JPS6059209A - Replacing method of bridge reinforced concrete floor panel - Google Patents
Replacing method of bridge reinforced concrete floor panelInfo
- Publication number
- JPS6059209A JPS6059209A JP16563283A JP16563283A JPS6059209A JP S6059209 A JPS6059209 A JP S6059209A JP 16563283 A JP16563283 A JP 16563283A JP 16563283 A JP16563283 A JP 16563283A JP S6059209 A JPS6059209 A JP S6059209A
- Authority
- JP
- Japan
- Prior art keywords
- reinforced concrete
- flange
- slab
- concrete floor
- floor panel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】 リート床版の張替え工法に関するものである。[Detailed description of the invention] This article concerns a method for relining REIT floor slabs.
橋梁鉄筋コンクリート床版が老朽化して亀裂が生じる等
により強度上の危険が考えられる場合には、鉄筋コンク
リート床版の張替えを行う必要がある。If the reinforced concrete deck slab of a bridge is aging and cracks appear, which poses a risk to its strength, it is necessary to replace the reinforced concrete deck slab.
従来、こうした張替えの必要が生じた場合は、第1図に
示す如く主桁aのフランジa′上にジベルbを介して一
体に固定され且つ」二面にアスファルトCを敷設された
鉄筋コンクリート床版dにおいて、第2図に示すように
、liil記主桁aのみを残した状態でエアーガウジン
グ或いはコアブレーカにより鉄筋コンクリート床版dを
解体除去する。このpz、主桁aのフランジa′上部は
ジベルbによるPi.9Jトな構造を有しておりコンク
リートのみを破砕して除去するのは困難なため、ジベル
bごと切断して除去するようにしている。Conventionally, when the need for such resurfacing arose, reinforced concrete slabs were fixed integrally onto the flange a' of the main girder a via dowels b, as shown in Figure 1, and had asphalt C laid on both sides. At step d, as shown in FIG. 2, the reinforced concrete slab d is dismantled and removed using air gouging or a core breaker, leaving only the main girder a. This pz, the upper part of flange a' of main girder a is Pi. Since it has a 9J-long structure and it is difficult to crush and remove only the concrete, the concrete is cut and removed together with the dowel b.
続いて、第2図における主桁aのフランジa′上に、ジ
ベルb′を新たに固着すると共に、従来の鉄筋コンクリ
ート橋梁の建設と同様に配筋し型枠を組んでコンクリー
トを打設することにより新たな鉄筋コンクリート床版d
′を形成し、その上面にアスファルトC′を敷設するよ
うにしている。Next, dowel b' is newly fixed on flange a' of main girder a in Fig. 2, and concrete is placed by arranging reinforcement, building formwork, and pouring concrete in the same manner as in the construction of conventional reinforced concrete bridges. New reinforced concrete floor slab d
' is formed, and asphalt C' is laid on the top surface.
しかし上記従来方式においては、鉄筋コンクリート床版
dの解体に多大の手数を要し、特に主桁aのフランジa
′−L部の解体は困難であり、解体作業に時間がかかる
問題を要する。また解体後に新たな鉄筋コンクリート床
版d′を+1PJ成する際にも、配筋、型枠の設置、足
場の建設等多大の現場作業が生じて作業に時間がかかる
問題かある。このように鉄筋コンクリート床版の張替え
に長114間を要することは、その間交通を瀝断してし
まうことになるので、近年の交通事情から重要な問題と
なっている。また1111記した解体作業時に騒音が発
生して騒音公害を生じる問題も有していた。However, in the above conventional method, it takes a lot of effort to dismantle the reinforced concrete deck slab d, and especially the flange a of the main girder a.
It is difficult to dismantle the '-L section, and the disassembly work takes a long time. Furthermore, when constructing a new reinforced concrete floor slab d' by 1PJ after demolition, a large amount of on-site work such as reinforcement, installation of formwork, and construction of scaffolding is required, resulting in the problem of time-consuming work. The fact that it takes 114 hours to replace the reinforced concrete slab in this way means that traffic is cut off during that time, which has become an important problem in light of recent traffic conditions. There was also the problem of noise pollution caused by noise generated during demolition work as described in 1111.
本発明は、こうした実情に鑑みてなしたものて°、補修
を要する鉄筋コンクリート床版を、主桁のフランジの幅
方向端部より適宜内側位置において切断して吊り上げる
ことにより11」記フランジ」二部だけを残して撤去し
、続いて、予め工場等において構成しておいた鋼製又は
合成等の新法版な、l1jJ記フランジの幅方向端部上
に載置して溶接又はボルトにより固定することにより、
騒音を生じることなく、短時間に張(I工事を行うこと
を目的とする。The present invention has been made in view of the above circumstances, and by cutting and lifting a reinforced concrete slab that requires repair at an appropriate inner position from the width direction end of the flange of the main girder, the two parts of the flange shown in 11. Remove the flange, leaving only the flange, and then place it on the widthwise end of the flange made of steel or synthetic material that has been constructed in advance at a factory, etc. in the width direction, and fix it with welding or bolts. According to
The purpose is to carry out construction work in a short period of time without causing noise.
以下本発明の実施例を図面を参照しつつ説明する。Embodiments of the present invention will be described below with reference to the drawings.
第4.5図は本発明を適用する補修が必要となった鉄筋
コンクリート橋梁の−(’Aを示すもので、図中1はに
桁、1′はフランジ、2は鉄筋コンクリ−1−1木版、
3はジベル、4はアスファルトを示す。Figure 4.5 shows -('A) of a reinforced concrete bridge that required repair to which the present invention was applied. ,
3 indicates dowel and 4 indicates asphalt.
」二部構成において、鉄筋コンクリート床版2の張替え
を行うに当り、ます主桁1のフランジ1′の長手方向に
沿い、且つフランジfの両幅端部から所要の間陥(例え
ば10〜20an)たけ内側位置において鉄筋コンクリ
ート床版2を垂直にタイヤモントカッタ等によって切断
5する。また同時に、第5図に示すように平行して設け
られた主桁1,1間においても前記鉄筋コンクリート床
版2を吊り上げて運搬できる大きさになるようnI前記
9ノ断ライン5と直角方向に切断6すると共に、予め鉄
筋コンクリート床版2に取付けておいた吊ピース7等に
より吊り」−げて撤去する。この際、ff1I記フラン
ジ1′に沿う切断5は、フランジ1′のに而まで正確に
切断する必要はなく、第4図に示すようにフランジ1′
の土面に切1所されない部分を残しておいても、1)I
I記吊り土は操作により、第6図に示すようにフランジ
1′上にコンクリートブロック8を残した状態〔コンク
リートブロック8上のアスファルトは除去する〕で鉄筋
コンクリート床版2をり離して撤去することができる。In the two-part structure, when re-cladding the reinforced concrete slab 2, a recess (for example, 10 to 20 ann) must be made along the longitudinal direction of the flange 1' of the main girder 1 and from both width ends of the flange f. The reinforced concrete floor slab 2 is vertically cut 5 at the inside position of the tower using a tire cutter or the like. At the same time, as shown in FIG. 5, even between the main girders 1 and 1 installed parallel to each other, the reinforced concrete slab 2 is made large enough to be lifted and transported in the direction perpendicular to the 9 cut line 5. At the same time as cutting 6, it is lifted up using hanging pieces 7 etc. that have been attached to the reinforced concrete floor slab 2 in advance and removed. At this time, the cut 5 along the flange 1' described in ff1I does not need to be cut exactly to the flange 1', and as shown in FIG.
Even if one uncut part is left on the soil surface, 1) I
The suspended soil described in I shall be removed by removing the reinforced concrete slab 2 by operation, leaving the concrete block 8 on the flange 1' (the asphalt on the concrete block 8 will be removed), as shown in Figure 6. I can do it.
続いて、第7図に示すように、予め工場などにおいて製
作された鋼抹版又は合成床版からなる新法版9を、1)
IJ記フランジ1′上に載16する。Next, as shown in Fig. 7, a new method plate 9 consisting of a steel plate or a synthetic plate previously manufactured in a factory, etc. is 1)
16 on the IJ flange 1'.
新法1iH9は、OjJ記コシコンクリートブロック8
面に近1妥し1]つフランジ1の幅端部]−而に位置す
るようにした端面鋼板10と、+Jii記コンクリート
ブロック8の上面をも同時にモ坦に1ηうようにした上
面鋼板11を有している。上記新法版9における端面鋼
板10の下端を、フランジ1に溶1妾12にて固定する
と共に、lII記上面鋼版11.11同志を溶接じにて
固定し、その後、1ai1iit 1面鋼板11」二に
アスファルト14等を敷設する・第8図はn’+1記新
床版新法定方式の他の例を示すもので、]二二部のフラ
ンジ1′上に、新法版9の端′面鋼板10に設けたフラ
ンジ10′を介してボルト15により固定するようにし
ている。この場合、前記第4図に示した切断ライン5よ
り更に内側で鉄筋コンクリート床版2を切断することに
より、フランジ1の幅方向端部にボルト固定のためのス
ペースを確保する必要がある。New law 1iH9 is OjJ Koshi concrete block 8
An end face steel plate 10 which is located close to the width end of the flange 1 and an upper face steel plate 11 which is located at the same time as the upper face of the concrete block 8 by 1η. have. The lower end of the end steel plate 10 in the above new law version 9 is fixed to the flange 1 with welding 12, and the upper steel plate 11 and 11 described in II are fixed together by welding, and then 1ai1iit 1face steel plate 11. 2. Lay asphalt 14 etc. on the flange 1' of section 2. Figure 8 shows another example of the new legal system for the new floor slab indicated by n'+1. It is fixed with bolts 15 via a flange 10' provided on the steel plate 10. In this case, it is necessary to secure a space for bolt fixing at the widthwise end of the flange 1 by cutting the reinforced concrete slab 2 further inside the cutting line 5 shown in FIG. 4.
また、上記において、コンクリートブロック8と新法版
9との接着が必要な場合は、端面鋼板10及び上面鋼板
11に作られた穴(図示せず)より接着旧を注入して一
体に固化させることができる。更にまた、111記アス
フアルト14の敷設は、上面鋼板11の溶接13接合部
のみを残して工場等で施工しておき、溶接作業終了後に
その部分の施工を行うようにしても、或いはすべて現場
にて行うJ:うにしても良い。In addition, in the above, if it is necessary to bond the concrete block 8 and the new law version 9, adhesive may be poured into holes (not shown) made in the end steel plate 10 and the top steel plate 11 to solidify them together. I can do it. Furthermore, the asphalt 14 described in No. 111 may be laid at a factory, leaving only the welded joint 13 of the upper steel plate 11, and then that part may be laid after the welding work is completed, or the asphalt 14 may be laid entirely on-site. J: You can do it by hand.
上記実施例においては、補修を要する鉄筋コンクリート
床版2を切断して除去するようにしており、しかも解体
が因難なフランジ1土部をコンクリートブロック8とし
てそのまま残すようにしているので、除去作業を容易且
つ短時間に行うことができ、しかも騒音を発生するよう
なこともない。また、新法版9は予め工場等で製作して
おくことができるので、1)II記鉄筋コンクリ−1・
床版2を除去した後、直ちに載置、固定することができ
、よって張替え作業全体の工期を剥しく短縮することが
できる。また、複数の主桁1が並設される広い幅の橋梁
においては、一部の主桁1,1間の鉄筋コンクリート床
版2の’3M替えを行っても、他の部分の強度は損われ
ないので、車輌等の通行或いは張替え作業を行うための
運搬作業等に利用することができる。In the above embodiment, the reinforced concrete slab 2 that requires repair is cut and removed, and the earthen part of the flange 1, which would be difficult to disassemble, is left as it is as a concrete block 8, so that the removal work is not necessary. It can be done easily and in a short time, and does not generate any noise. In addition, since the new law version 9 can be manufactured in advance at a factory etc., 1) II Reinforced Concrete 1.
After the floor slab 2 is removed, it can be placed and fixed immediately, so that the overall period of re-laying work can be significantly shortened. In addition, in a wide bridge where multiple main girders 1 are installed side by side, even if the reinforced concrete slab 2 between some main girders 1 and 1 is replaced by 3M, the strength of other parts will not be impaired. Therefore, it can be used for transportation work such as passing vehicles or performing reupholstery work.
尚、本発明は上記実施例にのみ限定されるものではなく
、新法版の形状構造は種々変更し得ること、その信奉発
明の要旨を逸脱しない範囲内において種々変更を加え得
ること、等は勿論である。It should be noted that the present invention is not limited to the above-described embodiments, and it goes without saying that the shape and structure of the new law version can be changed in various ways, and that various changes can be made within the scope of the gist of the invention. It is.
」二連した本発明の橋梁鉄筋コンクリート床版の張替え
工法によれば、次のような優れた効果を奏し得る。” According to the method for re-covering reinforced concrete decks of bridges according to the present invention, the following excellent effects can be achieved.
(1)張替え作業を急速、短時間に行うことができ、よ
って張替工事に伴なう交通障害の発生を最小限に1にぬ
ることができる。(1) The re-upholstery work can be carried out quickly and in a short time, thereby minimizing traffic disturbances caused by the re-upholstering work.
(ii) 補修を要する鉄筋コンクリート床版を切断に
より除去するようにしているので、従来のような種j撃
的な騒音公害を生しることがない。(ii) Since the reinforced concrete floor slabs that require repair are removed by cutting, there is no need to cause the destructive noise pollution that occurs in the past.
Qii) 新法版を鋼製床版或いは合成床版とすること
により、橋梁の強度向−1−を容易に可能にすることが
できる。Qii) By using steel deck slabs or synthetic deck slabs as the new law slabs, it is possible to easily improve the strength of bridges.
6ψ 現場作業を著しく減少させて]:費の低減を図り
得る。6ψ By significantly reducing on-site work]: Costs can be reduced.
第1図〜第3図は従来の橋梁鉄筋コンクリート床版の張
替え工法を手順を追って示した説明図、第4図は本発明
を適用した補修を要する橋梁の部分切断ilE面図、第
5図は第4図を■方向から見た平面図、第6図は本発明
の方法において鉄筋コンクリート床版を切断除去した状
態を示す説明図、第7図は本発明の方法において第6図
における鉄筋コンクリート床版を除去されたに桁のフラ
ンジ上に新法版を載置、固定する状態を示す説明図、第
8図は新法版の固定方式の他の例を示す説明図である。
lは)ミ桁、1′はフランジ、2は鉄筋コンクリート床
版、3はジベル、5,6は切断ライン、8はコンクリー
トブロック、9は新法版、IOは端面鋼板、11は上面
鋼板、12.じは溶接、15はボルトを示す。
#1 訂 出 願 人
石川A播磨重工業株式会社
’11 、X′r++11171人代理人#、l’ ;
F″r出1頭人代理人
第3図
第7図Figures 1 to 3 are explanatory diagrams showing the conventional bridge reinforced concrete deck resurfacing method step by step, Figure 4 is a partially cutaway IE view of a bridge that requires repair to which the present invention is applied, and Figure 5 is Fig. 4 is a plan view seen from the direction ■, Fig. 6 is an explanatory diagram showing the state in which the reinforced concrete floor slab is cut and removed in the method of the present invention, and Fig. 7 is the reinforced concrete floor slab in Fig. 6 in the method of the present invention. FIG. 8 is an explanatory diagram showing a state in which the new law plate is placed and fixed on the flange of the girder from which the new law plate has been removed. FIG. 8 is an explanatory diagram showing another example of the method of fixing the new law plate. 1 is a) Migir, 1' is a flange, 2 is a reinforced concrete slab, 3 is a dowel, 5 and 6 are cutting lines, 8 is a concrete block, 9 is a new law version, IO is an end steel plate, 11 is a top steel plate, 12. 1 indicates welding, and 15 indicates bolts. #1 Revised application person Ishikawa A Harima Heavy Industries Co., Ltd. '11, X'r++11171 agent #, l';
Figure 3 Figure 7
Claims (1)
ランジに沿い且つフランジの幅方向端部より適宜内側位
置において切断して吊り上げ撤去した後、予め形成して
おいた新床版をml記フランジの幅方向端部上に載置し
て溶接又はボルト固定することを特徴とするg梁鉄筋コ
ンクリート床版の張替え工法。1] After cutting and removing the reinforced concrete slab that requires repair along the flange of the main girder at an appropriate position inside the widthwise end of the flange, the new slab that had been previously formed was placed on the ml flange. A method for resurfacing reinforced concrete deck slabs of G-beams, which is characterized by placing them on the ends in the width direction and fixing them by welding or bolts.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16563283A JPS6059209A (en) | 1983-09-08 | 1983-09-08 | Replacing method of bridge reinforced concrete floor panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP16563283A JPS6059209A (en) | 1983-09-08 | 1983-09-08 | Replacing method of bridge reinforced concrete floor panel |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS6059209A true JPS6059209A (en) | 1985-04-05 |
Family
ID=15816048
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP16563283A Pending JPS6059209A (en) | 1983-09-08 | 1983-09-08 | Replacing method of bridge reinforced concrete floor panel |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS6059209A (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6245804A (en) * | 1985-08-23 | 1987-02-27 | 石川島播磨重工業株式会社 | Re-covering of bridge reinforced concrete |
JP2010024742A (en) * | 2008-07-22 | 2010-02-04 | Active:Kk | Bridge floor slab removing method |
JP5878657B1 (en) * | 2015-03-31 | 2016-03-08 | 三井造船株式会社 | Bridge slab support structure and floor slab replacement method |
JP2017053117A (en) * | 2015-09-08 | 2017-03-16 | 新日鉄住金エンジニアリング株式会社 | Renewal method for existing road, and renewed road |
JP2017122353A (en) * | 2016-01-08 | 2017-07-13 | Jfeスチール株式会社 | Replacement method of concrete slab and replacement structure |
JP2017128841A (en) * | 2016-01-18 | 2017-07-27 | Jfeスチール株式会社 | Replacement construction method of concrete slab |
-
1983
- 1983-09-08 JP JP16563283A patent/JPS6059209A/en active Pending
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS6245804A (en) * | 1985-08-23 | 1987-02-27 | 石川島播磨重工業株式会社 | Re-covering of bridge reinforced concrete |
JP2010024742A (en) * | 2008-07-22 | 2010-02-04 | Active:Kk | Bridge floor slab removing method |
JP5878657B1 (en) * | 2015-03-31 | 2016-03-08 | 三井造船株式会社 | Bridge slab support structure and floor slab replacement method |
JP2016194215A (en) * | 2015-03-31 | 2016-11-17 | 三井造船株式会社 | Bridge deck slab support structure and replacement method of deck slab |
JP2017053117A (en) * | 2015-09-08 | 2017-03-16 | 新日鉄住金エンジニアリング株式会社 | Renewal method for existing road, and renewed road |
JP2017122353A (en) * | 2016-01-08 | 2017-07-13 | Jfeスチール株式会社 | Replacement method of concrete slab and replacement structure |
JP2017128841A (en) * | 2016-01-18 | 2017-07-27 | Jfeスチール株式会社 | Replacement construction method of concrete slab |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5266291B2 (en) | Construction method of bridge deck and joint structure of precast deck | |
JP2872346B2 (en) | Prefab slab installation method | |
JPS6059209A (en) | Replacing method of bridge reinforced concrete floor panel | |
KR20020082728A (en) | Process and frame for substituting steel girder of a railway bridge for concrete slab | |
KR19990014533A (en) | Top plate formwork structure of steel concrete structure | |
JPH06101212A (en) | Reinforcing structure for reinforced concrete floor slab | |
CN113356428A (en) | Prestress superposed integral floor system applied to fabricated building and construction method | |
JPS6245804A (en) | Re-covering of bridge reinforced concrete | |
JPH04228710A (en) | Road slab for bridge | |
JPH108429A (en) | Structure of concrete protection fence and construction method therefor | |
JPS6255306A (en) | Method for withdrawing reinforced concrete floor panel of bridge | |
JPS6282147A (en) | Novel prestressed synthetic beam and its construction | |
JPS6059210A (en) | Replacing method of bridge reinforced concrete floor panel | |
JPS6364565B2 (en) | ||
JP2861219B2 (en) | Bridge deck repair steel slab and its mounting method | |
JP2003082617A (en) | Reinforcing structure of bridge structure and method for repairing bridge structure | |
JP2007107195A (en) | Steel floor slab reinforcing construction method and precast reinforcing slab used therefor | |
KR20030029571A (en) | table form estabishment apparatus for building and estabishment method thereof | |
JPS63171906A (en) | Method for reinforcing reinforced concrete floor panel of bridge | |
JPS5858308A (en) | Repairing of bridge beam floor plate by steel floor panel | |
JP2001279853A (en) | Synthetic floor slab and half precast floor slab | |
JPS6245805A (en) | Re-covering of bridge concrete floor panel | |
JPS6314906A (en) | Construction method for re-covering bridge concrete floor panel | |
KR200240457Y1 (en) | Frame for substitu ting steel girder of a railway bridge for concrete slab | |
JP7272918B2 (en) | Existing floor slab replacement method |