JPH08165899A - Tunnel lining method using timbering concurrently serving as reinforcing bar - Google Patents
Tunnel lining method using timbering concurrently serving as reinforcing barInfo
- Publication number
- JPH08165899A JPH08165899A JP6309137A JP30913794A JPH08165899A JP H08165899 A JPH08165899 A JP H08165899A JP 6309137 A JP6309137 A JP 6309137A JP 30913794 A JP30913794 A JP 30913794A JP H08165899 A JPH08165899 A JP H08165899A
- Authority
- JP
- Japan
- Prior art keywords
- concrete
- primary
- lining
- tunnel
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
Description
【0001】[0001]
【産業上の利用分野】本発明は、NATM(吹付けコン
クリート工法)で大断面のトンネルを掘進する場合の覆
工方法に関する。BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a lining method for excavating a tunnel having a large cross section by NATM (shot concrete method).
【0002】[0002]
【従来の技術】近年、岩盤に大断面のトンネルを掘進す
る場合には、NATMが標準工法として用いられてい
る。NATMでは、防止水工の施工の際には、従来、ト
ンネル周壁の吹付けコンクリートと鋼アーチ支保工等に
よる一次覆工の内面に防水シートを設置した後、二次覆
工コンクリートを打設していた。2. Description of the Related Art In recent years, NATM has been used as a standard method for excavating a tunnel having a large cross section in rock. When constructing preventive water works, NATM has conventionally installed a secondary lining concrete after installing a waterproof sheet on the inner surface of the primary lining by spraying concrete on the tunnel peripheral wall and steel arch support. Was there.
【0003】しかし、このような覆工方法では、一次覆
工の内面に防水シートを設置した後、二次覆工コンクリ
ートを打設するため、二次覆工を鉄筋で補強するのが煩
雑で、能率が悪く、工費が嵩むと言う問題があった。However, in such a lining method, since the secondary lining concrete is placed after placing the waterproof sheet on the inner surface of the primary lining, it is complicated to reinforce the secondary lining with reinforcing bars. However, there was a problem that the efficiency was low and the construction cost was high.
【0004】[0004]
【発明が解決しようとする課題】本発明は、トンネルの
覆工におけるかかる問題を解決するものであって、NA
TMで大断面のトンネルを掘進する場合の防止水工の施
工、二次覆工の鉄筋補強が容易で、トンネル覆工の品質
を向上させ、工費を低減することのできるトンネルの覆
工方法を提供することを目的とする。SUMMARY OF THE INVENTION The present invention is to solve such a problem in tunnel lining, and
A tunnel lining method that allows easy construction of preventive water works when digging a tunnel with a large cross section by TM and reinforcement of secondary lining steel bars, improves the quality of tunnel lining, and reduces construction costs. The purpose is to provide.
【0005】[0005]
【課題を解決するための手段】本発明では、大断面のト
ンネルの掘進において、地山掘削後コンクリートの一次
吹付けを行ない、一次吹付けコンクリートの内面に太径
鉄筋鋼アーチ支保工を固定し、太径鉄筋鋼アーチ支保工
の高さの半分程度までコンクリートの二次吹付けを行な
って一次覆工コンクリートを形成し、一次覆工コンクリ
ートの内面にコンクリート防水強化材を吹付け又は塗布
し、一次覆工コンクリートの内側に突出した状態で残っ
ている太径鉄筋鋼アーチ支保工を補強鉄筋として二次覆
工コンクリートを打設することにより上記課題を解決し
ている。According to the present invention, in excavation of a tunnel having a large cross section, a primary shot of concrete is carried out after ground excavation, and a large diameter reinforced steel arch support is fixed to the inner surface of the primary shot concrete. , The primary lining concrete is formed by performing secondary spraying of concrete up to about half the height of the large diameter steel reinforced steel arch support, and the concrete waterproofing reinforcement is sprayed or applied on the inner surface of the primary lining concrete, The above-mentioned problem is solved by placing the secondary lining concrete by using the large-diameter reinforced steel arch supports remaining in a state of protruding inside the primary lining concrete as reinforcing bars.
【0006】[0006]
【作用】一次覆工の内面に防水シートを設置せず、コン
クリート防水強化材を吹付け又は塗布し、また、一次覆
工の太径鉄筋鋼アーチ支保工を二次覆工の補強筋に兼用
して二次覆工コンクリートを打設するため、作業が容易
となり、トンネル覆工の品質が向上する。[Operation] Without installing a waterproof sheet on the inner surface of the primary lining, spray or apply concrete waterproof reinforcement material, and also use the large diameter steel reinforced steel arch support of the primary lining as the reinforcing bar of the secondary lining Since the secondary lining concrete is then placed, the work becomes easier and the quality of the tunnel lining is improved.
【0007】[0007]
【実施例】図1は大断面トンネルの掘削方法の一例の説
明図である。ここで、掘進するトンネルTは、断面積が
200m2を超え、断面形状が比較的偏平な大断面トン
ネルであり、このトンネルTの上半アーチ部2内に2本
の円形導坑1を小型のトンネル掘進機で先行掘削する。
この円形導坑1から地山に、所定の間隔でケーブルボル
ト3を打設する。更に、円形導坑1の周壁には、モルタ
ルの吹付けを行う。DESCRIPTION OF THE PREFERRED EMBODIMENTS FIG. 1 is an explanatory view of an example of a method of excavating a large cross section tunnel. Here, the tunnel T to be dug is a large cross-section tunnel having a cross-sectional area of more than 200 m 2 and a relatively flat cross-section, and two circular tunnels 1 are miniaturized in the upper half arch part 2 of this tunnel T. Pre-excavate with a tunnel machine.
Cable bolts 3 are driven from the circular tunnel 1 to the ground at a predetermined interval. Further, mortar is sprayed on the peripheral wall of the circular tunnel 1.
【0008】それから、上半アーチ部2を4t以上の大
型油圧ブレーカで整形切拡げ掘削する。掘削後、上半ア
ーチ部2には、防止水工5と鋼支保工6を施す。次に、
下半部7、インバート部8の盤下げ対象地山は、さく岩
機でさく孔し、弛め発破で弛めながら、D11級インパ
クトリッパーで掘り下げ、防止水工5と鋼支保工6を施
し、その後コンクリートによる二次覆工を行う。Then, the upper half arch portion 2 is shaped, cut, and excavated by a large hydraulic breaker of 4 tons or more. After excavation, prevention water works 5 and steel support works 6 are applied to the upper half arch portion 2. next,
The ground to be lowered in the lower half 7 and the invert 8 is drilled with a rock drill and loosened by loosening and blasting, and is dug down with a D11 class impact ripper, and water prevention 5 and steel support 6 are applied. , And then secondary lining with concrete.
【0009】図2は本発明の一実施例であるトンネルの
覆工における二次覆工前の状態を示す部分横断面図、図
3は二次覆工後の状態を示す部分縦断面図、図4は太径
鉄筋鋼アーチ支保工の断面図である。この実施例では、
上述の如き大断面のトンネルの掘進において、覆工を次
の如く行う。まず、地山掘削後コンクリートの一次吹付
けを行ない、一次吹付けコンクリート10の内面に太径
鉄筋鋼アーチ支保工11をロックボルト等で固定する。FIG. 2 is a partial cross-sectional view showing a state before secondary lining in tunnel lining according to an embodiment of the present invention, and FIG. 3 is a partial vertical cross-sectional view showing a state after secondary lining, FIG. 4 is a cross-sectional view of a large diameter reinforced steel arch support. In this example,
In the excavation of the large cross section tunnel as described above, lining is performed as follows. First, after excavating the natural ground, primary spraying of concrete is performed, and the large diameter reinforced steel arch support 11 is fixed to the inner surface of the primary spraying concrete 10 with a lock bolt or the like.
【0010】太径鉄筋鋼アーチ支保工11は、トンネル
Tの外周の形状に沿ってアーチ状に湾曲した所定長の太
径鉄筋12を上下二層に15cm程度の間隔で複数本配
置し、これらの太径鉄筋12を繋ぎ鉄筋13で互いに連
繋して形成されており、一端に継ぎ鋼板14を備えてい
る。太径鉄筋鋼アーチ支保工11は、トンネルTの外周
の長さに合わせて、必要数連結される。このとき、一端
は継ぎ鋼板14を継ぎボルト15で連結し、他端はスリ
ーブ16で連結する。The large-diameter reinforcing steel arch support 11 has a plurality of large-diameter reinforcing bars 12 curved in an arch shape along the outer circumference of the tunnel T and arranged in upper and lower two layers at intervals of about 15 cm. The large-diameter reinforcing bars 12 are connected to each other by the reinforcing bars 13, and a joint steel plate 14 is provided at one end. The necessary number of the large diameter reinforced steel arch supports 11 are connected according to the length of the outer circumference of the tunnel T. At this time, one end connects the joint steel plates 14 with the joint bolts 15, and the other end connects with the sleeve 16.
【0011】太径鉄筋鋼アーチ支保工11が固定される
と、太径鉄筋鋼アーチ支保工11の高さHの半分程度ま
でコンクリートの二次吹付けを行なって一次覆工コンク
リート17を形成する。この一次覆工コンクリート17
の内面には、ザイペックス等のコンクリート防水強化材
18を吹付け又は塗布する。このとき、太径鉄筋鋼アー
チ支保工11は図2に示すように、一次覆工コンクリー
ト17の内側に突出した状態で残っている。When the large diameter reinforced steel arch support 11 is fixed, the secondary blasting of concrete is performed up to about half the height H of the large diameter reinforced steel arch support 11 to form the primary lining concrete 17. . This primary lining concrete 17
Concrete waterproof reinforcement material 18 such as Zypex is sprayed or applied to the inner surface of the. At this time, as shown in FIG. 2, the large-diameter reinforced steel arch support 11 remains in a state of protruding inside the primary lining concrete 17.
【0012】そこで、一次覆工コンクリート17の内側
に突出した状態で残っている太径鉄筋鋼アーチ支保工1
1を補強鉄筋として二次覆工コンクリート19を打設す
る。必要に応じて突出した状態で残っている太径鉄筋鋼
アーチ支保工11に付加鉄筋を連結して二次覆工を強化
することも可能である。このように、一次覆工コンクリ
ート17の内面に防水シートを設置せず、コンクリート
防水強化材18を吹付け又は塗布し、また、一次覆工時
の太径鉄筋鋼アーチ支保工11を二次覆工の補強筋に兼
用して二次覆工コンクリート19を打設するため、作業
が容易となり、トンネル覆工の品質が向上する。Therefore, the large diameter reinforced steel arch support 1 which remains in a state of protruding inside the primary lining concrete 17
A secondary lining concrete 19 is placed by using 1 as a reinforcing bar. If necessary, it is also possible to strengthen the secondary lining by connecting additional reinforcing bars to the large-diameter reinforcing steel arch supporting structure 11 that remains in a protruding state. As described above, the waterproof sheet is not installed on the inner surface of the primary lining concrete 17, the concrete waterproofing reinforcement material 18 is sprayed or applied, and the large diameter reinforced steel arch support 11 at the time of the primary lining is secondaryly covered. Since the secondary lining concrete 19 is also placed as the reinforcing bar of the work, the work is facilitated and the quality of the tunnel lining is improved.
【0013】[0013]
【発明の効果】以上説明したように、本発明のトンネル
の覆工方法によれば、NATMで大断面のトンネルを掘
進する場合の防止水工の施工、二次覆工の鉄筋補強が容
易で、トンネル覆工の品質を向上させ、工費を低減する
ことができる。As described above, according to the tunnel lining method of the present invention, it is easy to perform preventive water work when digging a tunnel having a large cross section with NATM and to reinforce the secondary lining. , The quality of tunnel lining can be improved and the construction cost can be reduced.
【図1】大断面トンネルの掘削方法の一例の説明図であ
る。FIG. 1 is an explanatory diagram of an example of a method of excavating a large cross section tunnel.
【図2】本発明の一実施例であるトンネルの覆工の二次
覆工前の状態を示す部分横断面図である。FIG. 2 is a partial cross-sectional view showing a state before the secondary lining of the tunnel lining according to the embodiment of the present invention.
【図3】二次覆工後の状態を示す部分縦断面図である。FIG. 3 is a partial vertical sectional view showing a state after secondary lining.
【図4】太径鉄筋鋼アーチ支保工の断面図である。FIG. 4 is a cross-sectional view of a large diameter reinforced steel arch support.
【符号の説明】 1 円形導坑 2 上半アーチ部 3 ケーブルボルト 5 防水止工 6 鋼支保工 7 下半部 8 インバート部 10 一次吹付けコンクリート 11 太径鉄筋鋼アーチ支保工 12 太径鉄筋 13 繋ぎ鉄筋 14 継ぎ鋼板 15 継ぎボルト 16 スリーブ 17 一次覆工コンクリート 18 コンクリート防水強化材 19 二次覆工コンクリート T トンネル[Explanation of symbols] 1 circular guideway 2 upper half arch part 3 cable bolt 5 waterproof stop 6 steel support work 7 lower half part 8 invert part 10 primary shot concrete 11 thick steel bar arch support 12 thick steel bar 13 Connecting rebar 14 Joint steel plate 15 Joint bolt 16 Sleeve 17 Primary lining concrete 18 Concrete waterproofing reinforcement material 19 Secondary lining concrete T Tunnel
Claims (1)
掘削後コンクリートの一次吹付けを行ない、一次吹付け
コンクリートの内面に太径鉄筋鋼アーチ支保工を固定
し、太径鉄筋鋼アーチ支保工の高さの半分程度までコン
クリートの二次吹付けを行なって一次覆工コンクリート
を形成し、該一次覆工コンクリートの内面にコンクリー
ト防水強化材を吹付け又は塗布し、一次覆工コンクリー
トの内側に突出した状態で残っている太径鉄筋鋼アーチ
支保工を補強鉄筋として二次覆工コンクリートを打設す
ることを特徴とする補強筋兼用の支保工を用いたトンネ
ルの覆工方法。1. In the excavation of a large-section tunnel, primary blasting of concrete is performed after ground excavation, and a large diameter reinforced steel arch support is fixed to the inner surface of the primary shot concrete to provide a large diameter reinforced steel arch support. To the half of the height of the primary lining concrete to form a primary lining concrete, spray or apply concrete waterproofing reinforcement to the inner surface of the primary lining concrete, the inside of the primary lining concrete A method of lining a tunnel using a reinforcement also serving as a reinforcement, characterized in that the secondary lining concrete is placed by using the large diameter reinforced steel arch support that remains in a protruding state as reinforcement.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6309137A JPH08165899A (en) | 1994-12-13 | 1994-12-13 | Tunnel lining method using timbering concurrently serving as reinforcing bar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP6309137A JPH08165899A (en) | 1994-12-13 | 1994-12-13 | Tunnel lining method using timbering concurrently serving as reinforcing bar |
Publications (1)
Publication Number | Publication Date |
---|---|
JPH08165899A true JPH08165899A (en) | 1996-06-25 |
Family
ID=17989353
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP6309137A Pending JPH08165899A (en) | 1994-12-13 | 1994-12-13 | Tunnel lining method using timbering concurrently serving as reinforcing bar |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH08165899A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108843346A (en) * | 2018-07-18 | 2018-11-20 | 中铁十二局集团第二工程有限公司 | Lining construction method of the large section shallow-depth-excavation tunnel in water-rich sand layer |
CN109763852A (en) * | 2019-01-15 | 2019-05-17 | 西南交通大学 | A kind of advance support structure and its construction method suitable for scall |
CN110761804A (en) * | 2019-12-05 | 2020-02-07 | 中铁二十局集团第六工程有限公司 | Karst stratum tunnel secondary lining renovation construction structure and method based on sleeve lining |
JP2022500579A (en) * | 2019-06-19 | 2022-01-04 | 中鉄十九局集団第六工程有限公司China Railway 19Th Bureau Group Sixth Engineering Co., Ltd. | Support structure of two-stage high-speed closed tunnel with reverse arch and its construction method |
-
1994
- 1994-12-13 JP JP6309137A patent/JPH08165899A/en active Pending
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108843346A (en) * | 2018-07-18 | 2018-11-20 | 中铁十二局集团第二工程有限公司 | Lining construction method of the large section shallow-depth-excavation tunnel in water-rich sand layer |
CN109763852A (en) * | 2019-01-15 | 2019-05-17 | 西南交通大学 | A kind of advance support structure and its construction method suitable for scall |
CN109763852B (en) * | 2019-01-15 | 2020-12-18 | 西南交通大学 | Advanced support structure suitable for unconsolidated formation and construction method thereof |
JP2022500579A (en) * | 2019-06-19 | 2022-01-04 | 中鉄十九局集団第六工程有限公司China Railway 19Th Bureau Group Sixth Engineering Co., Ltd. | Support structure of two-stage high-speed closed tunnel with reverse arch and its construction method |
CN110761804A (en) * | 2019-12-05 | 2020-02-07 | 中铁二十局集团第六工程有限公司 | Karst stratum tunnel secondary lining renovation construction structure and method based on sleeve lining |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7125550B2 (en) | SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH | |
JP3824114B2 (en) | Whale bone method for large section tunnel | |
WO2006057545A1 (en) | Tunnelling method using pre-support concept and an adjustable apparatus thereof | |
JP3833403B2 (en) | Large-section tunnel sushi bone method | |
KR100656194B1 (en) | Open cut and cover method applying tunnel cut method | |
CN109026026A (en) | Under wear existing piping lane the multi-thread more arcading bored tunnel groups of big cross section construction method | |
CN112031814B (en) | Cave-entering construction method for crossing shallow-layer high-load highway | |
JPH09217594A (en) | Timbering method for tunnel | |
JP2874561B2 (en) | Fore piling method with stiffening of the leading leg using a shaft | |
KR100898969B1 (en) | Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof | |
CN106285691B (en) | A kind of method for tunnel construction that shield formula multi-arm development machine is combined with New Austrian Tunneling Method | |
JPH08165899A (en) | Tunnel lining method using timbering concurrently serving as reinforcing bar | |
CN108222012A (en) | A kind of foundation pit anchor cable excision and the construction method that supporting pile is carried out using anchor cable excision system | |
KR100217845B1 (en) | Construction process of underground structure | |
JPH0637830B2 (en) | Vertical shaft for shield method | |
CN112228076A (en) | Fast excavation construction method for hard rock large-span tunnel | |
JPH08165895A (en) | Excavating method for large-cross section tunnel | |
JP2002021491A (en) | Reinforcing method for leg portion of tunnel | |
JP3795859B2 (en) | Propulsion pipe for pipe propulsion method | |
JP4298853B2 (en) | Long tip receiving method | |
CN217999598U (en) | Joint stratum large-span tunnel pilot tunnel subsection step excavation supporting construction in advance | |
JP2520036B2 (en) | Construction method of large section underground cavity and large section tunnel | |
JP2932197B2 (en) | Excavation method for large or very large tunnel | |
JP2544829B2 (en) | How to build an underground cavity | |
JPH0776988A (en) | Preliminary construction method for tunnel facing front bedrock |