JPH0746152B2 - Structure of containment vessel wall - Google Patents
Structure of containment vessel wallInfo
- Publication number
- JPH0746152B2 JPH0746152B2 JP61136812A JP13681286A JPH0746152B2 JP H0746152 B2 JPH0746152 B2 JP H0746152B2 JP 61136812 A JP61136812 A JP 61136812A JP 13681286 A JP13681286 A JP 13681286A JP H0746152 B2 JPH0746152 B2 JP H0746152B2
- Authority
- JP
- Japan
- Prior art keywords
- mold
- formwork
- containment vessel
- steel plate
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E30/00—Energy generation of nuclear origin
- Y02E30/30—Nuclear fission reactors
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Structure Of Emergency Protection For Nuclear Reactors (AREA)
Description
【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、原子炉格納容器壁の構造に関するものであ
る。TECHNICAL FIELD The present invention relates to a structure of a wall of a reactor containment vessel.
従来、原子炉格納容器(以下、収納容器と略称する)を
鉄筋コンクリート構造とすることがなされており、この
種の収納容器を構築するには、現場において堰板を支保
工で支持して仮設の型枠を組み上げるとともに、鉄筋を
組み立て、その後に型枠内にコンクリートの打設を行
い、コンクリート養生後に型枠を撤去するといった工法
を行うことが一般的である。Conventionally, a reactor containment vessel (hereinafter, abbreviated as a storage vessel) has been made to have a reinforced concrete structure. To construct this type of storage vessel, a weir plate is supported at a site by a support work and temporarily installed. It is common practice to assemble the formwork, assemble the reinforcing bars, then place concrete in the formwork, and remove the formwork after curing the concrete.
〔発明が解決しようとする問題点〕 ところが格納容器を構築するために行う前述の工法にお
いては、多量の鉄筋を現場で逐一組み立てる必要がある
上に、堰板と支保工を用いて仮設の型枠を組み上げ、更
に、養生後に型枠を撤去する必要があるために、作業量
の多い複雑な工事を現場において行わなくてはならない
問題があった。このため原子炉建屋の構築工事において
収納容器の構築工事が工程上のクリティカルパスとなっ
ているのである。[Problems to be Solved by the Invention] However, in the above-mentioned construction method for constructing the containment vessel, it is necessary to assemble a large amount of reinforcing bars one by one on site, and a temporary mold using a weir plate and a supporting structure. Since it was necessary to assemble the frame and remove the formwork after curing, there was a problem that complicated construction with a large amount of work had to be performed on site. Therefore, in the construction of the reactor building, the construction of the storage container is a critical path in the process.
ところで従来、一対の鋼板の間にコンクリートを打設し
て形成され、引張り力を鉄筋の代わりに鋼板に負担させ
る構成とした鋼板コンクリート壁が知られている。従っ
て、この種の鋼板コンクリート壁を適用した場合に、前
記鉄筋の組み立て作業の簡略化を図りうるのであるが、
構造強度を見込んで設計される鋼板を格納容器の内面側
に設けた場合、事故時の温度上昇によって鋼板にライナ
ースラスト力が作用する虞があり、このため内側の鋼板
の設計が困難になるとともにこの鋼板のスラスト力がコ
ンクリート躯体に作用し、亀裂を生じさせるといった悪
影響を及ぼすことが考えられるため実質的に適用不可能
となる問題がある。By the way, conventionally, a steel plate concrete wall is known in which concrete is cast between a pair of steel plates, and a tensile force is applied to the steel plate instead of the reinforcing bars. Therefore, when this type of steel plate concrete wall is applied, it is possible to simplify the work of assembling the rebar,
If a steel plate designed with structural strength in mind is provided on the inner surface side of the containment vessel, the liner thrust force may act on the steel plate due to the temperature rise in the event of an accident, which makes it difficult to design the inner steel plate. Since the thrust force of the steel sheet may act on the concrete skeleton and cause adverse effects such as cracking, there is a problem that it is practically impossible to apply.
本発明は、前記問題に鑑みてなされたもので、従来必要
としていた仮設型枠および鉄筋の組み立て作業を簡略化
でき、工期の大幅な短縮化並びに施工の省力化をなしえ
るとともに、ライナー工事を簡略化することができ、鋼
板コンクリート構造の適用を可能とする格納容器壁の構
造を提供することを目的とする。The present invention has been made in view of the above problems, and can simplify the work of assembling the temporary formwork and the rebar, which has been conventionally required, and can significantly reduce the work period and save the labor of the construction, and also perform the liner construction. An object of the present invention is to provide a structure of a containment vessel wall which can be simplified and enables application of a steel plate concrete structure.
本発明は、前記問題点を解決するために、ライナー材が
内張りされたプレキャストコンクリート製内型枠と、前
記内型枠の外方に離間して配置された鋼板を具備してな
る外型枠とを連結材で連結して型枠ユニットを構成し、
内型枠と外型枠の間にコンクリートを打設してなるもの
である。In order to solve the above-mentioned problems, the present invention provides an outer formwork comprising a precast concrete inner formwork lined with a liner material, and a steel plate arranged apart from the inner formwork. And form a form unit by connecting with a connecting material,
It is made by placing concrete between the inner and outer molds.
工場生産可能な内型枠と外型枠によってコンクリート打
設時の型枠を構成でき、型枠組み立て工事の簡略化をな
しうるとともに、引張り力を負担して鉄筋の代わりとな
る鋼製外型枠を備えているために、鉄筋組み立て作業を
簡略化できる。The inner and outer molds that can be produced at the factory can form a mold for concrete placement, which simplifies the mold assembling work and also bears the pulling force to replace the steel rebar with a steel outer mold. Since the frame is provided, the rebar assembling work can be simplified.
第1図と第2図は本発明の一実施例を示し、第3図は原
子炉建屋1の内部に構築された格納容器Aを示してい
る。1 and 2 show an embodiment of the present invention, and FIG. 3 shows a containment vessel A built inside the reactor building 1.
第3図に示す原子炉建屋1は、その中央部に格納容器A
を備えた構成であり、格納容器Aの内部には原子炉本体
を格納した圧力容器3が設けられている。The reactor building 1 shown in FIG. 3 has a containment vessel A in the center thereof.
The pressure vessel 3 accommodating the reactor body is provided inside the containment vessel A.
前記格納容器Aは、筒状をなし、その断面構造は第1図
に示すように、外周部の外型枠5と、その内側のコンク
リート壁部6と、その内側のプレキャストコンクリート
製内型枠7と、内型枠7に内張りされたライナー材8を
主体として構成されている。The storage container A has a tubular shape, and its cross-sectional structure is, as shown in FIG. 1, an outer mold 5 on the outer peripheral portion, a concrete wall part 6 on the inner side thereof, and a precast concrete inner mold on the inner side. 7 and a liner material 8 lined in the inner formwork 7 as main components.
前記外型枠5は、所定の曲率で湾曲された鋼板10とその
内面に所定ピッチで固定されたスタッドボルト11とから
構成されるとともに、その内側に形成されたコンクリー
ト壁部6の内周部にはひび割れ防止用の補強筋12が埋設
されている。前記内型枠7は、プレキャストコンクリー
ト部13と、その内面に内張りされた鋼板からなるライナ
ー材8と、ライナー材8の外周面に所定ピッチで固定さ
れてコンクリート部13に埋設されたスタッドボルト14
と、プレキャストコンクリート部13の外周部に埋設され
た補強筋15とからなっている。そして、前記鋼板10とプ
レキャストコンクリート部13は、第2図に示すように、
鋼板10とプレキャストコンクリート部13に固定されたタ
イバー等の連結部材16によって互いに平行に連結されて
いる。The outer mold 5 comprises a steel plate 10 curved with a predetermined curvature and stud bolts 11 fixed to the inner surface of the stud bolt 11 at a predetermined pitch, and an inner peripheral portion of a concrete wall 6 formed inside thereof. A reinforcing bar 12 for preventing cracks is embedded in the inside. The inner formwork 7 includes a precast concrete portion 13, a liner material 8 made of a steel plate lined on the inner surface thereof, and a stud bolt 14 fixed to the outer peripheral surface of the liner material 8 at a predetermined pitch and embedded in the concrete portion 13.
And a reinforcing bar 15 embedded in the outer peripheral portion of the precast concrete portion 13. Then, the steel plate 10 and the precast concrete portion 13 are, as shown in FIG.
The steel plate 10 and the precast concrete part 13 are connected in parallel to each other by a connecting member 16 such as a tie bar fixed to the precast concrete part 13.
なお、前記格納容器Aは、前記外型枠5と内型枠7を連
結部材16で結合してなる第2図に示すような型枠ユニッ
トYを複数接合して構成された型枠に、コンクリートを
打設して構築されたものである。The storage container A has a mold formed by joining a plurality of mold units Y as shown in FIG. 2 in which the outer mold 5 and the inner mold 7 are connected by a connecting member 16, It was constructed by placing concrete.
次に、前記構成の格納容器Aを構築する方法について詳
細に説明する。Next, a method for constructing the storage container A having the above configuration will be described in detail.
前記構成の格納容器Aを構築するには、外型枠5と内型
枠7とが連結部材16で結合されてなり、格納容器Aをそ
の周方向に複数に分割した大きさの第2図に示す型枠ユ
ニットYを複数、工場で製作する。In order to construct the storage container A having the above structure, the outer mold 5 and the inner mold 7 are joined by the connecting member 16, and the storage container A is divided into a plurality of pieces in the circumferential direction. A plurality of form unit Y shown in are manufactured in a factory.
前述のように格納容器Aを複数に分割した大きさの型枠
ユニットYは、その大きさに合わせて海上輸送、また
は、陸上輸送等の輸送手段を適宜選択して現場に搬入さ
れる。As described above, the form unit Y having a size obtained by dividing the storage container A into a plurality of parts is carried into the site by appropriately selecting a transportation means such as sea transportation or land transportation according to the size.
前記構成の複数の型枠ユニットyを現場の所定位置に搬
入したならば、隣接する型枠ユニットYの相互の鋼板10
どうしを各々接合し、隣接するプレキャストコンクリー
ト部13どうしを接合して格納容器建築用の型枠を構成す
る。If a plurality of formwork units y having the above-mentioned configuration are carried into a predetermined position on the site, the steel plates 10 of the adjacent formwork units Y are mutually attached.
The precast concrete parts (13) adjacent to each other are joined together to form a formwork for building a containment vessel.
次に、鋼板10とプレキャストコンクリート壁部13との間
の間隙にコンクリートの打設を行ってコンクリート壁部
6を形成する。このように工場生産されて現場に設置さ
れた出来合いの型枠ユニットYに型枠の役目をさせるこ
とによって、従来、現場で構築する必要のあった支保工
や堰板からなる仮設型枠の構築作業を消滅して無支保工
化することができる。即ち、工場生産した型枠ユニット
Yを組み立てて格納容器Aを構築するために、プレハブ
化、ユニット化の促進となり、現場での作業量を削減で
き、工期の短縮化が可能になる。また、型枠ユニットY
は工場生産するために品質管理も容易であり、品質を安
定化することができる。なお、型枠ユニットYの据え付
けにあたっては、原子炉建屋1を構築する際に使用され
るクレーンを用いることができ、この使用によってクレ
ーンの利用効率も向上する。Next, concrete is poured into the gap between the steel plate 10 and the precast concrete wall portion 13 to form the concrete wall portion 6. In this way, by making the ready-made formwork unit Y produced at the factory and installed on the site to act as a formwork, construction of a temporary formwork consisting of supporting works and weirboards that had to be built on site in the past. The work can be eliminated and the work can be unsupported. That is, in order to construct the storage container A by assembling the formwork unit Y produced at the factory, the prefabrication and unitization are promoted, the work amount on site can be reduced, and the construction period can be shortened. In addition, the form unit Y
Since it is manufactured in a factory, quality control is easy and the quality can be stabilized. In installing the formwork unit Y, a crane used when constructing the reactor building 1 can be used, and the use efficiency of the crane is also improved by this use.
前述の如く構築された格納容器Aにあっては、スタッド
ボルト11…と連結部材16…とがコンクリート壁部6と鋼
板10との接合強度を向上させて鋼板10の座屈を防止す
る。また、格納容器Aにあっては、前記引張り力を鋼板
10が負担する構成のために、従来構造において引張り力
を負担していた鉄筋の組み立て工事を省略することがで
きる。一方、ライナー材8は事故時の急激な温度上昇を
防止するものである。In the storage container A constructed as described above, the stud bolts 11 and the connecting members 16 improve the joint strength between the concrete wall portion 6 and the steel plate 10 and prevent the steel plate 10 from buckling. Further, in the storage container A, the tensile force is applied to the steel plate.
Due to the configuration that 10 bears, it is possible to omit the work of assembling the reinforcing bar that previously bears the pulling force in the conventional structure. On the other hand, the liner material 8 prevents a rapid temperature rise in the event of an accident.
ところで、格納容器Aにあっては、事故時に想定される
内部側の急激な温度上昇に対応できる構造を採用する必
要がある。この点前記構造の格納容器Aにあっては、内
型枠7のプレキャストコンクリート部13が断熱作用を奏
する。更に、ライナー材8は、格納容器Aの構造強度を
負担する構造材ではないために、事故時の急激な温度上
昇により作用するライナースラスト力に対応するように
設計することができる。従ってこのライナー材8はその
歪チェックを行うことによって設計が可能になる。By the way, it is necessary for the storage container A to adopt a structure capable of coping with a sudden temperature increase on the inner side that is expected in the event of an accident. In this respect, in the storage container A having the above structure, the precast concrete portion 13 of the inner formwork 7 has a heat insulating effect. Furthermore, since the liner material 8 is not a structural material that bears the structural strength of the storage container A, it can be designed to cope with the liner thrust force acting due to a rapid temperature rise in the event of an accident. Therefore, the liner material 8 can be designed by checking its distortion.
また、格納容器Aの施工において、外周側に露出するの
は鋼板10であり、この鋼板10の外側の設備工事を格納容
器Aに構築中に実施することができるために、両方の工
事を平行して進行させることができ、施工性も向上す
る。Further, in the construction of the containment vessel A, it is the steel plate 10 that is exposed to the outer peripheral side, and since the equipment work on the outside of this steel sheet 10 can be carried out during construction of the containment vessel A, both constructions are parallel. Can be made to proceed, and the workability is also improved.
以上説明したように本発明は、プレキャストコンクリー
ト製内型枠と、前記内型枠の外方に内型枠と離間して配
置された外型枠との間にコンクリートを打設してなるも
のであり、工場で製造した出来合いの内型枠と外型枠を
現場に搬入して型枠を組み立てることができるために、
プレハブ化をなしえるものであり、従来現場で行ってい
た堰板と支保工からなる仮設型枠の組み立て作業と撤去
作業を省略でき、工期の短縮、並びに、施工の省略化を
なしうる効果がある。また、前記内型枠と外型枠は工場
生産可能であり、品質管理も容易になるために、品質を
向上することができる。また、引張り力は従来の鉄筋に
代わって外型枠の鋼板が負担するために、本発明構造を
採用することにより構造用の鉄筋を省略して鉄筋の組み
立て作業を簡略化でき、現場での作業量を大幅に削減で
きる効果がある。更に、内型枠にはライナー材が内張り
されているために、現場でのライナー工事を簡素化でき
る効果がある。INDUSTRIAL APPLICABILITY As described above, the present invention is one in which concrete is cast between a precast concrete inner formwork and an outer formwork located outside the inner formwork and spaced apart from the inner formwork. And because the ready-made inner and outer molds manufactured at the factory can be brought into the site and assembled,
Since it can be prefabricated, it is possible to omit the work of assembling and removing the temporary formwork consisting of the weir plate and the support work, which had been done on-site in the past, and it is possible to shorten the construction period and simplify the construction. is there. Further, the inner mold and the outer mold can be manufactured in a factory, and the quality control is facilitated, so that the quality can be improved. Further, since the tensile force is borne by the steel plate of the outer formwork in place of the conventional reinforcing bar, by adopting the structure of the present invention, the structural reinforcing bar can be omitted and the assembling work of the reinforcing bar can be simplified and This has the effect of significantly reducing the amount of work. Further, since the liner material is lined inside the inner formwork, there is an effect that the liner construction on site can be simplified.
第1図は、本発明の一実施例を示す断面図、第2図は型
枠ユニットの平面図、第3図は前記実施例の構造を格納
容器に適用して構築された原子炉建屋の構成図である。 A……格納容器、1……原子炉建屋、5……外型枠、6
……コンクリート壁部、7……内型枠、8……ライナー
材、10……鋼板、11,14……スタッドボルト、12,15……
補強筋、13……プレキャストコンクリート部。FIG. 1 is a cross-sectional view showing an embodiment of the present invention, FIG. 2 is a plan view of a formwork unit, and FIG. 3 is a reactor building constructed by applying the structure of the embodiment to a containment vessel. It is a block diagram. A: containment vessel, 1 reactor building, 5 outer mold, 6
…… Concrete wall, 7 …… Inner form, 8 …… Liner material, 10 …… Steel plate, 11,14 …… Stud bolt, 12,15 ……
Reinforcing bar, 13 …… Precast concrete section.
───────────────────────────────────────────────────── フロントページの続き (72)発明者 山本 勇 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (72)発明者 大沢 一彦 東京都中央区京橋2丁目16番1号 清水建 設株式会社内 (56)参考文献 特開 昭59−116090(JP,A) 特開 昭62−170885(JP,A) 実開 昭59−29797(JP,U) ─────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Isamu Yamamoto 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (72) Inventor Kazuhiko Osawa 2-16-1 Kyobashi, Chuo-ku, Tokyo Shimizu Construction Co., Ltd. (56) Reference JP-A-59-116090 (JP, A) JP-A-62-170885 (JP, A) Practical application Sho-59-29797 (JP, U)
Claims (4)
ンクリート製内型枠と、前記内型枠の外方に内型枠と離
間して配置された鋼板を具備してなる外型枠とを連結部
材で連結して型枠ユニットを構成し、前記型枠ユニット
を複数接合して型枠を構成し、前記内型枠と外型枠との
間にコンクリートを打設し、内型枠と外型枠を一体化し
てなる原子炉格納容器壁の構造。1. A connecting member for connecting an inner formwork made of precast concrete lined with a liner material and an outer formwork comprising a steel plate arranged outside the inner formwork and spaced apart from the inner formwork. To form a mold unit, join a plurality of the mold units to form a mold, and place concrete between the inner mold and the outer mold to form the inner mold and the outer mold. The structure of the wall of the reactor containment vessel that integrates the frame.
てなることを特徴とする特許請求の範囲第1項記載の原
子炉格納容器壁の構造。2. The structure of the reactor containment vessel wall according to claim 1, wherein stud bolts are attached to the inner surface of the outer form.
とを特徴とする特許請求の範囲第1項記載の原子炉格納
容器壁の構造。3. The structure of the reactor containment vessel wall according to claim 1, wherein a reinforcing bar is provided between the outer mold and the inner mold.
筋を埋設してなることを特徴とする特許請求の範囲第1
項記載の原子炉格納容器壁の構造。4. A precast concrete inner formwork having reinforcing bars embedded therein.
The structure of the wall of the containment vessel of paragraph.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61136812A JPH0746152B2 (en) | 1986-06-12 | 1986-06-12 | Structure of containment vessel wall |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP61136812A JPH0746152B2 (en) | 1986-06-12 | 1986-06-12 | Structure of containment vessel wall |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS62293188A JPS62293188A (en) | 1987-12-19 |
JPH0746152B2 true JPH0746152B2 (en) | 1995-05-17 |
Family
ID=15184080
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP61136812A Expired - Fee Related JPH0746152B2 (en) | 1986-06-12 | 1986-06-12 | Structure of containment vessel wall |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPH0746152B2 (en) |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007232420A (en) * | 2006-02-28 | 2007-09-13 | Hitachi Ltd | Nuclear reactor containment |
JP5358516B2 (en) * | 2010-06-07 | 2013-12-04 | 日立Geニュークリア・エナジー株式会社 | Construction method of reactor containment vessel |
-
1986
- 1986-06-12 JP JP61136812A patent/JPH0746152B2/en not_active Expired - Fee Related
Also Published As
Publication number | Publication date |
---|---|
JPS62293188A (en) | 1987-12-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP2586224B2 (en) | Building method using precast concrete formwork | |
JPH0746152B2 (en) | Structure of containment vessel wall | |
JPH10102423A (en) | Pca form and construction method of pier using the same pca form | |
JPH0746154B2 (en) | Structure of containment vessel wall | |
JP3194729B2 (en) | Reinforced concrete structure, method of constructing reinforced concrete structure, and reinforcing bar restraint | |
JP2575921B2 (en) | Method for constructing top slab of containment vessel and containment vessel | |
JP2797023B2 (en) | Construction method of beam | |
JP3114024B2 (en) | Frame joint structure | |
JPH0835210A (en) | Tower-like structure and construction method thereof | |
JPH0746153B2 (en) | Structure of containment vessel wall | |
JPH087276B2 (en) | How to build a lining tank | |
JPS63308B2 (en) | ||
JP2749474B2 (en) | Reverse construction method for underground structures | |
JPH05239810A (en) | Constructing method for reinforced concrete arch bridge | |
JP3191955B2 (en) | Formwork of prefabricated steel frame formwork unit | |
JP3312945B2 (en) | Construction method of concrete structure | |
JP792H (en) | Construction method of reinforced concrete structure | |
JP2000355909A (en) | Construction method for bridge floor | |
CN118438541A (en) | UHPC formwork construction process for prefabricated SW column of fabricated concrete | |
JPS61126259A (en) | Pillar of structure | |
JPS6232303B2 (en) | ||
JPH10152887A (en) | Precast-concrete-made form | |
JP2629496B2 (en) | Construction method of structure | |
JPH0835260A (en) | Tower-form structure and building method thereof | |
JPH02282538A (en) | Construction method of reinforced concrete-made building frame |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |