JPS6138066A - Assembling of suspension scaffold - Google Patents

Assembling of suspension scaffold

Info

Publication number
JPS6138066A
JPS6138066A JP16109884A JP16109884A JPS6138066A JP S6138066 A JPS6138066 A JP S6138066A JP 16109884 A JP16109884 A JP 16109884A JP 16109884 A JP16109884 A JP 16109884A JP S6138066 A JPS6138066 A JP S6138066A
Authority
JP
Japan
Prior art keywords
scaffold
divided
scaffolding
main girder
suspended
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP16109884A
Other languages
Japanese (ja)
Other versions
JPH0330671B2 (en
Inventor
鷲津 光一
渉 川喜田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Araigumi Co Ltd
Original Assignee
Araigumi Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Araigumi Co Ltd filed Critical Araigumi Co Ltd
Priority to JP16109884A priority Critical patent/JPS6138066A/en
Publication of JPS6138066A publication Critical patent/JPS6138066A/en
Publication of JPH0330671B2 publication Critical patent/JPH0330671B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Movable Scaffolding (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は高速道路など高架橋床板作業に使用する吊り足
場を高所に設置する工法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a construction method for installing suspended scaffolds at high locations for use in work on elevated bridge decks such as highways.

(従来技術) 高架橋床板作業はコンクリートまたは鋼板製のピアを最
初に道路計画にもとづいて30m乃至80mの間隔で立
設し、その上に橋梁メーカーによって主桁が設けられる
ことによってはじまる。
(Prior Art) Viaduct deck work begins by first erecting concrete or steel plate piers at intervals of 30 m to 80 m based on the road plan, and then installing main girders on top of the piers by the bridge manufacturer.

主桁は■型またはボックス型の桁材を用い、ピア上の平
面部間に架橋される。その後架橋床板作業が施工される
のであるが、この作業に先立ち、工事の安全と架橋下の
道路の安全上吊り足場を設(プることが必要である。従
来、この吊り足場の組立て工法は大略2種類あり、一つ
は最も初期的なもので、主桁の上に必要な足場材料を搬
入し、一部を該主桁の上で組み立て、主桁の下に足場板
を一枚ずつ吊り下げで主桁に固定し、該足場板を相互に
連結するものである。これに対し第2の吊り足場の組立
て工法は、持分・昭53−41892号に記載されてい
る如く、地上にて全横幅の足場をほぼ完成してこれをブ
ロックとし、ブロックごと高所に吊り上げ主桁に固縛し
、このようなブロックを縦に接続してゆくものである。
The main girder uses ■-shaped or box-shaped girder materials, and is bridged between the flat parts on the piers. Afterwards, the bridge deck work will be carried out, but prior to this work, it is necessary to install a suspended scaffold for the safety of the construction and the road under the bridge. Conventionally, the method of assembling this suspended scaffold was There are roughly two types. One is the most primitive one, in which the necessary scaffolding materials are brought in on top of the main girder, a portion is assembled on top of the main girder, and scaffolding boards are placed one by one under the main girder. It is fixed to the main girder by hanging, and the scaffold boards are connected to each other.On the other hand, the second method of assembling the suspended scaffold is to attach the scaffold to the ground, as described in Shibu-Sho 53-41892. The entire width of the scaffolding is almost completed and these blocks are hoisted to a high place and secured to the main girder, and these blocks are connected vertically.

(発明が解決しようとする問題点) 上記2種類の工法のうち、第1の工法では高所作業熟練
者によって専ら作業を行なうので作業に熟練度を必要と
する上に、この作業中は下の道路の通行が制限されるこ
とになる。また、第2の工法においては高所での足場組
立て作業は殆んどないが、地上において長時間全横幅の
道路を占領する儒れがあり、かつ広大な面積のものを水
平に吊り上げる困難性があるばかりか、この方法も地上
を長時間占領する点において交通安全上好ましくない。
(Problems to be solved by the invention) Of the two construction methods mentioned above, the first construction method requires a high level of skill because the work is carried out exclusively by people skilled in working at heights. Traffic on these roads will be restricted. In addition, although the second construction method does not involve assembling scaffolding at high places, it involves occupying the entire width of the road for a long time on the ground, and it is difficult to hoist something over a vast area horizontally. Not only that, but this method is also unfavorable in terms of traffic safety as it occupies the ground for a long period of time.

上記2m類の工法が長時間にわたり道路を占領して交通
停滞などの障害をおこすに対し、このような支障をなく
し、作業の容易性と安全性の向上を計る吊り足場の組立
て工法を意図する。
While the above-mentioned 2m construction method occupies the road for a long period of time and causes obstacles such as traffic stagnation, we intend to develop a method of assembling suspended scaffolding that eliminates such hindrances and improves ease of work and safety. .

(問題点を解決するための手段) この発明は下記工程からなることを特徴とする吊り足場
の組立て工法である。
(Means for Solving the Problems) The present invention is a method for assembling a suspended scaffold, which is characterized by comprising the following steps.

(イン間隔をおいて立設したピアの上面に渉した主桁の
下側に高所作業車によって前記主桁に直角に2条の横移
動用レールを間隔をあけて配置し、それぞれのレールに
モートルブロックを少なくとも各2個走行可能に配設す
る。
(Two rails for lateral movement are placed at right angles to the main girders with an interval between them using an aerial work vehicle under the main girders that span the top surface of the piers that are erected at intervals, and each rail At least two motor blocks are movably disposed on each side.

(ロ)床板の半分幅乃至三分の一幅の分割足場を側壁部
ごと組み立てる。
(b) Assemble divided scaffolding with half to one-third width of the floorboard including the side walls.

(ハ)該分割足場を上記モートルブロックにて吊り上げ
ると共に、吊り上げ中に上記側壁部を主桁にあてないよ
うにモートルブロックを横引きし吊り足場の所定位置に
まで該分割足場を吊り上げる。
(c) Hoist the divided scaffold with the motor block, pull the motor block sideways so that the side wall portion does not hit the main girder during lifting, and lift the divided scaffold to a predetermined position on the suspended scaffold.

(ニ)該分割足場を主桁に固定して吊り足場のほぼ片側
を完成する。
(d) Fix the divided scaffold to the main girder to complete almost one side of the suspended scaffold.

(ホ)他の片側の吊り足場は−り記(ロ)〜(ニ)に記
載と同様の手段によって完成づる。
(e) The hanging scaffolding on the other side is completed by the same means as described in (b) to (d).

(へ)両分2F+足場を中央においてクランプ金具また
は分割足場にて結合する。
(f) Join both 2F+scaffolds at the center using clamp fittings or split scaffolds.

次に本発明の吊り足場の組立て工法の手順を図によって
説明する。地上道路1上にピア2が30〜80m間隔に
立設され、ピアの柱を含む地上部分は占用帯と称して自
動車などは通行しない。
Next, the procedure for assembling a suspended scaffold according to the present invention will be explained with reference to the drawings. Piers 2 are erected on the ground road 1 at intervals of 30 to 80 m, and the above ground portion including the pillars of the pier is called a private zone and is closed to cars.

12はフェンスである。12 is a fence.

本工法は専らこの占用帯3を利用して工事をづるもので
自動車への交通妨害を最小限痘におさえるものである。
This construction method utilizes this exclusive use zone 3 exclusively for construction, thereby minimizing traffic disturbance to automobiles.

4はピアの上部平面部間を渉して設けた主桁で、■型を
用いるかボックス型の桁材を使用し架橋業者がピア上に
固定する。
4 is a main girder installed across the upper flat parts of the pier, and is fixed on the pier by a bridge construction company using a ■ type or box type girder material.

高架橋道路面とする床板は主桁の上につ(られるのであ
る。床板作業の開始に先立ち、第1図において高所作業
車11により主桁4の下側に主桁に直角に2条の横移動
用レール7を間隔をあけて配設すると共に、該レール7
のそれぞれにt−トルブロック6を各レール当り少なく
とも2個走行可能に配設する。レール7の間隔は4〜7
mとづる。@2図は上記横移動用レール7の下に分割2
.1lioを持ち込むか組み立てるもので、床板の幅の
ほぼ半分幅の分割足場10をレールの中央下方の占用帯
からホイストワイヤ8により吊り上げる。分割足場10
は側壁部(通常朝顔という)9と共に組み立てる。ホイ
ストワイヤ8は2条のレール7とそれぞれに配置したモ
ートルブロック6により4本を使用し分割足場を垂直に
品り[げる(第3図)。吊り上げ中分割足場の側壁部9
の上端がレール7に接触する前に七−トルブロック6を
横引きしレール7上を横移動しU(第4図)側壁部9と
レール7との接触をかわして吊り上げ、吊り足場として
の所定の位置に主桁4にチェノ5等によって固縛する(
第5図)、、他の半分の分割足場も同様の手順によって
吊り足場としての所定の位置に固縛しく第6〜9図)、
最後に両分側足場の中央をクランプ金具または分割足場
にて結合して吊り足場の組み立てを完了する。主桁の縦
方向については該吊り足場を連続的に接合して、完全な
吊り足場を形成することができる。そして工事が終了し
たら、この吊り足場10が解体されるが、解体する方法
は上記組立ての場合の逆の手順で行なわれる。
The deck plate that will serve as the road surface of the viaduct is installed on top of the main girder. Prior to the start of the deck work, two strips are placed on the underside of the main girder 4 at right angles to the main girder by the aerial work vehicle 11 in Figure 1. The rails 7 for lateral movement are arranged at intervals, and the rails 7
At least two T-tor blocks 6 are disposed on each rail so as to be movable. The spacing between rails 7 is 4 to 7.
Spelled as m. @2 Diagram is divided 2 below the horizontal movement rail 7 above.
.. 1io is brought in or assembled, and a divided scaffolding 10 having a width approximately half of the width of the floorboard is hoisted from the occupied zone below the center of the rail by a hoist wire 8. Split scaffolding 10
is assembled together with the side wall part (usually called morning glory) 9. Four hoist wires 8 are used to vertically move the divided scaffolding using two rails 7 and motor blocks 6 placed on each rail (Figure 3). Side wall part 9 of split scaffold during lifting
Before the upper end contacts the rail 7, pull the block 6 horizontally, move it horizontally on the rail 7, avoid contact between the side wall 9 of the U (Fig. 4) and lift it up, and use it as a suspended scaffold. Secure it to the main girder 4 in a predetermined position with a chain 5 etc. (
(Figure 5), the other half of the divided scaffold is secured in place as a hanging scaffold by the same procedure (Figures 6 to 9).
Finally, the centers of both scaffolds are connected using clamp fittings or split scaffolding to complete the assembly of the suspended scaffold. In the longitudinal direction of the main girder, the suspended scaffolds can be joined continuously to form a complete suspended scaffold. When the construction is completed, the hanging scaffold 10 is dismantled, but the dismantling method is the reverse of the above-mentioned assembly procedure.

(作用効果) 上記作業工程は地上にお1プる車輌交通の障害にならな
いピア脚部の含まれる部分、すなわち多くの場合中央分
離帯になっている占用帯で行ない、高所作業をできるだ
け少なくし、主桁下側に配設する横移動用レール及びモ
ードルゾロツクなどの取付けは高所作業車により短時間
に行イTい、高所作業車が道路上を占領する時間を短縮
し、分割足場の大きさも床板の横幅のはぼ半分程匪のも
のとしたので分割足場の吊り上げ時に交通の障害になる
範囲が小さく、もし占用帯で分割足場を組み立てる場合
でも車輌障害の範囲が小さくて済む。吊り上げ時には途
中でモートルブロックを横引きして分割足場を側方に移
動するので、分割足場の底面は地上から5m位の高さに
なっていて、高架橋床の側部下側の道路があき、吊り上
げ後主桁に分割足場を固縛プる時間が短時間に行なわれ
、道路上の交通規制時間を短時間にすることができる。
(Effects) The above work process is carried out in areas including the pier legs that do not interfere with vehicle traffic on the ground, that is, in the private area that is often a median strip, and minimize work at heights. However, the installation of the lateral movement rails and mode levers placed below the main girder can be done in a short time using an aerial work vehicle, reducing the time that the aerial work vehicle occupies the road. The size of the split scaffolding is about half the width of the floorboards, so when lifting the split scaffolding, the area that will obstruct traffic is small, and even if the split scaffolding is assembled in a private zone, the area that will cause damage to vehicles is small. It's over. During lifting, the motor blocks are pulled sideways and the divided scaffolding is moved to the side, so the bottom of the divided scaffolding is approximately 5m above the ground, and the road below the side of the viaduct floor is opened, allowing for the lifting. The time required to secure the divided scaffolding to the rear main girder is shortened, and the time required for traffic regulation on the road can be shortened.

従って、高架橋床の下の道路を使って全幅に捗る吊り足
場を製作して吊り上げていた従来のものに比し、道路の
車輌通行規制時間および範囲を著しく短縮することがで
きる。
Therefore, compared to the conventional method in which a suspension scaffold extending over the entire width of the road is manufactured and lifted using the road under the viaduct floor, the time and range of vehicle traffic restriction on the road can be significantly shortened.

このように本発明は楽な作業によって高所に確実に吊り
足場を設置することができ、その作業行程は殆んど占用
帯内の作業でまかなうことができ、かつ作業時間が短時
間で必るので地上の交通ls害の心配もなく、地上で広
い範囲の吊り足場をつくって吊り上げる場合の水平維持
手段、引き上げ手段、高所固定手段などの困難性が全く
ないという大きな効果がある。
In this way, the present invention allows suspended scaffolding to be reliably installed at high places with easy work, and most of the work can be done within the occupied zone, and the work time is short and necessary. Therefore, there is no need to worry about harm to traffic on the ground, and there is no need to worry about the difficulties of horizontal maintenance means, lifting means, and high place fixing means when building and hoisting scaffolding over a wide area on the ground.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図、第2図、第3図、第4図、第5図、第6図、第
7図、第8図および第9図【よそれぞれ本発明の作業工
程を示した正面図である。 2・・・ピア、4・・・主桁、6・・・モートルブロッ
ク、7・・・横移動用レール、9・・・側壁部、10・
・・分υ1足場、12・・・フェンス。
1, 2, 3, 4, 5, 6, 7, 8, and 9 are front views showing the working steps of the present invention, respectively. . 2... Pier, 4... Main girder, 6... Motor block, 7... Lateral movement rail, 9... Side wall part, 10...
...minute υ1 scaffold, 12...fence.

Claims (1)

【特許請求の範囲】 下記工程からなることを特徴とする吊り足場の組立て工
法。 (イ)間隔をおいて立設したピアの上面に渉した主桁の
下側に高所作業車によって前記主桁に直角に2条の横移
動用レールを間隔をあけて配置し、それぞれのレールに
モートルブロックを少なくとも各2個走行可能に配設す
る。 (ロ)床板の半分幅乃至三分の一幅の分割足場を側壁部
ごと組み立てる。 (ハ)該分割足場を上記モートルブロックにて吊り上げ
ると共に、吊り上げ中に上記側壁部を主桁にあてないよ
うにモートルブロックを横引きし吊り足場の所定位置に
まで該分割足場を吊り上げる。 (ニ)該分割足場を主桁に固定して吊り足場のほぼ片側
を完成する。 (ホ)他の片側の吊り足場は上記(ロ)〜(ニ)に記載
と同様の手段によって完成する。 (ヘ)両分割足場を中央においてクランプ金具または分
割足場にて結合する。
[Claims] A method for assembling a suspended scaffold, characterized by comprising the following steps. (b) Two lateral movement rails are placed at right angles to the main girders with an interval between them using an aerial work vehicle on the underside of the main girders that span the top surface of the piers that are erected at intervals. At least two motor blocks are disposed on each rail so as to be movable. (b) Assemble divided scaffolding with half to one-third width of the floorboard including the side walls. (c) Hoist the divided scaffold with the motor block, pull the motor block sideways so that the side wall portion does not hit the main girder during lifting, and lift the divided scaffold to a predetermined position on the suspended scaffold. (d) Fix the divided scaffold to the main girder to complete almost one side of the suspended scaffold. (E) The hanging scaffold on the other side is completed by the same means as described in (B) to (D) above. (f) Join both split scaffolds at the center using clamp fittings or split scaffolds.
JP16109884A 1984-07-30 1984-07-30 Assembling of suspension scaffold Granted JPS6138066A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16109884A JPS6138066A (en) 1984-07-30 1984-07-30 Assembling of suspension scaffold

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16109884A JPS6138066A (en) 1984-07-30 1984-07-30 Assembling of suspension scaffold

Publications (2)

Publication Number Publication Date
JPS6138066A true JPS6138066A (en) 1986-02-24
JPH0330671B2 JPH0330671B2 (en) 1991-05-01

Family

ID=15728562

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16109884A Granted JPS6138066A (en) 1984-07-30 1984-07-30 Assembling of suspension scaffold

Country Status (1)

Country Link
JP (1) JPS6138066A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273120A (en) * 1996-04-03 1997-10-21 Hiroshi Kamioka Execution method of prefabricated scaffolding for work in elevated position
JP2019007206A (en) * 2017-06-23 2019-01-17 日本橋梁株式会社 Method of installing non-scaffold for bridge inspection permanent scaffold
JP2023038515A (en) * 2021-09-07 2023-03-17 株式会社福田組 Suspended scaffold system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09273120A (en) * 1996-04-03 1997-10-21 Hiroshi Kamioka Execution method of prefabricated scaffolding for work in elevated position
JP2019007206A (en) * 2017-06-23 2019-01-17 日本橋梁株式会社 Method of installing non-scaffold for bridge inspection permanent scaffold
JP2023038515A (en) * 2021-09-07 2023-03-17 株式会社福田組 Suspended scaffold system

Also Published As

Publication number Publication date
JPH0330671B2 (en) 1991-05-01

Similar Documents

Publication Publication Date Title
JP2918475B2 (en) Pier construction method, pier dismantling method and lift-up / rotation device
JPS6138066A (en) Assembling of suspension scaffold
JP2772158B2 (en) Bridge girder erection method
JPH0312172B2 (en)
JPH0633627B2 (en) New construction method on existing facility
JPH0336362B2 (en)
JPS6124710A (en) Assembling construction of suspension scaffold
JPS6018508Y2 (en) Hanging scaffolding device
JP3138949B2 (en) How to install beam members
JP3032052U (en) Construction equipment for pier reinforcement work
JP4098581B2 (en) Overpass bridge construction method
JPH0667511U (en) Electric automatic special support lifting device
JPS621910A (en) Working vehicle for repairing bridge and its construction
JP3234442B2 (en) Building and scrap type building method
JPS5841107A (en) Traverse drawing constructing method of bridge beam
JP2003147705A (en) Constructing method for divided bridge body type traffic road
JP2004285799A (en) Construction method of bridge section side span of multi-level crossover road
JPS598875A (en) Construction of building roof
JP2627705B2 (en) Automatic frame assembly method
JPS626058A (en) Construction of working vehicle for reparing bridge
JPH049901B2 (en)
JP3867008B2 (en) Construction method of viaduct
JPS61270405A (en) Bridge maintenance apparatus
JP3035139B2 (en) Floor slab construction method for multi-story buildings
JPH05231003A (en) Construction method of building under elevated structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term