JPH086897B2 - Hanging boiler installation method - Google Patents
Hanging boiler installation methodInfo
- Publication number
- JPH086897B2 JPH086897B2 JP1757591A JP1757591A JPH086897B2 JP H086897 B2 JPH086897 B2 JP H086897B2 JP 1757591 A JP1757591 A JP 1757591A JP 1757591 A JP1757591 A JP 1757591A JP H086897 B2 JPH086897 B2 JP H086897B2
- Authority
- JP
- Japan
- Prior art keywords
- steel frame
- boiler
- floor
- suspended
- peripheral
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000000034 method Methods 0.000 title claims description 16
- 238000009434 installation Methods 0.000 title description 13
- 229910000831 Steel Inorganic materials 0.000 claims description 53
- 239000010959 steel Substances 0.000 claims description 53
- 230000002093 peripheral effect Effects 0.000 claims description 26
- 239000000725 suspension Substances 0.000 claims description 5
- 238000010276 construction Methods 0.000 description 4
- 239000000463 material Substances 0.000 description 4
- 238000011900 installation process Methods 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 230000002411 adverse Effects 0.000 description 1
- 239000000470 constituent Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B37/00—Component parts or details of steam boilers
- F22B37/02—Component parts or details of steam boilers applicable to more than one kind or type of steam boiler
- F22B37/24—Supporting, suspending or setting arrangements, e.g. heat shielding
- F22B37/244—Supporting, suspending or setting arrangements, e.g. heat shielding for water-tube steam generators suspended from the top
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Description
【0001】[0001]
【産業上の利用分野】本発明は鉄骨によって吊下げ支持
されるボイラの据付方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of installing a boiler suspended and supported by a steel frame.
【0002】[0002]
【従来の技術】図4は鉄骨によって吊下げ支持されるボ
イラの従来の据付工法の一例を示す側面図である。吊下
げ型ボイラは,中心部鉄骨1,その周辺部に設けられた
周辺部鉄骨2,中心部鉄骨1によって吊下げ支持される
ボイラ本体3,および周辺部鉄骨2に取付けられたボイ
ラ付帯機器4等から成立っている。そして,これらを組
立てる工法としては,まず大型の移動式クレーン5によ
って,中心部鉄骨1を構成する主柱,柱,梁等を下段か
ら順次積み上げて行き,最上部の大梁まで組立てる。そ
の後,ボイラ本体3の各部分を上部のものから順次吊下
げて行き,最下部まで組立てる。一方,周辺部鉄骨2と
これらの鉄骨部に配置されるボイラ付帯機器4は,ボイ
ラ本体3の組立てと平行して,移動式クレーン5により
構成部材や部品を1ピースづつ吊揚げ,下段の階から順
次上部の階へと組立てていた。2. Description of the Related Art FIG. 4 is a side view showing an example of a conventional installation method of a boiler suspended and supported by a steel frame. The hanging type boiler includes a central steel frame 1, a peripheral steel frame 2 provided around the central steel frame 2, a boiler main body 3 suspended and supported by the central steel frame 1, and a boiler accessory device 4 attached to the peripheral steel frame 2. And so on. As a construction method for assembling these, first, by using a large mobile crane 5, the main pillars, pillars, beams, etc. that compose the central steel frame 1 are sequentially stacked from the lower stage, and the uppermost girder is assembled. After that, each part of the boiler main body 3 is hung from the top one in order and assembled to the bottom. On the other hand, the peripheral steel frames 2 and the boiler auxiliary equipment 4 arranged on these steel frames are hung in parallel with the assembly of the boiler body 3 by the mobile crane 5 to lift the components and parts one by one, and the lower floor Assembled one by one to the upper floor.
【0003】[0003]
【発明が解決しようとする課題】従来のボイラ据付工法
は,前記のとおり,移動式クレーンによって構成部材や
部品を1ピースずつ吊揚げ,下部の階から上部の階へと
順次組立てていたので,次のような解決すべき課題があ
った。1) 各部材の取付が全て高所に吊揚げて行なわれ
るので,作業能率が悪い。2) 高所作業の安全を確保す
るために足場を必要とし,またその組立,解体にも多大
な人手を要する。3) したがってまた,大幅な工程短縮
の余地が少ない。As described above, in the conventional boiler installation method, the constituent members and parts are hoisted by the mobile crane one by one, and they are sequentially assembled from the lower floor to the upper floor. There were the following issues to be solved. 1) The work efficiency is poor because all the components are mounted in a high place. 2) A scaffold is required to secure the safety of work in high places, and a large amount of manpower is required for its assembly and disassembly. 3) Therefore, there is little room for drastic process reduction.
【0004】[0004]
【課題を解決するための手段】本発明は,前記従来の課
題を解決するために,中心部鉄骨と,同中心部鉄骨によ
って吊下げ支持されたボイラ本体と,上記中心部鉄骨の
周辺に設けられた周辺部鉄骨と,同周辺部鉄骨に取付け
られたボイラ付帯機器とを備えた吊下型ボイラの据付工
法において,上記中心部鉄骨の最上部から周辺に張出す
吊揚梁を仮設し,その張出し部分に吊揚設備を設けると
ともに,上記周辺部鉄骨の各階部分にそれぞれボイラ付
帯機器を配置して成るゾーンモジュールを地上で組立
て,それらゾーンモジュールの上層階部分を上記吊揚設
備で吊揚げつつ,その下部に下層階部分の上部を接合す
る工程を,順次繰返すことを特徴とする吊下型ボイラの
据付工法を提案するものである。In order to solve the above-mentioned conventional problems, the present invention provides a central steel frame, a boiler main body suspended and supported by the central steel frame, and a periphery of the central steel frame. In the installation method of the suspended boiler equipped with the peripheral steel frame and the boiler auxiliary equipment attached to the peripheral steel frame, a hoisting beam that extends from the top of the central steel frame to the periphery is temporarily installed, Assembling the zone module consisting of the equipment attached to the projecting part and the equipment attached to the boiler on each floor of the peripheral steel frame above ground, and the upper floors of these zone modules are lifted by the above equipment. At the same time, we propose an installation method for a suspended boiler, which is characterized by repeating the process of joining the upper part of the lower floor to the lower part in order.
【0005】[0005]
【作用】本発明の方法は,次の作用を有する。 1) 各部材を高所に吊揚げる回数が大幅に減少する。 2) 先に建方を完了させている中心部鉄骨から吊下げ支
持されるボイラ本体の据付工事と,周辺部鉄骨およびボ
イラ付帯機器の据付工事との,並行作業が可能となり,
工期が短縮される。 3) 地上作業が多いので,能率が向上するとともに,安
全性が向上する。The function of the present invention has the following functions. 1) The number of times each member is lifted to a high place is greatly reduced. 2) Installation work of the boiler main body, which is suspended from the central steel frame, which has been completed to be erected, and installation work of the peripheral steel frame and boiler auxiliary equipment, can be performed in parallel,
The construction period is shortened. 3) Since there are many ground operations, the efficiency is improved and the safety is improved.
【0006】[0006]
【実施例】次に本発明方法の一実施例を図1ないし図3
により説明する。図1は本実施例の方法により据付けを
完了した吊下型ボイラを示す全体側面図,図2は周辺部
鉄骨にボイラ付帯機器を配置して成るゾーンモジュール
を示す斜視図,図3(a),(b)は据付け過程を示す
図である。DESCRIPTION OF THE PREFERRED EMBODIMENTS Next, one embodiment of the method of the present invention will be described with reference to FIGS.
Will be described. FIG. 1 is an overall side view showing a suspended boiler that has been installed by the method of this embodiment, FIG. 2 is a perspective view showing a zone module in which boiler auxiliary equipment is arranged on a peripheral steel frame, and FIG. 3 (a). , (B) are diagrams showing an installation process.
【0007】本実施例により据付けられるボイラは,大
型の吊下型ボイラである。図1に示される中心部鉄骨1
0は,矩形状に配置された複数本の支持柱11と,それ
らの最上部に搭載された大梁12と,更に図示されてい
ない柱や梁等によって形成されている。ボイラ本体30
はその大梁12から吊棒等により,吊り下げられ,その
周囲に周辺部鉄骨20が設けられている。その周辺部鉄
骨20は,図示例では5層(符号25,26,27,2
8,29)から成っており,その各階にボイラ付帯機器
40が配置されている。The boiler installed according to this embodiment is a large hanging boiler. Central steel frame 1 shown in FIG.
0 is formed by a plurality of support pillars 11 arranged in a rectangular shape, a large beam 12 mounted on the uppermost of them, and pillars and beams not shown. Boiler body 30
Is suspended from the girder 12 by a suspension rod or the like, and a peripheral steel frame 20 is provided around the suspension. The peripheral steel frame 20 has five layers (reference numerals 25, 26, 27, 2 in the illustrated example).
8, 29), and the boiler auxiliary equipment 40 is arranged on each floor.
【0008】本実施例においてゾーンモジュール化の対
象となるのは,図1に示されるボイラ支持鉄骨のうちの
周辺部鉄骨20である。この周辺部鉄骨部を,図2に示
すように,鉄骨部材21,床材22,手摺23,吊柱2
4,ボイラ付帯機器40,および図示されていない水平
梁,垂直梁等を含め,各階単位のゾーン毎に地上で組立
ててモジュール化する。In this embodiment, the target of zone modularization is the peripheral steel frame 20 of the boiler supporting steel frame shown in FIG. As shown in FIG. 2, a steel frame member 21, a floor material 22, a handrail 23, a suspension column 2
4, including the boiler auxiliary equipment 40, and horizontal beams, vertical beams, etc., which are not shown, are assembled on the ground for each zone and are modularized.
【0009】この周辺部材鉄骨20は,方形水平断面に
形成された中心部鉄骨10の4辺を取囲んで形成されて
いるので,地上での組立てモジュール化に当たっては,
その一辺を単位(1ゾーン)として組立てる。本実施例
では,以下周辺部鉄骨を前後左右に分け,前部5階モジ
ュールを25a,後部5階モジュールを25b,左部5
階モジュール25c,右部5階モジュールを25dと
し,同様に4階モジュールを26a〜26d,3階モジ
ュールを27a〜27d,2階モジュールを28a〜2
8d等として,ボイラ据付工程を図3により説明する。
1階部のみは,図2に示された床材22やボイラ付帯機
器40等がほとんどないので,吊柱24や梁等を周辺部
鉄骨29a〜29dとする。Since the peripheral member steel frame 20 is formed so as to surround the four sides of the central portion steel frame 10 formed in a rectangular horizontal cross section, when assembling and modularizing on the ground,
Assemble one side as a unit (one zone). In the present embodiment, the peripheral steel frame is divided into front, rear, left and right in the following, with the front 5th floor module 25a, the rear 5th floor module 25b, and the left 5
The floor module 25c and the right fifth floor module are designated as 25d, and similarly, the fourth floor module is 26a to 26d, the third floor module is 27a to 27d, and the second floor module is 28a to 2.
The boiler installation process will be described with reference to FIG.
Since there is almost no floor material 22, the boiler auxiliary equipment 40, etc. shown in FIG. 2 only on the first floor, the hanging columns 24, beams, etc. are used as the peripheral steel frames 29a to 29d.
【0010】本実施例におけるボイラの据付順序として
は,中心部鉄骨10を形成する支持柱11と大梁12
を,順次大型クレーン等で吊揚げて移動しつつ建ててい
く。これと同時に地上では,各ゾーン毎に周辺部鉄骨お
よびボイラ付帯機器をモジュール化してゆく。このモジ
ュール化の順序は,言うまでもなく,周辺部鉄骨20の
最上部である5階モジュール25a〜25dを最初に組
み始め,順次下段のものを組立ててゆくものである。組
立てに際しては,床材22,鉄骨部材21,吊柱24等
を組立て,ボイラ付帯機器40も地上で正規のとおり配
置して取付ける。すなわち,このゾーン内に配置される
べき全ての部材を,地上で取付け組立てるのである。し
かし,モジュールが大型となり,搬送手段,例えばドー
リ55に搭載できない場合は,更に分割して組立て,別
体として搬送しても何ら差障りはない。The installation order of the boiler in this embodiment is as follows: the support column 11 and the girder 12 forming the central steel frame 10.
Are successively lifted by a large crane and moved to build. At the same time, on the ground, peripheral steel frames and boiler auxiliary equipment will be modularized for each zone. Needless to say, the modularization order is such that the uppermost 5th floor modules 25a to 25d of the peripheral steel frame 20 are first assembled, and then the lower ones are sequentially assembled. At the time of assembling, the floor material 22, the steel frame member 21, the suspension column 24, etc. are assembled, and the boiler auxiliary equipment 40 is also arranged and mounted on the ground in a regular manner. That is, all the members to be placed in this zone are mounted and assembled on the ground. However, if the module becomes large and cannot be mounted on the transportation means, for example, the dolly 55, there is no problem even if the module is further divided and assembled and transported as a separate body.
【0011】中心部の主鉄骨10の建方が完了次第,大
梁12の頂部に周辺部まで張出した吊揚梁50を仮設す
る。そして,その張出し部分,すなわち周辺部鉄骨20
の据え付け位置上方に,吊揚設備,例えばジャッキ,大
型ウインチ等51を据え付けて,接続装置52を垂下す
る。それから地上で組立てを完了したモジュールのう
ち,例えば前部5階モジュール25aをドーリ55に搭
載して,図3(a)に示されるように,前部の据え付け
位置真下に搬入し,その上部を完全に吊揚げ可能に接続
装置52と接続する。これと同時にまたは個別に,後部
5階モジュール25bや左右部5階モジュール25c,
25dもドーリ55によって搬入し,各接続装置52と
接続する。更にこれと並行して,ボイラ本体30の部品
31を搬送手段であるトレーラ56等によって搬入し,
上部のものから順次吊揚げて据え付ける工事も行なうこ
とができる。As soon as the main steel frame 10 in the central portion has been built, a hoisting beam 50 extending to the peripheral portion is temporarily installed on the top of the large beam 12. And the overhanging portion, that is, the peripheral steel frame 20
A hoisting equipment, such as a jack and a large winch 51, is installed above the installation position of, and the connecting device 52 is hung. Then, of the modules that have been assembled on the ground, for example, the front fifth-floor module 25a is mounted on the dolly 55 and, as shown in FIG. The connection device 52 is connected so that it can be completely lifted. At the same time or individually, the rear 5th floor module 25b and the left and right 5th floor modules 25c,
25d is also carried in by the dolly 55 and connected to each connecting device 52. In parallel with this, the parts 31 of the boiler main body 30 are carried in by a trailer 56 or the like which is a conveying means,
It is also possible to carry out the work of hoisting and installing from the top.
【0012】上述のようにして,各モジュールと吊揚装
置の接続が完了次第吊揚げてゆくが,吊揚げる高さは,
次層階のモジュールをドーリ55によって搬入できる高
さだけとする。そして,その次層階モジュール(例えば
4階モジュール26a)を搬入しては,先に吊揚げたモ
ジュール(例えば5階モジュール25a)と接合し一体
とする。このような搬入,接合,吊揚を,図3(b)に
示されるように繰返して,ボイラ付帯機器40を含む周
辺部鉄骨20を完成させる。また,中心部鉄骨によって
支持されるボイラ本体30の据付工事も並行して続行す
る。As described above, the modules are hoisted as soon as the connection between each module and the hoisting device is completed, but the hoisting height is
The height of the module on the next floor is limited to that which can be loaded by the dolly 55. Then, the next-floor floor module (for example, the fourth-floor module 26a) is carried in and joined with the previously hung module (for example, the fifth-floor module 25a) to be integrated. Such loading, joining, and lifting are repeated as shown in FIG. 3B to complete the peripheral steel frame 20 including the boiler auxiliary equipment 40. Also, the installation work of the boiler main body 30 supported by the central steel frame will be continued in parallel.
【0013】前述した各モジュールの接続と吊揚順序は
特に限定するものではないが,一辺のみ,例えば前部の
みについて,1階から5階まで全てを他辺よりも先行し
て吊揚げると,大きな荷重が前部のみに加わり,支持柱
11や大梁12等に悪影響を与えるので,そのようなや
り方は好ましくない。周辺全てが均等な荷重となるよう
に,例えば5階部分のみについて,4辺を別個に次々に
吊揚げるか,または相対する2辺を同時,もしくは4辺
を同時に吊揚げ,その後,次層階(例えば4階)部分の
モジュールを吊揚げるようにするのが望ましい。The connection and hoisting order of the above-mentioned modules are not particularly limited, but if only one side, for example, only the front part, is hoisted from the first floor to the fifth floor before all the other sides, Such a method is not preferable because a large load is applied only to the front part and adversely affects the support columns 11 and the girders 12. To ensure that the load is evenly distributed all around, for example, only the 5th floor part, 4 sides are hung separately one after the other, or 2 opposite sides are hung at the same time, or 4 sides are hung at the same time, and then the next floor It is desirable to be able to hoist the module in the (eg, 4th floor) part.
【0014】[0014]
【発明の効果】本発明の方法によれば,吊下型ボイラの
据付工事において,高所作業を大幅に減少させることが
でき,また中心部鉄骨によって吊下げ支持されるボイラ
本体の据付作業と,ボイラ付帯機器を含む周辺部鉄骨の
ゾーンモジュールの据付作業とを,並行して行なうこと
ができるので,次の効果が得られる。 1) 工期を大幅に短縮できる。 2) 地上作業の増加により,作業能率が向上し,作業人
員を減少することができる。 3) 工事の安全性が向上する。According to the method of the present invention, it is possible to significantly reduce the work at height in the installation work of the suspended boiler, and to install the boiler main body suspended and supported by the central steel frame. Since the peripheral steel frame zone module installation work including boiler auxiliary equipment can be performed in parallel, the following effects can be obtained. 1) The construction period can be greatly shortened. 2) The increase in ground work improves work efficiency and reduces the number of workers. 3) Construction safety is improved.
【図1】図1は本発明方法の一実施例により据付けを完
了した吊下型ボイラを示す全体側面図である。FIG. 1 is an overall side view showing a suspended boiler that has been installed by an embodiment of the method of the present invention.
【図2】図2は上記実施例において周辺部鉄骨にボイラ
付帯機器を取付けて成るゾーンモジュールを例示する斜
視図である。FIG. 2 is a perspective view illustrating a zone module in which a boiler accessory device is attached to a peripheral steel frame in the above embodiment.
【図3】図3は上記実施例における据付け過程を示す図
である。FIG. 3 is a diagram showing an installation process in the above embodiment.
【図4】図4は従来の据付工法の一例を示す側面図であ
る。FIG. 4 is a side view showing an example of a conventional installation method.
1 中心部鉄骨 2 周辺部鉄骨 3 ボイラ本体 4 ボイラ付帯機器 5 移動式クレーン 10 中心部鉄骨 11 支持柱 12 大梁 20 周辺部鉄骨 21 鉄骨部材 22 床材 23 手摺 24 吊柱 30 ボイラ本体 31 ボイラ本体部品 40 ボイラ付帯機器 50 吊揚梁 51 吊揚設備 52 接続装置 55 ドーリ 56 トレーラ 1 Central Steel Frame 2 Peripheral Steel Frame 3 Boiler Main Body 4 Boiler Ancillary Equipment 5 Mobile Crane 10 Central Steel Frame 11 Support Pillar 12 Girder 20 Peripheral Steel Frame 21 Steel Frame Member 22 Floor Material 23 Handrail 24 Suspended Pillar 30 Boiler Main Body 31 Boiler Main Body Parts 40 Boiler-equipped equipment 50 Lifting beam 51 Lifting equipment 52 Connecting device 55 Dory 56 Trailer
───────────────────────────────────────────────────── フロントページの続き (72)発明者 堀 光生 長崎県長崎市飽の浦町1番1号 三菱重工 業株式会社長崎造船所内 (72)発明者 吉岡 英侑 長崎県長崎市飽の浦町1番1号 三菱重工 業株式会社長崎造船所内 (56)参考文献 特開 昭63−118504(JP,A) 特開 昭60−62504(JP,A) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Mitsuo Hori 1-1, Atsunoura-machi, Nagasaki-shi, Nagasaki Mitsubishi Heavy Industries, Ltd. Nagasaki Shipyard (72) Inventor Hideyuki Yoshioka 1-1, Atsunoura-cho, Nagasaki-shi, Nagasaki Mitsubishi Heavy Industries, Ltd. Nagasaki Shipyard (56) Reference JP 63-118504 (JP, A) JP 60-62504 (JP, A)
Claims (1)
下げ支持されたボイラ本体と,上記中心部鉄骨の周辺に
設けられた周辺部鉄骨と,同周辺部鉄骨に取付けられた
ボイラ付帯機器とを備えた吊下型ボイラの据付工法にお
いて,上記中心部鉄骨の最上部から周辺に張出す吊揚梁
を仮設し,その張出し部分に吊揚設備を設けるととも
に,上記周辺部鉄骨の各階部分にそれぞれボイラ付帯機
器を配置して成るゾーンモジュールを地上で組立て,そ
れらゾーンモジュールの上層階部分を上記吊揚設備で吊
揚げつつ,その下部に下層階部分の上部を接合する工程
を,順次繰返すことを特徴とする吊下型ボイラの据付工
法。1. A central steel frame, a boiler main body suspended and supported by the central steel frame, a peripheral steel frame provided around the central steel frame, and a boiler accessory device attached to the peripheral steel frame. In the method for installing a suspended boiler equipped with and, a suspension beam that extends from the uppermost part of the central steel frame to the periphery is temporarily installed, and lifting equipment is installed on the overhanging part, and each floor part of the peripheral steel frame. Assemble zone modules consisting of the equipment attached to the boilers on the ground, suspend the upper floors of these zone modules with the above-mentioned lifting equipment, and join the upper portion of the lower floors to the lower portion in sequence. A method for installing a suspended boiler, which is characterized in that
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1757591A JPH086897B2 (en) | 1991-02-08 | 1991-02-08 | Hanging boiler installation method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP1757591A JPH086897B2 (en) | 1991-02-08 | 1991-02-08 | Hanging boiler installation method |
Publications (2)
Publication Number | Publication Date |
---|---|
JPH04257602A JPH04257602A (en) | 1992-09-11 |
JPH086897B2 true JPH086897B2 (en) | 1996-01-29 |
Family
ID=11947713
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP1757591A Expired - Fee Related JPH086897B2 (en) | 1991-02-08 | 1991-02-08 | Hanging boiler installation method |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH086897B2 (en) |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2576035B2 (en) * | 1993-05-14 | 1997-01-29 | 三菱重工業株式会社 | Zone module construction method for steel structure construction |
DE10014758C2 (en) * | 2000-03-24 | 2003-10-09 | Alstom Power Boiler Gmbh | Steam generator and assembly method for this |
JP2002098304A (en) * | 2000-09-21 | 2002-04-05 | Ishikawajima Harima Heavy Ind Co Ltd | Boiler framing building method |
DE10335499B3 (en) | 2003-07-31 | 2004-11-25 | Alstom Power Boiler Gmbh | Steam generator erection method has pre-assembled pipe wall modules attached to steam vessel frame before fitting frame cover |
JP2007107789A (en) * | 2005-10-12 | 2007-04-26 | Babcock Hitachi Kk | Installation method of boiler equipment |
JP5743205B2 (en) * | 2011-06-16 | 2015-07-01 | 株式会社日立製作所 | Boiler facility construction method |
JP5894140B2 (en) * | 2013-12-24 | 2016-03-23 | 三菱日立パワーシステムズ株式会社 | Boiler support structure |
EP2933555A1 (en) * | 2014-04-15 | 2015-10-21 | Alstom Technology Ltd | Method for erecting a boiler, module and boiler comprising the module |
US20160305111A1 (en) * | 2015-04-20 | 2016-10-20 | Alstom Technology Ltd | Method for erecting a boiler |
-
1991
- 1991-02-08 JP JP1757591A patent/JPH086897B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPH04257602A (en) | 1992-09-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH086897B2 (en) | Hanging boiler installation method | |
JPH11211003A (en) | Boiler and assembling method thereof | |
JPH06323503A (en) | Assembling method for large size suspension type boiler | |
JPH09229304A (en) | Construction technique of tower type boiler plant | |
JP2513802B2 (en) | Auxiliary device for lifting elevator guide rails | |
JPH07112807A (en) | Rack construction method and jig for automatic store | |
CN221478863U (en) | Support for module vehicle transportation tool | |
JP5080889B2 (en) | Blast furnace body ring block changing device, furnace body construction method and furnace body disassembly method | |
JP3352268B2 (en) | Transportation method of elevator shaft unit for elevator | |
JPH0791603A (en) | Assembly parallel progressing method for large suspension type boiler | |
JPH0335468B2 (en) | ||
JP2625378B2 (en) | Building construction method using ramen unit | |
CN117326466A (en) | Supporting method of crane assembly | |
JP2670220B2 (en) | Construction method of coal bunker and mill zone of coal-fired boiler | |
JPS63176290A (en) | Passenger conveyor suspension system | |
JPH04153460A (en) | Constructing method for building, and its equipment | |
JPH08326323A (en) | Constructing device for multistoried building | |
JPH07173941A (en) | Balcony transportation jig | |
JP2001171975A (en) | Heavy cargo carrying-in method into building and heavy cargo carrying-out method out of building | |
JP2717157B2 (en) | Horizontal transport device for building construction | |
JPH0791071A (en) | Spreading method for external wall panel and device thereof | |
JP2536347B2 (en) | Building construction method using traveling crane | |
JPH08326321A (en) | Construction of multistoried building | |
JP2003064879A (en) | Steel frame construction method and pallet for lifting steel frame beam | |
CN116517299A (en) | Steel structure modularization construction technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 19960716 |
|
LAPS | Cancellation because of no payment of annual fees |