JPS5858398A - Crack prevention of tunnel coating concrete - Google Patents
Crack prevention of tunnel coating concreteInfo
- Publication number
- JPS5858398A JPS5858398A JP56156091A JP15609181A JPS5858398A JP S5858398 A JPS5858398 A JP S5858398A JP 56156091 A JP56156091 A JP 56156091A JP 15609181 A JP15609181 A JP 15609181A JP S5858398 A JPS5858398 A JP S5858398A
- Authority
- JP
- Japan
- Prior art keywords
- lining
- tunnel
- mortar
- intervening layer
- lining concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
本発明はトンネル覆工コンクリ−1・のクラック防止工
法の創案に係り、各種トンネルの覆工においてそのクラ
ック発生を防止し、しかも安定且つ強固な覆工を形成す
ることのできる工法を提供しようとするものである。DETAILED DESCRIPTION OF THE INVENTION The present invention relates to the creation of a method for preventing cracks in tunnel lining concrete 1. It is an object of the present invention to prevent the occurrence of cracks in the lining of various tunnels, and to form stable and strong linings. The aim is to provide a construction method that allows for
近時におけるトンネル施工に尚っては従来一般のように
掘削されたトンイ、ル内に支保工と矢板などを用い地山
を支持させる方法に代え、掘削された地山に対して直ち
にコンクリートを吹付けて掘削による岩盤の凹凸を吹付
コンクリート層で平滑化シフ、又岩盤をできるだけ速か
に空気から遮断して露出した岩盤表面の膨張を抑え、こ
の状態でトンネル断面に対して放射状にロックボルト又
はアンカーボルトを打込んで岩盤に定着させ、掘削表層
部分の岩盤膨張をそれなりの深層部における岩盤と連結
一体化17て支持することが行われている。即ちこのよ
うに近時におけるl・ンネル施工は掘削後に吹付コンク
リートをロックボルト又はアンカーボルトによる1次覆
工で地山の安定化を図った後に一般的に厚さ20〜35
ttn程度の被覆コンクリート層による2次覆工を形成
しトンネル壁面を更に強固なものとすると共に仕上げを
なし、防水と美観を図り、又水路トンネルとする場合に
その水流抵抗を減少するようにしている。ところがこの
ような吹付施工をなすに当って、その表面にクラックの
発生が多いことが近時着目されつつあり、それによって
湧水がトンネル内に流出する。そこでこのようなりラッ
ク発生を防止することについても種々に検討がなされて
おり、その好ましい方法としては前記のような1次覆工
上に木材質の薄板又はシートを添着してから2次覆工を
なすものであって、このようにする々らばその2次覆工
上におけるクラックの発生を有効に防止することができ
る。然し斯様な薄板又はシートを用いたものについて実
地的に検討した結果によると岩盤に対しロックボルトや
アンカーボルトを配設し一体化された1次覆工と前記2
次穆工とがその薄板又はシートによって層別されたよう
なこととなり折角の岩盤との間の一体化特性が大きく損
われることとなり、振動圧や導水路における圧力変動(
加圧減圧の繰返し)に対して充分な耐力を得難くなる欠
点がある。In tunnel construction these days, instead of supporting the ground using shoring and sheet piles inside the excavated tunnel, as was the case in the past, concrete is immediately poured onto the excavated ground. The unevenness of the rock caused by the excavation is smoothed with a layer of shotcrete, and the rock is blocked from the air as quickly as possible to suppress the expansion of the exposed rock surface.In this state, rock bolts are installed radially to the tunnel cross section. Alternatively, anchor bolts are driven and anchored to the bedrock, and the expansion of the rock at the excavated surface layer is supported by connecting and integrating with the rock at a certain depth. In other words, in recent L-channel construction, after excavation, the ground is stabilized by primary lining with shotcrete using rock bolts or anchor bolts, and then the thickness is generally 20 to 35 mm.
A secondary lining is formed with a concrete layer of about ttn to further strengthen the tunnel wall surface, provide a finishing touch, improve waterproofing and aesthetics, and reduce water flow resistance when used as a waterway tunnel. There is. However, in recent years, attention has been drawn to the fact that cracks often occur on the surface of the sprayed construction, which causes spring water to flow into the tunnel. Therefore, various studies have been made to prevent the occurrence of racks, and the preferred method is to attach wood thin plates or sheets to the primary lining as described above, and then apply the secondary lining. By doing so, it is possible to effectively prevent the occurrence of cracks on the secondary lining. However, according to the results of practical studies using such thin plates or sheets, there is a primary lining that is integrated with rock bolts or anchor bolts against the bedrock, and a primary lining that is integrated with rock bolts or anchor bolts.
The structure is stratified by thin plates or sheets, which greatly impairs the integration characteristics with the bedrock, resulting in vibration pressure and pressure fluctuations in the headrace.
It has the disadvantage that it is difficult to obtain sufficient strength against repeated pressurization and depressurization.
本発明は上記したような実情に鑑み検討を重ねて創案さ
れたものであって、前記したような1次覆工と2次覆工
との間にそれらの各覆工よりも伸縮作用が犬でしかもそ
れらコンクリート覆工との間に略同等な接着強度を得る
ことのできるセメント混練物を用いた介在層を形成する
ことを提案するものであり、具体的には該介在層が5〜
1001cs’ / J程度の圧縮強度を持ち、耐着強
度としてけI Kr / crA前後ないし2それ以上
のものであって、気泡モルタルコンクリート、軽量モル
タル、パーライトモルタル、発泡レジン入りコンクリー
トの如きが用いられる。このような介在層は前記したよ
うな1次覆工又は2次覆工をなすだめの吹付設備そのも
ので、単にその材料を変えるだけで容易に実施できるが
、特に好ましい方法としては水セメント比(W/C)を
適当に犬とし、だ湿式の流動性モルタル又は気泡モルタ
ルを一力の管路でポンプ圧送し、このものに別系統で砂
及び軽量骨材(パーライトを含む)の倒れか一方又は双
方を乾式条件下でエアー圧送したものを吹付ノズル近傍
で合流添加して吹付け、或いは上記のよう々両材料を回
転円盤上に供給し、その回転力によって投射吹付けるも
のである。又これらの骨材に急結剤を混入してもよく、
更に場合によっては圧搾空気のみを合流させて前記モル
タル又は気泡モルタルを吹付けてもよい。形成されるト
ンネル覆工の状態は第1図に示す通りであって、掘削さ
れた岩盤1に対しトンネル2内からロックボルト3を放
射方向の如きに打込み、該ロックボルト3に対して1次
覆工4を形成してから前記介在層5を形成し、該介在層
5上に2次覆工6を形成する。1次覆工4については適
宜に鋼製支保工や金網などを併用することができ、その
厚さは10〜15m程度であり、ロックボルト3として
は太さが20〜30wn程度で長さが1.5〜3m程度
のものを岩盤1の組成を考慮して適当に選ぶ。The present invention has been devised after repeated studies in view of the above-mentioned circumstances, and has been developed so that the expansion and contraction action between the primary lining and the secondary lining is greater than that of each of the above-mentioned linings. Moreover, it is proposed to form an intervening layer using a cement mixture that can obtain approximately the same adhesive strength with the concrete lining, and specifically, the intervening layer is
It has a compressive strength of about 1001cs'/J, and has a resistance strength of around IKr/crA or more than 2, and is made of aerated mortar concrete, lightweight mortar, pearlite mortar, foamed resin-containing concrete, etc. . Such an intervening layer can be easily formed by simply changing the material using the spraying equipment used to form the primary lining or secondary lining as described above, but a particularly preferred method is to increase the water-cement ratio ( A wet fluid mortar or foam mortar is pumped through a single line, and sand and lightweight aggregates (including perlite) are added to this via a separate system. Alternatively, both materials may be air-fed under dry conditions and then combined and added near a spray nozzle and then sprayed. Alternatively, as described above, both materials may be supplied onto a rotating disk and sprayed by projection using the rotational force. Also, a quick setting agent may be mixed into these aggregates.
Furthermore, depending on the case, the mortar or foam mortar may be sprayed by combining only compressed air. The state of the tunnel lining to be formed is as shown in Fig. 1. Rock bolts 3 are driven into the excavated rock 1 from inside the tunnel 2 in a radial direction, and the rock bolts 3 are After forming the lining 4, the intervening layer 5 is formed, and the secondary lining 6 is formed on the intervening layer 5. For the primary lining 4, steel shoring, wire mesh, etc. can be used as appropriate, and its thickness is about 10 to 15 m, and the rock bolt 3 has a thickness of about 20 to 30 wn and a length of about 20 to 30 m. A thickness of approximately 1.5 to 3 m is appropriately selected in consideration of the composition of the rock mass 1.
介在層5の厚さは一般的に0.5〜5crnであり、斯
かる介在層5上に設けられる2次覆工6は厚さ20〜3
5副程度であることは前記した通りである。The thickness of the intervening layer 5 is generally 0.5 to 5 crn, and the secondary lining 6 provided on the intervening layer 5 has a thickness of 20 to 3 crn.
As mentioned above, there are about 5 servings.
具体的な設備としては第2図に示す通りで、混線機構4
6は材料供給機構41.43および42に連結され且つ
モルタルポンプ44に連結されていて、モルタルをホー
ス12で吹付ノズル13に送り、即ち図示のように吹付
ノズル13の直前位置において別の台車からの高圧空気
管11に合流せしめられ、混合管53で混合されてから
ノズル13から噴出させて吹付けるように成っている。The specific equipment is as shown in Figure 2.
6 is connected to material supply mechanisms 41, 43 and 42 and to a mortar pump 44, which conveys the mortar by means of a hose 12 to the spray nozzle 13, i.e. from a separate trolley at a position directly in front of the spray nozzle 13 as shown. The high-pressure air pipes 11 are mixed together in a mixing pipe 53, and the mixture is ejected from a nozzle 13 to be sprayed.
操作盤45については台車40がノズル13の近傍まで
進入するような場合は第2図のように台車40に設けら
れるが、台車40が遠隔した位置にあるような条件下で
はノズル13に近い位置に操作盤45を設けて吹付は状
況を確認しながら圧力条件、量などを適当に調整するよ
うにする。The operation panel 45 is provided on the trolley 40 as shown in FIG. 2 when the trolley 40 approaches the nozzle 13, but under conditions where the trolley 40 is located at a remote location, it is installed at a location close to the nozzle 13. An operation panel 45 is provided at the top of the sprayer so that the pressure conditions, amount, etc. can be adjusted appropriately while checking the spraying situation.
本発明によるものはノズルのみならず回転投射機構によ
っても吹付施工し得る。即ち前述した第2図において示
すような圧送ポンプ44からの管路11に連結された中
心管23は投射機構の中心軸にそつだ方向に横加して設
けられ、該中心管23の先端部は回転羽根16を有する
回転板18の中心部に向け、しかもこの回転板18との
間に適当な距離を採って開口されていて回転板18には
このような中心管23の開口端に対向させた攪拌機構部
35が設けられている。前記中心管23と同心状に設け
られているのが乾式材料供給筒22であって、該供給筒
22と中心管23との間には移送スクリュ19がホッパ
ー11部分から前記回転板18に向けて設けられており
、攪拌機構部35は第5図に示すように回転板18の中
心部に装着されるベース板36に突設されたもので、攪
拌翼37と38を多段に設は定着部材39と押圧部材3
9aで回転板18に定着され、しかも把手部36aを把
持して定着部材39aの弛緩条件下で適宜に取外し清掃
し或いは調整し得るように々つている。前記供給筒22
は駆動輪22aを取付け、適宜に回動されるように成っ
ているが、該供給筒22は固定のものでもよく、何れに
しても移送スクリュ19が中心管23に取付けられたブ
ーIJ 23 &で接手23bより図示左端側が回転さ
れることによりホッパー21に収容された資料を適切に
移送し、回転板18に供給でき、その供給量はスクリュ
19の回転速度に略比例したものとなる。回転板18は
供給筒22の外側に設けられた回転筒14の先端に取付
けられたもので、該回転筒14の基端に取付けたブー’
) 14 aによる駆動速度に比例した速度で該回転板
18上に資料を供給し、攪拌機構35で攪拌されてから
回転板18上に供給分散させる。上記した供給筒220
回転板18側先端部は攪拌翼37.38部分を被覆して
回転板18面に近接しているが、その一部に切欠部22
bを形成し、該切欠部22b部分から回転板18上に吐
出し、供給筒12を前記駆動輪22aによって回動し調
整操作することによって吹付方向を適宜に制限すること
は第4図に示す通りであり、斯様な制限調整操作の結果
と[7て垂直壁を両側に有する掘削トンネル2内アーチ
形吹付面その他の形状に即し回転吹付機構の吹付方向に
関する制限調整作用を加えるならば適切な吹付施工が得
られることは明かである。The invention can be sprayed not only by a nozzle but also by a rotary projection mechanism. That is, the central tube 23 connected to the conduit 11 from the pressure pump 44 as shown in FIG. The rotary plate 18 has an opening facing the center of the rotary plate 18 having the rotary blades 16 and an appropriate distance between the rotary plate 18 and the rotary plate 18 . A stirring mechanism section 35 is provided. A dry material supply cylinder 22 is provided concentrically with the central pipe 23, and between the supply cylinder 22 and the central pipe 23, a transfer screw 19 is inserted from the hopper 11 toward the rotary plate 18. As shown in FIG. 5, the stirring mechanism section 35 is provided protruding from a base plate 36 attached to the center of the rotary plate 18, and the stirring mechanism section 35 is provided with stirring blades 37 and 38 arranged in multiple stages. Member 39 and pressing member 3
The fixing member 39a is fixed to the rotary plate 18 by the fixing member 39a, and is arranged so that it can be removed for cleaning or adjustment as appropriate by gripping the handle portion 36a and under the condition that the fixing member 39a is relaxed. The supply tube 22
A drive wheel 22a is attached to the supply tube 22 so that it can be rotated as appropriate, but the supply tube 22 may be a fixed one. By rotating the left end side in the figure from the joint 23b, the material stored in the hopper 21 can be appropriately transferred and supplied to the rotary plate 18, and the amount supplied is approximately proportional to the rotational speed of the screw 19. The rotary plate 18 is attached to the tip of the rotary tube 14 provided outside the supply tube 22, and the rotary plate 18 is attached to the tip of the rotary tube 14 provided outside the supply tube 22.
) The material is supplied onto the rotary plate 18 at a speed proportional to the driving speed by 14a, stirred by the stirring mechanism 35, and then supplied and dispersed onto the rotary plate 18. The above-mentioned supply cylinder 220
The tip of the rotating plate 18 side covers the stirring blades 37 and 38 and is close to the surface of the rotating plate 18.
FIG. 4 shows that the spraying direction is appropriately restricted by forming a groove b, discharging from the notch 22b onto the rotary plate 18, and rotating and adjusting the supply tube 12 by the drive wheel 22a. As a result of such a limit adjustment operation, [7] If we add a limit adjustment effect regarding the blowing direction of the rotary blowing mechanism according to the shape of the arched blowing surface and other shapes in the excavated tunnel 2 having vertical walls on both sides. It is clear that a suitable spray application can be obtained.
本発明によるものの具体的な実施例について説明すると
以下の通りである。Specific examples according to the present invention will be described below.
実施例1゜
普通ポルトランドセメント272 Kg / u/、大
井用産細目砂712Kg/lt?、富士月産川砂利11
55Kf/J、水15aKy/m、減水剤0.68に9
/−の割合で混練した生コンクリートを用い、結晶質流
紋岩系の岩盤中に掘削されたトンネルに対し前記第1図
のように径25wnで長さ2mのロックボルトを100
crn間隔で打込み配設した条件下において覆工するに
尚り、従来の一般法に従って厚さが平均1.0cmの1
次覆工してから2次覆工を厚さ30ctn平均に吹付は
施工した第1対称区と、上記のような1次覆工と2次覆
工との間に厚さ0.5 vanのビニルシートを用いた
第2対称区および本発明に従い上記1次覆工と2次覆工
との間に上記配合に対し更に径1〜2論の膨張パーライ
ト(比重; 0.2 )を150 Ky / rr?配
合したパーライトモルタル(比重0.81強度45Ky
/cra)を介在層として厚さ2mに吹付けだ本発明区
とを形成した。Example 1 Normal Portland cement 272 Kg/u/, Oi fine sand 712 Kg/lt? , Fuji Tsukisan River Gravel 11
55Kf/J, water 15aKy/m, water reducing agent 0.68 to 9
As shown in Figure 1 above, 100 rock bolts with a diameter of 25wn and a length of 2m were installed into a tunnel excavated in crystalline rhyolitic bedrock using ready-mixed concrete mixed at a ratio of /-.
According to the conventional general method, 1.0 cm thick on average is used for lining under the condition that the lining is placed at crn intervals.
After the next lining, the secondary lining was sprayed to an average thickness of 30 ctn, with a thickness of 0.5 van between the first symmetrical area and the primary lining and secondary lining as described above. In addition to the above composition, 150 Ky of expanded pearlite (specific gravity: 0.2) with a diameter of 1 to 2 is added between the second symmetrical section using a vinyl sheet and the above primary lining and secondary lining according to the present invention. /rr? Blended pearlite mortar (specific gravity 0.81 strength 45Ky)
/cra) was sprayed to a thickness of 2 m to form an intervening layer.
即ちこれらの対称区および発明区について施工後のクラ
ック発生状況をクラック面積(クラック長さ層×クララ
ク幅rMl/ 靜)として測定した結果は次の第1表の
通りである。That is, the crack occurrence status after construction in these symmetric areas and invention areas was measured as crack area (crack length layer x crack width rMl/resistance), and the results are shown in Table 1 below.
第1表 (ia/W?)
父上記したよりな各区について91日後に超音波パルス
が9000の音波を2次棲エコンクリー1・と岩盤との
間に伝達させて1次覆工と2次覆工との間の剥離状態を
検討した結果は第2対称区のものが略全面的に剥離して
超音波が伝播しないのに対して第1対称区と発明区のも
のは何れも安定し7た層着状態をなし超音波の伝播が確
認された。Table 1 (ia/W?) After 91 days, ultrasonic pulses transmitted sound waves of 9,000 psi between the secondary eco-concretion 1 and the bedrock for each of the above-mentioned areas, and the primary lining and secondary lining were constructed. As a result of examining the state of separation between the two symmetrical areas, the one in the second symmetrical area was almost completely separated and the ultrasonic waves did not propagate, whereas the first symmetrical area and the invention area were both stable7. A state of adhesion was observed, and the propagation of ultrasonic waves was confirmed.
実施例26
実施例1と同じ方法で1次覆工および2次覆工を行い、
本発明区においてその1次覆工と2次覆工の間に介在層
を吹付施工するに当り、第2図に示すようにノズル13
の手前3mの位置で第1管路11と第2管路12とを連
結し、第1管路11から比重08の気泡ペーストをポン
プ圧送し、第2管路からは砂および急結剤を空気圧送し
7て第1管路と第2管路の合流点、即ち混合管53で合
流し2て比重1.2の気泡モルタルとしだものをノズル
13から吹付ける工法を実施1〜だ。即ちこの場合(1
1)
の施工後におけるクラック発生状況を実施例1と同じに
測定した結果は次の第2表の通りである。Example 26 Primary lining and secondary lining were performed in the same manner as in Example 1,
In spraying the intervening layer between the primary lining and the secondary lining in the present invention, the nozzle 13 is used as shown in FIG.
The first pipe line 11 and the second pipe line 12 are connected at a position 3 m in front of the pipe, and the foam paste with a specific gravity of 08 is pumped from the first pipe line 11, and the sand and quick-setting agent are pumped from the second pipe line. The first and second pipes are conveyed by air pressure, and the first pipe line and the second pipe line meet at the confluence point, that is, the mixing pipe 53, and then bubble mortar and soot with a specific gravity of 1.2 are sprayed from the nozzle 13. That is, in this case (1
1) The crack occurrence status after construction was measured in the same manner as in Example 1, and the results are shown in Table 2 below.
第2表
又施工91日後における1次覆工と2次覆工との間の層
着状態を超音波パルスにより横側した結果は、第2対称
区のものが剥離しているのに対し、第1対称区と本発明
区のものは全く剥離していないことを確認した。Table 2 also shows that the state of layer adhesion between the primary lining and secondary lining 91 days after construction was examined laterally using ultrasonic pulses, while the layer in the second symmetrical area had peeled off. It was confirmed that there was no peeling at all in the first symmetric area and the invention area.
実施例3
実施例2と同じに実施するに当り、第1管(12)
路からグラスファイバー人シ気泡モルタル(比重1.0
1強度35Kf/crI)を圧送し、第2管路から高圧
空気だけを圧送し、これを第1管路に合流させて吹付施
工し7だ。即ちこのように17で実施した場合において
も上記した実施例2と略同様な結果を得ることができた
。Example 3 In carrying out the same procedure as in Example 2, glass fiber foam mortar (specific gravity 1.0) was used from the first pipe (12).
1 strength of 35 Kf/crI), and only high-pressure air is sent under pressure from the second pipe line, which is merged into the first pipe line and sprayed. That is, even in the case where Example 17 was carried out in this manner, substantially the same results as in Example 2 described above could be obtained.
実施例4゜
実施例2におけると同じ配合のものを施工するに当って
実施例2におけるスラリー状モルタルを回転板の中心部
に向けた中心管を利用してポンプ圧送し、砂および急結
剤を上記中心筒と同心に設けられた供給管内のスクリュ
コンベアで同様に回転盤上へ供給せしめ、上記回転盤の
高速回転でトンネル内壁面に投射する方式によって投射
施工した。Example 4 In constructing the same composition as in Example 2, the slurry mortar in Example 2 was pumped using a central pipe directed toward the center of the rotary plate, and sand and quick setting agent were mixed. The material was similarly supplied onto a rotary disk using a screw conveyor in a supply pipe provided concentrically with the central tube, and the material was projected onto the inner wall of the tunnel by the high speed rotation of the rotary disk.
即ちこの場合において、その施工後経口による覆工のク
ラック発生状況を前記した各実施例におけると同じに測
定した結果は次の第3表に示す通シである。That is, in this case, the occurrence of cracks in the lining after construction was measured in the same manner as in each of the examples described above, and the results are shown in Table 3 below.
第3表
(クラック長さ闇×クラック幅un /’ m’ )又
施工91日後における1次覆工と2次覆工との間の層着
状況を検討し九結果は、超音波パルスにより第1対称区
と本発明区のものは全く剥離していないことが確認され
たのに対し、第2対称区のものは完全剥離状態と女って
いることを知った。Table 3 (Crack length x Crack width un /'m') Also, the layer adhesion between the primary lining and the secondary lining 91 days after construction was examined. It was confirmed that the samples in the first symmetrical area and the invention area were not peeled off at all, whereas the samples in the second symmetrical area were found to be completely peeled off.
以上説明したような本発明によればこの種トンネル覆工
におけるクラックの発生を有効に防止し、しかも安定且
つ強固で一体的なトンネル覆工の施工をなし得るもので
あって、工業的にその効果の大きい発明である。According to the present invention as described above, it is possible to effectively prevent the occurrence of cracks in this type of tunnel lining, and also to construct a stable, strong, and integral tunnel lining, and it is possible to achieve this from an industrial perspective. This is a highly effective invention.
(15)(15)
図面は本発明の実施態様を示すものであって、第1図は
本発明による覆工の形成状態を示した断面図、第2図は
その吹付は施工の1例としてのノズルの態様を示しだ平
面図、第3図は回転投射力による吹付機構の部分切欠側
面図、第4図はその回転板部分の縦断側面図、第5図は
その攪拌機構部の斜面図である。
然してこれらの図面において、1は岩盤、2はトンネル
、3はロックボルト、4は1次覆工、5は介在層、6は
2次覆工を示すものである。
特許出願人 伊 東 端 部
発明者 伊東端部
同 堀之内 徳 二
同 山本康弘
同 1) 中 秀 列間
似 出 2史 也F、1電
代理人 弁理士 白 川 −−1P・j・t・′弓
序・
(16)The drawings show embodiments of the present invention, and FIG. 1 is a cross-sectional view showing the state of formation of the lining according to the present invention, and FIG. 2 shows the form of a nozzle as an example of spraying. 3 is a partially cutaway side view of the spraying mechanism using rotational projection force, FIG. 4 is a vertical sectional side view of the rotary plate portion thereof, and FIG. 5 is a slope view of the stirring mechanism portion thereof. In these drawings, 1 is the rock mass, 2 is the tunnel, 3 is the rock bolt, 4 is the primary lining, 5 is the intervening layer, and 6 is the secondary lining. Patent Applicant Hajime Ito Inventor Habe Ito Tokuji Horinouchi Yasuhiro Yamamoto 1) Hide Naka Rema
Similar appearance 2 Fumiya F, 1 Den agent patent attorney Shirakawa -- 1P・j・t・'yūjō・ (16)
Claims (1)
シ1.てから1次覆工し、該1次覆工上に2次覆工を形
成するに当り、それら各覆工よりも伸縮作用の大きいセ
メント混線物による介在層を吹付は施工することを特徴
とするトンネル覆工コンクリートのクラック防止工法。 2、第1管路においてスラリー状に流動する気泡モルタ
ルを圧送し、第2管路で高圧空気を送り、ノズル手前で
合流せしめて吹付は介在層を施工する特許請求の範囲第
1項に記載のトンネル覆工コンクリートのクラック防止
工法。 3 第1管路においてスラリー状セメントペースト又は
モルタルをポンプ圧送17たものに砂、砂利又は軽量骨
材の何れか1種又は2′N4以上を空気圧送し7て添加
し且つ吹付けて介在層を形成する特許請求の範囲第1項
に記載のトンネル覆エコンクリートのクラック防止工法
、 4、 回転円板−ににスラリー状セメントペースト又は
モルタルと乾式状態の砂、砂利又は軽量骨材の何れか1
種又は2種以上を各別に供給し、前記回転円板の高速回
転による遠心力で投射し吹伺ける特許請求の範囲第1項
に記載のトンネル覆工コンクリートのクラック防止工法
・[Claims] 1. Rock bolts are installed in the bedrock of the excavated tunnel. After that, a primary lining is applied, and when forming a secondary lining on the primary lining, spraying is characterized in that an intervening layer of a cement mixed material, which has a larger expansion and contraction effect than each of the linings, is applied. A method to prevent cracks in tunnel lining concrete. 2. The foamed mortar flowing in the form of a slurry is pumped in the first pipe line, the high-pressure air is sent in the second pipe line, and the air is merged in front of the nozzle to form the intervening layer, as described in claim 1. A method to prevent cracks in tunnel lining concrete. 3 In the first pipe, to the slurry cement paste or mortar which has been pumped 17, one of sand, gravel or lightweight aggregate or 2'N4 or more is added by pneumatically pumping 7 and sprayed to form an intervening layer. 4. A method for preventing cracks in tunnel lining concrete according to claim 1, which comprises: 4. A rotating disk containing slurry cement paste or mortar and any one of sand, gravel, or lightweight aggregate in a dry state. 1
A method for preventing cracks in tunnel lining concrete according to claim 1, in which seeds or two or more seeds are supplied separately, and are projected and blown by centrifugal force caused by high-speed rotation of the rotating disk.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56156091A JPS5858398A (en) | 1981-10-02 | 1981-10-02 | Crack prevention of tunnel coating concrete |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP56156091A JPS5858398A (en) | 1981-10-02 | 1981-10-02 | Crack prevention of tunnel coating concrete |
Publications (1)
Publication Number | Publication Date |
---|---|
JPS5858398A true JPS5858398A (en) | 1983-04-06 |
Family
ID=15620106
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP56156091A Pending JPS5858398A (en) | 1981-10-02 | 1981-10-02 | Crack prevention of tunnel coating concrete |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS5858398A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58207497A (en) * | 1982-05-26 | 1983-12-02 | 財団法人鉄道総合技術研究所 | Method of formation construction of inner wall of tunnel |
JPS61130695U (en) * | 1985-02-01 | 1986-08-15 | ||
JPS6241898A (en) * | 1985-08-13 | 1987-02-23 | 佐藤工業株式会社 | Lining method in method of shielding type tunnel construction |
CN109538241A (en) * | 2018-10-18 | 2019-03-29 | 长安大学 | The prevention and control method in a kind of cast-in-place concrete liner structure crack |
-
1981
- 1981-10-02 JP JP56156091A patent/JPS5858398A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS58207497A (en) * | 1982-05-26 | 1983-12-02 | 財団法人鉄道総合技術研究所 | Method of formation construction of inner wall of tunnel |
JPH0236760B2 (en) * | 1982-05-26 | 1990-08-20 | Tetsudo Sogo Gijutsu Kenkyusho | |
JPS61130695U (en) * | 1985-02-01 | 1986-08-15 | ||
JPS6241898A (en) * | 1985-08-13 | 1987-02-23 | 佐藤工業株式会社 | Lining method in method of shielding type tunnel construction |
CN109538241A (en) * | 2018-10-18 | 2019-03-29 | 长安大学 | The prevention and control method in a kind of cast-in-place concrete liner structure crack |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6907708B2 (en) | Lightweight wall construction | |
AU758420B2 (en) | Concrete formulation | |
US20190308342A1 (en) | Apparatuses and systems for and methods of generating and placing zero-slump-pumpable concrete | |
US5421922A (en) | Method for applying a foamed fiber insulation | |
JP2003516302A5 (en) | ||
JPS5858398A (en) | Crack prevention of tunnel coating concrete | |
US2937429A (en) | Machine for pouring concrete pipe in situ | |
AU659082B2 (en) | Ferrocement composition, method of forming objects therefrom and apparatus for use in such a method | |
JPH09183646A (en) | Composition for spray mortar | |
JPS594194B2 (en) | Cement mortar spraying method | |
JP3482413B2 (en) | Lightweight cement mortar for bolt box filling method and bolt box filling method using lightweight cement mortar | |
JP6888909B2 (en) | Sprayed non-combustible material for foamed resin-based heat insulating material, non-combustible heat insulating structure and its construction method | |
AU774869C (en) | Lightweight wall construction | |
JPS6164956A (en) | In-site spray finishing construction method by fiber reinforced cement | |
JP4916786B2 (en) | Spray cement composition and spray method | |
NZ238299A (en) | Water course lining unit using cement and mesh | |
Taylor | Sprayed concrete | |
CN107938662A (en) | A kind of concrete core cement soil stirring pile consolidated subsoil construction technology | |
JP4386280B2 (en) | Rapid setting concrete spraying method and spraying apparatus used therefor | |
CA1135572A (en) | Surface finishes for rigid structures | |
JP2002068792A (en) | Admixture for mixing with cement or mortar | |
JPH0333837Y2 (en) | ||
JP4545304B2 (en) | Spray nozzle, quick setting cement concrete and spray method | |
CN104563466A (en) | Nozzle mechanism for mortar coating machine and mortar coating machine | |
JPS6220560Y2 (en) |