[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JPH11324224A - Column structure and its construction - Google Patents

Column structure and its construction

Info

Publication number
JPH11324224A
JPH11324224A JP14016598A JP14016598A JPH11324224A JP H11324224 A JPH11324224 A JP H11324224A JP 14016598 A JP14016598 A JP 14016598A JP 14016598 A JP14016598 A JP 14016598A JP H11324224 A JPH11324224 A JP H11324224A
Authority
JP
Japan
Prior art keywords
concrete
wire mesh
column
spiral
wire gauze
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
JP14016598A
Other languages
Japanese (ja)
Inventor
Masao Obata
政雄 小畑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP14016598A priority Critical patent/JPH11324224A/en
Publication of JPH11324224A publication Critical patent/JPH11324224A/en
Withdrawn legal-status Critical Current

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

PROBLEM TO BE SOLVED: To inexpensively give superior earthquake resistance to a column without becoming the obstruction of a construction plan in the case where the novel column is constructed by disposing a wire gauze so as to surround a main bar, placing concrete in the inside of the wire gauze and adhering concrete and the wire gauze. SOLUTION: A lath wire gauze 22 is provided so as to surround a main bar 21 to compose column structure 20. A hoop bar is provided on the main bar 21. In addition, the lath wire gauze 22 is held with a spiral bar 24. The spiral bar 24 is formed in the substantial same diameter as the column structure 20 and disposed so that the axial direction is the same as the extension direction of the main bar 21. Concrete is placed in a space surrounded by the lath wire gauze 22, and integrated to adhere to the lath wire gauze 22. Since the concrete is reinforced by the wire gauze from an outer periphery, the structure of high toughness can be realized as compared with the normal reinforced concrete column.

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】本発明は、構造物を構成する
柱構造およびその構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pillar structure constituting a structure and a method of constructing the same.

【0002】[0002]

【従来の技術】周知のように、ビルなどの構造物におい
て柱構造を構築するには、まず、柱を構成する鉄筋を組
み立てるとともに、これら鉄筋の周囲に型枠を配置し、
この型枠内にコンクリートを打設するという方法が用い
られていた。
2. Description of the Related Art As is well known, in order to construct a pillar structure in a structure such as a building, first, rebars constituting columns are assembled, and a formwork is arranged around these rebars.
A method of casting concrete in this formwork has been used.

【0003】図19および20に示すものは、このよう
な構築方法の一例を示すものである。これら図中におい
て、符号1は型枠を、2は柱主筋を、3はフープ筋をそ
れぞれ示している。これらを用いて柱構造を形成するに
は、まず、柱主筋2とフープ筋3とを立柱状に組み立
て、その周囲に、型枠1を構成する合板型枠材5を所定
の柱断面を形成するように配置する。次に、この合板型
枠材5を竪端太材6および横端太材7で補強するととも
に、柱構造を隔てて互いに平行に配置された横端太材
7,7間に、型枠1および型枠1によって囲まれた空間
Sを貫通するようにセパレータ8,8,…を配置し、こ
れらセパレータ8,8,…の両端を横端太材7に対して
締付金物10,10,…によって固定する。
FIGS. 19 and 20 show an example of such a construction method. In these figures, reference numeral 1 denotes a mold, 2 denotes a column main bar, and 3 denotes a hoop bar. In order to form a pillar structure using these, first, the pillar main reinforcement 2 and the hoop reinforcement 3 are assembled in a vertical pillar shape, and a plywood form material 5 constituting the mold 1 is formed around the pillar reinforcement in a predetermined column cross section. To be placed. Next, the plywood form member 5 is reinforced with a vertical end thick member 6 and a horizontal end thick member 7, and the form 1 is interposed between the horizontal end thick members 7, 7 arranged in parallel with each other with a columnar structure therebetween. Are arranged so as to penetrate the space S surrounded by the mold 1, and both ends of the separators 8, 8,. Fix by ...

【0004】このようにして型枠1を補強した後、空間
Sにコンクリートを打設し、コンクリートの硬化後に型
枠1を脱型することによって、柱構造を構築することが
できる。
[0004] After reinforcing the formwork 1 in this manner, concrete is poured into the space S, and after the concrete has hardened, the formwork 1 is removed, whereby a column structure can be constructed.

【0005】また、近年においては、プレキャストコン
クリートや鉄板からなる型枠部材を捨て型枠として使用
することによって、型枠撤去に係る作業を必要としない
打ち込み型枠工法の普及が進んできている。
[0005] In recent years, the use of a form member made of precast concrete or iron plate as a discard form has led to the spread of a drive-in form method that does not require work related to form removal.

【0006】図21および図22に示すものは、このよ
うな打ち込み型枠工法を用いた柱構造の構築方法の一例
を示すものであり、図中、符号12は、プレキャストコ
ンクリート版からなるせき板を、13は、せき板12の
外方に配置されてせき板12を保持するコラムクランプ
部材を示している。なお、これらの図中において、図1
9および図20に示したものと共通する構成について
は、同一の符号を付し、その説明を省略することとす
る。
FIGS. 21 and 22 show an example of a method of constructing a pillar structure using such a driving form method. In the drawings, reference numeral 12 denotes a weir plate made of a precast concrete slab. Reference numeral 13 denotes a column clamp member which is disposed outside the weir plate 12 and holds the weir plate 12. In these figures, FIG.
Components common to those shown in FIGS. 9 and 20 are denoted by the same reference numerals, and description thereof will be omitted.

【0007】これら図21および図22において示す工
法により、柱構造を形成する際には、まず、柱主筋2と
フープ筋3とを立柱状に組み立て、その周囲に、せき板
12,12,…を所定の柱断面を形成するように配置す
る。次に、このせき板12,12,…をコラムクランプ
部材13,13,…によって補強し、さらに、せき板1
2,12,…に囲まれた空間内にコンクリートを打設す
ることにより、柱構造を形成することができる。この場
合、せき板12,12,…の脱型は必要ない。
When forming a pillar structure by the construction method shown in FIGS. 21 and 22, first, the pillar main reinforcement 2 and the hoop reinforcement 3 are assembled in a vertical column shape, and the weirs 12, 12,. Are arranged so as to form a predetermined pillar cross section. Next, the weir plates 12, 12,... Are reinforced by column clamp members 13, 13,.
By casting concrete in the space surrounded by 2, 12, ..., a pillar structure can be formed. In this case, it is not necessary to remove the weir plates 12, 12,...

【0008】[0008]

【発明が解決しようとする課題】ところで、阪神大震災
後の各種の調査において報告されているように、大地震
時には、建築物の一階ピロティや中間階の鉄筋コンクリ
ート造の柱部位、あるいは、鉄道や高速道路等の高架柱
脚の鉄筋コンクリート造の柱部位が強大な地震力を受け
て圧壊する懸念があることが指摘されている。その結
果、耐震設計の見直しと並行して、全国各地で専門家に
よる耐震診断が急増し、これにより、特に、鉄筋コンク
リート造の柱部位のせん断補強工事が盛んに行われるよ
うになってきている。このようなせん断補強工事として
は、柱の周囲に鉄板や炭素繊維を巻き付けることによ
り、柱の靱性を向上させる手法が、最も一般的に採用さ
れている。
By the way, as reported in various investigations after the Great Hanshin Earthquake, at the time of a large earthquake, the first floor of the building, the reinforced concrete column on the middle floor, and the railway and It has been pointed out that there is a concern that a reinforced concrete column part of an elevated column base such as a highway may be crushed by a strong seismic force. As a result, in parallel with the review of the seismic design, the number of seismic diagnoses by specialists in all parts of the country has been rapidly increasing, and as a result, shear reinforcement work has been actively carried out especially on reinforced concrete columns. As such shear reinforcement work, a method of improving the toughness of a column by winding an iron plate or carbon fiber around the column is most commonly employed.

【0009】この柱の補強工事は、主に既存の柱構造を
対象としたものであるが、一方、新規に構造物を構築す
る場合に用いられていた上述の柱構造の構築方法におい
ては、靱性の増強についてまで考慮されておらず、あら
かじめ優れた耐震性を得ようとすると、柱断面を大きく
するか、コンクリート材料自体の強度を高めるか、ある
いは、鉄筋の量を増やすしか対処方法がなかった。しか
し、このような方法で耐震性を得ようとすれば、材料コ
スト等が嵩むものとなるだけでなく、建築計画に制約が
生じてしまうことも考えられる。
[0009] This column reinforcement work is mainly intended for existing column structures. On the other hand, in the above-mentioned method of constructing a column structure used for newly constructing a structure, No consideration has been given to increasing toughness, and in order to obtain excellent seismic resistance in advance, the only solution is to increase the column section, increase the strength of the concrete material itself, or increase the amount of reinforcing steel. Was. However, if it is attempted to obtain seismic resistance by such a method, not only the material cost and the like will increase but also the construction plan may be restricted.

【0010】このような事情に鑑み、本発明において
は、新規に柱を構築する場合に、安価に、しかも建築計
画の障害となることなく、その柱にあらかじめ優れた耐
震性を付与しておくことができるような技術を提供する
ことを課題とする。
In view of such circumstances, according to the present invention, when a new pillar is constructed, the pillar is provided with excellent seismic resistance in advance at low cost and without hindering the construction plan. It is an object of the present invention to provide a technology capable of performing such operations.

【0011】[0011]

【課題を解決するための手段】上記課題を解決するため
に本発明においては以下の手段を採用した。すなわち、
請求項1記載の柱構造は、主筋と、主筋を囲むように配
置された金網とを備えてなり、該金網内部にはコンクリ
ートが打設されて、該コンクリートと該金網とが付着す
る構成とされていることを特徴としている。
Means for Solving the Problems To solve the above problems, the present invention employs the following means. That is,
The pillar structure according to claim 1, comprising a main reinforcing bar and a wire mesh arranged so as to surround the main reinforcing bar, wherein concrete is poured into the wire mesh, and the concrete and the wire mesh are adhered to each other. It is characterized by being.

【0012】この柱構造においては、コンクリートがそ
の外周から金網によって補強されるために、通常の鉄筋
コンクリート柱に比較して靱性の高い構造を実現するこ
とができる。また、金網を捨て型枠とすることができ
る。
In this column structure, since the concrete is reinforced by the wire mesh from the outer periphery thereof, a structure having higher toughness as compared with ordinary reinforced concrete columns can be realized. In addition, the wire mesh can be used as a waste form.

【0013】請求項2記載の柱構造は、請求項1記載の
柱構造であって、スパイラル筋が、前記柱構造を囲むよ
うに、なおかつ、前記主筋の延在方向がその軸方向とな
るように配置され、前記金網は該スパイラル筋によって
補強されていることを特徴としている。
According to a second aspect of the present invention, there is provided the pillar structure according to the first aspect, wherein the spiral streak surrounds the pillar structure, and the main streaks extend in the axial direction. And the wire mesh is reinforced by the spiral streaks.

【0014】この柱構造においては、金網をスパイラル
筋によって補強することによって、靱性をより一層向上
させることができる。
In this column structure, the toughness can be further improved by reinforcing the wire netting with spiral streaks.

【0015】請求項3記載の柱構造の構築方法は、柱構
造を構築するための方法であって、該柱構造の設置対象
位置に主筋を立設しておき該主筋を囲むように金網を設
け、該金網によって囲まれた空間内にコンクリートを打
設することを特徴としている。
According to a third aspect of the present invention, there is provided a method for constructing a pillar structure, wherein a main reinforcing bar is erected at a position where the pillar structure is to be installed, and a wire netting is arranged to surround the main reinforcing bar. And concrete is poured into a space surrounded by the wire mesh.

【0016】この柱構造の構築方法においては、金網を
捨て型枠とすることができ、従来の打ち込み型枠工法と
同様に型枠脱型に係る作業が必要でない。
In this method of constructing a pillar structure, the wire mesh can be used as a discarded formwork, and the work related to the mold removal from the formwork is not required as in the conventional driving formwork method.

【0017】請求項4に係る柱構造の構築方法は、請求
項3記載の柱構造の構築方法であって、前記主筋を立設
するに際しては、スパイラル筋をその軸方向に圧縮した
ものを前記柱構造の設置対象位置を囲むように配置して
おき、該スパイラル筋によって囲まれた位置に前記主筋
を立設し、該主筋の立設後に、前記スパイラル筋をその
軸方向に引き伸ばすとともに、この引き伸ばされたスパ
イラル筋に対して前記金網を固定することを特徴として
いる。
According to a fourth aspect of the present invention, in the method of constructing a pillar structure according to the third aspect, when erecting the main reinforcement, the spiral reinforcement is compressed in an axial direction thereof. It is arranged so as to surround the installation target position of the pillar structure, the main muscle is erected at a position surrounded by the spiral muscle, and after the main muscle is erected, the spiral muscle is stretched in the axial direction. The wire mesh is fixed to the stretched spiral streaks.

【0018】この柱構造の構築方法においては、金網を
補強して柱構造の靱性を向上させるスパイラル筋の設置
を容易に行うことが可能である。
In this method of constructing a pillar structure, it is possible to easily install a spiral streak that reinforces the wire mesh and improves the toughness of the pillar structure.

【0019】[0019]

【発明の実施の形態】以下、本発明の実施の形態の一例
を、図面に基づいて説明する。図1および図2は、本発
明の一実施の形態である柱構造20の概略構成を示す図
である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS Hereinafter, an embodiment of the present invention will be described with reference to the drawings. FIGS. 1 and 2 are diagrams showing a schematic configuration of a pillar structure 20 according to an embodiment of the present invention.

【0020】図中に示すように、柱構造20は、主筋2
1,21,…と、主筋21,21,…を囲むように設け
られたラス金網22とを備えて構成されている。主筋2
1,21,…には、フープ筋23が設けられている。ま
た、ラス金網22は、スパイラル筋24によって保持さ
れている。このスパイラル筋24は、柱構造20と略同
一径に形成され、その軸方向が主筋21,21,…の延
在方向と同一となるように配置されている。
As shown in the figure, the pillar structure 20
, And a lath wire mesh 22 provided so as to surround the main bars 21, 21,. Main bar 2
The hoops 23 are provided at 1, 21,.... The lath wire mesh 22 is held by a spiral streak 24. The spiral streaks 24 are formed so as to have substantially the same diameter as the column structure 20, and are arranged such that the axial direction thereof is the same as the extending direction of the main streaks 21, 21,.

【0021】また、ラス金網22によって囲まれた空間
内には、コンクリート(図示省略)が打設され、このコ
ンクリートはラス金網22と付着して一体化される構成
とされる。すなわち、ラス金網22は、打ち込み型枠と
して使用される。このため、ラス金網22には、目の大
きさがコンクリートが漏れない程度のものが使用され
る。
In the space surrounded by the lath wire mesh 22, concrete (not shown) is cast, and the concrete is attached to the lath wire mesh 22 to be integrated therewith. That is, the lath wire mesh 22 is used as a driving formwork. For this reason, the lath wire mesh 22 having a mesh size such that the concrete does not leak is used.

【0022】図3および図4は、以上のような概略構成
とされた柱構造20を、さらに詳細に示した図である。
これら図中に示すように、ラス金網22の周囲には、押
さえ鉄筋26,26,…が、周方向に等間隔に、なおか
つ、主筋21,21,…と平行な方向に配置されてお
り、柱構造20の中心に関して互いに点対称に配置され
た押さえ鉄筋26,26間には、セパレーター金物27
が設けられている。図5、図6に拡大して示すように、
このセパレーター金物27は、フープ筋23に対して位
置決め金物28により固定されるとともに、その端部2
7aが、押さえ鉄筋26に対してフォームタイ金物29
を用いて結合されている。これにより、ラス金網22の
位置を適切に保持することが可能となるとともに、ラス
金網22の内側に打設されるコンクリートの側圧に対抗
することが可能となる。
FIGS. 3 and 4 are views showing the column structure 20 having the above-described schematic configuration in further detail.
As shown in these figures, pressing reinforcing bars 26, 26,... Are arranged around the lath wire mesh 22 at equal intervals in the circumferential direction and in a direction parallel to the main reinforcing bars 21, 21,. Separator metal fittings 27 are provided between the holding reinforcing bars 26, 26 arranged point-symmetrically with respect to the center of the column structure 20.
Is provided. As shown in FIGS. 5 and 6 in an enlarged manner,
The separator hardware 27 is fixed to the hoop 23 by the positioning hardware 28, and its end 2.
7a is the form tie hardware 29 against the holding steel 26.
Are combined using This makes it possible to appropriately maintain the position of the lath wire mesh 22 and to counteract the lateral pressure of concrete cast inside the lath wire mesh 22.

【0023】次に、柱構造20の構築方法についてを説
明する。まず、図7に示すように、床30上の柱の設置
対象位置に対して、スパイラル筋24を上下方向(軸方
向)に圧縮したものを配置し、さらに、スパイラル筋2
4に囲まれた部分に、主筋21,21,…およびフープ
筋23,23,…からなる鉄筋組立体31を形成する。
この場合、スパイラル筋24が、鉄筋組立作業の邪魔に
ならないように注意する必要がある。
Next, a method of constructing the pillar structure 20 will be described. First, as shown in FIG. 7, a spiral muscle 24 that is compressed in the vertical direction (axial direction) is arranged at the installation target position of the pillar on the floor 30.
4 and a reinforcing bar assembly 31 composed of main bars 21, 21,... And hoop bars 23, 23,.
In this case, care must be taken so that the spiral streaks 24 do not hinder the rebar assembling work.

【0024】次に、図8に示すように、床30上に配置
されたスパイラル筋24を上下方向に引き伸ばし、鉄筋
組立体31に対して固定することによって、これを下地
鉄骨としてセットする。
Next, as shown in FIG. 8, the spiral streaks 24 arranged on the floor 30 are stretched in the vertical direction and fixed to the reinforcing bar assembly 31 so that they are set as base steel frames.

【0025】さらに、図9に示すように、セパレーター
金物27,…を適所に配置し、これをフープ筋23に対
して緊結する。続いて、図10に示すように、スパイラ
ル筋24の外方からラス金網22を隙間無く張り巡ら
し、これらスパイラル筋24およびラス金網22を図示
しない結束線によって各所で固定する。
Further, as shown in FIG. 9, the metal parts 27,... Subsequently, as shown in FIG. 10, a lath wire mesh 22 is stretched from outside the spiral streaks 24 without any gap, and the spiral wires 24 and the lath wire mesh 22 are fixed at various places by binding wires (not shown).

【0026】さらに、ラス金網22の周囲に押さえ鉄筋
26,26,…(図5,6参照)を配置し、この押さえ
鉄筋26,26,…を、セパレータ金物27,27,…
とフォームタイ金物29,29,…(図5,6参照)と
を用いて外方から締め付けることにより、フープ筋2
3,23,…とスパイラル筋24,24,…とが正しい
かぶり寸法を保持するようにする。さらに、図11に示
すように、押さえ鉄筋26,26,…(図5,6参照)
とは別に、竪端太パイプ32,32,…をラス金網22
の周囲の各所に配置して、ラス金網22をより一層強固
に保持できるようにする。
(See FIGS. 5 and 6) are arranged around the lath wire mesh 22. The holding reinforcing bars 26, 26,.
(See FIGS. 5 and 6) and from outside using the form tie hardware 29, 29,.
, And the spiral streaks 24, 24,... Maintain the correct cover size. Further, as shown in FIG. 11, the holding reinforcing bars 26, 26,.
Separately, the vertical thick pipes 32, 32,.
Are arranged at various places around the lath so that the lath wire mesh 22 can be held more firmly.

【0027】そして、図12に示すように、ラス金網2
2内にコンクリートを打設し、コンクリートの硬化後に
は、竪端太パイプ32,32,…を撤去することによっ
て、柱構造20を完成することができる。
Then, as shown in FIG.
After the concrete is poured into the concrete 2 and the concrete is hardened, the columnar structure 20 can be completed by removing the vertical thick pipes 32, 32,.

【0028】上述の柱構造20においては、ラス金網2
2に囲まれた空間内にコンクリートが打設されて、コン
クリートとラス金網22とが付着する構成とされること
から、コンクリートがその外周からラス金網22によっ
て補強されることとなり、これにより、通常の鉄筋コン
クリート柱に比較して靱性の高い構造を実現することが
できる。したがって、耐震性を得るために柱断面を大き
くしたり、コンクリート材料自体の強度を高めたり、あ
るいは、鉄筋の量を増やす等の必要が無く、コストおよ
び建築計画の面において有利である。
In the above-described column structure 20, the lath wire mesh 2
The concrete is poured into the space surrounded by 2 and the concrete and the lath wire mesh 22 adhere to each other, so that the concrete is reinforced by the lath wire mesh 22 from the outer periphery thereof. A reinforced concrete column can realize a structure with higher toughness. Therefore, there is no need to increase the column cross section, increase the strength of the concrete material itself, or increase the amount of reinforcing bars in order to obtain earthquake resistance, which is advantageous in terms of cost and construction planning.

【0029】また、この場合、上述のように柱構造20
を囲むようにスパイラル筋24を設ければ、ラス金網2
2を強固に補強して、柱構造20の靱性をさらに向上さ
せ、より耐震性に優れた構造を実現することができる。
In this case, as described above, the pillar structure 20 is used.
The spiral wire 24 is provided so as to surround the lath wire mesh 2
2 can be strongly reinforced to further improve the toughness of the column structure 20 and realize a structure with more excellent earthquake resistance.

【0030】また、上述の柱構造20の構築方法におい
ては、ラス金網22が捨て型枠とされるために、通常の
鉄筋コンクリート柱と異なり、現場の型枠組立が容易で
あるとともに、型枠の脱型作業が必要でなく、現場労務
の大幅な省人化を図ることができる。さらに、従来の打
ち込み型枠工法とも異なり、ラス金網22を通じてコン
クリートの打設状況を把握できるために、作業の容易化
を図ることができ、施工性に優れている。
Also, in the above-described method of constructing the column structure 20, the lath wire mesh 22 is used as a discarded formwork, so that it is easy to assemble the formwork on site, unlike a normal reinforced concrete column, and to form the formwork. Since no demolding work is required, labor-saving of on-site labor can be greatly reduced. Further, unlike the conventional driving formwork method, since the concrete placing condition can be grasped through the lath wire mesh 22, the work can be facilitated and the workability is excellent.

【0031】また、上述のように、あらかじめスパイラ
ル筋24を圧縮した状態で、床30に載置しておき、主
筋21,21,…等の立設作業後に、このスパイラル筋
を上方に引き伸ばすようにすれば、スパイラル筋24を
簡単に取り付けることができ、ラス金網22を容易に補
強することが可能である。
As described above, the spiral muscle 24 is placed on the floor 30 in a state where it is compressed in advance, and after the main muscles 21, 21,... Are erected, the spiral muscle is stretched upward. In this case, the spiral streaks 24 can be easily attached, and the lath wire mesh 22 can be easily reinforced.

【0032】以上において本発明の実施の形態の一例を
説明したが、本発明は上記実施の形態に限定されるもの
でなく、構造上、意匠上の要求等に応じて、変形あるい
は他の構成を採用することができる。
Although an example of the embodiment of the present invention has been described above, the present invention is not limited to the above-described embodiment, but may be modified or modified in accordance with structural and design requirements. Can be adopted.

【0033】例えば、上記実施の形態の柱構造20は、
断面が円形の場合の例であったが、その代わりに、図1
3および図14に示すように、矩形断面を持つ柱構造3
5を形成してもよい。
For example, the column structure 20 of the above embodiment is
Although the example of the case where the cross section is circular is shown in FIG.
As shown in FIG. 3 and FIG.
5 may be formed.

【0034】図13および14においては、柱構造35
の断面形状に対応して、フープ筋37およびスパイラル
筋38が上方から見た場合に略正方形をなすような形状
に形成されているが、その他の構成については、上記実
施の形態とほぼ共通であるため、これら共通する構成に
ついては、上記実施の形態と同一の符号を用いている。
13 and 14, a pillar structure 35 is shown.
The hoop streaks 37 and the spiral streaks 38 are formed to have a substantially square shape when viewed from above, corresponding to the cross-sectional shape of FIG. Therefore, the same reference numerals are used for these common components as in the above embodiment.

【0035】また、柱構造35の構造の詳細は、図15
から図18において示すとおりである。この場合、上記
実施の形態に比較して、コンクリート打設時にラス金網
22およびスパイラル筋38に対してより大きな側圧が
作用することから、図中に示すように、ラス金網22の
周囲に竪端太パイプ32を適宜配置し、これをフォーム
タイ金物29を用いてセパレーター金物27に対して強
固に固定しておく必要がある。
The details of the structure of the pillar structure 35 are shown in FIG.
18 to FIG. In this case, a larger lateral pressure acts on the lath wire mesh 22 and the spiral streaks 38 during concrete casting than in the above-described embodiment. It is necessary to arrange the thick pipe 32 as appropriate and firmly fix it to the separator hardware 27 using the foam tie hardware 29.

【0036】また、以上説明したような柱構造20また
は35に対して、化粧仕上げが必要な場合は、その外周
面に、モルタル塗りの仕上げを施したり、あるいは、プ
ラスターボードを接着材で貼り付ける等することによっ
て対処が可能である。
When a decorative finish is required for the pillar structure 20 or 35 described above, the outer peripheral surface thereof is finished with mortar, or a plaster board is attached with an adhesive. Can be dealt with.

【0037】[0037]

【発明の効果】以上説明したように、請求項1に係る柱
構造においては、金網に囲まれた空間内にコンクリート
が打設されて、コンクリートと金網とが付着する構成と
されるため、コンクリートをその外周から補強して、靱
性の高い構造を実現することができる。したがって、耐
震性を得るために柱断面を大きくしたり、コンクリート
材料自体の強度を高めたり、あるいは、鉄筋の量を増や
す等の必要が無く、コストおよび建築計画の面において
有利である。さらに、金網を捨て型枠とすることができ
るために、施工性に優れている。またこの際に、請求項
2のように、柱構造を囲むようにスパイラル筋を設けれ
ば、金網を強固に補強することができ、柱構造の靱性を
さらに向上させ、より耐震性に優れた構造を実現するこ
とができる。
As described above, in the pillar structure according to the first aspect, concrete is poured into the space surrounded by the wire mesh so that the concrete and the wire mesh adhere to each other. Can be reinforced from its outer periphery to realize a structure with high toughness. Therefore, there is no need to increase the column cross section, increase the strength of the concrete material itself, or increase the amount of reinforcing bars in order to obtain earthquake resistance, which is advantageous in terms of cost and construction planning. Further, since the wire mesh can be used as a discarded formwork, the workability is excellent. Further, at this time, by providing a spiral streak so as to surround the column structure as in claim 2, the wire mesh can be strongly reinforced, the toughness of the column structure is further improved, and the seismic resistance is further improved. The structure can be realized.

【0038】また、請求項3に係る柱構造の構築方法に
おいては、金網が捨て型枠とされるために、通常の鉄筋
コンクリート柱と異なり、現場の型枠組立が容易である
とともに、型枠の脱型作業が必要でなく、現場労務の大
幅な省人化を図ることができる。さらに、従来の打ち込
み型枠工法とも異なり、金網を通じてコンクリートの打
設状況を把握できるために、作業の容易化を図ることが
できる。また、この場合、請求項4のように、あらかじ
め圧縮しておいたスパイラル筋の内側に主筋を立設し、
その後に、スパイラル筋を上方に引き伸ばすようにすれ
ば、金網を補強するためのスパイラル筋を簡単に取り付
けることができ、請求項3の発明を良好に実現すること
ができる。
In the method of constructing a pillar structure according to the third aspect, since the wire mesh is a discarded formwork, unlike a normal reinforced concrete column, it is easy to assemble the formwork on site and to form the formwork. Since no demolding work is required, labor-saving of on-site labor can be greatly reduced. Further, unlike the conventional driving formwork method, since the concrete placing condition can be grasped through a wire mesh, the work can be facilitated. In this case, the main muscle is erected inside the spiral muscle that has been compressed in advance, and
After that, if the spiral streaks are stretched upward, the spiral streaks for reinforcing the wire mesh can be easily attached, and the invention of claim 3 can be favorably realized.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の一実施の形態を模式的に示す柱構造
の正面図である。
FIG. 1 is a front view of a pillar structure schematically showing an embodiment of the present invention.

【図2】 同、平断面図である。FIG. 2 is a plan sectional view of the same.

【図3】 図1,2に示した柱構造の詳細を示す正面図
である。
FIG. 3 is a front view showing details of a pillar structure shown in FIGS.

【図4】 同、平断面図である。FIG. 4 is a plan sectional view of the same.

【図5】 図4に示したセパレーター金物とフープ筋お
よび押さえ鉄筋との取り合いを示した平断面図である。
FIG. 5 is a plan sectional view showing how the metal fittings of the separator shown in FIG.

【図6】 同、立断面図である。FIG. 6 is a vertical sectional view of the same.

【図7】 本発明の柱構造の施工方法を示す図であっ
て、鉄筋組立体を立設した際の状況を示す正面図であ
る。
FIG. 7 is a view showing a method of constructing a column structure according to the present invention, and is a front view showing a situation when a reinforcing bar assembly is erected.

【図8】 同、スパイラル筋をセットした際の状況を示
す正面図である。
FIG. 8 is a front view showing the situation when the spiral muscle is set.

【図9】 同、セパレーター金物を取り付けた際の状況
を示す正面図である。
FIG. 9 is a front view showing the situation when a metal separator is attached.

【図10】 同、ラス金網をスパイラル筋の周囲に張り
巡らした際の状況を示す正面図である。
FIG. 10 is a front view showing the situation when the lath wire mesh is stretched around the spiral streaks.

【図11】 同、竪端太パイプおよびフォームタイ金物
を取り付けた際の状況を示す正面図である。
FIG. 11 is a front view showing the situation when the vertical pipe and the foam tie hardware are attached.

【図12】 同、コンクリート打設時の状況を示す正面
図である。
FIG. 12 is a front view showing the situation during concrete placement.

【図13】 本発明の他の実施の形態を模式的に示す柱
構造の平断面図である。
FIG. 13 is a plan sectional view of a pillar structure schematically showing another embodiment of the present invention.

【図14】 同、正面図である。FIG. 14 is a front view of the same.

【図15】 図13,14に示した柱構造の詳細を示す
正面図である。
FIG. 15 is a front view showing details of the column structure shown in FIGS.

【図16】 同、平断面図である。FIG. 16 is a plan sectional view of the same.

【図17】 図16に示したセパレーター金物とフープ
筋および竪端太パイプとの取り合いを示した平断面図で
ある。
FIG. 17 is a cross-sectional plan view showing the connection between the separator hardware shown in FIG. 16 and the hoop streak and the vertical pipe.

【図18】 同、立断面図である。FIG. 18 is an elevational sectional view of the same.

【図19】 本発明の従来の技術を示す図であって、合
板型枠材を用いて鉄筋コンクリート製の柱構造を形成す
る際の状況を示す正面図である。
FIG. 19 is a view showing a conventional technique of the present invention, and is a front view showing a situation when a reinforced concrete column structure is formed using a plywood form material.

【図20】 同、平断面図である。FIG. 20 is a plan sectional view of the same.

【図21】 本発明の従来の技術の他の例を示す図であ
って、打ち込み型枠工法を用いて鉄筋コンクリート製の
柱構造を形成する際の状況を示す正面図である。
FIG. 21 is a view showing another example of the prior art of the present invention, and is a front view showing a situation when a reinforced concrete column structure is formed using a driving form method.

【図22】 同、平断面図である。FIG. 22 is a plan sectional view of the same.

【符号の説明】[Explanation of symbols]

20,35 柱構造 21 主筋 22 ラス金網 24,38 スパイラル筋 20, 35 pillar structure 21 main reinforcement 22 lath wire mesh 24, 38 spiral reinforcement

Claims (4)

【特許請求の範囲】[Claims] 【請求項1】 主筋と、主筋を囲むように配置された金
網とを備えてなり、該金網内部にはコンクリートが打設
されて、該コンクリートと該金網とが付着する構成とさ
れていることを特徴とする柱構造。
1. A structure comprising a main reinforcement and a wire mesh arranged so as to surround the main reinforcement, wherein concrete is cast into the inside of the wire mesh, and the concrete and the wire mesh are adhered to each other. A pillar structure characterized by:
【請求項2】 請求項1記載の柱構造であって、 スパイラル筋が、前記柱構造を囲むように、なおかつ、
前記主筋の延在方向がその軸方向となるように配置さ
れ、 前記金網は該スパイラル筋によって補強されていること
を特徴とする柱構造。
2. The pillar structure according to claim 1, wherein a spiral streak surrounds the pillar structure, and
A pillar structure, wherein the main reinforcement is arranged so that an extending direction of the main reinforcement is in the axial direction, and the wire mesh is reinforced by the spiral reinforcement.
【請求項3】 柱構造を構築するための方法であって、 該柱構造の設置対象位置に主筋を立設しておき該主筋を
囲むように金網を設け、 該金網によって囲まれた空間内にコンクリートを打設す
ることを特徴とする柱構造の構築方法。
3. A method for constructing a pillar structure, wherein a main bar is erected at an installation target position of the column structure, a wire mesh is provided so as to surround the main bar, and a space surrounded by the wire mesh is provided. A method of constructing a pillar structure, wherein concrete is poured into a column.
【請求項4】 請求項3記載の柱構造の構築方法であっ
て、 前記主筋を立設するに際しては、スパイラル筋をその軸
方向に圧縮したものを前記柱構造の設置対象位置を囲む
ように配置しておき、該スパイラル筋によって囲まれた
位置に前記主筋を立設し、該主筋の立設後に、前記スパ
イラル筋をその軸方向に引き伸ばすとともに、この引き
伸ばされたスパイラル筋に対して前記金網を固定するこ
とを特徴とする柱構造の構築方法。
4. The method of constructing a pillar structure according to claim 3, wherein, when the main reinforcement is erected, the spiral reinforcement is compressed in the axial direction so as to surround the installation target position of the pillar structure. The main muscle is erected at a position surrounded by the spiral muscle, and after the main muscle is erected, the spiral muscle is stretched in the axial direction, and the wire mesh is stretched with respect to the elongated spiral muscle. A method for constructing a pillar structure, characterized by fixing a pillar.
JP14016598A 1998-05-21 1998-05-21 Column structure and its construction Withdrawn JPH11324224A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14016598A JPH11324224A (en) 1998-05-21 1998-05-21 Column structure and its construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14016598A JPH11324224A (en) 1998-05-21 1998-05-21 Column structure and its construction

Publications (1)

Publication Number Publication Date
JPH11324224A true JPH11324224A (en) 1999-11-26

Family

ID=15262400

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14016598A Withdrawn JPH11324224A (en) 1998-05-21 1998-05-21 Column structure and its construction

Country Status (1)

Country Link
JP (1) JPH11324224A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001090459A1 (en) * 2000-05-25 2001-11-29 Nippon Steel Corporation Net body using spiral wires

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001090459A1 (en) * 2000-05-25 2001-11-29 Nippon Steel Corporation Net body using spiral wires
US6684912B2 (en) 2000-05-25 2004-02-03 Nippon Steel Corporation Net body using helical wire members

Similar Documents

Publication Publication Date Title
JP2522714B2 (en) Construction method of building frame
KR20120013739A (en) Method of Constructing Insitu Concrete Beam Using Preinstalled Precast Concrete Slab
JP2915897B1 (en) Building construction method
KR100731593B1 (en) A pre-fabricating forms for concrete-structure and the construction method thereof
JP2008075449A (en) Rigid-frame viaduct construction method
JPH11324224A (en) Column structure and its construction
JP2001059360A (en) Earthquake resisting wall, and earthquake resistant reinforcing construction method for existing building
JP2005030195A (en) Structure and its construction method
CN214061940U (en) Precast concrete assembled structure with rib mold structure
JP2002357009A (en) Vibration-control beam and method for building it
JP3889497B2 (en) Molding method for concrete basement
JPH0665973A (en) Constructing method of reinforced concrete structure such as foundation, wall, etc., and structure thereof
JP2000073448A (en) Connection method and structure for precast concrete beam and column
JPS6124735A (en) Mold frame for casting concrete
JPS6043547A (en) Mold frame and reinforcement iron integral assembling and constructing method
JP2004190423A (en) METHOD OF ANCHORING PC STEEL AT JOINT BETWEEN PCaPC COLUMN AND BEAM
JPH06158863A (en) Method for constructing concrete frame
JP2614000B2 (en) Basics of steel frame
JPH06306951A (en) Frame for multistoried building
JPH06136821A (en) Construction method for steel frame reinforced concrete structure
JP2018178609A (en) Building method and building
JP2578671B2 (en) Column and beam construction method
JPH08232366A (en) High damping building and construction method therefor
JPH05311748A (en) Connecting execution method of pole and beam
JPS6351529A (en) Construction of reinforced concrete underground beam and slab

Legal Events

Date Code Title Description
A300 Withdrawal of application because of no request for examination

Free format text: JAPANESE INTERMEDIATE CODE: A300

Effective date: 20050802