KR100389054B1 - Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof - Google Patents
Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof Download PDFInfo
- Publication number
- KR100389054B1 KR100389054B1 KR10-2000-0051349A KR20000051349A KR100389054B1 KR 100389054 B1 KR100389054 B1 KR 100389054B1 KR 20000051349 A KR20000051349 A KR 20000051349A KR 100389054 B1 KR100389054 B1 KR 100389054B1
- Authority
- KR
- South Korea
- Prior art keywords
- concrete
- pipe
- manhole
- concrete pipe
- water supply
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2200/00—Geometrical or physical properties
- E02D2200/11—Height being adjustable
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본발명은 지하에 매설된 상수도 배관의 제수변을 보호하기 위한 맨홀에 관한 것으로, 본발명의 목적은 공사기간을 단축시켜 줄 뿐만 아니라, 공사비용을 크게 절감시켜 주며, 품질 좋은 맨홀 구조체를 구현하고, 또한 시공후 유지관리하기에 용이한 상수도 맨홀용 프리캐스트 콘크리트 구조체 및 그것을 이용한 상수도 맨홀의 시공방법을 제공하는데 있으며, 이 목적을 달성하기 위한 본발명은, a) 높이조절용 잭(11)이 하면에 부착된 기초 콘크리트판(10)을 제수변(2)의 중앙 하부에 위치시킨 후 굴착부(3) 바닥에 지지시키는 단계; b) 하부 콘크리트관(20)을 기초 콘크리트판(10)의 상부에 얹어서 정착시키는 단계; c)높이조절용 잭(11)을 동작시켜 하부 콘크리트관(20)의 상측홈(21)과 상수관(1)을 끼워 맞추는 단계; d) 기초 콘크리트판(10)과 굴착부(3) 바닥과의 사이에 바닥 콘크리트재(50)를 채워 넣는 단계; e) 중간부 콘크리트관(30)의 하측홈(1)을 상수관(1)에 끼워 맞추면서 하부 콘크리트관(20)의 상단에 접속시키는 단계; f) 중간부 콘크리트관(30)의 상부에 상층부 콘크리트관(40)들을 연이어 접속시키는 단계; g) 상층부 콘크리트관(40)의 최상부에 철덮개(60)를 씌우고 굴착부(3)를 복구하는 단계;를 통하여 이루어진다.The present invention relates to a manhole to protect the water side of the water supply pipe buried underground, the purpose of the present invention not only shorten the construction period, but also greatly reduce the construction cost, implement a high quality manhole structure, In addition, the present invention provides a precast concrete structure for water supply manholes and a water supply manhole construction method using the same, which is easy to maintain after construction, and the present invention for achieving this purpose, a) height adjustment jack (11) is provided on the lower surface Placing the attached base concrete plate 10 at the center lower part of the dividing side 2 and supporting the bottom of the excavation part 3; b) fixing the lower concrete pipe 20 by placing it on top of the base concrete plate 10; c) fitting the upper groove 21 and the water supply pipe 1 of the lower concrete pipe 20 by operating the height adjusting jack 11; d) filling the bottom concrete member 50 between the base concrete plate 10 and the bottom of the excavation part 3; e) connecting the lower groove 1 of the intermediate concrete pipe 30 to the upper end of the lower concrete pipe 20 while fitting the water pipe 1; f) successively connecting the upper concrete pipes 40 to the upper portion of the intermediate concrete pipe 30; g) covering the top of the upper concrete pipe 40, the iron cover (60) and recovering the excavation (3) is made through.
Description
본발명은 지하에 매설된 상수도 배관의 제수변을 보호하기 위한 맨홀에 관한 것으로, 특히 공장에서 맨홀의 기초부 및 벽체를 프리캐스트 콘크리트 제품으로 기성하고 이를 현장에서 조립 설치하는 방식을 통하여 맨홀의 시공을 완료함으로써, 공사기간을 단축시켜 줄 뿐만 아니라, 공사비용을 크게 절감시켜 주며, 또한 유지관리하기에 용이한 상수도 맨홀용 프리캐스트 콘크리트 구조체 및 그것을 이용한 상수도 맨홀의 시공방법에 관한 것이다.The present invention relates to a manhole for protecting the water side of the water supply pipe buried underground, especially the construction of the manhole through the method of pre-installing the foundation and walls of the manhole as a precast concrete product in the factory By completing the present invention, the present invention relates to a precast concrete structure for a water supply manhole and a method of constructing a water supply manhole using the same, which not only shorten the construction period but also greatly reduce the construction cost and are easy to maintain.
상수도 맨홀은 수도관로의 방향변환 또는 수류를 조절하거나 차단할 목적으로 설치되는 제수변, 관로내에 축적된 공기를 뽑아 내기 위한 목적으로 설치되는 공기변, 소화호스를 연결하기 위한 소화용 제수변 등을 수용하여서 보호하거나 유지관리하기 위해 지중에 설치되는 지하 구조물이다.Water supply manhole is protected by accepting a distillation valve installed for the purpose of controlling the direction of the water pipe or controlling or blocking the water flow, an air valve installed for the purpose of extracting the accumulated air in the pipeline, and a fire extinguishing valve for connecting the fire hose. Or underground structures installed underground for maintenance.
이러한, 상수도 맨홀은 대부분 차도와 보도의 경계구간에 설치되고 있으나, 보차도 구분이 없는 도로에서는 불가피하게 차도에 설치된다.Most of these water supply manholes are installed at the boundary between the roadway and the sidewalk, but are inevitably installed on the roadway without a sidewalk.
종래, 맨홀의 시공은 지반굴착 - 제수변 설치 - 기초콘크리트 타설 - 벽체 및 상부슬래브 콘크리트 타설 - 주변 포장복구 등의 과정을 거치고 있다.Conventionally, the construction of the manhole is undergoing a process such as ground excavation-installation of the water side-concrete foundation-wall and upper slab concrete casting-surrounding pavement recovery.
상기와 같은 종래의 맨홀 시공방법은 맨홀 구조체를 형성하기 위한 모든 작업을 현장에서 직접 시행하기 때문에 다음과 같은 여러 문제점이 있었다.The conventional manhole construction method as described above has a number of problems, as follows, because all operations for forming the manhole structure are performed directly on the site.
즉, 콘크리트를 타설하기 위해 거푸집을 설치하고 해체하여야 하며 이를 양생해야 하는 등 콘크리트 구조체를 형성하는데 긴 기간이 소요되기 때문에 공사기간이 장기화(약 20일간)됨에 따라 공사비용이 많이 들게 되어 경제성이 떨어지는 문제점이 있었다.In other words, since it takes a long time to form a concrete structure, such as formwork and dismantle, and cure it to pour concrete, the construction period becomes long (about 20 days), resulting in high construction costs and economic efficiency. There was a problem.
그리고, 장기간의 차량통행 차단, 우회도로 확보 등으로 인해 시민불편이 가중되는 것은 물론이고, 안전사고가 발생될 위험에 장기간 동안 노출되는 문제점이 있었다.In addition, there is a problem that the inconvenience of citizens is increased due to long-term vehicle blocking, securing a detour road, and a long-term exposure to a risk of a safety accident.
또한, 콘크리트 구조체를 형성함에 있어 1차적으로 기초 콘크리트를 타설하고 양생시킨 다음, 2차로 벽체 및 슬래브 콘크리트를 시공하기 때문에, 콘크리트 품질을 확보하는데 있어 중요한 적정다짐 및 습윤양생이 어렵고, 1,2차콘크리트 시공으로 먼저 친 콘크리트와 나중에 친 콘크리트와의 시공 죠인트부에 균열이 불가피하게 발생되기 때문에, 시공완료 후 맨홀 주변의 지하수위 상승 및 우·오수의 침투로 인하여 맨홀의 내부가 물로 포화되어 제수변 등을 보호하기 위한 본연의 임무를 수행하고 있지 못한 실정이다.In addition, in the formation of the concrete structure, the foundation concrete is primarily poured and cured, and then the walls and slab concrete are constructed secondly, so that proper titration and wetting curing are difficult for securing the concrete quality. As the concrete construction inevitably causes cracks in the joints between the first and later concrete, the interior of the manhole is saturated with water due to the rise of groundwater level around the manhole and the penetration of rainwater and sewage. It is not doing its duty to protect the situation.
이에 따라, 본발명은 현장 구축에 의존하는 종래의 상수도 맨홀에서 나타나는 공사 장기화에 따른 문제, 품질관리 불량으로 인한 내구성 저하문제, 지하수, 우·오수 침투로 인한 상수도 장치가 부식되는 제 문제점들을 해결하고자 안출한것이다.Accordingly, the present invention aims to solve the problems caused by the prolonged construction in the conventional water supply manhole, which is dependent on the construction of the site, the problem of deterioration of durability due to poor quality control, and the problems of corrosion of the water supply system due to the infiltration of groundwater and rainwater. It was created.
따라서, 본발명의 목적은 공장에서 맨홀의 기초부 및 벽체를 프리캐스트 콘크리트 제품으로 기성하고 이를 현장에서 조립 설치하는 방식을 통하여 맨홀의 시공을 완료함으로써, 공사기간을 단축시켜 줄 뿐만 아니라, 공사비용을 크게 절감시켜 주며, 또한 품질 좋은 맨홀 구조체를 구현하고, 시공후 유지관리하기에 용이한 상수도 맨홀용 프리캐스트 콘크리트 구조체 및 그것을 이용한 상수도 맨홀의 시공방법을 제공하는데 있다.Therefore, the purpose of the present invention is to not only shorten the construction period, but also to reduce the construction period by completing the construction of the manhole through the method of pre-installing the foundation and walls of the manhole in the factory as precast concrete products and assembling and installing them on site. It is to provide a precast concrete structure for the water supply manhole and a construction method of the water supply manhole using the same, which greatly reduces the cost, implements a high quality manhole structure, and is easy to maintain after construction.
도1은 본발명에 의한 프리캐스트 콘크리트 구조체를 보여주는 사시도1 is a perspective view showing a precast concrete structure according to the present invention
도2는 본발명에 의해 구축한 상수도 맨홀의 측단면 구성도Figure 2 is a side cross-sectional configuration diagram of the water supply manhole constructed according to the present invention
도3은 본발명이 2지형 상수관에 적용된 맨홀의 평면구성도3 is a plan view of a manhole of the present invention applied to a two-terrain water pipe
도4는 본발명이 3지형 상수관에 적용된 맨홀의 평면구성도4 is a plan view of the manhole of the present invention applied to a triangular water pipe
도5는 본발명이 4지형 상수관에 적용된 맨홀의 평면구성도Figure 5 is a plan view of a manhole applied to the four-terminated water supply pipe of the present invention
< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>
1:상수관 2:제수변 3:굴착부1: water pipe 2: dilution 3: rig
10:기초 콘크리트판 11:높이조절용 잭 12:정착홈10: foundation concrete plate 11: height adjustment jack 12: fixing groove
20:하부 콘크리트관 21:상측홈 30:중간부 콘크리트관20: lower concrete pipe 21: upper groove 30: middle concrete pipe
31:하측홈 40:상층부 콘크리트관 50:바닥 콘크리트재31: lower groove 40: upper concrete pipe 50: floor concrete
60:철덮개 71:지수팽창제 72:콘크리트 접합제60: iron cover 71: exponent expansion agent 72: concrete bonding agent
73:고정편 a:단턱부73: Fixed piece a:
이하, 본발명의 기술구성을 본발명의 실시예들에 따른 첨부도면을 참조하여 구체적으로 설명한다.Hereinafter, the technical configuration of the present invention will be described in detail with reference to the accompanying drawings in accordance with embodiments of the present invention.
도1에는 본발명에 적용되는 콘크리트 구조체를 도시하고 있다.1 shows a concrete structure applied to the present invention.
이 도면에 도시된 바와 같이 본발명의 상수도 맨홀용 콘크리트 구조체는, 높이조절용 잭(11)들이 하면에 부착된 상태로 공장에서 기성되는 기초 콘크리트판 (10)과; 상기 기초 콘크리트판(10)의 상면에 얹혀져서 그 하단부가 정착되며, 상단부의 소정위치에 적어도 2이상의 반원형 상측홈(21)이 형성된 하부 콘크리트관(20)과; 상기 하부 콘크리트관(20)의 상부에 그 하단부가 접속되며 상기 하부 콘크리트관(20)의 상측홈(21)과 상응하는 위치 마다의 그 하단부에 반원형의 하측홈(31)이 형성된 중간부 콘크리트관(30)과; 상기 중간부 콘크리트관(30)의 상부에 연이어 접속되어 적층되는 다수의 상층부 콘크리트관(40);으로 구성된 것을 기술구성상의 기본적인 특징으로 한다.As shown in this figure, the concrete structure for the water supply manhole of the present invention includes: a base concrete plate 10 that is established in a factory with height adjustment jacks 11 attached to a lower surface thereof; A lower concrete pipe 20 mounted on an upper surface of the foundation concrete plate 10 and having a lower end thereof fixed thereto, and having at least two semicircular upper grooves 21 formed at predetermined positions of the upper concrete part; An intermediate concrete pipe having a lower end portion connected to an upper portion of the lower concrete pipe 20 and having a semicircular lower groove 31 formed at the lower end of each lower position corresponding to the upper groove 21 of the lower concrete pipe 20. 30; It consists of a plurality of upper concrete pipes (40) which are connected to the upper part of the intermediate concrete pipe (30) in succession to be laminated.
본발명을 실시함에 있어서, 상기 기초 콘크리트판 및 콘크리트관들은 4각으로 형성할 수도 있으나, 시공의 용이성 및 구조적 강성 등을 감안하여 볼 때 원형으로 형성됨이 바람직하다.In carrying out the present invention, the base concrete plate and concrete pipes may be formed in a quadrangular shape, but in view of the ease of construction and structural rigidity, etc., it is preferable that they are formed in a circular shape.
또한, 그 콘크리트 구조체들을 설치되는 맨홀의 특성에 따라 직경별·높이별·상수도 관로 방향별(예를 들어, 2지형 상수도관에 적용되는 콘크리트 구조체는 그 상수관로의 방향에 맞춘 2개의 홈이 형성되고, 3지형 또는 4지형 상수도관에 적용되는 콘크리트 구조체는 3개 또는 4개의 홈이 형성됨)로 다양하게 제작할 수도 있다.In addition, according to the characteristics of the manhole in which the concrete structures are installed, the diameter, the height, and the water supply pipe direction (for example, the concrete structure applied to the bi-type water supply pipe are formed with two grooves aligned with the direction of the water supply pipe). In addition, the concrete structure applied to the tri- or tetra-type water supply pipe may be variously manufactured by three or four grooves).
상기 기초 콘크리트판(10)에는 상기 하부 콘크리트관(20)의 하단부가 끼워 맞춰지는 정착홈(12)이 형성된다.The foundation concrete plate 10 is formed with a fixing groove 12 to which the lower end of the lower concrete pipe 20 is fitted.
상기 기초 콘크리트판(10)의 하면에 부착되는 잭(11)은 나사식으로 승하강되는 것을 사용하고 있으며, 이 나사식 잭(11)은 기초 콘크리트판(10)의 수평을 유지시킬 수 있는 위치의 4곳에 부착된다.Jack 11 attached to the lower surface of the base concrete plate 10 is used to lift and lower by a screw type, the screw jack 11 is a position that can maintain the horizontal level of the base concrete plate 10 It is attached to 4 places of.
상기 하부 콘크리트관(20)의 상단부와 상기 중간부 콘크리트관(30)의 상하단부 및 상기 상층부 콘크리트관(40)들의 상하단부에는 그것들이 적층되었을 때 상호 정합되는 단턱부(a)가 외주연을 따라 형성된다.The upper and lower ends of the lower concrete pipe 20 and the upper and lower ends of the intermediate concrete pipe 30 and the upper and lower ends of the upper concrete pipes 40, when they are stacked, a stepped portion (a) that is mutually matched to the outer periphery Formed accordingly.
본발명에 의한 상수도 맨홀의 시공방법은 상기와 같은 콘크리트 구조체를 이용하여서, a)기초 콘크리트판 설치단계 - b)하부 콘크리트관 설치단계 - c)하부 콘크리트관 높이조절단계 - d)바닥 콘크리트재 채움단계 - e)중간부 콘크리트관 설치단계 - f)상층부 콘크리트관 설치단계 - g)굴착부 포장단계를 순차적으로 진행하여서 완료된다.Water treatment manhole construction method according to the present invention using a concrete structure as described above, a) foundation concrete plate installation step-b) bottom concrete pipe installation step-c) bottom concrete pipe height adjustment step-d) floor concrete material filling Step-e) middle concrete pipe installation step-f) upper concrete pipe installation step-g) excavation paving step is completed in order to complete.
도2는 본발명의 콘크리트 구조체를 이용하여서 구축한 상수도 맨홀의 측단면 구성을 예시하고 있다. 도3은 2지형 상수관에 본발명이 적용된 맨홀의 평면구성을 나타내고 있으며, 도4는 3지형 상수관이 적용된 맨홀, 도5는 4지형 상수관이 적용된 맨홀의 평면구성을 예시하고 있다.Figure 2 illustrates a side cross-sectional configuration of the water supply manhole constructed using the concrete structure of the present invention. Figure 3 shows a planar configuration of the manhole to which the present invention is applied to the two-terrain water pipe, Figure 4 illustrates a planar configuration of the manhole to which the three-terrain water pipe is applied, and Figure 5 is a manhole to which the four-hole water pipe is applied.
이들 도면을 참조하여 본발명의 시공방법을 상세히 설명한다.The construction method of this invention is demonstrated in detail with reference to these drawings.
a) 기초콘크리판 설치단계는 상수관(1)이 매설되는 관로에서 제수변(2)이 설치될 지점의 지반을 소요깊이로 굴착하고, 상수관(1)에 제수변(2)을 연결시킨 상태에서, 높이조절용 잭(11)이 하면에 부착된 상태로 공장에서 제작된 기초 콘크리트판(10)을 상기 제수변(2)의 중앙 하부에 위치시킨 후 굴착부(3) 바닥에 상기 잭 (11)을 지지시키는 작업을 통하여 수행된다.a) The basic concrete installation step is to excavate the ground at the point where the distillation side (2) is to be installed in the pipeline where the water supply pipe (1) is embedded, and to connect the distillation side (2) to the water supply pipe (1). Position the base concrete plate 10 manufactured at the factory in the state in which the height adjustment jack 11 is attached to the lower surface of the dilution side 2, and then the jack 11 at the bottom of the excavation part 3. It is done through supporting work.
b) 하부 콘크리트관 설치단계는 상기 상수관(1)이 위에서 지나가는 자리에 반원형 상측홈(21)이 난 하부 콘크리트관(20)을 상기 상수관(1)과 기초 콘크리트판 (10)의 사이에 넣고 상기 기초 콘크리트판(10)의 상부에 얹어서 정착시키는 작업을 수행하여서 이루어진다. 이때, 상기 기초 콘크리트판(10)의 중앙에 형성되어 있는 정착홈(12)에 상기 하부 콘크리트관(20)의 하단부를 끼워 맞춰 조립하게 된다.b) The lower concrete pipe installation step is to place the lower concrete pipe 20 with a semicircular upper groove 21 between the water pipe 1 and the base concrete plate 10 at the place where the water pipe 1 passes from above. Put and put on the upper portion of the base concrete plate 10 is made by performing the operation to fix. At this time, the lower end of the lower concrete pipe 20 is fitted into the fixing groove 12 formed in the center of the base concrete plate 10 is assembled.
c) 하부 콘크리트관 높이조절단계는 상기 기초 콘크리트판(10)의 하부에 장착된 높이조절용 잭(11)을 동작시켜 상기 기초 콘크리트판(10) 및 하부 콘크리트관(20)을 들어올려 상기 상측홈(21)과 상수관(1)을 끼워 맞추는 작업을 통하여 이루어진다.c) lower concrete pipe height adjusting step is to operate the height adjustment jack 11 mounted on the lower portion of the base concrete plate 10 to lift the base concrete plate 10 and the lower concrete pipe 20 to the upper groove This is achieved by fitting 21 and the water pipe 1 together.
d) 바닥 콘크리트재 채움단계는 상기 높이조절용 잭(11)에 의해 형성된 상기 기초 콘크리트판(10)과 굴착부(3) 바닥과의 사이에 미경화된 바닥 콘크리트재(50)를 채워 넣는 작업을 통하여 이루어진다. 이때, 상기 높이조절용 잭(11)은 바닥 콘크리트재(50)에 의해 매립된다.d) filling the floor concrete material is to fill the uncured floor concrete material 50 between the base concrete plate 10 formed by the height adjustment jack 11 and the bottom of the excavation part 3; Is done through. At this time, the height adjustment jack 11 is buried by the bottom concrete material (50).
e) 중간부 콘크리트관 설치단계는 상기 상수관(1)이 아래에서 지나가는 자리에 반원형 하측홈(31)이 난 중간부 콘크리트관(30)을 상기 상수관(1)에 그 하측홈 (31)을 끼워 맞추면서 상기 하부 콘크리트관(20)의 상단에 얹어서 접속시킴으로써 이루어진다. 이때, 콘크리트관들의 상하부에 형성된 단턱부(a)를 끼워 맞춰 조립하게 된다.e) The intermediate concrete pipe installation step is to place the intermediate concrete pipe 30 with a semi-circular lower groove 31 in the place where the water pipe (1) passes from the bottom groove 31 to the water pipe (1) It is made by putting the upper concrete tube 20 on top of the fitting while fitting. At this time, by fitting the stepped portion (a) formed in the upper and lower parts of the concrete pipes are assembled.
f) 상층부 콘크리트관 설치단계는 상기 중간부 콘크리트관(30)의 상부에 상층부 콘크리트관(40)들을 연이어 접속시키면서 포장면까지 적층시키는 작업을 수행하는 단계이다. 이때 최상층에 설치되는 상층부 콘크리트관(40)은 높이변화 및 철덮개(60)의 규격에 따라 원뿔대형으로 맞춰서 제작된 것을 사용한다.f) The installation of the upper concrete pipe is a step of stacking up to the pavement surface while connecting the upper concrete pipes 40 to the upper portion of the intermediate concrete pipe 30 in succession. At this time, the upper concrete pipe 40 is installed on the top floor is used to produce a truncated cone-shaped according to the height change and the standard of the iron cover (60).
g) 굴착부 포장단계는 상기 상층부 콘크리트관(40)의 최상부에 철덮개(60)를 씌우고 굴착부(3)를 복구하면서 포장층을 형성하는 마무리 단계이다.g) Excavation paving step is a finishing step of forming a pavement layer while covering the top of the upper concrete pipe 40, the iron cover 60 and recovering the excavation (3).
이상과 같이 본발명은 공장에서 제작된 프리캐스트 콘크리트 구조체들을 이용하여서 현장에서는 조립설치하기만 하면 맨홀의 구축이 완료된다.As described above, the present invention is completed by using the precast concrete structures manufactured in the factory, the construction of the manhole is completed by simply assembling and installing in the field.
따라서, 종래 현장타설에 의한 방법은 약20일이 소요되나, 본발명은 1일이면충분하므로 공기가 대폭적으로 단축된다.Therefore, the conventional method of cast in place takes about 20 days, but the present invention is enough in one day, so the air is greatly shortened.
한편, 본발명에 의한 상수도 맨홀을 시공함에 있어서, 상기 하부 콘크리트관 (20)이 기초 콘크리트판(10)에 정착되는 부분, 상기 상수관(1)이 하부 및 중간부 콘크리트관(20)(30)에 끼워지는 상,하측홈(21)(31) 부분, 상기 하부 콘크리트관 (20)과 중간부 콘크리트관(30) 및 상층부 콘크리트관(40)들이 접속되는 부분들은, 지수팽창제(71)를 삽입한 후 고강도 콘크리트 접합제(72)로 접합하여서 수밀성을 확보시키게 된다.On the other hand, in the construction of the water supply manhole according to the present invention, the lower concrete pipe 20 is a part fixed to the base concrete plate 10, the water pipe 1 is the lower and middle concrete pipe 20, 30 The upper and lower grooves 21 and 31 to be fitted into the portion, the lower concrete pipe 20 and the intermediate concrete pipe 30 and the portion where the upper concrete pipe 40 is connected, the expansive expansion agent 71 After inserting it is bonded with a high-strength concrete binder (72) to ensure watertightness.
또한, 상기 하부, 중간부 및 상층부 콘크리트관(20)(30)(40)들이 접속되는 부분들에는 다수의 고정편(73)들을 일정간격으로 배치하고, 그 고정편(73)들을 볼트로 고정시켜서 접속력을 증대시키게 된다.In addition, a plurality of fixing pieces 73 are arranged at predetermined intervals in the portions to which the lower, middle and upper concrete pipes 20, 30 and 40 are connected, and fixing the fixing pieces 73 with bolts. This increases the connection power.
따라서, 본발명에 의해 완성된 맨홀은 각 구조체들의 연결부위에 지수팽창제가 삽입되고 고강도 콘크리트 접합제로 접합되는 한편, 고정편들에 의해 결속되는 3중 접합구조를 갖기 때문에 토압, 상재하중에 의해 파손될 염려가 없고 누수가 완전히 방지되는 고품질의 상수도 맨홀을 구현하게 된다.Therefore, the manhole completed by the present invention has a triple joint structure in which an expansive agent is inserted into the connection portion of each structure and joined with a high-strength concrete binder, and is bound by the fastening pieces, and thus can not be damaged by earth pressure and load. High quality tap water manholes without worry and leakage are completely prevented.
이상에서 살펴본 바와 같이 본발명의 상수도 맨홀용 프리캐스트 콘크리트 구조체 및 그것을 이용한 상수도 맨홀의 시공방법은, 기본적으로 공장에서 기성된 콘크리트 구조체를 이용하여 일체화된 맨홀을 얻게 되므로 맨홀의 내부에 누수가 발생될 염려가 없는 고품질을 확실하게 보장받을 수 있을 뿐만 아니라, 현장 시공이 대단히 간편하다.As described above, the construction method of the precast concrete structure for the water supply manhole of the present invention and the water supply manhole using the same, since the integrated manhole is basically obtained using the concrete structure established in the factory, water leakage may occur inside the manhole. Not only can the high quality be guaranteed without worry, and the construction is very easy.
따라서, 본발명에 의하면 현장에서의 공사기간이 대폭적으로 단축되며, 공기단축에 따라 시민의 불편이 해소되고, 안전사고의 발생 우려가 제거되며, 충분한 경제성이 확보(종래기술에 비해 약 40%의 공사비 절감효과)되는 등의 여러 효과를 갖는 매우 유용한 발명이다.Therefore, according to the present invention, the construction period at the site is drastically shortened, the inconvenience of citizens is eliminated due to the shortening of air, the possibility of occurrence of safety accident is eliminated, and sufficient economic efficiency is secured (approximately 40% of conventional technology). It is a very useful invention having various effects such as cost reduction effect.
Claims (6)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2000-0051349A KR100389054B1 (en) | 2000-08-31 | 2000-08-31 | Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR10-2000-0051349A KR100389054B1 (en) | 2000-08-31 | 2000-08-31 | Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR2020000024798U Division KR200214391Y1 (en) | 2000-08-31 | 2000-08-31 | Precast Concrete Structure for Manhole |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20020017835A KR20020017835A (en) | 2002-03-07 |
KR100389054B1 true KR100389054B1 (en) | 2003-07-16 |
Family
ID=19686586
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR10-2000-0051349A KR100389054B1 (en) | 2000-08-31 | 2000-08-31 | Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100389054B1 (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100834776B1 (en) | 2007-02-21 | 2008-06-05 | 이용희 | Multi layer manhole |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100743242B1 (en) * | 2007-01-09 | 2007-07-27 | (주)고려엔지니어링 | Sinkging method of sink using precast |
KR100804783B1 (en) * | 2007-08-17 | 2008-02-20 | (주)한국폴리텍 | Assembly manhole |
CN104099946B (en) * | 2014-06-20 | 2016-06-15 | 广州市市政工程设计研究总院 | Inspection-pit between a kind of Novel top pipeline section |
CN110847240B (en) * | 2019-12-23 | 2021-05-25 | 德州市公路工程总公司 | Inspection well in roadway and construction method |
-
2000
- 2000-08-31 KR KR10-2000-0051349A patent/KR100389054B1/en active IP Right Grant
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100834776B1 (en) | 2007-02-21 | 2008-06-05 | 이용희 | Multi layer manhole |
Also Published As
Publication number | Publication date |
---|---|
KR20020017835A (en) | 2002-03-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101193896B1 (en) | Pc wall with ancher wire for structrue | |
CN109914472B (en) | Soft soil area assembled comprehensive pipe gallery and construction method thereof | |
KR102431393B1 (en) | Construction Method of Underground Structures | |
CN113668612A (en) | Modular combined prefabricated electric power working well and construction method thereof | |
KR100938395B1 (en) | The Construction Method of Underpass using Steel-Concrete Composite Wall Pile | |
CN107558501B (en) | Construction method for reserved joint structure of underground passage free from later excavation | |
KR101167511B1 (en) | Underpass using precast concrete pile and method for constructing the same | |
KR100389054B1 (en) | Precast Concrete Structure for Manhole and Construction Method of Manhole for using It's Thereof | |
CN112012763B (en) | Construction method of double-layer primary support multi-arch tunnel structure | |
KR100413001B1 (en) | A valve room struture and method of constructing valve room to make use of compositeness construction material | |
KR200214391Y1 (en) | Precast Concrete Structure for Manhole | |
KR101526461B1 (en) | Functional precast concrete culvert | |
KR200428388Y1 (en) | Power transmission manhole | |
JP5022150B2 (en) | Tunnel merge structure and method for constructing tunnel merge structure | |
KR101524272B1 (en) | A repairing assembled structure precast-manhole and constructing method it | |
KR100499338B1 (en) | Conduit using phc pile | |
CN109826229B (en) | Concrete pile for constructing side wall of assembled pipe gallery | |
KR200275363Y1 (en) | The mold establishment necessit do not exist assembly road water pipe | |
JP2012251292A (en) | Pile foundation structure of outdoor facility and construction method for the same | |
KR100302684B1 (en) | A method of constructing valve room | |
KR200277616Y1 (en) | The precast concrete prefabricated of road water supply undertrain | |
KR200167817Y1 (en) | A positioning device for manhole cover | |
CN218027861U (en) | A prefabricated assembly quality for post-cast strip is as construction passageway | |
KR100377690B1 (en) | A valve room structure and method of constructing valve room | |
CN215630142U (en) | Modular combined prefabricated electric power working well |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
N231 | Notification of change of applicant | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130614 Year of fee payment: 11 |
|
FPAY | Annual fee payment |
Payment date: 20140613 Year of fee payment: 12 |
|
FPAY | Annual fee payment |
Payment date: 20150616 Year of fee payment: 13 |
|
FPAY | Annual fee payment |
Payment date: 20160614 Year of fee payment: 14 |
|
FPAY | Annual fee payment |
Payment date: 20170614 Year of fee payment: 15 |