[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JPS6043517A - Coffering work and tubular pile therefor - Google Patents

Coffering work and tubular pile therefor

Info

Publication number
JPS6043517A
JPS6043517A JP15269683A JP15269683A JPS6043517A JP S6043517 A JPS6043517 A JP S6043517A JP 15269683 A JP15269683 A JP 15269683A JP 15269683 A JP15269683 A JP 15269683A JP S6043517 A JPS6043517 A JP S6043517A
Authority
JP
Japan
Prior art keywords
pile
ground
pipe
water
piles
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP15269683A
Other languages
Japanese (ja)
Other versions
JPS6364570B2 (en
Inventor
Hiroshi Fukuchi
弘 福地
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIYOUHI JUKI KK
Original Assignee
JIYOUHI JUKI KK
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIYOUHI JUKI KK filed Critical JIYOUHI JUKI KK
Priority to JP15269683A priority Critical patent/JPS6043517A/en
Publication of JPS6043517A publication Critical patent/JPS6043517A/en
Publication of JPS6364570B2 publication Critical patent/JPS6364570B2/ja
Granted legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

PURPOSE:To facilitate coffering work by draining water from deep strata by a method in which a water pipe is provided near the lower end of a steel tubular pile, sheathing using the steel tubular pile is made in the ground for coffering, and water is pumped up from the bottom of the pile. CONSTITUTION:A water hole 9 is provided near the lower end of a steel tubular pile 1, and a coupler 6 is provided in the longitudinal direction of the periphery of the pile 1. The steel tubular piles 1 are connectedly driven in such a way as to surround the working area (a). A drain hose 10 having a net on its tip is inserted into the pile 1, and water coming into the pile 1 is pumped up by a pump, etc. Water can thus be drained from deep places of the ground of working area, and therefore, coffering work can be made easier.

Description

【発明の詳細な説明】 この発明は、基礎工等を行うため、地盤を掘削するいわ
ゆる根掘り工事等に際し、地盤の崩壊を防ぐと同時に、
作業区域内への水の浸入を防止する締切工事(いわゆる
山止め)の方法及びこれに使用する管状の杭に関するも
のである。
[Detailed Description of the Invention] This invention prevents the collapse of the ground when excavating the ground for foundation work, etc.
This invention relates to a method of cofferdam construction (so-called pile stoppage) to prevent water from entering the work area, and the tubular piles used for this method.

水中に橋脚等の構造物を構築する場合等に行われる締切
工事は、従来主としてシートパイルによって作業区域を
取り囲むことによって行われてきた。このシートパイル
は、通常衝撃法によって地中に圧入されるが、この場合
に問題となるのは、シートパイルの変形や損傷及びこれ
らに伴う打ち込みの困難性である。
BACKGROUND OF THE INVENTION Conventionally, cofferdam work, such as when constructing a structure such as a bridge pier underwater, has been carried out mainly by surrounding the work area with sheet piles. This sheet pile is usually press-fitted into the ground by the impact method, but the problems in this case are the deformation and damage of the sheet pile and the accompanying difficulty in driving it.

即ち、衝撃法によってシートパイルを地中に打ち込む場
合は、これに加える衝撃と共に、地盤からその反力を受
けることから、これによってシートパイル端部に亀裂や
曲げといった損傷や変形の他、座屈による変形を受けや
すい。いまシートパイルの長さをl、ヤング率をE、断
面二次モーメントをIとすると、−座屈荷重Pは、次の
通りである。
In other words, when a sheet pile is driven into the ground by the impact method, in addition to the impact applied, it receives a reaction force from the ground, which causes damage and deformation such as cracks and bending to the end of the sheet pile, as well as buckling. susceptible to deformation due to Now, assuming that the length of the sheet pile is l, the Young's modulus is E, and the moment of inertia of area is I, -buckling load P is as follows.

P=n2 π2 EI/I22 (但しn=1.2.3・・−) この式から明らかな通り、長い杭や剛性(EI)の低い
杭が比較的座屈を受けやすく、特にシートパイルは、薄
い板状のものであるから、断面二次モーメンl−1が小
さく、堅い地盤において強い衝撃を与えると簡単に曲が
ってしまうことになる。このようなことから、長いシー
トパイルでは、貫入試験でN値が50を越える地盤での
打ち込みが不可能であるとされてきた。
P=n2 π2 EI/I22 (however, n=1.2.3...-) As is clear from this equation, long piles and piles with low stiffness (EI) are relatively susceptible to buckling, and sheet piles are especially susceptible to buckling. Since it is a thin plate-like material, the moment of inertia l-1 of the cross section is small, and it will easily bend if a strong impact is applied to it on hard ground. For these reasons, it has been considered impossible to drive long sheet piles into the ground where the N value exceeds 50 in a penetration test.

また、この締切工事で問題となるものの一つに作業区間
おける湧水等の排水の問題がある。
In addition, one of the problems with this cofferdam construction is the problem of drainage of spring water, etc. in the work area.

水温基礎や水中基礎の場合はもちろんのこと、通常の地
上工事においても、掘り下げるに従って地下水等の湧水
が発生することがあることから、これを作業区間の外部
へと排水する必要がある。従来、締切工事での排水は、
根掘り底部の隅にいわゆる斎場と呼ばれる一段低く掘り
込んだ水溜を設け、これに水を導いてポンプで排水する
といった方法が採用されてきた。
Not only in the case of water-temperature foundations and submerged foundations, but also in normal above-ground construction, spring water such as groundwater may occur as the excavation is dug, so it is necessary to drain this water to the outside of the work area. Traditionally, drainage during cofferdam construction was
A method has been adopted in which a shallow water reservoir called a funeral hall is installed in the corner of the bottom of the root digging, and water is led into this and drained using a pump.

しかし、このような排水方法では、根掘り底部の水しか
排水することんかできず、さらにその下層の水を排水す
ることができない。このため、掘削する土砂が常に水を
含んでいる状態となり、掘削に困難を伴う。
However, with this drainage method, only the water at the bottom of the excavation can be drained, and furthermore, the water in the lower layer cannot be drained. For this reason, the earth and sand to be excavated always contains water, making excavation difficult.

この発明は、従来の締切工事における上記のような問題
点を解消すべくなされたものであって、堅い地盤におい
ても容易に杭を打ち込んで締切工事が行えると共に、地
盤に含まれる地下水等を相当深い所から排水を可能とし
、これによって根掘り工事等が容易に行えるようにする
ことを目的とするものである。以下、この発明の構成を
図示の実施例に基づき、詳細に説明する。
This invention was made in order to solve the above-mentioned problems in conventional cofferdam construction, and it is possible to easily drive piles and carry out cofferdam work even in hard ground, and to significantly reduce groundwater etc. contained in the ground. The purpose is to enable drainage from deep places, thereby making it easier to carry out root digging work, etc. EMBODIMENT OF THE INVENTION Hereinafter, the structure of this invention will be described in detail based on the illustrated embodiment.

この発明による締切工事では、シートパイルの代わりに
、第1図イで示すような管杭1が使用される。この管杭
1は、第3図で示すようにバイブロパイルハンマー4に
よって把持できるように鋼管2の上端に錆性のエンドグ
リップ3を溶接等により取り付けたもので、下端側には
尖鋭な推進刃5.5−・−が多数突設されている。
In the cofferdam construction according to the present invention, a pipe pile 1 as shown in FIG. 1A is used instead of a sheet pile. As shown in Fig. 3, this pipe pile 1 has a rust-resistant end grip 3 attached to the upper end of the steel pipe 2 by welding or the like so that it can be gripped by a vibropile hammer 4, and a sharp propelling blade is attached to the lower end. A large number of 5.5-- are provided protrudingly.

この推進刃5,5・−・は、例えば鋼管2の先端を切り
欠く等して、間管2と同質のもので形成してもよいが、
特に地盤が堅い場合は、刃の表面を硬質材料でコーティ
ングしたり、或いは鋼管2とは別材料の超硬チップを間
管2の先端に溶接して推進刃5,5・・−・とすること
もできる。
These propulsion blades 5, 5, etc. may be formed of the same material as the intermediate pipe 2, for example by notching the tip of the steel pipe 2, but
If the ground is particularly hard, the surface of the blade may be coated with a hard material, or a carbide tip made of a different material from the steel pipe 2 may be welded to the tip of the intermediate pipe 2 to form the propelling blades 5, 5, etc. You can also do that.

上記鋼管2の側面長手方向には、これを地中に打ち込ん
だとき、隣接する管杭1,1−・を互いに連結する継手
6,6が設けられている。この継手6.6は、嵌め込み
ゃすく、かつ打ち込みの際に外れ難く\、しかも止水性
の高いものがよく、図示の場合は、鋼管2の上下に亙っ
て丸形の継手が設けられ、第4図で示すように先端が互
いに嵌り合うことによって隣接する管杭1.1が水密状
態で連結される。
Joints 6, 6 are provided on the longitudinal side of the steel pipe 2 to connect adjacent pipe piles 1, 1- to each other when the pipe is driven into the ground. This joint 6.6 is preferably one that is easy to fit in, difficult to come off during driving, and has a high water-stopping property. As shown in FIG. 4, adjacent pipe piles 1.1 are connected in a watertight manner by fitting the tips into each other.

さらに後述するように地盤の水抜きをする管杭1につい
ては、鋼管2の適当な位置に通水孔9.9−・−・を明
けておく。
Further, as will be described later, for the pipe pile 1 for draining water from the ground, water holes 9.9 are opened at appropriate positions in the steel pipe 2.

この管杭1を地中に打ち込む場合は、通常第3図で示す
ようにバイブロパイルハンマー4によって同杭1に震動
を与えつつ地中に打ち込む。
When the pipe pile 1 is driven into the ground, it is usually driven into the ground while being vibrated by a vibropile hammer 4, as shown in FIG.

即ち、先ずクレーン7から釣り下げたバイブロパイルハ
ンマー4によってエンドグリップ3を把持して管杭1を
地上に垂直に立て、この状態で同杭1に震動を与えつつ
地中に推進させていく。
That is, first, the end grip 3 is gripped by the vibro pile hammer 4 suspended from the crane 7, and the pipe pile 1 is vertically erected on the ground, and in this state, the pile 1 is propelled into the ground while being vibrated.

そして打ち込んだ管杭1を地中から引き抜く場合は、バ
イブロパイルハンマー4によってエンドグリップ3を把
持し、この状態で僅かに震動を与えつつクレーン7によ
って上方へ引き抜く。こうして引き抜かれた管杭1の中
には、土砂が詰まっているので、クレーン7によって釣
り下げた状態のま一1管杭1に強い震動を与えることに
よってその中の土砂を排土することができる。
When the driven pipe pile 1 is to be pulled out of the ground, the end grip 3 is gripped by the vibropile hammer 4, and in this state, it is pulled upward by the crane 7 while giving a slight vibration. Since the pipe pile 1 pulled out in this way is filled with earth and sand, it is possible to remove the earth and sand by applying a strong vibration to the pipe pile 1 that is suspended by the crane 7. can.

上記のようにし゛て管杭1を打ち込む場合に、地盤から
の推進抵抗が特に強く、打ち込みにくいときは、打ち込
めるところまで管杭1を推進させたところで一旦同杭1
を引抜−き、その中から排土した後、再び同じ場所に管
杭1を差し込んでさらに打ち込むことにより、容易に同
杭1を推進させることができる。通常の場合は、これら
の作業を2〜3回程繰り返すことによって、どんな堅い
地盤でも管杭1を深いところまで打ち込むことが可能で
ある。
When driving the pipe pile 1 as described above, if the propulsion resistance from the ground is particularly strong and it is difficult to drive the pipe pile 1, once the pipe pile 1 is driven to the point where it can be driven,
After the pipe pile 1 is pulled out and the earth is removed from it, the pipe pile 1 can be easily propelled by inserting the pipe pile 1 into the same place again and driving it further. Normally, by repeating these operations two or three times, it is possible to drive the pipe pile 1 deep into any hard ground.

また、排土の際に、地盤が固結シルトのように硬い固結
層を含む場合は、管の中に入った土砂が硬く締め固めら
れ、管杭1の中から排土できない場合がある。そこでこ
ういう地盤に打ち込む場合は、鋼管2の下端側の径方向
にブレード8,8を着脱自在に取り付けるのがよく、図
示の場合は、上下に鋭い刃先を持った2本のブレード8
.8を互いに直交するよう鋼管2の下端に差し込んで取
り付けている。こうして管杭1を打ち込んだ場合、同杭
lの推進に伴って固結層の土砂が鋼管2の中に入る際に
、上記ブレード8.8が土砂を細かく砕く。このため、
管杭1を引き抜いた後、上記ブレード8,8を鋼管2か
ら引き抜くことによって、その中の土砂を鋼管2の下端
から簡単に排土することができる。
In addition, when removing soil, if the ground contains a hard consolidated layer such as consolidated silt, the soil that has entered the pipe may become hard and compacted, making it impossible to remove the soil from inside the pipe pile 1. . Therefore, when driving into this type of ground, it is best to detachably attach blades 8, 8 in the radial direction on the lower end side of the steel pipe 2. In the case shown in the figure, two blades 8 with sharp cutting edges on the top and bottom
.. 8 are inserted and attached to the lower end of the steel pipe 2 so as to be perpendicular to each other. When the pipe pile 1 is driven in this way, when the earth and sand in the consolidated layer enters the steel pipe 2 as the pile l is propelled, the blades 8.8 break the earth and sand into small pieces. For this reason,
After pulling out the pipe pile 1, by pulling out the blades 8, 8 from the steel pipe 2, the earth and sand therein can be easily removed from the lower end of the steel pipe 2.

このようにして上記の管杭1を地中に打ち込むことによ
り、従来のシートパイルでは困難であるとされていた堅
い地盤への長い杭の打ち込みが可能となった。因に第6
図は、本件発明者が試験的に打ち込みを行った地盤の柱
状図と、これに対応する貫入試験の結果をN値50まで
示したものである。この地盤は、深さ20mまでの 一
部どがN値50を越えているが、ここに長さ22m。
By driving the pipe pile 1 into the ground in this manner, it has become possible to drive long piles into hard ground, which was difficult to do with conventional sheet piles. Incidentally, the 6th
The figure shows a columnar diagram of the ground into which the inventor of the present invention has experimentally driven the ground, and the corresponding results of the penetration test up to an N value of 50. This ground has an N value of over 50 in some parts up to 20m deep, and is 22m long.

直径300寵の管杭1を日平社製の60psのバイブロ
パイルハンマーで簡単に打ち込むことができた。なお、
このときの一本当たりの打ち込み時間は概ね15〜16
分であった。
Pipe pile 1 with a diameter of 300 mm could be easily driven with a 60 ps vibro pile hammer manufactured by Nippeisha. In addition,
At this time, the driving time per piece is approximately 15-16
It was a minute.

この管杭1によって締切工事を行うには、第2図、第4
図及び第5図で示すように、いわゆる根掘りを行う一定
の作業区域aの周囲に継手6.6で継ぎ合わせながら管
杭lを打ち込み、上記区域aを取り囲む。
To carry out cofferdam work using this pipe pile 1, please refer to Figures 2 and 4.
As shown in the figures and FIG. 5, pipe piles 1 are driven around a certain work area a where so-called root digging is to be performed, while being joined by joints 6.6, to surround the area a.

こうして作業区域aを取り囲んだら、上記通水孔9,9
−を待った一部または全部の管杭1の中から土砂を取り
除き、地盤から同管杭1の中に浸入した水を揚水して、
地盤からの湧水。
After surrounding the work area a in this way, the water holes 9, 9
- Remove the earth and sand from some or all of the pipe piles 1, and pump up the water that has entered the pipe piles 1 from the ground.
Spring water from the ground.

漏水等を排水する。Drain water leakage, etc.

管杭lの中の土砂を排除する場合は、例えば管杭1の内
径より細い鋼管を使用し、これを管杭1の中に打ち込ん
だ後、静かに引き抜くことにより、管杭1の中の土砂を
その外側へ取り出すことができる。そして、鋼管に詰め
られた土砂は、間管をクレーン7で釣り下げたま\、バ
イブロパイルハンマー4で強い震動を与えることによっ
てその中から排除することができる。
To remove the earth and sand inside the pipe pile 1, for example, use a steel pipe that is thinner than the inner diameter of the pipe pile 1, drive it into the pipe pile 1, and then gently pull it out. Sediment can be taken out to the outside. The earth and sand packed in the steel pipe can be removed from the steel pipe by lowering the pipe with a crane 7 and applying strong vibrations with a vibro pile hammer 4.

中の土砂を取り除かれた管杭1では、通水孔9.9−・
からその周囲の地盤の水が浸入するため、第5図で示す
ように、先端にネット等を取り付けたホース10.10
−・・を同管杭1の中に差し込んでこれらを一本に纏め
、ポンプやバキュームウェル方式等で揚水することによ
り排水することができる。こうして作業区域a内の地盤
から排水することによって、地盤に含まれる水が相当深
い所まで排除することができる。このため、いわゆる根
掘りを行う際に、湧水等の発生も無く、つねに地盤が水
を含まない状態に維持できる。従って 排水のため、根
掘り底部にいわゆる斎場を設ける必要もない。
In the pipe pile 1 from which the earth and sand have been removed, the water passage hole 9.9-.
Since water from the surrounding ground will infiltrate from the hose, as shown in Figure 5, a hose 10.10 with a net etc. attached to the tip is used.
-... can be inserted into the same pipe pile 1 to collect them into one pipe, and the water can be drained by pumping the water using a pump or a vacuum well method. By draining the ground in the work area a in this manner, water contained in the ground can be removed to a considerable depth. Therefore, when performing so-called root digging, there is no generation of spring water, and the ground can always be maintained in a water-free state. Therefore, there is no need to provide a so-called funeral hall at the bottom of the excavation for drainage.

以上のようにして、この発明によれば、従来のシートパ
イルでは困難であった堅い地盤での”深いところまでの
締切工事が可能になると同時に、地盤の相当深い所まで
排水が可能となり、いわゆる根掘りが容易に行えるよう
になる。特に、杭打ち時間の短縮と同時に、バイブロパ
イルハンマーといった比較的簡便な機材によって深いと
ころまでの締め切り示可能となるので、工期の短縮と工
数の低減を図ることが可能となる。
As described above, according to the present invention, it is possible to perform deep cofferdam work on hard ground, which was difficult with conventional sheet piles, and at the same time, it is possible to drain water to a considerable depth in the ground, so-called This will make it easier to dig roots. In particular, it will shorten the pile driving time and also allow the use of relatively simple equipment such as a vibro-pile hammer to mark deep areas, which will shorten the construction period and reduce the number of man-hours. becomes possible.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図イは、この発明よにる管杭の一実施例を示す中間
部省略の斜視図、同図口は、イ図のB−B線断面図、第
2図は、この発明による方法の一実施例を示す締切状態
の平面図、第3図は、同じく杭打ち作業を示す説明図、
第4図は、同じく管杭の連結状態を示す平面図、第5図
は、第2図のl−A線断面図、第6図は、この発明よる
管杭を試験的に打ち込んだ地盤の構造を示す柱状図と同
地盤の貫入試験結果を示す図表である。 1−管杭 2−・鋼管 3−・・エンドグリップ 4−バイブロパイルハンマー 5−・−推進刃 6−・・・継手 8−・−ブレード a・一作業区域 特許出願人 有限会社上肥重機 代理人 弁理士 北條和由
Fig. 1A is a perspective view of an embodiment of the pipe pile according to the present invention with the middle part omitted; FIG. 3 is a plan view of the deadline state showing an example of the above, and FIG.
FIG. 4 is a plan view showing the connected state of the pipe piles, FIG. 5 is a sectional view taken along the line 1-A in FIG. 2, and FIG. These are a log diagram showing the structure and a chart showing the results of penetration tests on the same ground. 1-Pipe pile 2-Steel pipe 3-End grip 4-Vibro pile hammer 5-Propulsion blade 6-Joint 8-Blade a.1 Working area Patent applicant Kyohi Heavy Equipment Co., Ltd. People Patent Attorney Kazuyoshi Hojo

Claims (1)

【特許請求の範囲】 1、側面長手方向に継手を持った管杭を連結させながら
打ち込んで、作業区域を取り囲み、上記管杭の一部また
は全部の中から土砂を抜き取り、地盤から同管に浸入し
た水を揚水して上記作業区域の地盤から排水するように
したことを特徴とする締切工事方法。 2、鋼管の一端にバイラ゛ロバイルハンマーによって把
持することができるエンドグリップを設けると共に、そ
の下端から、尖鋭な推進刃を突設し、鋼管の側面長手方
向に沿って隣り合う管を互いに連結する継手を設けたこ
とを特徴とする管杭。 3、鋼管の先端側にあって、同管の径方向にブレードを
着脱自在に取り付けた特許請求の範囲第2項記載の管杭
[Claims] 1. Driving pipe piles with joints in the side longitudinal direction while connecting them, surrounding the work area, extracting earth and sand from part or all of the pipe piles, and inserting the pipes from the ground. A cofferdam construction method characterized in that infiltrated water is pumped up and drained from the ground in the work area. 2. An end grip is provided at one end of the steel pipe that can be gripped by a bi-robile hammer, and a sharp propelling blade is provided protruding from the lower end of the end grip to connect adjacent pipes to each other along the longitudinal direction of the side surface of the steel pipe. A pipe pile characterized by being provided with a joint that 3. The pipe pile according to claim 2, wherein a blade is detachably attached to the tip end of the steel pipe in the radial direction of the pipe.
JP15269683A 1983-08-22 1983-08-22 Coffering work and tubular pile therefor Granted JPS6043517A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP15269683A JPS6043517A (en) 1983-08-22 1983-08-22 Coffering work and tubular pile therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP15269683A JPS6043517A (en) 1983-08-22 1983-08-22 Coffering work and tubular pile therefor

Publications (2)

Publication Number Publication Date
JPS6043517A true JPS6043517A (en) 1985-03-08
JPS6364570B2 JPS6364570B2 (en) 1988-12-13

Family

ID=15546136

Family Applications (1)

Application Number Title Priority Date Filing Date
JP15269683A Granted JPS6043517A (en) 1983-08-22 1983-08-22 Coffering work and tubular pile therefor

Country Status (1)

Country Link
JP (1) JPS6043517A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341561A (en) * 2022-08-23 2022-11-15 深圳市市政工程总公司 Water area cofferdam construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5233308A (en) * 1975-09-08 1977-03-14 Tokyo Gas Co Ltd Method of reinforcing water contained sand subsoil

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5233308A (en) * 1975-09-08 1977-03-14 Tokyo Gas Co Ltd Method of reinforcing water contained sand subsoil

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115341561A (en) * 2022-08-23 2022-11-15 深圳市市政工程总公司 Water area cofferdam construction method

Also Published As

Publication number Publication date
JPS6364570B2 (en) 1988-12-13

Similar Documents

Publication Publication Date Title
US6164873A (en) Double-wing deformable stop-end pipe for forming the joining surfaces of concrete-cast wall elements
JPS6043517A (en) Coffering work and tubular pile therefor
JP5133625B2 (en) Steel pipe pile
JP6336850B2 (en) Pile head reinforcement method for foundation pile
JP3221895B2 (en) Construction method of large-diameter underground wall body and excavation equipment for burying pipes
CN208039236U (en) It is a kind of belong to underground pile connect wall construction method at wall equipment
JP6585930B2 (en) Caisson applied method
JPH0768707B2 (en) Open caisson method
JP4635725B2 (en) Pile construction system
KR100708408B1 (en) Construction method of a stone wall for reinforcement
JPH03228914A (en) Driving method for steel-pipe pile
JPH0626042A (en) Process of rotationally driving h-shape steel bar and h-shape steel bar used therefor
CN212956502U (en) Embedded rock type steel pipe pile is gone into to awl
JP2006009468A (en) Driving method of inner excavation type steel pipe sheet pile and the steel pipe sheet pile used therefor
CN111677519B (en) Reinforcing structure and reinforcing method for shield launching end and shield launching method
JP3084498B2 (en) Steel pipe pile head treatment method
JPS59213891A (en) Bore drilling method
JPS6012492B2 (en) Root hardening method using ready-made piles
JPS5991228A (en) Pit excavation work using caisson
JPH06240670A (en) Method and device for pulling pile
JPS62291317A (en) Quick construction of wide-width underground wall
JPH1037202A (en) Cutting excavation method and device removing underground spring water
JPS601451B2 (en) Water stop mountain stop wall construction method using Benoto pile excavator
JPH058298B2 (en)
JP2828786B2 (en) Casing shaft