[go: up one dir, main page]
More Web Proxy on the site http://driver.im/

JPH066818B2 - Reinforced steel composite column - Google Patents

Reinforced steel composite column

Info

Publication number
JPH066818B2
JPH066818B2 JP61157065A JP15706586A JPH066818B2 JP H066818 B2 JPH066818 B2 JP H066818B2 JP 61157065 A JP61157065 A JP 61157065A JP 15706586 A JP15706586 A JP 15706586A JP H066818 B2 JPH066818 B2 JP H066818B2
Authority
JP
Japan
Prior art keywords
steel frame
column
plate
joint structure
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP61157065A
Other languages
Japanese (ja)
Other versions
JPS6314937A (en
Inventor
義則 村井
精保 北川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP61157065A priority Critical patent/JPH066818B2/en
Publication of JPS6314937A publication Critical patent/JPS6314937A/en
Publication of JPH066818B2 publication Critical patent/JPH066818B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)
  • Reinforcement Elements For Buildings (AREA)

Description

【発明の詳細な説明】 「産業上の利用分野」 この発明は、柱が鉄筋コンクリート造、梁が鉄骨造の多
層建築物を構築する際に用いる鉄筋鉄骨複合柱に関する
ものである。
TECHNICAL FIELD The present invention relates to a reinforced steel composite column used when constructing a multi-layer building in which a column is a reinforced concrete structure and a beam is a steel frame.

「従来の技術」 従来、建築物の骨組として、柱を鉄筋コンクリート造、
梁を鉄骨造とする鉄筋鉄骨複合化構造が知られている。
これによれば、建築物全体を鉄骨造とする場合に比して
工費が嵩まず、また全体を鉄筋コンクリート造とする場
合に比して工期を短縮できる等、これら両者の利点を生
かして建築物を構築することができる。
"Conventional technology" Conventionally, as the frame of a building, pillars are reinforced concrete,
A reinforced steel composite structure having a beam as a steel structure is known.
According to this, the construction cost is less expensive than the case where the whole building is made of steel frame, and the construction period can be shortened compared to the case where the whole structure is made of reinforced concrete structure. Can be built.

このような鉄筋鉄骨複合化構造により建築物を構築する
場合、その柱には、柱主筋とフープ筋を予め建築物の階
高に相当する長さに組み立てた柱用鉄筋篭(先組鉄筋)
を用いることが一般的である。この柱用鉄筋篭を用いて
多層階の建築物を構築するには、まず最下階にその階の
階高に相当する長さの柱用鉄筋篭を建て、次にこの鉄筋
篭相互間に鉄骨梁を架け渡すと共に、鉄筋篭の外側に型
枠を組み立ててコンクリートを打設する。そして、この
コンクリートが硬化した後に、その直上階に鉄筋篭を継
ぎ足して建て、この後、、上記の手順を繰り返すことで
各階毎に順次上層部へ向かって建築物を構築するのであ
る。
When constructing a building with such a reinforced steel composite structure, the columns are made up of column main bars and hoop bars that have been assembled in advance to a length corresponding to the floor height of the building.
Is generally used. To construct a multi-story building using this pillar rebar cage, first build a pillar rebar cage of the length corresponding to the floor height of that floor on the bottom floor, and then between the rebar cages. Along with bridging the steel beams, the formwork is assembled on the outside of the rebar cage and concrete is poured. Then, after this concrete hardens, a reinforcing bar cage is added to the floor immediately above it, and thereafter, the above procedure is repeated to build a building for each floor in order toward the upper layer.

「発明が解決しようとする問題点」 しかしながら、上記のような各階の階高に相当する長さ
の柱用鉄筋篭を用い、これを順次継ぎ足して建築物を構
築するには、鉄筋篭の揚重作業や、鉄筋篭同士を継ぎ足
す作業を各階ごとに行なわなければならず、その手間が
かかって、梁を鉄骨造としたにもかかわらず、大幅な工
期の短縮は望めないものであった。
"Problems to be solved by the invention" However, in order to construct a building by using a reinforcing bar cage for pillars having a length corresponding to the floor height of each floor as described above, constructing a building by constructing a building It was necessary to perform heavy work and work to reinforce the reinforced baskets on each floor, and it took time and labor, but despite the beams being made of steel, it was impossible to expect a significant reduction in the construction period. .

また、上記鉄骨篭に鉄骨梁を取り付けるための有効な手
段は未だ確立されておらず、この点においても施工の手
間がかかるとともに、構造的な強度に対する心配もあっ
た。
In addition, an effective means for attaching the steel beam to the steel cage has not been established yet, and in this respect as well, it takes time and effort for the construction and there is concern about the structural strength.

この発明は上記の事情に鑑みてなされたもので、鉄筋鉄
骨複合化構造の建築物を構築するに当って、充分に工期
が短縮できるとともに、構造強度を充分に確保すること
ができる鉄筋鉄骨複合柱を提供することを目的としてい
る。
The present invention has been made in view of the above circumstances, in constructing a building of a reinforced steel frame composite structure, the construction period can be sufficiently shortened, and the structural strength can be sufficiently ensured. It is intended to provide pillars.

「問題点を解決するための手段」 この発明の鉄筋鉄骨複合柱は、複数の柱主筋とフープ筋
とによって複数階分の長さにわたって構成された柱用鉄
筋篭に、複数階分の鉄骨梁接合用の仕口構成体を所定の
間隔で取り付けてなり、上記仕口構成体は、梁鉄骨を交
差状態で一体化して構成された梁鉄骨部とこの梁鉄骨部
の交差部分を囲んで梁鉄骨部に一体化された筒状の型枠
兼用プレート部とを備え、かつ、前記鉄骨篭の複数の柱
主筋が上記仕口構成体の型枠兼用プレート部の内側を通
るとともに、その複数の柱主筋のうち少なくとも一部の
複数本の柱主筋が前記型枠兼用プレート部の内壁に内方
に延出して形成された取付フランジに固定されているも
のである。
"Means for Solving the Problems" The reinforced steel composite column of the present invention is a multi-story steel beam for a multi-story column rebar cage configured by a plurality of column main bars and hoop bars over a plurality of floor lengths. A joint structure for joining is attached at a predetermined interval, and the joint structure is a beam that surrounds a beam steel frame portion formed by integrating beam steel frames in an intersecting state and an intersection portion of the beam steel frame portion. A cylindrical formwork / plate plate unit integrated with a steel frame part, and a plurality of pillar main bars of the steel cage pass through the inside of the formwork / plate plate part of the joint structure, and At least a part of a plurality of pillar main bars is fixed to a mounting flange formed so as to extend inward on an inner wall of the form / plate plate portion.

「作用」 この発明では、鉄筋篭の内部及び周囲にコンクリートが
打設されて、複数階の鉄筋コンクリート柱を形成する。
また、鉄筋篭に固定された仕口構成体の梁鉄骨部は、こ
れに柱相互間に架け渡される鉄骨梁が接合されて、この
梁の端部として作用する。更に、仕口構成体の型枠兼用
プレート部は、仕口部の柱用型枠として寄与するととも
に、前記鉄骨梁と一体となってパネルゾーン(柱・梁交
差部)を補強する役目を果たし、柱と梁との剛接合を構
成することになる。
[Operation] In the present invention, concrete is placed inside and around the reinforced cage to form reinforced concrete columns on a plurality of floors.
Further, the beam steel frame portion of the joint structure fixed to the rebar cage is joined to the steel frame beam bridged between the columns, and acts as an end portion of the beam. Furthermore, the formwork / plate part of the joint structure serves as a pillar formwork of the joint part, and also serves to reinforce the panel zone (column / beam intersection) integrally with the steel frame beam. , Will form a rigid connection between the pillar and the beam.

「実施例」 以下、この発明の実施例について図面を参照して説明す
る。
[Examples] Examples of the present invention will be described below with reference to the drawings.

第1図ないし第6図は、この発明の一実施例である鉄筋
鉄骨複合柱を示す図である。この複合柱Aは、3層(3
階建)のラーメン構造の建築物を構築する際に使用され
るもので、鉄筋篭1と仕口構成体2、2、2とにより概
略構成されている。
1 to 6 are views showing a reinforced steel frame composite column which is an embodiment of the present invention. This composite pillar A has three layers (3
It is used when constructing a building having a (story) ramen structure, and is roughly configured by a reinforced basket 1 and a joint structure 2, 2, 2.

鉄筋篭1は、複数(図示例では12本)の柱主筋3、
3、…とフープ筋4、4、…とによって、建築物の3層
分の高さに相当する長さに予め組み立てられた先組鉄筋
である。柱主筋3、3、…のうち、そのコーナー部に位
置されている柱主筋3a、3a、…及び中間部の柱主筋
3b、3b、…にはねじ節鉄筋又は異形鉄筋が適用され
ている。
The rebar cage 1 includes a plurality of (12 in the illustrated example) column main bars 3,
It is a pre-assembled rebar preassembled by 3, ... and hoop reinforcements 4, 4, ... to a length corresponding to the height of three layers of a building. Of the main columnar bars 3, 3, ..., The main columnar bars 3a, 3a, ... Positioned at the corners thereof and the main columnar bars 3b, 3b ,.

この鉄筋篭1には、3つの仕口構成体2、2、…が取り
付けられている。この仕口構成体2、2、…には、後述
の如く建築物の鉄筋梁が接合されるものであり、第1図
において鉄筋篭1の最上部に取り付けられている仕口構
成体2には最上階の梁が、また中間部に取り付けられて
いる仕口構成体2、2には、それぞれ3階、2階の梁が
取り付けられるものである。
.. are attached to the rebar cage 1. Reinforcing bar beams of a building are joined to the joint structure bodies 2, 2, ... As described later, and the joint structure body 2 attached to the uppermost portion of the rebar cage 1 in FIG. Is a beam on the uppermost floor, and the beams on the third floor and the second floor are attached to the connection forming bodies 2 and 2 attached to the middle portion, respectively.

この仕口構成体2は、第2図及び第3図に示すように、
上部水平プレート5a(上フランジ)、下部水平プレー
ト5b(下フランジ)、及び垂直プレート5c(ウェ
ブ)からなるH型鉄骨が十字状に交差して一体化された
梁鉄骨部5と、この梁鉄骨部5の交差部分を囲繞するよ
うに、梁鉄骨部5に一体化されて取り付けられた型枠兼
用プレート部6、6、…とから構成されている。この型
枠兼用プレート部6の上端及び下端は、それぞれ前記梁
鉄骨部5の上部水平プレート5a及び下部水平プレート
5bから、前記柱主筋3、3、…の長さ方向に若干延出
されている。ここで、最上階に対応する位置に取り付け
られた仕口構成体2の型枠兼用プレート部6の上端は、
後述の如く床スラブとの接合の関係上、梁鉄骨部5の上
部水平プレート5aと面一に形成されている。また、型
枠兼用プレート部6、6、…の接合部、即ち型枠兼用プ
レート部6、6、…が互いに接合されて構成される箱体
のコーナー部には、その上端部及び下端部に、この箱体
の内方に延在する取付フランジ7、7、…取り付けられ
ている。取付フランジ7には、これを厚さ方向に貫通す
る挿通孔8が形成されている。また、上下の水平プレー
ト5a、5bには、梁鉄骨部5の交差部分の中心部に相
当する位置に空気孔9がそれぞれ形成されている。
As shown in FIG. 2 and FIG.
A beam steel frame portion 5 in which an H-shaped steel frame composed of an upper horizontal plate 5a (upper flange), a lower horizontal plate 5b (lower flange), and a vertical plate 5c (web) intersects in a cross shape and is integrated, and the beam steel frame. It is composed of form plate / plate portions 6, 6, ... Integrally attached to the beam steel frame portion 5 so as to surround the intersecting portion of the portion 5. The upper end and the lower end of the frame / plate portion 6 are slightly extended from the upper horizontal plate 5a and the lower horizontal plate 5b of the beam steel frame portion 5 in the longitudinal direction of the column main bars 3, 3, .... . Here, the upper end of the form / plate plate portion 6 of the joint structure 2 attached to the position corresponding to the uppermost floor is
As will be described later, it is formed so as to be flush with the upper horizontal plate 5a of the beam steel frame portion 5 because of the connection with the floor slab. .., that is, the corners of the box body formed by joining the mold / plate plates 6, 6, ... To the upper and lower ends thereof. , Are attached to the mounting flanges 7 extending inward of the box body. The mounting flange 7 is formed with an insertion hole 8 which penetrates the mounting flange 7 in the thickness direction. Further, air holes 9 are formed in the upper and lower horizontal plates 5a and 5b at positions corresponding to the central portions of the intersecting portions of the beam steel frame portions 5, respectively.

以上のように構成された仕口構成体は、前述の如く鉄筋
篭1の長さ方向に所定の間隔を置いて、即ち建築物の階
高に対応した位置に取り付けられている。この仕口構成
体2の鉄筋篭1への固定は、仕口構成体2の型枠兼用プ
レート部6、6、…の上下端に設けられている取付フラ
ンジ7、7、…の挿通孔8、8、…に、鉄筋篭1のコー
ナー部の柱主筋3a、3a、…が挿通され、さらに上下
からナット11が螺着、緊締されることによってなされ
ている(第4図参照)。なお、前記柱主筋3a、3aと
してねじ節鉄筋を用いない場合には、この部分は溶接等
により固定すれば良い。この時、中間部の柱主筋3b、
3b、…は、梁鉄骨部5及び型枠兼用プレート部6によ
り形成される空隙内を通って、この仕口構成体2を貫通
することとなる。そして、以上の構成により、鉄筋篭1
の柱主筋3、3、…は、前記仕口構成体2の型枠兼用プ
レート部6の内側に位置することとなる(第2図及び第
3図参照)。
As described above, the joint structure constructed as described above is attached at predetermined intervals in the length direction of the rebar cage 1, that is, at a position corresponding to the floor height of the building. The fixing of the joint structure 2 to the rebar cage 1 is performed by inserting the through holes 8 of the mounting flanges 7, 7, ... , 8 ... are inserted with the column main bars 3a, 3a, ... at the corners of the rebar cage 1, and the nuts 11 are screwed and tightened from above and below (see FIG. 4). In addition, when a threaded joint bar is not used as the column main bars 3a, 3a, this portion may be fixed by welding or the like. At this time, the column main bar 3b in the middle part,
The parts 3b, ... pass through the joint structure 2 through the space formed by the beam steel frame part 5 and the plate part 6 serving also as the formwork. With the above configuration, the rebar cage 1
The column main bars 3, 3, ... Are located inside the formwork / plate portion 6 of the joint structure 2 (see FIGS. 2 and 3).

また、前記鉄筋篭1の柱主筋3の下端には、それぞれス
リーブジョイント12(第1図参照)が取り付けられて
いる。さらに、この鉄筋篭1の柱主筋3、3、…の内部
には、この柱主筋3、3、…を内方より支持する枠状の
座屈防止枠14、14、…(第5図参照)が、鉄筋篭1
の長さ方向に所定の間隔を置いて取り付けられている。
Further, sleeve joints 12 (see FIG. 1) are attached to the lower ends of the column main bars 3 of the rebar cage 1, respectively. Further, inside the column main reinforcements 3, 3, ... Of the rebar cage 1, frame-shaped buckling prevention frames 14, 14, ... Supporting the column main reinforcements 3, 3 ,. ), Rebar cage 1
Are attached at a predetermined interval in the length direction.

次に、以上の構成を有する鉄筋鉄骨複合柱Aの使用方法
について、第6図を参照しながら説明する。
Next, a method of using the reinforced steel frame composite column A having the above configuration will be described with reference to FIG.

まず、複合柱Aをクレーン等によって吊り上げ、その下
端部を基礎Bに立設されている篭状の鉄筋15、15、
…にスリーブジョイント12によって接続することで、
この複合柱Aをそれぞれ所定位置に建てる。次に、隣接
して建てられた複合柱A、Aのそれぞれ最下部の仕口構
成体2、2相互間に、2階の梁16を架け渡し、この梁
16の端部と仕口構成体2の梁鉄骨部5のH型鉄骨の端
部とを、溶接またはボルト等で接合する。そして、1階
部分(梁下の部分)の鉄筋篭1の周囲に柱型枠(図示
略)を取り付け、この内部にコンクリートを打設する。
さらに、このコンクリートが硬化した後、順次上階で同
様の手順を繰り返すことにより、この建築物の柱、梁を
構築する。なお、床スラブや壁については、従来一般に
用いられる適宜の手段を用いれば良い。第7図は、複合
柱Aにコンクリートが打設された後の、中間階(2階、
3階)の仕口構成体2部分の詳細を示す図である。ま
た、第8図は、同様にコンクリートが打設され、さらに
屋上階のスラブ17が打設された後の、最上階(最上
階)の仕口構成体2部分の詳細を示す図である。
First, the composite pillar A is lifted by a crane or the like, and the lower end of the composite pillar A is erected in a basket-like rebar 15, 15,
By connecting to the sleeve joint 12 ...
Each of these composite pillars A is built in a predetermined position. Next, a beam 16 on the second floor is bridged between the joint structure bodies 2 and 2 at the bottom of the composite columns A and A, which are built adjacent to each other, and the ends of the beam 16 and the joint structure body. The end of the H-shaped steel frame of the beam steel frame part 2 of 2 is joined by welding or bolts. Then, a column form (not shown) is attached around the reinforced cage 1 on the first floor (the part under the beam), and concrete is placed inside this.
After the concrete is hardened, the columns and beams of this building are constructed by repeating the same procedure on the upper floors. As for the floor slab and the wall, any appropriate means generally used in the past may be used. Fig. 7 shows the intermediate floor (2nd floor,
It is a figure which shows the detail of the connection structure 2 part of the (3rd floor). Further, FIG. 8 is a view showing details of the uppermost floor (top floor) of the joint structure 2 portion after concrete is similarly cast and the slab 17 on the rooftop floor is further cast.

以上説明したように、この複合柱Aを用いることによ
り、鉄骨柱を建てる場合と同様に3層分の柱を一度に建
てることが可能であり、大幅な工期の短縮を図ることが
できる。ここで、複合柱Aの柱主筋3は、フープ筋4、
4、…及び座屈防止枠14、14、…により外方及び内
方から支持されているので、この複合柱Aが組立中に座
屈するようなことがない。
As described above, by using this composite pillar A, it is possible to build pillars for three layers at once, as in the case of building a steel frame pillar, and it is possible to significantly reduce the construction period. Here, the main pillar 3 of the composite pillar A is the hoop muscle 4,
.. and the buckling prevention frames 14, 14, ... Are supported from outside and inside, so that the composite column A will not buckle during assembly.

また、梁16と仕口構成体2、2との接続は、従来の鉄
骨造の場合と同様に行うことができると共に、仕口構成
体2の梁鉄骨部5は、これに梁16が接続された後は、
この梁16の端部として作用し、従って梁16に作用す
る荷重がこの梁鉄骨部5を通じて複合柱Aに伝達され
る。特に、鉄筋篭1と仕口構成体2とは、柱主筋3a、
3a、…が取付フランジ7の挿通孔8に挿通されて固定
されていること、及び型枠兼用プレート部6が、この内
部に打設されたコンクリートを拘束することにより、互
いに一体化されて、充分に剛に接合されることとなる。
Further, the connection between the beam 16 and the connection forming bodies 2 and 2 can be performed in the same manner as in the case of the conventional steel frame structure, and the beam steel frame portion 5 of the connection forming body 2 is connected to the beam 16 to this. After being done,
The load that acts as an end portion of the beam 16 and thus acts on the beam 16 is transmitted to the composite column A through the beam steel portion 5. In particular, the rebar cage 1 and the joint structure 2 are composed of pillar main bars 3a,
, 3a, ... Are inserted into the insertion holes 8 of the mounting flange 7 and fixed, and the form / plate portion 6 is integrated with each other by restraining the concrete cast therein, It will be joined sufficiently rigidly.

さらに、仕口構成体2の型枠兼用プレート部6、6、…
は、従来の鉄筋コンクリート造では施工が面倒であった
仕口部の型枠として作用することに加えて、仕口部の柱
コンクリートがこの型枠兼用プレート部6、6に拘束さ
れてコンファインド効果による補強作用をすると共に、
梁鉄骨部5(即ち梁16の端部)を補強するスチフナの
役割をも有することとなる。また、上下の水平プレート
5a、5bに形成されている前記空気孔9、9は、コン
クリート打設時において、柱型枠の内部及び型枠兼用プ
レート部6内部の空気の排出口となるから、コンクリー
トを柱型枠及び型枠兼用プレート部6内部の隅々にまで
充填することができる。
Further, the plate / combined plate portions 6, 6, ... Of the joint structure 2.
In addition to acting as a formwork for the joint part, which was difficult to construct in the conventional reinforced concrete construction, the column concrete of the joint part is restrained by the formwork / plate parts 6, 6 to provide a confined effect. With the reinforcement effect by
The steel frame portion 5 (that is, the end portion of the beam 16) also has a role of a stiffener. Further, since the air holes 9, 9 formed in the upper and lower horizontal plates 5a, 5b serve as air outlets inside the pillar formwork and inside the formwork / plate part 6 when concrete is poured. Concrete can be filled into every corner inside the column form and the form / plate plate 6.

以上、この発明の一実施例である複合柱Aについて説明
したが、この発明は前記実施例に限定されず、種々の応
用が可能である。例えば、前記実施例での複合柱Aは、
3層の建築物に適用されるような構成であるが、2層や
4層、あるいはより多層の構築物に対しても、柱主筋3
の長さと、仕口構造体2の数及び鉄筋篭1への取付間隔
を適宜変更することのみで、充分に対応できる。また、
前記複合柱Aでは、その仕口構造体2の梁鉄骨部5が十
字状に交差されて、4方向から梁16が接合されるよう
な構成であったが、外壁に接する柱のような場合にあっ
ては、梁鉄骨部5をT字状に交差させて、3方向から梁
16が接合されるような構成にすれば良い。勿論、建築
物の角部に設けられる柱であれば、L字状に2方向、あ
るいは架構形式状の必要に応じて、直線状に2方向、更
には1方向のみに梁16が接合されるような構成であっ
ても良い。また、接合される梁16の梁成寸法がそれぞ
れ異なる場合や、梁のレベルが異なって柱に段違いに取
り付けられるような場合にも、仕口構成体2の梁鉄骨部
5の形状を変更することのみで対応可能である。
The composite pillar A, which is one embodiment of the present invention, has been described above, but the present invention is not limited to the above-mentioned embodiment and various applications are possible. For example, the composite pillar A in the above embodiment is
Although the structure is applied to a three-story building, the pillar main bar 3 is also applicable to a two-story, four-story, or multi-story building.
Can be sufficiently coped with by simply changing the length, the number of the joint structures 2 and the mounting interval to the rebar cage 1. Also,
In the composite pillar A, the beam steel frame portions 5 of the joint structure 2 are crossed in a cross shape and the beams 16 are joined from four directions. However, in the case of a pillar contacting an outer wall In this case, the beam steel frame portions 5 may intersect in a T-shape so that the beams 16 are joined in three directions. Of course, in the case of a pillar provided at a corner of a building, the beams 16 are joined in two directions in an L-shape, or in two directions in a straight line, or in only one direction depending on the need of a frame form. Such a configuration may be used. Further, the shape of the beam steel frame portion 5 of the joint structure 2 is changed even when the beam forming dimensions of the beams 16 to be joined are different from each other or when the levels of the beams 16 are differently attached to the columns. It is possible to deal only with that.

また、前記型枠兼用プレート部6の形状も、前記実施例
に限定されず、例えば、このプレート部6の上端及び下
端の位置が、梁鉄骨部5の上下の水平プレート5a、5
bと面一であっても良い。更に言えば、柱主筋3と仕口
構成体2との固定方法や、鉄筋の形状についても、本実
施例に限定されず、周知の手段及び形状から適宜選択さ
れれば良い。
Moreover, the shape of the plate / cumulative plate portion 6 is not limited to the above-described embodiment, and for example, the positions of the upper end and the lower end of the plate portion 6 are the upper and lower horizontal plates 5a, 5a of the beam steel frame portion 5, respectively.
It may be flush with b. Furthermore, the method of fixing the column main bar 3 and the joint structure 2 and the shape of the reinforcing bar are not limited to those in this embodiment, and may be appropriately selected from known means and shapes.

さらに、前記複合柱Aでは、最上階の梁も仕口構成体2
により接合する構成としたが、最上階の梁を柱に対して
ピン接合する場合等にあっては、最上階用の仕口構成体
2は省略しても良い。第9図は、最上階の梁18が本実
施例の複合柱Aにピン接合された状態を示す図である。
第9図において、鉄筋篭1の柱主筋3(3a、3b)の
上端部は、ナット20を介して定着板19に固定されて
おり、また梁18は、アンカーボルト21、ナット22
により、柱の頂部に連結、固定されている。
Further, in the composite pillar A, the beam on the top floor is also the joint structure 2
However, in the case where the uppermost floor beam is pin-joined to the pillar, the uppermost floor connection structure 2 may be omitted. FIG. 9 is a view showing a state in which the uppermost beam 18 is pin-joined to the composite column A of this embodiment.
In FIG. 9, the upper ends of the column main bars 3 (3a, 3b) of the rebar cage 1 are fixed to the fixing plate 19 via nuts 20, and the beam 18 includes anchor bolts 21 and nuts 22.
Is connected and fixed to the top of the pillar.

そして、この複合柱Aを用いて建築物を構築する手順
は、従来工法から自由に選択されれば良く、例えば、前
記鉄骨梁の代わりに鉄筋コンクリート梁、鉄筋鉄骨コン
クリート梁、プレキャストコンクリート梁を使用しても
良いし、壁や床も同様に鉄筋コンクリート、プレキャス
トコンクリートであっても良い。また、柱もプレキャス
トコンクリートであっても良い。さらに、コンクリート
の打設順序も施工条件により適宜選択されれば良い。
The procedure for constructing a building using the composite pillar A may be freely selected from the conventional construction methods. For example, a reinforced concrete beam, a reinforced concrete beam, or a precast concrete beam is used instead of the steel beam. The walls and floor may also be reinforced concrete or precast concrete. The pillars may also be precast concrete. Furthermore, the order of placing concrete may be appropriately selected depending on the construction conditions.

なお、この複合柱Aの製造は、現場あるいは工場等の平
坦な作業場に適宜の架台を設け、この架台に仕口構成体
2を所定の間隔で載置した後、これら仕口構成体2に柱
主筋3、3、…を挿通して固定すれば良い。
In order to manufacture the composite pillar A, an appropriate gantry is provided on a flat work site such as a site or a factory, and the joint structures 2 are placed on the gantry at predetermined intervals. It suffices to insert and fix the column main bars 3, 3, ....

また、他の実施例として特に図示しないが、前記梁鉄骨
部5のフランジ5a縁部に前記柱主筋3a、3bを固定
しても良い。
Further, as another embodiment, although not particularly shown, the pillar main bars 3a and 3b may be fixed to the edge portion of the flange 5a of the beam steel frame portion 5.

「発明の効果」 以上詳細に説明したように、この発明によれば、複数階
の長さに亙る鉄筋篭に仕口構成体を取り付けたので、複
数階の柱を一度に建てることが可能であると共に、梁を
容易に接合することが可能であり、従って鉄筋鉄骨複合
化構造の建築物を構築するに当り、大幅に工期を短縮す
ることができる。
[Advantages of the Invention] As described in detail above, according to the present invention, since the connector structure is attached to the rebar cage over the length of a plurality of floors, it is possible to build the pillars of a plurality of floors at once. At the same time, the beams can be easily joined, and therefore the construction period can be greatly shortened when constructing a building having a reinforced steel frame composite structure.

また、柱主筋が仕口構成体の型枠兼用プレート部に固定
されているので、柱と梁とが充分に剛の状態で接合で
き、従って建築物の構造強度を充分に確保することがで
きる。
In addition, since the column main bar is fixed to the formwork / plate portion of the joint structure, the column and the beam can be joined in a sufficiently rigid state, so that the structural strength of the building can be sufficiently secured. .

また、複数の柱主筋のうち少なくとも一部の複数本の柱
主筋を、前記型枠兼用プレート部の内壁に内方に延出し
て形成された取付フランジに固定したので、筒状の型枠
兼用プレートと、その内側を挿通された柱主筋とを取付
フランジを介して容易かつ強固に固定することができる
上、取付フランジが型枠兼用プレートの内壁に、そこか
ら延出して形成されているので、内部にコンクリートが
打設される型枠兼用プレートの剛性を高めることができ
るといる利点もある。
In addition, since at least a part of the plurality of column main bars is fixed to a mounting flange formed to extend inwardly on the inner wall of the form-combined plate portion, the column main bar is also used. The plate and the column main bar inserted through the inside of the plate can be easily and firmly fixed via the mounting flange, and the mounting flange is formed on the inner wall of the form / plate so as to extend therefrom. Another advantage is that it is possible to increase the rigidity of the plate that also serves as the formwork in which concrete is placed.

さらに、仕口構成体には型枠兼用プレート部を設けたの
で、仕口部の柱型枠が不要であり、従って型枠作業の省
力化をも図ることができる。加えて、コンファインド効
果により仕口部の柱コンクリートが補強されるので、構
造的にバランスが良く耐力を充分に発揮できる信頼性の
高い構造を確保できる。
Further, since the mold plate serving also as the mold is provided in the joint structure, the column mold of the joint is not necessary, and therefore the labor of the mold work can be saved. In addition, since the concrete column in the joint is reinforced by the confined effect, it is possible to secure a highly reliable structure that is structurally well-balanced and can exert its proof stress sufficiently.

【図面の簡単な説明】[Brief description of drawings]

第1図はこの発明の一実施例である鉄筋鉄骨複合柱を示
す図であって、その全体概略構成を示す正面図、第2図
は同仕口構成体付近を拡大して示した斜視図、第3図は
同平面図、第4図は同実施例における型枠兼用プレート
部と柱主筋との固定状態を示す拡大正面図、第5図は同
座屈防止枠の取付状態を示す平断面図、第6図は同実施
例の使用方法を説明する図であって、立設された複合柱
に梁を取り付けている状態を示す正面図、第7図はコン
クリート打設後の中間階の仕口構成体部分を示す平断面
図、第8図は同最上階の仕口構成体部分を示す平断面
図、第9図は同最上階の梁がピン接合された状態を示す
平断面図である。 A……鉄筋鉄骨複合柱、1……鉄筋篭、2……仕口構成
体、3……柱主筋、4……フープ筋、5……梁鉄骨部、
6……型枠兼用プレート部。
FIG. 1 is a diagram showing a reinforced steel frame composite column which is an embodiment of the present invention, a front view showing the overall schematic configuration thereof, and FIG. 2 is an enlarged perspective view showing the vicinity of the joint structure. FIG. 3 is a plan view of the same, FIG. 4 is an enlarged front view showing a fixed state of the plate / combined plate portion and the column main bar in the same embodiment, and FIG. 5 is a plan view showing a mounted state of the buckling prevention frame. Sectional drawing, FIG. 6 is a view for explaining a method of using the same embodiment, and is a front view showing a state in which a beam is attached to an upright composite pillar, and FIG. 7 is an intermediate floor after placing concrete. Fig. 8 is a plan sectional view showing a joint structure portion of Fig. 8, Fig. 8 is a plan sectional view showing the joint structure portion of the same top floor, and Fig. 9 is a plan sectional view showing a state in which the top floor beam is pin-joined. It is a figure. A: Reinforced steel composite column, 1 ... Reinforced cage, 2 ... Joint structure, 3 ... Column main bar, 4 ... Hoop bar, 5 ... Beam steel frame,
6 ... Plate part that also serves as a formwork.

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】複数の柱主筋とフープ筋とによって複数階
分の長さにわたって構成された柱用鉄筋篭に、複数階分
の鉄骨梁接合用の仕口構成体を所定の間隔で取り付けて
なり、上記仕口構成体は、梁鉄骨を交差状態で一体化し
て構成された梁鉄骨部とこの梁鉄骨部の交差部分を囲ん
で梁鉄骨部に一体化された筒状の型枠兼用プレート部と
を備え、かつ、前記鉄筋篭の複数の柱主筋が上記仕口構
成体の型枠兼用プレート部の内側を通るとともに、その
複数の柱主筋のうち少なくとも一部の複数本の柱主筋が
前記型枠兼用プレート部の内壁に内方に延出して形成さ
れた取付フランジに固定されていることを特徴とする鉄
筋鉄骨複合柱。
1. A joint structure for joining a plurality of stories of a steel beam is attached at a predetermined interval to a reinforcement bar cage for a column constituted by a plurality of pillar main reinforcements and hoop reinforcements over a plurality of floor lengths. The above-mentioned joint structure is a tubular formwork / plate which is integrated with the beam steel frame part by surrounding the intersection part of the beam steel frame part and the beam steel frame part which are configured by integrating the beam steel frames in an intersecting state. And a plurality of column main bars of the reinforcing bar cage pass through the inside of the form and plate section of the joint structure, and at least a part of the plurality of column main bars has a plurality of column main bars. A reinforced steel frame composite column, characterized in that it is fixed to a mounting flange formed to extend inwardly on the inner wall of the formwork / plate portion.
JP61157065A 1986-07-03 1986-07-03 Reinforced steel composite column Expired - Lifetime JPH066818B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP61157065A JPH066818B2 (en) 1986-07-03 1986-07-03 Reinforced steel composite column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP61157065A JPH066818B2 (en) 1986-07-03 1986-07-03 Reinforced steel composite column

Publications (2)

Publication Number Publication Date
JPS6314937A JPS6314937A (en) 1988-01-22
JPH066818B2 true JPH066818B2 (en) 1994-01-26

Family

ID=15641450

Family Applications (1)

Application Number Title Priority Date Filing Date
JP61157065A Expired - Lifetime JPH066818B2 (en) 1986-07-03 1986-07-03 Reinforced steel composite column

Country Status (1)

Country Link
JP (1) JPH066818B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017095986A (en) * 2015-11-25 2017-06-01 株式会社安藤・間 Iron concrete structure reinforcement structure

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0280487A (en) * 1988-09-15 1990-03-20 Sumitomo Electric Ind Ltd Carbon fibver-reinforced composite carbon material
JPH06158713A (en) * 1993-07-14 1994-06-07 Shimizu Corp Joint construction
JP4255522B2 (en) * 1997-07-16 2009-04-15 安藤建設株式会社 Beam-column joint structure
JP2010013898A (en) * 2008-07-07 2010-01-21 Fujita Corp Steel reinforced concrete column assembling method
JP2010216075A (en) * 2009-03-13 2010-09-30 Daiwa House Industry Co Ltd Joint structure of reinforced concrete column and steel frame beam
JP2017089292A (en) * 2015-11-12 2017-05-25 清水建設株式会社 Construction method of junction between columns

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711171B2 (en) * 1985-03-28 1995-02-08 清水建設株式会社 Reinforced steel composite column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017095986A (en) * 2015-11-25 2017-06-01 株式会社安藤・間 Iron concrete structure reinforcement structure

Also Published As

Publication number Publication date
JPS6314937A (en) 1988-01-22

Similar Documents

Publication Publication Date Title
KR200414349Y1 (en) Connection structure of precast concrete structure
JPH066818B2 (en) Reinforced steel composite column
JP3384785B2 (en) Construction method of damping wall
JPS62133239A (en) Structural member for pillar
JP2566701Y2 (en) Joint structure between reinforced concrete columns and steel beams
JP3043938B2 (en) Joint structure between reinforced concrete columns and steel beams
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JP3146923B2 (en) Construction method of reinforced concrete building
JPH08158695A (en) Earthquake-proof tubular framework and frame structure of multistoried office building
JPH0711171B2 (en) Reinforced steel composite column
JPH0375704B2 (en)
JPH03275839A (en) Connection construction of reinforced concrete column and steel beam
JPS63103140A (en) Open structure of pillar and beam of multistoried building
JPH01287336A (en) Steel frame reinforced concrete lamination construction
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JPS6195136A (en) Construction of multistoried building skeletal by precast reinforced concrete unit
JP3125165B2 (en) Warehouse frame
JPH0448136B2 (en)
JP3158954B2 (en) Precast concrete members integrating columns and beams
JPH09221829A (en) Vibration damping device for reinforced concrete structure
JPH0673785A (en) Steel framed reinforced concrete column and construction of this column and steel skeleton beam
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JP2984626B2 (en) PC pillar construction method and its PC pillar
JPH0830360B2 (en) Connection method for columns and beams
JPS61225448A (en) Reinforcing bar composite pillar

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term