JPH10266134A - Construction method of bridge utilizing stretched cable - Google Patents
Construction method of bridge utilizing stretched cableInfo
- Publication number
- JPH10266134A JPH10266134A JP7157297A JP7157297A JPH10266134A JP H10266134 A JPH10266134 A JP H10266134A JP 7157297 A JP7157297 A JP 7157297A JP 7157297 A JP7157297 A JP 7157297A JP H10266134 A JPH10266134 A JP H10266134A
- Authority
- JP
- Japan
- Prior art keywords
- cable
- bridge
- construction
- girder
- pier
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
【0001】[0001]
【発明の属する技術分野】本発明は、張設ケーブルを利
用した橋梁の構築工法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method of a bridge using an extension cable.
【0002】[0002]
【従来の技術】従来の橋梁、特に、最大支間50〜15
0m程度の山岳橋梁では、図10に示したような張出し
架設工法により橋梁が構築されている。すなわち、ケー
ブルクレーン(図示せず)を用いて予め構築された中間
橋脚52まで工事用道路54を構築し、この工事用道路
54を通って資材及び機材を運搬し、中間橋脚52上に
タワークレーン50を組み上げると共に、このタワーク
レーン50により移動式作業車51を吊り上げて中間橋
脚52上に設置し、この移動式作業車51により桁部材
56aを架設して主桁56を構築する。2. Description of the Related Art Conventional bridges, particularly, a maximum span of 50 to 15 spans.
In a mountain bridge of about 0 m, a bridge is constructed by an overhanging erection method as shown in FIG. That is, a construction road 54 is constructed using a cable crane (not shown) to the pre-constructed intermediate pier 52, materials and equipment are transported through the construction road 54, and a tower crane is placed on the intermediate pier 52. The mobile work vehicle 51 is lifted by the tower crane 50 and installed on the intermediate pier 52, and a girder member 56a is erected by the mobile work vehicle 51 to construct the main girder 56.
【0003】[0003]
【発明が解決しようとする課題】山岳橋梁は急峻な地形
に建設されることが多く、かような地形で工事用道路5
4を構築しようとすると、工事用道路54は延長距離が
長くなる傾向があって工事費が膨大になったり、自然環
境を破壊したり、さらには工事用道路54の構築そのも
のが困難であるため工期が長くなるという問題点があ
る。Mountain bridges are often constructed on steep terrain, and construction roads 5
When the construction road 4 is to be constructed, the construction road 54 tends to be long in length, resulting in enormous construction costs, destruction of the natural environment, and difficulty in constructing the construction road 54 itself. There is a problem that the construction period becomes long.
【0004】また図10に示した張出し架設工法におい
て、両方向に延長しながら構築する主桁56は、構築
中、単一の中間橋脚52のみに支持されているため、比
較的不安定な構造となっており、例えば、両矢印Pで示
したような地震が発生した場合、その地震応答により両
矢印Q1のように大きく左右に振動する。したがって、
地震に対抗するため、中間橋脚52の所要断面力が、橋
梁完成後の設計断面力よりも大きくなる場合があり、そ
の場合には、構築中の地震に対する補強対策が必要とな
り、施工コストの上昇を招くという問題点がある。In the overhanging erection method shown in FIG. 10, the main girder 56, which is constructed while extending in both directions, is supported by only a single intermediate pier 52 during construction. it is, for example, when an earthquake as indicated by a double-headed arrow P occurs, vibrates largely left as double-headed arrow Q 1 by the seismic response. Therefore,
In order to resist earthquakes, the required section force of the intermediate pier 52 may be larger than the design section force after completion of the bridge. In that case, reinforcement measures for the earthquake under construction are required, and construction costs increase. There is a problem of inviting.
【0005】本発明は、上記従来の問題点を解決せんと
したものであり、その課題は、中間橋脚まで資材や機材
を搬送するための工事用道路を必要とせず、故に、施工
コスト低減や工期短縮が図れる橋梁の構築工法を提供す
ることにある。SUMMARY OF THE INVENTION The present invention has been made to solve the above-mentioned conventional problems, and has a problem that a construction road for transporting materials and equipment to an intermediate pier is not required. An object of the present invention is to provide a bridge construction method capable of shortening the construction period.
【0006】本発明の別の課題は、橋梁構築中の地震に
よる中間橋脚の断面力を、橋梁完成後の中間橋脚の設計
断面力よりも大きくすること無く、構築中における橋梁
の耐震性を向上させることができる橋梁の構築工法を提
供することにある。Another object of the present invention is to improve the seismic resistance of a bridge during construction without making the sectional force of the intermediate pier caused by an earthquake during construction of the bridge larger than the design sectional force of the intermediate pier after completion of the bridge. An object of the present invention is to provide a bridge construction method capable of causing the bridge to be constructed.
【0007】[0007]
【課題を解決するための手段】本発明は、上記課題を解
決するために、橋台間にケーブルを張設する工程と、橋
台間に予め立設された橋脚に該ケーブルを固定する工程
と、前記ケーブルを軌道として、橋桁を構成する桁部材
の複数を橋台間で順次搬送し、橋台・橋脚間及び橋脚間
に連設する工程とを含むことを特徴とする橋梁の構築工
法を提供する。SUMMARY OF THE INVENTION In order to solve the above-mentioned problems, the present invention provides a step of stretching a cable between abutments, and a step of fixing the cable to a pier previously set between the abutments. A step of sequentially transporting a plurality of girder members constituting the bridge girder between the abutments using the cable as a track, and connecting the girder members to the abutment / pier and between the abutments.
【0008】ここで、本発明における前記桁部材として
は、上床版と、下床版と、該上床版と該下床版とを連結
する腹材とが予めプレキャストコンクリートにて形成さ
れた部材を採用しても良い。Here, as the girder member in the present invention, a member in which an upper slab, a lower slab, and a web member for connecting the upper slab and the lower slab are formed in advance by precast concrete is used. You may adopt it.
【0009】また本発明においては、前記桁部材とし
て、下床版と、該下床版から立設する腹材とが予めプレ
キャスト化されて形成された部材を前記桁部材として採
用し、該桁部材を橋台・橋脚間及び橋脚間に連設した
後、前記腹材の上に上床版を形成する工程を含んでも良
い。In the present invention, a member formed by precasting a lower slab and an abdominal material erected from the lower slab in advance is adopted as the spar member. After the members are connected between the abutment and the pier and between the piers, a step of forming an upper floor slab on the abdominal material may be included.
【0010】さらに本発明では、橋桁を構成する桁部材
の複数を、ケーブルを軌道として橋台間で搬送する工程
において、桁部材を搬送する際の牽引手段としては、例
えば、エンドレスウインチ、シングルウインチ、又はチ
ルホール等の簡易な牽引・搬送手段を採用することがで
きる。また本工程において、ケーブルを軌道として桁部
材を搬送するとは、前記プレキャスト部材の荷重の一部
又は全てをケーブルにより支持しながら、このケーブル
に沿って搬送することを意味する。例えば、ケーブルに
摺動可能な手段か、あるいはケーブルに転動可能な手段
を桁部材に設ければ、該工程は容易に実施することがで
きる。Further, in the present invention, in the step of transporting a plurality of girder members constituting the bridge girder between the abutments using a cable as a track, as a traction means for transporting the girder member, for example, an endless winch, a single winch, Alternatively, a simple towing / transporting means such as a chill hole can be employed. In this step, transporting the girder member using the cable as a track means that the precast member is transported along the cable while supporting part or all of the load of the precast member with the cable. For example, if a means capable of sliding on the cable or a means capable of rolling on the cable is provided on the girder member, this step can be easily performed.
【0011】[0011]
【実施例】以下、本発明の実施例を添付図面を参照して
説明するが、本発明はこれに限定されるものではない。
図1は本発明の橋梁構築工法を説明するために、その一
工程を示した説明図であり、図2(a)〜(c)は図1に引き
続く工程を示した説明図であり、図3(a)〜(c)は図2に
引き続く工程を示した説明図である。また図4(a)(b)は
中間橋脚15a上端と、ここに形成されたPCケーブル
固定用の固定具18と、ここを通過する桁部材20との
配置関係を示した一部断面図であり、図5は搬送された
桁部材20を既設の主桁30に連結する際の工程を示し
た側面図であり、図6は図1乃至図3に示された工程と
は、異なる工程を示した説明図であり、図7は桁部材3
5を昇降させるクライミング機構23を示した正面図で
あり、図8(a)(b)は上床版用移動型枠32により上床版
35’を現場施工する工程を説明するための説明図であ
って、特に、図8(a)は図8(b)における切出し線a1−
a1,a2−a2に沿った断面図を、一点鎖線を境に左右
に配置した断面図であり、図9は施工過程において地震
動Pが作用した橋梁を簡略に示した側面図である。DESCRIPTION OF THE PREFERRED EMBODIMENTS Embodiments of the present invention will be described below with reference to the accompanying drawings, but the present invention is not limited thereto.
FIG. 1 is an explanatory view showing one step in order to explain the bridge construction method of the present invention, and FIGS. 2 (a) to 2 (c) are explanatory views showing steps subsequent to FIG. 3 (a) to 3 (c) are explanatory views showing steps subsequent to FIG. FIGS. 4A and 4B are partial cross-sectional views showing the positional relationship between the upper end of the intermediate pier 15a, the fixture 18 for fixing the PC cable formed here, and the girder member 20 passing therethrough. FIG. 5 is a side view showing a process for connecting the transported girder member 20 to the existing main girder 30, and FIG. 6 shows a process different from the processes shown in FIGS. FIG. 7 is an explanatory view shown, and FIG.
8 (a) and 8 (b) are explanatory views for explaining a process of on-site construction of the upper floor slab 35 'by the upper floor slab movable formwork 32. FIG. In particular, FIG. 8A shows the cut line a 1 − in FIG. 8B.
FIG. 9 is a cross-sectional view in which a cross-sectional view taken along a 1 , a 2 −a 2 is arranged on the left and right with a dashed-dotted line as a boundary, and FIG. .
【0012】ある。There is.
【0013】図1乃至図3に示した橋梁の構築工法で
は、橋台11a,11b間にPCケーブル13を張設
し、このPCケーブル13を固定具18によって予め立
設された中間橋脚15a,15b上に固定し、PCケー
ブル13を軌道として、複数の桁部材20を順次搬送
し、橋台11a,11bと中間橋脚15a,15bとの
間及び中間橋脚15a,15b間に連設して主桁30を
構築することを特徴とする。In the bridge construction method shown in FIGS. 1 to 3, a PC cable 13 is stretched between the abutments 11a and 11b, and the PC cable 13 is connected to intermediate bridge piers 15a and 15b which are previously erected by a fixture 18. A plurality of girders 20 are sequentially conveyed by using the PC cable 13 as a track, and connected between the abutments 11a and 11b and the intermediate piers 15a and 15b and between the intermediate piers 15a and 15b to be connected to the main girder 30. Is constructed.
【0014】以下に、上記橋梁の構築工法及びこの工法
で用いる装置について詳細に説明する。山岳橋梁を構築
するに際し、従来通り、工事用道路を構築すること無
く、ケーブルクレーン(図示せず)を用いて橋台11
a,11bと中間橋脚15a,15bとを構築し、橋台
11a,11bは複数のグランドアンカー15や杭等で
地山40に固定し、中間橋脚15a,15bの上端には
PCケーブル13を固定するための仮固定用フレーム1
8aを二本設ける。この二本の仮固定用フレーム18a
は、各中間橋脚15a,15b上の桁幅方向に主桁30
の幅よりも大きく離隔して配置し、図4(a)(b)に示した
ように、上端にケーブルバンド19を備え、このケーブ
ルバンド19は複数のPCケーブル13が挿通可能で、
且つ、挿通後にPCケーブル13を一体に固定できるも
のを使用する。The construction method of the bridge and the equipment used in this method will be described in detail below. When constructing a mountain bridge, a cable bridge (not shown) is used to construct an abutment 11 without constructing a construction road as before.
a, 11b and the intermediate piers 15a, 15b are constructed, and the abutments 11a, 11b are fixed to the ground 40 with a plurality of ground anchors 15 and piles, and the PC cable 13 is fixed to the upper ends of the intermediate piers 15a, 15b. Frame 1 for temporary fixing
8a are provided. These two temporary fixing frames 18a
Is the main girder 30 in the girder width direction on each intermediate pier 15a, 15b.
4 (a) and 4 (b), a cable band 19 is provided at the upper end, and the cable band 19 is capable of inserting a plurality of PC cables 13 therein.
In addition, a cable that can integrally fix the PC cable 13 after insertion is used.
【0015】次いで、図1に示したように、橋台11
a,11b間にエンドレスウインチ12を設置し、この
エンドレスウインチ12により複数のPCケーブル13
を搬送しながらケーブルバンド19内に挿通させて仮固
定し、一方の橋台11aから他方の橋台11bまでPC
ケーブル13を架設し、その後、緊張ジャッキを用いて
PCケーブル13に張力を導入する。かように張力を導
入した後、ケーブルバンド19で複数のPCケーブル1
3を一体に固定し、図4(a)(b)に示したように、施工用
サドル18bを形成する。この施工用サドル18bは、
二本の仮固定用フレーム18aをそれぞれ埋設するよう
に現場打ちコンクリートで形成し、二つの施工用サドル
18bの間には、桁部材20を通過させることができる
クリアランスを確保する。また施工用サドル18bの上
端面には、ローラー23dが転動できる幅の凸部18
b’を設け、この凸部18b’にはPCケーブル13を
埋設すると共に、中央に向かう両側からの上がり勾配を
設ける。Next, as shown in FIG.
An endless winch 12 is installed between the endless winch 12 and a plurality of PC cables 13.
While being transported, is temporarily fixed by being inserted into the cable band 19, and the PC is connected from one abutment 11a to the other abutment 11b.
The cable 13 is erected, and then tension is introduced into the PC cable 13 using a tension jack. After the tension is thus introduced, a plurality of PC cables 1 are
3 are integrally fixed to form a construction saddle 18b as shown in FIGS. 4 (a) and 4 (b). This saddle for construction 18b is
The two temporary fixing frames 18a are formed of cast-in-place concrete so as to be buried respectively, and a clearance through which the girder member 20 can pass is secured between the two construction saddles 18b. The upper end surface of the construction saddle 18b has a projection 18 having a width that allows the roller 23d to roll.
b 'is provided, and the PC cable 13 is buried in the protruding portion 18b' and a rising gradient is provided from both sides toward the center.
【0016】次に、図2(a)に示したように、橋台11
a上にエレクションノーズ21を組み立て、端部プレキ
ャスト部材17をエンドレスウインチ12で搬送して橋
台11bに固定する。そして、図2(b)に示したよう
に、エレクションノーズ21により、桁部材20を昇降
し、桁部材20の上端をエンドレスウインチ12に係合
して、PCケーブル13上を転動させて搬送する。ここ
で、主桁30を構成する各桁部材20としては、上床版
20aと、下床版20cと、これら上床版20aと下床
版20cとを連結する腹材20bとが、工場等において
予めプレキャストコンクリート等によって形成された部
材を採用する。また各桁部材20には、図4(a)(b)に示
したように、慣用のガイドレール22と慣用のクライミ
ング装置23とを予め固定しておく。すなわち、図示は
しないが、ガイドレール22は軸方向に延在するように
複数の孔が形成されたフランジを備え、締結具24によ
り腹材20bに固定される。またクライミング装置23
は、上方摺動部23a及び下方摺動部23cがガイドレ
ール22に嵌合可能かつ摺動可能なように形成されると
共に、ガイドレール22のフランジに設けられた孔にピ
ン(図示せず)を自在に抜き差しできる機構を備え、該
上方摺動部23aがジャッキ23bの上端に枢着され、
ジャッキ23bの下端に下方摺動部23cが枢着され、
下方摺動部23cにはブラケット23eを介してローラ
ー23dが設けられて形成されている。かような慣用の
クライミング装置23は、ジャッキ23bの伸長動作
と、上方摺動部23a及び下方摺動部23cにおけるピ
ンの抜き差し動作とが適宜繰り返されて、シャクトリ虫
のような動作でガイドレール22に沿って昇降するもの
である。上述した桁部材20のPCケーブル13上にお
ける転動は、前記桁部材20に前記ガイドレール22及
び前記クライミング装置23を固定し、クライミング装
置23のローラー23dをPCケーブル13上に載置
し、エンドレスウインチ12で桁部材20を牽引してロ
ーラー23dをPCケーブル13上で転がすことにより
実現される。また桁部材20が搬送されて中間橋脚15
a,15bに達すると、ローラー23dはPCケーブル
13から凸部18b’の上面に移り、ここを転がりなが
ら、桁部材20が二つの施工用サドル18bの間を通過
し、再度、ローラー23dはPCケーブル13上を転動
する。Next, as shown in FIG.
An erection nose 21 is assembled on a, and the end precast member 17 is transported by the endless winch 12 and fixed to the abutment 11b. Then, as shown in FIG. 2 (b), the spar member 20 is raised and lowered by the erection nose 21, the upper end of the spar member 20 is engaged with the endless winch 12, and is rolled on the PC cable 13 to be conveyed. I do. Here, as each girder member 20 constituting the main girder 30, an upper floor slab 20a, a lower floor slab 20c, and an abdominal material 20b connecting the upper floor slab 20a and the lower floor slab 20c are prepared in advance in a factory or the like. A member made of precast concrete or the like is used. Also, as shown in FIGS. 4A and 4B, a conventional guide rail 22 and a conventional climbing device 23 are fixed to each beam member 20 in advance. That is, although not shown, the guide rail 22 includes a flange having a plurality of holes formed so as to extend in the axial direction, and is fixed to the abdominal member 20b by the fastener 24. The climbing device 23
The upper sliding portion 23a and the lower sliding portion 23c are formed so as to be fittable and slidable on the guide rail 22, and a pin (not shown) is provided in a hole provided in a flange of the guide rail 22. The upper sliding portion 23a is pivotally attached to the upper end of the jack 23b,
A lower sliding portion 23c is pivotally attached to a lower end of the jack 23b,
The lower sliding portion 23c is provided with a roller 23d via a bracket 23e. In such a conventional climbing device 23, the operation of extending the jack 23b and the operation of pulling out and inserting the pins in the upper sliding portion 23a and the lower sliding portion 23c are repeated as appropriate, so that the guide rail 22 is moved like a shark insect. It goes up and down along. The above-mentioned rolling of the girder member 20 on the PC cable 13 is performed by fixing the guide rail 22 and the climbing device 23 to the girder member 20, placing the roller 23 d of the climbing device 23 on the PC cable 13, This is realized by pulling the spar member 20 by the winch 12 and rolling the roller 23 d on the PC cable 13. Further, the girder member 20 is conveyed to the intermediate pier 15
a and 15b, the roller 23d moves from the PC cable 13 to the upper surface of the convex portion 18b ', and while rolling, the girder member 20 passes between the two construction saddles 18b. Roll on the cable 13.
【0017】上述のように搬送した桁部材20は、図2
(b)に示したように、橋台11bに設置された端部プレ
キャスト部材17に連結され、さらに桁部材20は順次
搬送されて先に設置された桁部材20に連結される工程
が繰り返され、これにより主桁30は中間橋脚15bに
向かって徐々に張り出すように構築される。ここで、搬
送された桁部材20と既設の桁部材20との連結工程を
更に詳細に示せば、図5のようになる。すなわち、エレ
クションノーズ21で桁部材20を吊り上げる前に、桁
部材20左側の上下所定位置にはPC鋼棒26を突設し
ておき、一方、既設の主桁30端部の上下には引込みジ
ャッキ25を固定する。そして、桁部材20が搬送され
て既設の主桁30端部から所定長離隔した位置まで近づ
いた時点で、PC鋼棒26を引込みジャッキ25に挿通
し、この引込みジャッキ25で桁部材20を引き込ん
で、既設の主桁30端部に連結する。The spar member 20 transported as described above is shown in FIG.
As shown in (b), the process of being connected to the end precast member 17 installed on the abutment 11b, and the beam member 20 being sequentially transported and connected to the previously installed beam member 20 is repeated, Thus, the main girder 30 is constructed so as to gradually project toward the intermediate pier 15b. Here, the connection process between the conveyed girder member 20 and the existing girder member 20 is shown in more detail in FIG. That is, before the spar member 20 is lifted by the erection nose 21, the PC steel bar 26 is protruded at predetermined positions on the left and right sides of the spar member 20, while the retraction jacks are provided above and below the end of the existing main girder 30. 25 is fixed. Then, when the girder member 20 is conveyed and approaches a position separated by a predetermined length from the end of the existing main girder 30, the PC steel bar 26 is inserted into the retraction jack 25, and the girder member 20 is retracted by the retraction jack 25. Then, it is connected to the end of the existing main girder 30.
【0018】かような桁部材20の連結工程と前記搬送
工程とを繰返し、図3(a)に示したように、主桁30が
中間橋脚15bを越えて中間橋脚15aと15bとの中
央に達したら、次に、中間橋脚15aから橋台11aに
向かって主桁30が張出すように、桁部材20の連結工
程と搬送工程とを繰返し、中間橋脚15aと橋台11a
との間に主桁30が架設されたら、PCケーブル13及
びエンドレスウインチ12を撤去する。The connecting step of the girder member 20 and the transporting step are repeated, and as shown in FIG. 3A, the main girder 30 moves beyond the intermediate pier 15b to the center of the intermediate piers 15a and 15b. Then, the connecting step and the transporting step of the girder member 20 are repeated so that the main girder 30 extends from the intermediate pier 15a toward the abutment 11a, and the intermediate pier 15a and the abutment 11a are repeated.
When the main girder 30 is erected between the PC and the PC, the PC cable 13 and the endless winch 12 are removed.
【0019】次いで、中間橋脚15aから主桁端部30
aに向けて桁部材20の張出し架設を行うため、エレク
ションノーズ21を中間橋脚15aまで移動し、図3
(b)に示したように、このエレクションノーズ21によ
り桁部材20を吊り上げて、所定高さまで吊り下し、主
桁端部30bに連結する。そして、エレクションノーズ
21を張出し架設の方向に順次移動しながら、主桁端部
30bが主桁端部30aに達するまで桁部材20の連結
工程を繰り返す。中間橋脚15aと15bとの間に主桁
30が架設されたら、最後に、図3(c)に示したよう
に、橋面工作業台車22を用いて地覆や高欄といった橋
面工を設ければ、橋梁は完成する。Next, from the intermediate pier 15a to the main girder end 30
The erection nose 21 is moved to the intermediate pier 15a in order to erection of the girder member 20 toward a.
As shown in (b), the girder member 20 is lifted by the erection nose 21, hung to a predetermined height, and connected to the main girder end 30b. Then, while sequentially moving the erection nose 21 in the direction of erection and erection, the connecting process of the girder members 20 is repeated until the main girder end 30b reaches the main girder end 30a. When the main girder 30 is erected between the intermediate piers 15a and 15b, finally, as shown in FIG. 3 (c), a pier such as a ground cover or a railing is provided using the pier work truck 22. Then, the bridge is completed.
【0020】なお、上記橋梁の構築方法においては、桁
部材20の替わりに、上床版を現場打ちコンクリートに
て形成する桁部材(例えば、後述する桁部材35)を用
いても良く、この場合には、後述の移動型枠装置32を
用いれば上床版を形成することができる。In the bridge construction method, instead of the girder member 20, a girder member (for example, a girder member 35 described later) in which the upper slab is formed from cast-in-place concrete may be used. By using a movable form device 32 to be described later, an upper floor slab can be formed.
【0021】次に、図1乃至図3に示した工法とは異な
る工法について、図6を参照して説明する。図6の橋梁
の構築工法では、図1乃至図3に示した工法と同様に、
橋台11a,11bと中間橋脚15a,15bとを構築
し、橋台11a,11b間にエンドレスウインチ12を
設置すると共に、このエンドレスウインチ12を用いて
PCケーブル13を架設し、PCケーブル13に張力を
導入した後に、施工用サドル18bを形成する。ここ
で、主桁30を構成する桁部材35としては、図7及び
図8に示したように、下床版35cと、この下床版20
cから立設された腹材35bとが予めプレキャストコン
クリート等により一体に形成され、腹材35bの上端に
は上方フレーム35aを備え、上床版35’は、現場打
ちコンクリートが上方フレーム35a部分に打設されて
形成される部材を採用する。Next, a method different from the method shown in FIGS. 1 to 3 will be described with reference to FIG. In the construction method of the bridge of FIG. 6, similarly to the construction method shown in FIGS. 1 to 3,
Abutments 11a and 11b and intermediate piers 15a and 15b are constructed, an endless winch 12 is installed between the abutments 11a and 11b, and a PC cable 13 is erected using the endless winch 12 to introduce tension into the PC cable 13. After that, the construction saddle 18b is formed. Here, as the girder members 35 constituting the main girder 30, as shown in FIGS. 7 and 8, a lower floor slab 35 c and this lower floor slab 20
c is integrally formed in advance with precast concrete or the like, and an upper frame 35a is provided at the upper end of the web 35b. A member formed and formed is adopted.
【0022】そして、この桁部材35にはガイドレール
22及びクライミング装置23を固定し、次いで、図6
に示したように、橋台11a上に設置架台(図示せず)
を設け、この設置架台によって桁部材35を上昇して、
その上端をエンドレスウインチ12に係合し、ローラー
23dをPCケーブル13上に転動させて、桁部材35
を搬送する。そして、中間橋脚15aにおいては、搬送
した桁部材35を順次両方向に張り出すように連結して
主桁31a,31bを形成し、同時に、中間橋脚15b
においても主桁31c,31dを両方向に張出し架設
し、主桁31aは橋台11aまで延設し、主桁31bと
主桁31cとは相互に連結されるまで延設し、さらに主
桁31dは橋台11bに達するまで延設すれば、桁部材
35の架設工程は終了する。ここで、図6に示したよう
に、搬送時の桁部材35の高さが、主桁31a,31
b,31c,31dの高さと大きく異なる場合には、桁
部材35が各主桁における連結位置に達した時点で、図
7に示したように、クライミング装置23をガイドレー
ル22に沿って適宜昇降し、桁部材35の高さを各主桁
31a,31b,31c,31dの端部の高さと合わせ
てから、相互に連結する。Then, the guide rail 22 and the climbing device 23 are fixed to the beam member 35.
As shown in the above, the gantry (not shown) installed on the abutment 11a
Is provided, and the girder member 35 is raised by this installation base,
The upper end thereof is engaged with the endless winch 12, and the roller 23d is rolled on the PC cable 13 so that the spar member 35
Is transported. In the intermediate pier 15a, the conveyed girder members 35 are sequentially connected so as to project in both directions to form the main girder 31a, 31b.
In the above, the main girder 31c, 31d is also extended and installed in both directions, the main girder 31a is extended to the abutment 11a, the main girder 31b and the main girder 31c are extended until they are connected to each other, and further, the main girder 31d is abutment. If it is extended until it reaches 11b, the erection process of the girder member 35 is completed. Here, as shown in FIG. 6, the height of the girder member 35 at the time of conveyance is determined by the main girder 31a, 31.
When the heights of the beam members 35, 31c and 31d are significantly different from each other, the climbing device 23 is moved up and down along the guide rails 22 as shown in FIG. Then, the height of the beam members 35 is adjusted to the height of the end of each of the main beams 31a, 31b, 31c, 31d, and then connected to each other.
【0023】また上記桁部材35の架設工程と並行し
て、上床版35’の構築工程も行い、この上床版35’
の構築工程が終了すれば橋梁は完成する。ここで、上床
版35’の構築工程では、図8に示したような慣用の移
動型枠装置32、すなわち、フレーム32aの支柱下端
にキャスター32eが設けられ、フレーム32からは吊
り材32により型枠部材32dと足場32cとが釣支さ
れ、型枠部材32dは高さが適宜調整可能に形成された
もの用いて行う。In parallel with the step of erection of the spar member 35, a step of constructing the upper floor slab 35 'is also performed.
When the construction process is completed, the bridge is completed. Here, in the construction process of the upper floor slab 35 ′, a caster 32 e is provided at the lower end of the support of the frame 32 a, as shown in FIG. The frame member 32d is supported by the scaffold 32c, and the form member 32d is formed by using a member whose height is appropriately adjustable.
【0024】本発明の橋梁の構築工法では、橋台11
a,11b間に張設されたケーブル13が中間橋脚15
a,15bに固定されるので、これら橋台11a,11
bとケーブル13と中間橋脚15a,15bとは、所定
の剛性を備える架構として一体化される。したがって、
主桁の構築中、中間橋脚15a,15bに図9の両矢印
Pのような地震動が作用した場合でも、その地震応答に
よる中間橋脚15a,15bの振動Q2は、ケーブル1
3の張力Tにより抑制される。故に、張出し架設工程に
おいて、単一の中間橋脚のみにより主桁が支持されると
いった不安定な構造でも、構築中の中間橋脚の所要断面
力が、橋梁完成後の設計断面力よりも大きくなることが
無く、構築中の地震に対する補強対策も必要としないた
め施工コストの低減化が図れる。In the bridge construction method of the present invention, the abutment 11
A cable 13 stretched between a and 11b is an intermediate pier 15
a, 15b, these abutments 11a, 11b
b, the cable 13 and the intermediate piers 15a and 15b are integrated as a frame having a predetermined rigidity. Therefore,
During construction of the main girder, the intermediate piers 15a, even when the ground motion, such as a double arrow P in FIG. 9 is applied to 15b, intermediate pier 15a due to the seismic response, vibration Q 2 and 15b, the cable 1
3 is suppressed by the tension T. Therefore, even in an unstable structure where the main girder is supported only by a single intermediate pier in the overhanging erection process, the required sectional force of the intermediate pier under construction is larger than the design sectional force after completion of the bridge There is no need for reinforcement measures against earthquakes during construction, so construction costs can be reduced.
【0025】[0025]
【発明の効果】本発明の橋梁の構築工法では、橋台間に
張設されたケーブルを軌道として用いて桁部材を搬送す
るので、従来工法にて構築していた工事用道路を必要と
せず、故に、施工コスト低減や工期短縮が図れる。また
搬送中の桁部材の重量の一部又は全てがケーブルに支持
されるので、桁部材の搬送に用いる牽引装置、例えば、
エンドレスウインチ等の装置が負担する荷重は低減し、
故に、桁部材の搬送工程の容易化やこれら装置の簡略化
が可能になる。According to the bridge construction method of the present invention, since the girder member is transported using the cable stretched between the abutments as a track, a construction road constructed by the conventional method is not required. Therefore, the construction cost and the construction period can be reduced. Also, since part or all of the weight of the beam member being transported is supported by the cable, a traction device used for transporting the beam member, for example,
The load borne by devices such as endless winches is reduced,
Therefore, it is possible to facilitate the process of transporting the girder members and to simplify these devices.
【0026】また本発明では、橋台間に張設されたケー
ブルが橋脚に固定されるため、橋台とケーブルと橋脚と
が架構のように一体化され、ここに所定の剛性を得るこ
とができる。したがって、主桁を橋脚から張り出すよう
に構築している時に地震が発生しても、その地震応答に
よる橋脚の振動を抑制することができるので、構築中の
橋梁の耐震性を向上させることができると共に、張り出
し施工中の中間橋脚の所要断面力を低減できて施工コス
トの低減化が図れる。In the present invention, since the cable stretched between the abutments is fixed to the pier, the abutment, the cable and the pier are integrated like a frame, and a predetermined rigidity can be obtained here. Therefore, even if an earthquake occurs while the main girder is being constructed to extend from the pier, the vibration of the pier due to the earthquake response can be suppressed, and the seismic resistance of the bridge under construction can be improved. The required cross-sectional force of the intermediate pier during the overhanging construction can be reduced, and the construction cost can be reduced.
【0027】さらに本発明において、下床版と、該下床
版から立設する腹材とが予めプレキャスト化されて形成
された部材を桁部材として採用し、この桁部材を橋台・
橋脚間及び橋脚間に連設した後、腹材の上に上床版を形
成する工程を行えば、搬送中における桁部材の荷重を軽
量化することができて、ケーブルの重量負担を低減化す
ることができる。Further, in the present invention, a member formed by precasting a lower deck and a web material standing upright from the lower deck is adopted as a girder member, and this girder member is used as an abutment / abutment.
If the process of forming the upper floor slab on the abdominal material after the connection between the piers and the piers is performed, the load on the girder member during the transportation can be reduced, and the weight burden of the cable is reduced. be able to.
【図1】本発明の橋梁構築工法を説明するために、その
一工程を示した説明図である。FIG. 1 is an explanatory view showing one step of a bridge construction method according to the present invention for explaining the method.
【図2】(a)〜(c)は図1に続く工程を示した説明図であ
る。FIGS. 2 (a) to 2 (c) are explanatory diagrams showing steps subsequent to FIG.
【図3】(a)〜(c)は図2に続く工程を示した説明図であ
る。FIGS. 3 (a) to 3 (c) are explanatory views showing steps subsequent to FIG. 2;
【図4】(a)(b)は中間橋脚上端と、ここに形成されたP
Cケーブル固定用の固定具と、ここを通過する桁部材と
の配置関係を示した一部断面図である。4 (a) and 4 (b) show the upper end of the intermediate pier and the P formed here.
FIG. 4 is a partial cross-sectional view showing a positional relationship between a fixture for fixing a C cable and a girder member passing therethrough.
【図5】搬送された桁部材を既設の主桁に連結する際の
工程を示した側面図である。FIG. 5 is a side view showing a process when the conveyed girder member is connected to an existing main girder.
【図6】図1乃至図3に示された工程とは、異なる工程
を示した説明図である。FIG. 6 is an explanatory view showing a step different from the steps shown in FIGS. 1 to 3;
【図7】桁部材を昇降させるクライミング機構を示した
正面図である。FIG. 7 is a front view showing a climbing mechanism that raises and lowers the beam member.
【図8】(a)(b)は上床版用移動型枠により上床版を現場
施工する工程を説明するための説明図である。8 (a) and 8 (b) are explanatory diagrams for explaining a process of on-site construction of an upper floor slab using a movable mold for the upper floor slab.
【図9】施工過程において地震動が作用した橋梁を簡略
に示した側面図である。FIG. 9 is a side view schematically showing a bridge on which an earthquake motion has acted in a construction process.
【図10】従来の張出し架設工法を示す側面図である。FIG. 10 is a side view showing a conventional overhang construction method.
11a,11b 橋台 13 PCケーブル(ケーブル) 15a,15b 中間橋脚(橋脚) 18 固定具 20 桁部材(プレキャスト部材) 20a 上床版 20b 腹材 20c 下床版 35 桁部材 35’ 上床版 35b 腹材 35c 下床版 11a, 11b Abutment 13 PC cable (cable) 15a, 15b Intermediate pier (pier) 18 Fixture 20 Girder member (precast member) 20a Upper floor slab 20b Abdominal material 20c Lower floor slab 35 Beam member 35 'Upper floor slab 35b Abdominal material 35c Lower Floor slab
Claims (2)
程と、 前記ケーブルを軌道として、橋桁を構成する桁部材の複
数を橋台間で順次搬送し、橋台・橋脚間及び橋脚間に連
設する工程とを含むことを特徴とする橋梁の構築工法。1. A step of stretching a cable between abutments, a step of fixing the cable to a pier previously erected between the abutments, and using the cable as a track to connect a plurality of girder members constituting a bridge girder. A step of sequentially transporting the bridges between the bridges and connecting them between the abutments / piers and between the piers.
が予めプレキャスト化されて形成された部材を前記桁部
材として採用し、 該桁部材を橋台・橋脚間および橋脚間に連設した後、前
記腹材の上に上床版を形成する工程を含むことを特徴と
する請求項1記載の橋梁の構築工法。2. A member formed by precasting a lower slab and an abdominal material erected from the lower slab in advance are used as the girder members, and the girder members are used between abutments / piers and between piers. 2. The method according to claim 1, further comprising the step of forming an upper floor slab on the web material after the bridge is connected to the bridge.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07157297A JP3146172B2 (en) | 1997-03-25 | 1997-03-25 | Construction method of bridge using extension cable |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP07157297A JP3146172B2 (en) | 1997-03-25 | 1997-03-25 | Construction method of bridge using extension cable |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH10266134A true JPH10266134A (en) | 1998-10-06 |
JP3146172B2 JP3146172B2 (en) | 2001-03-12 |
Family
ID=13464563
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP07157297A Expired - Fee Related JP3146172B2 (en) | 1997-03-25 | 1997-03-25 | Construction method of bridge using extension cable |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP3146172B2 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001020225A (en) * | 1999-07-05 | 2001-01-23 | Mitsubishi Heavy Ind Ltd | Erection method of bridge and equipment therefor |
KR20020012670A (en) * | 2000-08-08 | 2002-02-20 | 김정현 | A Bridge Establishing Method Using Fabricated Jack Support Unit |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP4326711B2 (en) | 2001-02-28 | 2009-09-09 | 富士フイルム株式会社 | Curtain application method |
-
1997
- 1997-03-25 JP JP07157297A patent/JP3146172B2/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001020225A (en) * | 1999-07-05 | 2001-01-23 | Mitsubishi Heavy Ind Ltd | Erection method of bridge and equipment therefor |
KR20020012670A (en) * | 2000-08-08 | 2002-02-20 | 김정현 | A Bridge Establishing Method Using Fabricated Jack Support Unit |
Also Published As
Publication number | Publication date |
---|---|
JP3146172B2 (en) | 2001-03-12 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP3885584B2 (en) | Construction method of composite truss bridge | |
JP5059491B2 (en) | Assembly method of mobile suspension support | |
JP2008274637A (en) | Construction method for continuous viaduct | |
US7415746B2 (en) | Method for constructing a self anchored suspension bridge | |
JP3440422B2 (en) | Bridge construction method and bridge construction device | |
JPH11181724A (en) | Method for constructing horizontal beam of main tower made of concrete | |
JPH11181725A (en) | Method for constructing horizontal beam of main tower made of concrete | |
CN112609595A (en) | Construction method for closure section of beam-arch combined rigid frame bridge | |
JP3146172B2 (en) | Construction method of bridge using extension cable | |
US6412132B1 (en) | Methods for constructing a bridge utilizing in-situ forms supported by beams | |
KR20060002650A (en) | Upper bridge structure construcion method with precast segment deck or box using a lifting traveller | |
CN112160246A (en) | Method for mounting combined beam | |
KR200363059Y1 (en) | Upper bridge structure construcion system with precast segment deck or box using a lifting traveller | |
KR20070010449A (en) | Construction method for arched bridge | |
JP2000104220A (en) | Erection of combined truss bridge | |
JPS6041165B2 (en) | Equipment for cantilevering bridge structures made of reinforced concrete or prestressed concrete into sections. | |
JP4375788B2 (en) | Construction method of upper-floor type suspension floor slab bridge | |
JP3827111B2 (en) | Construction method of concrete bridge girder | |
JPH11269825A (en) | Installation method of bridge girder and lifting equipment | |
JPH11323838A (en) | Construction method of bridge | |
JP2584418B2 (en) | Overhang construction method and stress improvement device for synthetic cable-stayed bridge | |
JPH0336362B2 (en) | ||
JP4838329B2 (en) | Construction method of upper-floor type suspension floor slab bridge | |
JPH06185017A (en) | Bridge girder erection method and device thereof | |
CN116427278A (en) | Large multi-span self-propelled automatic die carrier |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
S533 | Written request for registration of change of name |
Free format text: JAPANESE INTERMEDIATE CODE: R313533 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 7 Free format text: PAYMENT UNTIL: 20080105 |
|
R350 | Written notification of registration of transfer |
Free format text: JAPANESE INTERMEDIATE CODE: R350 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20080105 Year of fee payment: 7 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20090105 Year of fee payment: 8 |
|
FPAY | Renewal fee payment (prs date is renewal date of database) |
Year of fee payment: 9 Free format text: PAYMENT UNTIL: 20100105 |
|
LAPS | Cancellation because of no payment of annual fees |