JPS63103121A - Field piling work - Google Patents
Field piling workInfo
- Publication number
- JPS63103121A JPS63103121A JP24704486A JP24704486A JPS63103121A JP S63103121 A JPS63103121 A JP S63103121A JP 24704486 A JP24704486 A JP 24704486A JP 24704486 A JP24704486 A JP 24704486A JP S63103121 A JPS63103121 A JP S63103121A
- Authority
- JP
- Japan
- Prior art keywords
- hole
- pile
- pit
- excavated
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 28
- 239000004567 concrete Substances 0.000 claims abstract description 27
- 239000002689 soil Substances 0.000 claims abstract description 26
- 238000000034 method Methods 0.000 claims abstract description 6
- 238000010276 construction Methods 0.000 claims description 8
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 238000004898 kneading Methods 0.000 claims description 4
- 238000007599 discharging Methods 0.000 claims 1
- 239000010802 sludge Substances 0.000 claims 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 8
- 238000005728 strengthening Methods 0.000 abstract description 4
- 238000003756 stirring Methods 0.000 abstract description 3
- 238000009412 basement excavation Methods 0.000 abstract description 2
- 102000001999 Transcription Factor Pit-1 Human genes 0.000 abstract 5
- 108010040742 Transcription Factor Pit-1 Proteins 0.000 abstract 5
- 230000015556 catabolic process Effects 0.000 abstract 1
- 238000006731 degradation reaction Methods 0.000 abstract 1
- 239000002131 composite material Substances 0.000 description 8
- 239000008267 milk Substances 0.000 description 4
- 210000004080 milk Anatomy 0.000 description 4
- 235000013336 milk Nutrition 0.000 description 4
- 239000000440 bentonite Substances 0.000 description 3
- 229910000278 bentonite Inorganic materials 0.000 description 3
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 3
- 230000000694 effects Effects 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 239000004568 cement Substances 0.000 description 2
- RYGMFSIKBFXOCR-UHFFFAOYSA-N Copper Chemical compound [Cu] RYGMFSIKBFXOCR-UHFFFAOYSA-N 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 229910052802 copper Inorganic materials 0.000 description 1
- 239000010949 copper Substances 0.000 description 1
- 238000005553 drilling Methods 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 230000032258 transport Effects 0.000 description 1
- 230000003313 weakening effect Effects 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
【発明の詳細な説明】
(産業上の利用分野)
この発明は基礎工事現場において、鉄筋コンクリートく
いを構築する方法に関するもので、基礎くい工事の分野
で利用される。DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method for constructing reinforced concrete piles at a foundation construction site, and is used in the field of foundation pile construction.
(従来の技術)
従来基礎くい設置に関しては、くい設置予定地にくい穴
壁を強化しつつ、くい穴を掘削し、該くい穴に既製コン
クリートくいを埋設する方法(特公明58−4128号
)が知られている。(Prior art) Regarding the conventional foundation pile installation, there is a method (Japanese Patent Publication No. 58-4128) of excavating a pile hole and burying a ready-made concrete pile in the hole while strengthening the wall of the hole where the pile is planned to be installed. Are known.
次に現場にコンクリートくいを構築するには、スクリュ
ーオーガーを用いて掘削土を排土し、くい穴内へベント
ナイトを入れた後、鉄筋篭を挿入し、ついでベントナイ
トとコンクリートとを置換する現場コンクリートくいの
構築工法も知られている。Next, to construct a concrete pile on site, the excavated soil is removed using a screw auger, bentonite is poured into the pile hole, a reinforcing bar cage is inserted, and then the bentonite and concrete are replaced with the concrete pile on site. Construction methods are also known.
(発明により解決すべき問題点)
前記既製コンクリートくいの設置工法は、騒音が比較的
少なく、排上等の処理も比較的少なくてすむので、各所
で多用されている。(Problems to be Solved by the Invention) The installation method of ready-made concrete piles is widely used in various places because it generates relatively little noise and requires relatively little treatment such as evacuation.
然し乍ら既製くいは、強度的信頼度が大きい反面、生産
工場から、工事現場まで運搬しなければならないので、
運搬中にくいに掛る曲げ応力に耐える為に、基礎くいが
本来必要とする応力以上に補強する必要(多量の鉄筋を
入れ、又は張力をかけた鋼材を入れる)とするのみなら
ず、重量その他の制約があるので、長い(例えば20m
以上)、太い(例えば直径1m前後)くいは使用できな
い間H点があった。However, although ready-made piles have high strength and reliability, they must be transported from the production factory to the construction site.
In order to withstand the bending stress that is applied to the piles during transportation, it is not only necessary to reinforce the foundation piles beyond the stress that is originally required (by inserting a large amount of reinforcing bars or tensile steel), but also to strengthen them due to weight and other factors. Due to restrictions, it is long (e.g. 20m)
(above), there was a point H while thick piles (for example, around 1 m in diameter) could not be used.
また従来の現場構築くいにあっては、全排土を必要とし
、くい穴掘削時に穴壁がjlL易い問題点があった。In addition, conventional on-site construction piles require the removal of all the earth, and there is a problem in that the hole wall is easily damaged when the pile hole is excavated.
(問題点を解決する為の手段)
然るにこの発明は、くい穴掘削時に、掘削土をくい穴壁
に加圧練りっけを行って、掘削土の排出量を著しく軽減
すると共に、くい穴壁を強化してくい六の崩壊を未然に
防止することに成功しな。(Means for Solving the Problems) However, the present invention significantly reduces the amount of excavated soil by pressurizing and kneading the excavated soil onto the walls of the pit during excavation, and at the same time, the amount of excavated soil is significantly reduced. Succeed in preventing Kuiroku's collapse by strengthening it.
またくい穴底部付近に溜ったスライムを可及的に除去す
ることによって、構築コンクリートくいの下部付近の脆
弱化を未然に防止し、強度的信頼度の高い基礎くいのt
i築設置に成功しなのである。In addition, by removing as much slime that has accumulated near the bottom of the pile hole as possible, weakening of the bottom of the concrete pile can be prevented, resulting in a foundation pile with high strength and reliability.
The installation was successful.
即ちこの発明は、コンクリートくい設置予定地に、穴壁
を強化し乍ら所定深さのくい穴を掘り、ついでくい穴下
部に溜ったスライムを可及的に除去した後、鉄筋篭を挿
入し、然る後、くい穴内にコンクリートを充填して現場
くいを構築する方法である。That is, this invention involves digging a hole to a predetermined depth at a site where concrete piles are to be installed, strengthening the hole wall, removing as much slime as possible from the bottom of the hole, and then inserting a reinforcing bar cage. After that, concrete is filled into the pile hole and the pile is constructed on site.
前記において、穴壁の強化は例えば掘削土を破砕して泥
化し、これを回転ドラムなどにより穴壁へ練りつける。In the above, the hole walls are reinforced by, for example, crushing the excavated soil and turning it into mud, and kneading this into the hole walls using a rotating drum or the like.
これによって掘削土の相当多量部分を練りつけることに
よって排土が少なくなると共に、くい穴壁を補強する。By kneading a considerable portion of the excavated soil, the amount of soil removed is reduced and the walls of the pit are reinforced.
またスライムの除去は、アースオーガーの先端に付属さ
せた螺旋羽根を利用して(螺旋羽根に掘削土が付着する
ので、そのまま引き上げることによる)排出する場合と
、排出管を用いて吸引排除する場合とある。In addition, slime can be removed by using a spiral blade attached to the tip of the earth auger (excavated soil will stick to the spiral blade, so just pull it up), or by suctioning it using a discharge pipe. a.
前記における鉄筋篭は、上下端板間に鉄筋を等間隔に配
置、該鉄筋の外周に螺筋を、又はフープ筋周繞して構成
したもの、又は上下端板のないもの、又は上部端板と下
部m管鍔との間に鉄筋を等rgjrWJに配置し、該鉄
筋に螺筋、又はフープ筋を周繞固定した鉄筋篭、或いは
上又は下へコンクリート筒を連結しなものがある。The above-mentioned reinforcing bar cage is constructed by placing reinforcing bars at equal intervals between upper and lower end plates, and having spiral bars or hoop bars surrounding the outer periphery of the reinforcing bars, or having no upper and lower end plates, or having an upper end plate. There are reinforcing bars arranged at equal rgjrWJ between the lower m-tube collar and a reinforcing cage with screw bars or hoop bars fixed around the reinforcing bars, or a concrete tube connected above or below.
U記のように、くい六の底部スライムを除去することに
よって、現場構築のコンクリートくいのこの発明によれ
ば、くい穴掘削時に、掘削土を破砕して穴壁へ練りつけ
るので、穴壁を補強し、その崩壊を防止することができ
る。またくい大底のスライムを排除するので、コンクリ
ートくいの全長強度を均等に保つことができる。According to the invention of the concrete pile built on site, by removing the slime at the bottom of the pile as described in U, when excavating a pile hole, the excavated soil is crushed and kneaded into the hole wall, so the hole wall is It can be reinforced and prevented from collapsing. Since the slime at the bottom of the pile is removed, the strength of the entire length of the concrete pile can be maintained evenly.
(実施例1)
゛ 次にこの発明の実施例を第1図乃至第3図について
説明する。(Embodiment 1) Next, an embodiment of the present invention will be described with reference to FIGS. 1 to 3.
先づアースオーガー1を用いてコンクリートくい構築予
定地へくい穴2を掘削する。この場合のアースオーガー
1は、中空軸3の上下適当箇所に掘削すべきくい穴2の
内径とほぼ等しい外径のドラム4.4aが固定してあり
、各ドラム間には撹拌羽根5.5が放射状、かつ上下千
鳥状に突設され、下端にオーガー刃6と補助螺旋7とが
順次設けである。前記オーガー刃6は、くい穴2の掘削
用であって、その外径はくい穴2の径より若干小さく、
補助螺旋はオーガー刃6による掘削土を、若干距離(例
えば50G〜Lm)上方へ移送するスクリューコンベア
である。First, using the earth auger 1, a hole 2 is excavated at the site where the concrete pile is to be constructed. In the earth auger 1 in this case, drums 4.4a having an outer diameter approximately equal to the inner diameter of the hole 2 to be drilled are fixed at appropriate positions above and below the hollow shaft 3, and stirring blades 5.5a are installed between each drum. are protruded radially and vertically in a staggered manner, and an auger blade 6 and an auxiliary spiral 7 are sequentially provided at the lower end. The auger blade 6 is used for digging the hole 2, and its outer diameter is slightly smaller than the diameter of the hole 2.
The auxiliary spiral is a screw conveyor that transports the soil excavated by the auger blade 6 upward by a certain distance (for example, 50 G to Lm).
前記中空軸3は、アースオーガー1に係る回転力に耐え
得ると共に、内側を加圧水又はセメント “ミルクが流
送できるようになっている。The hollow shaft 3 is capable of withstanding the rotational force of the earth auger 1, and allows pressurized water or cement milk to flow inside.
前記において、掘削機のやぐらに直立支持したアースオ
ーガー1を回転すると、予定地面はオーガー刃6によっ
て逐次掘削され、オーガー刃6が下降するにつれてくい
六が掘削される。この場合に掘削土は、補助螺旋7によ
って上方へ運ばれ、ついで撹拌羽根5.5により破砕さ
れ、ドラム4.4aの回転につれてくい穴壁側へ加圧さ
れつつ練りつけられる。掘削土の土質によっても異なる
が、相当多産の掘削土が練りつけられる。前記オーガー
刃6の掘削時に、中空軸3の下端から適量の水を噴射れ
ば、オーガー刃6の掘削を円滑にすることができると共
に、掘削土を泥土化して、ドラム4.4aによる練り付
けを一層容易にすることができる。またくい穴2内に噴
出水が溜れば、余剰水は泥水となって溢出し、若干の自
動排土ができることになる。前記のようにして、予定深
さまで掘進したならば、アースオーガー1からの水を噴
出しつつ、オーガー刃に土を固着したまま引き上げると
、補助螺旋に詰った土が恰もくい穴2の栓のようになっ
て、補助螺旋7から上の掘削土およびスライムを引き上
げ、引つづきくい穴2外へ排出することになる。前記に
おいて、水に代えてセメントミルク又はベントナイト、
又はこれら置換材の複合物を中空軸から噴出すれば、オ
ーガー刃の下方がバキュームにならないので好適である
。In the above, when the earth auger 1, which is supported upright on the tower of the excavator, is rotated, the planned ground is successively excavated by the auger blade 6, and as the auger blade 6 descends, the auger 6 is excavated. In this case, the excavated soil is carried upward by the auxiliary spiral 7, is then crushed by the stirring blades 5.5, and is kneaded under pressure against the borehole wall as the drum 4.4a rotates. It depends on the quality of the excavated soil, but the excavated soil is kneaded with a fairly high yield. When excavating with the auger blade 6, if an appropriate amount of water is injected from the lower end of the hollow shaft 3, the auger blade 6 can dig smoothly, and the excavated soil can be turned into mud and kneaded by the drum 4.4a. can be made even easier. Furthermore, if the gushing water accumulates in the hole 2, the excess water will turn into muddy water and overflow, allowing some automatic soil removal. Once the earth has been excavated to the planned depth as described above, the water from the earth auger 1 is spouted out and the soil is pulled up with the soil stuck to the auger blade. In this way, the upper excavated soil and slime are pulled up from the auxiliary spiral 7 and subsequently discharged to the outside of the pile hole 2. In the above, cement milk or bentonite is used instead of water,
Alternatively, it is preferable to eject a composite of these replacement materials from a hollow shaft, since the area below the auger blade will not be vacuumed.
次に上下端板8.9に数本の鉄筋10.10を等間隔に
固定し、これに螺筋12を周繞固定してなる鉄筋篭11
を、前記くい穴2内へ挿入し、ついで生コンクリート移
送管13を注出しつつ移送管13を鉄筋篭11の内側へ
挿入し、前記移送管13がくい穴底に達しなならば、前
記移送管13がら生コンクリートを出しながら移送管1
3を次引き上げて、くい穴内へ生コンクリートを充填す
る。Next, several reinforcing bars 10.10 are fixed to the upper and lower end plates 8.9 at equal intervals, and a screw bar 12 is fixed to the reinforcing bars 12 around the periphery of the reinforcing bars 11.
into the pile hole 2, and then insert the transfer pipe 13 into the inside of the reinforcing bar basket 11 while pouring out the fresh concrete transfer pipe 13. If the transfer pipe 13 does not reach the bottom of the pile hole, the transfer pipe 13 is poured out. Transfer pipe 1 while taking out fresh concrete from pipe 13.
3, and fill the hole with ready-mixed concrete.
このようにしてくい穴2内には、鉄Ba1lが埋設され
たコンクリートくい14ができ上る。In this way, a concrete pile 14 in which iron Ba1l is buried is created in the pile hole 2.
(実施例2)
次に第4図および第5図の実施例は、前記実施例1の鉄
筋篭11に代えて、鉄筋篭15の下端に鋼管16を連結
し、複合篭17としたもので、その他の点は全て実施例
1と同様である6尚、第4図は銅管16をくい大成に到
達させた場合、第5図は鋼管16の下端をくい大成から
若干持ち上げた場合の実施例である。(Example 2) Next, in the embodiment shown in FIGS. 4 and 5, a steel pipe 16 is connected to the lower end of the reinforcing bar cage 15 in place of the reinforcing bar cage 11 of the first embodiment, thereby forming a composite cage 17. , all other points are the same as in Example 1. 6 In addition, Fig. 4 shows the case where the copper pipe 16 has reached the final stage, and Fig. 5 shows the case where the lower end of the steel pipe 16 has been lifted slightly from the final stage. This is an example.
(実施例3)
第6図乃至第8図の実施例は、くい穴を他部より大径に
拡底した場合のの実施例である。(Embodiment 3) The embodiments shown in FIGS. 6 to 8 are examples in which the bottom of the hole is enlarged to a larger diameter than other parts.
第6図は鉄筋篭11の下端が拡底部18の底面から若干
上げた場合の実施例、第7図は鉄筋篭11の下端が拡底
部18の底面に到達した場合の実施例、第8図は複合篭
17を用いた場合の実施例である。FIG. 6 shows an example in which the lower end of the reinforcing bar basket 11 is slightly raised above the bottom surface of the expanded bottom part 18, FIG. 7 shows an example in which the lower end of the reinforcing bar cage 11 reaches the bottom surface of the expanded bottom part 18, and FIG. 8 This is an example in which a composite basket 17 is used.
前記実施例中、複合篭17を用いたものは、鋼管16の
補強によってコンクリートくい先端の強度を増強するこ
とができる。Among the above embodiments, in the case where the composite basket 17 is used, the strength of the tip of the concrete pile can be increased by reinforcing the steel pipe 16.
(実施例4)
第9図の実施例は、鉄筋の上端にコンクリ−I・筒20
を接続したもので、その他の点についてはる。(Example 4) In the example shown in Fig. 9, concrete I/tube 20
The other points are as follows.
(発明の効果)
この発明によれば、掘削土をくい穴壁へ圧密諌つつけて
補強するので、くい穴掘削後、コンクリート打設までに
崩壊するおそれがなく、掘削土の排出量も少なくてすむ
効果がある。またくい底のスライムを可及的に排除する
ので、スライムに起因するコンクリートくいの強度低下
を未然に防止し得る効果がある。(Effects of the Invention) According to this invention, since the excavated soil is consolidated and reinforced to the wall of the pile hole, there is no risk of collapse after the pile hole is excavated and before concrete is poured, and the amount of excavated soil discharged is also small. It has a soothing effect. Furthermore, since the slime at the bottom of the pile is removed as much as possible, it has the effect of preventing a decrease in the strength of concrete piles caused by slime.
図はこの発明の実施例を示すもので、第1図はくい穴掘
削時の断面図、第2図は同じく鉄筋篭を挿入し、コンク
リートミルクを注入した時の断面図、第3図は同じくく
い穴の横断平面図、第4図は同じく複合篭を用いた実施
例の断面図、第5図は同じく複合篭の下端をくい底より
若干上に引き上げた実施例の断面図、第6図は同じく拡
底の実施例の断面図、第7図は拡底の実施例で鉄筋篭を
くい底に当接した実施例の断面図、第8図は同じく複合
篭を用いた実施例の断面図第9図は同じく囃
コンクリート筒を用いた複合基の実施例の断面図 ゛で
ある。The figures show examples of the present invention. Figure 1 is a cross-sectional view when drilling a hole, Figure 2 is a cross-sectional view when a reinforcing cage is inserted and concrete milk is poured, and Figure 3 is a cross-sectional view when concrete milk is poured. 4 is a cross-sectional view of an embodiment using a composite cage; FIG. 5 is a sectional view of an embodiment in which the lower end of the composite cage is raised slightly above the bottom of the stake; FIG. 6 7 is a sectional view of an embodiment with an expanded bottom, in which a reinforcing bar cage is in contact with the pile bottom, and FIG. 8 is a sectional view of an embodiment using a composite cage. Figure 9 is a cross-sectional view of an example of a composite base using a concrete pipe.
Claims (1)
乍ら所定深さのくい穴を掘り、ついでくい穴下部に溜っ
たスライムを可及的に除去した後、鉄筋篭を挿入し、然
る後、くい穴内にコンクリートを充填することを特徴と
した現場くい構築方法 2 穴壁の強化は、掘削土を破砕泥化して加圧練りつけ
により行うこととした特許請求の範囲第1項記載の現場
くい構築方法 3 スライムの除去は、アースオーガーの先端部へ泥土
を付着させたままアースオーガーを排出することにより
なした特許請求の範囲第1項記載の現場くい構築方法 4 スライムの除去は、排泥管を挿入し、吸引排除する
こととした特許請求の範囲第1項記載の現場くい構築方
法 5 鉄筋篭は、鉄筋を円周上に等間隔に配置し、該鉄筋
の外周に螺筋を周繞固定し、鉄筋端に上下端板を設け、
又は端板なしとした特許請求の範囲第1項記載の現場く
い構築方法 6 鉄筋篭は、上部端板と、下部の鋼管鍔との間に鉄筋
を等間隔に配置し、該鉄筋に螺筋を周繞固定した特許請
求の範囲第1項記載の現場くい構築方法 7 鉄筋篭は、鉄筋の上端又は下端にコンクリート筒を
連結した特許請求の範囲第1項記載の現場くい構築方法[Claims] 1. A hole of a specified depth is dug at the site where concrete piles are planned to be installed, while the walls of the hole are strengthened, and after removing as much slime as possible that has accumulated at the bottom of the hole, a reinforced cage is installed. A method for constructing piles on site 2, characterized by inserting concrete into the pile hole and then filling the hole with concrete.The patent claims that the hole wall is strengthened by crushing the excavated soil and kneading it into mud under pressure. On-site pile construction method according to claim 1 3 The slime is removed by discharging the earth auger with mud attached to the tip of the earth auger. 4 The on-site pile construction method according to claim 1, in which the slime is removed by inserting a sludge pipe and removing it by suction. A screw bar is fixed around the outer circumference of the reinforcing bar, upper and lower end plates are provided at the end of the reinforcing bar,
Or the method for constructing piles on site according to claim 1 without end plates 6 The reinforcing bar cage has reinforcing bars arranged at equal intervals between the upper end plate and the lower steel pipe collar, and the reinforcing bars are provided with screw bars. The on-site pile construction method 7 according to claim 1, in which the reinforcing bar cage is fixed around the circumference of the reinforcing bars.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24704486A JPS63103121A (en) | 1986-10-17 | 1986-10-17 | Field piling work |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP24704486A JPS63103121A (en) | 1986-10-17 | 1986-10-17 | Field piling work |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS63103121A true JPS63103121A (en) | 1988-05-07 |
Family
ID=17157576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP24704486A Pending JPS63103121A (en) | 1986-10-17 | 1986-10-17 | Field piling work |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS63103121A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63197717A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
JPS63197716A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
JPS63197718A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5549644A (en) * | 1978-10-02 | 1980-04-10 | Carrier Corp | Controller for air conditioner |
JPS56146515A (en) * | 1980-04-14 | 1981-11-14 | Sanwa Kiko Kk | Method and apparatus for burying existing pile |
-
1986
- 1986-10-17 JP JP24704486A patent/JPS63103121A/en active Pending
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5549644A (en) * | 1978-10-02 | 1980-04-10 | Carrier Corp | Controller for air conditioner |
JPS56146515A (en) * | 1980-04-14 | 1981-11-14 | Sanwa Kiko Kk | Method and apparatus for burying existing pile |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63197717A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
JPS63197716A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
JPS63197718A (en) * | 1987-02-09 | 1988-08-16 | Kajima Corp | Construction work of in-situ pile |
JPH0629509B2 (en) * | 1987-02-09 | 1994-04-20 | 鹿島建設株式会社 | Construction method of field construction pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4832535A (en) | Process for compaction-reinforcement-grouting or for decompaction-drainage and for construction of linear works and plane works in the soils | |
CN103114577A (en) | Rotary excavating hole-forming construction method for building pile foundation | |
CN110080779B (en) | Tunnel bottom karst cave treatment construction method | |
EP0370396B1 (en) | A reinforced concrete load-bearing pile with multi-branches and enlarged footings and means for forming the pile | |
JPS63103121A (en) | Field piling work | |
EP0541812B1 (en) | Construction method of improving or strengthening ground | |
KR101765879B1 (en) | Composite block for ground reinforcement and reinforceing method of the foundation bottom using the same | |
GB2132667A (en) | Method of installing precast concrete piles | |
JPH03257215A (en) | Pile constructing method | |
JPH0280710A (en) | Preparing cast-in-place concrete pile | |
JPS63226408A (en) | Construction of pile at site | |
JPS63171918A (en) | Construction of pile on site | |
CN114703848B (en) | Old pile pulling-out method | |
JP3904294B2 (en) | Underground excavation method and underground structure construction method using this method | |
JPH08177044A (en) | Constructing method of cast-in-place concrete pile and form device for molding pile head used for constructing method | |
JPH02311617A (en) | Construction of foundation pile | |
WO2023218396A1 (en) | Method of installation of a drill pile and the drill pill | |
JP3423772B2 (en) | Shaft excavation apparatus, shaft excavation method and shaft | |
KR900005913B1 (en) | Base stake inflated in bump state at lower end there of and its construction | |
JPS5924028A (en) | Setting of large-diameter casing and casing thereof | |
JPH0442493B2 (en) | ||
JPH01131717A (en) | Construction of in-situ pile | |
JPH0757947B2 (en) | Cast-in-place pile construction method | |
JPH10183613A (en) | Construction method for pile | |
JPS5955916A (en) | On-site pile construction in banking-created ground |