidewall formwork member 30. A block out 28 is formed for work (see FIG. 2).

도 4에는 기초슬래브 거푸집부재(10)에 의하여 만들어진 공간에 콘크리트가 타설되어 암거(300)의 바닥슬래브(310)를 제작하는 형상이 개략적으로 도시되어 있는데, 양측의 기초슬래브 거푸집부재(10)의 전후면에는 바닥슬래브(310)의 전후면을 이루는 기초슬래브 마감판부재(102)가 각각 장착된다. 우선 버림 콘크리트가 타설된다. 이후 바닥슬래브 콘크리트가 타설되는데, 바닥슬래브 콘크리트의 타설에 앞서 우선 버림 콘크리트의 상면에 바닥슬래브 보강철근(150)이 배근되며 강선이 통과되는 파이프(18)도 함께 배설된다.4 schematically shows a shape in which concrete is poured into a space made by the foundation slab formwork member 10 to fabricate the floor slab 310 of the culvert 300, wherein the foundation slab formwork members 10 of both sides are formed. On the front and rear surfaces, the base slab closing plate members 102 forming the front and rear surfaces of the bottom slab 310 are respectively mounted. First, discarded concrete is poured. Thereafter, the floor slab concrete is poured, prior to placing the floor slab concrete, the bottom slab reinforcement 150 is disposed on the upper surface of the discarded concrete, and the pipe 18 through which the steel wire passes is also disposed together.

상기 기초슬래브 마감판부재(102)는 바닥슬래브(310) 콘크리트 타설시 콘크리트에 의한 측압을 충분히 지지할 수 있어야 하는데, 이를 위해서 도 4 및 도 5에 도시된 바와 같이, 기초슬래브 마감판부재(102)의 배면에 ㅁ자형강(108), ㄱ자형강(106)등을 보강할 수도 있다.The foundation slab closing plate member 102 should be able to fully support the side pressure due to the concrete when placing the floor slab 310 concrete, for this purpose, as shown in Figure 4 and 5, the foundation slab closing plate member 102 On the back of the) may be reinforced K-shaped steel 108, L-shaped steel 106, and the like.

상기 기초슬래브 마감판부재(102)는 예를 들면 볼트 등과 같은 체결부재(도시되지 않음)에 의하여 양측의 기초슬래브 거푸집부재(10)와 착탈가능하게 결합된다.The foundation slab closing plate member 102 is detachably coupled to the foundation slab formwork member 10 on both sides by a fastening member (not shown), such as a bolt.

다음으로는 암거의 측벽부(320)를 형성하도록 암거(300)의 측벽부 콘크리트 외부에 설치되는 외부 측벽 거푸집부재(30)의 구성에 대하여 설명한다.Next, the configuration of the outer sidewall formwork member 30 installed outside the sidewall portion concrete of the culvert 300 to form the sidewall portion 320 of the culvert will be described.

도 6에는 상기 외부 측벽 거푸집부재(30)의 일실시예의 정면도가 도시되어 있다. 외부 측벽 거푸집부재(30)는 암거(300)의 측벽부 콘크리트와 접하는 면이 평면으로 이루어진 철재판으로 구성되는데, 콘크리트와 접하는 면의 배면에는 보강을 위하여 형강이 격자형으로 배열될 수 있다.6 shows a front view of one embodiment of the outer sidewall formwork member 30. The outer side wall formwork member 30 is composed of a steel plate made of a flat surface of the side wall portion of the culvert 300 in contact with the concrete, the back surface of the surface in contact with the concrete may be arranged in a grid for reinforcement.

본 발명에 있어서, 상기 외부 측벽 거푸집부재(30)는, 콘크리트 타설시에는 상기 기초슬래브 거푸집부재(10)에 고정설치되지만, 콘크리트 타설을 마치고 탈거된 후에는 상기 기초슬래브 거푸집부재(10)로부터 분리되어 상기 기초슬래브 거푸집부재(10)의 레일부(16)를 따라 전후 방향으로 이동이 가능하다. 콘크리트 타설을 위해서는 상기 외부 측벽 거푸집부재(30)는 직립한 형태로 볼트 등과 같은 착탈가능한 체결수단에 의하여 상기 기초슬래브 거푸집부재(10)에 체결되어 고정된다.In the present invention, the outer side wall formwork member 30 is fixed to the foundation slab formwork member 10 during concrete placement, but is separated from the foundation slab formwork member 10 after it is removed after finishing the concrete placement. It is possible to move in the front-rear direction along the rail portion 16 of the foundation slab formwork member 10. For concrete pouring, the outer sidewall formwork member 30 is fastened and fixed to the foundation slab formwork member 10 by detachable fastening means such as bolts in an upright form.

한편, 콘크리트의 타설이 완료된 후 외부 측벽 거푸집부재(30)는 기초슬래브 거푸집부재(10)로부터 분리되어 암거(300)로부터 탈거되는데, 탈거된 외부 측벽 거푸집부재(30)는 또 다른 암거(300)의 연속 제작을 위하여 전방 또는 후방으로 전진하여 다시 기초슬래브 거푸집부재(10)와 재결합된다. 이때, 탈거된 외부 측벽 거푸집부재(30)의 전, 후방 전진을 위하여 상기 외부 측벽 거푸집부재(30)에는 상기 기초슬래브 거푸집부재(10)에 형성된 레일부(16)를 따라 구동되는 구동부(32)가 구비되어 있다.On the other hand, after the casting of the concrete is completed, the outer sidewall formwork member 30 is separated from the base slab formwork member 10 and detached from the culvert 300. The removed outer sidewall formwork member 30 is another culvert 300. Advancing forward or backward for the continuous fabrication of the re-combination with the foundation slab formwork member 10 again. At this time, the drive unit 32 is driven along the rail portion 16 formed in the foundation slab formwork member 10 to the outer sidewall formwork member 30 to move forward and backward of the removed outer sidewall formwork member 30. Is provided.

도 7 내지 도 9에는 상기 외부 측벽 거푸집부재(30)에 구비된 상기 구동부(32)의 일실시예 구조가 상세히 개시되어 있는데, 도 7은 상기 구동부(32)가 구동불능상태에 있을 때의 정면도이고, 도 8은 상기 구동부(32)가 구동가능상태에 있을 때의 측면도이며, 도 9는 상기 구동부(32)의 평면도이다.7 to 9 illustrate one embodiment structure of the driving unit 32 provided in the outer side wall formwork member 30, and FIG. 7 is a front view when the driving unit 32 is in a non-driven state. 8 is a side view when the drive unit 32 is in a driveable state, and FIG. 9 is a plan view of the drive unit 32.

도 7 내지 도 9에 도시된 구동부(32)의 실시예에서, 상기 구동부(32)는, 상기 외부 측벽 거푸집부재(30)의 외부 측면에 고정설치된 구동부하우징(44)과, 상기 구동부하우징(44)의 내부에서 상하로 승하강하는 구동체(48)와, 상기 구동체(48)의 하측에 구비된 구동바퀴(51)로 구성되어 있다. 상기 구동부(32)는 상기 외부 측벽 거푸집부재(30)가 기초슬래브 거푸집부재(10)와 체결되어 고정되어 있는 경우 도 7에서와 같이 상기 구동체(48)가 상기 구동부하우징(44) 내부에서 상승한 위치에 있게 되어 구동바퀴(51)가 들려 있어 구동불능상태가 되며, 상기 외부 측벽 거푸집부재(30)가 기초슬래브 거푸집부재(10)로부터 분리되어 전후로 이동되어야 하는 경우에는 도 8에서와 같이 구동체(48)가 상기 구동부하우징(44) 내부에서 구동위치로 하강하게 되어 상기 구동바퀴(51)가 기초슬래브 거푸집부재(10)의 레일부(16) 위에 놓여 구동가능상태에 있게 된다.In the embodiment of the drive unit 32 shown in FIGS. 7 to 9, the drive unit 32 includes a drive unit housing 44 fixed to an outer side of the outer side wall formwork member 30, and the drive unit housing 44. A driving body 48 that moves up and down inside and outside the center) and a driving wheel 51 provided below the driving body 48. When the outer side wall formwork member 30 is fastened and fixed to the base slab formwork member 10, the driving part 32 is formed by raising the driving body 48 inside the driving part housing 44 as shown in FIG. 7. In the case where the driving wheel 51 is lifted up and becomes impossible to drive, the outer side wall formwork member 30 is to be separated from the base slab formwork member 10 and moved back and forth. 48 is lowered into the drive position inside the drive unit housing 44 such that the drive wheel 51 is placed on the rail portion 16 of the foundation slab formwork member 10 and is in a driveable state.

이와 같이 구동체(48)가 상기 구동부하우징(44)의 내부에서 구동불능상태 또는 구동가능상태를 유지할 수 있도록, 상기 구동체(48)와 상기 구동부하우징(44)에 각각 볼트구멍을 형성하고 비구동상태 또는 구동가능상태일 때의 해당 볼트구멍에 각각 고정볼트(46)를 끼워 넣게 된다.As such, the bolt holes are formed in the driving body 48 and the driving unit housing 44 so that the driving body 48 can maintain a non-driven state or a driving state within the driving unit housing 44. The fixing bolts 46 are inserted into the corresponding bolt holes in the driving state or the driving state.

본 발명에서는 이와 같이 외부 측벽 거푸집부재(30)가 기초슬래브 거푸집부재(10)를 따라 전후로 이동할 수 있으므로, 1지간의 암거 시공이 완료되면 용이하게 외부 측벽 거푸집부재(30)를 해체하여 이동시켜 조립하므로써 다시 연속되는 지간의 암거를 시공할 수 있는 준비를 할 수 있으므로, 암거의 연속적인 시공이 가능하며 암거의 시공에 소요되는 공기를 단축시킬 수 있게 된다.In the present invention, since the outer sidewall formwork member 30 can be moved back and forth along the foundation slab formwork member 10, the outer sidewall formwork member 30 is easily dismantled and assembled when the culling construction of one paper is completed. By doing so, it is possible to prepare for the construction of the culvert between successive sections again, so that the construction of the culvert can be continued and the air required for the construction of the culvert can be shortened.

또한, 상기 외부 측벽 거푸집부재(30)는 상측의 철재판 일부가 하측의 철재판과 볼팅결합되어 착탈이 가능하도록 되어 있는데, 이는 제작하고자 하는 암거의 규격, 특히 높이가 다양할 경우 상측의 철재판 일부, 즉 조절부재(33)를 적절히 착탈함으로써 암거의 규격에 맞는 새로운 외부 측벽 거푸집부재(30)를 구비할 필요성을 불식시킬 수 있는 것이다.In addition, the outer side wall formwork member 30 is a part of the upper steel plate is bolted and coupled to the lower side of the iron plate is to be removable, this is the standard of the culvert to be manufactured, in particular the height of the upper steel plate By appropriately detaching a part, ie, the adjusting member 33, it is possible to eliminate the need to have a new outer side wall formwork member 30 that meets the specifications of the culvert.

본 발명에 있어서, 상기 외부 측벽 거푸집부재(30)에는 암거(300)의 증기촉진양생을 위한 증기를 공급하기 위하여 증기공급관(50)이 그 외부에 설치된다. 상기 증기공급관(50)에는 다수개의 증기분출구(도시되지 않음)가 형성되어 있어, 외부의 보일러(도시되지 않음)로부터 증기공급관(50)을 통하여 공급되는 증기가 상기 증기분출구를 통하여 분출하게 된다. 증기분출구를 통하여 분출된 증기는 상승하기 때문에, 증기공급관(50)은 도 6에 도시된 바와 같이 외부 측벽 거푸집부재(30)의 하부에 암거(300)의 길이방향으로 위치하는 것이 바람직하다. 그러나, 상기 증기공급관(50)의 갯수와 설치위치는 반드시 이에 한정되지 아니하므로, 필요에 따라서는 다수개의 증기공급관(50)이 외부 측벽 거푸집부재(30)의 임의의 위치에 배열되어도 무방하다. 이와 같이, 본 발명에서는 외부 측벽 거푸집부재(30)의 외부에 증기를 공급할 수 있는 증기공급관(50)을 구비하고 있으므로, 후술하는 바와 같이, 증기공급이 용이하므로 타설된 콘크리트를 증기에 의하여 촉진양생시킬 수 있으며, 그에 따라 암거 콘크리트의 양생에 필요한 시간을 단축시켜 전체적인 암거 시공에 필요한 공기를 현저하게 단축시킬 수 있게 된다.In the present invention, the outer side wall formwork member 30 is provided with a steam supply pipe 50 to the outside for supplying steam for the steam promoting curing of the culvert 300. The steam supply pipe 50 is formed with a plurality of steam outlets (not shown), the steam supplied through the steam supply pipe 50 from an external boiler (not shown) is ejected through the steam outlet. Since the steam ejected through the steam outlet rises, the steam supply pipe 50 is preferably located in the longitudinal direction of the culvert 300 in the lower portion of the outer side wall formwork member 30, as shown in FIG. However, since the number and installation position of the steam supply pipe 50 is not necessarily limited thereto, a plurality of steam supply pipe 50 may be arranged at any position of the outer side wall formwork member 30 as necessary. As described above, since the present invention includes a steam supply pipe 50 capable of supplying steam to the outside of the outer side wall formwork member 30, as described later, steam is easily supplied to facilitate the curing of the poured concrete by steam. Therefore, it is possible to shorten the time required for curing the culvert concrete, thereby significantly reducing the air required for the construction of the culvert.

본 발명에 있어서, 상기 외부 측벽 거푸집부재(30)의 상부에는 안전난간(57)이 구비된 작업자 보행용 작업대(38)가 접철식으로 설치되어 있다. 도 10에는 상기 작업대(38)의 정면도가 도시되어 있는데, 본 발명에 구비된 작업자 보행용 작업대(38)는 외부 측벽 거푸집부재(30)가 기초슬래브 거푸집부재(10)에 고정되어 콘크리트 타설 위치에 있을 경우에는 도 10에서와 같이 펼쳐져서 보행가능상태가 되나, 콘크리트의 타설이 완료되어 외부 측벽 거푸집부재(30)가 기초슬래브 거푸집부재(10)로부터 분리되어 탈거된 상태에서는 도 15에 도시된 바와 같이 접혀져서 보행불능상태가 된다.In the present invention, on the upper side of the side wall formwork member 30, a worker walking work platform 38 having a safety handrail 57 is provided in a folding manner. 10 is a front view of the workbench 38, the worker walking workbench 38 provided in the present invention is the outer side wall formwork member 30 is fixed to the foundation slab formwork member 10 in the concrete pouring position If present, as shown in FIG. 10, the state becomes a walkable state, but when the casting of the concrete is completed and the outer sidewall formwork member 30 is separated from the foundation slab formwork member 10 and removed, as shown in FIG. 15. Folded together, they become unable to walk.

도 2 및 도 10을 참조하여 상기 작업대(38)의 일실시예 구조를 살펴보면, 상기 작업대(38)는 작업자가 보행할 수 있는 보행판(58)과, 상기 보행판(58)의 외측에 힌지연결되어 접철가능하게 설치된 안전난간(57)과, 상기 보행판(58)의 하부에서 일측이 힌지연결(52)되어 있는 지지대(54)로 구성되어 있다. 상기 지지대(54)의 타측은 외부 측벽 거푸집부재(30)의 측면에 걸쳐진다.Referring to FIGS. 2 and 10, the structure of the work bench 38 will be described. The work bench 38 may include a walking board 58 which can be walked by a worker, and a hinge outside the walking board 58. It is composed of a safety rail 57 connected to be folded and installed, and a support 54 having one side hinged at the lower side of the walking board 58. The other side of the support 54 spans the side of the outer sidewall formwork member 30.

보행가능상태에서는 상기 안전난간(57)이 보행판(58)의 일측에 수직하게 세워지고 지지대(54)의 일측이 외부 측벽 거푸집부재(30)의 측면에 걸쳐지므로써 보행판(58)의 하부를 지지하게 된다. 보행불능상태에서는 상기 안전난간(57)이 회동하여 접철되며 지지대(54)의 일측을 외부 측벽 거푸집부재(30)의 측면에 걸쳐지지 않게 하여 보행판(58)을 더이상 지지하지 않게 하므로써 도 15에서와 같이 보행판이 외부 측벽 거푸집부재(30)와 나란한 위치로 내려오게 된다. 이와 같이, 본 발명에서는 콘크리트 타설시에는 보행가능상태가 되는 작업대(38)를 보행가능상태로 만들어 작업자가 안전하게 보행할 수 있도록 하므로써 콘크리트 타설 작업시 작업자가 용이하게 작업할 수 있도록 하면서도, 콘크리트 타설이 완료되어 거푸집장치를 이동시킬 때는 작업대(38)가 접철상태로 되도록 구성하였으므로, 거푸집장치의 이동에 방해가 되지 않도록 구성하였다.In the walkable state, the safety rail 57 is vertically erected to one side of the walking board 58, and one side of the support 54 extends across the side of the outer sidewall form member 30, thereby lowering the walking board 58. Will be supported. In the improper state of walking, the safety handrail 57 is pivoted and pivoted so that one side of the support 54 does not span the side of the outer side wall form member 30 so that the walking plate 58 is no longer supported. As shown, the walking board is lowered to a position parallel to the outer side wall formwork member 30. As described above, in the present invention, while making the worktable 38, which becomes a walkable state at the time of concrete pouring, to allow the worker to walk safely, the worker can easily work during the concrete placing work, while the concrete placing is When the formwork is completed and moved the worktable 38 is configured to be in a folded state, it was configured so as not to interfere with the movement of the formwork.

다음으로는 본 발명에 따른 이동식 거푸집장치(200)에 있어서, 상기 암거(300)의 내부면을 형성하는 내부 거푸집장치(60)에 대하여 설명한다. 도 11에는 본 발명에 구비된 내부 거푸집장치(60)의 일실시예 형상이 정면도로 도시되어 있다.Next, in the movable formwork apparatus 200 according to the present invention, an internal formwork apparatus 60 for forming the inner surface of the culvert 300 will be described. 11 is a front view of an embodiment of the formwork device 60 provided in the present invention.

본 발명에 있어서, 내부 거푸집장치(60)는 상기 외부 측벽 거푸집부재(30)와 소정 간격 이격되어 설치되므로써 암거(300)의 내부면을 형성하게 되는데, 구체적으로는 도 11에 도시된 바와 같이, 암거(300)의 측벽 콘크리트 내면과 마주하게 되는 측벽판부재(66)와, 암거(300)의 상부슬래브 콘크리트의 하부면과 마주하게 되는 상부슬래브판부재(64)를 구비하고 있다.In the present invention, the inner formwork device 60 is formed to be spaced apart from the outer sidewall formwork member 30 by a predetermined interval to form the inner surface of the culvert 300, specifically, as shown in FIG. A side wall plate member 66 facing the inner surface of the side wall concrete of the culvert 300 and an upper slab plate member 64 facing the lower surface of the upper slab concrete of the culvert 300 are provided.

본 발명에 있어서, 상기 내부 거푸집장치(60)는 콘크리트 타설시 확장되고, 타설이 완료시에는 수축하여 암거의 전후방향으로 이동할 수 있는 상태가 된다. 이를 위하여 내부 거푸집장치(60)에는 하부에 구동장치(62)가 구비된 베이스(80)가 구비되는데, 상기 베이스(80)에는 신축되어 측벽판부재(66)를 좌우로 움직이며, 상부슬래브판부재(64)를 상하로 움직여서 내부 거푸집장치(60)를 확장/수축시킬 수 있는 신축수단(70,71,72)이 구비된다.In the present invention, the internal formwork device 60 is expanded when concrete is poured, and when the casting is completed, it is in a state capable of moving in the front and rear direction of the culvert. To this end, the internal formwork device 60 is provided with a base 80 provided with a driving device 62 at the bottom, the base 80 is stretched to move the side wall plate member 66 to the left and right, the upper slab plate Stretching means (70, 71, 72) is provided to move the member 64 up and down to expand / contract the internal formwork device (60).

도 11에 도시된 실시예를 통하여 상기 베이스(80)와 신축수단(70,71,72)의 구조를 살펴보면, 베이스(80)의 하부에는 베이스(80)를 승하강시킬 수 있는 승하강장치(84)가 구비된다. 또한, 상기 베이스(80)의 하부에는 베이스(80)가 하강하였을 때, 베이스(80)가 암거(300)의 전후방향으로 이동할 수 있도록 하는 구동장치(62)가 구비된다.Looking at the structure of the base 80 and the expansion means (70, 71, 72) through the embodiment shown in Figure 11, the lower portion of the base 80 to raise and lower the base 80 ( 84). In addition, the lower portion of the base 80 is provided with a driving device 62 to allow the base 80 to move in the front and rear direction of the culvert 300 when the base 80 is lowered.

상기 베이스(80)의 상부에는 상기 상부슬래브판부재(64)를 지지하는 지지기둥(86)이 설치되어 있다. 도 10에 도시된 실시예에는 상기 지지기둥(86)과 상기 베이스(80)와 상기 상부슬래브판부재(64)가 일체로 연결되어 있어, 상기 승하강장치(84)에 의하여 베이스(80)가 상승하게 되면 상부슬래브판부재(64)도 상승하여 콘크리트 타설위치에 놓이게 되며, 상기 승하강장치(84)에 의하여 베이스(80)가 하강하게 되면 상부슬래브판부재(64)도 하강하게 되어 상부슬래브의 콘크리트면으로부터 떨어져 수축하는 위치에 있게 된다. 한편, 베이스(80)가 상승한 위치에서는 상기 구동장치(62)도 암거(300)의 바닥슬래브로부터 들어올려지게 되고, 베이스(80)가 하강한 위치에 있게 되면 상기 구동장치(62)가 암거(300)의 바닥슬래브 상부면 위에 놓이게 되어 베이스(80)가 전후로 이동할 수 있게 된다. 상기 구동장치(62)의 원활한 구동을 위하여 바닥슬래브의 상부면에는 레일(312)을 설치할 수 있는데, 상기 레일(312)은 도 11에 도시된 바와 같이 ㄱ자형강이나 강봉으로 구성될 수 있다. 그러나 레일(312)이 반드시 이에 한정되는 것은 아니다.A support pillar 86 for supporting the upper slab plate member 64 is installed at an upper portion of the base 80. In the embodiment shown in FIG. 10, the support pillar 86, the base 80, and the upper slab plate member 64 are integrally connected, and the base 80 is moved by the elevating device 84. Ascending, the upper slab plate member 64 is also raised to be placed in the concrete placing position, and when the base 80 is lowered by the elevating device 84, the upper slab plate member 64 is also lowered to the upper slab It is in a position to contract away from the concrete surface of the. On the other hand, in the position where the base 80 is raised, the drive device 62 is also lifted from the bottom slab of the culvert 300, and when the base 80 is in the lowered position, the drive device 62 is culverted ( The floor slab 300 is placed on the upper surface of the base 80 so that it can move back and forth. A rail 312 may be installed on an upper surface of the floor slab for smooth driving of the driving device 62. The rail 312 may be formed of an L-shaped steel or a steel bar as shown in FIG. However, the rail 312 is not necessarily limited thereto.

한편, 상기 베이스(80)에 설치된 지지기둥(86)에는 양측의 측벽판부재(66)를 좌우로 움직일 수 있는 신축수단(70)이 각각 설치된다. 도 11에 도시된 바와 같이, 양측의 측벽판부재(66)의 배면에는 신축수단(70)이 설치되어 있어 상기 신축수단(70)의 신축에 의하여 양측의 측벽판부재(66)의 상측이 좌우로 움직이게 된다. 상기 양측의 측벽판부재(66)를 지지하여 신축하는 신축수단(70)의 일례로서는, 유압을 이용한 유압실린더를 이용할 수도 있으나, 단순한 구조로서는 도 15에 도시된 바와 같이 측벽판부재(66)와 연결된 단부는 힌지로 구성되어 있고, 타단부는 자유단부로 구성되어 상기 지지기둥(86)에 걸쳐지는 지지봉의 형태로 구성될 수도 있다. 이러한 지지봉은 측벽판부재(66)의 확장상태에서는 단부가 지지기둥(86)에 걸쳐져 있게 되고, 수축상태에서는 단부가 지지기둥(86)에 걸쳐지지 않게 되어 측벽판부재(66)의 수축이 가능하도록 한다.On the other hand, the support column 86 installed on the base 80 is provided with elastic means 70 which can move the side wall plate member 66 on both sides from side to side. As shown in FIG. 11, expansion means 70 is provided on the rear surface of the side wall plate member 66 on both sides, so that the upper side of the side wall plate member 66 on both sides is extended by the expansion and contraction of the expansion means 70. Will move to. As an example of the expansion and contraction means 70 for supporting and stretching the side wall plate members 66 on both sides, a hydraulic cylinder using hydraulic pressure may be used, but as a simple structure, the side wall plate members 66 and The connected end is composed of a hinge, and the other end may be configured in the form of a support rod that is configured as a free end and spans the support pillar 86. The supporting rod has an end portion extending over the support pillar 86 in the expanded state of the side wall plate member 66, and in the contracted state, the end portion does not span the support pillar 86, so that the side wall plate member 66 can be contracted. Do it.

일반적으로 박스형 암거(300)의 각 모서리에는 헌치부가 형성되는데, 헌치부가 형성된 암거(300)의 경우, 측벽판부재(66)의 하단부에는 헌치부 형성을 위한 헌치부판부재(68)를 설치한다. 상기 헌치부판부재(68)는 일측이 상기 측벽판부재(66)에 힌지연결되는데, 상기 헌치부판부재(68)의 배면에도 헌지부판부재(68)를 회동시킬 수 있도록 신축수단(72)이 설치된다. 상기 신축수단(72) 역시 유압실린더 형식으로 구성될 수도 있으나, 도면에 도시된 바와 같이 양측에 내부에 나사부가 형성되어 있는 커플링을 구비하여, 커플링을 회전시키므로써 커플링에 끼워진 봉부재의 길이가 신축되는 구조로 구성될 수도 있다.In general, each corner of the box-shaped culvert 300 is formed with a haunch, in the case of the culvert 300 having the haunch, the lower end of the side wall plate member 66 has a haunch plate member 68 for forming a haunch portion. Install. One side of the haunting plate member 68 is hinged to the side wall plate member 66, the stretching means 72 to rotate the haunch plate member 68 on the back of the haunch plate member 68 ) Is installed. The expansion means 72 may also be configured as a hydraulic cylinder type, but as shown in the figure has a coupling with a thread formed therein on both sides, by rotating the coupling of the rod member fitted to the coupling It may be composed of a structure that is stretched in length.

도 14에 도시된 실시예에서는, 상기 측벽판부재(66)의 신축수단(70)은 측벽판부재(66)의 상부에만 설치되어 있으며, 측벽판부재(66)의 하부에는 측벽판부재(66)를 서로 연결하되 역시 신축이 가능한 또 다른 신축수단(71)이 설치되어 있다. 상기 신축수단(71) 역시 양측에 내부에 나사부가 형성되어 있는 커플링을 구비하여, 커플링을 회전시키므로써 커플링에 끼워진 봉부재의 길이가 신축되는 구조로 구성될 수도 있다.In the embodiment shown in FIG. 14, the expansion and contraction means 70 of the side wall plate member 66 is provided only on the upper side of the side wall plate member 66, and the side wall plate member 66 is disposed below the side wall plate member 66. ) Is connected to each other, but also has another expansion means 71 that can be stretched. The expansion means 71 may also have a coupling in which threaded portions are formed therein at both sides thereof, such that the length of the rod member fitted to the coupling is stretched by rotating the coupling.

또한, 상기 측벽판부재(66)의 상측 일부는 상술한 외측 측벽 거푸집부재(30)의 조절부재(33)와 동일한 역할을 하도록 조절부재(63)로 형성되는데, 이는 제작하고자 하는 암거의 규격, 특히 높이가 다양할 경우 새로운 내부 거푸집장치(60)를 구비할 필요 없이, 상기 측벽판부재(66)의 일부로써, 볼팅결합되어 있는 조절부재(33)를 적절히 착탈함으로써 높이가 서로 다른 암거의 제작시 융통성 있게 내측 거푸집장치(60)를 운용할 수 있는 것이다.In addition, the upper portion of the side wall plate member 66 is formed of the adjustment member 63 to play the same role as the control member 33 of the outer side wall formwork member 30 described above, which is the standard of the culvert to be manufactured, Particularly, if the height varies, there is no need to provide a new internal formwork device 60, and as a part of the side wall plate member 66, by appropriately detaching the adjusting member 33 is bolted coupled to manufacture the culverts of different heights When the inner formwork device 60 can be flexibly operated.

이러한 내부 거푸집장치(60)의 거동을 살펴보면, 암거(300)를 제작하기 위한 콘크리트 타설위치에서는, 상기 측벽판부재(66)의 배면에 설치된 신축수단(70, 71) 및 헌치부판부재(68)의 배면에 설치된 신축수단(72)이 각각 신장하여 상기 측벽판부재(66)와 헌치부판부재(68)가 외부를 향하여 이동한다. 그와 동시에 베이스(80)도 상승상태가 되어 상기 상부슬래브판부재(64)도 상승하게 된다. 이때 베이스(80) 하부의 구동장치(62)는 하부슬래브로부터 들어올려진 상태가 된다. 본 명세서에서는 이러한 내부 거푸집장치(60)의 상태를 "확장상태"라고 한다.Looking at the behavior of the internal formwork device 60, in the concrete placing position for manufacturing the culvert 300, the expansion means (70, 71) and the haunch plate member 68 installed on the back of the side wall plate member 66 Stretching means 72 installed on the back of the elongated respectively, the side wall plate member 66 and the haunting plate member 68 is moved toward the outside. At the same time, the base 80 is also raised, and the upper slab plate member 64 is also raised. At this time, the driving device 62 below the base 80 is in a lifted state from the lower slab. In this specification, the state of such an internal formwork device 60 is referred to as an "expanded state".

콘크리트의 타설이 완료되어 내부 거푸집장치(60)를 암거(300)로부터 탈거할 경우에는, 상기 신축수단(70, 71, 72)이 수축하여 상기 측면판부재(66)와 헌치부판부재(68)가 내부를 향하여 이동하게 되어 암거(300)의 내부면으로부터 떨어지게 된다. 그와 동시에 베이스(80)도 하강하게 되어 상부슬래브판부재(64)도 암거(300)의 상부슬래브로부터 떨어지게 된다. 이때 베이스(80)가 하강됨으로써 구동장치(62)가 바닥슬래브(310) 위에(구체적으로는 레일 위에) 놓이게 되어 내부 거푸집장치(60)가 전후로 이동할 수 있는 상태가 된다. 본 명세서에서는 이러한 내부 거푸집장치(60)의 상태를 "수축상태"라고 한다. 도 14 및 도 15에는 본 발명에 따른 이동식 거푸집장치(200)의 설치상태가 도시되어 있는데, 도 14에 도시된 내부 거푸집장치(60)의 상태는 확장상태이고 도 15에 도시된 내부 거푸집장치(60)의 상태는 수축상태이다.When the casting of the concrete is completed and the internal formwork device 60 is removed from the culvert 300, the expansion means 70, 71, and 72 contract and the side plate member 66 and the haunch plate member 68. ) Is moved inward to fall from the inner surface of the culvert 300. At the same time, the base 80 is also lowered so that the upper slab plate member 64 is also separated from the upper slab of the culvert 300. At this time, as the base 80 is lowered, the driving device 62 is placed on the bottom slab 310 (specifically, on the rail), and the internal formwork device 60 can move back and forth. In this specification, the state of such an internal formwork device 60 is referred to as "shrinkage state". 14 and 15 show an installation state of the mobile formwork apparatus 200 according to the present invention, the state of the internal formwork device 60 shown in FIG. 14 is an expanded state and the internal formwork device shown in FIG. 15 ( 60) is a contraction state.

도 12에는 암거(300)의 전면과 후면을 형성하기 위한 전후면 마감판부재(104)가 도시되어 있다. 전후면 마감판부재(104)는 철재판형 부재로 이루어지는데, 도 12에 도시된 바와 같이 보강을 위하여 배면에는 ㅁ자형강(108)과 ㄱ자형강(106)이 격자형상으로 배열될 수 있다.12 shows the front and rear closing plate member 104 for forming the front and rear of the culvert 300. The front and rear closing plate member 104 is made of a steel plate-like member, for the reinforcement as shown in Figure 12, the K-shaped steel 108 and the L-shaped steel 106 may be arranged in a grid shape.

다음으로는 첨부도면을 참조하여 본 발명에 따른 이동식 거푸집장치(200)의 설치 및 분해, 그리고 이를 이용한 암거의 증기촉진양생 연속시공방법을 설명한다.Next, with reference to the accompanying drawings will be described the installation and disassembly of the mobile formwork apparatus 200 according to the present invention, and the method for continuous steam-promoting curing of the culvert using the same.

우선, 암거(300)를 시공하기에 앞서 작업노선을 선정하고 양생시설 및 기계 기구를 배치하고 후속하여 중장비를 이용하여 작업노선을 따라 터파기를 하여, 암거(300) 시공 준비를 한다. 시공준비가 완료되면 도 4에 도시된 바와 같이, 기초슬래브 거푸집부재(10)를 설치하고 기초슬래브 거푸집부재(10)의 전후에 기초슬래브 마감판부재(102)를 각각 결합한다. 암거(300)의 바닥슬래브를 위한 콘크리트를 타설하기에 앞서 바닥슬래브 보강철근(150)을 배근하고 파이프관(18)을 설치한 후, 파이프관(18) 내에 강선을 삽입하여 긴장한다. 강선의 긴장시 양측의 기초슬래브 거푸집부재(10)가 긴장력에 의하여 서로 근접하는 것을 방지하기 위하여 기초슬래브 거푸집부재(10)의 상부에 임시로 지지대(도시되지 않음)를 가로질러 설치하는 것도 바람직하다. 기초슬래브 거푸집부재(10)와 기초슬래브 마감판부재(102)의 설치가 완료되면 콘크리트를 타설하여 암거(300)의 바닥슬래브(310)를 형성한다.First, prior to constructing the culvert 300, the work route is selected, the curing facility and the mechanical apparatus are arranged, and subsequently, the trench is drilled along the work route using heavy equipment to prepare for the construction of the culvert 300. When the construction preparation is completed, as shown in FIG. 4, the foundation slab formwork member 10 is installed and the foundation slab closing plate members 102 are coupled to each other before and after the foundation slab formwork member 10. Before placing concrete for the floor slab of the culvert 300, the bottom slab reinforcement 150 is placed and pipe pipe 18 is installed, and then a steel wire is inserted into the pipe pipe 18 to relax. In order to prevent the base slab formwork members 10 on both sides from coming close to each other by a tension force when the steel wire is tensioned, it is also preferable to temporarily install a support (not shown) on the upper part of the base slab formwork member 10. . When the installation of the foundation slab formwork member 10 and the foundation slab closing plate member 102 is completed, the concrete is poured to form the floor slab 310 of the culvert 300.

암거(300)의 바닥슬래브(310)가 일정 정도 양생되면 도 13에 도시된 바와 같이, 암거(300)의 측벽 및 상부슬래브 보강을 위한 보강철근(152)을 배근한다. 보강철근(152)의 배근이 완료되면 보강철근(152)의 외부로는 외부 거푸집장치를 설치하고 내부로는 내부 거푸집장치(60)를 설치한다.When the bottom slab 310 of the culvert 300 is cured to a certain degree, as shown in FIG. 13, the reinforcing bar 152 for reinforcing the sidewall and the upper slab of the culvert 300 is reinforced. When the reinforcement of the reinforcing bar 152 is completed, the external formwork device is installed to the outside of the reinforcing bar 152 and the internal formwork device 60 is installed to the inside.

구체적으로, 기초슬래브 거푸집부재(10)의 상부에 외부 측벽 거푸집부재(30)를 수직하게 설치하고 외부 측벽 거푸집부재(30)의 하단부와 기초슬래브 거푸집부재(10)의 상부를 볼트에 의하여 체결하여 외부 측벽 거푸집부재(30)를 고정시킨다.Specifically, the outer side wall formwork member 30 is vertically installed on the upper portion of the foundation slab formwork member 10, and the lower end of the outer side wall formwork member 30 and the upper portion of the foundation slab formwork member 10 are fastened by bolts. The outer side wall formwork member 30 is fixed.

내부 거푸집장치(60)는, 도 14에 도시된 바와 같이, 상기 측벽판부재(66)의 배면에 설치된 신축장치(70, 71) 및 헌치부판부재(68)의 배면에 설치된 신축장치(72)를 각각 신장하여 상기 측벽판부재(66)와 헌지부판부재(68)가 외부를 향하여 이동함과 동시에 베이스(80)를 상승시켜 상기 상부슬래브판부재(64)도 상승 위치에 있게 하여 내부 거푸집장치(60)를 확장상태로 만든다. 이때 베이스(80) 하부의 구동장치(62)는 바닥슬래브(310)로부터 들어올려진 상태가 된다. 작업자의 편의를 위하여 외부 측벽 거푸집부재(30)의 상부에 설치된 작업대(38)는 보행가능상태가 된다. 암거(300)의 전후면으로는 전후면 마감판부재(104)가 설치된다.As shown in FIG. 14, the internal formwork device 60 includes an expansion device 70 provided on the rear surface of the side wall plate member 66 and an expansion device 72 provided on the rear surface of the haunting plate member 68. E) to extend the side wall plate member 66 and the hunt plate member 68 toward the outside, and at the same time raise the base 80 so that the upper slab plate member 64 is also in a raised position. The formwork device 60 is brought into an expanded state. At this time, the driving device 62 below the base 80 is in a lifted state from the bottom slab 310. For the convenience of the operator, the work table 38 installed on the upper sidewall formwork member 30 becomes a walkable state. Front and rear surface closing plate member 104 is installed on the front and rear surfaces of the culvert 300.

이와 같이, 외부 거푸집장치와 내부 거푸집장치(60)의 설치가 완료되면, 도 16에 도시된 바와 같이 콘크리트를 타설하게 된다. 콘크리트 타설시, 굳지 않은 콘크리트에 의한 압력에 의하여 외부 측벽 거푸집부재(30)의 상부가 서로 벌어지는 것을 방지하기 위하여 양측의 외부 측벽 거푸집부재(30)의 상부에 가로질러 간격유지장치(42)를 설치하는 것도 바람직하다. 상기 간격유지장치(42)는 양측에 내부에 나사부가 형성되어 있는 커플링을 구비하여, 커플링을 회전시키므로써 커플링에 끼워진 봉부재의 길이가 신축되는 구조로 구성될 수 있으며, 통상의 턴버클 장치로도 구성될 수 있다. 도면에 도시된 실시예에서는 상기 간격유지장치(42)가 턴버클 장치로 구성되어 있다.As such, when the installation of the external formwork device and the internal formwork device 60 is completed, the concrete is poured as shown in FIG. 16. When placing concrete, a space keeping device 42 is installed across the upper sides of the outer sidewall formwork members 30 on both sides to prevent the upper portions of the outer sidewall formwork members 30 from being separated from each other by the pressure of the hardened concrete. It is also preferable. The gap retaining device 42 has a coupling having a threaded portion formed therein at both sides thereof, and may be configured to have a structure in which a length of a rod member fitted to the coupling is stretched and contracted by rotating the coupling. It can also be configured as a device. In the embodiment shown in the figure, the spacing device 42 is configured as a turnbuckle device.

콘크리트의 타설이 완료되면, 외부 거푸집장치의 외면과 개방된 상부슬래브면을 모두 덮도록 양생커버(도시되지 않음)를 덮는다. 양생커버에 의하여 외부 거푸집장치와 상부슬래브면이 모두 덮이면, 보일러를 이용하여 외부 거푸집장치와 암거의 바닥슬래브(310) 상의 증기공급관(50,61)으로 증기를 공급한다. 공급된 증기는 증기공급관(50)의 증기분출구로부터 분출되어 양생커버 내부에 가득하게 되고, 이러한 증기의 열기에 의하여 타설된 콘크리트가 증기촉진양생된다. 이때, 자동온도제어장치를 설치하여 정확한 양생온도 및 시간을 제어할 수도 있다. 이와 같이, 본 발명에서는 외부 거푸집장치와 암거의 바닥슬래브(310) 상에 증기공급관(50,61)을 두어 증기를 공급하므로써 타설된 콘크리트를 용이하게 증기양생시키게 되므로써 콘크리트를 촉진양생시킬 수 있으며, 그에 따라 공기를 현저하게 줄일 수 있게 된다. 또한, 증기양생을 통하여 콘크리트의 균열, 박리현상, 강도저하 등의 열화현상을 방지할 수 있게 되었고, 양생에 적합한 온도와 습도를 가진 증기를 공급함으로써, 건조 수축되어 발생할 수 있는 크랙현상이나 크리이프 현상을 방지할 수 있게 된 것이다.When the casting of the concrete is completed, the curing cover (not shown) is covered to cover both the outer surface of the external formwork and the open upper slab surface. When both the external formwork and the upper slab surface is covered by the curing cover, the boiler supplies steam to the steam supply pipes 50 and 61 on the bottom slab 310 of the external formwork and the culvert. The supplied steam is ejected from the steam outlet of the steam supply pipe 50 to fill the inside of the curing cover, and the concrete poured by the heat of the steam is steam-promoted. At this time, it is possible to control the correct curing temperature and time by installing an automatic temperature control device. As described above, in the present invention, by supplying steam by supplying steam by placing steam supply pipes 50 and 61 on the external formwork and the bottom slab 310 of the culvert, it is possible to facilitate the curing of the concrete by easily steam curing the poured concrete. This makes it possible to significantly reduce the air. In addition, it is possible to prevent deterioration such as cracking, peeling, and deterioration of concrete through steam curing, and by supplying steam having a temperature and humidity suitable for curing, cracking or creep may occur due to dry shrinkage. Will be able to prevent.

한편, 상기 양생커버는 단순한 포대형태로 이루어질 수 있으며, 다른 실시예로서는 외부 거푸집부재의 외면에는 판재로 이루어진 것이 외부 측벽 거푸집부재(30)와 소정 간격을 가지고 덮여지며, 상부슬래브의 개방면에는 포대형태로 된 것이 덮여지는 형태로 구성될 수도 있다.On the other hand, the curing cover may be made of a simple bag shape, and in another embodiment, the outer surface of the outer formwork member is made of a plate is covered with a predetermined distance from the outer sidewall formwork member 30, the bagged form on the open surface of the upper slab It may be configured in the form of being covered with.

본 발명에서, 암거(300)의 시공은 1지간을 완성한 후, 완성된 1지간의 암거(300)에 이웃하는 지간에 암거를 연속하여 시공하게 된다.In the present invention, the construction of the culvert 300 is to complete the construction of one section, the construction of the culvert next to the adjacent section of the culvert 300 of the completed one section.

증기촉진양생이 완료되어 암거(300)의 제작이 완료되면, 후속하여 이웃하는 암거(300)를 형성하기 위하여 앞서 설명한 터파기 작업, 기초슬래브 거푸집부재(10) 설치 작업 및 기초슬래브 마감판부재(102) 결합작업, 파이프관 및 바닥슬래브 보강철근 배근작업, 강선 긴장작업, 바닥슬래브 콘크리트 타설작업 등을 수행하여 이웃하는 암거(300)의 바닥슬래브(310) 제작을 완료한다.When the steam-promoting curing is completed and the production of the culvert 300 is completed, the above-described digging work, the installation work of the base slab formwork member 10 and the foundation slab closing plate member are formed in order to form the neighboring culvert 300. 102) to complete the production of the floor slab 310 of the neighboring culvert 300 by performing the coupling work, pipe pipe and floor slab reinforcement reinforcement work, steel wire tension work, floor slab concrete pouring work.

이웃한 암거(300)의 상기 바닥슬래브(310)의 상부면에는 내부 거푸집장치(60)의 베이스(80)에 구비된 구동장치(62)가 구동할 수 있도록 레일(312)을 설치하고, 상기 레일(312)의 일측에는 외부의 보일러와 연결된 증기공급관(61)을 설치한다. 증기양생이 완료되어 시공이 끝난 암거(300)로부터 외부 거푸집장치와 내부 거푸집장치(60)를 탈거한다. 구체적으로 암거(300)의 전후면에 설치되어 있던 전후면 마감판부재(104)를 탈거한다. 아울러, 외부 거푸집장치의 외부 측벽 거푸집부재(30)를 기초슬래브 거푸집부재(10)로부터 분리시키고, 외부 측벽 거푸집부재(30)에 장착된 구동부(32)의 구동체(48)를 구동부하우징(44) 내에서 하강시킨 후 고정볼트(46)로 위치고정하여 구동체(48)의 구동바퀴(51)가 기초슬래브 거푸집부재(10)의 보강부재(14) 상면에 형성된 레일부(16)에 놓이도록 한다. 탈거된 외부 측벽 거푸집부재(30)의 구동바퀴(51)가 상기 레일부(16)를 따라 구동함에 따라 탈거된 외부 측벽 거푸집부재(30)는 용이하게 이웃하는 지간의 암거(300) 제작을 위하여 미리 설치하여 둔 이웃한 기초슬래브 거푸집부재(10)의 레일부(16)로 이동하게 된다. 이동된 외부 측벽 거푸집부재(30)는 다시 기초슬래브 거푸집부재(10)와 체결되어 고정된다. 외부 측벽 거푸집부재(30)의 이동시에는 도 15에 도시된 바와 같이, 작업대(38)가 이동작업을 방해하지 않도록 접혀진 위치로 만들어지는 것이 바람직하다.The rail 312 is installed on the upper surface of the bottom slab 310 of the neighboring culvert 300 so that the driving device 62 provided in the base 80 of the internal formwork device 60 can be driven. On one side of the rail 312 is installed a steam supply pipe 61 connected to the external boiler. Steam curing is completed to remove the external formwork device and the internal formwork device 60 from the culvert 300 is completed construction. Specifically, the front and rear surface closing plate member 104 installed on the front and rear surfaces of the culvert 300 is removed. In addition, the outer side wall formwork member 30 of the outer formwork device is separated from the base slab formwork member 10, and the drive unit housing 44 of the drive unit 32 mounted to the outer sidewall formwork member 30 is driven. ) And lowered in the fixed bolt 46 to position the driving wheel 51 of the driving body 48 on the rail portion 16 formed on the upper surface of the reinforcing member 14 of the foundation slab formwork member 10. To be. As the driving wheel 51 of the detached outer sidewall formwork member 30 is driven along the rail portion 16, the detached outer sidewall formwork member 30 is easily fabricated for culvert 300 between neighboring grounds. It moves to the rail part 16 of the neighboring foundation slab formwork member 10 installed previously. The moved outer sidewall formwork member 30 is again fastened and fixed with the foundation slab formwork member 10. At the time of movement of the outer side wall formwork member 30, it is preferable that the worktable 38 is made in a folded position so as not to interfere with the movement work.

한편, 내부 거푸집장치(60)는, 상기 신축수단(70, 71, 72)을 수축시켜 상기측벽판부재(66)와 헌치부판부재(68)가 내부를 향하여 이동되도록 하므로써 암거(300)의 내부면으로부터 떨어지게 하며, 그와 동시에 베이스(80)도 하강시켜 상부슬래브판부재(64)를 암거(300)의 상부슬래브로부터 떨어지게 만들어 내부 거푸집장치(60)를 도 15에 도시된 바와 같은 수축상태로 만들게 된다. 이러한 수축상태에서는 베이스(80)가 하강됨으로써 구동장치(62)가 바닥슬래브(310) 위에(구체적으로는 레일 위에) 놓이게 되어 내부 거푸집장치(60)가 레일(312)을 따라 전후로 이동할 수 있는 상태가 된다. 이웃하는 지간의 암거(300)를 제작하기 위하여 이미 이웃하는 지간의 바닥슬래브(310)가 설치되고 그 위에 레일(312)이 설치되어 있으므로, 내부 거푸집장치(60)의 구동장치(62)는 이미 완성된 암거의 레일(312)과 이웃하는 지간의 암거의 바닥슬래브(310)상의 레일(312)을 따라 이동하여 이웃하는 지간의 암거의 바닥슬래브(310) 위에 용이하게 위치하게 된다. 내부 거푸집장치(60)의 이동이 완료되면, 앞서 설명한 바와 같이 내부 거푸집장치(60)를 다시 확장상태로 만들어 암거 제작을 위한 콘크리트 타설이 가능한 상태로 만든다. 이후에 이루어지는 작업은 앞서 설명한 바와 동일한 내용이 반복되므로 추가적인 설명은 생략한다.On the other hand, the internal formwork device 60, by contracting the expansion means (70, 71, 72) so that the side wall plate member 66 and the haunch plate member 68 is moved toward the inside of the culvert 300 At the same time, the base 80 is also lowered so that the upper slab plate member 64 is separated from the upper slab of the culvert 300 so that the inner formwork device 60 is contracted as shown in FIG. 15. Will be made. In this contracted state, the base 80 is lowered so that the driving device 62 is placed on the bottom slab 310 (specifically, on the rail) so that the internal formwork 60 can move back and forth along the rail 312. Becomes In order to manufacture the culvert 300 between neighboring grounds, since the bottom slab 310 of the neighboring grounds is already installed and the rail 312 is installed thereon, the driving device 62 of the internal formwork 60 is already The rails 312 of the completed culverts and the neighboring grounds move along the rails 312 on the bottom slab 310 of the culverts and are easily positioned on the bottom slab 310 of the culverts of the neighboring grounds. When the movement of the internal formwork device 60 is completed, as described above, the internal formwork device 60 is made to be in an expanded state again, thereby making it possible to place concrete for culvert production. Subsequent operations will be repeated since the same contents as described above will be omitted.

위의 실시예에서, 바닥슬래브 보강철근(150)이 먼저 설치되고 바닥슬래브(310)가 타설된 후에 암거(300)의 측벽 및 상부슬래브 보강철근(152)을 설치하는 것으로 설명하였으나, 바닥슬래브 보강철근(150)의 설치와 동시에 측벽 및 상부 슬래브 보강철근(152)을 설치한 후 바닥슬래브(310)를 타설하는 것도 가능하다. 바닥슬래브(310)의 시공이 완료된 후에는 앞서 설명한 바와 같이, 외부 거푸집장치와 내부 거푸집장치(60)를 각각 조립하여 설치하고, 콘크리트를 타설하여 암거(300)를 형성한다.In the above embodiment, the floor slab reinforcement 150 is installed first and the bottom slab 310 is installed after the sidewall and upper slab reinforcement 152 of the culvert 300 has been described, but the bottom slab reinforcement It is also possible to pour the bottom slab 310 after installing the side walls and the upper slab reinforcing bars 152 simultaneously with the installation of the reinforcing bar 150. After the construction of the floor slab 310 is completed, as described above, the external formwork device and the internal formwork device 60 are assembled and installed, respectively, and the concrete is poured to form the culvert 300.

이상에서 설명한 바와 같이 본 발명에 따른 이동식 철재 거푸집장치는 조립식으로 이루어져 있으며, 특히 외부 측벽 거푸집부재와 내부 거푸집장치가 각각 시공완료 후 용이하게 이동할 수 있는 구조를 가지고 있으므로, 1지간의 암거를 시공한 후에 이웃하는 지간의 암거의 시공을 위하여 간편하게 이동할 수 있으므로 연속적인 암거의 시공이 매우 용이하다.As described above, the mobile steel formwork device according to the present invention is constructed as a prefabricated structure, and in particular, since the outer sidewall formwork member and the inner formwork device each have a structure that can be easily moved after the completion of construction, the construction of one culvert Since it can be easily moved for the construction of culverts between neighboring lands, the construction of continuous culverts is very easy.

또한, 본 발명에 따른 이동식 철재 거푸집장치는 그 조립과 분해가 용이하므로, 종래의 기술과는 달리 거푸집 및 동바리 설치기간을 단축시킬 수 있게 되며, 반복사용이 가능하다.In addition, since the mobile steel formwork according to the present invention is easy to assemble and disassemble, unlike the prior art, it is possible to shorten the formwork and copper bar installation period, it is possible to use repeatedly.

특히, 본 발명에 따른 이동식 철재 거푸집장치는 거푸집부재에 증기를 공급할 수 있는 구성이 구비되어 있어, 별도의 장비 없이도 용이하게 증기를 공급할 수 있어, 암거의 증기양생이 용이하므로, 암거의 양생기간을 단축시켜 전체 암거 시공에 소요되는 공기를 단축시킬 수 있게 된다. 또한, 콘크리트의 양생기간을 단축시킴으로 해서 공기를 단축시킬 수 있고, 동절기 및 기상악화시에도 적응력이 우수하여 별도의 양생비가 들지 않는다.In particular, the mobile steel formwork apparatus according to the present invention is provided with a configuration that can supply steam to the formwork member, it is possible to easily supply steam without additional equipment, it is easy to cure the steam of the culvert, the curing period of the culvert By shortening it is possible to shorten the air required for the entire culvert construction. In addition, it is possible to shorten the air by shortening the curing period of the concrete, and even in winter and weather worsening adaptability is excellent, does not cost a separate curing cost.

나아가, 본 발명에 따른 이동식 철재 거푸집장치는 철재로 이루어져 있으므로, 강성이 우수하여 작업시 변형이나 뒤틀림 등이 발생하지 아니하므로 콘크리트의 충분한 다짐이 이루어질 수 있으며, 그에 따라 콘크리트의 내구성, 수밀성 등이 증대되어 암거의 품질이 향상된다. 또한, 이동식 철재 거푸집장치를 사용함으로써 제품면이 미려하게 된다.Furthermore, since the movable steel formwork device according to the present invention is made of steel, it is excellent in rigidity, so that deformation or warpage does not occur during work, and thus sufficient compaction of concrete can be achieved, thereby increasing durability, watertightness, etc. of concrete. The quality of the culvert is improved. In addition, the surface of the product is beautiful by using a movable steel formwork.

Claims (8)

콘크리트 암거(300)를 연속적으로 제작하기 위한 이동식 거푸집장치로서,As a mobile formwork for continuously manufacturing the concrete culvert 300, 상기 암거(300)의 바닥슬래브(310)를 형성하기 위한 기초슬래브 거푸집부재(10)와, 상기 기초슬래브 거푸집부재(10)의 상면을 따라 전후 이동이 가능하여 1지간의 암거 시공이 완료되면 상기 기초슬래브 거푸집부재(10)로부터 분리되어 이웃하는 지간의 암거 시공을 위하여 이동하며, 암거의 측벽부(320)를 형성하도록 암거(300)의 측벽부 외부에 설치되고 증기공급관(50)이 외면에 설치되어 있어 암거 콘크리트 타설 후 증기를 공급하여 콘크리트를 증기촉진양생시킬 수 있는 외부 측벽 거푸집부재(30)와, 상기 암거(300)의 바닥슬래브(310)의 전후면을 형성하기 위한 기초슬래브 마감판부재(102)와, 상기 암거(300)의 전후면을 형성하기 위한 전후면마감판부재(104)를 포함하는 외부 거푸집장치; 및The base slab formwork member 10 and the base slab formwork member 10 for forming the bottom slab 310 of the culvert 300 can be moved back and forth along the upper surface of the foundation slab formwork member 10 when the culvert construction between the lands is completed. It is separated from the foundation slab formwork member 10 and moves for culling construction between neighboring lands, and is installed outside the side wall portion of the culvert 300 to form the side wall portion 320 of the culvert, and the steam supply pipe 50 is disposed on the outer surface. It is installed to supply the steam after the culvert concrete pouring the outer side wall formwork member 30 to steam the curing of the concrete, and the foundation slab closing plate for forming the front and rear surfaces of the bottom slab 310 of the culvert 300 An external formwork device including a member 102 and a front and rear finish plate member 104 for forming a front and rear surface of the culvert 300; And 상기 외부 거푸집장치와 소정 간격 이격되어 설치되므로써 암거(300)의 내부면을 형성하게 되는 내부 거푸집장치(60)로서, 암거(300)의 측벽 콘크리트 내면과 마주하게 되는 측벽판부재(66)와, 암거(300)의 상부슬래브 콘크리트의 하부면과 마주하게 되는 상부슬래브판부재(64)와, 신축되어 측벽판부재(66)를 좌우로 움직이며 상부슬래브판부재(64)를 상하로 움직여서 내부 거푸집장치(60)를 확장/수축시킬 수 있는 신축수단(70,71,72)과, 전후로 이동할 수 있도록 구동장치(62)가 구비되어 있어, 암거 시공을 위한 콘크리트 타설시에는 상기 신축수단(70,71,72)을 신장시켜 상기 측벽판부재(66)와 상부슬래브판부재(64)를 확장상태로 만들고, 암거 시공이 완료되면 상기 신축수단(70,71,72)을 수축시켜 상기 측벽판부재(66)와 상부슬래브판부재(64)를 수축상태로 함과 동시에 상기 구동장치(62)가 구동가능상태로 되어 1지간의 암거 시공이 완료되면 이웃하는 지간의 암거 시공을 위하여 이동할 수 있는 베이스(80)를 포함하는 내부 거푸집장치(60)를 구비하고 있는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.An inner formwork device 60 which forms an inner surface of the culvert 300 by being spaced apart from the outer formwork device by a predetermined distance, the sidewall plate member 66 facing the inner surface of the sidewall concrete of the culvert 300; The upper slab plate member 64 facing the lower surface of the upper slab concrete of the culvert 300 is stretched and moves the side slab plate member 66 to the left and right to move the upper slab plate member 64 up and down to form an internal formwork. Expansion means (70, 71, 72) that can be expanded / contracted to the device 60, and the drive device 62 to move back and forth, the expansion means (70, when placing concrete for culvert construction) 71 and 72 to extend the side wall plate member 66 and the upper slab plate member 64, and when the culling is completed, the expansion means 70, 71 and 72 are contracted to contract the side wall plate member. At the same time as the 66 and the upper slab plate member 64 in a contracted state When the drive device 62 is in a driveable state and the completion of the culling construction between one section is completed, the internal formwork device 60 including the base 80 that can move for culling construction between neighboring grounds is provided. Movable formwork for making culverts. 제 1항에 있어서,The method of claim 1, 상기 기초슬래브 거푸집부재(10)에는 외부 측벽 거푸집부재(30)의 이동을 위한 레일부(16)가 구비되어 있으며, 상기 외부 측벽 거푸집부재(30)에는 상기 레일부(16)를 따라 구동되어 상기 외부 측벽 거푸집부재(30)를 전후로 이동시키는 구동부(32)가 구비되어 있는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.The base slab formwork member 10 is provided with a rail portion 16 for the movement of the outer sidewall formwork member 30, and the outer sidewall formwork member 30 is driven along the rail portion 16 to the The movable formwork for culvert production, characterized in that the drive unit 32 for moving the outer sidewall formwork member 30 back and forth is provided. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 암거의 바닥슬래브(310) 상에는 상기 내부 거푸집장치(60)가 이동할 수 있도록 레일부(312)가 구비되고, 상기 외부 측면 거푸집부재(30)에 구비된 증기공급관(50)과 아울러 암거 콘크리트 타설후 증기를 공급하여 콘크리트를 양생시킬 수 있도록 상기 레일부(312)의 일측으로 증기공급관(61)이 구비되는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.On the bottom slab 310 of the culvert, the rail unit 312 is provided to move the internal formwork device 60, and the culvert concrete is poured together with the steam supply pipe 50 provided in the outer side formwork member 30. After the steam supply pipe to one side of the rail unit 312 so as to cure the concrete, the movable formwork for culvert production, characterized in that it is provided. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 외부 측벽 거푸집부재(30)의 상부에는 접철식으로 구성되어 외부 측벽 거푸집부재(30)의 고정설치 상태에서는 펼쳐져서 작업자가 보행할 수 있는 보행가능상태가 되고, 외부 측벽 거푸집부재(30)의 이동시에는 접혀져서 작업자가 보행할 수 없는 보행불능상태로 되는 안전난간(57)이 구비된 작업자 보행용 작업대(38)가 설치되어 있는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.The top of the outer side wall formwork member 30 is foldable and is expanded in a fixed installation state of the outer side wall formwork member 30 to become a walkable state that an operator can walk, and when the outer side wall formwork member 30 moves. The portable molder for culvert production, characterized in that the worker walking work platform (38) is provided with a safety handrail (57) that is folded and is unable to walk, which is unable to walk. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 베이스(80)의 하부에는 베이스(80)를 승하강시킬 수 있는 승하강장치(84)가 구비되며, 상기 베이스(80)의 상부에는 상기 상부슬래브판부재(64)를 지지하는 지지기둥(86)이 설치되어 있고, 상기 지지기둥(86)에는 신축에 의하여 양측의 측벽판부재(66)를 좌우로 움직일 수 있는 신축수단(70)이 각각 설치되어 있는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.A lifting device 84 capable of lifting the base 80 up and down is provided at the bottom of the base 80, and a support pillar for supporting the upper slab plate member 64 is provided at the top of the base 80. 86 is provided, and the support pillar 86 is provided with a movable form for culvert, characterized in that each of the expansion means 70 that can move the side wall plate member 66 on both sides by expansion and contraction. Device. 제 1항 또는 제 2항에 있어서,The method according to claim 1 or 2, 상기 내부 거푸집장치(60)의 측벽판부재(66)와 상기 외부 측벽 거푸집부재(30)에는 그 일부로써, 규격이 다른 암거의 제작시 높이방향으로의 길이를 늘리거나 줄일 수 있도록 착탈이 가능한 조절부재(33,63)가 구비되어 있는 것을 특징으로 하는 암거 제작용 이동식 거푸집장치.As a part of the side wall plate member 66 and the outer side wall formwork member 30 of the inner formwork device 60, detachable adjustment is possible to increase or decrease the length in the height direction during fabrication of different culverts. Mobile formwork for culvert production, characterized in that the members (33,63) are provided. 암거(300)의 바닥슬래브(310)를 형성하기 위한 기초슬래브 거푸집부재(10)와, 상기 기초슬래브 거푸집부재(10)의 상면을 따라 전후 이동이 가능하며 암거의 측벽부(320)를 형성하도록 암거(300)의 측벽부 외부에 설치되고 증기공급관(50)이 외면에 설치되어 있는 외부 측벽 거푸집부재(30)와, 상기 암거(300)의 바닥슬래브(310)의 전후면을 형성하기 위한 기초슬래브 마감판부재(102)와, 상기 암거(300)의 전후면을 형성하기 위한 전후면 마감판부재(104)를 포함하는 외부 거푸집장치; 및 상기 외부 거푸집장치와 소정 간격 이격되어 설치되므로써 암거(300)의 내부면을 형성하게 되는 내부 거푸집장치(60)로서, 암거(300)의 측벽 콘크리트 내면과 마주하게 되는 측벽판부재(66)와, 암거(300)의 상부슬래브 콘크리트의 하부면과 마주하게 되는 상부슬래브판부재(64)와, 신축되어 측벽판부재(66)를 좌우로 움직이며 상부슬래브판부재(64)를 상하로 움직여서 내부 거푸집장치(60)를 확장/수축시킬 수 있는 신축수단(70,71,72)과, 전후로 이동할 수 있도록 구동장치(62)가 구비되어 있는 베이스(80)를 포함하는 내부 거푸집장치(60)를 구비하고 있는 암거 제작용 이동식 거푸집장치를 이용한 암거의 증기촉진양생 연속시공방법으로서,The base slab formwork member 10 for forming the bottom slab 310 of the culvert 300 and the back and forth movement along the upper surface of the base slab formwork member 10 are possible to form the side wall portion 320 of the culvert Foundation for forming the front and rear surfaces of the outer side wall formwork member 30, which is installed outside the side wall portion of the culvert 300 and the steam supply pipe 50 is installed on the outer surface, and the bottom slab 310 of the culvert 300. An external formwork device including a slab closing plate member 102 and a front and rear closing plate member 104 for forming a front and rear surface of the culvert 300; And an inner formwork device 60 which forms an inner surface of the culvert 300 by being spaced apart from the outer formwork device by a predetermined distance, and the sidewall plate member 66 facing the inner surface of the sidewall concrete of the culvert 300. The upper slab plate member 64 facing the lower surface of the upper slab concrete of the culvert 300 is stretched and moves the sidewall plate member 66 to the left and right and the upper slab plate member 64 to move up and down inside. Internal formwork device 60 including expansion means (70, 71, 72) that can expand / contract the formwork device (60), and a base (80) provided with a drive device (62) to move back and forth As a continuous method of steam-promoting curing of a culvert using a portable formwork for making a culvert, 상기 기초슬래브 거푸집부재(10), 기초슬래브 마감판부재(102)를 결합하고, 그 내측으로 바닥슬래브 보강철근(150)과 암거(300)의 측벽 및 상부슬래브 보강철근(152)을 배근한 후 콘크리트를 타설하여 바닥슬래브(310)를 시공하고,After combining the foundation slab formwork member 10 and the foundation slab closing plate member 102, the inner side of the slab reinforcement 150 and the sidewall and upper slab reinforcement 152 of the culvert 300 to the inside, Construct the floor slab 310 by pouring concrete, 상기 기초슬래브 거푸집부재(10) 및 기초슬래브 마감판부재(102)와 외부 측벽 거푸집부재(30) 및 전후면 마감판부재(104)를 결합하여 외부 거푸집장치를 설치를 완료하고,The base slab formwork member 10 and the base slab closing plate member 102 and the outer sidewall formwork member 30 and the front and rear surface closing plate member 104 are combined to complete the installation of an external formwork device. 상기 보강철근(152)의 내측으로 수축상태의 내부 거푸집장치(60)를 설치하고,Installing the inner formwork device 60 in a contracted state inside the reinforcing bar 152, 상기 내부 거푸집장치(60)에 구비된 신축수단(70,71,72)을 신장시키고 상기 베이스(80)의 승하강장치(84)를 상승시켜 상기 측벽판부재(66)와 상부슬래브판부재(64)를 확장시킴으로써 내부 거푸집장치(60)를 확장상태로 만들고,Extending and contracting means (70, 71, 72) provided in the internal formwork device 60 and the lifting device 84 of the base 80 is raised to raise the side wall plate member 66 and the upper slab plate member ( Expand the internal formwork device 60 by expanding 64, 상기 외부 거푸집장치와 내부 거푸집장치(60) 사이의 공간에 콘크리트를 타설하여 암거(300)를 시공하고,Constructing a culvert 300 by placing concrete in the space between the external formwork device and the internal formwork device 60, 외부 거푸집장치와 암거의 상부슬래브 전체가 덮이도록 양생커버를 덮은 후 외부 측벽 거푸집부재(30)의 증기공급관(50)과 암거의 바닥슬래브(310) 상의 증기공급관(61)으로 증기를 공급하여 암거(300)를 증기에 의한 촉진양생을 시키며,After covering the curing cover to cover the entire upper slab of the external formwork and the culvert, the steam is supplied to the steam supply pipe 50 of the outer side wall formwork member 30 and the steam supply pipe 61 on the bottom slab 310 of the culvert Promote curing by steam (300), 암거(300)의 양생이 완료되면, 외측 거푸집장치의 결합을 해제하고, 내부 거푸집장치(60)의 신축수단(70,71,72)을 수축시키고 상기 베이스(80)의 승하강장치(84)를 하강시켜 상기 측벽판부재(66)와 상부슬래브판부재(64)를 수축시킴과 동시에 상기 베이스(80)의 구동장치(62)를 구동가능상태가 되도록 함으로써 상기 내부 거푸집장치(60)를 수축상태로 만들고,When curing of the culvert 300 is completed, the coupling of the outer formwork device is released, the expansion means 70, 71, 72 of the inner formwork device 60 are contracted and the lifting device 84 of the base 80 is contracted. The inner die device 60 is contracted by lowering the side wall plate member 66 and the upper slab plate member 64 to make the driving device 62 of the base 80 a driveable state. State, 상기 내부 거푸집장치(60)와 상기 외부 거푸집장치를 이웃하는 지간의 암거(300) 시공을 위하여 이동시키는 것을 특징으로 하는 암거의 증기촉진양생 연속시공방법.The internal formwork device 60 and the external formwork device for steam cure continuous construction method characterized in that for moving the culvert 300 between the neighboring land construction. 제 7항에 있어서,The method of claim 7, wherein 내부 거푸집장치(60)를 수축상태로 만든 후에,After making the inner formwork 60 in a contracted state, 이웃하는 지간의 암거의 연속시공을 위하여 상기의 과정에서 완성된 암거(300)의 이웃한 지간에 다시 상기 기초슬래브 거푸집부재(10), 기초슬래브 마감판부재(102)를 결합하여 그 내측으로 바닥슬래브 보강철근(150)과 암거(300)의 측벽 및 상부슬래브 보강철근(152)을 배근한 후 콘크리트를 타설하여 바닥슬래브(310)를 시공하고,The foundation slab formwork member 10 and the foundation slab closing plate member 102 are combined to the neighboring section of the culvert 300 completed in the above process for continuous construction of the culvert between neighboring grounds, and the bottom of the culvert 300 After laying the slab reinforcement 150 and the sidewalls of the culvert 300 and the upper slab reinforcement 152, the concrete is poured to construct a floor slab 310, 상기 완성된 암거(300)로부터 탈거된 외부 측벽 거푸집부재(30)를 이동시켜 다시 결합하여 외부 거푸집장치를 설치하고,The external side wall formwork member 30 removed from the completed culvert 300 is moved and combined again to install an external formwork device, 상기 수축상태의 내부 거푸집장치(60)를 이웃한 암거(300)의 완성된 바닥슬래브(310) 상부로 이동시켜 확장상태로 만들고 다시 콘크리트를 타설하여 연속적인 암거를 시공하는 것을 특징으로 하는 암거의 증기촉진양생 연속시공방법.The internal formwork device 60 in the contracted state is moved to the upper side of the completed bottom slab 310 of the culvert 300 adjacent to the expanded state, and the concrete is poured again to construct a continuous culvert Continuous steam curing curing method.
KR10-2001-0070237A 2001-11-12 2001-11-12 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same KR100448221B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR10-2001-0070237A KR100448221B1 (en) 2001-11-12 2001-11-12 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR10-2001-0070237A KR100448221B1 (en) 2001-11-12 2001-11-12 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same

Related Child Applications (1)

Application Number Title Priority Date Filing Date
KR2020010037339U Division KR200267831Y1 (en) 2001-12-04 2001-12-04 Movable Steel Form for Constructing Culvert

Publications (2)

Publication Number Publication Date
KR20020005537A KR20020005537A (en) 2002-01-17
KR100448221B1 true KR100448221B1 (en) 2004-09-10

Family

ID=19715913

Family Applications (1)

Application Number Title Priority Date Filing Date
KR10-2001-0070237A KR100448221B1 (en) 2001-11-12 2001-11-12 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same

Country Status (1)

Country Link
KR (1) KR100448221B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100777036B1 (en) * 2006-06-28 2007-11-16 최승선 Manufacturing equipment for a pc box culvert with liner, assembling method for a pc box culvert, manufacturing method for a pc box culvert, and pc box culvert using the same method
KR101814726B1 (en) * 2017-08-03 2018-01-30 최해순 Size changeable type movable steel form for cable tunnel structure

Families Citing this family (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100463032B1 (en) * 2002-08-30 2004-12-23 주식회사 토암건설 Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
KR100692055B1 (en) * 2005-05-06 2007-03-12 삼성물산 주식회사 Movable Concrete Form and Multi-level Construction Method Using the Same
KR101103001B1 (en) * 2010-05-18 2012-01-05 동도산업 주식회사 Inner formwork for pre-stressed concrete box girder of precast segmental method
KR101437842B1 (en) * 2012-07-10 2014-09-04 한국철도기술연구원 Low depth tunnel construction method using variable mould system
KR101372261B1 (en) * 2013-01-23 2014-03-10 현대알루미늄(주) Box form structure for culvert construction
KR101714152B1 (en) * 2015-06-02 2017-03-08 삼성물산 주식회사 Hollowcore slab automation manufacturing method
CN106437769B (en) * 2016-11-09 2018-06-01 辽宁工程技术大学 The self-propelled hydraulic formwork jumbo poured for Deep Foundation Pit of Metro Stations engineering top plate
KR101956695B1 (en) * 2016-12-06 2019-06-19 홍주이엔씨(주) The mould for fslm girder with inner mould easily removable
CN112376612B (en) * 2020-12-08 2024-10-25 安徽建工建设投资集团有限公司 Construction system and construction method for large-section multi-cabin cast-in-situ utility tunnel roof template

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100777036B1 (en) * 2006-06-28 2007-11-16 최승선 Manufacturing equipment for a pc box culvert with liner, assembling method for a pc box culvert, manufacturing method for a pc box culvert, and pc box culvert using the same method
KR101814726B1 (en) * 2017-08-03 2018-01-30 최해순 Size changeable type movable steel form for cable tunnel structure

Also Published As

Publication number Publication date
KR20020005537A (en) 2002-01-17

Similar Documents

Publication Publication Date Title
KR101130923B1 (en) the mold with self-propelled type trolley for construction of continuous structure and the construction method of continuous structure therewith
KR101081791B1 (en) Beam making method using moulding jack apparatus and end moulding apparatus
CN112265114B (en) Prefabricated box girder template and construction method applying same
CN110394885B (en) Be applied to prefabricated whole fluid pressure type template of box culvert
KR100448221B1 (en) Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
CN101965254B (en) Method and installation for manufacturing hollow, prismatic, modular reinforced concrete elements, and element obtained therefrom
KR100463032B1 (en) Movable Steel Form for Constructing Culvert and Continuous Constructing Method of Culvert Using the Same
CN114182952A (en) Prefabricated part formwork system and operation method thereof
KR100949785B1 (en) Mold for manufacturing PC beam
KR101150829B1 (en) The mold with self-propelled type trolley for construction of retaining wall
KR200298104Y1 (en) Mobile form for forming concrete box on construction work
KR20020035038A (en) mould form apparatus for box girder of ILM and method of construction for box-girder
KR200267831Y1 (en) Movable Steel Form for Constructing Culvert
CN113478633A (en) Production method of cavity wall and concrete prefabricated part production line
CN220218950U (en) Railway prefabricated box girder side form
CN110847065A (en) Prefabricated assembled box channel and construction method
CN117464811A (en) Modeling device of prefabricated box girder capable of being adjusted in lifting mode
CN214819438U (en) Self-propelled integral hydraulic formwork equipment for prefabricating T-shaped beam
JPH0143086B2 (en)
CN212335790U (en) Large cantilever bent cap construction trolley
JP2829363B2 (en) Formwork equipment for pillar construction
CN216809621U (en) Integrated universal hydraulic T-beam template
CN112411406A (en) Light truss type porous box culvert template system and construction method
CN109057824B (en) Tunnel cable trench forming device and forming method
CN113738157A (en) Temporary supports on two sides of post-cast strip of building and method for constructing constructional column by using temporary supports

Legal Events

Date Code Title Description
A201 Request for examination
G15R Request for early opening
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20121224

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20130830

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20140827

Year of fee payment: 11

FPAY Annual fee payment

Payment date: 20150821

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20160829

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20170825

Year of fee payment: 14

FPAY Annual fee payment

Payment date: 20190827

Year of fee payment: 16